CC SR 20250819 04 - Landslide Emergency Extension CITY COUNCIL MEETING DATE: 08/19/2025 AGENDA REPORT AGENDA HEADING: Regular Business AGENDA TITLE: Consideration to receive updates on the Greater Portuguese Bend-Ancient Altamira Landslide Complex. RECOMMENDED COUNCIL ACTION: (1) Receive and file an update on current conditions in the Greater Portuguese Bend- Ancient Altamira Landslide Complex (Landslide Complex); (2) Receive and file an update on emergency stabilization activities in the Landslide Complex; (3) Receive and file a report on the Fiscal Year 2024-25 Deep Dewatering Well (DDW) and winterization emergency stabilization measures; (4) Review a ranked priority order list of costs associated with the Fiscal Year 2025- 26 DDW and winterization programs; (5) Receive and file a financial update on City expenditures for emergency protective and stabilization measures in response to the acceleration of the Landslide Complex; (6) Approve the submittal of a grant application to the Federal Emergency Management Agency’s (FEMA) Hazard Mitigation Grant Program (HMGP) for the Portuguese Bend Landslide Remediation Project with a $10 million match from the unallocated fund balance in the General Fund; (7) Award a professional services agreement to Geo-Logic Associates, Inc. (GLA) for final engineering design, environmental documents, and related services for the Portuguese Bend Landslide Remediation Project (Capital Improvement Project (CIP) 8304) in the amount of $460,685 with a contingency of 15% or $69,103; (8) Authorize the Mayor to execute the agreement with GLA in a form approved by the City Attorney; (9) Adopt Resolution No. 2025-___, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, CALIFORNIA, EXTENDING FOR A TERM OF 60 DAYS THE TEMPORARY PROHIBITION ON TRAVEL BY UNICYCLES, BICYCLES, MOTORCYCLES, AND OTHER ONE- OR TWO- WHEELED VEHICLES ON PALOS VERDES DRIVE SOUTH WITHIN THE LANDSLIDE COMPLEX DUE TO CONTINUED ROADWAY CONDITIONS; (10) Adopt Resolution No. 2025-__, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, CALIFORNIA, CONTINUING THE LOCAL EMERGENCY DECLARATION AS ESTABLISHED BY RESOLUTION NO. 2023 - 47 ADOPTED ON OCTOBER 3, 2023 FOR AN ADDITIONAL 60 DAY PERIOD; and, (11) Adopt Resolution No. 2025-__, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, CALIFORNIA, EXTENDING THE STATE OF LOCAL EMERGENCY WITHIN THE GEOGRAPHIC BOUNDARIES OF THE 1 PORTUGUESE BEND COMMUNITY ASSOCIATION, PORTUGUESE BEND BEACH CLUB, AND SEAVIEW NEIGHBORHOODS BASED ON SUDDEN ENERGY SHORTAGES, PLANNED DEENERGIZING EVENTS, AND INTERNET SERVICE SHUT OFFS AS ESTABLISHED BY RESOLUTION NOS. 2024-52 AND 2024-57 FOR AN ADDITIONAL 60 DAYS. FISCAL IMPACT: Approving a professional services agreement with GLA for final engineering design and related services for the Portuguese Bend Landslide Remediation Project (CIP 8304) will result in fiscal impact of up to $529,787 inclusive of contingency. The approved Fiscal Year (FY) 2025-26 CIP includes funding for final engineering design, environmental documents, and related services for this project; of which $700,000 is from the CIP Fund as the required 30% matching funds for the Federal Emergency Management Agency (FEMA) Building Resilient Infrastructure and Communities (BRIC) grant that the City was awarded for Phase 1 Design in the amount of $2.3 million as the 70% federal funds. Staff notes that FEMA previously issued a notification that the BRIC program was being discontinued; however, recent court filings indicate that the program is not being discontinued. FEMA representatives have verbally informed the City that the City’s Phase 1 Design award will continue, and Staff are seeking written confirmation. Should the BRIC program not provide funding for this work, the City funding in the approved FY 2025 -26 CIP is sufficient to complete the study. Approving submittal of an application to the FEMA Hazard Mitigation Grant Program for the Portuguese Bend Landslide Remediation Project requires a $10 million local match. Based on the projected FY 2025-26 fund balance and assuming all CIP projects are completed, the Capital Infrastructure Program (CIP) Fund is estimated to end the year with a $2.2 million balance, with an additional $5 million held in reserves. As a result, sufficient funding is not available from the CIP Fund to meet the match requirement. The City Council may consider allocating the required match from the City’s General Fund unallocated balance. According to projections presented at the FY 2025 -26 budget workshop, the General Fund is expected to end the year with a $27.3 million balance, o f which $17 million is held in reserves and $10.3 million unallocated. For cash flow purposes, staff anticipates that the $10.3 million will be needed to support the FEMA Voluntary Property Acquisition Buyout Program, with reimbursement expected within the same fiscal year. Therefore, should the City Council elect to allocate the $10 million match from the General Fund for the Portuguese Bend Landslide Remediation Project , the timing is anticipated to be reasonable, as the project is expected to be a multi-year project. Once the FEMA grant has been awarded, a budget appropriation request for the matching funds of $10 million will be presented to the City Council for consideration. VR Portuguese Bend Landslide Budget The Portuguese Bend Landslide emergency response is projected to reach approximately $48 million from the period beginning in October 2022 through the fiscal year (FY) ending June 30, 2025, including purchase order carryovers and continuing appropriations from FY 2023-24. This amount is funded through various sources, including the General Fund, CIP Fund, ARPA, Supervisor Hahn’s Social Program Grant, and Metro Funds. 2 Additionally, for FY 2025-26, the City Council adopted the following budget of $17,750,000 in the CIP for the Portuguese Bend Landslide and $860,300 for property tax assessments in the General Fund: FY 2025-26 Adopted Budget: Capital Infrastructure Program (CIP) Fund: Funding Source: Capital Infrastructure Program (CIP) Fund FY 2025-26 Adopted Budget 8202 - Abalone Cove Sanitary Sewer Repair Program 3,000,000 8304 - Portuguese Bend Landslide Remediation 700,000 8307 - Portuguese Bend Landslide Remediation - Emergency Stabilization Measures 8,050,000 Construction 5,750,000 Professional Services (Engineering, Environmental, Inspection, Management 1,725,000 Contingency 575,000 8308 - Portuguese Bend Landslide Remediation - Deep Dewatering Wells 1 thru 6 Permanent Power (City's Federal Grant Match) 525,000 8309 - Portuguese Bend Landslide Hydrology & Hydraulics Study 1,400,000 TOTAL - FY 2025-26 (CIP FUND) $13,675,000 Special Revenue (Restricted) Funds: Funding Sources: Special Revenue (Restricted) Funds FY 2025-26 Adopted Budget 8302 - Palos Verdes Drive South Landslide Repair Program 2,500,000 Gas Tax (Fund 202) 750,000 Prop C (Fund 215) 1,150,000 Measure R (Fund 220) 600,000 8308 - Portuguese Bend Landslide Remediation - Deep Dewatering Wells 1 thru 6 Permanent Power 1,575,000 Federal Grant 1,575,000 TOTAL - FY 2025-26 SPECIAL REVENUE (RESTRICTED) FUNDS $4,075,000 General Fund: Funding Source: General Fund FY 2025-26 Adopted Budget 3150 Property Tax Assessments KCLAD 475,902 ACLAD 384,398 TOTAL - FY 2025-26 General Fund $860,300 3 As part of the FY 2025-26 budget process, the City Council directed staff to present a priority list of landslide emergency response projects/activities totaling $9 million so that the City Council may consider future budget reductions based on the priority order rank list. As such, included in this report is the ranked priority order list of projects. Should the City Council enact any budget reductions, then any agreements/contracts for those projects/activities impacted by the budget reductions could be cancelled or reduced with 30 days due notice to the vendor and payment for costs incurred within the cancellation period, if applicable. Since the majority of expenditures occurred in FY 2024-25, the following summarizes the approved appropriations and expenditures for that fiscal year: For FY 2024-25, the City Council appropriated $36.8 million (including Purchase Order carryovers and continuing appropriation from FY 2023 -24) for emergency work outside the normal bidding process due to the emergency declaration as follows: • $23.9 million for emergency response, boreholes and deep dewatering wells (DDW), including $9.6 million approved on May 7, 2024 (unspent balance from Hydraugers Project by June 30, 2024 was carried over in FY 2024-25) and $6.1 million on October 1, 2024. • $4 million for emergency stabilization measures for additional DDWs approved on October 1, 2024. • $4 million for winterization approved on October 1, 2024. • $1.1 million for operations and maintenance of DDWs between January and March 31, 2025, approved on December 17, 2024. • Approximately $3.9 million of the following CIP projects are deferred to FY 2025 - 26 as approved on January 21, 2025: o $0.6 million for Crenshaw Blvd. Rehab; o $0.6 million for Park Playground Improvements; o $0.55 million for the Sidewalk Management program; o $1.7 million for Western Avenue Beautification; and, o $0.5 million for Altamira Canyon Drainage • $2 million for operations and maintenance of DDWs (approximately $1.5 million from April 1, 2025 through June 30, 2025) and approximately $0.5 million for additional fissure filling approved on January 21, 2025. • $710,000 from the CIP Fund approved on March 18, 2025 for repairs to the Abalone Cove Sanitary Sewer System by: o Reallocating $400,000 from the Measure R Fund to the CIP Fund for landslide emergency road repairs, o Reallocating $200,000 from the Gas Tax Fund to the CIP Fund for landslide emergency road repairs, and o Appropriating the remaining $110,000 from the CIP Fund. • $500,000 from the CIP Fund for additional operations and maintenance costs associated with the DDW Program approved on May 6, 2025. Assistance to the geologic hazard abatement districts was approved in the form of loans and in-kind assistance as follows: • On February 4, 2025, the City Council affirmed the use of the financial assistance loan to Abalone Cove Landslide Hazard Abatement District (ACLAD) in the amount 4 of $1.6 million approved by the City Council on July 2, 2024 for ACLAD to implement their deep dewatering well plan; and • $100,000 for in-kind project and construction management services provided by the City to assist the ACLAD with implementation of their DDW plan. In summary, the following tables are a summary of approved budget appropriations in FY 2024-25 and summary of funding sources by Fund. FY 2024-25 Summary of Budget Appropriations: [Continued on Next Page] FY 2024-25 Budget Appropriations (Summary) in millions TOTAL FY 2024-25 Adopted Budget $4.6 $13.7 October 1, 2024 $14.1 Emergency response, boreholes, DDW, winterization ARPA Fund 0.5 LA County Grant (Sup. Hahn)2.2 CIP Emergency Reserves 5.0 General Fund Unallocated Fund Balance - Transfers Out 6.4 December 17, 2024 $1.1 O&M for DDDW between Jan-Mar 2025 CIP Fund 1.1 January 21, 2025 $2.0 Additional O&M for DDW between Apr-Jun 2025 and fissure filling CIP Fund (DDW)1.5 CIP Fund (Fissure Filling)0.5 February 4, 2025 $0.1 In-Kind Services for ACLAD Affirmed $1.6 million of loans to ACLAD and KCLAD CIP Fund (DDW)0.1 March 18, 2025 $0.7 Additional O&M Ab Cove Sanitary Sewers CIP Fund 0.1 Reallocate Measure R 0.4 Reallocate Gas Tax 0.2 May 6, 2025 $0.5 Additional O&M DDW CIP Fund 0.5 TOTAL - FY 2024-25 $36.8 Carryover from FY 2023-24 ( Prof/Tech, Reallocation 5 FY 2024-25 Summary of Funding Sources (by Fund): ORIGINATED BY: Ramzi Awwad, Director of Public Works Vina Ramos, Director of Finance VR Brandy Forbes, Director of Community Development REVIEWED BY: Catherine Jun, Deputy City Manager CJ APPROVED BY: Ara Mihranian, AICP, City Manager ATTACHED SUPPORTING DOCUMENTS: A. Resolution No. 2025-___ Continuing Temporary Prohibition of One- or Two- Wheeled Vehicles on Palos Verdes Drive South for 60 Days (Page A-1) B. Resolution No. 2025-___ Continuing Local Emergency (Page B-1) C. Resolution No. 2025-___ Continuing Local De-energization Emergency (Page C-1) D. Displacement Rate Contour Map: July 1 and August 5, 2025 (Page D-1) E. Landslide GPS Survey Report: July 1 and August 5, 2025 (Page E-1) F. Professional Services Agreement with Geologic for the PBL Remediation Project (Page F-1) G. Proposal from Geologic for the PBL Remediation Project (Page G-1) H. Request for Proposal for the PBL Remediation Project (Page H-1) I. CIP Sheet for the PBL Remediation Project (Page I-1) BACKGROUND: The Greater Portuguese Bend Landslide Complex, sometimes called the Ancient Altamira Landslide Complex (Landslide Complex) encompassed four historically active landslide areas in the City: the Portuguese Bend Landslide (PBL), the Abalone Cove Landslide (ACL), the Klondike Canyon Landslide (KCL), and the Beach Club Landslide (BCL). The Landslide Complex now also includes areas outside of the City’s historical boundaries of those known landslides, predominantly uphill from the PBL and ACL, within the Landslide Complex as mapped by various agencies (i.e., U.S. Geological Survey and California Geological Survey) and other researchers. Funding Sources for FY 2024-25 TOTAL In Millions CIP Fund 14.5 CIP Fund (Reserves)5.0 CIP Fund (Cont Approp 01/21/25)0.5 General Fund (Transfers-Out Reserves to the CIP Fund) 6.4 General Fund 3.4 Special Revenue (Restricted) Funds ARPA Fund 3.4 Metro Fund (Prop C, Measure R)1.4 Sup. Hahn's Social Program Grant 2.2 TOTAL $36.81 6 On October 3, 2023, the City Council conducted a discussion regarding the conditions of the Landslide Complex. After considering information presented that evening, including public testimony, the City Council unanimously adopted Resolution No. 2023-47 declaring the existence of a local emergency within the geographic boundaries of the Landslide Complex and adopted Urgency Ordinance No. 674U to establish a 45-day moratorium on the acceptance or processing of applications, issuance of permits, and construction of all structures within the Landslide Complex (Moratorium). The City Council has extended the local emergency on multiple occasions, and it remains in effect until August 30, 2025, unless extended again this evening. On August 20, 2024, the City Council authorized the emergency installation of immediate stabilization and protection measures consisting of deep dewatering wells (DDWs) in response to exponential acceleration of the Landslide Complex as a result of historic rainfall during the 2022-23 and 2023-24 rainy seasons. On October 1, 2024, the City Council authorized an expansion of the DDW program to the Abalone Cove area, on City-owned property. Additionally, the City Council authorized a winterization program on City-owned property in the Landslide Complex without waiving the Abalone Cove Landslide Hazard Abatement District’s (ACLAD) and Klondike Canyon Landslide Hazard Abatement District’s (KCLAD) responsibilities as identified in their plans of control. On February 18, 2025, the City Council affirmed only using the $1.6 million City loan to implement ACLAD’s DDW Plan including two monitoring wells and instrumentation that would be installed, maintained and operated by ACLAD within their jurisdictional boundaries. A sum of $100,000 was also approved to provide ACLAD with professional services (i.e. project management and geologist). On March 18, 2025, the City Council approved amending the loan agreement to ACLAD by extending the first loan payment from December 1, 2025 to December 1, 2026; and updating the scope to include the implementation of DDWs. Tonight, the City Council will receive its 60-day standing report on the current conditions of the Landslide Complex and consider extending the prohibition of one- and two-wheeled vehicles along Palos Verdes Drive South through the Landslide Complex and extending the Local State of Emergency and Building Moratorium. DISCUSSION: Current Conditions Geologic Conditions The City’s contracted geologist, Mike Phipps of the firm Cotton, Shires & Associates, Inc. (CSA) previously reported that rainfall from the wetter than average rainy seasons in 2022-23 and 2023-24 and the resulting runoff and infiltration into the Landslide Complex had an adverse effect on the landslide area. The 2024-25 rainy season has been drier than average and has been relatively beneficial. As of August 12, 2025, only 6.58 inches of rain has fallen at the Rolling Hills Fire Station 7 56 rain gauge since the start of the 2024-25 rainy season (October 1, 2024), representing just 48% of the season average. The impact of the well below-average 2024-25 rainy season continues to be beneficial in terms of landslide movement, which generally continues to slowly decelerate in areas that are still moving. This is believed to be largely due to significantly below-average rainfall through early-August, positive effects from the major winterization efforts undertaken by the City and ACLAD and KCLAD in the fall and early winter, and ongoing dewatering efforts by the City and ACLAD and KCLAD. Recent GPS survey data published by McGee Surveying Consulting for the approximately “monthly” monitoring periods ending July 1, 2025 and August 5, 2025 were reviewed and analyzed (Attachment E). Figures 1 and 2 present scaled displacement rates (i.e., movement velocities), movement vectors, and contours (aka “heat map”) of displacement rates for the July 1, 2025 and August 5, 2025 full monitoring periods. (Attachment D) Figure 1: Scaled Displacement Rates for July 1, 2025 Monitoring Period 8 Figure 2: Scaled Displacement Rates for August 5, 2025 Monitoring Period For all points monitored across the entire Landslide Complex, the following are the key conclusions for the time period of June 3 through August 5, 2025: • The ACL movement, within its historical boundary, has decelerated an average of approximately 25% between June 3 and August 5, 2025. The average rate of movement for these points was 0.99 ft/month from June 3 through August 5, 2025. The ACL movement has decelerated an average of 69% since the deep dewatering program commenced mid-September 2024. The fastest moving area remains the upper portion of the ACL at an average of 1.15 feet per month (about 3.2 inches per week); however, the area of the ACL moving in the 3 to 4 inch per week range (light blue area on the heat map Figures 1 and 2 above) continues to shrink considerably, most likely in response to recent deep dewatering efforts by ACLAD. It is anticipated that this movement rate will continue to decelerate as dewatering production increases. • The PBL, within its historical boundary, has decelerated an average of 24% from June 3 through August 5, 2025. The average rate of movement for these points was 0.58 ft/month from June 3 through August 5, 2025. The PBL movement has decelerated an average of 83% since the deep dewatering program commenced in mid-September 2024. Following completion of DDWs 1 through 6, by late October 2024 the PBL experienced a dramatic reduction in movement velocity. From October 2024 through mid-February 2025 the PBL was viewed as having reached a steady state of movement. A slight uptick in movement velocity occurred in response to rainfall in February and March 2025; however, since April 9 2025, the GPS monitoring data indicate that the PBL has been steadily decelerating. • The KCL continues to have no measurable movement since mid -October 2024. Although some points in the KCL appear to show measurable changes in their GPS position, these movements are at or below the limits of instrument precision. Further absolute vector analysis shows that the changes are not in a consistent progressive pattern, but rather in random directions, which indicates GPS “noise” rather than actual movement. This lack of measurable movement indicated by the GPS survey in the KCL continues to be corroborated by periodic field reconnaissance of the Seaview and Portuguese Bend Beach Club (PBBC) neighborhoods performed by CSA. Because there is no movement occurring, the KCL has decelerated 100% since the deep dewatering program commenced in mid-September 2024. • The Greater Ancient Altamira Landslide Complex/Ancient Portuguese Bend Landslide Complex points outside of the historical boundaries of the ACL and PBL have decelerated an average of 25% from June 3 through August 5, 2025. The average rate of movement for these points was 0.90 ft/month from June 3 through August 5, 2025. The Greater Portuguese Bend/Ancient Altamira Landslide Complex points have decelerated an average of 72% since the deep dewatering program commenced in mid-September, 2024. • There continues to be no measurable movement of points along the Burma Road switchbacks since December 3, 2024. Vector analysis performed on the GPS points in this area confirms that the reported data represent GPS instrument “noise” rather than actual movement. • There continues to be no measurable movement of points along Burma Road, located just north of the mapped boundary of major landslide movement (2023 - 2025) and downslope from recent movement occurring in Rolling Hills in the Flying Triangle Landslide, as well as areas of Cinchring Road and Quail Ridge Road. This lack of measurable movement continues to support a hypothesis that the Altamira Complex and the landslide(s) further north-northeast in Rolling Hills, portions of which continue to creep, are not directly structurally connected. • There continues to be no measurable movement of GPS points located outside of the mapped Greater Ancient Altamira Landslide Complex/Ancient Portuguese Bend Landslide Complex, including at Abalone Shoreline Park, in the Island View tract, at the top of Burma Road, at the west end of the former Livingston Quarry area (Forrestal), and in the Seaview Tract. Table 1 on the following page provides a summary of movement rates for each sub-slide over time. 10 Table 1: Sub-Slide Movement Rates as of August 5, 2025 Sub-Slide Oct 2022 Oct 2023* July 2024** August, 2025 August 5, 2025 Decrease from July 2024 Peak Average Movement (Inches/Week) % KCL 0.06 0.33 4.34 0.0 100% PBL 0.17 0.91 11.02 1.60 85% ACL 0.14 0.72 10.25 2.72 73% Upper Altamira 0.08 0.52 9.17 2.48 73% Factor of Movement KCL 1 5.5 72.3 0 - PBL 1 5.4 64.8 9.4 - ACL 1 5.1 72.3 19.4 - Upper Altamira 1 6.5 114.6 31 - *Month of emergency declaration **Month of peak movement rate Open Space, Palos Verdes Nature Preserve, Trails, and Beach Conditions Out of concern for public safety and in consultation with the City Geologist, the City Manager has temporarily closed much of the Portuguese Bend, Filiorum, and Abalone Cove Reserves (subareas of the Palos Verdes Nature Preserve) including approximately 16 miles of passive recreational trails. The City Manager has also temporarily closed Abalone Cove Beach, Sacred Cove Beach, and the beach below the Archery Range (east of Inspiration Point) in close coordination with the City Geologist, Los Angeles County Lifeguards, and the California Coastal Commission. Staff continue to monitor these and other areas, and extensive repairs will likely be needed before these trails and open space areas can be reopened for public use after the area has been stabilized. Emergency Stabilization Activities DDW Program Status The DDW component of the emergency stabilization funded by the City Council, inclusive of test boreholes and monitoring wells, is complete. Figure 3 shows the location of the DDWs, test boreholes, and monitoring wells. [Continued on Next Page] 11 Figure 3: Deep Dewatering Wells Following are key notes regarding specific DDWs: The total combined water extraction rate of the DDWs is currently approximately 600 gallons per minute or 0.86 million gallons per day. • Since the start of the DDW program, approximately 306 million gallons, or 940 acre- feet of water have been extracted. • DDW-5 has sheared due to land movement. The City’s Geologists are evaluating the potential for re-drilling or re-locating this well. Funding for this and other DDW activities comes from FY2025-26 DDW maintenance and operations funds approved by the City Council as part of the FY2025-26 Capital Improvement Program (CIP). • DDW-7 has sheared, and based on its low production rate, the City’s Geologists are advising that the well be re-located rather than re-drilled in its approximate existing location. • DDW-8 has sheared due to land movement. Re -drilling is underway and should be complete shortly. • DDW-9A has sheared due to land movement. Redrilling is scheduled to begin following the completion of re-drilling DDW-8. • DDW11 sheared and based on the low production rate, the City’s Geologists are advising that this DDW should not be re-drilled, but rather re-located, should additional funding become available. Due to the significant cost of relocating this DDW, considered to be well above maintenance and operations, there are currently no plans in place to relocate the well. 12 Table 2: DDW Current Water Extraction Rates as of August 11, 2025 DDW No. Date Operational Current Approximate Water Extraction Rate (Gallons Per Minute) Total Water Extraction to Date Acre-Ft Million Gallons 1 9/13/2024 100 (re-drilled 3/21/25) 126 41 2 9/17/2024 100 (re-drilled 5/29/25) 123 40 3 9/21/2024 90 (re-drilled 3/24/25) 121 39 4 9/21/2024 N/A (decommissioned 3/27/25) 90 29 4A 3/29/2025 55 5 9/25/2024 Offline (re-drilled 3/26/25; redrill required) 116 38 6 9/28/2024 80 (re-drilled 12/29/24 and 5/23/25) 101 33 7 10/15/2024 N/A (decommissioned 6/3/25) 15 5 8 10/17/2024 Offline (re-drill in progress) 59 19 9 10/25/2024 N/A (decommissioned 11/07/24) 67 22 9A 11/16/2024 55 (re-drilled 12/29/24 and 5/10/25; redrill required) 10 10/24/2024 120 (re-drilled 5/11/25) 120 39 11 12/3/2024 N/A (decommissioned 3/14/25) 2 1 Totals 600 940 306 Underground water pressure measuring instruments, called vibrating wire piezometers (piezometers) were installed to assist in determining the effects of DDWs on reducing high water pressures, including locally artesian pressures, that might be contributing to accelerated landslide movement. Five monitoring wells with piezometers were installed at the locations shown in Figure 4 on the following page. The piezometers were installed under the deep slip plane as well as under the shallow slip plane to measure uplift pressure on each slip plane. Additional monitoring wells with piezometers were considered but not installed so that more of the limited funding amount could be directed towards landslide stabilization activities. [Continued on Next Page] 13 Figure 4: Water Pressure Measurement Instrument Locations Chart 1 shows water pressures from the piezometers installed under the deep slip plane and Chart 2 shows water pressures from the piezometers installed above the deep slip plane and below the shallower slip plane. The charts show water pressure from the time the piezometers were installed until the present time, or until they stopped functioning due to landslide shearing. Pressure on the plots has been converted to equivalent feet of water pressure. [Continued on Next Page] 14 Chart 1: PBL Deep Slip Plane Water Pressure Chart 2: PBL Mid-Deep Slip Plane Water Pressure 15 For those piezometers near the DDWs (P-1, P-2, and P-3), the plots show a marked decrease in pressure immediately following the start of the DDW program . The surviving piezometer, P-2, continued to show a marked pressure drop over time, which correlates to reduced surface movement in nearby GPS survey points. There has been a slight uptick in pressure between June and the beginning of August; most likely due to well pump maintenance and sporadic downtime. The piezometers far away from DDWs (E-2-2 and E-2-5) show only a slight, but somewhat continuous decrease in pressure over time. The slight reduction shown in piezometer E- 2-2 and E-2-5 is likely the result of drying conditions and below normal rainfall. It is notable that the drop in pressure for piezometer P-2 where there is water pumping reached almost twice the drop in pressure for piezometer E-2-5 where there is no water pumping. Emergency Winterization Status Preparations for the 2025-26 rainy season have started with field reconnaissance by geologists. The information from the field-reconnaissance will be used to prioritize improvements and repairs, as constrained with the approved winterization budget in the FY 2025-26 CIP. ACLAD Update Following is the status of ACLAD’s activities as of August 11, 2025. Figure 5 shows the locations of the ACLAD dewatering wells. • 6 original/shallow wells are operational and extracting water at a rate of approximately 114 gallons per minute. • 10 DDWs are operational and extracting water at a rate of approximately 318 gallons per minute. • ACLAD pumped 6.8 million gallons in the month of July 2025. • Drain wells do not operate during the evening hours due to the use of generators. • Drain line connections for an additional 2 DDWs have been completed. • 2 Monitoring Wells with piezometers have been installed. • Various repairs and drainage line improvements have been completed. ACLAD installed piezometers in the vicinity of their DDWs to collect data on the impact of the DDWs on high water pressures, including local artesian pressures, that might be contributing to accelerated landslide movement. Two monitoring wells with piezometers were installed at the locations shown in Figure 5. The piezometers were installed under the deep slip plane as well as under the shallow slip plane to measure uplift pressure on each slip plane. [Continued on Next Page] 16 Figure 5: ACLAD Dewatering Wells with Water Pressure Measurement Instrument Locations The City’s consultant engineering geologists, in coordination with ACLAD, reviewed the data from the piezometers and prepared charts to show water pressure over time. Charts 3 and 4 show water pressure from the time the piezometers were installed until the present time. Pressure on the plots has been converted to equivalent feet of water pressure. [Continued on Next Page] 17 Chart 3: ACLAD Deep Slip Plane Water Pressure Chart 4: ACLAD Mid-Deep Slip Plane Water Pressure These plots show a positive, strong correlation to pressure drops at the slide planes after the initiation of the ACLAD DDW program (beginning on 6/24/25) and a more positive correlation to initiation of specific DDWs that are closest to the piezometer locations. Staff 18 notes that although pumping near the piezometers has only been active within the last month or so, the minimal amount of data already displays distinct drops in pressure from the initiation of nearby pumping wells. Additionally, the City has revised the partial (mid-month) GPS monitoring points to include a number of points in the vicinity of the recent ACLAD DDW’s, to further the assessment of ACLAD DDW effectiveness in slowing the land movement. A prominent deceleration of ACL and Altamira monitoring points occurred from July 1 to August 5, (average deceleration 20%) compared to June 3 to July 1 period (average deceleration 6%). This is interpreted to be a response to ACLAD DDW’s coming online, specifically DDW21 on 6/23/25, DDW’s 25 through 28 on 6/24/25, DDW29 on 7/9/25 and DDW8 on 7/23/25. Of particular note is a significant deceleration in movement velocity for GPS monuments AB57, AB58 and AB59 from July to August, compared to other monuments. This deceleration is illustrated in Chart 5 below, with the dashed lines depicting the steeper (declining) slope of movement velocity for AB57, AB58 and AB59. Chart 5: ACLAD DDW Dewatering Impact on Land Movement KCLAD Update Following is the status of KCLAD’s activities as of August 12, 2025. Figure 6 shows the locations of KCLAD dewatering wells. 19 • KCLAD Well 5’s pump is set at 110 feet below ground surface and is extracting 26 gallons per minute while maintaining a water level of 72 feet below ground surface. This pump needs service and is scheduled to be pulled as soon as new KCLAD Well 7 is put into production. • KCLAD Well 6 has been returned to service following a period of shutdown due to poor performance. The pump has been serviced and reinserted at a depth of 150 feet below ground surface. The reinstalled pump is currently extracting 190 gallons per minute while maintaining a water level of approximately 88 feet below ground surface. • New KCLAD Well 7 is nearing completion of construction. Drilling has been completed, and crews are now working on supporting infrastructure including discharge lines and electrical power. The target pump depth will be 175 feet below surface level. Work will be completed in the coming weeks. • Repairs are also planned for KCLAD Well 3 and KCLAD Well 4, both shallow wells, to bring them back into service. • Weekly readings are uploaded to the KCLAD website (KCGHAD.org). Figure 6: KCLAD Dewatering Wells There has been no measurable movement in the Seaview and PBBC neighborhood since mid-October 2024. KCLAD and Staff continue to coordinate on drainage and winterization efforts. 20 Utility Updates Natural Gas (Southern California Gas Company – SoCalGas) Dates Area Affected Update 2024 July 29 Portuguese Bend Community Association (PBCA) Natural gas shut off due to land movement. August & September Seaview Natural gas shut off due to land movement. September 6 Portuguese Bend Beach Club (PBBC) Natural gas shut off due to land movement. 2025 Q1 Seaview & PBBC Following months of no measurable movement, SoCalGas conducted a detailed system integrity assessment of underground infrastructure to determine how to safely restore gas. April Seaview & PBBC Steel pipelines in PBBC and Seaview showed a higher-than-expected resilience to subsurface movement and stress, resulting in positive potential of restoration. May – July Seaview SoCalGas began work on restoring service in Seaview. Restoration of service includes modernizing portions of the existing infrastructure, adding safety mitigation such as automatic shut-off valves, additional manual valves, and real- time pressure monitoring equipment. The work is continuing generally according to plan with the exception that some additional segments of pipe are being replaced. With the exception of homes on PVDS Service Rd, all other homes in Seaview that have taken the steps necessary to receive gas service, have now had their service restored. August Seaview- PVDS Service Rd PBBC SoCalGas began work on restoring service in PBBC. All restoration plans are dependent upon sustained minimal land movement rates, which will continue to be monitored by SoCalGas and local partners. SoCalGas will continue to monitor the safety of the natural gas system in Seaview through electronic pressure monitoring, land movement markers, and increased leak surveys. SoCalGas will also 21 continue to coordinate with first responders, city officials and third-party experts monitoring and responding to dynamic land movement conditions. The City will continue working with CPUC and SoCalGas to advocate for restoring gas service to the PBCA in a manner that aligns with public safety and community needs. Electricity (Southern California Edison – SCE) Dates Area Affected Update 2024 August 31 PBCA 193 metered accounts notified that power will be turned off on September 1 for an indefinite period of time. September 1 PBCA and City of RPV Sewer System Area de-energized (including power to City’s sewer system and the ACLAD dewatering wells). September 2 Seaview Notice issued that homes in the Seaview would be subject to the following service shut offs: 75 properties will be deenergized for varying hours ranging from 24 hours to 1-3 weeks while a box loop is constructed and 30 properties will be deenergized indefinitely. September 6 PBBC Customers that power would be shut off SCE followed through, de-energizing the area on September 9th. September 9 PBBC Area de-energized. September 9 Seaview Power restored to the 38 properties that had been planned to be without electricity for 1-3 weeks, leaving 30 properties without electricity. Q4 Re-energized 16 customers located primarily on Fruit Tree Road, Plumtree Road, and Narcissa Drive in the western portion of the Landslide Complex. 2025 January 13 Seaview & PBBC Plan proposed to temporarily restore power to up to 116 customers, including approximately 76 properties by approximately the end of Q1 (March 31, 2025), excluding red-tagged homes. February - July Seaview & PBBC 75 homes and 2 KCLAD dewatering well meters re-energized. 14 homes in the PBBC and Seaview communities remain without power, 22 Dates Area Affected Update awaiting electrical inspection clearance. SCE will re-energize the remaining homes on a weekly basis upon successful completion of electrical inspection. August Seaview & PBBC As part of our ongoing efforts to enhance the resiliency and reliability SCE infrastructure, SCE will begin installing an innovative solution —Tension Relief Strategy — in certain areas of the Palos Verdes Peninsula. For more information, please visit: Energized.edison.com/rpv On May 23, 2025 the City Manager sent SCE CEO Steve Powell a letter requesting reconsideration of land movement threshold to start restoring electric power to the PBCA area. Additionally, it was requested that SCE consider bearing the cost of undergrounding the relocated box loop to help with wildfire resilience and view impacts. SCE provided a response to City Staff on May 30, 2025 declining to change their land movement threshold (1 inch or less per week) in PBCA and declining to bear the cost of undergro unding their relocation. The City will continue working with CPUC and SCE to advocate for restoring electric power to the PBCA in a manner that aligns with public safety and community needs. As a separate item, City Staff and SCE have been working together to redesign and relocate the temporary pole that SCE placed at the Ladera Linda Community Park. On March 4, 2025, the City Council granted a 6 -month time extension for SCE to relocate their power pole. During this time, City Staff and SCE have been focusing on finding an agreeable circuit loop system that meets the needs of the community and SCE in the long term. City Staff took the options to City Council on July 15, 2025, however, due to SCE being unavailable to attend, City Staff requested the item to be continued for another 90 days to allow more time to coordinate with SCE. This item is now tentatively scheduled for the September 16 City Council meeting. Sanitary Sewer – Portuguese Bend Community The sanitary sewer system in the PBCA is known as the Abalone Cove Sanitary Sewer System (Ab Cove Sewer) and is owned, maintained, and operated by the City. Crews continue to regularly inspect the sewer lines and make repairs as breaks are identified through inspections or resident notification. As noted above, the City’s sewer system is normally energized by SCE and is currently using generators to maintain operations while power is shut-off in the PBCA. Sanitary Sewer – Seaview Neighborhood The sanitary sewer system in the Seaview neighborhood is maintained and operated by the Los Angeles County Public Works Department (LACPW), which has been inspecting 23 the sewer system, on an as-needed basis, in areas affected by the landslide. LACPW has reported some localized settling; however, this has not been to a level necessitating repairs. Sanitary Sewer – PBBC The sanitary sewer system in the PBBC is privately owned, operated, and maintained and discharges into the Los Angeles County Sanitation Districts (LACSD) sewer trunk line on PVDS. LACSD have been coordinating with the PBBC, so that the sewer line integrity is maintained. It should be noted that this sanitary sewer system is also powered by SCE. Sanitary Sewer – Palos Verdes Drive South Trunk Lines The sanitary sewer trunk lines adjacent to Palos Verdes Drive South (PVDS) are owned, maintained, and operated by the Los Angeles County Sanitation Districts (San Districts). Due to continued ground movement, the San District is currently replacing the inflexible steel pipe with flexible high density polyethene pipe to both increase the force main’s resilience to ground movement and to provide more effective redundancy preventi ng single points of failure. Construction is scheduled to minimize impacts on traffic to the extent possible, which includes overnight work for certain activities. The replacement project is now expected to be complete by the end of summer 2025. A sewer spill from the San Districts’ above-ground sewer trunk pipe occurred on July 23, 2025 along the south side of PVDS, near the area known as the “ski jump”. The spill occurred at a pipe sleeve (designed to allow some movement of the sewer trunk pipe) because landslide movement was higher than anticipated. The spill traveled across the road to an isolated low-lying area on the north side of PVDS to the west of Peppertree Drive. San Districts staff cleaned and recovered the spill along the road, with the majority of the flow gathering at the low-lying area, which was raked to remove any wastewater debris. The spill did not enter any storm drains that could reach the ocean. Pipe restraints will be added to the pipe sleeve to limit movement and minimize the likelihood of future spills. Water (California Water Service – Cal Water) Throughout the Landslide Complex, Cal Water has brought sections of water lines above ground and completed other emergency measures as follows: Dates Area Affected Update 2024 April 16 PBCA; PVDS (near Wayfarers Chapel) Sections of water line along Clovetree Pl were brought above ground. An emergency portable booster connection were installed near Fruit Tree Rd and Narcissa Dr. 24 Dates Area Affected Update August 21 Seaview Sections of water line along PVDS were brought above ground. October 4 Seaview Sections of water lines along Dauntless Dr, Exultant Dr, and Admirable Dr were brought above ground. October 24 PBBC; PBCA Sections of water lines along Yacht Harbor Dr, Vanderlip Dr, and Burma Rd were brought above ground. November 14 PBCA Sections of water lines along Narcissa Dr, Ginger Root Ln, Cinnamon Ln, and Figtree Rd were brought above ground. December 2 PBCA Sections of water lines near the intersection of Narcissa Dr and Cinnamon Ln were brought above ground. December 6 PBCA A water line near 100 Vanderlip Dr was brought above ground to connect to another above ground line along Vanderlip Dr. 2025 June PBCA – Burma Rd Road restoration is underway. Once complete, will connect the existing above ground main near the Ishibashi Trailhead to the existing above ground main near Vanderlip Trail. PBCA – Narcissa Dr Construction has begun. Anticipated to be completed in July 2025. Will bring existing water lines above ground near the intersection of Narcissa Dr and Vanderlip Dr. July PBCA – Burma Rd Road restoration is complete. Currently the HDPE water main is in process of being installed. PBCA – Narcissa Dr Construction has been completed. Future PBCA – Sweetbay Rd Bring various segments of existing water lines above ground. Project start date is expected to be established in the coming weeks. Communications There are two providers of communications infrastructure in the Landslide Complex area, Cox Communications and Frontier Communications (Frontier). 25 Dates Area Affected Update 2024 September 9 PBCA Cox Communications disconnected 146 customers September PBCA Frontier indicated to the City that they will keep their facilities operational so long as they have power supply. 2025 Q1 PBCA Frontier prepared a concept plan and determined that it is feasible to install fiber optic communication lines, contingent upon easements. Q2 PBCA Frontier surveyed the area in order to properly draft and prepare the easement requests. Frontier and Public Works Staff will continue to coordinate once the easements requests have further progressed. Cost of FY 2024-25 DDW and Winterization Emergency Stabilization Measures The City Council approved funding for the installation, operation, and maintenance of DDWs as well as winterization at the project-level as described in the Fiscal Impact section of this report. To provide a full disclosure of costs to date in the interest of increasing public transparency, Staff are providing a more detailed accounting of expenditures to include the specific cost for each DDW and winterization area by major component. The figures presented in the report are preliminary and there may be min or adjustments once all accounts are reconciled. The costs include all work completed through June 30, 2025 under previously appropriated budgets. DDW Installation To calculate the cost of each DDW, there were expenses for certain activities not attributable to one individual DDW, but that needed to be assigned to certain DDWs to properly distribute costs. These activities include test boreholes installed in advance of DDWs to obtain subsurface geological information on the depth, size, and angle of the landslide slip plane to inform the design of the DDWs including location, depth, materials, and equipment. Additionally, these activities include the construction of access roads so that construction equipment could reach test borehole and DDW sites. To assign costs for these activities, the relative proximity of each test borehole and resulting benefit for the design of a DDW was determined as shown in Figure 7. Accordingly, the cost for each test borehole was distributed to the benefiting DDW(s). Next, the cost of equipment, labor, and materials used to install and commission a DDW was calculated. These costs are primarily proportional to the depth of each DDW as well as the magnitude of site development needed such as access paths, equipment pads 26 and ground stabilization. It is noted that DDWs 1 through 6 share most of the same mechanical infrastructure due to their relative proximity to each other, which results in a lower equipment cost per location. Finally, professional services costs were calculated. These include engineering geology to design the test boreholes and DDWs, geologist monitoring and guidance during installation, and geologist interpretation and recommendations of operational and maintenance information of the wells to optimize and report on their performance. Also, construction management and inspection services were needed to coordinate the logistics of construction, analyze cost proposals against industry averages, manage construction schedules, and administer contracts. Additionally, a lthough the work was performed in accordance with the City Council’s active state of local emergency declaration relating to the land movement in the Landslide Complex, there remain ed applicable federal and state regulations, as well as the City’s Natural Community Conservation Plan / Habitat Conservation Plan (NCCP /HCP); requiring the project’s compliance, reporting, and monitoring during construction with regards to environmental, cultural, and tribal resources potentially affected by the work. The various component costs for each DDW are presented in Table 3. Figure 7: DDW and Borehole Map with Associated Access and Site Development Work 27 Table 3: Summary of DDW Installation Costs for FY2024-25 DDW Test Borehole Access & Site Dev Equipment1 Drilling Geology & Engr2 Const Mgmt & Inspection3 Envrnmt Compliance4 Total 1 $752,295 $343,781 $43,956 $149,072 $105,365 $54,647 $104,128 $1,553,244 2 $619,060 $406,240 $35,743 $162,635 $100,018 $51,873 $98,844 $1,474,412 3 $619,060 $406,240 $35,743 $162,635 $100,018 $51,873 $98,844 $1,474,412 4 $619,060 $406,240 $35,743 $162,635 $100,018 $51,873 $98,844 $1,474,412 5 $619,060 $406,240 $35,743 $162,635 $100,018 $51,873 $98,844 $1,474,412 6 $611,523 $280,707 $35,204 $319,290 $101,901 $52,850 $100,705 $1,502,181 7 $334,604 $270,614 $103,369 $160,625 $71,045 $36,847 $70,211 $1,047,314 8 $336,604 $270,614 $103,369 $160,625 $71,209 $36,932 $70,373 $1,049,724 9 $185,290 $130,162 $101,254 $129,547 $44,648 $23,156 $44,124 $658,182 10 $185,290 $130,162 $101,254 $129,547 $44,648 $23,156 $44,124 $658,182 11 $185,290 $130,162 $101,254 $129,547 $44,648 $23,156 $44,124 $658,182 Total $5,067,134 $3,181,162 $732,632 $1,828,794 $883,535 $458,239 $873,164 $ 13,024,660 1. Includes pumps, instruments, and well casings. 