CC SR 20250916 D - Landslide Emergency Contract Continuation (Granicus Version with Link for Attachments) CITY COUNCIL MEETING DATE: 09/16/2025 AGENDA REPORT AGENDA HEADING: Consent Calendar AGENDA TITLE: Consideration to continue the emergency justification for work and emergency contracting for the Greater Portuguese Bend-Ancient Altamira Landslide Emergency Project. RECOMMENDED COUNCIL ACTION: (1) Reconfirm, by a four-fifths vote, there is a need to continue the work on the Emergency Project declared by Council-adopted Resolution No. 2024-20 on May 7, 2024, finding an emergency exists requiring immediate action in the Greater Portuguese Bend-Ancient Altamira Landslide Complex (Landslide Complex) to seek to mitigate the movement of the landslide; (2) Direct the City Clerk to confirm the same in the minutes of this City Council meeting, via Minute Order, reflecting this action; (3) Approve Retroactive Amendment No. 1 to the Professional Services Agreement (PSA) with Cotton, Shires and Associates for City-wide geotechnical consulting, including landslide emergency stabilization geotechnical consulting through June 30, 2025, and related services, increasing the not-to-exceed amount for the initial 5-year term by $1,190,474 from $400,000 to $1,590,474 while maintaining a 15% contingency, and authorize the Mayor and City Clerk to execute Amendment No. 1, to the PSA with Cotton, Shires and Associates, Inc. in a form approved by the City Attorney; (4) Approve Retroactive Amendment No. 1 to the PSA with McGee Surveying Consulting for Portuguese Bend Landslide Monitoring Program Surveying and related services, increasing the not-to-exceed amount for the term between September 5, 2023 and June 30, 2024 by $405,123 from $64,400 to $469,523, and extending the contract term by one year, with an amended contract end date of June 30, 2025, and authorize the Mayor and City Clerk to execute Amendment No. 1 to the PSA with McGee Surveying Consulting, in a form approved by the City Attorney; (5) Approve Retroactive Amendment No. 2 to the PSA with Ocean Blue Environmental Services, Inc. for City-wide environmental cleanup and related services, increasing the not-to-exceed amount for the term between May 17, 2022 and June 30, 2024 by $1,738,479 from $532,082 to $2,270,561 while maintaining a 15% contingency, and authorize the Mayor and City Clerk to execute Amendment No. 2, to the PSA with Ocean Blue Environmental Services, Inc. in a form approved by the City Attorney; (6) Approve Retroactive Amendment No. 1 to the PSA with Hardy & Harper, Inc. for city-wide public works maintenance and related services, increasing the not-to- exceed amount for the initial 5-year term by $261,213 from $2,167,651 to $2,428,864 while maintaining a 15% contingency, and authorize the Mayor and 1 City Clerk to execute Amendment No. 1 to the PSA with Hardy & Harper, Inc., in a form approved by the City Attorney; (7) Approve Retroactive Amendment No. 1 to the Public Works Agreement (PWA) with Hardy & Harper, Inc. for roadway maintenance and related services, increasing the not-to-exceed amount for the initial 5-year term by $2,324,438 from $2,000,435 to $4,324,873 while maintaining a 10% contingency, and authorize the Mayor and City Clerk to execute Amendment No. 1 to the PWA with Hardy & Harper, Inc., in a form approved by the City Attorney; (8) Approve Retroactive Amendment No. 2 to the PSA with Monaco Mechanical, Inc. for City-wide plumbing and related services, removing the annual not-to-exceed amount of $100,000 as a result of actual expenditures for services needed to respond to the landslide emergency, for the initial 6-year term with no change to the total contract not-to-exceed amount, and while maintaining a 10% contingency, and authorize the Mayor and City Clerk to execute Amendment No. 2 to the PSA with Monaco Mechanical, Inc., in a form approved by the City Attorney; (9) Ratify payments for emergency repairs to the Abalone Cove Sanitary Sewer System during the period between July 22, 2024 and