Loading...
CC SR 20250715 03 - SCE Ladera Linda Pole Update CITY COUNCIL MEETING DATE: 07/15/2025 AGENDA REPORT AGENDA HEADING: Regular Business AGENDA TITLE: Consideration to approve permanently relocating a Southern California Edison (SCE) temporary power pole currently at the Ladera Linda Community Park. RECOMMENDED COUNCIL ACTION: (1) Review the power pole relocation design options prepared by both City Staff and SCE; (2) Determine if SCE’s design option is most practical for a permanent solution, and if acceptable, authorize City Staff to coordinate with SCE to remove the temporary power pole located at the Ladera Linda Community Park and permanently relocate it using SCE’s overhead option and under the terms and conditions of the City- approved encroachment permit; and (3) Authorize the City Manager to approve the required easement on City land for the implementation of the overhead variation of the City’s preferred option to permanently relocate the temporary power pole located at the Ladera Linda Community Park. FISCAL IMPACT: There is no fiscal impact to the City for the recommended action, if deemed acceptable by the City Council. Costs to relocate the temporary power pole from Ladera Linda Community Park to a permanent location using SCE’s above-ground design solution will have no cost to the City except for staff and consultant time to review project plans. Furthermore, future maintenance costs of the above- ground wires and power pole would be borne by SCE. Amount Budgeted: N/A Additional Appropriation: N/A Account Number(s): N/A ORIGINATED BY: Deanna Fraley, PE, Principal Engineer REVIEWED BY: Ramzi Awwad, Director of Public Works APPROVED BY: Ara Mihranian, AICP, City Manage ATTACHED SUPPORTING DOCUMENTS: A. City’s Proposed Box Loop Design (page A-1) B. City Manager Letter to SCE – May 23, 2025 (page B-1) 1 C. SCE Response Letter to City – May 30, 2025 (page C-1) D. March 4, 2025 City Council Staff Report (page D-1) E. SCE’s Original Proposed Box Loop Design - Overhead (page E-1) F. September 3, 2024 Terms and Conditions of the City-Issued Encroachment Permit with SCE (page F-1) BACKGROUND: On Wednesday, August 21, 2024, Staff at the Ladera Linda Community Park (LL Park) encountered a SCE crew initiating unpermitted and unannounced work to install a power pole and guy wire in the outdoor recreational area east of the community center building (see Figure 1 below). Figure 1- Existing Temporary SCE Power Pole at Ladera Linda Community Park Starting location of unpermitted SCE work for a guy wire 2 When asked about this unpermitted work, SCE explained that the electrical infrastructure on the west end of Dauntless Drive (near where it turns into Admirable Drive) supplied power to approximately 40 homes along the landward side of Dauntless Drive, but needed to be decommissioned, due to extreme stress from land movement. To avoid a permanent outage, SCE developed plans to connect those homes to existing infrastructure from the east end of Dauntless Drive, within the vicinity of LL Park. SCE planned to install one power pole at LL Park and five more along the right-of-way on Dauntless Drive. These new power poles would provide the Dauntless Drive homes with a connection to a power source that runs from Palos Verdes Drive South along Forrestal Drive. Establishing this connection would enable SCE to only de-energize the failing electrical infrastructure on the west end of Dauntless, thereby avoiding an outage for the 40 homes generally east of the Exultant and Dauntless Drives intersection. The City expressed strong opposition to the power pole at LL Park and sought alternative routes that included undergrounding lines or obtaining easements from homeowners. However, SCE indicated that those alternatives would require additional time to implement, which meant that long-term de-energization would be necessary for the 40 homes along the landward side of Dauntless Drive while alternatives were considered and implemented. As a result, on August 29, 2024, Staff authorized SCE to temporarily install the pole at LL Park and agreed to issue a retroactive encroachment permit with conditions. The conditions to the retroactive permit stipulated, among other things, that the temporary pole be relocated within 6 months, with an option to extend for two additional 3-month extensions, provided SCE makes good faith progress in designing a permanent solution and maintains regular communication with the City. On September 3, 2024, the City Council directed staff to continue processing the encroachment permit for SCE under the aforementioned terms and conditions (Attachment F). On March 4, 2025, Staff requested that the City Council approve a three-month extension to continue working with SCE on an appropriate permanent solution and relocation of the power pole at LL Park (Attachment D). After consideration of information presented that evening including testimony from residents, SCE and City Staff, the City Council approved a six-month extension. Since the City Council-approved extension, Staff and SCE have discussed various design routes for the temporary power pole relocation, including proposals developed by SCE and City Staff. The City Council is now being asked to review the design options and identify the most practical relocation of the power pole at LL Park. DISCUSSION: On January 23, 2025, SCE presented Staff with two proposed options (Attachment E) to remove the temporary pole at LL Park. One option was to reroute the electrical service along Forrestal and Main Sail (also known as Intrepid) Drives, as shown in Figure 2. The 3 City expressed a concern with this route due to a higher risk for wildfires adjacent to open space Preserve land. Another option was along Schooner Drive, also shown in Figure 2. SCE indicated that the Schooner Drive option would require new poles and easements which may be difficult to secure from affected property owners. City Staff emphasized the City’s desire to underground any new infrastructure for aesthetic reasons and wildfire risk concerns. SCE noted that they were skeptical about how undergrounding would work in this area due to the slope grade and proximity of houses and pools close to the property lines. Additionally, SCE stated that the new route would maintain the SCE standard with covered conductors and poles designed to mitigate wildfire risk. Figure 2- Forrestal and Main Sail/ Intrepid Drive Electrical Route Additionally, Staff were informed by SCE that it is their policy to implement the overhead version of any project that can be designed above ground in order to reduce the cost; therefore, the City would have to pay for any undergrounding using City funds. Since the two options were presented, Staff and the City’s contracted firm, Transtech Engineers, continued discussions with SCE to further refine a new route that meets SCE’s requirements and is most suitable for the City under the constraints . Through these discussions, Transtech and City staff developed alternative designs which could be implemented in an underground or overhead configuration, as shown in Figure 3 on the following page. Staff proposed and recommended an underground option due to the area 4 being in a Very High Fire Hazard Severity Zone along with the utility pole and its scenic implications. Figure 3 – City Preferred Route (Underground) The overhead variation of the City’s alternative design consists of placing approximately 215 feet of overhead primary wire from an existing pole near the corner of Dauntless Drive and the stairs to LL Park, to a new pole just north of the lot at 3495 Daun tless Drive, and then continuing with approximately 100 feet of primary wire to the next existing pole. It should be noted that the intent of the design is to place the new power pole such that it would no longer be in the viewing frame as observed from the LL Park grounds. The maximum height of the power pole is expected to be approximately 45 feet, as measured from adjacent grade to the top of the power pole. Attachment A depicts the proposed concept. Although Staff brought these concerns to SCE, they rejected the new underground proposal but did offer to change their proposed route to an overhead variation utilizing the City’s design. SCE indicated that they did not believe the underground configuration 5 was feasible or practical due to the existing terraced slopes, and even if it was, the cost of undergrounding would need to be borne by the City. For those reasons, SCE stated that their preferred option remains an overhead configuration utilizing the City’s proposed alternative design as shown in Figure 4 below. Even with these options designed to keep all existing and proposed facilities on City owned property, SCE further affirmed that they will refuse to maintain the underground option if the City chose to go that route. Figure 4 – SCE Preferred Route (Overhead) On May 23, 2025, the City Manager sent a letter to SCE President, Steve Powell, requesting he and SCE staff, among other things, reconsider the undergrounding option and to recall the recent wildfires in the surrounding communities of Southern California where SCE is undergrounding replacement infrastructure at their cost (Attachment