2. Includes design, geotechnical, and peer-review. 3. Includes cost validation for construction contractor bids, budget and schedule management, and construction inspection. 4. Includes emergency permits, environmental impact monitoring, and record keeping. DDW Operations and Maintenance Following their installation and commissioning, each DDW entered an operations and maintenance phase. This phase consisted of operating, maintaining, and monitoring the performance of the submersible pumps, discharge line(s) and power source. The cost of this phase through Fiscal Year 2024-25 is presented in Table 4 on the following page. Each DDW was inspected approximately 3 times per week to ensure each well was extracting groundwater at an optimal well depth and rate, and to identify any maintenance work proactively to reduce unexpected shutdowns. Due to the DDWs’ distance from existing sources of power, generators were rented and refueled on a regular basis to provide continuous power to each DDW pump. Since the initial date of commissioning of the first DDW, land movement impacted overall extraction rates, and in some cases rendered many DDWs inactive. As a result, a total of 13 re-drills were performed under the design and recommendations of the Project’s Geologist, Geo-Logic Associates, Inc. (GLA), and peer-reviewed by CSA. The cost of re- drilling and instances of re-drills at each DDW location is attributable to their overall run time since their initial date of operation, the relative rate of land mo vement within the general area of each DDW, and the ease of re-drilling a DDW in relation to any subsurface obstructions such as the existing well casing, unrecoverable pumps and connecting piping. As further described in the DDW status update above, DDWs 11 and 7 were de- commissioned rather than being re-drilled due to relatively low extraction rates during their operational runtimes. While the magnitude of cost associated with professional services is significantly lower than that during DDW installation, the above -described regular monitoring of the DDWs’ performance and implementation of remedial measures such as pump replacements and re-drilling required the continued use of professional services. The same is applicable to reporting on performance and impacts to land movement. The groundwater extracted by each DDW is directly discharged to the ocean, and does not require any pre-treatment before discharge. However, environmental compliance with the current discharge system requires, at minimum, monthly water quality monitoring, sampling and reporting to the regional and state Water Quality Control Boards. This cost, 28 along with other required environmental reporting, is also factored in the overall expenditure. Table 4: Summary of DDW Operations and Maintenance Costs for FY2024-25 DDW Depth (ft) Re- Drills Run Days Generator & Fuel Pump Maint1 Re-Drills Geology & Engr2 Const Mgmt & Inspection3 Envrnmt Compliance4 Total 1 242 1 290 $164,795 $9,266 $59,733 $19,485 $10,267 $19,284 $282,828 2 245 1 286 $164,795 $9,266 $79,426 $21,126 $11,131 $20,908 $306,652 3 242 1 282 $164,795 $9,266 $59,733 $19,485 $10,267 $19,284 $282,828 4 251 1 282 $164,795 $9,266 $53,260 $8,945 $9,982 $18,750 $274,998 5 230 2 278 $177,551 $9,266 $114,010 $25,072 $13,210 $24,813 $363,921 6 260 2 275 $164,795 $9,266 $135,704 $25,817 $13,603 $25,550 $374,733 7 238 0 231 $158,636 $7,266 $ - $13,827 $7,285 $13,684 $200,698 8 331 1 261 $158,636 $9,266 $70,419 $19,862 $10,465 $19,657 $288,306 9 & 9A 342 3 248 $136,921 $7,266 $363,991 $42,353 $22,316 $41,916 $614,762 10 265 1 249 $136,921 $7,266 $82,077 $18,857 $9,936 $18,663 $273,720 11 & 11A 180 0 101 $76,655 $3,100 $ - $6,647 $3,502 $6,578 $96,484 Total 13 $1,669,294 $89,758 $1,018,352 $231,476 $121,965 $229,087 $3,359,933 1. Includes pumps, instruments, and well casings. 2. Includes design, geotechnical, and peer-review. 3. Includes cost validation for construction contractor bids, budget and schedule management, and construction inspection. 4. Includes emergency permits, environmental impact monitoring, and record keeping. Winterization A summary of the costs to implement winterization measures within the Landslide Complex is provided in Table 5 below. The work focused on preventing surface runoff from infiltrating into the ground in the most impactful locations, which contributes to further land movement. Typically, this was at the landslide boundaries and major fissures, particularly those in canyons. The magnitude of work and relative cost to implement the winterization measures generally correlates to the total area winterized in each location. The work was performed as designed and recommended by the GLA and peer-reviewed by CSA, with field modifications to fit budget constraints and localized conditions. Construction of the winterization measures required construction management and inspection as well as monitoring by GLA to assure conformance to the design intent and recommendations. Similar to the DDW and exploratory borehole installations, a consultant provided services to ensure the work conformed to applicable federal, state and NCCP/HCP environmental compliance requirements. Finally, as with all other activities, cost proposals were independently reviewed by a third -party consultant to ensure consistency with industry pricing before being approved. Table 5: Summary of Cost to Complete Winterization Measures in FY2024-25 Shaping, Grading & Fissure Filling Canyon Lining Storm Response Geology & Eng- ineering2 Const Mgmt. & Inspection3 Environ- mental Compliance4 Total Altamira Canyon & Tributaries $1,353,527 $365,784 $123,806 $146,949 $77,427 $145,433 $2,212,926 Kelvin Canyon & Tributaries $167,497 $166,462 - $26,626 $14,029 $26,351 $400,967 Seaview Neighborhood1 $680,1771 - - $54,229 $28,573 $53,670 $816,650 Klondike Canyon $865,122 $271,065 $26,153 $92,703 $48,845 $91,747 $1,395,636 Total $3,066,324 $803,312 $149,959 $320,508 $168,875 $317,201 $4,826,178 1. Includes Exultant Dr, Admirable Dr, Dauntless Dr, and Palos Verdes Drive South Frontage Street 2. Includes design, geotechnical, and peer-review. 3. Includes cost validation for construction contractor bids, budget and schedule management, and construction inspection. 4. Includes emergency permits, environmental impact monitoring, and record keeping. 29 Summary Table 6 below summarizes the cost of implementing each main component of emergency landslide stabilization measures. Table 6: FY 2024-25 Emergency Landslide Stabilization Cost Summary DDW Installation $13,024,660 DDW Operations & Maintenance $3,359,933 Winterization $4,826,178 Total $21,210,770 Ranked Order Priority List of Landslide Emergency Response Activity Costs As part of the FY 2025-26 budget process, the City Council directed staff to present a priority list of landslide emergency response projects/activities totaling $9 million so that the City Council may consider future budget reductions based on the priority order rank list. To prepare a line-item version of estimated costs; Staff analyzed the actual operations and maintenance cost of each DDW, or group of DDWs where there are shared components, from the time of installation to the end of Fiscal Year 2024-25 as summarized in the previous section. The trends for fuel consumption, re-drilling rates, and other maintenance activities were applied to a full fiscal year. The resulting estimated annual operations and maintenance costs are presented in Table 7. The same methodology was applied to emergency winterization activities, which is presented in Table 8. Although the total cost of DDW operations in FY 2024-25 are comparable to the estimated costs in FY 2025-26, they are not identical for the following primary reasons: • Since the buildout of the DDW program was not completed until approximately the mid-point of FY 2024-25, the respective runtimes for each DDW and associated operations and maintenance costs, including re-drills did not span the full fiscal year cycle as compared with the estimated costs for FY 2025-26, which project the DDW program to be fully operating for the entire duration of the fiscal year; with the exception of DDW-11 which has been decommissioned and therefore not included in the estimated operations and maintenance cost for FY 2025-26. • As of July 1, 2025, the City is directly contracting with companies for the various operations and maintenance services without the use of a general contractor to coordinate or perform these services, resulting in greater efficiency in performing the work with and relatively lower costs. Similar comparisons for the total cost of the winterization program in FY 2024 -25 and estimated costs for FY 2025-26 can be made. The primary reasons for their differences in cost are as follows: • Winterized areas such as Klondike Canyon and the Seaview Neighborhood are largely in-tact, resulting in less work and relative cost to keep these areas winterized in FY 2025-26. 30 • The areas anticipated for winterization work in FY 2025 -26 are within existing winterized footprints, which reduces the scope of related professional services to ensure environmental and regulatory compliance. • The above reductions in anticipated work and relative estimated costs are partially offset by the scope of work anticipated to safely access and repair areas within Altamira Canyon, Kelvin Canyon, and connecting tributaries that were winterized in FY 2024-25 but have since been damaged by land movement. The GPS surveying associated with the emergency stabilization efforts are not directly attributable to a specific element; therefore, that cost is presented separately. Finally, due to the uncertainty associated with rapidly changing landslide conditions, a minor contingency is also included. Those costs were added to the DDW and winterization totals and presented in Table 9. Table 7: Estimated Cost of DDW Operations & Maintenance in FY 2025-26 DDW # Generator & Fuel Monitoring & Maintenance2 Re-drilling Geology and Engineering Construction Management & Inspection3 Environmental Compliance4 Totals DDW1 $341,0001 $34,000 $114,000 $25,000 $8,000 $10,000 $1,841,000 DDW2 $34,000 $115,000 $26,000 $8,000 $10,000 DDW3 $34,000 $117,000 $26,000 $8,000 $10,000 DDW4 $34,000 $117,000 $26,000 $8,000 $10,000 DDW5 $34,000 $238,000 $53,000 $16,000 $21,000 DDW6 $34,000 $240,000 $53,000 $16,000 $21,000 DDW75 $67,000 $34,000 $181,000 $40,000 $12,000 $16,000 $350,000 DDW8 $67,000 $34,000 $127,000 $28,000 $8,000 $11,000 $275,000 DDW9A $67,000 $34,000 $399,000 $89,000 $26,000 $36,000 $651,000 DDW10 $67,000 $34,000 $133,000 $30,000 $9,000 $12,000 $285,000 Totals $609,000 $340,000 $1,781,000 $396,000 $119,000 $157,000 $3,402,000 1. Includes a standby generator for DDWs1-6. 2. Includes performance data monitoring & reporting; repair/replacement of pumps, piping, instruments & other equipment. 3. Includes cost validation for construction contractor bids, budget and schedule management, and construction inspection. 4. Includes emergency permits, environmental impact monitoring, and record keeping. 5. DDW-7 is currently sheared. Re-drill cost assumes installation of a relocated well in addition to re-drills. Table 8: Estimated Cost of Winterization in FY 2025-26 Area Construction1 Geology & Engineering Construction Management & Inspection2 Environmental Compliance4 Totals Altamira Canyon & Tributaries $1,800,000 $396,000 $155,000 $250,000 $2,601,000 Kelvin Canyon & Tributaries $50,000 $77,000 $32,000 $48,000 $507,000 Seaview Neighborhood $150,000 $35,000 $16,000 $20,000 $221,000 Klondike Canyon $50,000 $77,000 $33,000 $48,000 $508,000 Fissure Filling3 $200,000 $44,000 $20,000 $27,000 $291,000 Totals $2,850,000 $629,000 $256,000 $393,000 $4,128,000 1. Includes grading, shaping, fissure filling, canyon liner modifications and storm response. 2. Includes cost validation for construction contractor bids, budget and schedule management, and construction inspection. 3. Locations to be determined according to project geologist priority recommendations. 4. Includes emergency permits, environmental impact monitoring, and record keeping. 31 Table 9: Total Estimated Cost of Emergency Stabilization FY 2025-26 DDW Operations & Maintenance $3,402,000 Winterization $4,128,000 Surveying $320,000 Contingency $200,000 Total FY2025-26 $8,050,000 To prepare a priority order ranked list of the emergency response items, Staff asked the project geologist, GLA; as well as the City’s contracted peer review geologist, CSA, for their technical recommendations. Below is the technical reasoning provided by the geologists for determining which elements of the program are most important, given constrained resources. The geologists have stated that DDW program is more important than the winterization program because it directly affects known areas of high groundwater pressure, at various depths, which is the primary cause of landslide movement. Within the DDW program, following are the geologists’ recommended ranking priorities (highest to lowest): 1. DDW-1, DDW-2, and DDW-3 because they represent part of a cluster that has had the most impact on the Landslide Complex in terms of reducing land movement in the KCL to below instrument error and in the PBL to one to two inches per week locally. These three DDWs together would still provide notable benefit, although not to the same extent as the entire set of DDWs in the area. 2. DDW-9A and DDW-10 because although they have shown less impact on the Landslide Complex than the DDWs closer to the KCL, they still provide a breadth of benefit, i.e. in the other areas of the Landslide Complex, that would not otherwise exist. 3. DDW-5 because without it, there would still be a cluster of three DDWs nearby , which is not as effective as four or more DDWs, but would still provide some benefit. 4. DDW-8 because it is isolated and less impactful than a group of wells. 5. DDW-7 because it is isolated and less impactful than a group of wells. 6. DDW-4 because without it, there would still be a cluster of four DDWs in the general area, which is not as effective as five or more DDWs, but would still provide some benefit. 7. DDW-6 because without it, there would still be five other DDWs in the general area and those five DDWs would provide a substantial benefit, although not to the same extent as is currently the case with six DDWs. Within the winterization program, following are the geologists’ recommended ranking priorities (highest to lowest): 32 1. Altamira Canyon because it has the newest fissures where runoff infiltration can occur as compared to other areas where the FY 2024 -25 winterization program will still provide a benefit. 2. Kelvin Canyon; for the same reason as Altamira Canyon; however, Kelvin Canyon is a lower priority than Altamira Canyon because Altamira Canyon carries more flow. 3. Klondike Canyon because most of the FY 2024 -25 winterization work remains intact. However, based on lessons learned from the FY 2024 -25 winterization program, there remain erosion control needs as well as vulnerabilities in the Klondike Canyon liner that should be better secured. 4. Fissure filling on City land throughout the Landslide Complex because there are new fissures since the FY 2024-25 winterization program. 5. Seaview neighborhood because most of the FY 2024 -25 winterization work remains intact. The total estimated cost of the DDW and winterization programs for FY2025-26 is less than $9 million; therefore, additional landslide projects are added to the priority order rank list. Below is the reasoning for determining the priority order of the additional projects (highest to lowest): 1. Palos Verdes Drive South Landslide Repair Program (CIP 8302) because this important arterial roadway provides access for emergency services to several neighborhoods, is the evacuation route for the south side of the City, is a main thoroughfare for commercial centers in the City, and carries traffic (approximately 15,000 daily trips) that would otherwise create congestion on Palos Verdes Drive East, Palos Verdes Drive North, Hawthorne Boulevard, and Western Avenue. 2. Abalone Cove Sanitary Sewer Repair Program (CIP 8202) because an operational sanitary sewer system is necessary to avoid red-tagging of additional homes. 3. GPS Surveying because without a robust data collection program, the behavior of the Landslide Complex and any mitigation measures could not be properly scientifically analyzed. 4. PBL Hydrology & Hydraulics Study (CIP 8309) because this study is essential to a complete understanding of the Landslide Complex, which leads to the most efficient and effective solution. 5. PBL DDW1-6 Permanent Power (CIP 8308) because providing permanent power to DDWs significantly reduces their operational costs. Additionally, 75% of the cost of this project is funded by a federal grant. 6. PBL Remediation (CIP 8304) because although the design phase of this project currently has approved federal funding, there remains a significant gap in the total construction funding needed. Based on the technical recommendations of the geologists, and other considerations, below in Table 10 is the overall priority order list of the landslide activities and associated costs (highest to lowest). 33 Table 10: Total Estimated Cost of Landslide Activities in Priority Order for FY 2025-26 Landslide Activity Item Cost PVDS Landslide Repair $2,500,000 Ab Cove Sanitary Sewer Repair $ 3,000,000 GPS Surveying $320,000 PBL Hydrology & Hydraulics Study $1,400,000 DDW-1, DDW-2, & DDW-3 $912,000 DDW1-6 Permanent Power* (City’s Federal Match) $525,000 DDW-9A & DDW-10 $936,000 DDW-5 $365,000 DDW-8 $275,000 DDW-7 $350,000 DDW-4 $197,000 DDW-6 $367,000 Altamira Canyon $2,601,000 Kelvin Canyon $507,000 Klondike Canyon $508,000 Fissure Filling $291,000 Seaview Neighborhood $221,000 PBL Remediation $700,000 Contingency $200,000 Total Cost – FY2025-26* $16,175,000 *The total cost for DDW1-6 is $2.1 million with $525,000 as the City’s Federal match and $1,575,000 as the grant amount. The total budget, including the Federal Grant, for landslide activities is $17,750,000. The City Council is being asked to review the above ranked priority order list of costs associated with the FY 2025-26 DDW and winterization programs. Financial Update Expenditures to Date and FY 2024-25 Draft Year-End Overall, the City’s estimated expenditures for the Portuguese Bend Landslide from October 2022 through June 2025 are approximately $48 million including continuing appropriations and Purchase Order (PO) carryover from FY 2023-24 approved on January 21, 2025. As shown in Table 11 on the following page, year-to-date expenditures and encumbrances have increased from $33.1 million, as reported on July 1, 2025, to $36.8 million. This figure is preliminary and subject to change, pending the Finance Department’s completion of the year-end closing process over the next few months, which will incorporate services provided by June 30, 2025. Overall, compared to FY 2023-24, the projected $36.8 million for FY 2024-25 represents a 294% increase. These costs include emergency response and stabilization efforts such as test boreholes, deep dewatering wells, maintenance of the deep dewatering wells, winterization, fissure filling, road repairs, sewer repairs, estimated time and costs for personnel dedicated to the project, legal services, loans to ACLAD and KCLAD, in-kind support to ACLAD, and increased tax assessments borne by the City. 34 Table 11: PB Landslide Estimated Costs – Stabilization Measures/Emergency Response/Other – October 2022-June 2025 *This figure is preliminary and subject to change, pending the Finance Department’s completion of the year-end closing process over the next few months, which will incorporate all services provided by June 30, 2025. FY 2025-26 Adopted Budget On June 17, 2025, the City Council adopted the FY 2025-26 Budget which includes $17,750,000 of Portuguese Bend Landslide projects, as summarized in the Fiscal Impact page (page 2 of the report). Of this amount, almost $13.7 million is funded by the CIP Fund and $4 million from Special Revenue (Restricted) Funds. Additionally, the FY 2025- 26 budget includes $860,000 for property tax assessment fees paid to KCLAD and ACLAD, funded by the General Fund. Since the fiscal year just began, as of July 31, 2025, the total expenditures are $22,145, with additional $2,151,855 encumbered, representing 16% of the total budget (Tables 11 and 12). As shown in Table 13, the City has also paid $860,300 in tax assessments, representing 100% spent of the total budget in assessments, as these payments were due in July. [Continued on Next Page] FY 22-23 FY 23-24 FY 24-25 Oct. 22- June 25 DESCRIPTION ACTUAL ACTUAL DRAFT June 30* Projected TOTAL Stabilization Measures in millions DDW Program 1.4 16.4 17.8 Winterization 4.8 4.8 Emergency Response Other (Supplies, Equipment, Prof Tech, De-energization) 1.2 2.2 3.3 Fissure Filling 0.6 0.4 1.0 Road Repairs (CIP, Prop C, Gas Tax)1.0 2.8 2.7 6.5 Ab Cove Sewer Repairs 0.0 0.8 4.7 5.6 Personnel Costs 0.1 1.2 1.0 2.3 Legal Services 0.0 0.1 0.1 0.3 PBL Remediation 0.5 1.1 0.2 1.7 ACLAD/KCLAD Loans 3.6 3.6 Tax Assessments 0.2 0.2 0.7 1.1 TOTAL: October 2022 - June 2025 1.9 9.3 36.8 48.0 35 Table 11: PB Landslide - FY 2025-26 Adopted Budget and YTD – CIP Fund Program Funding Source: Capital Infrastructure Program (CIP) Fund 330 FY 2025-26 Adopted Budget Expenditures ($) Encumbered ($) YTD Spent & Encumbered (%) Balance 07-31-25 8202 Abalone Cove Sanitary Sewer Repair Program 3,000,000 0 0 0% 3,000,000 8304 Portuguese Bend Landslide Remediation 700,000 0 0 0% 700,000 8307 Portuguese Bend Landslide Remediation - Emergency Stabilization Measures $8,050,000 Construction 5,750,000 22,145 1,076,855 19% 4,651,000 Soft Costs (Engineering, Environmental, Inspection, Management 1,725,000 0 1,075,000 62% 650,000 Contingency 575,000 0 0 0% 575,000 8308 Portuguese Bend Landslide Remediation - Deep Dewatering Wells 1 thru 6 Permanent Power (City's Federal Match) 525,000 0 0 0% 525,000 8309 Portuguese Bend Landslide Hydrology & Hydraulics Study 1,400,000 0 0 0% 1,400,000 TOTAL - FY 2025-26 (CIP FUND) $13,675,000 $22,145 $2,151,855 16% $11,501,000 Table 12: PB Landslide - FY 2025-26 Adopted Budget and YTD – Special Revenue Funds Funding Sources: Special Revenue (Restricted) Funds FY 2025-26 Adopted Budget Expenditures ($) Encumbered ($) YTD Spent & Encumbered (%) Balance 07-31-25 8302 Palos Verdes Drive South Landslide Repair Program $2,500,000 Gas Tax (Fund 202) 750,000 0 0 0% 750,000 Prop C (Fund 215) 1,150,000 0 0 0% 1,150,000 Measure R (Fund 220) 600,000 0 0 0% 600,000 8308 Portuguese Bend Landslide Remediation - Deep Dewatering Wells 1 thru 6 Permanent Power Federal Grant (Fund 331) 1,575,000 0 0 0% 1,575,000 TOTAL - FY 2025-26 SPECIAL REVENUE FUNDS $4,075,000 $0 $0 0% $4,075,000 Table 13: PB Landslide - FY 2025-26 Adopted Budget – General Fund Funding Sources: General Fund FY 2025-26 Adopted Budget Expenditures ($) Encumbered ($) YTD Spent & Encumbered (%) Balance 3150 Property Tax Assessments KCLAD 475,902 475,902 0 100% $0 ACLAD 384,398 384,398 0 100% $0 TOTAL - FY 2025-26 $860,300 $860,300 $0 100% $0 36 ACLAD/KCLAD Loans $3,527,500 On August 20, 2024, the City received signed loan agreements from ACLAD and KCLAD in the amounts of $1.6 million and $1.9 million, respectively. As of April 3, 2025, both loans have been fully disbursed, totaling $3.52 million, in accordance with the loan agreements. The loans have a 12-year term with a 2.5% interest rate, and the first estimated payment is scheduled for December 2026. Per the agreements, the funds will be used to stabilize land movement, including the installation of dewatering and monitoring wells, system improvements, surface drainage enhancements, grading, and infilling of fractures. Tables 14a and 14b below are a summary of expenditures that were used for the loan ending July 2025. Financial information was provided by the districts. For ACLAD, as of July 31, 2025, $1,447,895 or 90% have been spent (Table 14a). Majority of the loan amount (99%) was used for maintenance and operations. Of the 99% in maintenance and operations, 60% was used for well drilling and 38% was general operations such as generators, supplies, and well repairs. In accordance with the loan agreement, no expenditures were made on legal services. Legal service expenses incurred by the District were paid from their annual operating budget. Table 14a: ACLAD – Summary of Expenditures for the City Loan of $1,610,000 As of July 31, 2025, KCLAD spent $709,543 or 37% of the loan (Table 14b). Majority of the loan amount (95%) was used for maintenance and operations, and 5% used for contract services for consulting and geology. Of the 95% of maintenance and operations, approximately 74% was for pipeline maintenance. In accordance with the loan agreement, no expenditures were made on legal services. Legal service expenses incurred by the District were paid from their annual operating budget. ACLAD City Loan $1,610,000 Total by Category July 31, 2025 Category Deposits Payments Spent by Category (%) City Loan 1,610,000 Bank Fees 161 0% Maintenance & Operations 555,435 38% Maintenance & Operations: Repair & Maintenance 17,529 1% Maintenance & Operations: Utilities, Propane, SCE, Diesel 574 0% Maintenance & Operations: Well Drilling 874,196 60% Grand Total $1,610,000 $1,447,895 Total Spent 90% Loan Balance $162,105 37 Table 14b: KCLAD – Summary of Expenditures for the City Loan of $1,917,500 BRIC and HMGP Grant Update On April 15, 2025, CalOES notified the City that California along with other states received notification through a FEMA Advisory, that FEMA is discontinuing the Building, Resiliency, Infrastructure, and Community (BRIC) program; through which the City had been selected for $23.3 million in grant funds (with a required $10 million non-federal match) for the PBL Remediation Project, later revised to $16.4 million (with a required $7 million non -federal match) due to overlapping emergency stabilization work. The notification further stated that FEMA Regions will work with applicants to end their BRIC projects after the completion of Phase 1, for which the City has already been awarded approximately $2.3 million (with a required non -federal match of approximately $700,000) or at another appropriate stopping point. Staff have been verbally informed by FEMA that the Phase 1 grant award will not be withdrawn, and Staff are seeking written confirmation. In consideration of the FEMA Advisory, the City submitted a Notice of Intent (NOI) to apply for FEMA’s Hazard Mitigation Grant Program (HMGP) for the PBL Remediation Project to cover a similar scope as the BRIC grant project, expanded based on current conditions. The City was notified by CalOES that the NOI was reviewed by CalOES and determined to represent an eligible HMGP activity; therefore, the City may now move forward with submitting a grant application by September 15, 2025 for funding consideration. The grant requires non-federal matching funds of 25%. The cost estimate of the revised scope of the PBL Remediation Project, expanded based on current conditions, is $40 million; which means that the required non-federal match is $10 million. Based on the City’s fund balance status, the only currently available source of matching funds is from the unallocated fund balance in the General Fund. According to projections presented at the FY 2025-26 budget workshop, the General Fund is expected to end the year with a KCLAD City Loan $1,917,500 Total by Category July 31, 2025 Category Deposits Payments Spent Category (%) City Loan 1,917,500 Administration:Admin consulting 18,961 3% Administration:Board Expenses 132 0% Administration:Geology Consulting 17,247 2% Bank Charges & Fees 159 0% Maintenance & Operations 34,544 5% Maintenance & Operations:Extraordinary Repair 18,400 3% Maintenance & Operations:Utilities SCE, Cal Water, generator 37,560 5% Maintenance & Operations:Well Drilling Expense 57,949 8% Maintenance & Operations:Well Maint - Pipeline Maint 524,590 74% Grand Total $1,917,500 $709,543 Total Spent (%)37% Loan Balance 1,207,957$ 38 $27.3 million balance, of which $17 million is held in reserves and $10.3 million unallocated. For cash flow purposes, staff anticipates that the $10.3 million will be needed to support the FEMA Voluntary Property Acquisition Buyout Program, with reimbursement expected within the same fiscal year. Therefore, should the City Council elect to allocate the $10 million match from the General Fund for the PBL Remediation Project, the timing is anticipated to be reasonable, as the project is expected to be a multi -year project. Staff seek City Council approval to submit the grant application with a commitment for a $10 million match from the unallocated fund balance in the General Fund. Should the City Council approve submittal of the grant application, Staff will return to request that the City Council accordingly adopt a resolution to that effect. Design Services for the PBL Remediation Project (CIP 8304) The original PBL Remediation Project design was nearing completion in early 2024. However, known site conditions of the PBL have changed dramatically since that time to an extent resulting in the city implementing emergency landslide stabilization measures through the installation of several DDWs and winterizing areas within the Landslide Complex as part of a separate project (CIP 8307). As such, modifications to the scope and final design of CIP 8304 (as part of Phase 1 described in the Fiscal Impact and Grant Update sections above) are necessary to be reflective of the existing conditions of the PBL and the relative stabilization measures currently in place across the Landslide Complex. A concept plan for the project has been developed and is generally based on the conceptual comprehensive build-out presented to City Council on January 21, 2025 , but limited to the PBL boundary. In response, staff solicited a proposal from GLA to prepare final plans, specifications, construction documents and associated permits and environmental documents reflective of the current site conditions (Attachment H). On July 3, 2025, Cal OES formally approved the City’s request for a noncompetitive procurement of a contractor (GLA) for professional services, including geology, engineering, environmental studies, grant administration and similar services to complete the Phase 1 scope of work. The approval is justified by the emergency conditions within the Landslide Complex requiring immediate actions to stabilize land movement and infrastructure that cannot be delayed by a competitive procurement process. Staff evaluated GLAs proposal (Attachment G) and negotiated a scope, schedule and fee as part of the proposed professional services agreement (PSA) (Attachment F). Accordingly, Staff recommend that the City Council approve a PSA with GLA to complete the final engineering and design of the project. A summary of the scope of services is as follows: Scope of Services: • Prepare all studies, investigations, analyses, and reports necessary to inform the preparation of construction documents specifying improvements to mitigate the PBL to a negligible rate of movement and provide long-term protection from 39 recurring landslide activity including from future intense and prolonged rainfall events by addressing the root cause of the landslide. • Prepare construction drawings/plans, specifications, and any other documents necessary for a construction contractor to construct the proposed improvements. • Develop comprehensive cost estimate of the proposed improvements • Develop a detailed project delivery schedule for the proposed improvements • Prepare all documents necessary for third-party completion of Environmental and Historic Preservation requirements pursuant to the National Environmental Policy Act (NEPA) and federal funding • Utility and agency coordination as needed for the proposed improvements. • Prepare documents for any property acquisitions and easements necessary to construct the proposed improvements • Prepare all necessary documents to obtain permits to construct the proposed improvements • Prepare all documents necessary to procure a construction contractor to construct the proposed improvements in compliance with federal funding requirements. Schedule: The scope of services outlined above are scheduled to be completed within approximately six months of the City Council’s approval of the PSA. Cost: The total fee for the scope of services described above is $460,685 with a contingency of 15% or $69,103, for adjustments to the scope based on information learned during the initial field reconnaissance and study phase. The approved FY 2025-26 CIP includes funding for the scope of services in the amount of $700,000 from the CIP Fund (Attachment I). The Grant Funding section above provides information regarding how the CIP funds allocated for GLA’s proposed scope of services are associated with staff’s ongoing pursuit for securing grant funding. If deemed acceptable, the City Council is being asked to award a PSA to GLA for final engineering design, environmental documents, and related services for the PBL Remediation Project (Capital Improvement Project (CIP) 8304) in the amount of $460,685 with a contingency of 15% or $69,103 Bicycle, Motorcycle, Unicycle and Other Similar Wheeled Vehicle Prohibition Since the City Council’s declaration of a local emergency, the City Geologist has been regularly reviewing survey data and conducting field observations of PVDS in the Landslide Complex. While the City’s Geologist reports the rate of land movement has slowed, there remain areas of PVDS where land movement is two to three inches per week. Overall, pavement conditions on PVDS remain very poor, with cracks, bumps, fissures, and other irregularities. Deformations in the pavement can occur overnight. On July 26, 2025; a sinkhole formed overnight in the southbound lane of PVDS near the area commonly known as the “ski jump” between Narcissa Drive and Peppertree Drive. 40 Repair of the sinkhole required a full closure of PVDS for several hours, and a partial closure for several more hours. Although four-wheeled vehicles (i.e. cars) can, with due care, navigate the road when it is open, the impact on one- and two-wheeled vehicles remains pronounced. Despite the added signs prohibiting bicyclists, motorcyclists, unicycles and other similar wheeled devices from traversing the landslide, there remain those who ignore the prohibition at their peril. Were the City Council to end the current prohibition, the Office of the City Attorney remains of the considered legal opinion that permitting one- or two-wheeled vehicle traffic across the landslide will pose a liability risk to the City and that the same is not presently safe for these vehicles to travel on PVDS, even using due care, across the landslide for the reasons noted above. Since the Emergency Declaration on October 3, 2023, there have been three claims filed prior to the Bicycle, Motorcycle, Unicycle and Other Similar Wheeled Vehicle Prohibition. The declaration of emergency, together with the repeated warnings about roadway conditions, has resulted in the City successfully defending claims in court for damage to vehicles where drivers have ignored the declaration and City warnings. Based on these recent claims and roadway conditions, Staff and the City Attorney recommend extending the existing resolution prohibiting one - or two-wheeled vehicles on PVDS for an additional 60 days (Attachment A). With respect to vehicle damage claims, the declaration of emergency, together with the repeated warnings about roadway conditions, has resulted in the City successfully defending claims in court for damage to vehicles where drivers have ignored the declaration and City warnings. Extension of the Local Emergency Declaration On October 3, 2023, the City Council adopted Resolution No. 2023-47 declaring a local emergency. The emergency declaration is deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Government Code § 8630 requires the City Council to review the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within the geographic boundaries of the Landslide Complex has been abated or mitigated to insignificance. The City Council has extended the local emergency on multiple occasions within the 60 - day window and it remains in effect until August 30, 2025, unless extended again this evening. At this time, the City Council is being asked to extend the local emergency declaration an additional 60 days through October 18, 2025, which does not require a public hearing. If extended this evening, the Council would consider renewing the local emergency declaration again during the next landslide update on October 7, 2025. The City Council is being asked to adopt the attached resolution thereby extending the Declaration of Local Emergency by 60 days (Attachment B). 41 Extension of the Local Emergency Declaration for Utility Shutoffs On August 6, 2024, the City Council adopted Resolution No. 2024 -52 declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off natural gas service to approximately 135 homes in the PBCA due to safety concerns. On September 3, 2024, the City Council adopted Resolution No. 2024-57, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned de-energization events, and internet shut-offs in the PBCA, Seaview, and PBBC neighborhoods. The emergency declaration is deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Government Code § 8630 requires the City Council to review the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency because of a severe energy shortage has been abated or mitigated to insignificance. The City Council has extended the local emergency declaration for utility shutoffs on multiple occasions within the 60 day window and it remains in effect until August 30, 2025, unless extended again this evening. At this time, the City Council is being asked to extend the local emergency declaration an additional 60 days through October 18, 2025, which does not require a public hearing. If extended this evening, the Council would consider renewing the local emergency declaration again during the next landslide update on October 7, 2025. The City Council is being asked to adopt the attached resolution thereby extending the Declaration of Local Emergency due to a severe and sudden energy shortage by 60 days (Attachment C). ADDITIONAL INFORMATION: Continuing the Emergency Work and Emergency Contract As a separate item on tonight’s agenda, the City Council is being provided with an update on the Portuguese Bend Landslide Emergency construction contracting and being asked to reconfirm the need to continue the emergency work. This is a recurring agenda matter and requires a 4/5th vote. Study to Create a Toll Road on PVDS On January 21, 2025, the City Council directed staff to pursue alternative or additional funding sources for landslide remediation and management efforts. Subsequently, the City Council directed Staff to analyze the possibility of converting PVDS to a toll road, including potential revenue and cost, feasibility, as well as potential unintended consequences such as diverted traffic. In accordance with the City Council’s direction, Staff reached out several firms that work with other municipalities and state departments of transportation on tolling operations and requested proposals for a high-level feasibility study of tolling PVDS. Two firms have provided proposals. Staff reviewed the proposals and will present a proposed professional services agreement for a toll road study for the City Council’s consideration at the September 2, 2025 City Council meeting. Additionally, Staff will provide other relevant information for the City Council’s consideration such as legal requirements and Coastal Commission jurisdiction. 42 Wayfarers Chapel Slope at PVDS Material from the Wayfarers’ Chapel slope adjacent to PVDS was sloughing off into the shoulder and second travel lane of PVDS. The shoulder and second travel lane were closed and a concrete barrier was installed to protect the remaining travel lane from falling debris. In recent weeks, the City Geologist expressed concern that the risk for more significant sloughing, which could impact the last remaining travel lane, has increased. Therefore, Staff requested that Wayfarers Chapel re-shape its slope, in coordination with the City Geologist, to minimize the risk of debris going into the last remaining travel lane of PVDS. Around July 21, 2025, a Wayfarers Chapel contractor began re-shaping the slope, with monitoring by CSA. The work continues and is expected to conclude in approximately 2-3 weeks. Permanent Power to DDWs 1-6 The approved FY 2025-26 CIP includes a project for the engineering, design, and construction for connecting DDWs 1 through 6 to a permanent power source, effectively eliminating the use of diesel generators to power these DDWs. The approved budget anticipates funding 75% of the project with a grant being sought through CalOES and FEMA with 25% city-matched funding. Proposals are currently being solicited for the engineering and design phase of the project. This phase is anticipated to be completed by December 2025. Construction is anticipated to commence shortly thereafter and be completed by September 2026. Abatement of 4361 Exultant Drive Structure The City’s Community Development Department is abating red-tagged structures, as a public nuisance, on property located at 4361 Exultant Drive. The abatement involves the demolition of unsafe structures, overgrown vegetation, and other materials or debris on the property. The demolition of the structures will be conducted in compliance with the Southern California Air Quality Management District (AQMD) regulations including a Procedure 5 (P5) asbestos plan. The P5 asbestos plan includes detailed procedures to safely manage disturbed asbestos-containing materials to ensure regulatory compliance and to protect public health and the environment. This includes the use of water to mitigate dust, in compliance with the PF asbestos plan. The AQMD review of the P5 asbestos plan has caused some delay in the initiation of demolition activities, but permits are scheduled to be issued as of writing this report. Demolition activities are anticipated to begin the week of August 18 and completed as quickly as 2-3 working days, with the structure being removed in sections with the use of equipment including, but not limited to, an excavator. Once structures are demolished, general grading will be completed and fissures on the property will be filled. There will not be public access to the site once the abatement is completed, as the site will remain privately owned. 43 Area residents and the resident association have been briefed on the upcoming abatement including measures to minimize impacts to the surrounding neighborhood. Staff will continue communicating with the area residents and resident association leading up to the scheduled abatement and during the abatement process. Permanent Building Regulations for Greater Portuguese Bend Landslide Complex On October 3, 2023, the City Council adopted Interim Urgency Ordinance No. 674U pursuant to Government Code §§ 36937 and 65858 prohibiting new construction within the Greater Portuguese Bend Landslide Complex, with the exception of actions necessary to prevent or mitigate loss of, or damage to, life, health, property, or essential public services. This moratorium was extended for an additional 10 months and 15 days on November 14, 2023 with the City Council adoption of Interim Urgency Ordinance No. 675U, and again on September 3, 2024 by Interim Urgency Ordinance 686U, for a total of two years. This moratorium has been extended to the maximum two -year life and is set to expire on October 2, 2025. At the August 5, 2025 meeting, City Council considered what actions to take to permanently respond to the conditions that gave rise to the landslide moratorium in the first instance. At that meeting, City Council introduced Ordinance No. 692 to repeal the prior regulations of Chapter 15.20 and replace with proposed code amendments to Chapter 15.20 of the RPVMC to address the impacts of the substantial change in circumstances of the land movement, the unpredictability of future weather conditions that may exacerbate movement, and the threat to loss or damage to life, health, property, or essential public services. Such amendments include, among other items, prohibiting new construction of single-family residences or additions to existing single-family residences, as well as amending the Landslide Complex Map to correspond to the boundary limits of recent land movement. The second reading and adoption of these regulations is on tonight’s agenda, as a separate Consent Calendar item. If adopted, the new regulations will go into effect thirty days later (September 18, 2025). Under the regulations in the proposed ordinance, property owners in the landslide area would be permitted to replace, restore, and repair development within its existing footprint. Additionally, the boundaries of the landslide complex would be updated to co rrespond with the expanded limits of recent land movement. Disaster Cost Recovery Applications Update (FEMA and CalOES) As previously included in the prior reports, in response to the declared federal disaster for the winter storms that occurred between January 31 and February 9, 2024 , and the Governor’s state of emergency for the indefinite de -energization of power, the City tabulated the costs it incurred through September 12, 2024 for reimbursement consideration by FEMA and CalOES. Table 16 summarizes the City’s requests for cost recovery from CalOES and FEMA in the amount of $61.4 million. Of this amount, $39.4 million is public assistance (City) and $22 million of individual assistance (residents). 