November 6, 2024 to Ramona, Inc. in the amount of $191,602; (10) Ratify payments for delivering soil for fissure filling within the Landslide Complex during the period between December 6, 2023 and June 30, 2025 to BD White Topsoil Co., Inc. in the amount of $127,052; (11) Ratify payments for emergency repairs to the Abalone Cove Sanitary Sewer System during the period between July 17, 2023 and June 4, 2025 to Clarke Contracting Corporation in the amount of $1,977,321; (12) Ratify payments for emergency repairs to the Abalone Cove Sanitary Sewer System during the period between January 31, 2025 and April 16, 2025 to Colich and Sons, LP in the amount of $243,684; (13) Ratify payments for emergency roadway repairs within the Landslide Complex during the period between August 2, 2024 and June 11, 2025 to Inland Engineering Services, Inc. in the amount of $91,853; (14) Ratify payments for fueling services for the Abalone Cove Sanitary Sewer System lift station generators during the period between September 10, 2024 and May 28, 2025 to Ferrellgas, LP in the amount of $101,068; (15) Ratify payments for maintenance and repair services for the Abalone Cove Sanitary Sewer System lift station generators during the period between October 18, 2024 and July 30, 2025 to Genesis Electrical, Inc. in the amount of $83,313; (16) Ratify payments for emergency sewer and storm drain repairs within the Landslide Complex on April 15, 2024 to Southwest Pipeline Technologies, Inc. in the amount of $33,000; (17) Ratify payments for sewer and storm drain repairs within the Landslide Complex during the period between March 7, 2024 and April 30, 2025 to Performance Pipeline Technologies, Inc. in the amount of $92,710. FISCAL IMPACT: There is no fiscal impact to the Fiscal Year (FY) 2025-26 budget associated with the recommended City Council actions. The recommended City Council action ratifies payments and retroactively approves contracts for work performed in Fiscal Year 2 (FY) 2024-25 already paid for using previously approved FY 2024- 25 budget. The end of year estimates for FY 2024-25 include the dollar amounted cited in the recommended ratified payments. The recommended City Council action is only for emergency services already performed under the City Manager’s emergency authority approved by the City Council via Resolution No. 2023-47 on October 3, 2023, and does not affect FY 2025-26 budget. Following is a summary of the approved budget appropriations in FY 2024-25 that were used to pay for the services the City Council is being asked to ratify, along with the funding sources. FY 2024-25 Summary of Budget Appropriations: [CONTINUED ON NEXT PAGE] FY 2024-25 Budget Appropriations (Summary) in millions TOTAL FY 2024-25 Adopted Budget $4.6 $13.7 October 1, 2024 $14.1 Emergency response, boreholes, DDW, winterization ARPA Fund 0.5 LA County Grant (Sup. Hahn)2.2 CIP Emergency Reserves 5.0 General Fund Unallocated Fund Balance - Transfers Out 6.4 December 17, 2024 $1.1 O&M for DDDW between Jan-Mar 2025 CIP Fund 1.1 January 21, 2025 $2.0 Additional O&M for DDW between Apr-Jun 2025 and fissure filling CIP Fund (DDW)1.5 CIP Fund (Fissure Filling)0.5 February 4, 2025 $0.1 In-Kind Services for ACLAD Affirmed $1.6 million of loans to ACLAD and KCLAD CIP Fund (DDW)0.1 March 18, 2025 $0.7 Additional O&M Ab Cove Sanitary Sewers CIP Fund 0.1 Reallocate Measure R 0.4 Reallocate Gas Tax 0.2 May 6, 2025 $0.5 Additional O&M DDW CIP Fund 0.5 TOTAL - FY 2024-25 $36.8 Carryover from FY 2023-24 ( Prof/Tech, Reallocation 3 FY 2024-25 Summary of Funding Sources (by Fund): Amount Budgeted: See Fiscal Impact above Additional Appropriation: N/A Account Number(s): Funding sources – see Fiscal Impact above VR ORIGINATED BY: David Copp, Deputy Public Works Director REVIEWED BY: Ramzi Awwad, Public Works Director APPROVED BY: Ara Mihranian, AICP, City Manager ATTACHED SUPPORTING DOCUMENTS: Please click here to access the attachments below. A. September 2, 2025 City Council Staff Report – Emergency Landslide Stabilization