B). On May 30, 2025, the City received a response letter from SCE Executive Vice President, Jill Anderson, reaffirming their decision to not underground the City’s preferred route (Attachment C). Due to the additional costs for underground and lack of maintenance commitment from SCE, the City Council is being asked to consider proceeding with the overhead 6 configuration of the revised option (Figure 4) so that the temporary pole at LL Park can be removed and relocated whereby the new power pole will not be in the view frame as observed from LL Park. In order to proceed with the overhead option, the City will need to provide a public utility easement to SCE, so they can install, access, and maintain their new infrastructure. If acceptable, the City Council is also being asked to authorize the City Manager to proceed with required easement documents to allow the permanent power pole to be relocated on the slope at LL Park which will be outside the view frame from the park grounds. SCE estimates that they can prepare their design, provide the easement documents to the City, and complete installation within approximately two to three months. CONCLUSION: The City Council is being asked to consider approving relocating the temporary power pole at the LL Park with a new permanent electrical service alignment consisting of overhead lines and poles and provide necessary easements, based on SCE’s position that they will not pay for nor maintain an underground alignment, even if the City bears the cost of installation. ALTERNATIVES: In addition to Staff’s Recommendations, the following alternative actions are available for the City Council’s consideration: 1. Do not approve the overhead option thereby making the temporary power pole at the LL Park permanent. 2. Direct Staff to further investigate the feasibility and cost for implementing an underground option to remove the temporary power pole from the LL Park. 3. Take other action as the Council deems appropriate. 7 A-1 A-2 ADMINISTRATION DEPARTMENT CITY MANAGER’S OFFICE 30940 HAWTHORNE BLVD. / RANCHO PALOS VERDES, CA 90275-5391 / (310) 544-5207 / FAX (310) 544-5291 / WWW.RPVCA.GOV May 23, 2025 Via email and U.S. Mail Steven D. Powell President and Chief Executive Officer Southern California Edison 2244 Walnut Grove Avenue Rosemead, CA 91770 SUBJECT: Greater Portuguese Bend Landslide Update and the Ladera Linda Community Center SCE Box Loop Project Dear Mr. Powell, On behalf of the Rancho Palos Verdes City Council and community, I am writing on matters related to the Greater Portuguese Bend Landslide Complex (Landslide Complex) and the Ladera Linda Community Center Box Loop Project (Project). As you are aware, on October 3, 2023, the Rancho Palos Verdes City Council declared a local state of emergency in response to the accelerated rate of movement of the Landslide Complex. The City has been monitoring land movement within the Landslide Complex since 2007 using Global Position System (GPS) monitoring points at over 100 points. Since October 2022, in certain areas of the Landslide Complex, the rate of movement has been documented at approximately 12 inches a week. As you are aware, Southern California Edison (SCE) along with SoCalGas and Cox Communications indefinitely shut-off service to properties within the Portuguese Bend Community Association (PBCA), Seaview, and Portuguese Bend Beach Club (PBBC) neighborhoods in and around August and September 2024. In September 2024, the City began installing and operating Deep Dewatering Wells (DDWs) along the toe of the Landslide Complex based on recommendations made by the City’s Geotechnical Consultants. Soon after operating the DDWs, the City began to see a sudden and significant reduction in the rate of movement especially in the Seaview and PBBC neighboring. On January 13, 2025, Mayor Bradley, Councilmember Perestam, Public Works Director Awwad and myself met with you and members of SCE’s staff to B-1 2 discuss the reduced rate of movement and our request to re-energize the area including the City’s DDWs which have been powered by generators. At this meeting, we were informed that SCE would consider re-energizing neighborhoods if the rate of movement measured less than 1 inch per week, and because the rate of movement in the Seaview and PBBC neighborhoods met that threshold, these two neighborhoods would be re- energized in the weeks to come. In and around March 2025 and up to now, SCE has been re-energizing these neighborhoods which has been welcomed news for many affected by the power shut-offs. As of April 2025, the PBBC and Seaview neighborhoods continue to measure