44 Table 16: Cost Recovery Applications AGENCY COST RECOVERY TYPE DISASTER EVENT REQUESTED AMOUNT In Millions FEMA Public Assistance (City) Winter Storm (Jan/Feb 24) 38.4 CalOES Public Assistance (City) Energy Shutoff 1.0 CalOES Individual Assistance Energy Shutoff 22.0 TOTAL $61.4 As reported in previous staff reports, according to FEMA and CalOES, natural disaster recovery funds will not be provided for landslide remediation efforts because it is considered “pre-existing.” Out of the $39.4 million application for public assistance (City), Staff is projecting only approximately $1.5 million in potential disaster recovery funds from the Winter Storm and Energy Shutoff. If deemed eligible, the reimbursement process could take anywhere from one to three years before the City receives the funds. In July 2025, FEMA informed staff that the reimbursement request for protective measures and debris removal, totaling approximately $596,000, has been approved and forwarded to CalOES to initiate the funding process. Staff continue to coordinate with both FEMA and CalOES to facilitate the reimbursement. A continuous update on the reimbursement will be provided once the funding has been officially awarded to the City. For the remaining recovery applications, as previously reported, on January 17, 2025, of the $38.4 million applied for public assistance related to the winter storm, summarized and shown in Table 17, the City received seven denial letters from FEMA, followed by an additional denial letter on February 25, 2025 for a total of $37.9 million. Pursuant to the Stafford Act and Code of Federal Regulations, the City has 60 days from the Notice of Eligibility Determination to file an appeal. On March 17, 2025, the City filed appeals of the first seven denial letters, and on April 25, 2025, the City filed a remaining appeal letter. The appeal will be heard by FEMA’s District 9 Administrator, Robert Fenton, and his decision is then appealable to FEMA’s Headquarters in Washinton D.C. To date, the City has not received any response from the appeal letters filed aside from a confirmation of receipt. It should be noted that both ACLAD and KCLAD filed appeals as well for the denials they received for disaster recovery assistance. Both ACLAD and KCLAD have received notification from CalOES that they will not be recommending overturning the denial to Mr. Fenton. For the $22 million individual assistance (IA) application that the City submitted on behalf of the residents, the City has been notified that these funds will not become available. 45 Table 17: Cost Recovery FEMA Applications (Denied $37.9 million) AGENCY COST RECOVERY TYPE CATEGORY DESCRIP- TION REQUESTED AMOUNT DENIAL REASON FEMA Public Assistance (City) #754845 Category D - Water Control Facilities Lanslide - Drainage 200,000 (1) Damage not directly caused by the severe winter storms; (2) Facilities were unstable based on pre-disaster evidence. FEMA Public Assistance (City) #754846 Category F - Utilities Landslide Utilities 3,000,000 (1) Damage not directly caused by the severe winter storms; (2) Facilities were unstable based on pre-disaster evidence. FEMA Public Assistance (City) #753361 Category B - Emergency Protective Measures PVDS Temporary Civil Repairs 5,375,000 (1) Damage not directly caused by the severe winter storms; (2) Roads ineligible because another Federal Agency is legally responsible for the repairs and maintenance of the roads; (3) Emergency work claimed is due to an existing unstable landslide. FEMA Public Assistance (City) #753364 Category B - Emergency Protective Measures PB Landslide Stabilization and Monitoring 9,000,000 (1) Work claimed is not required as a result of the declared disaster; (2) Facility (slopes, canyons, hilldsides) is an ineligible unimproved natural feature; (3) Existing unstable landslide. FEMA Public Assistance (City) #754843 Category C - Utilities Landslide Roads 11,635,000 (1) Work claimed is not required as a result of the declared disaster; (2) Facility were unstable based on pre-disaster evidence. FEMA Public Assistance (City) #754842 Category G - Parks, Recreational Facilities, and Other Items Damages at Portuguese Bend Trails, Filiorum Reserves, 3,231,000 (1) Work claimed is not required as a result of the declared disaster; (2) Facility were unstable based on pre-disaster evidence. FEMA Public Assistance (City) #730185 Category G - Parks, Recreational Facilities, and Other Items Peppertree, Burma Road X Rim Trails 11,415 (1) Work claimed is not required as a result of the declared disaster; (2) Facility were unstable based on pre-disaster evidence. FEMA received 2/25/25 Public Assistance (City) #754844 Category C- Road and Bridges Palos Verde Drive South - Schooner and Seacove 5,425,000 (1) Work claimed has not been demonstrated that the repair is a result of the declared disaster; (2) Roads ineligible because another Federal Agency is legally responsible for the repairs and maintenance of the roads; TOTAL COST RECOVERY - DENIED $37,877,415 46 FEMA Voluntary Property Acquisition Buyout Program On October 28, 2024, the City, FEMA and Cal OES announced a $42 million Voluntary Property Acquisition Buyout Program (Buyout Program) for property owners in the Landslide Complex whose homes have been damaged or threatened by land movement. Established with funding from FEMA’s HMGP, which is a grant not disaster assistance, the Buyout Program is intended to help eligible homeowners relocate to safer areas by offering fair market value for their properties based on pre-disaster appraisals. Properties acquired by the City through this Buyout Program will be permanently converted to open space and deed-restricted, protecting the community from future redevelopment risks in these vulnerable areas. More information about the Buyout Program including, but not limited to, funding sources, minimum eligibility requirements, application evaluation methods and program participation requirements was previously made available as part of the February 4, 2025 City Council Staff Report related to updates and action items for the Landslide Complex. As well, information on the Buyout Program may be found on the City’s website. The City received 85 applications for the first round of program funding . After review for eligibility and determining estimated costs for the prioritized properties based on the program guidelines, the City has determined funding will be available for buyouts of 22 properties (13 red-tagged, and 9 yellow-tagged) in the first round of program funding. All remaining eligible applications will be considered for any future rounds of program funding. On December 19, 2024, the City issued Requests for Proposals (RFPs) for appraisal services, title companies, escrow professionals, and land surveyors related to the Buyout Program. Submitted proposals were evaluated and professional service agreements with selected firms were approved by the City Council on March 18, 2025. In February 2025, the City’s Community Development Department notified 23 program participants that their Buyout Program application was still active and being processed for further evaluation. The notification letter requested that program participants schedule a reinspection of their properties with the City’s Building & Safety Division and to submit FEMA required processing forms. City Staff received the requested information and completed the re-inspection of the 23 properties. With the award of professional service agreements for Buyout Program services and the completion of requested inspections and forms, City Staff connected program participants with property appraisers in order to further implement the Buyout Program. As well, City Staff authorized the preparation of the preliminary title reports for the 23 program properties. Appraisals were completed at the beginning of May 2025. On May 12, 2025 Property owners received a copy of the appraisal and were provided the opportunity to appeal it. As well, the City collected additional required forms and information for the program from the 23 program properties in order to complete the response to FEMA’s Request for Information (RFI) that was due on June 27, 2025. On June 2, 2025 one of the property owners withdrew from the program. After reviewing the appraisal information for the 47 remaining 22 program properties and updating the application budget as part of the RFI response, the first round funding would only be able to fund the acquisition of the remaining 22 program properties. City staff is working as quickly as possible to move through this lengthy and complex process, which involves multiple levels of close review by FEMA. Each property must be carefully vetted for compliance with program rules and regulations. In the coming weeks, the City plans to onboard a consultant dedicated to managing the buyout program. There is not a definitive timeline for when the first of the 22 properties may be purchased. The City is still in the “pre-award” phase of the grant process with FEMA. Once the City is formally awarded the grant, which could happen in at least several months from now, the $42 million will come in installments, likely on a quarterly basis, which is standard practice. The City will receive these payments as reimbursements only after the transactions are completed in batches. For cash flow purposes, the program does not provide advance payments. As such, staff anticipates that approximately $10 million will be needed during the initial phase of awards to support the program while awaiting reimbursements. The Voluntary Property Buyout Program is funded by FEMA’s Hazard Mitigation Grant Program (HMGP). This is different from FEMA’s Building Resilient Infrastructure and Communities (BRIC) program, which was recently ended by the federal government and may result in the City losing funding for a separate grant for the Portuguese Bend Landslide (PBL) Remediation project. At this time, City staff has not been notified of any changes to the status of the HMGP. The City has submitted a rolling application for additional HMGP funding in order to potentially offer more rounds of the buyout program. CONCLUSION: Over the past four months the average movement velocity for the portion of the Landslide Complex that is still moving accelerated slightly between February 3, 2025 and March 9, 2025, possibly in response to moderate rainfall that fell in this period. It the n decelerated slightly between March 9, 2025 and April 5, 2025, and has decelerated considerably between April 5, 2025 and June 3, 2025. Based upon a review of approximately weekly readings of 20 select GPS monitoring points located mostly in the lower po rtions of the Landslide Complex; with below-average rainfall conditions during the rainy season, in - place winterization measures, and the ongoing dewatering effort, it can be concluded that the: • KCL has stopped moving. • PBL was previously viewed as having reached a steady state of movement since the end of October 2024; however, it continues to decelerate. • ACL and upper Altamira Complex areas continue to decelerate. • Fastest moving area remains the upper portion of the ACL at an average of 1.15 feet per month (about 3.2 inches per week); however, the area of the ACL moving at this rate continues to shrink, most likely in response to recent deep dewatering 48 efforts by ACLAD. It is anticipated that this movement rate will continue to decelerate as additional wells come online and dewatering production increases. Using the City’s $1.6M loan,10 ACLAD DDWs are operational as of August 11, 2025, and two monitoring wells have been installed. Additional DDWs are being considered in the coming weeks, depending on available fund s. ACLAD estimates that the current dewatering rate among all wells is approximately 432 gallons per minute (114 and 318 gallons per minute for shallow and DDWs, respectively). At this juncture, it is too early to draw conclusions as to the efficacy of the ACLAD DDWs, particularly because some of them only recently became operational and others are in the process of coming online. Due to ongoing high rates of movement and associated impacts in certain parts of the Landslide Complex, Staff recommend that the City Council extend the temporary prohibition on one- and two-wheeled vehicles, extend the local emergency declaration, extend the de-energization emergency declaration for an additional 60 days, approve the submittal of a grant application to the FEMP HMGP for the PBL Remediation Project with a $10 million match from the unallocated fund balance in the General Fund, and award a PSA to GLA for final engineering design, environmental documents, and related services for the PBL Remediation Project. ALTERNATIVES: In addition to Staff recommendation, the following alternative actions are available for the City Council’s consideration: 1. Take no action, and receive and file this report. 2. Do not extend the temporary prohibition of one- or two-wheeled vehicles on PVDS and allow one- and two-wheeled to begin using PVDS again. 3. Do not adopt one, or both, of the resolutions continuing the local emergency declarations. 49 RESOLUTION NO. 2025-__ A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, EXTENDING FOR A TERM OF SIXTY (60) DAYS THE TEMPORARILY PROHIBITION ON TRAVEL BY UNICYCLES, BICYCLES, MOTORCYCLES, AND OTHER ONE- OR TWO-WHEELED VEHICLES ON PALOS VERDES DRIVE SOUTH WITHIN THE LANDSLIDE COMPLEX DUE TO CONTINUED ROADWAY CONDITIONS WHEREAS, the Greater Portuguese Bend Landslide Complex (the Landslide Complex) encompasses four historically active landslide areas in the City: the Portuguese Bend Landslide (PBL), the Abalone Cove Landslide (ACL), the Klondike Canyon Landslide (KCL), and the Beach Club Landslide (BCL). It also includes the Flying Triangle Landslide (FTL) in the City of Rolling Hills as mapped by various agencies (i.e., U.S. Geological Survey, California Geological Survey) and other researchers; and WHEREAS, following the 2022-23 rainy season, the Landslide Complex’s movement has accelerated exponentially. Therefore, on October 3, 2023, the City Council of the City of Rancho Palos Verdes adopted Resolution No. 2023-047 based on its authority pursuant to Section 8610 et seq. and Section 8630 et seq. of the Government Code, and Chapter 2.23 of the Rancho Palos Verdes Municipal Code, declaring a state of local emergency for the Landslide Complex based on the accelerated movement of the land. The declaration of emergency has been renewed as required by law and currently applies; and WHEREAS, following the City Council’s declaration of a local emergency, the City experienced another record-setting rainy season; and WHEREAS, since the City Council’s declaration of a local emergency, the City Geologist, Mike Phipps of Cotton, Shires, and Associates, Inc. (CSA), has been regularly conducting field mapping throughout the Landslide Complex; observing conditions at various locations, and reviewing survey and rainfall data; and WHEREAS, the City Geologist most recently reported to the City Council on May 7, 2024, in summary, that the Landslide Complex continues moving at unprecedented rates, predominantly in response to the two consecutive seasons of significantly above average rainfall; and WHEREAS, the City Geologist stated that land movement continued to manifest at the ground surface in the form of landslide scarps, fissures, grabens/sinkholes, tensional cracking, shear zones and thrust features; and that due to the continued acceleration, the ground movement features have continued to enlarge, expand, widen, or grow depending on the type of feature and location, A-1 Resolution No. 2025-__ Page 2 of 4 which also affects Palos Verdes Drive South (PVDS) as it traverses the Landslide Complex area; and WHEREAS, the City Geologist summarized that road conditions on PVDS continue to be adversely impacted due to differential rates of land movement ranging from about 5 to 8 inches per week, at the time of the report to the City Council on May 7, 2024; and WHEREAS, traffic signs on PVDS in the landslide area include various signs warning of the landslide conditions, with some specifically directed at bicyclists and motorcyclists. Out of an abundance of caution, Staff (through a consultant), conducted a review of signs on PVDS. As a result, additional signs were installed, including signs installed on June 1, 2024 specifically directed at bicyclists and motorcyclists; and WHEREAS, despite the existing bicycle warning signs, Staff has been anecdotally informed of bicycle crashes, and at least one claim has been filed against the City (which was prior to the additional bicycle and motorcycle signs installed on June 1) and at least two claims for injury to persons or property have been filed with the City; and WHEREAS, Section 8610 of the Government Code provides the local disaster council with broad powers to “develop plans for meeting any condition constituting a local emergency or state of emergency, including, but not limited to, earthquakes, natural or manmade disasters specific to that jurisdiction, or state of war emergency….”; and WHEREAS, Chapter 2.24 designates the City Council, the director of emergency services, the assistant director of emergency services, and the chiefs of emergency services as the City’s Disaster Council; and WHEREAS, the director of emergency services (the city manager), “[i]n the event of the proclamation of a local emergency […], the director [of emergency services] is empowered: a. To make and issue rules and regulations on matters reasonably related to the protection of life and property as affected by such emergency….”; and WHEREAS, the City Council finds that despite consistent and recently increased signage, riders of bicycles and motorcycles continue to use PVDS, and that the land movement is creating frequent localized deviations in the road, which can be navigated safely in cars and trucks, but that are more dangerous for two- wheeled vehicles such as bicycles and motorcycles; and WHEREAS, the City Council finds that the safety of bicycle, motorcycle and other two-wheeled riders is a compelling interest; and A-2 Resolution No. 2025-__ Page 3 of 4 WHEREAS, the City Council finds that in order to further the City’s compelling interest in the safety of riders, it is appropriate to temporarily route bicycles and motorcycles away from the portion of PVDS within the Landslide Complex, until such time as the City may be able to slow the land movement sufficiently to reduce the frequency and severity of road deviations to minimize the risk of injury to persons or property; and WHEREAS, on June 18, 2024, the City Council duly adopted Resolution No. 2024-39 prohibiting, for a period of six (6) months, bicycles, motorcycles, and other two-wheeled vehicles from traversing PVDS with the Landslide Complex; and WHEREAS, the City Council has, since that date and at various City Council meetings, duly adopted resolutions prohibiting for specified periods set forth therein, unicycles, bicycles, motorcycles, and other one- or two-wheeled vehicles from traversing PVDS with the Landslide Complex; and WHEREAS, staff and the Office of the City attorney are of the opinion that conditions on PVDS have not stabilized to the point that this prohibition should be allowed to terminate and is of the further opinion the existing prohibition should be extended for an additional sixty (60) day period. NOW, THEREFORE THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES DOES HEREBY FIND, DETERMINE AND RESOLVE AS FOLLOWS: Section 1: The above recitals are true and correct and incorporated herein by reference. Section 2: For a period of sixty (60) calendar days from and after the date of this resolution, the portion of PVDS within the Landslide Complex shall be closed to unicycle, bicycle, motorcycle, and other one- or two-wheeled vehicle traffic. Section 3: Updates on the rate of movement and repair of PVDS will be provided at City Council meetings where the City Council is considering extending the local state of emergency, including an assessment of the relative safety of traveling on PVDS by unicycles, bicycles, motorcycles, and other one- or two- wheeled vehicles through the Landslide Complex, with the purpose of lifting the prohibition as soon as possible. Section 4: This Resolution shall be effective immediately upon adoption by the City Council upon a majority vote. / / / / / / A-3 Resolution No. 2025-__ Page 4 of 4 PASSED, APPROVED, AND ADOPTED at a regular meeting of the City Council of the City of Rancho Palos Verdes, California, on this 19th day of August, 2025. David Bradley, Mayor ATTEST: Teresa Takaoka, City Clerk STATE OF CALIFORNIA ) COUNTY OF LOS ANGELES )ss CITY OF RANCHO PALOS VERDES ) I, Teresa Takaoka, City Clerk of the City of Rancho Palos Verdes, do hereby certify that the foregoing Resolution No. 2025-__, was duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on August 19, 2025 __________________________________ Teresa Takaoka, City Clerk A-4 01203.0023/1027433.1 RESOLUTION NO. 2025-__ A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, CALIFORNIA, CONTINUING THE LOCAL EMERGENCY DECLARATION AS ESTABLISHED BY RESOLUTION NO. 2023-47 ADOPTED ON OCTOBER 3, 2023 FOR AN ADDITIONAL 60 DAY PERIOD WHEREAS, on October 3, 2023, the City Council of the City of Rancho Palos Verdes adopted Resolution No. 2023-47, declaring a local state of emergency because of the alarming increase of land movement in the Greater Portuguese Bend Landslide Complex, as depicted in Resolution No. 2023-47 Exhibits “A” and “B”. Resolution No. 2023-47, and the exhibits thereto, is incorporated by reference; WHEREAS, on October 3, 2023, the City Council by a 4/5 vote also adopted Interim Urgency Ordinance No. 674U, establishing a moratorium on all construction in the Landslide Complex; WHEREAS, on November 14, 2023, the City Council by a 4/5 vote adopted Resolution No. 2023-56, extending the state of emergency for an additional 60 days; WHEREAS, on December 19, 2023, the City Council by a 4/5 vote adopted Resolution No. 2023-61, extending the state of emergency for an additional 60 days; WHEREAS, on February 6, 2024, the City Council by a 4/5 vote adopted Resolution No. 2024-05, extending the state of emergency for an additional 60 days; WHEREAS, on March 19, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-13, extending the state of emergency for an additional 60 days; WHEREAS, on May 7, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-20, extending the state of emergency for an additional 60 days; WHEREAS, on July 2, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-44, extending the state of emergency for an additional 60 days; WHEREAS, on August 6, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-51, extending the state of emergency by an additional 60 days; WHEREAS, on October 1, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-50, extending the state of emergency by an additional 60 days; WHEREAS, on November 19, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-70, extending the state of emergency by an additional 60 days; and WHEREAS, on December 17, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-77, extending the state of emergency by an additional 60 days; and B-1 Resolution No. 2025-__ Page 2 of 3 WHEREAS, on February 4, 2025, the City Council by a 5-0 vote adopted Resolution No. 2025-06, extending the state of emergency by an additional 60 days; and WHEREAS, on March 18, 2025, the City Council by a 5-0 vote adopted Resolution No. 2025-18, extending the state of emergency by an additional 60 days; and WHEREAS, on May 6, 2025, the City Council by a 5-0 vote adopted Resolution No. 2025-27, extending the state of emergency by an additional 60 days; and WHEREAS, on July 1, 2025, the City Council by a 5-0 vote adopted Resolution No. 2025-45, extending the state of emergency by an additional 60 days; and WHEREAS, the state of emergency is deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Government Code § 8630 requires the City Council to review of the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within the geographic boundaries of the Landslide Complex has been abated or mitigated to insignificance; and, WHEREAS, after consideration of all facts reasonably available the City Council now desires to extend the declaration of a state of local emergency within the Landslide Complex. NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, CALIFORNIA, HEREBY FINDS, DETERMINES, AND RESOLVES AS FOLLOWS: Section 1. Recitals. The City Council hereby determines that the above recitals are true and correct and incorporates the same as the findings of the City Council. Section 2. Proclamation of Emergency . The City Council finds, pursuant to RPVMC Chapter 2.24 and Government Code §§ 8630 and 8680.9, there exists an actual condition of peril to the safety of persons and property exiting within the Greater Portuguese Bend Landslide, comprised of the Portuguese Bend Landslide, the Abalone Cove Landslide, and the Klondike Canyon Landslide), as depicted in Exhibits “A” and “B” of Resolution No. 2023-47, and based on the staff report and recommendations and public testimony, and hereby proclaims that a state of local emergency continues to exist throughout the same. Section 3. Authority Granted. It is further proclaimed and ordered that during the existence of said local emergency, the powers, authority, functions and duties of the Disaster Council, Director, and the City’s emergency services organizations shall be those prescribed by State Law, City ordinances, Resolution No. 2023-47 and any other applicable resolutions, and approved plans of the City in order to mitigate the effects of the local emergency. Section 4. Immunity Invoked. To the maximum extent permitted by law, and pursuant to Government Code § 866, the City Council hereby invokes the immunity B-2 Resolution No. 2025-__ Page 3 of 3 afforded to the City of Rancho Palos Verds in adopting and implementing the declaration of local emergency within the Landslide Complex Section 5. Duration. The local emergency shall be deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Section 6. Continuing Declaration. Government Code § 8630 requires the City Council to review of the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within Landslide Complex has been abated or mitigated to insignificance. Section 7. Severability. If any subsection, sentence, clause, phrase, or word of this Resolution or any application of it to any person, structure, gathering, or circumstance is held to be invalid or unconstitutional by a decision of a court of competent jurisdiction, then such decision will not affect the validity of the remaining portions or applications of this Resolution. Section 8. Effectiveness. This Resolution shall take effect immediately. A copy of the Proclamation and this Resolution shall be forwarded to the California Emergency Management Agency. The City Clerk shall certify to the passage and adoption of this resolution.. PASSED, APPROVED AND ADOPTED on this 19th day of August, 2025. ________________________________ David Bradley, Mayor ATTEST: ________________________________ Teresa Takaoka, City Clerk STATE OF CALIFORNIA ) COUNTY OF LOS ANGELES ) ss CITY OF RANCHO PALOS VERDES ) I, Teresa Takaoka, City Clerk of the City of Rancho Palos Verdes, hereby certify that the above Resolution No. 2025-__ was duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on August 19, 2025. ___________________________ Teresa Takaoka, City Clerk B-3 01203.0023/1027441.1 RESOLUTION NO. 2025-__ A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, CALIFORNIA, EXTENDING THE STATE OF LOCAL EMERGENCY WITHIN THE GEOGRAPHIC BOUNDARIES OF THE PORTUGUESE BEND COMMUNITY ASSOCIATION, PORTUGUESE BEND BEACH CLUB, AND SEAVIEW NEIGHBORHOODS, BASED ON SUDDEN ENERGY SHORTAGES, PLANNED DEENERGIZING EVENTS, AND INTERNET SERVICE SHUT OFFS AS ESTABLISHED BY RESOLUTION NOS. 2024-52 AND 2024-57 FOR AN ADDITIONAL 60 DAYS WHEREAS, the City of Rancho Palos Verdes is home to four out of five sub-slides that comprise the Greater Portuguese Landslide Complex (Landslide Complex): the Portuguese Bend Landslide, Abalone Cove Landslide, Klondike Canyon Landslide, and Beach Club Landslide. The Portuguese Bend Landslide encompasses the Portuguese Bend Community Association (PBCA), the Seaview Neighborhood (Seaview), and the Portuguese Bend Beach Club (PBBC). The Landslide Complex has been active since the 1950s; WHEREAS, the 2022-2023 rainy season brought exceptional amounts of rain to the region, dumping 20.9” of rain or 190% of the average annual rainfall in the region; WHEREAS, by April 26, 2024, total rainfall for the 2023-24 season (beginning Oct 1, 2023) was 23.01" or 169% of the historical 67-year average of 13.63" for this rain gauge. (All data based on LACDPW Rainfall Gauge No. 1011B at Rolling Hills FS.); WHEREAS, beginning in 2018, but particularly since May 2023, the land movement in the Landslide Complex has increased significantly due to increased rainfall in the last two rainy seasons, which caused the water table to rise dramatically and destabilize the landslides. The City has established, via repeated geologic studies, that a significant factor in the speed of land movement in the Landslide Complex is the amount of water in the soil; WHEREAS, on October 3, 2023, the City Council of the City of Rancho Palos Verdes adopted Resolution No. 2023-47, declaring a local state of emergency due to the alarming increase of land movement in the Landslide Complex. The state of emergency based on the land movement has been extended as required by law and is still active; WHEREAS, on August 6, 2024, the City Council by unanimous vote adopted Resolution No. 2024-52, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service to approximately 135 homes in the PBCA due to safety concerns; WHEREAS, on September 3, 2024, the City Council by unanimous vote adopted Resolution No. 2024-57, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned de- energization events, and internet shut-offs in the PBCA, Seaview, and PBBC; C-1 Resolution No. 2025-__ Page 2 of 4 WHEREAS, on October 1, 2024, the City Council by unanimous vote adopted Resolution No. 2024-61, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; WHEREAS, on November 19, 2024, the City Council by unanimous vote adopted Resolution No. 2024-71, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; WHEREAS, on December 17, 2024, the City Council by unanimous vote adopted Resolution No. 2024-78, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; WHEREAS, on February 4, 2025, the City Council by unanimous vote adopted Resolution No. 2025-07, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, on March 18, 2025, the City Council by unanimous vote adopted Resolution No. 2025-16, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, on May 6, 2025, the City Council by unanimous vote adopted Resolution No. 2025-28, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, on July 1, 2025, the City Council by unanimous vote adopted Resolution No. 2025-45, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; andWHEREAS, after consideration of all facts reasonably available the City Council now desires to extend the declaration of a state of local emergency within the Landslide Complex. NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, CALIFORNIA, HEREBY FINDS, DETERMINES, AND RESOLVES AS FOLLOWS: Section 1. Recitals. The City Council hereby determines that the above recitals are true and correct and incorporates the same as the findings of the City Council. Section 2. Extension of Local State of Emergency. The City Council finds, pursuant to RPVMC Chapter 2.24 and Government Code §§ 8630, 8680.9, and 8558 there exists an actual condition of peril to the safety of persons and property existing C-2 Resolution No. 2025-__ Page 3 of 4 within the PBCA, Seaview, and PBBC, as established by Resolutions No. 2024-52 and 2024-57, and based on the staff report and recommendations and public testimony, and hereby proclaims that a state of local emergency continues to exist throughout the same. Section 3. Authority Granted. It is further proclaimed and ordered that during the existence of said local emergency, the powers, authority, functions and duties of the Disaster Council, Director, and the City’s emergency services organizations shall be those prescribed by State Law, City ordinances, Resolution Nos. 2023-52 and 2024-57, and any other applicable resolutions, and approved plans of the City in order to mitigate the effects of the local emergency. Section 4. Immunity Invoked. To the maximum extent permitted by law, and pursuant to Government Code § 866, the City Council hereby invokes the immunity afforded to the City of Rancho Palos Verds in adopting and implementing the declaration of local emergency within the Landslide Complex. Section 5. Duration. The local emergency shall be deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Government Code § 8630 requires the City Council to review of the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within the geographic boundaries of the Landslide Complex has been abated or mitigated to insignificance. Section 6. Continuing Declaration. Government Code § 8630 requires the City Council to review of the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within the PBCA has been abated or mitigated to insignificance. Section 7. Severability. If any subsection, sentence, clause, phrase, or word of this Resolution or any application of it to any person, structure, gathering, or circumstance is held to be invalid or unconstitutional by a decision of a court of competent jurisdiction, then such decision will not affect the validity of the remaining portions or applications of this Resolution. Section 8. CEQA. The City Council finds that this Resolution is proposed to allow the City to continue to address and mitigate an imminent threat to public health and safety and therefore is exempt from CEQA pursuant to Public Resources Code, Section 21080(b)(4) and CEQA Guidelines, Section 15269. Section 9. Effectiveness. This Resolution shall take effect immediately. A copy of the Proclamation and this Resolution shall be forwarded to the California Office of Emergency Management. The City Clerk shall certify to the passage and adoption of this resolution. PASSED, APPROVED AND ADOPTED on this 19th day of August, 2025. ________________________________ C-3 Resolution No. 2025-__ Page 4 of 4 David Bradley, Mayor ATTEST: ________________________________ Teresa Takaoka, City Clerk STATE OF CALIFORNIA ) COUNTY OF LOS ANGELES ) ss CITY OF RANCHO PALOS VERDES ) I, Teresa Takaoka, City Clerk of the City of Rancho Palos Verdes, hereby certify that the above Resolution No. 2025-__ was duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on August 19, 2025. ___________________________ Teresa Takaoka, City Clerk C-4 No r t h No r t h 0 250 500 1000 (feet) PONY TRAIL PORTUGUESE BEND LANDSLIDE FLYING TRIANGLE LANDSLIDE KLONDIKE CANYON LANDSLIDE ABALONE COVE LANDSLIDE ABALONE COVE PORTUGUESE POINT INSPIRATION POINT SACRED COVE PALOS VERDES DRIVE SOUTH BURMA ROAD EXPLANATION Limits of the Ancient Portuguese Bend Landslide Complex Limits of Historically Mapped Landslides 2023/2024 Landslide Features (based on CSA field mapping) SEAVIEW TRACT Limits of 2023-2024 Major Landslide Movement (based on CSA field mapping and bathymetry survey) LIMITS OF 2023-2024 MAJOR LANDSLIDE MOVEMENT GPS Monument Displacement Rate (June 3, 2025 to July 1, 2025) Displacement Vector Scale 1"= 8"/week 1. 0 2.0 3. 0 3.0 3.0 2.0 3.0 Displacement Rate Table Minimum Rate (inch/week) 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 Maximum Rate (inch/week) 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 Color 10.00 11.00 11.00 12.00 1.00 2.00 12.00 13.00 0.00 1.00 APPROXIMATE BOUNDARY OF ANCIENT PORTUGUESE BEND LANDSLIDE COMPLEX BEACH CLUB LANSDSLIDE DDW-10 DDW-9A DDW-9 DDW-11 DDW-8 DDW-7 DDW-5 DDW-4 DDW-6 DDW-1 DDW-2 DDW-3 RP05 0.02 RP01 0.03 AB80 0.03 RP03 0.03 FT10 0.04 KC23 0.04 AB760.04 KC15 0.04 CR53 0.05 KC26 0.05 AB78 0.05 KC16 0.05 CW06 0.05 KC28 0.05 KC14 0.05 KC22 0.06 RP02 0.06 KC30 0.06 AB640.06 CR56 0.06 CW01 0.06 KC21 0.06 KC25 0.06 CR57 0.06 AB010.06 KC35 0.06 KC13 0.06 KC37 0.07 CR58 0.07 FT09 0.07 KC36 0.07 KC34 0.07 FT08 0.07 CW08 0.07 KC07 0.08 AB77 0.08 CW05 0.08 KC18 0.08 KC29 0.09 KC31 0.09 KC06 0.09 AB79 0.09 KC17 0.09 KC05 0.10 KC19 0.10 CR60 0.11 CR59 0.11 AB170.12 KC20 0.13 CR50 0.16 PB13 0.57 PB290.68 PB26 0.75 UB02 0.87 PB76 1.28 AB83 2.67 PB12 1.48 PB67 1.59 PB77 1.63 PB091.67 PB08 1.77 PB20 1.81 PB061.93 PB21 1.94 PB27 2.01 AB742.05 PB07 2.15 AB82 2.18 PB55 2.33 PB69 2.34 AB73 2.45 AB67 2.52 PB70 2.53 PB72 2.54 PB59 2.56 PB04 2.61 AB16 2.65 PB68 2.68 PB752.74 AB62 2.76 PB18 2.93 PB543.01 AB65 3.04 AB04 3.05 AB51 3.13 PB71RP 3.24 AB63 3.29 AB53 3.30 AB68 3.32 AB813.33 AB75 3.34 AB213.35 AB57 3.37 AB663.37 CR54 3.41 AB60 3.53 AB583.61 AB59 3.62 AB13 3.71 AB70 3.77 AB24 3.93 DDW-29 DDW-26 DDW-16DDW-25 DDW-24 DDW-28 DDW-27 DDW-8 DDW-22 DDW-21 WW-3 MW-18 WW-12 WW-13 WW-30 WW-1 WW-6 WW-7 WW-17 WW-11 WW-15 WW-21 UDW-ACLAD-1 KC-1 KC-3 KC-4 KC-6 KC-5 KC-2 KC-7 KC-4A COTTON,S HIRES AND ASSOCIATES, INC. CONSULTING ENGINEERS AND GEOLOGISTS RANCHO PALOS VERDES, CALIFORNIA SC6163 POS MP July 14, 2025 1"=500' FIGURE NO. PROJECT NO. DATE SCALE APPROVED BY GEO/ENG BY GPS MONITORING DISPLACEMENT RATE CONTOUR MAP (7/1/25 DATA) 1 Abalone Cove, Portuguese Bend, Klondike Canyon Hillshade basemap produced from publicly available LiDAR: "2015 - 2016 LARIAC Lidar DEM: Los Angeles Region, CA" D-1 No r t h No r t h 0 250 500 1000 (feet) PONY TRAIL PORTUGUESE BEND LANDSLIDE FLYING TRIANGLE LANDSLIDE KLONDIKE CANYON LANDSLIDE ABALONE COVE LANDSLIDE ABALONE COVE PORTUGUESE POINT INSPIRATION POINT SACRED COVE PALOS VERDES DRIVE SOUTH BURMA ROAD EXPLANATION Limits of the Ancient Portuguese Bend Landslide Complex Limits of Historically Mapped Landslides 2023/2024 Landslide Features (based on CSA field mapping) SEAVIEW TRACT Limits of 2023-2024 Major Landslide Movement (based on CSA field mapping and bathymetry survey) LIMITS OF 2023-2024 MAJOR LANDSLIDE MOVEMENT GPS Monument Displacement Rate (July 1, 2025 to August 5, 2025) Displacement Vector Scale 1"= 8"/week 1. 0 2.0 1. 0 2.0 2.0 2.0 3 . 0 Displacement Rate Table Minimum Rate (inch/week) 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 Maximum Rate (inch/week) 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 Color 10.00 11.00 11.00 12.00 1.00 2.00 12.00 13.00 0.00 1.00 APPROXIMATE BOUNDARY OF ANCIENT PORTUGUESE BEND LANDSLIDE COMPLEX BEACH CLUB LANSDSLIDE DDW-10 DDW-9A DDW-9 DDW-11 DDW-8 DDW-7 DDW-5 DDW-4 DDW-6 DDW-1 DDW-2 DDW-3 WW-3 MW-18 WW-12 WW-13 WW-30 WW-1 WW-6 WW-7 WW-17 WW-11 WW-15 WW-21 UDW-ACLAD-1 KC-1 KC-3 KC-4 KC-6 KC-5 KC-2 KC-7 KC-4A RP05 0.00 KC17 0.00 CW06 0.00 AB80 0.01 CR56 0.02 RP03 0.02 KC21 0.02 AB01 0.02 CR57 0.02 FT08 0.02 KC28 0.02 KC14 0.03 KC13 0.03 KC16 0.03 KC25 0.03 CR53 0.03 AB64 0.04 KC30 0.04 AB77 0.04 CW08 0.04 KC20 0.04 FT09 0.04 CR59 0.04 KC36 0.04 KC22 0.04 KC26 0.04 KC06 0.05 RP02 0.05 AB76 0.05 AB79 0.05 KC05 0.05 KC19 0.06 KC18 0.06 AB17 0.06 KC31 0.07 KC23 0.07 KC34 0.07 KC29 0.07 CW01 0.07 KC07 0.07 KC35 0.08 FT10 0.08 RP01 0.08 AB78 0.09 CR58 0.09 KC37 0.09 CR50 0.10 KC15 0.10 CW05 0.11 CR60 0.12 PB13 0.44 PB26 0.56 PB29 0.60 UB02 0.74 PB76 1.03 AB50 1.13 PB12 1.26 PB67 1.28 PB09 1.29 PB77 1.33 PB08 1.51 PB20 1.54 PB06 1.56 PB21 1.66 AB74 1.69 PB07 1.74 PB27 1.80 PB55 1.85 AB73 1.92 PB69 1.93 PB70 1.98 PB59 2.02 AB67 2.04 PB72 2.06PB04 2.10 AB16 2.12 PB68 2.14 PB75 2.19 AB62 2.22 PB18 2.24 PB54 2.31 AB04 2.42 AB65 2.48 AB57 2.54 AB63 2.54 PB71RP 2.56 AB51 2.60 AB75 2.62 AB53 2.65 AB21 2.65 AB66 2.70AB68 2.72 CR54 2.74 AB81 2.74 AB59 2.79 AB60 2.79 AB58 2.82 AB70 2.98 AB13 3.05 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 AB24 3.17 ACLAD 25 ACLAD 24 ACLAD 28 ACLAD 27 ACLAD 16 ACLAD 26 ACLAD 29 ACLAD 8 ACLAD 21 ACLAD 22 AB83 2.45 COTTON,S HIRES AND ASSOCIATES, INC. CONSULTING ENGINEERS AND GEOLOGISTS RANCHO PALOS VERDES, CALIFORNIA SC6163 POS MP August 12, 2025 1"=500' FIGURE NO. PROJECT NO. DATE SCALE APPROVED BY GEO/ENG BY GPS MONITORING DISPLACEMENT RATE CONTOUR MAP (8/5/25 DATA) 1 Abalone Cove, Portuguese Bend, Klondike Canyon Hillshade basemap produced from publicly available LiDAR: "2015 - 2016 LARIAC Lidar DEM: Los Angeles Region, CA" D-2 Notes: An average month is 30.42 days * = Indicates no horizontal movement detected in the Period at the 95% level of confidence $ = Overall Movement is Relative to the Date of Origin which varies, see Year & Page 1 for Date 1 = Probable Error of the Indicated Movement not the Rate/Month 2 = Periodic Movement Time Intervals are as indicated and reflected in the Rates NAVD88 Rate/Mo Rate/Mo Point North (ft)East (ft)Elev(ft)North East Height Azim.º2D Dist.North East Height Azim.º2D Dist.95%Err(1)Rate/Mo.Note % Chg North East Height Azim.º2D Dist.95%Err(1)Rate/Mo.Note % Chg AB01 1729427.541 6445709.638 178.665 -0.04 0.03 0.04 147 0.05 -0.01 0.02 -0.01 108 0.02 0.04 * AB04 1728354.661 6447085.495 62.124 -37.33 -37.85 -5.45 225 53.16 -0.70 -0.74 -0.09 227 1.02 0.04 1.11 -5 -0.31 -0.32 -0.08 226 0.44 0.04 0.97 -23 AB13 1729879.809 6448223.087 355.358 -49.09 -12.95 -9.67 195 50.77 -1.21 -0.24 -0.32 191 1.24 0.04 1.34 -7 -0.55 -0.08 -0.07 188 0.56 0.04 1.21 -18 AB16 1730324.7 6447525.616 374.411 -34.19 -6.51 -2.21 191 34.80 -0.87 -0.17 -0.07 191 0.88 0.04 0.96 -5 -0.40 -0.06 0.06 188 0.41 0.04 0.89 -15 AB17 1731420.996 6446727.797 442.756 -0.12 0.02 -0.04 169 0.13 0.04 0.01 -0.07 17 0.04 0.04 * AB21 1729304.341 6449661.701 393.911 -50.73 -13.32 -1.03 195 52.45 -1.09 -0.22 0.01 192 1.12 0.04 1.21 -5 AB24 1729777.782 6447746.149 333.531 -52.57 -13.81 -2.39 195 54.36 -1.28 -0.26 -0.16 191 1.31 0.04 1.42 -8 -0.60 -0.08 -0.07 188 0.61 0.04 1.32 -13 AB50 1728066.982 6448225.122 184.6 -18.02 -23.06 2.62 232 29.26 AB51 1729577.176 6447292.137 303.733 -39.83 -14.40 -1.69 200 42.36 -0.99 -0.32 -0.03 198 1.04 0.04 1.13 -9 AB53 1730380.25 6449703.645 347.88 -50.86 -8.73 -5.25 190 51.60 -1.09 -0.15 -0.11 188 1.10 0.04 1.20 -9 -0.52 -0.06 0.02 186 0.52 0.04 1.14 -10 AB57 1731889.045 6449748.235 553.313 -37.86 -11.13 -11.62 196 39.46 -0.91 -0.66 -0.23 216 1.12 0.04 1.22 -1 AB58 1731067.821 6449071.869 396.657 -50.20 -3.06 -9.01 183 50.29 -1.20 -0.09 -0.23 184 1.20 0.04 1.31 -5 -0.58 -0.01 -0.01 181 0.58 0.04 1.26 -7 AB59 1730794.757 6450206.551 419.594 -56.11 -6.00 -14.78 186 56.43 -1.20 -0.17 -0.33 188 1.21 0.04 1.31 -5 -0.61 -0.06 -0.15 185 0.61 0.04 1.33 2 AB60 1729045.517 6447966.822 176.015 -44.19 -20.75 -3.44 205 48.81 -1.06 -0.51 -0.05 206 1.18 0.04 1.28 -7 AB62 1728875.92 6446905.237 139.373 -34.43 -20.22 -3.64 210 39.93 -0.77 -0.50 -0.11 213 0.92 0.04 1.00 -3 AB63 1729019.085 6447283.504 168.667 -40.21 -23.53 -12.18 210 46.59 -0.95 -0.56 -0.25 210 1.10 0.04 1.19 0 -0.42 -0.25 -0.12 211 0.49 0.04 1.07 -18 AB64 1731829.229 6447374.39 531.653 -1.46 1.31 -0.60 138 1.96 0.00 -0.02 0.01 276 0.02 0.04 * AB65 1731665.594 6448268.771 446.602 -40.08 4.71 -11.93 173 40.36 -1.01 0.02 -0.33 179 1.01 0.04 1.10 -9 AB66 1730001.724 6448479.497 367.626 -45.56 -11.03 -6.66 194 46.88 -1.09 -0.26 -0.16 193 1.12 0.04 1.22 -6 AB67 1731147.92 6447739.424 397.998 -32.49 -2.33 -7.33 184 32.57 -0.83 -0.10 -0.18 187 0.84 0.04 0.91 -8 AB68 1730214.364 6448046.022 385.34 -44.49 -9.34 -8.11 192 45.46 -1.08 -0.23 -0.25 192 1.11 0.04 1.20 -7 AB70 1729240.259 6448335.67 249.361 -51.22 -17.20 -4.79 199 54.03 -1.21 -0.34 -0.14 196 1.26 0.04 1.37 -8 AB73 1728416.229 6448379.362 303.336 -39.81 -14.67 -3.37 200 42.43 -0.78 -0.25 -0.06 198 0.82 0.04 0.89 -7 AB74 1729590.893 6446842.91 268.592 -14.69 -10.23 -3.31 215 17.90 -0.53 -0.43 -0.15 219 0.68 0.04 0.74 -4 AB75 1729586.159 6449327.916 347.569 -34.00 -8.44 -1.45 194 35.03 -1.09 -0.23 -0.02 192 1.11 0.04 1.21 -5 AB76 1730022.733 6446807.045 385.811 -0.39 0.41 -0.47 134 0.56 -0.01 0.00 -0.01 180 0.01 0.04 * AB77 1733161.909 6446514.813 895.367 -0.01 -0.04 0.05 256 0.04 -0.02 -0.01 0.10 214 0.03 0.04 * AB78 1732238.883 6448523.504 568.822 -2.28 0.63 -0.92 165 2.37 -0.02 0.00 -0.03 187 0.02 0.04 * AB79 1734784.198 6448718.974 1169.695 -0.01 -0.02 -0.07 252 0.02 -0.02 -0.02 -0.06 222 0.03 0.04 * AB80 1734692.164 6447838.317 1165.493 0.02 0.01 -0.06 39 0.02 0.01 0.00 -0.09 27 0.01 0.04 * AB81 1731129.388 6448787.457 394.125 -11.01 -0.98 -2.19 185 11.05 -1.10 -0.12 -0.21 186 1.11 0.04 1.21 -6 AB82 1732186.324 6448634.476 555.956 -3.01 0.13 -1.64 178 3.02 -0.73 -0.01 -0.36 181 0.73 0.04 0.79 1 -0.36 0.03 -0.14 175 0.36 0.79 -2 AB83 1729273.842 6446953.426 214.69 -0.41 -0.16 0.00 201 0.44 -0.41 -0.16 0.00 201 0.44 0.04 0.97 2 CR50 1733013.029 6451036.344 872.299 -0.59 -1.03 -0.36 240 1.19 -0.03 -0.04 0.07 237 0.05 0.04 0.06 CR53 1732779.419 6450222.774 780.317 -0.86 -1.42 -0.41 239 1.66 -0.01 -0.01 0.06 203 0.02 0.04 * CR54 1731201.368 6450982.603 517.595 -43.87 -9.22 -9.95 192 44.83 -1.08 -0.35 -0.12 198 1.14 0.04 1.23 -3 CR55A 1735437.65 6450188.396 1157.375 -0.02 -0.01 0.10 211 0.02 -0.02 0.01 -0.03 144 0.02 0.04 * CR56 1733194.376 6449201.895 782.605 -0.03 0.00 0.02 180 0.03 0.00 -0.02 0.01 264 0.02 0.04 * CR57 1731568.832 6451323.462 619.463 -0.04 -0.06 0.52 237 0.08 0.01 0.01 0.06 45 0.02 0.04 * CR58 1732680.377 6452989.306 916.918 -0.23 -0.24 -0.08 226 0.34 -0.02 0.01 0.04 159 0.02 0.04 * CR59 1731860.914 6453394.68 878.094 -0.05 -0.07 0.00 231 0.08 0.01 -0.03 0.04 291 0.04 0.04 * CR60 1732970.723 6452807.498 921.824 -0.11 -0.09 -0.03 221 0.14 0.00 0.04 0.03 90 0.04 0.04 * CW01 1734174.324 6450266.353 1175.391 0.01 0.03 0.05 66 0.03 -0.01 -0.01 0.01 231 0.02 0.04 * CW05 1732067.205 6450634.436 701.932 -1.15 -1.07 0.00 223 1.57 -0.01 -0.03 0.03 252 0.03 0.04 * CW06 1730906.256 6452118.193 529.818 0.02 0.02 0.05 52 0.02 -0.01 0.01 0.01 121 0.02 0.04 * CW08 1729146.315 6453119.788 607.535 0.03 0.01 0.08 15 0.03 0.02 0.01 -0.05 38 0.02 0.04 * FT08 1729388.674 6453350.481 658.386 -0.01 -0.02 -0.05 252 0.03 0.02 -0.02 -0.06 315 0.02 0.04 * FT09 1729052.861 6454289.235 590.875 -0.04 -0.06 0.05 240 0.07 0.02 0.00 0.08 0 0.02 0.04 * FT10 1730454.574 6452471.919 482.307 0.01 0.00 -0.04 45 0.01 0.01 0.00 0.05 5 0.01 0.04 * KC05 1727077.187 6453174.096 226.831 -4.81 -5.00 -1.03 226 6.94 0.00 -0.03 0.02 275 0.03 0.04 * KC06 1727782.493 6453384.968 295.769 -2.42 -11.70 -4.58 258 11.94 0.01 -0.03 0.02 288 0.03 0.04 * KC07 1727759.372 6453683.875 313.507 0.00 0.02 0.00 92 0.02 0.00 -0.03 0.00 275 0.03 0.04 * KC13 1726576.314 6453068.873 192.033 -4.84 -0.76 0.83 189 4.90 0.00 -0.02 -0.03 278 0.02 0.04 *-0.02 0.03 0.02 129 0.03 0.04 * KC14 1726742.294 6453805.521 260.022 -0.15 -0.53 0.08 255 0.55 0.00 -0.02 0.02 276 0.02 0.04 * KC15 1727584.379 6453111.502 284.135 -6.07 -9.59 -2.97 238 11.35 -0.01 -0.01 0.06 222 0.01 0.04 *-0.02 0.02 0.04 126 0.03 0.04 * KC16 1727602.236 6454098.234 327.293 -0.01 0.00 0.39 180 0.01 0.00 -0.02 0.00 259 0.02 0.04 * KC17 1727295.878 6453019.502 212.735 -6.89 -6.92 -2.52 225 9.76 0.01 -0.03 0.03 295 0.03 0.04 * KC18 1727979.503 6452613.658 289.167 -21.00 -8.51 -2.01 202 22.66 0.01 -0.03 0.00 281 0.03 0.04 * KC19 1727780.028 6453488.581 302.852 -0.38 -8.64 -3.48 267 8.65 -0.01 -0.03 0.07 245 0.03 0.04 * KC20 1727695.363 6453561.612 303.833 0.20 -7.93 -3.46 271 7.94 0.01 -0.04 0.07 289 0.04 0.04 * KC21 1728095.836 6453495.11 383.692 0.02 0.03 0.09 57 0.03 0.02 -0.01 0.01 332 0.02 0.04 * KC22 1728008.152 6453287.403 329.169 -2.01 -10.48 -5.18 259 10.67 0.01 0.01 -0.05 49 0.02 0.04 * KC23 1727348.756 6453321.595 267.635 -2.67 -5.42 -1.67 244 6.04 0.00 -0.01 0.08 261 0.01 0.04 * KC25 1726304.904 6452805.421 19.798 -0.38 -0.19 0.00 207 0.43 0.02 -0.01 -0.01 325 0.02 0.04 * KC26 1726723.081 6452425.82 31.118 -6.45 -1.30 6.37 191 6.58 0.01 0.00 0.01 18 0.02 0.04 *-0.01 0.03 0.02 109 0.03 * KC28 1726768.64 6451998.871 26.286 -9.16 -1.03 6.35 186 9.21 0.00 -0.02 0.02 270 0.02 0.04 * KC29 1726923.942 6451934.539 19.995 -10.49 -3.09 2.09 196 10.93 -0.02 -0.01 0.05 209 0.03 0.04 * KC30 1727529.523 6452141.997 97.717 -14.52 -4.52 -2.53 197 15.21 0.00 -0.02 -0.01 273 0.02 0.04 * KC31 1727911.088 6452353.174 206.881 -13.84 -5.03 -0.61 200 14.73 0.00 -0.03 0.04 264 0.03 0.04 *-0.02 0.00 0.05 189 0.02 * KC34 1726698.403 6454866.431 325.424 0.00 0.00 0.06 303 0.00 0.01 -0.02 0.02 285 0.02 0.04 * KC35 1726861.657 6454504.96 313.34 0.00 0.00 0.04 226 0.01 0.01 -0.02 0.02 293 0.02 0.04 * KC36 1726390.079 6454165.114 255.046 0.01 -0.04 0.04 285 0.04 0.01 -0.02 0.03 292 0.02 0.04 * KC37 1726109.831 6454779.83 280.36 0.01 -0.01 0.04 308 0.02 0.00 -0.02 0.04 270 0.02 0.04 * PB04 1727617.842 6448831.399 164.198 -58.09 -20.34 -6.32 199 61.55 -0.82 -0.28 -0.04 199 0.87 0.04 0.95 -4 PB06 1727893.575 6449747.559 173.711 -74.87 -14.28 -9.35 191 76.22 -0.64 -0.06 -0.02 185 0.64 0.04 0.70 -1 PB07 1728087.495 6450197.655 195.741 -88.43 -22.10 -4.47 194 91.15 -0.71 -0.12 -0.05 189 0.72 0.04 0.78 -1 -0.32 -0.01 0.03 182 0.33 0.04 0.71 -18 PB08 1728155.54 6450450.32 196.359 -81.97 -19.48 2.68 193 84.25 -0.59 -0.06 0.07 186 0.59 0.04 0.64 -10 PB09 1728202.603 6450840.992 188.889 -85.98 -10.03 -3.63 187 86.56 -0.56 0.02 0.08 178 0.56 0.04 0.60 -5 PB12 1728201.294 6451566.153 177.921 -129.19 -38.42 -15.37 197 134.78 -0.49 -0.07 -0.01 188 0.49 0.04 0.54 -8 -0.25 -0.01 0.02 183 0.25 0.04 0.54 -2 PB13 1728004.356 6452132.632 205.674 -81.61 -31.71 -4.87 201 87.56 -0.17 -0.09 -0.03 208 0.19 0.04 0.21 5 PB18 1730379.841 6450714.186 356.06 -67.04 3.19 -11.52 177 67.12 -0.97 -0.10 -0.15 186 0.98 0.04 1.06 -7 PB20 1728688.253 6451110.724 225.004 -124.51 -24.95 -18.54 191 126.99 -0.60 -0.03 -0.03 183 0.60 0.04 0.66 -14 PB21 1729192.838 6451171.26 265.947 -105.38 -0.79 -14.07 180 105.38 -0.65 0.02 -0.04 178 0.65 0.04 0.70 -10 PB26 1729503.63 6452246.022 280.006 -59.02 -3.54 -5.33 183 59.12 -0.25 0.04 0.05 171 0.25 0.04 0.27 0 PB27 1729187.936 6451834.154 261.065 -151.40 -1.91 -23.36 181 151.42 -0.67 0.02 -0.01 178 0.67 0.04 0.73 -10 PB29 1728802.313 6452076.469 159.894 -86.63 -44.02 -26.04 207 97.17 -0.15 -0.17 -0.04 229 0.23 0.04 0.25 -23 PB54 1729640.547 6450438.262 355.725 -54.35 -10.42 -2.89 191 55.34 -0.99 -0.13 0.02 188 1.00 0.04 1.09 -6 -0.48 -0.03 0.05 183 0.48 0.04 1.04 -10 PB55 1728724.539 6450789.911 231.319 -87.74 -14.13 -15.01 189 88.87 -0.77 -0.08 -0.06 186 0.78 0.04 0.84 4 PB59 1727705.263 6448642.466 151.588 -61.10 -19.20 -11.80 197 64.05 -0.81 -0.26 -0.02 198 0.85 0.04 0.93 -4 PB67 1727547.797 6450841.489 64.043 -90.93 -16.69 -11.97 190 92.45 -0.52 -0.09 -0.04 190 0.53 0.04 0.58 -12 PB68 1727620.453 6448967.701 171.676 -44.99 -15.29 -1.43 199 47.52 -0.86 -0.23 -0.03 195 0.89 0.04 0.97 -5 PB69 1727736.875 6448761.566 162.138 -46.17 -17.02 -2.54 200 49.20 -0.74 -0.27 -0.06 200 0.78 0.04 0.85 -13 PB70 1727808.851 6448602.154 149.487 -46.05 -17.44 -6.75 201 49.25 -0.80 -0.26 -0.06 198 0.84 0.04 0.92 -8 PB71RP 1728421.505 6449739.977 282.942 -12.16 -1.63 -1.90 188 12.27 -1.07 -0.17 -0.13 189 1.08 0.04 1.18 -6 -0.50 -0.06 -0.01 187 0.50 0.04 1.09 -14 PB72 1727613.274 6449325.777 199.14 -37.05 -15.65 3.25 203 40.22 -0.80 -0.28 -0.05 199 0.85 0.04 0.92 -8 PB75 1729042.127 6450344.846 267.999 -41.73 -7.06 -3.90 190 42.32 -0.91 -0.04 -0.07 183 0.91 0.04 0.99 -6 PB76 1729966.776 6451645.924 290.838 -6.32 0.05 -0.96 180 6.32 -0.43 0.01 -0.01 178 0.43 0.04 0.46 -11 -0.20 0.04 0.02 168 0.21 0.04 0.46 -6 PB77 1727517.156 6451675.62 98.745 -3.47 -0.41 -0.30 187 3.50 -0.54 -0.10 -0.01 190 0.54 0.04 0.59 -1 -0.27 -0.01 0.01 183 0.27 0.04 0.58 -7 UB02 1727470.505 6450140.789 65.601 -110.61 7.01 -1.55 176 110.83 -0.28 0.07 0.02 167 0.29 0.04 0.31 -10 PVE3RP 1729195.912 6438764.684 346.918 0.03 0.01 0.04 0.03 0.03 0.02 0.01 0.03 0.02 *0.01 0.01 0.02 0.02 0.02 * RP01 1725591.737 6455633.557 292.733 -0.01 0.01 0.06 0.01 0.00 -0.01 -0.03 0.01 0.02 *-0.03 0.03 0.00 0.05 0.02 * RP02 1730832.977 6445586.632 480.678 -0.01 0.02 0.05 0.02 -0.01 0.02 0.05 0.02 Fixed *-0.01 0.02 0.05 0.02 Fixed Fixed Periodic Movements M77 to M78 (US Feet) June 17, 2025 to July 1, 2025 (14 days / 0.460 Mo.)NAD83 CA SPC Zone 5 Original Position to July 1, 2025 June 3, 2025 to July 1, 2025 (28 days / 0.920 Mo.) PORTUGUESE BEND LANDSLIDE MONITORING - MOVEMENT at July 1, 2025 Page 58 Prepared by McGee Surveying Consulting - Document Date: July 6, 2025 Monitoring Point Movements FULL PVDS MONITORING #78 (M78) July 1, 2025 Positions $ Overall Movements (US Feet)Periodic Movements M76 to M78 (US Feet) E-1 RP03 1730848.517 6445628.196 479.982 0.02 -0.02 0.00 0.03 -0.01 0.01 0.00 0.01 0.02 *-0.01 0.02 0.03 0.02 0.02 * RP05 1730809.662 6445501.989 474.263 0.00 0.00 0.00 0.00 0.00 0.01 0.00 0.01 0.02 Fixed -0.01 0.03 0.03 0.03 0.02 * Av.0.91 Av.