Contract Continuation (Linked) B. July 1, 2025 City Council Staff Report – Emergency Landslide Stabilization Contract Continuation and Award of Multiple Contracts for Emergency Landslide Stabilization and Related Infrastructure Repairs (Linked) C. Amendment No. 1 to the PSA with Cotton, Shires and Associates, Inc. (Page C-1) D. PSA with Cotton, Shires and Associates, Inc. (Page D-1) E. Amendment No. 1 to the PSA with McGee Surveying Consulting(Page E-1) F. PSA with McGee Surveying Consulting. (Page F-1) G. Amendment No. 2 to the PSA with Ocean Blue Environmental Services, Inc. (Page G-1) H. Amendment No. 1 to the PSA with Ocean Blue Environmental Services, Inc. (Page H-1) I. PSA with Ocean Blue Environmental Services, Inc. (Page I-1) J. Amendment No. 1 to the PSA for city-wide public works maintenance and related services with Hardy & Harper, Inc. (Page J-1) K. PSA for city-wide public works services with Hardy & Harper, Inc. (Page K- 1) Funding Sources for FY 2024-25 TOTAL In Millions CIP Fund 14.5 CIP Fund (Reserves)5.0 CIP Fund (Cont Approp 01/21/25)0.5 General Fund (Transfers-Out Reserves to the CIP Fund) 6.4 General Fund 3.4 Special Revenue (Restricted) Funds ARPA Fund 3.4 Metro Fund (Prop C, Measure R)1.4 Sup. Hahn's Social Program Grant 2.2 TOTAL $36.81 4 L. Amendment No. 1 to the PSA for roadway maintenance services with Hardy & Harper, Inc. (Page L-1) M. PSA for roadway maintenance services with Hardy & Harper, Inc. (Page M- 1) N. Amendment No. 2 to the PSA with Monaco Mechanical, Inc. (Page N-1) O. Amendment No. 1 to the PSA with Monaco Mechanical, Inc. (Page O-1) P. PSA with Monaco Mechanical, Inc. (Page P-1) Q. Invoices from Ramona, Inc. for emergency sewer repairs in the Abalone Cove Sanitary Sewer System (Page Q-1) R. Invoices from BD White Topsoil Co., Inc. for delivering soil for fissure filling within the Landslide Complex (Page R-1) S. Invoices from Clarke Contracting Corporation for emergency repairs to the Abalone Cove Sanitary Sewer System (Page S-1) T. Invoices from Colich and Sons, LP for emergency repairs to the Abalone Cove Sanitary Sewer System (Page T-1) U. Invoices from Inland Engineering Services, Inc. for emergency roadway repairs within the Landslide Complex (Page U-1) V. Invoices from Ferrellgas, LP for fueling services for the Abalone Cove Sanitary Sewer System lift station generators (Page V-1) W. Invoices from Genesis Electrical, Inc. for maintenance and repair services for the Abalone Cove Sanitary Sewer System lift station generators (Page W-1) X. Invoices from Southwest Pipeline Technologies, Inc. for sewer and storm drain repairs within the Landslide Complex (Page X-1) Y. Invoices from Performance Pipeline Technologies, Inc. for sewer and storm drain repairs within the Landslide Complex (Page Y-1) EXECUTIVE SUMMARY: • Reconfirm the City Manager’s emergency contracting authority for work related to the Greater Portuguese Bend-Ancient Altamira Landslide Complex (Landslide Complex) thereby: o Authorizing the City Manager to order work expedites the ability to respond to the emergency as compared to the regular bidding and City Council contract approval process. o The City Manager may only order work within City Council appropriated budget. o Reconfirming this authority is required by the City Council at every meeting pursuant to state law while the local emergency exists. • Ratify payments already made and retroactively approve contracts for work already performed in FY 2024-25 under the City Manager’s emergency authorization for Landslide Complex emergency stabilization. o Using City Council appropriated FY 2024-25 funds, the City Council authorized the City Manager to order work outside the regular bidding and City Council contract approval process on an emergency basis. 