-6.1 Av.0.96 Av.-11 E-2 Notes: An average month is 30.42 days * = Indicates no horizontal movement detected in the Period at the 95% level of confidence $ = Overall Movement is Relative to the Date of Origin which varies, see Year & Page 1 for Date 1 = Probable Error of the Indicated Movement not the Rate/Month 2 = Periodic Movement Time Intervals are as indicated and reflected in the Rates 3 = AB82 was destroyed and reset nearby. No movement data available this period. NAVD88 Rate/Mo Rate/Mo Point North (ft)East (ft)Elev(ft)North East Height Azim.º2D Dist.North East Height Azim.º2D Dist.95%Err(1)Rate/Mo.Note % Chg North East Height Azim.º2D Dist.95%Err(1)Rate/Mo.Note % Chg AB01 1729427.53 6445709.64 178.66 -0.05 0.03 0.04 151 0.06 -0.01 0.00 -0.01 180 0.01 0.04 * AB04 1728353.98 6447084.75 62.06 -38.01 -38.59 -5.51 225 54.17 -0.68 -0.75 -0.07 228 1.01 0.04 0.88 -21 -0.37 -0.42 -0.06 228 0.56 0.04 0.81 -18 AB13 1729878.58 6448222.78 355.14 -50.32 -13.26 -9.89 195 52.04 -1.23 -0.31 -0.22 194 1.27 0.04 1.10 -18 -0.70 -0.15 -0.11 192 0.72 0.04 1.04 -13 AB16 1730323.83 6447525.47 374.30 -35.06 -6.65 -2.32 191 35.68 -0.87 -0.14 -0.11 189 0.88 0.04 0.77 -20 -0.49 -0.08 -0.02 189 0.49 0.04 0.71 -16 AB17 1731420.97 6446727.79 442.74 -0.15 0.02 -0.06 174 0.15 -0.02 -0.01 -0.02 198 0.03 0.04 * AB21 1729303.25 6449661.50 393.84 -51.82 -13.52 -1.10 195 53.55 -1.09 -0.20 -0.07 191 1.11 0.04 0.96 -21 AB24 1729776.50 6447745.81 333.45 -53.85 -14.15 -2.47 195 55.68 -1.28 -0.34 -0.08 195 1.32 0.04 1.15 -19 -0.72 -0.18 -0.04 194 0.74 0.04 1.08 -15 AB50 1728066.69 6448224.75 184.68 -18.31 -23.43 2.70 232 29.74 -0.29 -0.37 0.08 232 0.47 0.04 0.41 AB51 1729576.15 6447291.79 303.68 -40.86 -14.75 -1.74 200 43.44 -1.03 -0.34 -0.06 198 1.08 0.04 0.94 -17 AB53 1730379.16 6449703.47 347.74 -51.94 -8.90 -5.39 190 52.70 -1.09 -0.18 -0.14 189 1.10 0.04 0.96 -20 -0.62 -0.09 -0.07 188 0.62 0.04 0.91 -13 AB57 1731888.18 6449747.62 553.10 -38.72 -11.74 -11.83 197 40.46 -0.86 -0.62 -0.22 216 1.06 0.04 0.92 -25 AB58 1731066.65 6449071.73 396.42 -51.37 -3.20 -9.25 184 51.47 -1.17 -0.14 -0.24 187 1.18 0.04 1.02 -22 -0.66 -0.06 -0.14 185 0.67 0.04 0.97 -13 AB59 1730793.60 6450206.41 419.31 -57.27 -6.14 -15.06 186 57.59 -1.16 -0.14 -0.29 187 1.16 0.04 1.01 -23 -0.72 -0.09 -0.16 187 0.73 0.04 1.06 12 AB60 1729044.47 6447966.31 176.00 -45.23 -21.25 -3.45 205 49.98 -1.05 -0.51 -0.02 206 1.16 0.04 1.01 -21 AB62 1728875.17 6446904.70 139.31 -35.18 -20.76 -3.70 211 40.85 -0.75 -0.54 -0.07 215 0.92 0.04 0.80 -20 AB63 1729018.18 6447282.95 168.37 -41.11 -24.09 -12.47 210 47.65 -0.90 -0.56 -0.30 212 1.06 0.04 0.92 -23 -0.52 -0.32 -0.19 211 0.61 0.04 0.89 -9 AB64 1731829.22 6447374.38 531.62 -1.47 1.30 -0.63 139 1.96 -0.01 -0.01 -0.04 236 0.01 0.04 * AB65 1731664.56 6448268.82 446.28 -41.11 4.75 -12.26 173 41.39 -1.03 0.05 -0.32 177 1.03 0.04 0.90 -19 AB66 1730000.62 6448479.27 367.47 -46.66 -11.26 -6.81 194 48.00 -1.10 -0.23 -0.15 192 1.13 0.04 0.98 -20 AB67 1731147.07 6447739.36 397.77 -33.34 -2.40 -7.56 184 33.42 -0.85 -0.07 -0.23 184 0.85 0.04 0.74 -19 AB68 1730213.25 6448045.82 385.19 -45.61 -9.54 -8.26 192 46.60 -1.12 -0.20 -0.15 190 1.13 0.04 0.99 -18 AB70 1729239.05 6448335.37 249.17 -52.42 -17.50 -4.97 198 55.27 -1.21 -0.30 -0.19 194 1.24 0.04 1.08 -21 AB73 1728415.46 6448379.14 303.27 -40.58 -14.89 -3.43 200 43.23 -0.77 -0.22 -0.06 196 0.80 0.04 0.70 -22 AB74 1729590.34 6446842.48 268.42 -15.25 -10.66 -3.48 215 18.61 -0.56 -0.43 -0.18 218 0.70 0.04 0.61 -18 AB75 1729585.09 6449327.70 347.52 -35.07 -8.66 -1.50 194 36.12 -1.07 -0.22 -0.05 191 1.09 0.04 0.95 -22 AB76 1730022.75 6446807.03 385.80 -0.38 0.39 -0.48 134 0.54 0.02 -0.01 -0.02 319 0.02 0.04 * AB77 1733161.90 6446514.83 895.28 -0.02 -0.03 -0.04 233 0.03 -0.01 0.01 -0.09 130 0.02 0.04 * AB78 1732238.92 6448523.50 568.77 -2.24 0.63 -0.97 164 2.33 0.04 0.00 -0.05 355 0.04 0.04 * AB79 1734784.20 6448719.00 1169.74 0.00 0.00 -0.03 207 0.00 0.00 0.02 0.04 77 0.02 0.04 * AB80 1734692.16 6447838.32 1165.52 0.01 0.01 -0.04 43 0.02 0.00 0.00 0.02 207 0.00 0.04 * AB81 1731128.25 6448787.36 393.85 -12.15 -1.08 -2.46 185 12.19 -1.14 -0.10 -0.27 185 1.14 0.04 0.99 -18 AB82 1732183.08 6448636.94 555.42 -6.26 2.59 -2.17 158 6.77 -3.24 2.46 -0.53 143 4.07 0.04 3.54 3 AB83 1729272.92 6446953.00 214.67 -1.34 -0.59 -0.02 204 1.47 -0.93 -0.43 -0.02 205 1.02 0.04 0.89 -8 -0.59 -0.27 -0.05 205 0.65 0.94 15 CR50 1733013.06 6451036.38 872.37 -0.56 -1.00 -0.29 241 1.14 0.03 0.03 0.07 46 0.04 0.04 * 1733061.29 6452360.81 976.03 -0.74 -1.05 -0.22 CR53 1732779.41 6450222.78 780.42 -0.87 -1.41 -0.31 238 1.66 -0.01 0.00 0.10 159 0.01 0.04 * CR54 1731200.29 6450982.24 517.39 -44.95 -9.59 -10.16 192 45.96 -1.08 -0.37 -0.21 199 1.14 0.04 CR55A 1735437.63 6450188.39 1157.42 -0.04 -0.02 0.15 207 0.05 -0.02 -0.01 0.05 203 0.02 0.04 * CR56 1733194.38 6449201.90 782.62 -0.02 0.00 0.03 175 0.02 0.01 0.00 0.01 18 0.01 0.04 * CR57 1731568.83 6451323.46 619.44 -0.05 -0.07 0.50 235 0.08 -0.01 0.00 -0.03 210 0.01 0.04 * CR58 1732680.34 6452989.32 917.04 -0.27 -0.23 0.04 221 0.35 -0.04 0.01 0.12 161 0.04 0.04 * CR59 1731860.92 6453394.70 878.22 -0.05 -0.05 0.13 226 0.07 0.01 0.02 0.12 71 0.02 0.04 * CR60 1732970.75 6452807.54 921.90 -0.08 -0.05 0.05 210 0.10 0.02 0.04 0.08 61 0.05 0.04 * CW01 1734174.33 6450266.38 1175.49 0.02 0.06 0.15 74 0.06 0.00 0.03 0.10 84 0.03 0.04 * CW05 1732067.17 6450634.47 702.04 -1.18 -1.04 0.11 221 1.57 -0.03 0.03 0.11 133 0.05 0.04 * CW06 1730906.25 6452118.19 529.78 0.01 0.02 0.02 57 0.02 0.00 0.00 -0.04 153 0.00 0.04 * CW08 1729146.30 6453119.78 607.54 0.01 0.00 0.09 5 0.01 -0.01 -0.01 0.01 202 0.02 0.04 * FT08 1729388.67 6453350.49 658.43 -0.01 -0.02 -0.01 231 0.02 -0.01 0.01 0.04 122 0.01 0.04 * FT09 1729052.88 6454289.23 590.87 -0.02 -0.07 0.04 254 0.07 0.02 0.00 -0.01 343 0.02 0.04 * FT10 1730454.54 6452471.91 482.28 -0.03 0.00 -0.07 191 0.03 -0.03 -0.01 -0.03 198 0.03 0.04 * KC05 1727077.21 6453174.10 226.79 -4.79 -4.99 -1.07 226 6.92 0.02 0.00 -0.04 13 0.02 0.04 * KC06 1727782.49 6453384.95 295.73 -2.42 -11.72 -4.62 258 11.96 0.00 -0.02 -0.04 267 0.02 0.04 * KC07 1727759.40 6453683.88 313.47 0.03 0.03 -0.04 41 0.04 0.03 0.00 -0.03 2 0.03 0.04 * KC13 1726576.32 6453068.88 192.02 -4.83 -0.75 0.82 189 4.89 0.01 0.00 -0.01 27 0.01 0.04 *0.02 0.02 -0.02 36 0.03 0.04 * KC14 1726742.30 6453805.52 259.98 -0.14 -0.54 0.04 256 0.55 0.01 0.00 -0.04 338 0.01 0.04 * KC15 1727584.42 6453111.50 284.07 -6.03 -9.60 -3.03 238 11.34 0.04 -0.01 -0.06 351 0.04 0.04 *0.02 0.01 -0.05 26 0.03 0.04 * KC16 1727602.24 6454098.23 327.27 0.00 -0.01 0.37 257 0.01 0.01 -0.01 -0.02 312 0.01 0.04 * KC17 1727295.88 6453019.50 212.71 -6.89 -6.92 -2.54 225 9.76 0.00 0.00 -0.03 180 0.00 0.04 * KC18 1727979.49 6452613.68 289.14 -21.01 -8.49 -2.04 202 22.66 -0.01 0.02 -0.03 125 0.02 0.04 * KC19 1727780.05 6453488.58 302.77 -0.36 -8.64 -3.56 268 8.65 0.02 0.00 -0.08 2 0.02 0.04 * KC20 1727695.38 6453561.62 303.78 0.21 -7.92 -3.52 272 7.93 0.01 0.01 -0.05 33 0.02 0.04 * KC21 1728095.83 6453495.10 383.64 0.01 0.02 0.03 54 0.02 0.00 -0.01 -0.06 247 0.01 0.04 * KC22 1728008.14 6453287.41 329.14 -2.02 -10.48 -5.21 259 10.67 -0.02 0.01 -0.03 158 0.02 0.04 * KC23 1727348.76 6453321.57 267.55 -2.66 -5.45 -1.75 244 6.06 0.01 -0.03 -0.08 285 0.03 0.04 * KC25 1726304.91 6452805.41 19.80 -0.38 -0.20 0.00 208 0.43 0.01 -0.01 0.00 306 0.01 0.04 * KC26 1726723.07 6452425.81 31.12 -6.46 -1.31 6.38 191 6.59 -0.01 -0.01 0.01 225 0.02 0.04 *-0.03 0.00 0.00 182 0.03 * KC28 1726768.65 6451998.87 26.27 -9.15 -1.04 6.33 186 9.20 0.01 0.00 -0.01 354 0.01 0.04 * KC29 1726923.97 6451934.54 19.96 -10.46 -3.10 2.05 196 10.91 0.03 0.00 -0.04 354 0.03 0.04 * KC30 1727529.54 6452142.01 97.73 -14.51 -4.51 -2.52 197 15.20 0.01 0.01 0.02 37 0.01 0.04 * KC31 1727911.11 6452353.19 206.80 -13.82 -5.01 -0.70 200 14.70 0.02 0.02 -0.09 46 0.03 0.04 *0.02 0.00 -0.07 357 0.02 * KC34 1726698.43 6454866.44 325.36 0.03 0.00 -0.01 2 0.03 0.03 0.00 -0.07 10 0.03 0.04 * KC35 1726861.69 6454504.96 313.28 0.03 -0.01 -0.02 348 0.03 0.03 0.00 -0.06 356 0.03 0.04 * KC36 1726390.10 6454165.11 254.99 0.03 -0.04 -0.01 306 0.05 0.02 0.00 -0.05 357 0.02 0.04 * KC37 1726109.87 6454779.85 280.32 0.05 0.00 0.00 1 0.05 0.03 0.01 -0.04 24 0.04 0.04 * PB04 1727617.01 6448831.13 164.17 -58.92 -20.61 -6.35 199 62.43 -0.83 -0.27 -0.02 198 0.87 0.04 0.76 -20 PB06 1727892.93 6449747.49 173.63 -75.52 -14.34 -9.43 191 76.87 -0.65 -0.07 -0.08 186 0.65 0.04 0.57 -19 PB07 1728086.78 6450197.55 195.64 -89.15 -22.21 -4.57 194 91.87 -0.72 -0.11 -0.10 188 0.72 0.04 0.63 -19 -0.40 -0.04 -0.06 186 0.40 0.04 0.58 -16 PB08 1728154.91 6450450.29 196.38 -82.60 -19.51 2.70 193 84.87 -0.63 -0.03 0.02 183 0.63 0.04 0.55 -15 PB09 1728202.07 6450841.06 188.87 -86.51 -9.96 -3.65 187 87.08 -0.53 0.07 -0.02 173 0.54 0.04 0.47 -23 PB12 1728200.78 6451566.08 177.81 -129.71 -38.49 -15.48 197 135.30 -0.52 -0.08 -0.11 188 0.52 0.04 0.45 -15 -0.29 -0.04 -0.07 188 0.29 0.04 0.43 -14 PB13 1728004.19 6452132.55 205.62 -81.78 -31.79 -4.92 201 87.74 -0.16 -0.08 -0.05 206 0.18 0.04 0.16 -22 PB18 1730378.91 6450714.09 355.89 -67.97 3.10 -11.69 177 68.04 -0.93 -0.09 -0.17 186 0.93 0.04 0.81 -23 PB20 1728687.61 6451110.68 224.88 -125.15 -25.00 -18.66 191 127.63 -0.64 -0.05 -0.13 184 0.64 0.04 0.56 -15 PB21 1729192.15 6451171.28 265.89 -106.07 -0.78 -14.13 180 106.07 -0.69 0.02 -0.06 179 0.69 0.04 0.60 -15 PB26 1729503.40 6452246.08 279.97 -59.24 -3.48 -5.37 183 59.35 -0.23 0.06 -0.04 166 0.23 0.04 0.20 -25 PB27 1729187.19 6451834.18 260.85 -152.15 -1.88 -23.57 181 152.16 -0.75 0.02 -0.22 178 0.75 0.04 0.65 -11 PB29 1728802.11 6452076.33 159.79 -86.84 -44.16 -26.14 207 97.42 -0.21 -0.14 -0.10 214 0.25 0.04 0.22 -11 PB54 1729639.59 6450438.16 355.59 -55.31 -10.53 -3.03 191 56.30 -0.96 -0.11 -0.14 186 0.96 0.04 0.84 -23 -0.56 -0.05 -0.04 185 0.56 0.04 0.81 -7 PB55 1728723.77 6450789.91 231.14 -88.51 -14.14 -15.19 189 89.64 -0.77 -0.01 -0.18 180 0.77 0.04 0.67 -20 PB59 1727704.47 6448642.19 151.51 -61.90 -19.48 -11.88 197 64.89 -0.79 -0.28 -0.08 199 0.84 0.04 0.73 -21 PB67 1727547.27 6450841.43 63.93 -91.46 -16.75 -12.08 190 92.98 -0.53 -0.06 -0.11 186 0.53 0.04 0.46 -20 PB68 1727619.59 6448967.49 171.60 -45.86 -15.50 -1.51 199 48.41 -0.87 -0.21 -0.08 194 0.89 0.04 0.77 -20 PB69 1727736.10 6448761.34 162.13 -46.94 -17.25 -2.55 200 50.01 -0.77 -0.23 -0.01 197 0.80 0.04 0.70 -18 PB70 1727808.05 6448601.95 149.44 -46.86 -17.64 -6.80 201 50.07 -0.80 -0.21 -0.05 194 0.83 0.04 0.72 -22 PB71RP 1728420.45 6449739.83 282.71 -13.21 -1.77 -2.13 188 13.33 -1.06 -0.14 -0.23 188 1.07 0.04 0.93 -21 -0.63 -0.08 -0.10 187 0.63 0.04 0.91 -4 PB72 1727612.46 6449325.51 199.14 -37.86 -15.92 3.26 203 41.07 -0.81 -0.27 0.00 198 0.86 0.04 0.75 -19 NAD83 CA SPC Zone 5 Original Position to Aug. 5, 2025 July 1, 2025 to August 5, 2025 (35 days / 1.151 Mo.)July 15, 2025, to August 5, 2025 (21 days / 0.690 Mo.) PORTUGUESE BEND LANDSLIDE MONITORING - MOVEMENT at August 5, 2025 Page 60/60 Prepared by McGee Surveying Consulting - Document Date: August 7, 2025 Monitoring Point Movements FULL PVDS MONITORING #80 (M80) August 5, 2025 Positions $ Overall Movements (US Feet)Periodic Movements M78 to M80 (US Feet)Periodic Movements M79 to M80 (US Feet) E-3 PB75 1729041.21 6450344.84 267.85 -42.64 -7.06 -4.05 189 43.22 -0.91 0.00 -0.15 180 0.91 0.04 0.79 -20 PB76 1729966.35 6451645.95 290.76 -6.75 0.08 -1.03 179 6.75 -0.43 0.03 -0.08 176 0.43 0.04 0.37 -20 -0.26 0.02 -0.04 176 0.26 0.04 0.38 1 PB77 1727516.60 6451675.57 98.68 -4.03 -0.46 -0.36 187 4.05 -0.55 -0.05 -0.07 185 0.56 0.04 0.48 -18 -0.32 -0.04 -0.03 186 0.32 0.04 0.47 -8 UB02 1727470.22 6450140.89 65.58 -110.90 7.10 -1.57 176 111.13 -0.29 0.10 -0.03 161 0.31 0.04 0.27 -15 0.00 0.00 0.00 PVE3RP 1729195.89 6438764.68 346.90 0.01 0.00 0.02 0.01 -0.02 0.00 -0.02 0.02 0.02 *0.01 0.01 -0.03 0.01 0.02 * RP01 1725591.77 6455633.54 292.74 0.03 0.00 0.07 0.03 0.03 -0.01 0.01 0.03 0.02 *0.02 0.00 -0.03 0.02 0.02 * RP02 1730832.97 6445586.61 480.63 -0.02 0.00 0.00 0.02 -0.01 -0.02 -0.05 0.02 Fixed *-0.01 -0.02 0.01 0.02 Fixed * RP03 1730848.51 6445628.19 479.99 0.02 -0.02 0.00 0.03 0.00 -0.01 0.01 0.01 0.02 *-0.01 0.00 0.01 0.01 0.02 * RP05 1730809.66 6445501.99 474.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.02 Fixed 0.00 0.00 0.00 0.00 0.02 Fixed Av.0.79 Av.-19.3 Av.0.80 Av.-8 E-4 01203.0001/835260.1 1 PROFESSIONAL SERVICES AGREEMENT By and Between CITY OF RANCHO PALOS VERDES and GEOLOGIC ASSOCIATES, INC. F-1 01203.0001/835260.1 AGREEMENT FOR PROFESSIONAL SERVICES BETWEEN THE CITY OF RANCHO PALOS VERDES AND GEOLOGIC ASSOCIATES, INC. THIS AGREEMENT FOR PROFESSIONAL SERVICES (“Agreement”) is made and entered into on August 19, 2025 by and between the CITY OF RANCHO PALOS VERDES, a California municipal corporation (“City”) and GEOLOGIC ASSOCIATES, INC., a California Corporation (“Consultant”). City and Consultant may be referred to, individually or collectively, as “Party” or “Parties.” RECITALS A. Consultant, following submission of a proposal for the performance of the services defined and described particularly in Article 1 of this Agreement, was selected by the City to perform those services. B. Pursuant to the City of Rancho Palos Verdes Municipal Code, City has authority to enter into and execute this Agreement. C. The Parties desire to formalize the selection of Consultant for performance of those services defined and described particularly in Article 1 of this Agreement and desire that the terms of that performance be as particularly defined and described herein. OPERATIVE PROVISIONS NOW, THEREFORE, in consideration of the mutual promises and covenants made by the Parties and contained herein and other consideration, the value and adequacy of which are hereby acknowledged, the parties agree as follows: ARTICLE 1. SERVICES OF CONSULTANT 1.1 Scope of Services. In compliance with all terms and conditions of this Agreement, the Consultant shall provide those services specified in the “Scope of Services”, as stated in the Proposal, attached hereto as Exhibit “A” and incorporated herein by this reference, which may be referred to herein as the “services” or “work” hereunder. As a material inducement to the City entering into this Agreement, Consultant represents and warrants that it has the qualifications, experience, and facilities necessary to properly perform the services required under this Agreement in a thorough, competent, and professional manner, and is experienced in performing the work and services contemplated herein. Consultant shall at all times faithfully, competently and to the best of its ability, experience and talent, perform all services described herein. Consultant covenants that it shall follow the highest professional standards in performing the work and services required hereunder and that all materials will be both of good quality as well as fit for the purpose intended. For purposes of this Agreement, the phrase “highest professional standards” shall mean those standards of practice recognized by one or more first-class firms performing similar work under similar circumstances. F-2 01203.0001/835260.1 2 1.2 Consultant’s Proposal. The Scope of Service shall include the Consultant’s Proposal which shall be incorporated herein by this reference as though fully set forth herein. In the event of any inconsistency between the terms of such Proposal and this Agreement, the terms of this Agreement shall govern. 1.3 Compliance with Law. Consultant shall keep itself informed concerning, and shall render all services hereunder in accordance with, all ordinances, resolutions, statutes, rules, and regulations of the City and any Federal, State or local governmental entity having jurisdiction in effect at the time service is rendered. 1.4 California Labor Law. If the Scope of Services includes any “public work” or “maintenance work,” as those terms are defined in California Labor Code section 1720 et seq. and California Code of Regulations, Title 8, Section 16000 et seq., and if the total compensation is $1,000 or more, Consultant shall pay prevailing wages for such work and comply with the requirements in California Labor Code section 1770 et seq. and 1810 et seq., and all other applicable laws, including the following requirements: (a) Public Work. The Parties acknowledge that some or all of the work to be performed under this Agreement is a “public work” as defined in Labor Code Section 1720 and that this Agreement is therefore subject to the requirements of Division 2, Part 7, Chapter 1 (commencing with Section 1720) of the California Labor Code relating to public works contracts and the rules and regulations established by the Department of Industrial Relations (“DIR”) implementing such statutes. The work performed under this Agreement is subject to compliance monitoring and enforcement by the DIR. Consultant shall post job site notices, as prescribed by regulation. (b) Prevailing Wages. Consultant shall pay prevailing wages to the extent required by Labor Code Section 1771. Pursuant to Labor Code Section 1773.2, copies of the prevailing rate of per diem wages are on file at City Hall and will be made available to any interested party on request. By initiating any work under this Agreement, Consultant acknowledges receipt of a copy of the DIR determination of the prevailing rate of per diem wages, and Consultant shall post a copy of the same at each job site where work is performed under this Agreement. (c) Penalty for Failure to Pay Prevailing Wages. Consultant shall comply with and be bound by the provisions of Labor Code Sections 1774 and 1775 concerning the payment of prevailing rates of wages to workers and the penalties for failure to pay prevailing wages. The Consultant shall, as a penalty to the City, forfeit $200 (two hundred dollars) for each calendar day, or portion thereof, for each worker paid less than the prevailing rates as determined by the DIR for the work or craft in which the worker is employed for any public work done pursuant to this Agreement by Consultant or by any subcontractor. F-3 F-4 01203.0001/835260.1 4 subcontractor's compliance with Division 2, Part 7, Chapter 1 (commencing with Section 1720) of the California Labor Code, and shall make such compliance a requirement in any contract with any subcontractor for work under this Agreement. Consultant shall be required to take all actions necessary to enforce such contractual provisions and ensure subcontractor's compliance, including without limitation, conducting a review of the certified payroll records of the subcontractor on a periodic basis or upon becoming aware of the failure of the subcontractor to pay his or her workers the specified prevailing rate of wages. Consultant shall diligently take corrective action to halt or rectify any such failure by any subcontractor. 1.5 Licenses, Permits, Fees and Assessments. Consultant shall obtain at its sole cost and expense such licenses, permits and approvals as may be required by law for the performance of the services required by this Agreement. Consultant shall have the sole obligation to pay for any fees, assessments and taxes, plus applicable penalties and interest, which may be imposed by law and arise from or are necessary for the Consultant’s performance of the services required by this Agreement, and shall indemnify, defend and hold harmless City, its officers, employees or agents of City, against any such fees, assessments, taxes, penalties or interest levied, assessed or imposed against City hereunder. 1.6 Familiarity with Work. By executing this Agreement, Consultant warrants that Consultant (i) has thoroughly investigated and considered the scope of services to be performed, (ii) has carefully considered how the services should be performed, and (iii) fully understands the facilities, difficulties and restrictions attending performance of the services under this Agreement. If the services involve work upon any site, Consultant warrants that Consultant has or will investigate the site and is or will be fully acquainted with the conditions there existing, prior to commencement of services hereunder. Should the Consultant discover any latent or unknown conditions, which will materially affect the performance of the services hereunder, Consultant shall immediately inform the City of such fact and shall not proceed except at Consultant’s risk until written instructions are received from the Contract Officer in the form of a Change Order. 1.7 Care of Work. The Consultant shall adopt reasonable methods during the life of the Agreement to furnish continuous protection to the work, and the equipment, materials, papers, documents, plans, studies and/or other components thereof to prevent losses or damages, and shall be responsible for all such damages, to persons or property, until acceptance of the work by City, except such losses or damages as may be caused by City’s own negligence. 1.8 Further Responsibilities of Parties. Both parties agree to use reasonable care and diligence to perform their respective obligations under this Agreement. Both parties agree to act in good faith to execute all instruments, prepare all documents and take all actions as may be reasonably necessary to carry F-5 01203.0001/835260.1 5 out the purposes of this Agreement. Unless hereafter specified, neither party shall be responsible for the service of the other. 1.9 Additional Services City shall have the right at any time during the performance of the services, without invalidating this Agreement, to order extra work beyond that specified in the Scope of Services or make changes by altering, adding to or deducting from said work. No such extra work may be undertaken unless a written Change Order is first given by the Contract Officer to the Consultant, incorporating therein any adjustment in (i) the Contract Sum for the actual costs of the extra work, and/or (ii) the time to perform this Agreement, which said adjustments are subject to the written approval of the Consultant. Any increase in compensation of up to 15% (fifteen percent) of the Contract Sum; or, in the time to perform of up to 90 (ninety) days, may be approved by the Contract Officer through a written Change Order. Any greater increases, taken either separately or cumulatively, must be approved by the City Council. It is expressly understood by Consultant that the provisions of this Section shall not apply to services specifically set forth in the Scope of Services. Consultant hereby acknowledges that it accepts the risk that the services to be provided pursuant to the Scope of Services may be more costly or time consuming than Consultant anticipates and that Consultant shall not be entitled to additional compensation therefor. City may in its sole and absolute discretion have similar work done by other Consultants. No claims for an increase in the Contract Sum or time for performance shall be valid unless the procedures established in this Section are followed. If in the performance of the Services, the Contractor becomes aware of material defects in the Scope of Work, duration, or span of the Services, or the Contractor becomes aware of extenuating circumstance that will or could prevent the completion of the Services, on time or on budget, the Contractor shall inform the City’s Contract Officer of an anticipated Change Order. This proposed change order will stipulate the facts surrounding the issue, proposed solutions, proposed costs, and proposed schedule impacts. 1.10 Special Requirements. Additional terms and conditions of this Agreement, if any, which are made a part hereof are set forth in the “Special Requirements” attached hereto as Exhibit “B” and incorporated herein by this reference. In the event of a conflict between the provisions of Exhibit “B” and any other provisions of this Agreement, the provisions of Exhibit “B” shall govern. ARTICLE 2. COMPENSATION AND METHOD OF PAYMENT. 2.1 Contract Sum. Subject to any limitations set forth in this Agreement, City agrees to pay Consultant the amounts specified in the “Schedule of Compensation” attached hereto as Exhibit “C” and incorporated herein by this reference. The total compensation, including reimbursement for actual expenses, shall not exceed $460,685 (Four Hundred Sixty Thousand Six Hundred F-6 01203.0001/835260.1 6 Eighty Five Dollars) (the “Contract Sum”), unless additional compensation is approved pursuant to Section 1.9. 2.2 Method of Compensation. (a) The method of compensation may include: (i) a lump sum payment upon completion; (ii) payment in accordance with specified tasks or the percentage of completion of the services; (iii) payment for time and materials based upon the Consultant’s rates as specified in the Schedule of Compensation, provided that (a) time estimates are provided for the performance of sub tasks, and (b) the Contract Sum is not exceeded; or (iv) such other methods as may be specified in the Schedule of Compensation. (b) A retention of 10% shall be held from each payment as a contract retention to be paid as part of the final payment upon satisfactory and timely completion of services. This retention shall not apply for on-call agreements for continuous services or for agreements for scheduled routine maintenance of City property or City facilities. 2.3 Reimbursable Expenses. Compensation may include reimbursement for actual and necessary expenditures for reproduction costs, telephone expenses, and travel expenses approved by the Contract Officer in advance, or actual subcontractor expenses of an approved subcontractor pursuant to Section 4.5, and only if specified in the Schedule of Compensation. The Contract Sum shall include the attendance of Consultant at all project meetings reasonably deemed necessary by the City. Coordination of the performance of the work with City is a critical component of the services. If Consultant is required to attend additional meetings to facilitate such coordination, Consultant shall not be entitled to any additional compensation for attending said meetings. 2.4 Invoices. Each month Consultant shall furnish to City an original invoice, using the City template, or in a format acceptable to the City, for all work performed and expenses incurred during the preceding month in a form approved by City’s Director of Finance. By submitting an invoice for payment under this Agreement, Consultant is certifying compliance with all provisions of the Agreement. The invoice shall detail charges for all necessary and actual expenses by the following categories: labor (by sub-category), travel, materials, equipment, supplies, and sub- contractor contracts. Sub-contractor charges shall also be detailed by such categories. Consultant shall not invoice City for any duplicate services performed by more than one person. City shall independently review each invoice submitted by the Consultant to determine whether the work performed and expenses incurred are in compliance with the provisions of this Agreement. Except as to any charges for work performed or expenses incurred by Consultant which are disputed by City, or as provided in Section 7.3, City will use its best efforts to cause Consultant to be paid within 45 (forty-five) days of receipt of Consultant’s correct and undisputed invoice; however, Consultant acknowledges and agrees that due to City warrant run procedures, the City cannot guarantee that payment will occur within this time period. In the event any charges or expenses are disputed by City, the original invoice shall be returned by City F-7 01203.0001/835260.1 7 to Consultant for correction and resubmission. Review and payment by City for any invoice provided by the Consultant shall not constitute a waiver of any rights or remedies provided herein or any applicable law. 2.5 Waiver. Payment to Consultant for work performed pursuant to this Agreement shall not be deemed to waive any defects in work performed by Consultant. ARTICLE 3. PERFORMANCE SCHEDULE 3.1 Time of Essence. Time is of the essence in the performance of this Agreement. 3.2 Schedule of Performance. Consultant shall commence the services pursuant to this Agreement upon receipt of a written notice to proceed and shall perform all services within the time period(s) established in the “Schedule of Performance” attached hereto as Exhibit “D” and incorporated herein by this reference. When requested by the Consultant, extensions to the time period(s) specified in the Schedule of Performance may be approved in writing by the Contract Officer through a Change Order, but not exceeding 90 (ninety) days cumulatively. 3.3 Force Majeure. The time period(s) specified in the Schedule of Performance for performance of the services rendered pursuant to this Agreement shall be extended because of any delays due to unforeseeable causes beyond the control and without the fault or negligence of the Consultant, including, but not restricted to, acts of God or of the public enemy, unusually severe weather, fires, earthquakes, floods, epidemics, quarantine restrictions, riots, strikes, freight embargoes, wars, litigation, and/or acts of any governmental agency, including the City, if the Consultant shall within 10 (ten) days of the commencement of such delay notify the Contract Officer in writing of the causes of the delay. The Contract Officer shall ascertain the facts and the extent of delay, and extend the time for performing the services for the period of the enforced delay when and if in the judgment of the Contract Officer such delay is justified. The Contract Officer’s determination shall be final and conclusive upon the parties to this Agreement. In no event shall Consultant be entitled to recover damages against the City for any delay in the performance of this Agreement, however caused, Consultant’s sole remedy being extension of the Agreement pursuant to this Section. 3.4 Term. Unless earlier terminated in accordance with Article 7 of this Agreement, this Agreement shall continue in full force and effect until completion of the services but not exceeding one year from the date herof, except as otherwise provided in the Schedule of Performance (Exhibit “D”). F-8 01203.0001/835260.1 8 ARTICLE 4. COORDINATION OF WORK 4.1 Representatives and Personnel of Consultant. The following principals of Consultant (“Principals”) are hereby designated as being the principals and representatives of Consultant authorized to act in its behalf with respect to the work specified herein and make all decisions in connection therewith: Gary L. Lass Chief Executive Officer (Name) (Title) William McCormick Principal Engineering Geologist (Name) (Title) It is expressly understood that the experience, knowledge, capability and reputation of the foregoing principals were a substantial inducement for City to enter into this Agreement. Therefore, the foregoing principals shall be responsible during the term of this Agreement for directing all activities of Consultant and devoting sufficient time to personally supervise the services hereunder. All personnel of Consultant, and any authorized agents, shall at all times be under the exclusive direction and control of the Principals. For purposes of this Agreement, the foregoing Principals may not be replaced nor may their responsibilities be substantially reduced by Consultant without the express written approval of City. Additionally, Consultant shall utilize only the personnel included in the Proposal to perform services pursuant to this Agreement. Consultant shall make every reasonable effort to maintain the stability and continuity of Consultant’s staff and subcontractors, if any, assigned to perform the services required under this Agreement. Consultant shall notify City of any changes in Consultant’s staff and subcontractors, if any, assigned to perform the services required under this Agreement, prior to and during any such performance. City shall have the right to approve or reject any proposed replacement personnel, which approval shall not be unreasonably withheld. 4.2 Status of Consultant. Consultant shall have no authority to bind City in any manner, or to incur any obligation, debt or liability of any kind on behalf of or against City, whether by contract or otherwise, unless such authority is expressly conferred under this Agreement or is otherwise expressly conferred in writing by City. Consultant shall not at any time or in any manner represent that Consultant or any of Consultant’s officers, employees, or agents are in any manner officials, officers, employees or agents of City. Neither Consultant, nor any of Consultant’s officers, employees or agents, shall obtain any rights to retirement, health care or any other benefits which may otherwise accrue to City’s employees. Consultant expressly waives any claim Consultant may have to any such rights. F-9 01203.0001/835260.1 9 4.3 Contract Officer. The Contract Officer shall be Ramzi Awwad, Public Works Director, or such person as may be designated by the Director of Public Works. It shall be the Consultant’s responsibility to assure that the Contract Officer is kept informed of the progress of the performance of the services and the Consultant shall refer any decisions which must be made by City to the Contract Officer. Unless otherwise specified herein, any approval of City required hereunder shall mean the approval of the Contract Officer. The Contract Officer shall have authority, if specified in writing by the City Manager, to sign all documents on behalf of the City required hereunder to carry out the terms of this Agreement. 4.4 Independent Consultant. Neither the City nor any of its employees shall have any control over the manner, mode or means by which Consultant, its agents or employees, perform the services required herein, except as otherwise set forth herein. City shall have no voice in the selection, discharge, supervision or control of Consultant’s employees, servants, representatives or agents, or in fixing their number, compensation or hours of service. Consultant shall perform all services required herein as an independent contractor of City and shall remain at all times as to City a wholly independent contractor with only such obligations as are consistent with that role. Consultant shall not at any time or in any manner represent that it or any of its agents or employees are agents or employees of City. City shall not in any way or for any purpose become or be deemed to be a partner of Consultant in its business or otherwise or a joint venturer or a member of any joint enterprise with Consultant. 4.5 Prohibition Against Subcontracting or Assignment. The experience, knowledge, capability and reputation of Consultant, its principals and employees were a substantial inducement for the City to enter into this Agreement. Therefore, Consultant shall not contract with any other entity to perform in whole or in part the services required hereunder without the express written approval of the City; all subcontractors included in the Proposal are deemed approved. In addition, neither this Agreement nor any interest herein may be transferred, assigned, conveyed, hypothecated or encumbered voluntarily or by operation of law, whether for the benefit of creditors or otherwise, without the prior written approval of City. Transfers restricted hereunder shall include the transfer to any person or group of persons acting in concert of more 25% (twenty five percent) of the present ownership and/or control of Consultant, taking all transfers into account on a cumulative basis. In the event of any such unapproved transfer, including any bankruptcy proceeding, this Agreement shall be void. No approved transfer shall release the Consultant or any surety of Consultant of any liability hereunder without the express consent of City. ARTICLE 5. INSURANCE AND INDEMNIFICATION 5.1 Insurance Coverages. Without limiting Consultant’s indemnification of City, and prior to commencement of any services under this Agreement, Consultant shall obtain, provide and maintain at its own F-10 01203.0001/835260.1 10 expense during the term of this Agreement, policies of insurance of the type and amounts described below and in a form satisfactory to City. (a) General liability insurance. Consultant shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in an amount not less than $1,000,000 per occurrence, $2,000,000 general aggregate, for bodily injury, personal injury, and property damage. The policy must include contractual liability that has not been amended. Any endorsement restricting standard ISO “insured contract” language will not be accepted. (b) Automobile liability insurance. Consultant shall maintain automobile insurance at least as broad as Insurance Services Office form CA 00 01 covering bodily injury and property damage for all activities of the Consultant arising out of or in connection with Services to be performed under this Agreement, including coverage for any owned, hired, non- owned or rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident. (c) Professional liability (errors & omissions) insurance. Consultant shall maintain professional liability insurance that covers the Services to be performed in connection with this Agreement, in the minimum amount of $1,000,000 per claim and in the aggregate. Any policy inception date, continuity date, or retroactive date must be before the effective date of this Agreement and Consultant agrees to maintain continuous coverage through a period no less than three (3) years after completion of the services required by this Agreement. (d) Workers’ compensation insurance. Consultant shall maintain Workers’ Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance (with limits of at least $1,000,000). (e) Subcontractors. Consultant shall include all subcontractors as insureds under its policies or shall furnish separate certificates and certified endorsements for each subcontractor. All coverages for subcontractors shall include all of the requirements stated herein. (f) Additional Insurance. Policies of such other insurance, as may be required in the Special Requirements in Exhibit “B”. 5.2 General Insurance Requirements. (a) Proof of insurance. Consultant shall provide certificates of insurance to City as evidence of the insurance coverage required herein, along with a waiver of subrogation endorsement for workers’ compensation. Insurance certificates and endorsements must be approved by City’s Risk Manager prior to commencement of performance. Current certification of insurance shall be kept on file with City at all times during the term of this Agreement. City reserves the right to require complete, certified copies of all required insurance policies, at any time. F-11 01203.0001/835260.1 11 (b) Duration of coverage. Consultant shall procure and maintain for the duration of this Agreement insurance against claims for injuries to persons or damages to property, which may arise from or in connection with the performance of the Services hereunder by Consultant, its agents, representatives, employees or subconsultants. (c) Primary/noncontributing. Coverage provided by Consultant shall be primary and any insurance or self-insurance procured or maintained by City shall not be required to contribute with it. The limits of insurance required herein may be satisfied by a combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and non- contributory basis for the benefit of City before the City’s own insurance or self-insurance shall be called upon to protect it as a named insured. (d) City’s rights of enforcement. In the event any policy of insurance required under this Agreement does not comply with these specifications or is canceled and not replaced, City has the right but not the duty to obtain and continuously maintain the insurance it deems necessary and any premium paid by City will be promptly reimbursed by Consultant or City will withhold amounts sufficient to pay premium from Consultant payments. In the alternative, City may cancel this Agreement. (e) Acceptable insurers. All insurance policies shall be issued by an insurance company currently authorized by the Insurance Commissioner to transact business of insurance or that is on the List of Approved Surplus Line Insurers in the State of California, with an assigned policyholders’ Rating of A- (or higher) and Financial Size Category Class VI (or larger) in accordance with the latest edition of Best’s Key Rating Guide, unless otherwise approved by the City’s Risk Manager. (f) Waiver of subrogation. All insurance coverage maintained or procured pursuant to this agreement shall be endorsed to waive subrogation against City, its elected or appointed officers, agents, officials, employees and volunteers or shall specifically allow Consultant or others providing insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss. Consultant hereby waives its own right of recovery against City, and shall require similar written express waivers and insurance clauses from each of its subconsultants. (g) Enforcement of contract provisions (non-estoppel). Consultant acknowledges and agrees that any actual or alleged failure on the part of the City to inform Consultant of non-compliance with any requirement imposes no additional obligations on the City nor does it waive any rights hereunder. (h) Requirements not limiting. Requirements of specific coverage features or limits contained in this section are not intended as a limitation on coverage, limits or other requirements, or a waiver of any coverage normally provided by any insurance. Specific reference to a given coverage feature is for purposes of clarification only as it pertains to a given issue and is not intended by any party or insured to be all inclusive, or to the exclusion of other coverage, or a waiver of any type. If the Consultant maintains higher limits than the minimums shown above, the City requires and shall be entitled to coverage for the higher limits maintained F-12 01203.0001/835260.1 12 by the Consultant. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the City. (i) Notice of cancellation. Consultant agrees to oblige its insurance agent or broker and insurers to provide to City with a 30 (thirty) day notice of cancellation (except for nonpayment for which a 10 (ten) day notice is required) or nonrenewal of coverage for each required coverage. (j) Additional insured status. General liability policies shall provide or be endorsed to provide that City and its officers, officials, employees, and agents, and volunteers shall be additional insureds under such policies. This provision shall also apply to any excess/umbrella liability policies. (k) Prohibition of undisclosed coverage limitations. None of the coverages required herein will be in compliance with these requirements if they include any limiting endorsement of any kind that has not been first submitted to City and approved of in writing. (l) Separation of insureds. A severability of interests provision must apply for all additional insureds ensuring that Consultant’s insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the insurer’s limits of liability. The policy(ies) shall not contain any cross-liability exclusions. (m) Pass through clause. Consultant agrees to ensure that its subconsultants, subcontractors, and any other party involved with the project who is brought onto or involved in the project by Consultant, provide the same minimum insurance coverage and endorsements required of Consultant. Consultant agrees to monitor and review all such coverage and assumes all responsibility for ensuring that such coverage is provided in conformity with the requirements of this section. Consultant agrees that upon request, all agreements with consultants, subcontractors, and others engaged in the project will be submitted to City for review. (n) Agency’s right to revise specifications. The City reserves the right at any time during the term of the contract to change the amounts and types of insurance required by giving the Consultant 90 (ninety) days advance written notice of such change. If such change results in substantial additional cost to the Consultant, the City and Consultant may renegotiate Consultant’s compensation. (o) Self-insured retentions. Any self-insured retentions must be declared to and approved by City. City reserves the right to require that self-insured retentions be eliminated, lowered, or replaced by a deductible. Self-insurance will not be considered to comply with these specifications unless approved by City. (p) Timely notice of claims. Consultant shall give City prompt and timely notice of claims made or suits instituted that arise out of or result from Consultant’s performance under this Agreement, and that involve or may involve coverage under any of the required liability policies. F-13 01203.0001/835260.1 13 (q) Additional insurance. Consultant shall also procure and maintain, at its own cost and expense, any additional kinds of insurance, which in its own judgment may be necessary for its proper protection and prosecution of the work. 5.3 Indemnification. To the full extent permitted by law, Consultant agrees to indemnify, defend and hold harmless the City, its officers, employees and agents (“Indemnified Parties”) against, and will hold and save them and each of them harmless from, any and all actions, either judicial, administrative, arbitration or regulatory claims, damages to persons or property, losses, costs, penalties, obligations, errors, omissions or liabilities whether actual or threatened (herein “claims or liabilities”) that may be asserted or claimed by any person, firm or entity arising out of or in connection with the negligent performance of the work, operations or activities provided herein of Consultant, its officers, employees, agents, subcontractors, or invitees, or any individual or entity for which Consultant is legally liable (“indemnitors”), or arising from Consultant’s or indemnitors’ reckless or willful misconduct, or arising from Consultant’s or indemnitors’ negligent performance of or failure to perform any term, provision, covenant or condition of this Agreement, and in connection therewith: (a) Consultant will defend any action or actions filed in connection with any of said claims or liabilities and will pay all costs and expenses, including legal costs and attorneys’ fees incurred in connection therewith; (b) Consultant will promptly pay any judgment rendered against the City, its officers, agents or employees for any such claims or liabilities arising out of or in connection with the negligent performance of or failure to perform such work, operations or activities of Consultant hereunder; and Consultant agrees to save and hold the City, its officers, agents, and employees harmless therefrom; (c) In the event the City, its officers, agents or employees is made a party to any action or proceeding filed or prosecuted against Consultant for such damages or other claims arising out of or in connection with the negligent performance of or failure to perform the work, operation or activities of Consultant hereunder, Consultant agrees to pay to the City, its officers, agents or employees, any and all costs and expenses incurred by the City, its officers, agents or employees in such action or proceeding, including but not limited to, legal costs and attorneys’ fees. Consultant shall incorporate similar indemnity agreements with its subcontractors and if it fails to do so Consultant shall be fully responsible to indemnify City hereunder therefore, and failure of City to monitor compliance with these provisions shall not be a waiver hereof. This indemnification includes claims or liabilities arising from any negligent or wrongful act, error or omission, or reckless or willful misconduct of Consultant in the performance of professional services hereunder. The provisions of this Section do not apply to claims or liabilities occurring as a result of City’s sole negligence or willful acts or omissions, but, to the fullest extent permitted by law, shall apply to claims and liabilities resulting in part from City’s negligence, except that design professionals’ indemnity hereunder shall be limited to claims and liabilities arising out of the negligence, recklessness or willful misconduct of the design professional. The F-14 01203.0001/835260.1 14 indemnity obligation shall be binding on successors and assigns of Consultant and shall survive termination of this Agreement. ARTICLE 6. RECORDS, REPORTS, AND RELEASE OF INFORMATION 6.1 Records. Consultant shall keep, and require subcontractors to keep, such ledgers, books of accounts, invoices, vouchers, canceled checks, reports, studies or other documents relating to the disbursements charged to City and services performed hereunder (the “books and records”), as shall be necessary to perform the services required by this Agreement and enable the Contract Officer to evaluate the performance of such services. Any and all such documents shall be maintained in accordance with generally accepted accounting principles and shall be complete and detailed. The Contract Officer shall have full and free access to such books and records at all times during normal business hours of City, including the right to inspect, copy, audit and make records and transcripts from such records. Such records shall be maintained for a period of three (3) years following completion of the services hereunder, and the City shall have access to such records in the event any audit is required. In the event of dissolution of Consultant’s business, custody of the books and records may be given to City, and access shall be provided by Consultant’s successor in interest. Notwithstanding the above, the Consultant shall fully cooperate with the City in providing access to the books and records if a public records request is made and disclosure is required by law including but not limited to the California Public Records Act. 6.2 Reports. Consultant shall periodically prepare and submit to the Contract Officer such reports concerning the performance of the services required by this Agreement as the Contract Officer shall require. Consultant hereby acknowledges that the City is greatly concerned about the cost of work and services to be performed pursuant to this Agreement. For this reason, Consultant agrees that if Consultant becomes aware of any facts, circumstances, techniques, or events that may or will materially increase or decrease the cost of the work or services contemplated herein or, if Consultant is providing design services, the cost of the project being designed, Consultant shall promptly notify the Contract Officer of said fact, circumstance, technique or event and the estimated increased or decreased cost related thereto and, if Consultant is providing design services, the estimated increased or decreased cost estimate for the project being designed. 6.3 Ownership of Documents. All drawings, specifications, maps, designs, photographs, studies, surveys, data, notes, computer files, reports, records, documents and other materials (the “documents and materials”) prepared by Consultant, its employees, subcontractors and agents in the performance of this Agreement shall be the property of City and shall be delivered to City upon request of the Contract Officer or upon the termination of this Agreement, and Consultant shall have no claim for further employment or additional compensation as a result of the exercise by City of its full rights of ownership use, reuse, or assignment of the documents and materials hereunder. Any use, reuse or assignment of such completed documents for other projects and/or use of F-15 01203.0001/835260.1 15 uncompleted documents without specific written authorization by the Consultant will be at the City’s sole risk and without liability to Consultant, and Consultant’s guarantee and warranties shall not extend to such use, reuse or assignment. Consultant may retain copies of such documents for its own use. Consultant shall have the right to use the concepts embodied therein. All subcontractors shall provide for assignment to City of any documents or materials prepared by them, and in the event Consultant fails to secure such assignment, Consultant shall indemnify City for all damages resulting therefrom. Moreover, Consultant with respect to any documents and materials that may qualify as “works made for hire” as defined in 17 U.S.C. § 101, such documents and materials are hereby deemed “works made for hire” for the City. 6.4 Confidentiality and Release of Information. (a) All information gained or work product produced by Consultant in performance of this Agreement shall be considered confidential, unless such information is in the public domain or already known to Consultant. Consultant shall not release or disclose any such information or work product to persons or entities other than City without prior written authorization from the Contract Officer. (b) Consultant, its officers, employees, agents or subcontractors, shall not, without prior written authorization from the Contract Officer or unless requested by the City Attorney, voluntarily provide documents, declarations, letters of support, testimony at depositions, response to interrogatories or other information concerning the work performed under this Agreement. Response to a subpoena or court order shall not be considered “voluntary” provided Consultant gives City notice of such court order or subpoena. (c) If Consultant, or any officer, employee, agent or subcontractor of Consultant, provides any information or work product in violation of this Agreement, then City shall have the right to reimbursement and indemnity from Consultant for any damages, costs and fees, including attorney’s fees, caused by or incurred as a result of Consultant’s conduct. (d) Consultant shall promptly notify City should Consultant, its officers, employees, agents or subcontractors be served with any summons, complaint, subpoena, notice of deposition, request for documents, interrogatories, request for admissions or other discovery request, court order or subpoena from any party regarding this Agreement and the work performed there under. City retains the right, but has no obligation, to represent Consultant or be present at any deposition, hearing or similar proceeding. Consultant agrees to cooperate fully with City and to provide City with the opportunity to review any response to discovery requests provided by Consultant. However, this right to review any such response does not imply or mean the right by City to control, direct, or rewrite said response. ARTICLE 7. ENFORCEMENT OF AGREEMENT AND TERMINATION 7.1 California Law. This Agreement shall be interpreted, construed and governed both as to validity and to performance of the parties in accordance with the laws of the State of California. Legal actions concerning any dispute, claim or matter arising out of or in relation to this Agreement shall be F-16 01203.0001/835260.1 16 instituted in the Superior Court of the County of Los Angeles, State of California, or any other appropriate court in such county, and Consultant covenants and agrees to submit to the personal jurisdiction of such court in the event of such action. In the event of litigation in a U.S. District Court, venue shall lie exclusively in the Central District of California, in the County of Los Angeles, State of California. 7.2 Disputes; Default. In the event that Consultant is in default under the terms of this Agreement, the City shall not have any obligation or duty to continue compensating Consultant for any work performed after the date of default. Instead, the City may give notice to Consultant of the default and the reasons for the default. The notice shall include the timeframe in which Consultant may cure the default. This timeframe is 15 (fifteen) days, but may be extended, though not reduced, if circumstances warrant. During the period of time that Consultant is in default, the City shall hold all invoices and shall, when the default is cured, proceed with payment on the invoices. In the alternative, the City may, in its sole discretion, elect to pay some or all of the outstanding invoices during the period of default. If Consultant does not cure the default, the City may take necessary steps to terminate this Agreement under this Article. Any failure on the part of the City to give notice of the Consultant’s default shall not be deemed to result in a waiver of the City’s legal rights or any rights arising out of any provision of this Agreement. 7.3 Retention of Funds. Consultant hereby authorizes City to deduct from any amount payable to Consultant (whether or not arising out of this Agreement) (i) any amounts the payment of which may be in dispute hereunder or which are necessary to compensate City for any losses, costs, liabilities, or damages suffered by City, and (ii) all amounts for which City may be liable to third parties, by reason of Consultant’s acts or omissions in performing or failing to perform Consultant’s obligation under this Agreement. In the event that any claim is made by a third party, the amount or validity of which is disputed by Consultant, or any indebtedness shall exist which shall appear to be the basis for a claim of lien, City may withhold from any payment due, without liability for interest because of such withholding, an amount sufficient to cover such claim. The failure of City to exercise such right to deduct or to withhold shall not, however, affect the obligations of the Consultant to insure, indemnify, and protect City as elsewhere provided herein. 7.4 Waiver. Waiver by any party to this Agreement of any term, condition, or covenant of this Agreement shall not constitute a waiver of any other term, condition, or covenant. Waiver by any party of any breach of the provisions of this Agreement shall not constitute a waiver of any other provision or a waiver of any subsequent breach or violation of any provision of this Agreement. Acceptance by City of any work or services by Consultant shall not constitute a waiver of any of the provisions of this Agreement. No delay or omission in the exercise of any right or remedy by a non-defaulting party on any default shall impair such right or remedy or be construed as a waiver. Any waiver by either party of any default must be in writing and shall not be a waiver of any other default concerning the same or any other provision of this Agreement. F-17 01203.0001/835260.1 17 7.5 Rights and Remedies are Cumulative. Except with respect to rights and remedies expressly declared to be exclusive in this Agreement, the rights and remedies of the parties are cumulative and the exercise by either party of one or more of such rights or remedies shall not preclude the exercise by it, at the same or different times, of any other rights or remedies for the same default or any other default by the other party. 7.6 Legal Action. In addition to any other rights or remedies, either party may take legal action, in law or in equity, to cure, correct or remedy any default, to recover damages for any default, to compel specific performance of this Agreement, to obtain declaratory or injunctive relief, or to obtain any other remedy consistent with the purposes of this Agreement. Notwithstanding any contrary provision herein, Consultant shall file a statutory claim pursuant to Government Code Sections 905 et seq. and 910 et seq., in order to pursue a legal action under this Agreement. 7.7 Termination Prior to Expiration of Term. This Section shall govern any termination of this Contract except as specifically provided in the following Section for termination for cause. The City reserves the right to terminate this Contract at any time, with or without cause, upon thirty (30) days’ written notice to Consultant, except that where termination is due to the fault of the Consultant, the period of notice may be such shorter time as may be determined by the Contract Officer. Upon receipt of any notice of termination, Consultant shall immediately cease all services hereunder except such as may be specifically approved by the Contract Officer. Consultant shall be entitled to compensation for all services rendered prior to the effective date of the notice of termination and for any services authorized by the Contract Officer thereafter in accordance with the Schedule of Compensation or such as may be approved by the Contract Officer, except as provided in Section 7.3. In the event of termination without cause pursuant to this Section, the City need not provide the Consultant with the opportunity to cure pursuant to Section 7.2. 7.8 Termination for Default of Party. If termination is due to the failure of the other Party to fulfill its obligations under this Agreement: (a) City may, after compliance with the provisions of Section 7.2, take over the work and prosecute the same to completion by contract or otherwise, and the Consultant shall be liable to the extent that the total cost for completion of the services required hereunder exceeds the compensation herein stipulated (provided that the City shall use reasonable efforts to mitigate such damages), and City may withhold any payments to the Consultant for the purpose of set-off or partial payment of the amounts owed the City as previously stated. (b) Consultant may, after compliance with the provisions of Section 7.2, terminate the Agreement upon written notice to the City‘s Contract Officer. Consultant shall be entitled to payment for all work performed up to the date of termination. F-18 01203.0001/835260.1 18 7.9 Attorneys’ Fees. If either party to this Agreement is required to initiate or defend or made a party to any action or proceeding in any way connected with this Agreement, the prevailing party in such action or proceeding, in addition to any other relief which may be granted, whether legal or equitable, shall be entitled to reasonable attorney’s fees. Attorney’s fees shall include attorney’s fees on any appeal, and in addition a party entitled to attorney’s fees shall be entitled to all other reasonable costs for investigating such action, taking depositions and discovery and all other necessary costs the court allows which are incurred in such litigation. All such fees shall be deemed to have accrued on commencement of such action and shall be enforceable whether or not such action is prosecuted to judgment. ARTICLE 8. CITY OFFICERS AND EMPLOYEES: NON-DISCRIMINATION 8.1 Non-liability of City Officers and Employees. No officer or employee of the City shall be personally liable to the Consultant, or any successor in interest, in the event of any default or breach by the City or for any amount which may become due to the Consultant or to its successor, or for breach of any obligation of the terms of this Agreement. 8.2 Conflict of Interest. Consultant covenants that neither it, nor any officer or principal of its firm, has or shall acquire any interest, directly or indirectly, which would conflict in any manner with the interests of City or which would in any way hinder Consultant’s performance of services under this Agreement. Consultant further covenants that in the performance of this Agreement, no person having any such interest shall be employed by it as an officer, employee, agent or subcontractor without the express written consent of the Contract Officer. Consultant agrees to at all times avoid conflicts of interest or the appearance of any conflicts of interest with the interests of City in the performance of this Agreement. No officer or employee of the City shall have any financial interest, direct or indirect, in this Agreement nor shall any such officer or employee participate in any decision relating to the Agreement which affects her/his financial interest or the financial interest of any corporation, partnership or association in which (s)he is, directly or indirectly, interested, in violation of any State statute or regulation. The Consultant warrants that it has not paid or given and will not pay or give any third party any money or other consideration for obtaining this Agreement. 8.3 Covenant Against Discrimination. Consultant covenants that, by and for itself, its heirs, executors, assigns, and all persons claiming under or through them, that there shall be no discrimination against or segregation of, any person or group of persons on account of race, color, creed, religion, sex, gender, sexual orientation, marital status, national origin, ancestry or other protected class in the performance of this Agreement. Consultant shall take affirmative action to insure that applicants are employed and that employees are treated during employment without regard to their race, color, creed, F-19 01203.0001/835260.1 19 religion, sex, gender, sexual orientation, marital status, national origin, ancestry or other protected class. 8.4 Unauthorized Aliens. Consultant hereby promises and agrees to comply with all of the provisions of the Federal Immigration and Nationality Act, 8 U.S.C. § 1101 et seq., as amended, and in connection therewith, shall not employ unauthorized aliens as defined therein. Should Consultant so employ such unauthorized aliens for the performance of work and/or services covered by this Agreement, and should any liability or sanctions be imposed against City for such use of unauthorized aliens, Consultant hereby agrees to and shall reimburse City for the cost of all such liabilities or sanctions imposed, together with any and all costs, including attorneys’ fees, incurred by City. ARTICLE 9. MISCELLANEOUS PROVISIONS 9.1 Notices. Any notice, demand, request, document, consent, approval, or communication either party desires or is required to give to the other party or any other person shall be in writing and either served personally or sent by prepaid, first-class mail, in the case of the City, to the City Manager and to the attention of the Contract Officer (with her/his name and City title), City of Rancho Palos Verdes, 30940 Hawthorne Blvd., Rancho Palos Verdes, California 90275 and in the case of the Consultant, to the person(s) at the address designated on the execution page of this Agreement. Either party may change its address by notifying the other party of the change of address in writing. Notice shall be deemed communicated at the time personally delivered or in 72 (seventy two) hours from the time of mailing if mailed as provided in this section. 9.2 Interpretation. The terms of this Agreement shall be construed in accordance with the meaning of the language used and shall not be construed for or against either party by reason of the authorship of this Agreement or any other rule of construction which might otherwise apply. 9.3 Counterparts. This Agreement may be executed in counterparts, each of which shall be deemed to be an original, and such counterparts shall constitute one and the same instrument. 9.4 Integration; Amendment. This Agreement including the attachments hereto is the entire, complete and exclusive expression of the understanding of the parties. It is understood that there are no oral agreements between the parties hereto affecting this Agreement and this Agreement supersedes and cancels any and all previous negotiations, arrangements, agreements and understandings, if any, between the parties, and none shall be used to interpret this Agreement. No amendment to or modification of this Agreement shall be valid unless made in writing and approved by the Consultant and by F-20 F-21 F-22 01203.0001/835260.1 A-1 EXHIBIT “A” SCOPE OF SERVICES Consultant shall perform the scope of services in accordance with exhibit “E”. F-23 01203.0001/835260.1 B-1 EXHIBIT “B” SPECIAL REQUIREMENTS (Superseding Contract Boilerplate) Added text indicated in bold italics, deleted text indicated in strikethrough. I. Section 1.1, Scope of Services, is amended to read: In compliance with all terms and conditions of this Agreement, the Consultant shall provide those services specified in the “Scope of Services”, as stated in the Proposal, attached hereto as Exhibit “A” and incorporated herein by this reference, which may be referred to herein as the “services” or “work” hereunder. As a material inducement to the City entering into this Agreement, Consultant represents and warrants that it has the qualifications, experience, and facilities necessary to properly perform the services required under this Agreement in a thorough, competent, and professional manner, and is experienced in performing the work and services contemplated herein. Consultant shall at all times faithfully, competently and to the best of its ability, experience and talent, perform all services described herein. Consultant covenants that it shall follow the highest professional standards in performing the work and services required hereunder and that all materials will be both of good quality as well as fit for the purpose intended. For purposes of this Agreement, the phrase “highest professional standards” shall mean those standards of practice recognized by one or more first-class expert-level firms performing similar work under similar circumstances. II. Section 1.2, Consultant’s Proposal, is amended to read: The Scope of Service shall include the Consultant’s Proposal, attached hereto as Exhibit “E” and which shall be incorporated herein by this reference, as though fully set forth herein. In the event of any inconsistency between the terms of such Proposal and this Agreement, the terms of this Agreement shall govern. III. Section 1.4, Compliance with California Labor Law, is amended to add a new Subsection (j), as follows: (j) Registration with DIR. Pursuant to Labor Code section 1771.1, Contractor and all subcontractors must be registered with, and pay an annual fee to, the DIR prior to and during the performance of any work under this Agreement. IV. Section 2.2, Method of Compensation, is amended to read: (a) The method of compensation may include: (i) a lump sum payment upon completion; (ii) payment in accordance with specified tasks or the percentage of completion of the services; (iii) payment for time and materials based upon the Consultant’s rates as specified in the Schedule of Compensation, provided that (a) time estimates are provided for the performance of sub tasks, and (b) the Contract Sum is not exceeded; or (iv) such other methods as may be specified in the Schedule of Compensation. F-24 01203.0001/835260.1 B-2 (b) A retention of 10% shall be held from each payment as a contract retention to be paid as part of the final payment upon satisfactory and timely completion of services. This retention shall not apply for on-call agreements for continuous services or for agreements for scheduled routine maintenance of City property or City facilities. V. Section 2.3, Reimbursable Expenses, is amended to read: Compensation may include reimbursement for actual and necessary expenditures for reproduction costs, telephone expenses, and travel expenses approved by the Contract Officer in advance, or actual subcontractor expenses of an approved subcontractor pursuant to Section 4.5, and only if specified in the Schedule of Compensation. The Contract Sum shall include the attendance of Consultant at all project meetings reasonably deemed necessary by the City. Coordination of the performance of the work with City is a critical component of the services. If Consultant is required to attend additional meetings to facilitate such coordination, Consultant shall not be entitled to any additional compensation beyond the total contract value for attending said meetings, unless approved through a change order. VI. Section 2.4, Invoices, is amended to read: Each month Consultant shall furnish to City an original invoice, using the City template, or in a format acceptable to the City, for all work performed and expenses incurred during the preceding month in a form approved by City’s Director of Finance. By submitting an invoice for payment under this Agreement, Consultant is certifying compliance with all provisions of the Agreement. The invoice shall detail charges for all necessary and actual expenses by the following categories: labor (by sub-category), travel, materials, equipment, supplies, and sub- contractor contracts. Sub-contractor charges shall also be detailed by such categories. Consultant shall not invoice City for any duplicate services performed by more than one person. City shall independently review each invoice submitted by the Consultant to determine whether the work performed and expenses incurred are in compliance with the provisions of this Agreement. Except as to any charges for work performed or expenses incurred by Consultant which are disputed by City, or as provided in Section 7.3, City will use its best efforts to cause Consultant to be paid within 45 (forty-five) days of receipt of Consultant’s correct and undisputed invoice; however, Consultant acknowledges and agrees that due to City warrant run procedures, the City cannot guarantee that payment will occur within this time period , but in no case longer than 90 days from invoice submittal . In the event any charges or expenses are disputed by City, the original invoice shall be returned by City to Consultant for correction and resubmission. Review and payment by City for any invoice provided by the Consultant shall not constitute a waiver of any rights or remedies provided herein or any applicable law. VII. Section 6.3, Ownership of Documents, is amended to read: All drawings, specifications, maps, designs, photographs, studies, surveys, data, notes, computer files, reports, records, documents and other materials (the “documents and materials”) prepared by Consultant, its employees, subcontractors and agents in the performance of this Agreement shall be the property of City (upon payment of any outstanding balances to the Consultant) and shall be delivered to City upon request of the Contract Officer or upon the F-25 01203.0001/835260.1 B-3 termination of this Agreement, and Consultant shall have no claim for further employment or additional compensation as a result of the exercise by City of its full rights of ownership use, reuse, or assignment of the documents and materials hereunder. Any use, reuse or assignment of such completed documents for other projects and/or use of uncompleted documents without specific written authorization by the Consultant will be at the City’s sole risk and without liability to Consultant, and Consultant’s guarantee and warranties shall not extend to such use, reuse or assignment. Consultant may retain copies of such documents for its own use. Consultant shall have the right to use the concepts embodied therein. All subcontractors shall provide for assignment to City of any documents or materials prepared by them, and in the event Consultant fails to secure such assignment, Consultant shall indemnify City for all damages resulting therefrom. Moreover, Consultant with respect to any documents and materials that may qualify as “works made for hire” as defined in 17 U.S.C. § 101, such documents and materials are hereby deemed “works made for hire” for the City. F-26 01203.0001/835260.1 C-1 EXHIBIT “C” SCHEDULE OF COMPENSATION II. Consultant shall perform the following tasks at the rates provided in their fee schedule as part of Exhibit “E”. II. Within the budgeted amounts for each Task, and with the approval of the Contract Officer, funds may be shifted from one Task subbudget to another so long as the Contract Sum is not exceeded per Section 2.1, unless Additional Services are approved per Section 1.9. NOT APPLICABLE III. The City will compensate Consultant for the Services performed upon submission of a valid invoice. Each invoice is to include: A. Line items for all personnel describing the work performed, the number of hours worked, and the hourly rate. B. Line items for all materials and equipment properly charged to the Services. C. Line items for all other approved reimbursable expenses claimed, with supporting documentation. D. Line items for all approved subcontractor labor, supplies, equipment, materials, and travel properly charged to the Services. IV. The total compensation for the Services shall not exceed the Contract Sum as provided in Section 2.1 of this Agreement. V. The Consultant’s billing rates for all personnel are attached as Exhibit C-1. NOT APPLICABLE. F-27 01203.0001/835260.1 D-1 EXHIBIT “D SCHEDULE OF PERFORMANCE I. The Services shall commence following Notice-to-Proceed, and will include the scope of services specified in Exhibit “A”, as the scope of work for the project is developed and related work is authorized by the City II. The Contract Officer may approve extensions for performance of the services in accordance with Section 3.2. Any further extensions require City Council approval. F-28 01203.0001/835260.1 D-2 EXHIBIT “E” CONSULTANT’S PROPOSAL [CONTINUED ON NEXT PAGE] F-29 Portuguese Bend LandslideRemediation Project July 16, 2025 Proposal for: Prepared for:Prepared by: City of Rancho Palos Verdes F-30 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 1 a) Cover Letter July 16, 2025 Ramzi Awwad Public Works Director, City of Rancho Palos Verdes 30940 Hawthorne Blvd., Rancho Palos Verdes, CA 90275 Re: Proposal for Portuguese Bend Landslide Remediation Project Dear Mr. Awwad: In response to the City’s urgent need to stabilize the Portuguese Bend Landslide and safeguard essential infrastructure, Geo- Logic Associates, Inc. (GLA) has assembled a highly qualified team to deliver practical, defensible solutions that meet both the technical and regulatory challenges of this complex project. GLA brings extensive experience in landslide evaluation, dewatering system design, and groundwater infiltration control across California. Our versatile team includes licensed civil engineers, geologists, and environmental specialists who have worked on complex landslide stabilization projects in similar geologic settings. Firm Information Geo-Logic Associates, Inc. 2777 East Guasti Road, Suite 1 (Headquarters) Ontario, CA 91761 | Phone: (909) 626‐2282 GLA is a corporation, currently in good standing in the State of California. Our firm consists of 300 staff in 29 offices in the United States and Peru, including licensed civil engineers, geologists, hydrogeologists, and environmental scientists. Our professionals hold the following licenses to practice in California: PE, GE, PG, CEG, CHG, QISP, QSD, and QSP. DUNS Number: 79-804-2685 Corporate Officers Gary Lass, PG, CEG, CHG Title: Chief Executive Officer Email: garylass@geo-logic.com Phone: (909) 626-2282 Nicole Sweetland, PhD, PG Title: President Email: nsweetland@geo-logic.com Phone: (909) 626-2282 Primary Contact William McCormick, PG, CEG, Principal Engineering Geologist Phone: (707) 953-1837 | Email: bmccormick@geo-logic.com We understand the critical timeline and federal compliance requirements associated with this project. Our approach emphasizes responsiveness, quality control, and practical, buildable design documents that meet the City’s expectations and regulatory obligations. We look forward to the opportunity to continue to support the City in this vital effort and if you have any questions or need additional information, please contact Mr. McCormick at bmccormick@geo-logic.com. Sincerely, GEOLOGIC ASSOCIATES, INC. John Hower, PG, CEG William V. McCormick, PG, CEG Senior Vice President Principal Engineering Geologist F-31 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 2 b) Approach to Scope of Services The following approach outlines our detailed methodology for delivering the City’s required scope of services in a clear, phased, and efficient manner. Our team’s strategy emphasizes technical rigor, proactive coordination, federal funding compliance, and constructible, resilient solutions that directly support the City’s goal of achieving long-term landslide stabilization. 1. Studies, Investigations, Computer Models, and Reports: GLA will build on prior studies by refining the existing geotechnical model using updated field investigations, groundwater monitoring data, and slope movement records. We will perform targeted investigations to evaluate the current groundwater regime, identify remaining data gaps, and calibrate slope stability models using finite element or limit-equilibrium methods. Our approach prioritizes addressing the root cause of instability through refined groundwater characterization and design-driven geotechnical modeling. 2. Construction Drawings, Specifications, and Documents: Our engineering team will develop a complete, constructible, and agency-compliant set of plans and specifications. We will incorporate utility conflict avoidance, erosion control, traffic management, and logistical phasing strategies. All drawings will be prepared and stamped by California-licensed engineers and surveyors, reviewed by our internal QA/QC team, and delivered in both PDF and native formats. Plans will be developed in progressive milestones (60%, 90%, Final) to enable iterative review and refinement. 3. Cost Estimate: A detailed, itemized cost estimate will be prepared in line with current market rates and recent bid data for similar projects and it will include contingencies, soft costs, and unit pricing broken down by bid item and construction phase; submit to City staff for review and approval. 4. Schedule Management: GLA will develop detailed project schedule at start of project using critical path method; regularly update schedule, assess risks, and develop mitigation strategies for any delays. GLA will utilize MS Project software (or similar). 5. City Council Staff Report and Presentation: We will prepare a clear and visually supported presentation for City Council, along with a staff report that aligns with City formatting and content standards. We will rehearse presentation materials with City staff to ensure alignment with community messaging and project goals. 6. Environmental Compliance Documents: GLA and our subconsultant LSA will prepare all documentation required to support third-party NEPA and historic preservation reviews in accordance with federal funding guidelines and will coordinate closely with the City and funding agencies to ensure all requirements are fully addressed. 7. Utility and Agency Coordination: GLA and our subconsultant VELA Engineering, will review construction plans and specifications, identify potential utility conflicts, coordinate with utility companies, and prepare and submit relocation or adjustment documents as necessary. 8. Property Acquisitions and Easements: GLA and our subconsultant Epic Land Solutions, will complete a review of final plans and specifications to assess whether proposed improvements may extend onto adjacent properties/public rights-of- way, and if property acquisition or easements are required; we will delineate such needs graphically. We will coordinate with City, legal advisors, and property owners (if applicable) to understand legal implications of acquiring property or easements and whether existing easements can be leveraged. A boundary survey in support of easement acquisitions if necessary and create legal descriptions and exhibits for said acquisitions. 9. Permitting: GLA will develop a comprehensive permitting matrix identifying agency requirements and timelines. We will identify, prepare and submit needed permit applications to local/state/federal agencies. 10. Construction Procurement: Our team will prepare the Notice Inviting Bids using finalized construction drawings, bid documents, the City’s standard forms, and contract templates. We will conduct a pre-bid conference, respond to Requests for Information, participate in the bid opening, and evaluate bids for responsiveness, completeness, project understanding, and bid amount. A memo documenting the award recommendation will be prepared, and upon review and concurrence by City staff, GLA will draft the City Council Staff Report. Additionally, we will prepare and present recommendations to the City Council for awarding the construction contract. 11. Administration and Coordination: We will maintain weekly progress meetings and repare status updates to City staff, including activity summaries, budget tracking, and schedule or other agreed upon time interval performance to ensure transparency, responsiveness, and the ability to resolve issues in real time. PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 3 c) Organization and Staffing GLA has carefully selected a team of professionals with the expertise necessary to perform all of the required services, as depicted in the organizational chart below. Our proposed Project Manager, Mr. William McCormick, PG, CEG, brings more than 39 years of technical and project management experience in complex geotechnical investigations and landslide remediation projects throughout California and he will be the primary contact person responsible for the overall delivery of the project. Mr. McCormck and key staff will remain assigned to this project through completion of the Scope of Services and any changes to key staff will be reported and submitted for approval of the City. The qualifications and availability of our key team members are summarized in the table below. GLA has the staff and resources available to meet the City’s needs. F-33 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 4 Team Member / Role / Availability Similar Experience William McCormick, PG, CEG Project Manager and Geologic and Geotechnical Analysis Task Manager 75% (All Tasks) »Emergency Design for the Portuguese Bend Landslide Remediation Project and Winterization »Geologic/Hydrogeologic Characterization and Dewatering Design for the Portuguese Bend Landslide Project »On-Call Geotechnical Services for Marin County and Sonoma County Public Works Departments, California Gary Lass, PG, CHG, CEG Principal-in-Charge 100% Support As Needed »Final Design for the Portuguese Bend Landslide Remediation Project »Hydrology and Hydraulic Study for 923 acres for Sunshine Canyon Landfill »Feasibility Study for the Portuguese Bend Landslide Remediation Project Courtney A. Barrett, PE,, QSD, QISP Civil Design Task Manager 75% (Task 1, 2, 3, 4, 5, 10) »Hydrology Analysis and Civil Design Portuguese Bend Landslide »Design and Construction Management Services for the Sunshine Canyon Landfill, Sylmar, California »Design Services for the Newby Island Landfill, Milpitas, California Subconsultants LSA Environmental Support (Task 6) »Environmental Assessment, Monitoring and Reporting for Portuguese Bend Mitigation, Design, Well-Drilling, and Winterization Implementation Epic Land Solutions Property Acquisition (Task 8) »Eminent Domain Property Acquisition for I-710 Corridor Project EIR including locations at LA County Sanitation Districts’ Long Beach Main Pumping Plant Evolution Mapping Surveying (Task 2, 8) »Regional Hydraulic Study for San Bernardino County Green-tech Compost Facility teamed with GLA »Surveying complex coastal landslide sites such as Portuguese Bend F-34 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 5 d) Staff Qualifications and Experience BRIEF FIRM HISTORY AND PRIOR EXPERIENCE GLA is an employee-owned multi-disciplinary civil, environmental, geologic, and geotechnical consulting firm established in 1991. GLA employs over 350 professionals located throughout 29 U.S. office locations as well as an office in Lima, Peru. To meet the City’s goals for landslide stabilization, Geo-Logic Associates (GLA) has assembled a multidisciplinary team of engineers, geologists, and environmental specialists with direct experience in geotechnical investigations, groundwater and surface water interaction, slope stabilization design, and federally funded infrastructure projects. Our staff have successfully delivered projects involving landslide mitigation, dewatering system design, slope modeling, drainage and utility design, environmental documentation, and construction support for public agencies across California. Our team’s qualifications include extensive experience with slope stability analysis, hydrologic and hydraulic modeling, drainage and erosion control design, permit and utility coordination, and preparation of construction-ready plans and specifications. We routinely manage projects from investigation through design and construction, ensuring integration across disciplines and delivering solutions that are practical, cost-effective, and resilient to changing site conditions and climate extremes. Our staff also have extensive experience in the planning, computer modeling, design, and construction phases of open and closed conduit drainage channels, grading and drainage improvements, sediment control and transport, open and closed channel hydraulics and hydrology, site paving and roadway plans, and public and private utilities. GLA has provided the City with professional hydrogeologic and geotechnical consulting services for the Landslide Complex since 2017, and developed preliminary mitigation plans, and technical specifications for its mitigation. In 2018, GLA was selected to complete a feasibility study (FS) for the City and completed a watershed model in 2019. The FS was widely circulated, and internally and externally peer reviewed. It showed that: • The basal failure surface(s) that formed over an extended period of time is an effective hydraulic barrier; • The predominant cause of landsliding within the Landslide Complex is artesian pressure that acts on the basal failure surface throughout the geometry of the slide; • One of the main contributors to the development of artesian pressure is surface water infiltration from canyons and ravines that are at higher elevations; • Seepage within the Landslide Complex sliding mass caused by infiltration of surface water through onsite cracks, onsite ravines, and infiltration caused by irrigation, and through influx from leaky septic systems, are secondary sources of instability; • The Landslide Complex is broken into multiple blocks, with relative movements affected; and • The 2019 watershed model identified critical areas where stormwater was ponding and infiltrating into the landslide area. Following the acceptance of the FS and watershed model in 2019, GLA completed the preliminary mitigation design which called for: (i) management of groundwater that is the source of artesian pressure; (ii) relief of residual artesian pressure at the toe of the slide; within the entire Landslide Complex; and (iii) infilling of cracks and improvement of surface drainage to minimize seepage into the landslide mass. The first two items will be addressed by installation of deep dewatering wells and horizontal/directional drains, where appropriate, generally outside of the landslide footprint and below the basal failure surface (so they do not get sheared off as the slide moves). F-35 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 6 In 2023, GLA was selected to provide the final Landslide Mitigation, Exploration, Dewatering and Winterization Design. Work on this project includes siting deep exploratory boreholes, daily slope monitoring and strategic planning for more permanent stabilization techniques. In the process, GLA has developed a keen awareness of the City’s and local needs, as well as state and local standards and procedures. Our recent work has further refined the complex nature of the landslide complex, especially in the PBL where a deeper landslide was discovered that had never historically failed before. This success is founded on the principles of ensuring that our work is conducted to a high professional standard, our work product is technically defensible, our clients’ best interests inform our decisions, and our services are provided cost effectively. The long-term working relationships we have with our clients is a testament to the effectiveness of this approach. GLA staff have a history of providing hydrogeological and hydraulic services to the City , and as a result, we have an unparalleled familiarity with site geologic and hydrogeologic conditions. The City and others have largely characterized the geologic, hydrologic, hydrogeologic, and geotechnical conditions that drive regional slope failure and have implemented some preliminary mitigation measures. However, now the City is undertaking a focused effort to meet the following objectives: • Long-term stabilization of the landslide complex • Repair and upgrade related infrastructure • Compliance with applicable federal, state, and local environmental laws and regulations GLA will work closely with the City to utilize the results of the numerous prior and ongoing geologic studies and engineering evaluations. This project will provide a comprehensive and coordinated approach to controlling stormwater runoff and mitigating infiltration at the source. Portions of our civil design, especially surface water management and drainage improvements will rely on the final results of the hydrologic/hydraulic study that is being commissioned by the City with Geosyntec*. Our team will utilize industry-leading tools and expertise to deliver high-quality plans that meet regulatory standards and support the City’s sustainability goals. We look forward to working with the City to implement this critical program. STAFF QUALIFICATIONS The resumes for key staff are presented in the following pages. *Note: Our study does not include hydrologic analysis since a comprehensive study is being independently done by others F-36 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 7 Project Manager and Geotechnical and Geological Analysis Task Manager: William McCormick, PG, CEG William McCormick, PG, CEG Principal Engineering Geologist Mr. McCormick has over 39 years of technical experience and in contract and project management of major geotechnical investigations and material testing and inspection projects in the Northern California. He is an experienced project manager with long-term on-call projects for multiple Sonoma County Departments, the Counties of Napa and Marin, and the City of Santa Rosa, to name a few. His technical expertise includes landslide evaluation, mitigation design and construction observation and management of landslide repairs, Alquist-Priolo Earthquake Fault Zone evaluation studies, geologic and geomorphic mapping and exploration, site feasibility and geotechnical design studies for infrastructure including roadways, highways, bridges and alignment studies, civil developments, park sites, geotechnical evaluations involving erosion, drainage, slope stability, engineering geology, retaining walls, soil nail walls, earth dams, forensic studies, distressed properties, expert witness testimony, construction monitoring for engineering geologic/geotechnical mitigation projects, construction management, and peer review of geologic, geotechnical and fault studies. Mr. McCormick has performed geologic, fault, and geotechnical peer review services for numerous entities including Sonoma County, Mendocino County, City of Santa Rosa and the City of Concord. Mr. McCormick has also presented on engineering geologic topics throughout the US as well as in China, Australia, New Zealand, Italy, England and Scotland. Landslide Mitigation,Exploration, Dewatering and Winterization Design, Portuguese Bend Landslide Complex, Rancho Palos Verdes, California Project Geologist. The Portuguese Bend Landslide Complex (PBLC), located along the Pacific Coast in the scenic City of Rancho Palos Verdes (City), is among the most recognizable landslide features in California. The massive landslide encompasses approximately 239 acres and 38 million cubic yards of sliding mass, with lateral dimensions approximately 0.9 miles x 0.8 miles. Ground movement rates vary widely across the site but have been measured recently to be as much as 11 feet per year near the landslide’s toe at the coast. Mr. McCormick is lead geologist in geologic data assessment to develop a working geologic model across the entire, newly re- activated Altamira Landslide. Work includes siting deep explorations, daily piezometric and slope monitoring and strategic planning for ore permanent stabilization techniques. Mr. McCormick was also key in assisting with winterization design recommendations and designs intended to reduce surface water infiltration deep into the landslide complex across canyons and highly fissured ground. Mr. McCormick has a deep understanding of the surface and subsurface hydrologic conditions affecting the part of Rancho Palos Verdes and adjacent environments. On-Call Geotechnical Services, Marin County Public Works Department, Marin County, and Sonoma County Public Infrastructure, Sonoma County, California Served as Contract Manager for an on-call geotechnical services contract for the last 15 years for Marin County and the last 25 years for Sonoma County. Services included geotechnical assessment, design and construction services for two major storm drains, four pump stations, numerous creek and levee stabilization projects, and numerous landslides and roadway repair projects, including retaining wall design. Many of these projects were located in areas of highly compressible soil, unstable slopes, large slides, or liquefiable soil conditions. EDUCATION MS, Geology, 1986 San Diego State University BS, Geology, 1983 San Diego State University PROFESSIONAL REGISTRATIONS Professional Geologist, CA, No. 5022 Certified Engineering Geologist, CA, No. 1673 CERTIFICATIONS Loss Prevention System Safety Training PROFESSIONAL AFFILIATIONS 2023 Recipient of “Honorary Member Status” of Association of Environmental and Engineering Geologists (AEG) F-37 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 8 Principal In Charge: Gary L. Lass, PG, CEG, CHG Gary L. Lass, PG, CEG, CHG Chief Executive Officer Mr. Lass has more than 40 years of experience providing successful geological, environmental, geotechnical, and hydrogeologic services throughout the Western United States and Mexico. He has acted as Principal-in-Charge, and/or Project Manager for geologic and hydrogeologic characterizations for Remedial Investigations (RIs), Feasibility Studies (FSs), Remedial Action Plans (RAPs), Evaluation Monitoring Programs (EMPs), Engineering Feasibility Studies (EFS), Corrective Action Programs (CAPs), groundwater monitoring and reporting programs, and site closures. Mr. Lass has extensive experience with all aspects of landfill siting, expansion, design, permitting, construction, operations, monitoring and closure and is a specialist in CCR Title 27 compliance, having acted as Principal-in-Charge, and/or Project Manager for geotechnical, geologic and/or hydrogeologic characterizations projects at hundreds of landfill sites throughout the western United States. Hydrology and Hydraulics Assessment for Pre- and Post-Development Conditions of a Major Improvement Project Sunshine Canyon Landfill, Los Angeles County, CA Principal-in-charge for this comprehensive hydrology and hydraulics study within an approximately 923-acre watershed area to assess the impact of proposed entrance improvements on downstream regional flood control facilities and to evaluate the adequacy of proposed on-site drainage improvements. Hydrology and Hydraulics Assessment for Composting Facility, San Bernardino County, CA Principal-in-charge for this hydrology and hydraulics analysis for a 1,400-acre watershed area tributary to the project site. The analysis considered off-site run-on and proposed on-site improvements. Portuguese Bend Landslide Complex, Rancho Palos Verdes, California - Landslide Mitigation Design and the Feasibility Study. Principal-in-Charge of the Portuguese Bend Landslide Complex (PBLC), located along the Pacific Coast in the scenic City of Rancho Palos Verdes (City), is among the most recognizable landslide features in California. The massive landslide encompasses approximately 239 acres and 38 million cubic yards of sliding mass, with lateral dimensions approximately 0.9 miles x 0.8 miles. Ground movement rates vary widely across the site but have been measured recently to be as much as 11 feet per year near the landslide’s toe at the coast. Projects includes landslide mitigation design as well as a 2018 Feasibility Study. Key design components included innovative engineering approaches for surface water using environmentally-friendly-lined swales and for relief or artesian pressure by directional drains. The preliminary project design report was accepted by a unanimous vote of the City Council. EDUCATION Master of Science, Geochemistry, 1978 California State University, Los Angeles Bachelor of Science, Geology, 1974 California State University, Los Angeles PROFESSIONAL REGISTRATIONS Registered Geologist, California, No. 3653 Certified Engineering Geologist, California, No. 1093 Certified Hydrogeologist, California, No. 18 Certified Engineering Geologist, Oregon, No. E1577 Registered Geologist, Arizona, No. 28820 F-38 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 9 Civil Engineer Task Manager: Courtney A. Barrett, PE, QSD, QISP Courtney A. Barrett, PE, QSD, QISP Senior Engineer III Ms. Barrett is a Registered Civil Engineer with over 21 years of experience in engineering. Her experience includes preparation of grading and drainage plans, liner design, design of erosion control best management practices, preparation of technical specifications, engineer’s estimates, and providing construction quality assurance and construction support services on a variety of landfill projects. She has been the CQA Officer for cell development, landfill closure, storm drain installation, and landfill gas well installation projects at various sites in California and has worked with a variety of public agencies to design capital improvement projects, prepare specifications and cost estimates, provide engineering and permitting oversight, and related duties. Portuguese Bend Landslide Remediation Phase I Design, Rancho Palos Verdes, California Project Engineer for mitigation plans and hydrology part of the Phase I services to develop remedial design for the Portuguese Bend Landslide Complex located along the Pacific Coast in the scenic City of Rancho Palos Verdes (City). Work included revision of hydrology and hydraulics calculations, validation and calibration of the slope stability model, engineering evaluations, design support and development of planning and irrigation plans. develop construction plans and specifications, develop cost estimates, and support construction logistics. Design and Construction Management Services for the Sunshine Canyon Landfill, Republic Services, Inc., Sylmar, California Project Manager, design engineer and resident engineer for the design and construction of City/County Cell – 4 (CC-4) Part 1, CC-4 Part 2A, CC-4 Part 3, CC-4 Part 4A, 4B, & 4C, CC-5A, CC-3B Part 2, West Drainage Channel Phase II, drainage components of the Ultimate Entrance road, and the relocation of the Southern California Edison Transmission power poles around the perimeter of the landfill and the CQA Engineer for CC-4 Part 4A, 4B, & 4C, and CC-5A. Project work at the site includes development of construction drawings, CQA Manual, and technical specifications. Design components included grading, drainage channels, sump and pump, and geosynthetic liner system. Work also includes onsite resident engineering services including pre-bid activities, onsite construction oversite, field design changes, response to contractor questions, and tracking construction schedules and project costs. Design Services for the Newby Island Landfill, Republic Services, Inc., Milpitas, California Design Engineer responsible for the preparation of the Overliner Units 1, 2, and 3 design. Development of the design report, construction drawings, CQA Manual, and technical specifications. Design components included grading, leachate sump and force main, and geosynthetic liner system. EDUCATION Bachelor of Science, Civil Engineering, 2003 University of California, Davis PROFESSIONAL REGISTRATIONS Arizona Professional Engineer, No. 55166 California Professional Engineer, No. 78076 Hawaii Professional Engineer, No. PE-15661 New Mexico Professional Engineer, No. 21872 Nevada Professional Engineer, No. 022633 Oregon Professional Engineer, No. 88426PE Utah Professional Engineer, No. 8746089-2202 PROFESSIONAL Certifications California Qualified Industrial SWPPP Practitioner, No 78076 California Qualified SWPPP Practitioner, No 22227 California Qualified SWPPP Developer, No 78076 F-39 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 10 REFERENCE PROJECTS Portuguese Bend Landslide Feasibility Study and Hydrologic Model Rancho Palos Verdes, California geo-logic.com Page 1 ` Feasibility Study and Hydrologic Model Daniel B. Stephens and Associates, Inc. (DBS&A), a subsidiary of Geo-Logic Associates, Inc., assisted city staff in their preparation for an anticipated federal infrastructure plan expected in 2017 to provide funds for landslide abatement. Part of this effort was to review and update an existing engineering feasibility study (FS) prepared by the U.S. Army Corps of Engineers (USACE) in 2000. The USACE FS only proposed a coastal dike in an effort to stabilize coastal erosion, however, the landslide itself was not directly addressed. DBS&A commenced a thorough compilation and review of all available historical work on the Portuguese Bend landslide, adjacent area landslides including Abalone Cove, Klondike Canyon, and the larger Altamira Complex. This review resulted in the compilation of nearly 100 GB of historical files in electronic format that had not been organized before. In addition, DBS&A completed a systematic and through review of the historical data, reports, studies, engineering work, and research along with available public scientific literature to characterize the landslide geology, hydrogeology, groundwater occurrence, recharge, past mitigation efforts, and past successes and failures. The comprehensive review formed the basis of an updated hydrogeologic conceptual site model that was used to prepare a new engineering feasibility study in 2018 to evaluate and present available options for landslide abatement including groundwater extraction wells, horizontal drains (hydraugers), and stormwater control. A watershed model was prepared to quantify groundwater recharge components including rainfall and irrigation. Areas of critical stormwater ponding and infiltration were identified. The FS included geotechnical modeling and conceptual-level cost estimates for groundwater extraction wells, hydraugers, fracture-sealing, stormwater control, and a partial centralized sanitary sewer to replace some septic systems in the area. DBSA directed and participated in several city council meetings to present the draft FS options, receive public stakeholder comments, and incorporate the comments into a final FS report. The final FS outlined the primary components of subsequent work elements completed by the City from 2019 to present. Client City of Rancho Palos Verdes, California Contact Elias Sassoon Ara Mihranian Doug Wilmore (310) 544-5252 Timeframe 2017-2019 Contract Amount $202,840 Personnel John J. Dodge, PG, CHG (Project Manager) Gregory Schnaar, PhD, PG (VA) • Collaboration with City staff • Comprehensive historical document and data compilation and review • Hydrogeologic conceptual site model • Watershed and geotechnical modeling • Stormwater flow path characterization • Quantification of stormwater infiltration and groundwater recharge • Engineering options for stormwater control and landslide abatement • Conceptual cost estimates • Collaboration with Palos Verdes Peninsula Land Conservancy • City Council meetings and public stakeholder review F-40 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 11 Portuguese Bend Landslide Rancho Palos Verdes, California geo-logic.com Page 1 ` The Portuguese Bend Landslide (PBL), located along the Pacific Coast in the City of Rancho Palos Verdes (City), is among the most recognizable landslide features in California and the fastest-moving landslide in the United States. This massive landslide encompasses approximately 239 acres and 38 million cubic yards, with lateral dimensions of approximately 0.9 miles by 0.8 miles. Ground movement rates vary widely across the site but have been recently measured to be as much as 11 feet per year near the landslide’s toe at the coast. In 2018, GLA prepared a feasibility study for the City’s use in developing and comparing options to mitigate the ongoing landslide movement. Subsequently, the City commissioned GLA to develop a mitigation design to the permit level. Key components of GLA’s mitigation design included innovative engineering approaches for surface water control using geosynthetic-lined swales and for artesian groundwater pressure relief using directionally installed drains. To design surface water management features, GLA performed a hydrologic analysis to calculate the estimated design flows for a 100-year, 24-hour design storm event using the methodology outlined in the Los Angeles County Department of Public Works Hydrology Manual. The hydrologic parameters were then applied in hydraulic calculations to design the proposed engineered swales, culvert pipes, and a flow reduction area included in the mitigation design package. GLA also supported the City in characterizing new, larger landslide movement and developing emergency mitigation measures to reduce land movement and addressing the concerns of residents, the City Council, and the Palos Verdes Peninsula Land Conservancy. GLA delivered three project briefings to the public on the City’s behalf, and GLA’s original design report was accepted by a unanimous vote of the City Council. Client City of Rancho Palos Verdes, California Contact Ron Dragoo, PE, Principal Engineer Department of Public Works (310) 544-5250 Timeframe 2019-Present Contract Amount $580,000 Personnel William McCormick, PG Neven Matasovic, Ph.D, CEG, PE, GE Alan Witthoeft, PE, GE Mark Vincent, PG, CEG, CHG Caleb Miller, PE Gary Lass, PG, CEG, CHG • Landslide mitigation • Deep dewatering well design and monitoring • 3D slope stability modelling • 3D seepage finite element modelling • Surface water control design • Surface water control design • Permit-level plan and specification development • Community outreach and City Council meetings • Interface with Land Conservancy • Geosynthetics design • Hydrology and hydraulics evaluation • Horizontal and directional drain design • Fracture infill design • Order-of-magnitude cost estimate • Winterization design F-41 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 12 Sonoma County 2025 Landslide Road Damage Sonoma County, California geo-logic.com Page 1 ` GLA is continuing a geologic and geotechnical assessment and mitigation design services for six recent roadway/landslide projects in the County. GLA personnel have been provide geotechnical and design services for the County for over 25 consecutive years. GLA (as Prime) conducted project management, geologic, and geotechnical investigations; provided geotechnical design criteria; assembled a team of survey, civil, and structural engineers; and provided the County with plans and specs for retaining walls, sheet pile wall and rip-rap slope stabilization repairs. GLA completed the projects in accordance with the government reimbursement schedule and allowed projects to be set out to bid in record time (months instead of years). GLA personnel are also providing construction observation and inspection for key elements to ensure conformance to the plans. Client Sonoma County Public Infrastructure Department, California Contact Johannes Hoevertsz johannes.hoevertsz@sonoma-county.org (707) 556-2231 Timeframe 2024-Present Contract Amount $600,000 Personnel William McCormick, PG, CEG Mohsen Mahdavi, Ph.D, PE, GE Fouad Mina, PE Jarot Tamba Project Highligts: • Emergency Response and • Relative Risk Assessments • Prime Consultant to assemble • Design Team • Rapid Geotechnical • Investaigation and • Characterization • Civil and Structural Plan and • Specifications • Construction Consultation, • Observation and Testing F-42 PROPOSAL: GREATER PORTUGUESE BEND LANDSLIDE COMPLEX/ANCIENT ALTAMIRA LANDSLIDE COMPLEX DRAINAGE STUDY CITY OF RANCHO PALOS VERDES www.geo-logic.com 13 e) Project Schedule The following critical-path-method schedule outlines the major tasks, sub-tasks, deliverables, and interim milestones required to complete the Scope of Work in accordance with the City’s objectives and timeline. ID Task Name Duration Start Finish 1 SSttuuddiieess aanndd GGeeootteecchhnniiccaall AAnnaallyyssii ss 58 days Wed 8/6/25 Fri 10/24/25 2 DDrraafftt RReeppoo rrtt 34 days Wed 8/6/25 Mon 9/22/25 3 CCiittyy RRee vvii eeww 11 days Mon 9/22/25 Mon 10/6/25 4 FF iinnaall RReeppoorrtt 15 days Mon 10/6/25 Fri 10/24/25 5 PPllaannss aanndd SSppeecciiffiiccaattiioonnss 128 days Wed 8/6/25 Fri 1/30/26 6 TTooppooggrraapphhii cc SSuurrvveeyy aanndd 6600%% PPllaannss43 days Wed 8/6/25 Fri 10/3/25 7 CCiittyy RRee vvii eeww 11 days Fri 10/3/25 Fri 10/17/25 8 9900%% PPllaannss 46 days Fri 10/17/25 Fri 12/19/25 9 CCiittyy RRee vvii eeww 24 days Tue 12/9/25 Fri 1/9/26 10 110000%% PPllaannss 16 days Fri 1/9/26 Fri 1/30/26 11 SSttaaffff RReeppoo rrtt 32 days Fri 10/17/25 Mon 12/1/25 12 DDrraafftt 22 days Fri 10/17/25 Mon 11/17/25 13 FF iinnaall 11 days Mon 11/17/25Mon 12/1/25 14 EEnnvviirroonnmmeennttaall DD ooccuummeenntt ss 128 days Wed 8/6/25 Fri 1/30/26 15 6600%%53 days Wed 8/6/25 Fri 10/17/25 16 9900%%46 days Fri 10/17/25 Fri 12/19/25 17 FF iinnaall 31 days Fri 12/19/25 Fri 1/30/26 18 UUttiill iittyy aanndd AAggeenncc yy CCoooorrddiinnaattiioonn 98 days Wed 8/6/25 Fri 12/19/25 19 DDrraafftt 48 days Wed 8/6/25 Fri 10/10/25 20 FF iinnaall 51 days Fri 10/10/25 Fri 12/19/25 21 PPrrooppeerrttyy AAqquuiissii ttiioo nn aanndd EEeeaasseemmeenntt ss 85 days Mon 9/22/25Fri 1/16/26 22 6600%%31 days Mon 9/22/25 Mon 11/3/25 23 9900%%35 days Mon 11/3/25 Fri 12/19/25 24 FF iinnaall 21 days Fri 12/19/25 Fri 1/16/26 25 PPee rrmmiitt DD ooccuummeennttss 128 days Wed 8/6/25 Fri 1/30/26 26 DDrraafftt 58 days Wed 8/6/25 Fri 10/24/25 27 FF iinnaall 71 days Fri 10/24/25 Fri 1/30/26 28 CCoonnssttrruuccttiioonn PPrrooccuurreemmeenntt 86 days Fri 12/19/25 Fri 4/17/26 29 DDrraafftt 46 days Fri 12/19/25 Fri 2/20/26 30 FF iinnaall 41 days Fri 2/20/26 Fri 4/17/26 31 AAddmmiinniissttrraattii oonn aanndd CCoooorrddii nnaattiioonn 183 days Wed 8/6/25 Fri 4/17/26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12Aug '25 Sep '25 Oct '25 Nov '25 Dec '25 Jan '26 Feb '26 Mar '26 Apr '26 Milestone Summary Project Summary Manual Task Manual Summary Proposed Schedule - Portuguese Bend Landslide Remediation Project Page 1 Project: Proposed Schedule Portuguese Bend Landslide Remediation ProjectDate: Wed 7/16/25 F-43 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 14 f) Quality Control Plan When GLA starts a new project, we identify the reviewer(s) for each task and assign a senior professional to do coordination review. Overall quality assurance for this contract will be the responsibility of the Project Manager, William McCormick, CEG. GLA will prepare all technical documents and plans with review and approval by appropriately licensed professionals, and engineering drawings and specifications will be sealed by a California registered professional engineer. We will conduct routine quality control reviews to verify that all project deliverables and supporting documents are complete, understandable, conform to standards, and meet City’s expectations. GLA maintains a reputation for preparing high-quality technical reports. A careful process of document production maintains our high standard. This process includes reviews for technical accuracy by a technical manager familiar with the project goals and objectives; a complete editorial review that ensures logical sequence of ideas and clear, concise writing; and a final quality assurance check by the project manager prior to submission to a client. Our team knows the importance of providing high-quality final deliverables that thoroughly address all applicable requirements. Report and plan preparation typically involves development of a draft (or 60%, 90%, and 100% submittal for plans) for client review and comment, and completion of a final draft with client input and approval. All GLA deliverables are reviewed in accordance with GLA’s Quality Assurance Manual (QAM) to ensure a high-quality end product. GLA employs a full- time production team responsible for conducting final editorial reviews and production of all documents. This ensures quality, accuracy, compliance, and completeness of reports prepared by GLA. Reports are delivered according to need or preference in hard-copy and/or electronic format. GLA has an accounting team that assists with contract review, invoice production, review, and submittal. Our contract specialists review all contract requirements and consistently follow specific invoicing procedures in our Deltek Vision accounting system when each project is opened, ensuring consistency and accuracy on all of our invoices. Utilizing this system, we are able to produce draft and final invoices that include all back-up documentation as required. Draft invoices are provided to the PM for review and approval. Once approved, invoices are submitted to the correct financial contact and to the PM as requested. Monitoring Quality of Subcontractor Work Project teams that include multiple subcontractors add value to projects by enabling personnel from specialized backgrounds and varying disciplines to work together to produce the best solution. However, multiple team members also means added complexity and increased need for oversight. GLA understands our role and, as the prime, we will ensure that our subcontractors provide the same level of quality that we expect from our staff. To ensure that the quality of subcontractor work is carefully monitored, GLA adheres to the following oversight procedures: • Regular communication with all subcontractors • Quality assurance and data review/audit of work performed by subcontractors • All reports and documentation prepared by subcontractors are subject to GLA’s internal review and production process prior to submission to the client g) Accepance of Conditions GLA has reviewed the sample professional services agreement and is proposing that the City consider incorporating the following revisions to the contract. 6.3 Ownership of Documents. After Consultant has been paid for the services generating its work product, all drawings, specifications, maps, designs, photographs, studies, surveys, data, notes, computer files, reports, records, documents and other materials (the “documents and materials”) prepared by Consultant, its employees, subcontractors and agents in the performance of this Agreement shall be the property of City and shall be delivered to City upon request of the Contract Officer or upon the termination of this Agreement, and Consultant shall have no claim for further employment or additional compensation as a result of the exercise by City of its full rights of ownership use, reuse, or assignment of the documents and materials hereunder. Any use, reuse or F-44 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 15 assignment of such completed documents for other projects and/or use of uncompleted documents without specific written authorization by the Consultant will be at the City’s sole risk and without liability to Consultant, and Consultant’s guarantee and warranties shall not extend to such use, reuse or assignment. Consultant may retain copies of such documents for its own use. Consultant shall have the right to use the concepts embodied therein. All subcontractors shall provide for assignment to City of any documents or materials prepared by them, and in the event Consultant fails to secure such assignment, Consultant shall indemnify City for all damages resulting therefrom. Moreover, Consultant with respect to any documents and materials that may qualify as “works made for hire” as defined in 17 U.S.C. § 101, such documents and materials are hereby deemed “works made for hire” for the City. h) Fees and Cost Estimate All work performed under thsi contract will be on a time and materials basis, in accordance with our 2025 Standard Fee Schedule (attached). As per our Standard Fee Schedule, any outside and subcontrated services will be billed on a cost + 15% basis. Our estimated costs for this project is broken down by tasks and is presented below. Task Description Amount (USD) Task 1 Studies, Investigations, Computer Models, and Report $87,200 1A Study, Analysis, and Reports $55,000 1B New Topographic Survey $32,200 Task 2 Plans and Specifications $155,000 2A 60% Design $95,000 2B 90% Design $45,000 2C 100% Design $15,000 Task 3 Cost Estimate $7,500 Task 4 Schedule $5,000 Task 5 Staff Report/Presentation $5,000 Task 6 Environmental Compliance $142,485 6A 60%$33,810 6B 90% $103,730 6C 100% $4,945 Task 7 Utility and Agency Coordination $8,500 Task 8 Property Aquisition and Eeasements TBD Task 9 Permit Documents $10,000 Task 10 Construction Procurement $15,000 Task 11 Administration and Coordination $25,000 ESTIMATED TOTAL $460,685 F-45 Schedule 2025 SoCal Effective Through 12/31/2025 2025 FEE SCHEDULE PROFESSIONAL STAFF Staff Professional I ....................................................................................................... $1 46.00/Hour Staff Professional II ........................................................................................................ 165.00/Hour Staff Professional III ....................................................................................................... 181.00/Hour Project Professional I ..................................................................................................... 19 3.00/Hour Project Professional II .................................................................................................... 21 6.00/Hour Project Professional III ................................................................................................... 23 3.00/Hour Senior Professional I ...................................................................................................... 24 0.00/Hour Senior Professional II ..................................................................................................... 25 8.00/Hour Senior Professional III .................................................................................................... 27 5.00/Hour Principal Professional I .................................................................................................. 287 .00/Hour Principal Professional II ................................................................................................. 312 .00/Hour Principal Professional III ................................................................................................ 340 .00/Hour Court Appearance (Expert Witness, Deposition, etc.; four-hour minimum) ............ 2 x HourlyRate FIELD/LABORATORY STAFF Technician I .................................................................................................................... 105.00/Hour Technician II ................................................................................................................... 126.00/Hour Technician III (or Minimum Prevailing Wage) ............................................................... 143.00/Hour Technician IV ................................................................................................................. 158.00/Hour Laboratory Manager ...................................................................................................... 190.0 0/Hour Principal Technician ....................................................................................................... 21 3.00/Hour Managing Technician ..................................................................................................... 190.0 0/Hour CADD/GIS CADD/GIS/Database Manager I ..................................................................................... 126.00/Hour CADD/GIS/Database Manager II .................................................................................... 149.00/Hour CADD Designer .............................................................................................................. 16 5.00/Hour GIS Specialist.................................................................................................................. 165.00/Hour SUPPORT STAFF Administrative Assistant I ................................................................................................ 93.00/Hour Administrative Assistant II ............................................................................................. 113.00/Hour Administrative Assistant III ............................................................................................ 134.0 0/Hour Technical Editor ............................................................................................................. 118.00/Hour Senior Technical Editor .................................................................................................. 165.00/Hour *Overtime Premium is 35% of PERSONNEL CHARGE EQUIPMENT CHARGES BAT Permeameter ........................................................................................................... 200 .00/Day Compaction Testing Equipment & Supplies ...................................................................... 50.00/Day Peel & Shear Strength Apparatus (FML Seams) ......................................................... 900.00/Month Portable Laboratory (8’ x 32’ trailer) with equipment ................................................. 1,200/Month Portable Laboratory (mobilization / demobilization) ...........................................................1,500.00 ReMi/Refraction Seismograph ........................................................................................ 600.00/Day Sealed Single Ring Infiltrometer (SSRI) ............................................... 200.00/Day or 750.00/Month Sealed Double Ring Infiltrometer (SDRI) ..................................................................... Call for Quote Slope Inclinometer .......................................................................................................... 2 50.00/Day Unmanned Aerial Vehicle (Drone) Reconnaissance ........................................................ 250.00/Day F-46 Schedule 2025 SoCal Effective Through 12/31/2025 EXPENSES Vehicle Use for Field Services ............................................................... 17.00/Hour or 500.00/week Soil Sampling Equipment & Drilling Supplies .................................................................... 7.00/Hour Groundwater Sampling Equipment and Supplies ........................................................... 17.00/Hour Per Diem ............................................................ Lesser of (Cost +15%) or (Local Government Rate) Outside Services (Consultants, Surveys, Chemical lab Tests, etc.) ................................... Cost + 15% Reimbursables (Maps, Photos, Permits, Expendable Supplies, etc.) ............................... Cost + 15% Outside Equipment (Drill Rig, Backhoe, Monitoring Equipment, etc.) ............................. Cost + 15% PERMITS, FEES AND BONDS The costs of all permits, fees, and performance bonds required by government agencies are to be paid by the Client, unless stated otherwise in an accompanying proposal. INSURANCE Geo-Logic Associates, Inc. carries workers' compensation, comprehensive general liability and automobile with policy limits normally acceptable to most clients. The cost for this insurance is covered by the fees listed in this schedule. Cost of any special insurance required by the Client, including increases in policy limits, adding additional insured parties and waivers of subrogation, are charged at cost plus 15%. Unless otherwise stated, such charges are in addition to the estimated or maximum charges stated in any accompanying proposal. TERMS Payment is due upon presentation of invoice and is past due thirty (30) days from invoice date. Past due accounts are subject to a finance charge of one and one-half percent (1-1/2%) per month, or the maximum rate allowed by law. PROPOSAL PERIOD Unless otherwise stated, a proposal accompanying this schedule is effective for sixty (60) days. If authorization to proceed is not received within this period, Geo-Logic Associates, Inc. reserves the right to renegotiate the fee. F-47 Schedule 2025 SoCal Effective Through 12/31/2025 2025 FEE SCHEDULE TEST NAME TEST METHOD UNIT RATE Geotechnical / Physical Properties Moisture Content, gravimetric .................................................................D2216/D4643 ................... $25/Test Moisture Content (volumetric and gravimetric) and Bulk Density ...........D7263 ............................... $40/Test Porosity ............................................................................................................................................. $250/Test Particle Size Analyses Standard Sieves and Hydrometer ........................................................D422 ............................... $250/Test Particle Size Analysis – Dry Sieve .........................................................D421 ............................... $140/Test Particle Size Analysis – Aggregate, no hydrometer ..............................D422/C136/CT202 .......... $180/Test Particle Size Analyasis with Gravel with hydrometer ...........................D422 ............................... $300/Test Percent Passing #200 Sieve ..................................................................D1140/C117 ................... $110/Test Atterberg Limits Liquid Limit, Plastic Limit, Plasticity Index (LL, PL, and PI) ...................D4318 ............................. $190/Test Liquid Limit ...........................................................................................D4318 ............................. $105/Test Plastic Limit ..........................................................................................D4318/CTM 204 ............. $105/Test Specific Gravity,Fine (<4.75mm diameter materials) ...............................D854 ............................... $150/Test Specific Gravity,Coarse (>4.75mm diameter materials) ...........................C127 ............................... $130/Test Proctor Compaction Test Method A or B (<25% retained on a 3/8” sieve) ..................................D698/D1557 ................... $240/Test Method C (>25% retained on a 3/8” sieve) ..........................................D698/D1557 ................... $290/Test Moisture Density Single Point, std/mod (Proctor check point) ...........D698/D1557 .................... $90/Point Moisture Density Curve ............................................................................CTM 216 ......................... $260/Test Percent Organic Matter by Muffle Furnace .............................................D2974 ............................. $115/Test Permeability / Conductivity Testing Hydraulic Conductivity, Fixed Wall, up to 6” Diameter Cell .....................Modified ......................... $315/Test Flexible Wall Method, 1” to 4” Diameter Sample ....................................D5084 ............................. $370/Tes t Strength and Consolidation Testing Consolidation Testing Consolidation Test (single point) .........................................................D2435 ............................. $105/Test Consolidation Test (without rate data) ................................................D2435 ............................. $190/Test Test rate data per load increment .......................................................D2435 ...................... $80/Test-Load Expansion/Collapse Testing Expansion Index of Soils .......................................................................D4829 ............................. $180/Test Expansion Indext Test w/Cement or Lime treated soils ......................D4829 ............................. $230/Test Strength Testing Unconfined Compressive Strength (UC), 2-3”......................................D2166 ............................. $125/Test Triaxial Compression Unconsol.-Undrained Triax. Compression (UU), 2-3”, 1-pt test ...........D2850 ............................. $215/Test Consolidated Undrained Triax. Compression (CU), 2-3” (per point) ....D4767 ............................ $500/Point Consolidated Drained Triax. Compressions (CD), 2-3” (per point).......D7181 ............................ $745/Point Direct Shear Direct Shear Test (saturated) ...............................................................D3080 .............................. $90/Point Direct Shear Test (saturated, recycled – strain rate 0.0042”/min) ......D3080 ............................ $180/Point Direct Shear Test (consolidated drained) .............................................D3080 ............................ $205/Point Direct Shear Test (consolidated drained, residual) ..............................D3080 ............................ $350/Point Direct Shear Test (at natural moisture) ...............................................D3080 .............................. $80/Point R-Value .....................................................................................................D2844/CTM301 .............. $280/Test F-48 Schedule 2025 SoCal Effective Through 12/31/2025 2025 FEE SCHEDULE TEST NAME TEST METHOD UNIT RATE Aggregate Testing Sand Equivalent ........................................................................................D2419/CMT 217 ............. $100/Test Durability Index (coarse) ..........................................................................D3744/CMT 229 ............. $200/Test Durability Index (fine) ...............................................................................D3744/CMT 229 ............. $180/Test Soil with Amendments and Slurry Testing R-Value (lime- or cement-treated soils) ...................................................D2844/CTM301 .............. $330/Tes t Compressive Strength, Soil-Cement .........................................................D1633/D1632 ................ $205/Point Pocket Penetrometer ......................................................................................................................... $20/Test Soil Chemistry pH of Soil ............................................................................................................................................ $25/Test Chloride Content (subcontracted) ............................................................CTM 422 ........................... $65/Test Sulfate Content (subcontracted) ..............................................................CTM 417 ........................... $65/Test Soil Resistivity (subcontracted) ................................................................G57/CTM 643 ................. $150/Test Corrosion Series (Min. resistivity, pH, SO4, Cl; subcontracted) ........................................................ $240/Test All test methods are ASTM unless otherwise noted. Special sample preparation and laboratory testing not listed above will be charged at applicable personnel rates. All laboratory test rates are for standard turn-around time and normal reporting procedures. Rush orders will be subject to a 25 percent premium. Manpower requirements or test protocol may preclude the granting of a rush request. F-49 GEOLOGIC ASSOCIATES, INC. Portuguese Bend Landslide RemediaƟon Project - Staff Hour EsƟmates* Task 1 Study, Analysis and Report $55,000 Admin Asst. II $113/hr. CADD Designer $165/hr. 50 $8,250 Staff Professional II $165/hr. 16 $2,640 Staff Professional III $181/hr. Project Professional I $193/hr. 14 $2,702 Project Professional II $216/hr. Senior Professional I $240/hr. Senior Professional II $258/hr. 30 $7,740 Principal Professional I $287/hr. 24 $6,888 Principal Professional II $312/hr. 80 $24.960 Principal Professional III $340/hr. 4 $1,360 Misc./Expenses $460 Total $55,000 Task 2 Plans and SpecificaƟons $155,000 (60%, 90%, 100% submiƩals) Admin Asst. II $113/hr. CADD Designer $165/hr. 200 $33,000 Staff Professional II $165/hr. Staff Professional III $181/hr. Project Professional I $193/hr. Project Professional II $216/hr. 60 $12,960 Senior Professional I $240/hr. Senior Professional II $258/hr. Senior Professional III $275/hr. 160 $44,000 Principal Professional I $287/hr. 80 $22,960 Principal Professional II $312/hr. 120 $37,440 Principal Professional III $340/hr. 12 $4.080 F-50 Misc./Expenses $560 Total $155,000 Task 3 Cost EsƟmaƟng $7,500 Admin Asst. II $113/hr. CADD Designer $165/hr. Staff Professional II $165/hr. Staff Professional III $181/hr. 20 $3,620 Project Professional I $193/hr. Project Professional II $216/hr. Senior Professional I $240/hr. Senior Professional II $258/hr. Senior Professional III $275/hr. 12 $3,300 Principal Professional I $287/hr. 2 $574 Principal Professional II $312/hr. Principal Professional III $340/hr. Misc./Expenses $9 Total $7,500 Task 4 Schedule Management $5,000 Admin Asst. II $113/hr. CADD Designer $165/hr. Staff Professional II $165/hr. Staff Professional III $181/hr. Project Professional I $193/hr. Project Professional II $216/hr. Senior Professional I $240/hr. Senior Professional II $258/hr. Senior Professional III $275/hr. 9 $2,475 Principal Professional I $287/hr. Principal Professional II $312/hr. 8 $2,496 Principal Professional III $340/hr. Misc./Expenses $29 F-51 Total $5,000 Task 5 Staff Report and PresentaƟon $5,000 Admin Asst. II $113/hr. CADD Designer $165/hr. 8 $1,320 Staff Professional II $165/hr. Staff Professional III $181/hr. Project Professional I $193/hr. Project Professional II $216/hr. Senior Professional I $240/hr. Senior Professional II $258/hr. Senior Professional III $275/hr. 2 $550 Principal Professional I $287/hr. Principal Professional II $312/hr. 10 $3,120 Principal Professional III $340/hr. Misc./Expenses $10 Total $5,000 Task 7 UƟlity CoordinaƟon $8,500 Admin Asst. II $113/hr. CADD Designer $165/hr. 4 $660 Staff Professional II $165/hr. 32 $5,280 Staff Professional III $181/hr. Project Professional I $193/hr. Project Professional II $216/hr. Senior Professional I $240/hr. Senior Professional II $258/hr. Senior Professional III $275/hr. 8 $2,200 Principal Professional I $287/hr. Principal Professional II $312/hr. 1 $312 Principal Professional III $340/hr. Misc./Expenses $48 Total $8,500 F-52 Task 9 Permit Documents $10,000 Admin Asst. II $113/hr. 4 $452 CADD Designer $165/hr. 6 $990 Staff Professional II $165/hr. 30 $4,950 Staff Professional III $181/hr. Project Professional I $193/hr. Project Professional II $216/hr. Senior Professional I $240/hr. Senior Professional II $258/hr. Senior Professional III $275/hr. 8 $2,200 Principal Professional I $287/hr. Principal Professional II $312/hr. 4 $1,248 Principal Professional III $340/hr. Misc./Expenses $160 Total $10,000 Task 10 ConstrucƟon Procurement $15,000 Admin Asst. II $113/hr. CADD Designer $165/hr. Staff Professional II $165/hr. Staff Professional III $181/hr. 16 $2,896 Project Professional I $193/hr. Project Professional II $216/hr. 8 $1,728 Senior Professional I $240/hr. Senior Professional II $258/hr. Senior Professional III $275/hr. 24 $6,600 Principal Professional I $287/hr. F-53 Principal Professional II $312/hr. 12 $3,744 Principal Professional III $340/hr. Misc./Expenses $32 Total $15,000 Task 11 AdministraƟon and CoordinaƟon $25,000 Admin Asst. II $113/hr. 14 $1,582 CADD Designer $165/hr. Staff Professional II $165/hr. Staff Professional III $181/hr. Project Professional I $193/hr. Project Professional II $216/hr. Senior Professional I $240/hr. Senior Professional II $258/hr. Senior Professional III $275/hr. Principal Professional I $287/hr. Principal Professional II $312/hr. 75 $23,400 Principal Professional III $340/hr. Misc./Expenses $18 Total $25,000 TOTAL GLA SERVICE FEES $286,000 *Labor breakdown hours are our best esƟmate of the distribuƟon of labor by staff level for these tasks. Actual hours by staff level can vary, depending on staff availability at the Ɵme the services are needed/performed. We will not exceed the overall budget without prior wriƩen authorizaƟon. F-54 ESTIMATE DATE:07/14/25 SURVEYOR:Joshua Tremba evolutionmapping.com NAME:Geo-Logic Associates PROJECT: # HOURS HOURLY RATE SUBTOTAL 8 $135.00 $1,080.00 425 ac $40/ac $16,880.00 4 $135.00 $540.00 16 $135.00 $2,160.00 32 $135.00 $4,320.00 # HOURS HOURLY RATE $20,660.00 8 $270.00 $2,160.00 8 $270.00 $2,160.00 8 $270.00 $2,160.00 2 $270.00 $540.00 4 $80.00 $320.00 $7,340.00 TOTAL $28,000.00 50% DEPOSIT DUE $14,000.00 WE APPRECIATE YOUR BUSINESS! Additional Field Work: Establish and mark ground control QA/QC check shots Travel Time THIS ESTIMATE IS VALID FOR 30 DAYS Supplemental topography Static ties to PB Monitoring Survey Control CLIENT INFO SCOPE OF WORK: Data Collection and Processing: Static and control processing and reporting LiDAR/RGB Flight - UAV (*****ac @ $40/ac) Orthophoto processing Greater Portuguese Bend Landslide Complex / Ancient Altamira Landslide Complex Drainage Study The, field work, processing, and delivery of a "bare earth" DTM surface capable of supporting 1- foot contours. The mapping shall be confined to the area as shown on the attached exhibit, approximately 425 acres. A high-resolution orthophoto shall also be provided as part of the deliverable. LiDAR processing Analyis, editing & Drafting ESTIMATE OF SERVICES PO Box 302 Angelus Oaks, CA 92305 909-794-8068 F-55 F-56 LSA Geo-Logic Associates NEPA Environmental Assessment and Related Technical Analyses for the Portuguese Bend Landslide Remediation Project 7/18/2025 Rounded Fee Escalation 5% % in Year 91% Year 1 $315 $250 $135 $110 $300 $260 $200 $135 $295 $170 $205 $155 $135 $290 $195 $135 $115 $275 $195 $115 $210 $160 $140 9% Year 2 $331 $263 $142 $116 $315 $273 $210 $142 $310 $179 $215 $163 $142 $305 $205 $142 $121 $289 $205 $121 $221 $168 $147 100% Weighted Average $316 $251 $136 $110 $301 $261 $201 $136 $296 $171 $206 $156 $136 $291 $196 $136 $116 $276 $196 $116 $211 $161 $141 Phase 01 Project Initiation 1.1 Project Initiation 4.00 12.00 4.00 20.00 $4,721.15 $4,700.00 1.2 Project Description 2.00 4.00 16.00 4.00 4.00 1.00 31.00 $5,032.55 $5,000.00 1.3 Purpose and Need 2.00 8.00 10.00 $2,641.84 $2,600.00 8.00 24.00 0.