5 o City Council ratification of payments and retroactive approval of contracts for work ordered by the City Manager as part of the landslide emergency is a best practice and increases public transparency. • No FY 2025-26 new budget appropriation or expenditure of approved budget is associated with these actions. o Payment ratifications and retroactive contract approvals are for work already completed and paid for using funds previously appropriated by the City Council in FY 2024-25 as detailed in the Fiscal Impacts section. o Retroactive contracts do not cover any new work for FY 2025-26 as those were separately approved by the City Council on July 1, 2025. BACKGROUND: On October 3, 2023, the City Council adopted Resolution No. 2023-47, declaring a state of local emergency relating to the land movement in the Landslide Complex and providing the City Manager authorization to approve matters related to the emergency for ratification by the City Council. The state of emergency, as well as the continuation of associated emergency contracting has been timely renewed and is current. Pursuant to Public Contract Code § 22050, the City Manager and Director of Public Works must report to the City Council at its regular meeting the reasons justifying why the emergency continues to exist and why action outside of the normal bidding process is necessary to respond to the emergency. Furthermore, Public Contract Code § 22050 states that the City Council shall, at every regularly scheduled meeting, consider and reaffirm that there is a need to continue to remediate the emergency until the authorized emergency repairs have been completed. Accordingly, because the work has not yet been completed, this item is on tonight’s agenda. This item will be placed on each subsequent agenda until all aspects of the project are completed. The City Council most recently approved continuing the emergency justification for work and emergency contracting for the Greater Portuguese Bend-Ancient Altamira Landslide Emergency Project on September 2, 2025 (Attachment A), and is therefore due to reaffirm the need to continue to remediate the emergency at this evenings meeting. DISCUSSION: Re-affirm Need to Continue Emergency Work To support the need for continued emergency contracting authority, the current status of the Deep Dewatering Wells (DDWs) program is being provided: Since the start of the DDW program, approximately 328 million gallons, or 1,007 acre- feet of water have been extracted. Extraction rates are currently influenced by the following circumstances: • DDW-1 has sheared due to land movement and is offline. Re-drilling will commence following the completion of re-drilling DDW-5. 6 • DDW-5 has sheared due to land movement and is offline. Re-drilling began on 9/2/2025 and should be completed this week. • DDW-7 has sheared, and based on its low production rate, the City’s Geologists have advised that the well be re-located rather than re-drilled in its approximate existing location. • DDW-9A is offline due to low water level. The submersible pump is being adjusted and the well will be back online shortly. • DDW11 has sheared and based on the low production rate, the City’s Geologists are advising that this DDW should not be re-drilled, but rather re-located, should additional funding become available. Due to the significant cost of relocating this DDW, considered to be well above maintenance and operation costs, there are currently no plans in place to relocate the well. Table 1 - DDW Current Water Extraction Rates as of September 8, 2025 DDW No. Date Operational Current Approximate Water Extraction Rate (Gallons Per Minute) Total Water Extraction to Date Acre-Ft Million Gallons 1 9/13/2024 Offline (re-drilled 3/21/25)  132 43 2 9/17/2024 95 (re-drilled 5/29/25) 135 44 3 9/21/2024 75 (re-drilled 3/24/25) 132 43 4 9/21/2024 N/A, Decommissioned 3/27/25 95 31 4A 3/29/2025 50 5 9/25/2024 Offline (re-drilled 3/26/25; offline - redrill in progress)  116 38 6 9/28/2024 80 (re-drilled 12/29/24 and 5/23/25) 110 36 7 10/15/2024 N/A, Decommissioned 6/3/25  15 5 8 10/17/2024 95 (re-drilled 8/14/25) 69 22 9 10/25/2024 N/A, Decommissioned 11/07/24  69 22 9A 11/16/2024 Offline (re-drilled 12/29/24, 5/10/25, 8/22/25) 10 10/24/2024 120 (re-drilled 5/11/25) 132 43 11 