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 4.00 1.00 61.00 $12,395.53 $12,300.00 Phase 02 Technical Analyses 2.1 Air Quality/Climate 0.00 $0.00 $0.00 2.2 Noise 0.00 $0.00 $0.00 2.3 Cultural Resources 0.00 $0.00 $0.00 2.3.1 APE Map 1.00 1.00 6.00 8.00 $1,808.10 $1,800.00 2.3.2 Records Search 4.00 2.00 6.00 $1,205.40 $1,200.00 2.3.3 Field Survey 0.00 $0.00 $0.00 2.3.4 Cultural Report 0.00 $0.00 $0.00 2.4 Biological Resources 0.00 $0.00 $0.00 2.4.1 Literature Review/Field Survey 2.00 12.00 12.00 4.00 30.00 $5,353.99 $5,400.00 2.4.2 Draft Biological Assessment 0.00 $0.00 $0.00 2.4.3 Final Biological Assessment 0.00 $0.00 $0.00 2.4.4 Resource Agency Consultation 0.00 $0.00 $0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 12.00 0.00 12.00 0.00 1.00 4.00 0.00 0.00 0.00 0.00 0.00 12.00 0.00 0.00 44.00 $8,367.49 $8,400.00 Phase 03 Preparation of the Environmental Assessment 3.1 Early Agency Consultation 2.00 10.00 4.00 16.00 $3,987.87 $4,000.00 3.2 Draft Environmental Assessment 0.00 $0.00 $0.00 3.3 Environmental Assessment and Public Circulation 0.00 $0.00 $0.00 3.4 FONSI 0.00 $0.00 $0.00 2.00 10.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 0.00 16.00 $3,987.87 $4,000.00 Phase 04 Project Management 4.1 Project Management 4.00 4.00 $1,004.50 $1,000.00 4.2 Attendance at Meetings 1.00 3.50 4.50 $1,195.36 $1,200.00 1.00 7.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.50 $2,199.86 $2,200.00 Records Search $2,150.50 $2,200.00 Reproduction $16.94 $17.00 Mileage $237.28 $200.00 GPS Units $82.50 $83.00 $2,487.22 $2,500.00 $29,437.96 $29,400.00 Total LSA FeesEV P - N o i s e As s o c i a t e - B i o l o g y To t a l L S A H o u r s Wo r d P r o c c e s o r / A d m i n i s t r a t i v e Phase 02 Technical Analyses Subtotal Phase 03 Preparation of the Environmental Assessment Subtotal Phase 04 Project Management Subtotal Pr i n c i p a l - C u l t u r a l R e s o u r c e s Bi o l o g i s t Bi o l o g i s t Pr i n c i p a l i n C h a r g e Pr o j e c t M a n a g e r En v i r o n m e n t a l P l a n n e r As s i s t a n t E n v i r o m e n t a l P l a n n e r Pr i n c i p a l - A i r Q u a l i t y As s o c i a t e - A i r Q u a l i t y As s o c i a t e - A i r Q u a l i t y Ai r Q u a l i t y S p e c i a l i s t Pr i n c i p a l - B i o l o g y As s o c i a t e B i o l o g y Reimbursable Expenses Total Subtotal Reimbursable Expenses As s o c i a t e - C u l t u r a l R e s o u r c e s Ar c h a e o l o g i s t Fi e l d C r e w - C u l t u r a l R e s o u r c e s Phase 01 Project Initiation Subtotal As s o c i a t e - N o i s e No i s e a n d V i b r a t i o n A n a l y s t As s o c i a t e - G I S Gr a p h i c s & G I S S p e c i a l i s t F-57 LSA Geo-Logic Associates NEPA Environmental Assessment and Related Technical Analyses for the Portuguese Bend Landslide Remediation Project 7/18/2025 Rounded Fee Escalation 5% % in Year 91% Year 1 $315 $250 $135 $110 $300 $260 $200 $135 $295 $170 $205 $155 $135 $290 $195 $135 $115 $275 $195 $115 $210 $160 $140 9% Year 2 $331 $263 $142 $116 $315 $273 $210 $142 $310 $179 $215 $163 $142 $305 $205 $142 $121 $289 $205 $121 $221 $168 $147 100% Weighted Average $316 $251 $136 $110 $301 $261 $201 $136 $296 $171 $206 $156 $136 $291 $196 $136 $116 $276 $196 $116 $211 $161 $141 Phase 01 Project Initiation 1.1 Project Initiation 0.00 $0.00 $0.00 1.2 Project Description 0.00 $0.00 $0.00 1.3 Purpose and Need 0.00 $0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 $0.00 Phase 02 Technical Analyses 2.1 Air Quality/Climate 4.00 6.00 13.00 56.00 79.00 $12,978.14 $13,000.00 2.2 Noise 3.00 20.00 30.00 53.00 $8,211.79 $8,200.00 2.3 Cultural Resources 0.00 $0.00 $0.00 2.3.1 APE Map 0.00 $0.00 $0.00 2.3.2 Records Search 0.00 $0.00 $0.00 2.3.3 Field Survey 11.00 1.00 12.00 $1,702.63 $1,700.00 2.3.4 Cultural Report 1.00 2.00 24.00 10.00 2.00 6.00 45.00 $7,955.64 $8,000.00 2.4 Biological Resources 0.00 $0.00 $0.00 2.4.1 Literature Review/Field Survey 0.00 $0.00 $0.00 2.4.2 Draft Biological Assessment 8.00 40.00 8.00 10.00 12.00 8.00 12.00 98.00 $17,709.34 $17,700.00 2.4.3 Final Biological Assessment 1.00 2.00 4.00 16.00 4.00 4.00 4.00 8.00 43.00 $8,171.61 $8,200.00 2.4.4 Resource Agency Consultation 10.00 10.00 10.00 8.00 38.00 $7,915.46 $7,900.00 1.00 3.00 0.00 0.00 4.00 6.00 13.00 56.00 22.00 66.00 12.00 10.00 10.00 2.00 24.00 11.00 10.00 3.00 20.00 30.00 27.00 12.00 26.00 368.00 $64,644.60 $64,700.00 Phase 03 Preparation of the Environmental Assessment 3.1 Early Agency Consultation 0.00 $0.00 $0.00 3.2 Draft Environmental Assessment 4.00 12.00 20.00 48.00 8.00 4.00 96.00 $14,143.36 $14,100.00 3.3 Environmental Assessment and Public Circulation 4.00 6.00 8.00 10.00 4.00 32.00 $5,524.75 $5,500.00 3.4 FONSI 0.00 $0.00 $0.00 8.00 18.00 28.00 58.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.00 8.00 128.00 $19,668.11 $19,600.00 Phase 04 Project Management 4.1 Project Management 2.00 8.00 10.00 $2,641.84 $2,600.00 4.2 Attendance at Meetings 6.00 5.50 11.50 $3,279.69 $3,300.00 8.00 13.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.50 $5,921.53 $5,900.00 Records Search $0.00 $0.00 Reproduction $0.00 $0.00 Mileage $0.00 $0.00 $0.00 $0.00 $90,234.24 $90,200.00 Total LSA Fees - 60% - 90%EV P - N o i s e As s o c i a t e - B i o l o g y To t a l L S A H o u r s Wo r d P r o c c e s o r / A d m i n i s t r a t i v e Phase 02 Technical Analyses Subtotal Phase 03 Preparation of the Environmental Assessment Subtotal Phase 04 Project Management Subtotal Pr i n c i p a l - C u l t u r a l R e s o u r c e s Bi o l o g i s t Bi o l o g i s t Pr i n c i p a l i n C h a r g e Pr o j e c t M a n a g e r En v i r o n m e n t a l P l a n n e r As s i s t a n t E n v i r o m e n t a l P l a n n e r Pr i n c i p a l - A i r Q u a l i t y As s o c i a t e - A i r Q u a l i t y As s o c i a t e - A i r Q u a l i t y Ai r Q u a l i t y S p e c i a l i s t Pr i n c i p a l - B i o l o g y As s o c i a t e B i o l o g y Reimbursable Expenses Total Subtotal Reimbursable Expenses As s o c i a t e - C u l t u r a l R e s o u r c e s Ar c h a e o l o g i s t Fi e l d C r e w - C u l t u r a l R e s o u r c e s Phase 01 Project Initiation Subtotal As s o c i a t e - N o i s e No i s e a n d V i b r a t i o n A n a l y s t As s o c i a t e - G I S Gr a p h i c s & G I S S p e c i a l i s t F-58 LSA Geo-Logic Associates NEPA Environmental Assessment and Related Technical Analyses for the Portuguese Bend Landslide Remediation Project 7/18/2025 Rounded Fee Escalation 5% % in Year 91% Year 1 $315 $250 $135 $110 $300 $260 $200 $135 $295 $170 $205 $155 $135 $290 $195 $135 $115 $275 $195 $115 $210 $160 $140 9% Year 2 $331 $263 $142 $116 $315 $273 $210 $142 $310 $179 $215 $163 $142 $305 $205 $142 $121 $289 $205 $121 $221 $168 $147 100% Weighted Average $316 $251 $136 $110 $301 $261 $201 $136 $296 $171 $206 $156 $136 $291 $196 $136 $116 $276 $196 $116 $211 $161 $141 Phase 01 Project Initiation 1.1 Project Initiation 0.00 $0.00 $0.00 1.2 Project Description 0.00 $0.00 $0.00 1.3 Purpose and Need 0.00 $0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 $0.00 Phase 02 Technical Analyses 2.1 Air Quality/Climate 0.00 $0.00 $0.00 2.2 Noise 0.00 $0.00 $0.00 2.3 Cultural Resources 0.00 $0.00 $0.00 2.3.1 APE Map 0.00 $0.00 $0.00 2.3.2 Records Search 0.00 $0.00 $0.00 2.3.3 Field Survey 0.00 $0.00 $0.00 2.3.4 Cultural Report 0.00 $0.00 $0.00 2.4 Biological Resources 0.00 $0.00 $0.00 2.4.1 Literature Review/Field Survey 0.00 $0.00 $0.00 2.4.2 Draft Biological Assessment 0.00 $0.00 $0.00 2.4.3 Final Biological Assessment 0.00 $0.00 $0.00 2.4.4 Resource Agency Consultation 0.00 $0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 $0.00 Phase 03 Preparation of the Environmental Assessment 3.1 Early Agency Consultation 0.00 $0.00 $0.00 3.2 Draft Environmental Assessment 0.00 $0.00 $0.00 3.3 Environmental Assessment and Public Circulation 0.00 $0.00 $0.00 3.4 FONSI 1.00 8.00 2.00 11.00 $2,606.68 $2,600.00 1.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 11.00 $2,606.68 $2,600.00 Phase 04 Project Management 4.1 Project Management 1.00 1.50 2.50 $693.11 $700.00 4.2 Attendance at Meetings 1.00 2.75 3.75 $1,007.01 $1,000.00 2.00 4.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.25 $1,700.12 $1,700.00 Records Search $0.00 $0.00 Reproduction $0.00 $0.00 Mileage $0.00 $0.00 $0.00 $0.00 $4,306.79 $4,300.00 Total LSA Fees - 60% - 90%EV P - N o i s e As s o c i a t e - B i o l o g y To t a l L S A H o u r s Wo r d P r o c c e s o r / A d m i n i s t r a t i v e Phase 02 Technical Analyses Subtotal Phase 03 Preparation of the Environmental Assessment Subtotal Phase 04 Project Management Subtotal Pr i n c i p a l - C u l t u r a l R e s o u r c e s Bi o l o g i s t Bi o l o g i s t Pr i n c i p a l i n C h a r g e Pr o j e c t M a n a g e r En v i r o n m e n t a l P l a n n e r As s i s t a n t E n v i r o m e n t a l P l a n n e r Pr i n c i p a l - A i r Q u a l i t y As s o c i a t e - A i r Q u a l i t y As s o c i a t e - A i r Q u a l i t y Ai r Q u a l i t y S p e c i a l i s t Pr i n c i p a l - B i o l o g y As s o c i a t e B i o l o g y Reimbursable Expenses Total Subtotal Reimbursable Expenses As s o c i a t e - C u l t u r a l R e s o u r c e s Ar c h a e o l o g i s t Fi e l d C r e w - C u l t u r a l R e s o u r c e s Phase 01 Project Initiation Subtotal As s o c i a t e - N o i s e No i s e a n d V i b r a t i o n A n a l y s t As s o c i a t e - G I S Gr a p h i c s & G I S S p e c i a l i s t F-59 An oicial website of the United States government Here’s how you know Extended SAM Maintenance Window Show Details Aug 8, 2025 Records Retention Policy Impacts Old SAM Registration Data Show Details May 21, 2025 See All Alerts Home Data Bank Data Services HelpSearch Search All Words e.g. 1606N020Q02 Search Results Saved Searches Filter By Keyword Search For more information on how to use our keyword search, visit our help guide Simple Search Search Editor e.g. 123456789, Smith Corp Entity Location Status Any Words All Words Exact Phrase Geo-Logic Associates, Inc. Active✔ Inactive Reset Entity Information All Entity Information Entities Disaster Response Registry Responsibility / Qualific F-60 WARNING SAM.gov An oicial website of the U.S. General Services Administration No matches found Your search did not return any results for active records. Would you like to include inactive records in your search results? Search Inactive Go Back Our Website About This Site Our Community Release Notes System Alerts Our Partners Acquisition.gov USASpending.gov Grants.gov More Partners Policies Terms of Use Privacy Policy Restricted Data Use Freedom of Information Act Accessibility Customer Service Help Check Entity Status Federal Service Desk External Resources Contact This is a U.S. General Services Administration Federal Government computer system that is "FOR OFFICIAL USE ONLY." This system is subject to monitoring. Individuals found performing unauthorized activities are subject to disciplinary action including criminal prosecution. This system contains Controlled Unclassified Information (CUI). All individuals viewing, reproducing or disposing of this information are required to protect it in accordance with 32 CFR Part 2002 and GSA Order CIO 2103.2 CUI Policy. F-61 Portuguese Bend LandslideRemediation Project July 16, 2025 Proposal for: Prepared for:Prepared by: City of Rancho Palos Verdes G-1 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 1 a) Cover Letter July 16, 2025 Ramzi Awwad Public Works Director, City of Rancho Palos Verdes 30940 Hawthorne Blvd., Rancho Palos Verdes, CA 90275 Re: Proposal for Portuguese Bend Landslide Remediation Project Dear Mr. Awwad: In response to the City’s urgent need to stabilize the Portuguese Bend Landslide and safeguard essential infrastructure, Geo- Logic Associates, Inc. (GLA) has assembled a highly qualified team to deliver practical, defensible solutions that meet both the technical and regulatory challenges of this complex project. GLA brings extensive experience in landslide evaluation, dewatering system design, and groundwater infiltration control across California. Our versatile team includes licensed civil engineers, geologists, and environmental specialists who have worked on complex landslide stabilization projects in similar geologic settings. Firm Information Geo-Logic Associates, Inc. 2777 East Guasti Road, Suite 1 (Headquarters) Ontario, CA 91761 | Phone: (909) 626‐2282 GLA is a corporation, currently in good standing in the State of California. Our firm consists of 300 staff in 29 offices in the United States and Peru, including licensed civil engineers, geologists, hydrogeologists, and environmental scientists. Our professionals hold the following licenses to practice in California: PE, GE, PG, CEG, CHG, QISP, QSD, and QSP. DUNS Number: 79-804-2685 Corporate Officers Gary Lass, PG, CEG, CHG Title: Chief Executive Officer Email: garylass@geo-logic.com Phone: (909) 626-2282 Nicole Sweetland, PhD, PG Title: President Email: nsweetland@geo-logic.com Phone: (909) 626-2282 Primary Contact William McCormick, PG, CEG, Principal Engineering Geologist Phone: (707) 953-1837 | Email: bmccormick@geo-logic.com We understand the critical timeline and federal compliance requirements associated with this project. Our approach emphasizes responsiveness, quality control, and practical, buildable design documents that meet the City’s expectations and regulatory obligations. We look forward to the opportunity to continue to support the City in this vital effort and if you have any questions or need additional information, please contact Mr. McCormick at bmccormick@geo-logic.com. Sincerely, GEOLOGIC ASSOCIATES, INC. John Hower, PG, CEG William V. McCormick, PG, CEG Senior Vice President Principal Engineering Geologist G-2 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 2 b) Approach to Scope of Services The following approach outlines our detailed methodology for delivering the City’s required scope of services in a clear, phased, and efficient manner. Our team’s strategy emphasizes technical rigor, proactive coordination, federal funding compliance, and constructible, resilient solutions that directly support the City’s goal of achieving long-term landslide stabilization. 1. Studies, Investigations, Computer Models, and Reports: GLA will build on prior studies by refining the existing geotechnical model using updated field investigations, groundwater monitoring data, and slope movement records. We will perform targeted investigations to evaluate the current groundwater regime, identify remaining data gaps, and calibrate slope stability models using finite element or limit-equilibrium methods. Our approach prioritizes addressing the root cause of instability through refined groundwater characterization and design-driven geotechnical modeling. 2. Construction Drawings, Specifications, and Documents: Our engineering team will develop a complete, constructible, and agency-compliant set of plans and specifications. We will incorporate utility conflict avoidance, erosion control, traffic management, and logistical phasing strategies. All drawings will be prepared and stamped by California-licensed engineers and surveyors, reviewed by our internal QA/QC team, and delivered in both PDF and native formats. Plans will be developed in progressive milestones (60%, 90%, Final) to enable iterative review and refinement. 3. Cost Estimate: A detailed, itemized cost estimate will be prepared in line with current market rates and recent bid data for similar projects and it will include contingencies, soft costs, and unit pricing broken down by bid item and construction phase; submit to City staff for review and approval. 4. Schedule Management: GLA will develop detailed project schedule at start of project using critical path method; regularly update schedule, assess risks, and develop mitigation strategies for any delays. GLA will utilize MS Project software (or similar). 5. City Council Staff Report and Presentation: We will prepare a clear and visually supported presentation for City Council, along with a staff report that aligns with City formatting and content standards. We will rehearse presentation materials with City staff to ensure alignment with community messaging and project goals. 6. Environmental Compliance Documents: GLA and our subconsultant LSA will prepare all documentation required to support third-party NEPA and historic preservation reviews in accordance with federal funding guidelines and will coordinate closely with the City and funding agencies to ensure all requirements are fully addressed. 7. Utility and Agency Coordination: GLA and our subconsultant VELA Engineering, will review construction plans and specifications, identify potential utility conflicts, coordinate with utility companies, and prepare and submit relocation or adjustment documents as necessary. 8. Property Acquisitions and Easements: GLA and our subconsultant Epic Land Solutions, will complete a review of final plans and specifications to assess whether proposed improvements may extend onto adjacent properties/public rights-of- way, and if property acquisition or easements are required; we will delineate such needs graphically. We will coordinate with City, legal advisors, and property owners (if applicable) to understand legal implications of acquiring property or easements and whether existing easements can be leveraged. A boundary survey in support of easement acquisitions if necessary and create legal descriptions and exhibits for said acquisitions. 9. Permitting: GLA will develop a comprehensive permitting matrix identifying agency requirements and timelines. We will identify, prepare and submit needed permit applications to local/state/federal agencies. 10. Construction Procurement: Our team will prepare the Notice Inviting Bids using finalized construction drawings, bid documents, the City’s standard forms, and contract templates. We will conduct a pre-bid conference, respond to Requests for Information, participate in the bid opening, and evaluate bids for responsiveness, completeness, project understanding, and bid amount. A memo documenting the award recommendation will be prepared, and upon review and concurrence by City staff, GLA will draft the City Council Staff Report. Additionally, we will prepare and present recommendations to the City Council for awarding the construction contract. 11. Administration and Coordination: We will maintain weekly progress meetings and repare status updates to City staff, including activity summaries, budget tracking, and schedule or other agreed upon time interval performance to ensure transparency, responsiveness, and the ability to resolve issues in real time. G-3 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 3 c) Organization and Staffing GLA has carefully selected a team of professionals with the expertise necessary to perform all of the required services, as depicted in the organizational chart below. Our proposed Project Manager, Mr. William McCormick, PG, CEG, brings more than 39 years of technical and project management experience in complex geotechnical investigations and landslide remediation projects throughout California and he will be the primary contact person responsible for the overall delivery of the project. Mr. McCormck and key staff will remain assigned to this project through completion of the Scope of Services and any changes to key staff will be reported and submitted for approval of the City. The qualifications and availability of our key team members are summarized in the table below. GLA has the staff and resources available to meet the City’s needs. G-4 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 4 Team Member / Role / Availability Similar Experience William McCormick, PG, CEG Project Manager and Geologic and Geotechnical Analysis Task Manager 75% (All Tasks) »Emergency Design for the Portuguese Bend Landslide Remediation Project and Winterization »Geologic/Hydrogeologic Characterization and Dewatering Design for the Portuguese Bend Landslide Project »On-Call Geotechnical Services for Marin County and Sonoma County Public Works Departments, California Gary Lass, PG, CHG, CEG Principal-in-Charge 100% Support As Needed »Final Design for the Portuguese Bend Landslide Remediation Project »Hydrology and Hydraulic Study for 923 acres for Sunshine Canyon Landfill »Feasibility Study for the Portuguese Bend Landslide Remediation Project Courtney A. Barrett, PE,, QSD, QISP Civil Design Task Manager 75% (Task 1, 2, 3, 4, 5, 10) »Hydrology Analysis and Civil Design Portuguese Bend Landslide »Design and Construction Management Services for the Sunshine Canyon Landfill, Sylmar, California »Design Services for the Newby Island Landfill, Milpitas, California Subconsultants LSA Environmental Support (Task 6) »Environmental Assessment, Monitoring and Reporting for Portuguese Bend Mitigation, Design, Well-Drilling, and Winterization Implementation Epic Land Solutions Property Acquisition (Task 8) »Eminent Domain Property Acquisition for I-710 Corridor Project EIR including locations at LA County Sanitation Districts’ Long Beach Main Pumping Plant Evolution Mapping Surveying (Task 2, 8) »Regional Hydraulic Study for San Bernardino County Green-tech Compost Facility teamed with GLA »Surveying complex coastal landslide sites such as Portuguese Bend G-5 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 5 d) Staff Qualifications and Experience BRIEF FIRM HISTORY AND PRIOR EXPERIENCE GLA is an employee-owned multi-disciplinary civil, environmental, geologic, and geotechnical consulting firm established in 1991. GLA employs over 350 professionals located throughout 29 U.S. office locations as well as an office in Lima, Peru. To meet the City’s goals for landslide stabilization, Geo-Logic Associates (GLA) has assembled a multidisciplinary team of engineers, geologists, and environmental specialists with direct experience in geotechnical investigations, groundwater and surface water interaction, slope stabilization design, and federally funded infrastructure projects. Our staff have successfully delivered projects involving landslide mitigation, dewatering system design, slope modeling, drainage and utility design, environmental documentation, and construction support for public agencies across California. Our team’s qualifications include extensive experience with slope stability analysis, hydrologic and hydraulic modeling, drainage and erosion control design, permit and utility coordination, and preparation of construction-ready plans and specifications. We routinely manage projects from investigation through design and construction, ensuring integration across disciplines and delivering solutions that are practical, cost-effective, and resilient to changing site conditions and climate extremes. Our staff also have extensive experience in the planning, computer modeling, design, and construction phases of open and closed conduit drainage channels, grading and drainage improvements, sediment control and transport, open and closed channel hydraulics and hydrology, site paving and roadway plans, and public and private utilities. GLA has provided the City with professional hydrogeologic and geotechnical consulting services for the Landslide Complex since 2017, and developed preliminary mitigation plans, and technical specifications for its mitigation. In 2018, GLA was selected to complete a feasibility study (FS) for the City and completed a watershed model in 2019. The FS was widely circulated, and internally and externally peer reviewed. It showed that: • The basal failure surface(s) that formed over an extended period of time is an effective hydraulic barrier; • The predominant cause of landsliding within the Landslide Complex is artesian pressure that acts on the basal failure surface throughout the geometry of the slide; • One of the main contributors to the development of artesian pressure is surface water infiltration from canyons and ravines that are at higher elevations; • Seepage within the Landslide Complex sliding mass caused by infiltration of surface water through onsite cracks, onsite ravines, and infiltration caused by irrigation, and through influx from leaky septic systems, are secondary sources of instability; • The Landslide Complex is broken into multiple blocks, with relative movements affected; and • The 2019 watershed model identified critical areas where stormwater was ponding and infiltrating into the landslide area. Following the acceptance of the FS and watershed model in 2019, GLA completed the preliminary mitigation design which called for: (i) management of groundwater that is the source of artesian pressure; (ii) relief of residual artesian pressure at the toe of the slide; within the entire Landslide Complex; and (iii) infilling of cracks and improvement of surface drainage to minimize seepage into the landslide mass. The first two items will be addressed by installation of deep dewatering wells and horizontal/directional drains, where appropriate, generally outside of the landslide footprint and below the basal failure surface (so they do not get sheared off as the slide moves). G-6 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 6 In 2023, GLA was selected to provide the final Landslide Mitigation, Exploration, Dewatering and Winterization Design. Work on this project includes siting deep exploratory boreholes, daily slope monitoring and strategic planning for more permanent stabilization techniques. In the process, GLA has developed a keen awareness of the City’s and local needs, as well as state and local standards and procedures. Our recent work has further refined the complex nature of the landslide complex, especially in the PBL where a deeper landslide was discovered that had never historically failed before. This success is founded on the principles of ensuring that our work is conducted to a high professional standard, our work product is technically defensible, our clients’ best interests inform our decisions, and our services are provided cost effectively. The long-term working relationships we have with our clients is a testament to the effectiveness of this approach. GLA staff have a history of providing hydrogeological and hydraulic services to the City , and as a result, we have an unparalleled familiarity with site geologic and hydrogeologic conditions. The City and others have largely characterized the geologic, hydrologic, hydrogeologic, and geotechnical conditions that drive regional slope failure and have implemented some preliminary mitigation measures. However, now the City is undertaking a focused effort to meet the following objectives: • Long-term stabilization of the landslide complex • Repair and upgrade related infrastructure • Compliance with applicable federal, state, and local environmental laws and regulations GLA will work closely with the City to utilize the results of the numerous prior and ongoing geologic studies and engineering evaluations. This project will provide a comprehensive and coordinated approach to controlling stormwater runoff and mitigating infiltration at the source. Portions of our civil design, especially surface water management and drainage improvements will rely on the final results of the hydrologic/hydraulic study that is being commissioned by the City with Geosyntec*. Our team will utilize industry-leading tools and expertise to deliver high-quality plans that meet regulatory standards and support the City’s sustainability goals. We look forward to working with the City to implement this critical program. STAFF QUALIFICATIONS The resumes for key staff are presented in the following pages. *Note: Our study does not include hydrologic analysis since a comprehensive study is being independently done by others G-7 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 7 Project Manager and Geotechnical and Geological Analysis Task Manager: William McCormick, PG, CEG William McCormick, PG, CEG Principal Engineering Geologist Mr. McCormick has over 39 years of technical experience and in contract and project management of major geotechnical investigations and material testing and inspection projects in the Northern California. He is an experienced project manager with long-term on-call projects for multiple Sonoma County Departments, the Counties of Napa and Marin, and the City of Santa Rosa, to name a few. His technical expertise includes landslide evaluation, mitigation design and construction observation and management of landslide repairs, Alquist-Priolo Earthquake Fault Zone evaluation studies, geologic and geomorphic mapping and exploration, site feasibility and geotechnical design studies for infrastructure including roadways, highways, bridges and alignment studies, civil developments, park sites, geotechnical evaluations involving erosion, drainage, slope stability, engineering geology, retaining walls, soil nail walls, earth dams, forensic studies, distressed properties, expert witness testimony, construction monitoring for engineering geologic/geotechnical mitigation projects, construction management, and peer review of geologic, geotechnical and fault studies. Mr. McCormick has performed geologic, fault, and geotechnical peer review services for numerous entities including Sonoma County, Mendocino County, City of Santa Rosa and the City of Concord. Mr. McCormick has also presented on engineering geologic topics throughout the US as well as in China, Australia, New Zealand, Italy, England and Scotland. Landslide Mitigation,Exploration, Dewatering and Winterization Design, Portuguese Bend Landslide Complex, Rancho Palos Verdes, California Project Geologist. The Portuguese Bend Landslide Complex (PBLC), located along the Pacific Coast in the scenic City of Rancho Palos Verdes (City), is among the most recognizable landslide features in California. The massive landslide encompasses approximately 239 acres and 38 million cubic yards of sliding mass, with lateral dimensions approximately 0.9 miles x 0.8 miles. Ground movement rates vary widely across the site but have been measured recently to be as much as 11 feet per year near the landslide’s toe at the coast. Mr. McCormick is lead geologist in geologic data assessment to develop a working geologic model across the entire, newly re- activated Altamira Landslide. Work includes siting deep explorations, daily piezometric and slope monitoring and strategic planning for ore permanent stabilization techniques. Mr. McCormick was also key in assisting with winterization design recommendations and designs intended to reduce surface water infiltration deep into the landslide complex across canyons and highly fissured ground. Mr. McCormick has a deep understanding of the surface and subsurface hydrologic conditions affecting the part of Rancho Palos Verdes and adjacent environments. On-Call Geotechnical Services, Marin County Public Works Department, Marin County, and Sonoma County Public Infrastructure, Sonoma County, California Served as Contract Manager for an on-call geotechnical services contract for the last 15 years for Marin County and the last 25 years for Sonoma County. Services included geotechnical assessment, design and construction services for two major storm drains, four pump stations, numerous creek and levee stabilization projects, and numerous landslides and roadway repair projects, including retaining wall design. Many of these projects were located in areas of highly compressible soil, unstable slopes, large slides, or liquefiable soil conditions. EDUCATION MS, Geology, 1986 San Diego State University BS, Geology, 1983 San Diego State University PROFESSIONAL REGISTRATIONS Professional Geologist, CA, No. 5022 Certified Engineering Geologist, CA, No. 1673 CERTIFICATIONS Loss Prevention System Safety Training PROFESSIONAL AFFILIATIONS 2023 Recipient of “Honorary Member Status” of Association of Environmental and Engineering Geologists (AEG) G-8 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 8 Principal In Charge: Gary L. Lass, PG, CEG, CHG Gary L. Lass, PG, CEG, CHG Chief Executive Officer Mr. Lass has more than 40 years of experience providing successful geological, environmental, geotechnical, and hydrogeologic services throughout the Western United States and Mexico. He has acted as Principal-in-Charge, and/or Project Manager for geologic and hydrogeologic characterizations for Remedial Investigations (RIs), Feasibility Studies (FSs), Remedial Action Plans (RAPs), Evaluation Monitoring Programs (EMPs), Engineering Feasibility Studies (EFS), Corrective Action Programs (CAPs), groundwater monitoring and reporting programs, and site closures. Mr. Lass has extensive experience with all aspects of landfill siting, expansion, design, permitting, construction, operations, monitoring and closure and is a specialist in CCR Title 27 compliance, having acted as Principal-in-Charge, and/or Project Manager for geotechnical, geologic and/or hydrogeologic characterizations projects at hundreds of landfill sites throughout the western United States. Hydrology and Hydraulics Assessment for Pre- and Post-Development Conditions of a Major Improvement Project Sunshine Canyon Landfill, Los Angeles County, CA Principal-in-charge for this comprehensive hydrology and hydraulics study within an approximately 923-acre watershed area to assess the impact of proposed entrance improvements on downstream regional flood control facilities and to evaluate the adequacy of proposed on-site drainage improvements. Hydrology and Hydraulics Assessment for Composting Facility, San Bernardino County, CA Principal-in-charge for this hydrology and hydraulics analysis for a 1,400-acre watershed area tributary to the project site. The analysis considered off-site run-on and proposed on-site improvements. Portuguese Bend Landslide Complex, Rancho Palos Verdes, California - Landslide Mitigation Design and the Feasibility Study. Principal-in-Charge of the Portuguese Bend Landslide Complex (PBLC), located along the Pacific Coast in the scenic City of Rancho Palos Verdes (City), is among the most recognizable landslide features in California. The massive landslide encompasses approximately 239 acres and 38 million cubic yards of sliding mass, with lateral dimensions approximately 0.9 miles x 0.8 miles. Ground movement rates vary widely across the site but have been measured recently to be as much as 11 feet per year near the landslide’s toe at the coast. Projects includes landslide mitigation design as well as a 2018 Feasibility Study. Key design components included innovative engineering approaches for surface water using environmentally-friendly-lined swales and for relief or artesian pressure by directional drains. The preliminary project design report was accepted by a unanimous vote of the City Council. EDUCATION Master of Science, Geochemistry, 1978 California State University, Los Angeles Bachelor of Science, Geology, 1974 California State University, Los Angeles PROFESSIONAL REGISTRATIONS Registered Geologist, California, No. 3653 Certified Engineering Geologist, California, No. 1093 Certified Hydrogeologist, California, No. 18 Certified Engineering Geologist, Oregon, No. E1577 Registered Geologist, Arizona, No. 28820 G-9 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 9 Civil Engineer Task Manager: Courtney A. Barrett, PE, QSD, QISP Courtney A. Barrett, PE, QSD, QISP Senior Engineer III Ms. Barrett is a Registered Civil Engineer with over 21 years of experience in engineering. Her experience includes preparation of grading and drainage plans, liner design, design of erosion control best management practices, preparation of technical specifications, engineer’s estimates, and providing construction quality assurance and construction support services on a variety of landfill projects. She has been the CQA Officer for cell development, landfill closure, storm drain installation, and landfill gas well installation projects at various sites in California and has worked with a variety of public agencies to design capital improvement projects, prepare specifications and cost estimates, provide engineering and permitting oversight, and related duties. Portuguese Bend Landslide Remediation Phase I Design, Rancho Palos Verdes, California Project Engineer for mitigation plans and hydrology part of the Phase I services to develop remedial design for the Portuguese Bend Landslide Complex located along the Pacific Coast in the scenic City of Rancho Palos Verdes (City). Work included revision of hydrology and hydraulics calculations, validation and calibration of the slope stability model, engineering evaluations, design support and development of planning and irrigation plans. develop construction plans and specifications, develop cost estimates, and support construction logistics. Design and Construction Management Services for the Sunshine Canyon Landfill, Republic Services, Inc., Sylmar, California Project Manager, design engineer and resident engineer for the design and construction of City/County Cell – 4 (CC-4) Part 1, CC-4 Part 2A, CC-4 Part 3, CC-4 Part 4A, 4B, & 4C, CC-5A, CC-3B Part 2, West Drainage Channel Phase II, drainage components of the Ultimate Entrance road, and the relocation of the Southern California Edison Transmission power poles around the perimeter of the landfill and the CQA Engineer for CC-4 Part 4A, 4B, & 4C, and CC-5A. Project work at the site includes development of construction drawings, CQA Manual, and technical specifications. Design components included grading, drainage channels, sump and pump, and geosynthetic liner system. Work also includes onsite resident engineering services including pre-bid activities, onsite construction oversite, field design changes, response to contractor questions, and tracking construction schedules and project costs. Design Services for the Newby Island Landfill, Republic Services, Inc., Milpitas, California Design Engineer responsible for the preparation of the Overliner Units 1, 2, and 3 design. Development of the design report, construction drawings, CQA Manual, and technical specifications. Design components included grading, leachate sump and force main, and geosynthetic liner system. EDUCATION Bachelor of Science, Civil Engineering, 2003 University of California, Davis PROFESSIONAL REGISTRATIONS Arizona Professional Engineer, No. 55166 California Professional Engineer, No. 78076 Hawaii Professional Engineer, No. PE-15661 New Mexico Professional Engineer, No. 21872 Nevada Professional Engineer, No. 022633 Oregon Professional Engineer, No. 88426PE Utah Professional Engineer, No. 8746089-2202 PROFESSIONAL Certifications California Qualified Industrial SWPPP Practitioner, No 78076 California Qualified SWPPP Practitioner, No 22227 California Qualified SWPPP Developer, No 78076 G-10 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 10 REFERENCE PROJECTS Portuguese Bend Landslide Feasibility Study and Hydrologic Model Rancho Palos Verdes, California geo-logic.com Page 1 ` Feasibility Study and Hydrologic Model Daniel B. Stephens and Associates, Inc. (DBS&A), a subsidiary of Geo-Logic Associates, Inc., assisted city staff in their preparation for an anticipated federal infrastructure plan expected in 2017 to provide funds for landslide abatement. Part of this effort was to review and update an existing engineering feasibility study (FS) prepared by the U.S. Army Corps of Engineers (USACE) in 2000. The USACE FS only proposed a coastal dike in an effort to stabilize coastal erosion, however, the landslide itself was not directly addressed. DBS&A commenced a thorough compilation and review of all available historical work on the Portuguese Bend landslide, adjacent area landslides including Abalone Cove, Klondike Canyon, and the larger Altamira Complex. This review resulted in the compilation of nearly 100 GB of historical files in electronic format that had not been organized before. In addition, DBS&A completed a systematic and through review of the historical data, reports, studies, engineering work, and research along with available public scientific literature to characterize the landslide geology, hydrogeology, groundwater occurrence, recharge, past mitigation efforts, and past successes and failures. The comprehensive review formed the basis of an updated hydrogeologic conceptual site model that was used to prepare a new engineering feasibility study in 2018 to evaluate and present available options for landslide abatement including groundwater extraction wells, horizontal drains (hydraugers), and stormwater control. A watershed model was prepared to quantify groundwater recharge components including rainfall and irrigation. Areas of critical stormwater ponding and infiltration were identified. The FS included geotechnical modeling and conceptual-level cost estimates for groundwater extraction wells, hydraugers, fracture-sealing, stormwater control, and a partial centralized sanitary sewer to replace some septic systems in the area. DBSA directed and participated in several city council meetings to present the draft FS options, receive public stakeholder comments, and incorporate the comments into a final FS report. The final FS outlined the primary components of subsequent work elements completed by the City from 2019 to present. Client City of Rancho Palos Verdes, California Contact Elias Sassoon Ara Mihranian Doug Wilmore (310) 544-5252 Timeframe 2017-2019 Contract Amount $202,840 Personnel John J. Dodge, PG, CHG (Project Manager) Gregory Schnaar, PhD, PG (VA) • Collaboration with City staff • Comprehensive historical document and data compilation and review • Hydrogeologic conceptual site model • Watershed and geotechnical modeling • Stormwater flow path characterization • Quantification of stormwater infiltration and groundwater recharge • Engineering options for stormwater control and landslide abatement • Conceptual cost estimates • Collaboration with Palos Verdes Peninsula Land Conservancy • City Council meetings and public stakeholder review G-11 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 11 Portuguese Bend Landslide Rancho Palos Verdes, California geo-logic.com Page 1 ` The Portuguese Bend Landslide (PBL), located along the Pacific Coast in the City of Rancho Palos Verdes (City), is among the most recognizable landslide features in California and the fastest-moving landslide in the United States. This massive landslide encompasses approximately 239 acres and 38 million cubic yards, with lateral dimensions of approximately 0.9 miles by 0.8 miles. Ground movement rates vary widely across the site but have been recently measured to be as much as 11 feet per year near the landslide’s toe at the coast. In 2018, GLA prepared a feasibility study for the City’s use in developing and comparing options to mitigate the ongoing landslide movement. Subsequently, the City commissioned GLA to develop a mitigation design to the permit level. Key components of GLA’s mitigation design included innovative engineering approaches for surface water control using geosynthetic-lined swales and for artesian groundwater pressure relief using directionally installed drains. To design surface water management features, GLA performed a hydrologic analysis to calculate the estimated design flows for a 100-year, 24-hour design storm event using the methodology outlined in the Los Angeles County Department of Public Works Hydrology Manual. The hydrologic parameters were then applied in hydraulic calculations to design the proposed engineered swales, culvert pipes, and a flow reduction area included in the mitigation design package. GLA also supported the City in characterizing new, larger landslide movement and developing emergency mitigation measures to reduce land movement and addressing the concerns of residents, the City Council, and the Palos Verdes Peninsula Land Conservancy. GLA delivered three project briefings to the public on the City’s behalf, and GLA’s original design report was accepted by a unanimous vote of the City Council. Client City of Rancho Palos Verdes, California Contact Ron Dragoo, PE, Principal Engineer Department of Public Works (310) 544-5250 Timeframe 2019-Present Contract Amount $580,000 Personnel William McCormick, PG Neven Matasovic, Ph.D, CEG, PE, GE Alan Witthoeft, PE, GE Mark Vincent, PG, CEG, CHG Caleb Miller, PE Gary