12/3/2024 N/A, Decommissioned 3/14/25  2 1 Totals 515 1,007 328 To support the need for continued emergency contracting authority, recommendations for the 2025-26 rainy season emergency winterization have been developed and are being presented to the City Council for their consideration this evening under a separate agenda item. Fiscal Year 2024-25 Payment Ratification and Retroactive Contract Approvals Upon the City Council’s declaration of a state of local emergency relating to the land movement in the Landslide Complex on October 3, 2023, various companies were hired to perform emergency response work ranging from landslide stabilization to public infrastructure repairs. Staff utilized existing contracts to deliver these services where possible, but in some cases, contracts were not in place at the time the emergency response was needed and there was not sufficient time or staff resources to put contracts 7 in place. Therefore, work was ordered under the City Manager’s authority pursuant to the emergency declaration. Staff now seek City Council ratification of payments and retroactive contract approval for work performed through June 30, 2025, in accordance with best practices and increased public transparency. Payments have already been made using previously appropriated City Council funds for the payment ratifications and retroactive amendments presented this evening. The City Council action only covers work performed through FY 2024-25, ending June 30, 2025, and does not include any work for FY 2025-26. The proposed retroactive contract amendments serve to provide a complete agreement record reflective of the landslide emergency work completed by, and amounts paid to each contractor through June 30, 2025. Reference can be made to the Council Recommended Action for a general description of the services provided and reference can be made to the recitals provided in each proposed contract amendment (Attachments C, E, G, J, L, and N) for a detailed description of the scope and cost of services for each contractor. Fiscal Year 2025-26 To rely less on emergency work orders and more on pre-approved contracts for anticipated landslide work in FY 2025-26, Staff presented multiple on-call contracts for City Council consideration at its July 1, 2025 meeting. In response, the City Council approved multiple contracts for emergency landslide stabilization and related infrastructure repair work at the July 1, 2025 meeting (Attachment B). These contracts are expected to cover all landslide work in FY 2025-26; however, work outside these contracts may be needed. Should that be the case, Staff will present new contracts for City Council consideration in advance when possible; or may request retroactive approval in cases when immediate action is necessary. In all cases, no work will be conducted beyond City Council-approved budgets. For vendors with retroactive amendments for FY 2024-25 that have also been separately awarded landslide or other contracts with the City for FY 2025-26, the retroactive amendments presented in this staff report either sunset June 30, 2025 or partition the scope of services for FY 2024-25 landslide emergency response from other services. CONCLUSION: The effects of the ongoing land movement continue to be felt in the Greater Portuguese Bend-Ancient Altamira Landslide Complex. Staff recommend reconfirming that there is a need to continue to remediate the emergency identified by City Council-adopted Resolution No. 2024-20 (originally by Resolution No. 2023-47). 8 Additionally, Staff recommend ratifying payments and retroactively approving contracts for emergency stabilization work performed in FY 2024-25 under the City Manager’s orders pursuant to the emergency declaration. ALTERNATIVES: In addition to Staff recommendation, the following alternative actions are available for the City Council’s consideration: 1. Identify recommended amendments to the proposed contract amendments for FY 2024-25. 2. Take other action or provide direction, as deemed appropriate. 9