Lass, PG, CEG, CHG • Landslide mitigation • Deep dewatering well design and monitoring • 3D slope stability modelling • 3D seepage finite element modelling • Surface water control design • Surface water control design • Permit-level plan and specification development • Community outreach and City Council meetings • Interface with Land Conservancy • Geosynthetics design • Hydrology and hydraulics evaluation • Horizontal and directional drain design • Fracture infill design • Order-of-magnitude cost estimate • Winterization design G-12 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 12 Sonoma County 2025 Landslide Road Damage Sonoma County, California geo-logic.com Page 1 ` GLA is continuing a geologic and geotechnical assessment and mitigation design services for six recent roadway/landslide projects in the County. GLA personnel have been provide geotechnical and design services for the County for over 25 consecutive years. GLA (as Prime) conducted project management, geologic, and geotechnical investigations; provided geotechnical design criteria; assembled a team of survey, civil, and structural engineers; and provided the County with plans and specs for retaining walls, sheet pile wall and rip-rap slope stabilization repairs. GLA completed the projects in accordance with the government reimbursement schedule and allowed projects to be set out to bid in record time (months instead of years). GLA personnel are also providing construction observation and inspection for key elements to ensure conformance to the plans. Client Sonoma County Public Infrastructure Department, California Contact Johannes Hoevertsz johannes.hoevertsz@sonoma-county.org (707) 556-2231 Timeframe 2024-Present Contract Amount $600,000 Personnel William McCormick, PG, CEG Mohsen Mahdavi, Ph.D, PE, GE Fouad Mina, PE Jarot Tamba Project Highligts: • Emergency Response and • Relative Risk Assessments • Prime Consultant to assemble • Design Team • Rapid Geotechnical • Investaigation and • Characterization • Civil and Structural Plan and • Specifications • Construction Consultation, • Observation and Testing G-13 PROPOSAL: GREATER PORTUGUESE BEND LANDSLIDE COMPLEX/ANCIENT ALTAMIRA LANDSLIDE COMPLEX DRAINAGE STUDY CITY OF RANCHO PALOS VERDES www.geo-logic.com 13 e) Project Schedule The following critical-path-method schedule outlines the major tasks, sub-tasks, deliverables, and interim milestones required to complete the Scope of Work in accordance with the City’s objectives and timeline. ID Task Name Duration Start Finish 1 SSttuuddiieess aanndd GGeeootteecchhnniiccaall AAnnaallyyssii ss 58 days Wed 8/6/25 Fri 10/24/25 2 DDrraafftt RReeppoo rrtt 34 days Wed 8/6/25 Mon 9/22/25 3 CCiittyy RRee vvii eeww 11 days Mon 9/22/25 Mon 10/6/25 4 FF iinnaall RReeppoorrtt 15 days Mon 10/6/25 Fri 10/24/25 5 PPllaannss aanndd SSppeecciiffiiccaattiioonnss 128 days Wed 8/6/25 Fri 1/30/26 6 TTooppooggrraapphhii cc SSuurrvveeyy aanndd 6600%% PPllaannss43 days Wed 8/6/25 Fri 10/3/25 7 CCiittyy RRee vvii eeww 11 days Fri 10/3/25 Fri 10/17/25 8 9900%% PPllaannss 46 days Fri 10/17/25 Fri 12/19/25 9 CCiittyy RRee vvii eeww 24 days Tue 12/9/25 Fri 1/9/26 10 110000%% PPllaannss 16 days Fri 1/9/26 Fri 1/30/26 11 SSttaaffff RReeppoo rrtt 32 days Fri 10/17/25 Mon 12/1/25 12 DDrraafftt 22 days Fri 10/17/25 Mon 11/17/25 13 FF iinnaall 11 days Mon 11/17/25Mon 12/1/25 14 EEnnvviirroonnmmeennttaall DD ooccuummeenntt ss 128 days Wed 8/6/25 Fri 1/30/26 15 6600%%53 days Wed 8/6/25 Fri 10/17/25 16 9900%%46 days Fri 10/17/25 Fri 12/19/25 17 FF iinnaall 31 days Fri 12/19/25 Fri 1/30/26 18 UUttiill iittyy aanndd AAggeenncc yy CCoooorrddiinnaattiioonn 98 days Wed 8/6/25 Fri 12/19/25 19 DDrraafftt 48 days Wed 8/6/25 Fri 10/10/25 20 FF iinnaall 51 days Fri 10/10/25 Fri 12/19/25 21 PPrrooppeerrttyy AAqquuiissii ttiioo nn aanndd EEeeaasseemmeenntt ss 85 days Mon 9/22/25Fri 1/16/26 22 6600%%31 days Mon 9/22/25 Mon 11/3/25 23 9900%%35 days Mon 11/3/25 Fri 12/19/25 24 FF iinnaall 21 days Fri 12/19/25 Fri 1/16/26 25 PPee rrmmiitt DD ooccuummeennttss 128 days Wed 8/6/25 Fri 1/30/26 26 DDrraafftt 58 days Wed 8/6/25 Fri 10/24/25 27 FF iinnaall 71 days Fri 10/24/25 Fri 1/30/26 28 CCoonnssttrruuccttiioonn PPrrooccuurreemmeenntt 86 days Fri 12/19/25 Fri 4/17/26 29 DDrraafftt 46 days Fri 12/19/25 Fri 2/20/26 30 FF iinnaall 41 days Fri 2/20/26 Fri 4/17/26 31 AAddmmiinniissttrraattii oonn aanndd CCoooorrddii nnaattiioonn 183 days Wed 8/6/25 Fri 4/17/26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 1 8 15 22 29 5 12Aug '25 Sep '25 Oct '25 Nov '25 Dec '25 Jan '26 Feb '26 Mar '26 Apr '26 Milestone Summary Project Summary Manual Task Manual Summary Proposed Schedule - Portuguese Bend Landslide Remediation Project Page 1 Project: Proposed Schedule Portuguese Bend Landslide Remediation ProjectDate: Wed 7/16/25 G-14 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 14 f) Quality Control Plan When GLA starts a new project, we identify the reviewer(s) for each task and assign a senior professional to do coordination review. Overall quality assurance for this contract will be the responsibility of the Project Manager, William McCormick, CEG. GLA will prepare all technical documents and plans with review and approval by appropriately licensed professionals, and engineering drawings and specifications will be sealed by a California registered professional engineer. We will conduct routine quality control reviews to verify that all project deliverables and supporting documents are complete, understandable, conform to standards, and meet City’s expectations. GLA maintains a reputation for preparing high-quality technical reports. A careful process of document production maintains our high standard. This process includes reviews for technical accuracy by a technical manager familiar with the project goals and objectives; a complete editorial review that ensures logical sequence of ideas and clear, concise writing; and a final quality assurance check by the project manager prior to submission to a client. Our team knows the importance of providing high-quality final deliverables that thoroughly address all applicable requirements. Report and plan preparation typically involves development of a draft (or 60%, 90%, and 100% submittal for plans) for client review and comment, and completion of a final draft with client input and approval. All GLA deliverables are reviewed in accordance with GLA’s Quality Assurance Manual (QAM) to ensure a high-quality end product. GLA employs a full- time production team responsible for conducting final editorial reviews and production of all documents. This ensures quality, accuracy, compliance, and completeness of reports prepared by GLA. Reports are delivered according to need or preference in hard-copy and/or electronic format. GLA has an accounting team that assists with contract review, invoice production, review, and submittal. Our contract specialists review all contract requirements and consistently follow specific invoicing procedures in our Deltek Vision accounting system when each project is opened, ensuring consistency and accuracy on all of our invoices. Utilizing this system, we are able to produce draft and final invoices that include all back-up documentation as required. Draft invoices are provided to the PM for review and approval. Once approved, invoices are submitted to the correct financial contact and to the PM as requested. Monitoring Quality of Subcontractor Work Project teams that include multiple subcontractors add value to projects by enabling personnel from specialized backgrounds and varying disciplines to work together to produce the best solution. However, multiple team members also means added complexity and increased need for oversight. GLA understands our role and, as the prime, we will ensure that our subcontractors provide the same level of quality that we expect from our staff. To ensure that the quality of subcontractor work is carefully monitored, GLA adheres to the following oversight procedures: • Regular communication with all subcontractors • Quality assurance and data review/audit of work performed by subcontractors • All reports and documentation prepared by subcontractors are subject to GLA’s internal review and production process prior to submission to the client g) Accepance of Conditions GLA has reviewed the sample professional services agreement and is proposing that the City consider incorporating the following revisions to the contract. 6.3 Ownership of Documents. After Consultant has been paid for the services generating its work product, all drawings, specifications, maps, designs, photographs, studies, surveys, data, notes, computer files, reports, records, documents and other materials (the “documents and materials”) prepared by Consultant, its employees, subcontractors and agents in the performance of this Agreement shall be the property of City and shall be delivered to City upon request of the Contract Officer or upon the termination of this Agreement, and Consultant shall have no claim for further employment or additional compensation as a result of the exercise by City of its full rights of ownership use, reuse, or assignment of the documents and materials hereunder. Any use, reuse or G-15 PROPOSAL: PORTUGUESE BEND LANDSLIDE REMEDIATION PROJECT CITY OF RANCHO PALOS VERDES www.geo-logic.com 15 assignment of such completed documents for other projects and/or use of uncompleted documents without specific written authorization by the Consultant will be at the City’s sole risk and without liability to Consultant, and Consultant’s guarantee and warranties shall not extend to such use, reuse or assignment. Consultant may retain copies of such documents for its own use. Consultant shall have the right to use the concepts embodied therein. All subcontractors shall provide for assignment to City of any documents or materials prepared by them, and in the event Consultant fails to secure such assignment, Consultant shall indemnify City for all damages resulting therefrom. Moreover, Consultant with respect to any documents and materials that may qualify as “works made for hire” as defined in 17 U.S.C. § 101, such documents and materials are hereby deemed “works made for hire” for the City. h) Fees and Cost Estimate All work performed under thsi contract will be on a time and materials basis, in accordance with our 2025 Standard Fee Schedule (attached). As per our Standard Fee Schedule, any outside and subcontrated services will be billed on a cost + 15% basis. Our estimated costs for this project is broken down by tasks and is presented below. Task Description Amount (USD) Task 1 Studies, Investigations, Computer Models, and Report $87,200 1A Study, Analysis, and Reports $55,000 1B New Topographic Survey $32,200 Task 2 Plans and Specifications $155,000 2A 60% Design $95,000 2B 90% Design $45,000 2C 100% Design $15,000 Task 3 Cost Estimate $7,500 Task 4 Schedule $5,000 Task 5 Staff Report/Presentation $5,000 Task 6 Environmental Compliance $142,485 6A 60%$33,810 6B 90% $103,730 6C 100% $4,945 Task 7 Utility and Agency Coordination $8,500 Task 8 Property Aquisition and Eeasements TBD Task 9 Permit Documents $10,000 Task 10 Construction Procurement $15,000 Task 11 Administration and Coordination $25,000 ESTIMATED TOTAL $460,685 G-16 Schedule 2025 SoCal Effective Through 12/31/2025 2025 FEE SCHEDULE PROFESSIONAL STAFF Staff Professional I ....................................................................................................... $1 46.00/Hour Staff Professional II ........................................................................................................ 165.00/Hour Staff Professional III ....................................................................................................... 181.00/Hour Project Professional I ..................................................................................................... 19 3.00/Hour Project Professional II .................................................................................................... 21 6.00/Hour Project Professional III ................................................................................................... 23 3.00/Hour Senior Professional I ...................................................................................................... 24 0.00/Hour Senior Professional II ..................................................................................................... 25 8.00/Hour Senior Professional III .................................................................................................... 27 5.00/Hour Principal Professional I .................................................................................................. 287 .00/Hour Principal Professional II ................................................................................................. 312 .00/Hour Principal Professional III ................................................................................................ 340 .00/Hour Court Appearance (Expert Witness, Deposition, etc.; four-hour minimum) ............ 2 x HourlyRate FIELD/LABORATORY STAFF Technician I .................................................................................................................... 105.00/Hour Technician II ................................................................................................................... 126.00/Hour Technician III (or Minimum Prevailing Wage) ............................................................... 143.00/Hour Technician IV ................................................................................................................. 158.00/Hour Laboratory Manager ...................................................................................................... 190.0 0/Hour Principal Technician ....................................................................................................... 21 3.00/Hour Managing Technician ..................................................................................................... 190.0 0/Hour CADD/GIS CADD/GIS/Database Manager I ..................................................................................... 126.00/Hour CADD/GIS/Database Manager II .................................................................................... 149.00/Hour CADD Designer .............................................................................................................. 16 5.00/Hour GIS Specialist.................................................................................................................. 165.00/Hour SUPPORT STAFF Administrative Assistant I ................................................................................................ 93.00/Hour Administrative Assistant II ............................................................................................. 113.00/Hour Administrative Assistant III ............................................................................................ 134.0 0/Hour Technical Editor ............................................................................................................. 118.00/Hour Senior Technical Editor .................................................................................................. 165.00/Hour *Overtime Premium is 35% of PERSONNEL CHARGE EQUIPMENT CHARGES BAT Permeameter ........................................................................................................... 200 .00/Day Compaction Testing Equipment & Supplies ...................................................................... 50.00/Day Peel & Shear Strength Apparatus (FML Seams) ......................................................... 900.00/Month Portable Laboratory (8’ x 32’ trailer) with equipment ................................................. 1,200/Month Portable Laboratory (mobilization / demobilization) ...........................................................1,500.00 ReMi/Refraction Seismograph ........................................................................................ 600.00/Day Sealed Single Ring Infiltrometer (SSRI) ............................................... 200.00/Day or 750.00/Month Sealed Double Ring Infiltrometer (SDRI) ..................................................................... Call for Quote Slope Inclinometer .......................................................................................................... 2 50.00/Day Unmanned Aerial Vehicle (Drone) Reconnaissance ........................................................ 250.00/Day G-17 Schedule 2025 SoCal Effective Through 12/31/2025 EXPENSES Vehicle Use for Field Services ............................................................... 17.00/Hour or 500.00/week Soil Sampling Equipment & Drilling Supplies .................................................................... 7.00/Hour Groundwater Sampling Equipment and Supplies ........................................................... 17.00/Hour Per Diem ............................................................ Lesser of (Cost +15%) or (Local Government Rate) Outside Services (Consultants, Surveys, Chemical lab Tests, etc.) ................................... Cost + 15% Reimbursables (Maps, Photos, Permits, Expendable Supplies, etc.) ............................... Cost + 15% Outside Equipment (Drill Rig, Backhoe, Monitoring Equipment, etc.) ............................. Cost + 15% PERMITS, FEES AND BONDS The costs of all permits, fees, and performance bonds required by government agencies are to be paid by the Client, unless stated otherwise in an accompanying proposal. INSURANCE Geo-Logic Associates, Inc. carries workers' compensation, comprehensive general liability and automobile with policy limits normally acceptable to most clients. The cost for this insurance is covered by the fees listed in this schedule. Cost of any special insurance required by the Client, including increases in policy limits, adding additional insured parties and waivers of subrogation, are charged at cost plus 15%. Unless otherwise stated, such charges are in addition to the estimated or maximum charges stated in any accompanying proposal. TERMS Payment is due upon presentation of invoice and is past due thirty (30) days from invoice date. Past due accounts are subject to a finance charge of one and one-half percent (1-1/2%) per month, or the maximum rate allowed by law. PROPOSAL PERIOD Unless otherwise stated, a proposal accompanying this schedule is effective for sixty (60) days. If authorization to proceed is not received within this period, Geo-Logic Associates, Inc. reserves the right to renegotiate the fee. G-18 Schedule 2025 SoCal Effective Through 12/31/2025 2025 FEE SCHEDULE TEST NAME TEST METHOD UNIT RATE Geotechnical / Physical Properties Moisture Content, gravimetric .................................................................D2216/D4643 ................... $25/Test Moisture Content (volumetric and gravimetric) and Bulk Density ...........D7263 ............................... $40/Test Porosity ............................................................................................................................................. $250/Test Particle Size Analyses Standard Sieves and Hydrometer ........................................................D422 ............................... $250/Test Particle Size Analysis – Dry Sieve .........................................................D421 ............................... $140/Test Particle Size Analysis – Aggregate, no hydrometer ..............................D422/C136/CT202 .......... $180/Test Particle Size Analyasis with Gravel with hydrometer ...........................D422 ............................... $300/Test Percent Passing #200 Sieve ..................................................................D1140/C117 ................... $110/Test Atterberg Limits Liquid Limit, Plastic Limit, Plasticity Index (LL, PL, and PI) ...................D4318 ............................. $190/Test Liquid Limit ...........................................................................................D4318 ............................. $105/Test Plastic Limit ..........................................................................................D4318/CTM 204 ............. $105/Test Specific Gravity,Fine (<4.75mm diameter materials) ...............................D854 ............................... $150/Test Specific Gravity,Coarse (>4.75mm diameter materials) ...........................C127 ............................... $130/Test Proctor Compaction Test Method A or B (<25% retained on a 3/8” sieve) ..................................D698/D1557 ................... $240/Test Method C (>25% retained on a 3/8” sieve) ..........................................D698/D1557 ................... $290/Test Moisture Density Single Point, std/mod (Proctor check point) ...........D698/D1557 .................... $90/Point Moisture Density Curve ............................................................................CTM 216 ......................... $260/Test Percent Organic Matter by Muffle Furnace .............................................D2974 ............................. $115/Test Permeability / Conductivity Testing Hydraulic Conductivity, Fixed Wall, up to 6” Diameter Cell .....................Modified ......................... $315/Test Flexible Wall Method, 1” to 4” Diameter Sample ....................................D5084 ............................. $370/Tes t Strength and Consolidation Testing Consolidation Testing Consolidation Test (single point) .........................................................D2435 ............................. $105/Test Consolidation Test (without rate data) ................................................D2435 ............................. $190/Test Test rate data per load increment .......................................................D2435 ...................... $80/Test-Load Expansion/Collapse Testing Expansion Index of Soils .......................................................................D4829 ............................. $180/Test Expansion Indext Test w/Cement or Lime treated soils ......................D4829 ............................. $230/Test Strength Testing Unconfined Compressive Strength (UC), 2-3”......................................D2166 ............................. $125/Test Triaxial Compression Unconsol.-Undrained Triax. Compression (UU), 2-3”, 1-pt test ...........D2850 ............................. $215/Test Consolidated Undrained Triax. Compression (CU), 2-3” (per point) ....D4767 ............................ $500/Point Consolidated Drained Triax. Compressions (CD), 2-3” (per point).......D7181 ............................ $745/Point Direct Shear Direct Shear Test (saturated) ...............................................................D3080 .............................. $90/Point Direct Shear Test (saturated, recycled – strain rate 0.0042”/min) ......D3080 ............................ $180/Point Direct Shear Test (consolidated drained) .............................................D3080 ............................ $205/Point Direct Shear Test (consolidated drained, residual) ..............................D3080 ............................ $350/Point Direct Shear Test (at natural moisture) ...............................................D3080 .............................. $80/Point R-Value .....................................................................................................D2844/CTM301 .............. $280/Test G-19 Schedule 2025 SoCal Effective Through 12/31/2025 2025 FEE SCHEDULE TEST NAME TEST METHOD UNIT RATE Aggregate Testing Sand Equivalent ........................................................................................D2419/CMT 217 ............. $100/Test Durability Index (coarse) ..........................................................................D3744/CMT 229 ............. $200/Test Durability Index (fine) ...............................................................................D3744/CMT 229 ............. $180/Test Soil with Amendments and Slurry Testing R-Value (lime- or cement-treated soils) ...................................................D2844/CTM301 .............. $330/Tes t Compressive Strength, Soil-Cement .........................................................D1633/D1632 ................ $205/Point Pocket Penetrometer ......................................................................................................................... $20/Test Soil Chemistry pH of Soil ............................................................................................................................................ $25/Test Chloride Content (subcontracted) ............................................................CTM 422 ........................... $65/Test Sulfate Content (subcontracted) ..............................................................CTM 417 ........................... $65/Test Soil Resistivity (subcontracted) ................................................................G57/CTM 643 ................. $150/Test Corrosion Series (Min. resistivity, pH, SO4, Cl; subcontracted) ........................................................ $240/Test All test methods are ASTM unless otherwise noted. Special sample preparation and laboratory testing not listed above will be charged at applicable personnel rates. All laboratory test rates are for standard turn-around time and normal reporting procedures. Rush orders will be subject to a 25 percent premium. Manpower requirements or test protocol may preclude the granting of a rush request. G-20 Page 1 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 City of Rancho Palos Verdes Request for Proposal Portuguese Bend Landslide Remediation Project Public Works Department Attention: Ramzi Awwad, Public Works Director 30940 Hawthorne Blvd, Rancho Palos Verdes, CA 90275 Phone: 310-544-5275 | Email: rawwad@rpvca.gov RFP Release Date: July 9, 2025 RFP Submittal Deadline: July 16, 2025 H-1 Page 2 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 Portuguese Bend Landslide Remediation Project The City of Rancho Palos Verdes is requesting proposals from qualified consulting firms to prepare plans, specifications, construction documents, and associated items such as permits and environmental documents, for the Portuguese Bend Landslide Remediation Project. All correspondence and questions regarding this RFP should be submitted via email to: Ramzi Awwad, Public Works Director Email: rawwad@rpvca.gov Please submit an electronic version of your proposal to the above email address by 5:30PM, on July 16, 2025 H-2 Page 3 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 TABLE OF CONTENTS I. Introduction Page 4 II. Project Objective Page 4 III. Project Description and Background Page 4 IV. Scope of Services Page 5 V. Preliminary Project Schedule Page 8 VI. Submittal Requirements Page 9 VII. Evaluation and Selection Process Page 11 VIII. Attachment A – Sample Professional Services Agreement H-3 Page 4 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 I. INTRODUCTION The City of Rancho Palos Verdes (City) is a scenic, upscale, residential coastal community, with a population of approximately 42,000, located on the Palos Verdes Peninsula of southwestern Los Angeles County. The City is a contract city, meaning that some services are provided by contract with agencies (both public and private) and some services are delivered by the City’s own employees. City Government: Rancho Palos Verdes is a General Law City and has operated under the Council-Manager form of government since its incorporation in 1973. Policy-making and legislative authority are vested in the governing City Council, which consists of five Council Members, including the Mayor and Mayor Pro-Tem. The City is fiscally sound and functions on an annual budget cycle. The purpose of this document is to provide proposers with the information needed to submit a proposal for review by the City and enter into a Professional Service Agreement with the City. Enclosed is a blank Professional Services Agreement form for proposers’ review. II. PROJECT OBJECTIVE The object of the Portuguese Bend Landslide Remediation Project (Project) is to stabilize the Portuguese Bend Landslide within the Greater Portuese Bend Landslide Complex by reducing the rate of movement to a negligible amount. III. PROJECT DESCRIPTION AND BACKGROUND The City faces an escalating geohazard due to the reactivation and worsening of the Portuguese Bend Landslide (PBL) – an ancient landslide area spanning 240 acres that has remained unstable for decades. Efforts to remediate the PBL began in 2017 and resulted in a 2018 Feasibility Study as well as a concept plan used to prepare a Draft Environmental Impact Report (DEIR) in 2023. However, subsequent consecutive years of record rainfall significantly intensified land movement. Portions of the slope have recently moved up to one foot per week and are now shifting 1–3 inches per week. The increasing velocity threatens critical infrastructure and regional public safety. Completion of the PBL Remediation Project requires modifying the scope of the concept plan and completing final engineering as well as associated items such as permits and environmental documents. The overall concept is not expected to change; however, the type, number, and location of dewatering wells must be updated. H-4 Page 5 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 IV. SCOPE OF SERVICES The City is requesting a proposal to prepare accepting proposals to prepare final plans, specifications, construction documents, and associated items such as permits and environmental documents. SCOPE OF WORK 1. Studies, Investigations, Computer Models, and Reports: Prepare all studies, investigations, computer models, and reports necessary to inform the preparation of construction documents to mitigate the Portuguese Bend Landslide to a negligible rate of movement and provide long-term protection from recurring landslide activity including from future intense and prolonged rainfall events by addressing the root cause of the landslide, i.e. the proposed improvements. 2. Construction Drawings/Plans, Specifications, and other Documents: Prepare construction drawings/plans, specifications, and any other documents necessary for a construction contractor to construct the proposed improvements. a. Construction plans shall include all necessary sheets, including but not limited to cover sheet, general notes, boundary/topographic survey, existing site plan, demolition plan, proposed site plan, plan and profile, restoration plan, utility conflict management or relocation plan, erosion control plan, stormwater pollution prevention plan, traffic control plans, staging and logistics plan, and construction details with all necessary details and notes pertinent to the project. b. All construction plan sheets shall be stamped by a licensed Professional Engineer registered in the State of California. Surveys shall be stamped by a licensed Land Surveyor registered in the State of California. c. All construction plan sheets shall include a box for City administrative approval by the Director of Public Works in the signature block. d. All construction plans shall be delivered to the City electronically in PDF format. e. Upon completion of design, native files (.dwg, models, etc.) shall be provided to the City. 3. Cost Estimate: Develop a comprehensive cost estimate of the proposed improvements. a. Cost estimate shall include details by category of work and shall include all items necessary to for the improvements to be constructed and transferred to the City, including items such as, but not limited to, professional services. 4. Schedule Management: Develop a detailed project schedule using the critical path method. Schedule shall encompass the start of the project through completion of all identified tasks. H-5 Page 6 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 a. Regularly assess progress of work, identify schedule risks and develop mitigation strategies to avoid delays, document realized delays with reason for delay, develop plan to recover from schedule delays. b. Provide timely schedule updates to City. 5. Staff Report and Presentation to the City Council: Prepare and deliver a staff report and presentation of the proposed improvements to the City Council. 6. Environmental Compliance Documents: Prepare all documents necessary for third-party completion of Environmental and Historic Preservation requirements pursuant to NEPA and federal funding. 7. Utility and Agency Coordination: Coordinate with all utility companies and other agencies affected by the proposed improvements. a. Identify any conflict or need for coordination with a utility company or other agency. b. Obtain needed information. c. Communicate with each utility company or agency to determine the need for adjustment and details. d. Prepare and submit utility relocation documents per requirements of each utility. e. Prepare and submit coordination documents with each affected agency. 8. Property Acquisitions and Easements: Prepare documents for any property acquisitions and easements necessary to construct the proposed improvements. a. Determine if property acquisition or easements are required to implement the project; delineate such needs graphically by preparing partial plans and exhibits as necessary. b. Recommend alternatives to avoid property acquisition and easements, if possible, with advantages and disadvantages of each alternative. 9. Permits: Prepare all necessary documents to obtain permits to construct the proposed improvements. a. Identify any needed permits from the City and from external agencies. b. Prepare and submit permit application packages to each agency. 10. Construction Procurement: Prepare all documents necessary to procure a construction contractor to construct the proposed improvements in compliance with federal funding requirements. a. Prepare a Notice Inviting Bids using the final plans, specifications, and bid documents combined with the City’s standard forms and contract. b. Conduct a pre-bid conference including preparing an agenda, chairing the conference, and producing meeting minutes. c. Respond to Requests for Information during the bidding process. H-6 Page 7 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 d. Evaluate bids and make a recommendation to award in compliance with federal funding requirements. Prepare a memorandum documenting the recommendation including, at a minimum: i. Determining if each bid is responsible and responsive. ii. Irregularities. iii. Significant deviations of a bid from other bids that may indicate a lack of understanding of the bid documents. iv. Lowest responsible and responsive bid. e. Prepare a City Council staff report, using the City’s template, to recommend award of a construction contract. f. Prepare and deliver a presentation to the City Council to recommend award of a construction contract. 11. Administration & Coordination: Meet with City Staff and provide a weekly update, obtain guidance, resolve issues, and receive decisions. At a minimum, the following items shall be included in the weekly updates: i. Summary of activities from prior week. ii. Summary of activities for upcoming weeks. iii. Design budget status. iv. Design schedule status. Consultant shall complete other tasks deemed necessary for the accomplishment of a complete and comprehensive outcome as described in the project objective. Consultant shall expand on the above-noted tasks, where appropriate, and provide suggestions which might lead to efficiencies and enhance the results or usefulness of the work. Deliverables As part of the Services, Consultant will prepare and deliver the following tangible work products to the City. 1. Studies, investigations, computer models, and reports. a. Draft b. Final 2. Construction drawings/plans, specifications, and other documents; cost estimate, and schedule. a. 60% b. 90% c. Final 3. Staff report and presentation to the City Council. a. 90% b. Final 4. Environmental Compliance Documents: a. 60% H-7 Page 8 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 b. 90% c. Final 5. Utility and agency matrix of conflicts and resolution, communication records, relocation request documents, and agreements. a. Draft b. Final 6. Property acquisitions and easement needs matrix, drawings, partial plans, exhibits, alternatives with advantages and disadvantages. a. 60% b. 90% c. Final 7. Permit needs matrix and permit application packages. a. Draft b. Final 8. Noticer inviting construction bids compliant with federal funding requirements, pre-bid agenda and meeting minutes, Request for Information responses, bid evaluation and recommendation memo compliant with federal funding requirements, and City Council staff report recommending award of construction contract. a. Draft b. Final 9. Summary of activities, issues, and progress. a. Weekly City staff may request that check-sets or working versions of documents be submitted for ongoing routine review. City staff will review all deliverables, including preparatory or record materials for service deliverables, and provide comments. Consultant is required to revise draft deliverables to address City staffs’ comments. V. PRELIMINARY PROJECT SCHEDULE A. RFP Schedule The following is the anticipated schedule for the RFP process: Request for Proposal issued July 9, 2025 Proposal due July 16, 2025 Notice of Award August 6, 2025 B. Anticipated Project Schedule Draft Deliverables 1, 5, and 7 September 15, 2025 60% Deliverables 2, 4, and 6 September 15, 2025 H-8 Page 9 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 90% Deliverables 2, 3, 4, 6, and 8 December 31, 2025 Final Deliverables 1, 2, 3, 4, 5, 6, 7, and 8 January 31, 2025 Deliverable 9 Weekly Please note that this schedule is preliminary. It is included to provide the Consultant with a sense of the expected timeline for the Scope of Service and emphasize the urgent nature of the work and the City’s expectation that the Scope of Services will be completed as quickly as possible. VI. SUBMITTAL REQUIREMENTS 1. The submittal should be typed and as brief as possible while adequately describing the qualifications of the firm. The final submittal shall be sent as a PDF via email to Ramzi Awwad, Public Works Director, at rawwad@rpvca.gov. 2. The proposal shall include the following information, including the same information for subcontractors, in the following format: a) Cover Letter: Provide the name, address, and phone number of the firm; the present staff (size, classification, credentials); the primary contact’s name, phone number, and email address; any qualifying statements or comments regarding the proposal; and identification of any sub-consultants and their responsibilities. Identify the firm’s type of organization (individual, partnership, corporation), including names and contact information for all officers, and proof that the organization is currently in good standing. The proposal shall include the DUNS registration number recognizing the firm’s ability to work on federally funded projects. (No more than one page) b) Approach to Scope of Services: State the Scope of Services with any additions, expansions, clarifications, modifications, value-adding strategies, or innovations such that the deliverables contained in this RFP can be most comprehensively and efficiently delivered. (No more than one page) c) Organization and Staffing: Identify the person who will be the Project Manager and primary contact person responsible for the overall delivery of the project. Provide an organizational chart of the project team that clearly delineates communication and reporting relationships among the project staff and among the sub-consultants involved in the project. Identify key personnel to perform work in the various tasks and include major areas of subcontracted work. Indicate the expected contributions of each staff member in time as a percentage of the total effort. Specifically show the availability of staff to H-9 Page 10 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 provide the necessary resource levels to meet the City’s needs. Indicate that the Project Manager and key staff will remain assigned to this project through completion of the Scope of Services and that City approval is required for any changes to key staff. (No more than two pages) d) Staff Qualifications and Experience: Describe qualifications of the assigned staff and sub-contractors including relevant technical experience. Staff assigned to complete the Scope of Services must have previous experience in providing the necessary services as described under the Scope of Services. A registered Certified Engineering Geologist be the Project Manager. Description of Consultant’s experience should include: • Prior Experience: Demonstrate that the firm has significant experience providing services similar to those described under the Scope of Services. (No more than two page) • Staff Qualifications: Provide resumes for the Project Manager and any other key staff members to be assigned to contribute to the Scope of Services, with an emphasis on similar services which they provided to other agencies. (No more than five pages) • Reference Projects: Include at least three projects with similar scope of services performed by the project team within the past three years and indicate the specific responsibilities of each team member on the reference project. Provide contact information for each client. (No more than three pages) e) Project Schedule: Provide a detailed critical-path-method schedule for completion of the tasks and sub-tasks required to accomplish the scope of work. Note all deliverables and interim milestones on the schedule. (No more than one 11” x 17” page) f) Quality Control Plan: Describe the quality control procedures and associated staff responsibilities which will ensure that the deliverables will meet the City’s needs. (No more than one page) g) Acceptance of Conditions: State the offering firm’s acceptance of all conditions listed in the Request for Proposal (RFP) document and Sample Professional Services Agreement (Attachment A). Any exceptions or suggested changes to the RFP or Professional Services Agreement (PSA), including the suggested change, the reasons therefore and the impact it may H-10 Page 11 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 have on cost or other considerations on the firm’s behalf must be stated in the proposal. Unless specifically noted by the firm, the City will rely on the proposal being in compliance with all aspects of the RFP and in agreement with all provisions of the PSA. 3. The proposal shall include proposed fee detailed by task and sub-task to a sufficient level such that an independent third-party cost estimate can be performed to validate that the fee is consistent with industry fees for a similar scope of services. VII. EVALUATION AND SELECTION PROCESS 1. The Proposals Will be Evaluated Based on the Following Criteria: a) Approach to Scope of Services (30%) • A proposed Scope of Services that results in comprehensively and efficiently completing the deliverables contained in this RFP. b) Staff Qualifications and Experience (30%) • Relevance of experience of the proposing firm (to provide support resources to the project team) • Relevance of experience and strength of qualifications of the Project Manager • Relevance of experience and strength of qualifications of the key personnel performing the work • Relevance of referenced projects and client review of performance during those projects c) Proposal Schedule (30%) • Ability to complete the work in the shortest schedule possible (excluding time for review and community meetings). d) Quality Control (10%) • Adequate immediate supervision and review of staff performing the work as well as appropriate independent peer review of the work by qualified technical staff not otherwise involved in the project. 2. Award Notification The City will notify the proposer of the outcome of the evaluation process and intent to award. This RFP does not commit the City to award an agreement, nor pay any costs incurred in the preparation and submission of the proposal in anticipation of an agreement. The City reserves the right to reject any or all proposals, or any part thereof, to waive any formalities or informalities, and to award the agreement to the proposer deemed to be in the best interest of the City and the Department. H-11 Page 12 of 12 City of Rancho Palos Verdes RFP- Portuguese Bend Landslide Remediation Project July 9, 2025 3. Award of Agreement The selected firm shall be required to enter into a written agreement (see sample City agreement in Attachment A) with the City, in a form approved by the City Attorney, to perform the Scope of Services. This RFP and the proposal, or any part thereof, may be incorporated into and made a part of the final agreement; however, the City reserves the right to further negotiate the terms and conditions of the agreement with the selected consultant. H-12 Funding source for future needs undetermined -$ 2,712,044$ 700,000$ 19,995,000$ Committed as of 4/17/2025 2,500,000$ 2,000,000$ 1,500,000$ 29,407,044$ -$ -$ N/A FUNDING FY25/26 FY26/27 FY27/28 FY28/29 FY29/30 Future Fiscal Years Engineering $ 350,000 $ 1,290,000 -$ The Portuguese Bend Landslide creates a number of challenges for the City and the community including damage to Palos Verdes Drive South, utilities, and public and private properties. The completion of this project will help minimize movement in the Portuguese Bend Landslide, thereby minimizing potential impacts to the surrounding environment including marine life in the event the existing above-ground sewer lines are damaged. It will also minimize damage to public and private properties, including the roadway, and will alleviate the need for the annual Palos Verdes Drive South Landslide Repair Program. Estimated annual operating / maintenance cost TBD ESTIMATED SCHEDULE Planning (Grant Administration and Procurement) begins in Fiscal Year 2023-24 and continues into 2024-25 Engineering and Environmental in Fiscal Year 2025-26 Work beyond Fiscal Year 2026-27 is dependent on identifying available funding sources. Project Location Map Background and Justification -$ 2,712,044$ 700,000$ TBD TBD TBD TBD -$ $2,500,000 $ 2,000,000 $ 1,500,000 330 (CIP Fund) 220 (Measure R)292,300$ -$ Construction Funding Unknown - Pursuing Various Grant Opportunities 2,419,744$ 700,000$ $ - $ 12,900,000 $ - $ 645,000 Project Contingency $ - $ 3,870,000 Inspection $ - $ 645,000 Construction Management Insert Descriptive Photo PROJECT DESCRIPTION This project is intended to slow movement of the Portuguese Bend Landslide to a negligible rate and consists of the following elements: - Infilling fissures in the earth to prevent rainwater infiltration - Installing context sensitive, long-term drainage systems - Installing hydraugers to intercept and/or extract groundwater - Installing deep dewatering wells (DDWs) to extract groundwater - Operations and maintenance of the DDWs Note: The scope of work does not include separate dewatering and drainage elements that would need to be implemented by KCLAD and ACLAD to provide for a comprehensive landslide remediation plan. PROJECT COST ESTIMATES $ 645,000 Overall Planning $ - $ - FY25/26 FY26/27 FY27/28 FY28/29 FY29/304/17/2025 Committed as of Environmental $ 350,000 8300 Series Landslide Improvement Projects 8304 Portuguese Bend Landslide Remediation I-1