undetectable movement while the PBCA is measuring movement around 4 inches a week (Attachment A). In light of current rate of movement in the PBCA, the City is requesting SCE reconsider its threshold for re-energizing this neighborhood. The City’s cost to respond to the acceleration of the Landslide Complex is projected to total approximately $48.5 million between October 2022 and June 30, 2025. The City’s cost for the current fiscal year is estimated to be over $37 million. The City’s cost responding to land movement is roughly equivalent to the City’s General Fund budget of $39 million for the current fiscal year. Of this cost, the City is projected to spend approximately $3 million this fiscal year to maintain and operate the DDWs which includes the fuel for the generators powering the DDWs. If power were restored to this area, this would save the City costs incurred for fueling the DDWs which have been instrumental in slowing and stabilizing the landslide. Moreover, restored power in the PBCA will also result in a cost savings to the Abalone Cove Landslide Abatement District (ACLAD) who also manage and operate DDWs with generators in the area. As you are aware, City Staff has been working closely with SCE on a solution to relocate the errant power pole that was installed at the Ladera Linda Community Park (LLCP). Although the teams have been making progress in the discussions, I am writing to request that SCE move forward with the underground option, at their cost, to resolve this issue. For background purposes, on Wednesday, August 21, 2024, Staff at the LLCP encountered an SCE crew initiating unpermitted and unannounced work to install a power pole and guy wire in the outdoor recreational area east of the LLCP building (Attachment A). SCE had neither obtained permits/approvals/easements/licenses to install equipment on City park property nor coordinated with City Staff in advance. Therefore, the City immediately issued a formal stop work order. Subsequently, SCE indicated the need to expeditiously install a power pole at LLCC to continue providing power to approximately 40 homes along the landward side of Dauntless Drive, a portion of which lies in the west side of Seaview, which has been severely impacted by land movement. The City expressed strong opposition to the pole at LLCC and sought alternative routes that included undergrounding lines or obtaining easements from homeowners. However, SCE indicated that those alternatives would require additional time to implement and may result in indefinite outages for residents. B-2 3 Given the importance of resolving the matter quickly and ensuring continued electrical service to the Seaview community, the City authorized SCE to complete installation of the pole at LLCC (Attachment B) and issued a retroactive encroachment permit with certain conditions. One of the key conditions was that the temporary pole must be relocated within 6 months, with an option to extend for 2 additional 3 -month periods, provided SCE makes good faith progress in designing a permanent solution to relocate the pole. Since that time, City Staff and SCE have been meeting on a regular basis to identify a mutually agreeable final design for this circuit that would provide power to the 40 homes on the landward side of Dauntless Drive. To allow more time for City Staff and SCE to work together towards a solution, on March 4, 2025, the City council authorized a 6-month extension to the terms and conditions of the encroachment permit. There are the following design options that have been discussed between the City and SCE for the box loop project: Forrestal Drive and Main Sail Drive – Option A (Attachment C) SCE presented the City with an option to place new poles and overhead lines along Forrestal Drive and Main Sail Drive, as shown in Attachment B. City Staff expressed concern with this option because it would increase the risk of wildfires with the introduction of new vertical poles at the edge of Forrestal Reserve, a subarea of the overall Palos Verdes Nature Preserve. Additionally, it would require the installation of 10 new poles. Schooner Drive – Option B (Attachment C) SCE presented the City with a second option to place new poles and overhead lines in the vicinity of Schooner Drive, as shown in Attachment B. City Staff preferred this option; however, City Staff proposed that a portion of the route be placed underground to reduce the risk of wildfire. SCE shared that the new re -route would maintain the SCE standard with covered conductors and poles designed to mitigate wildfire risk. Additionally, SCE expressed skepticism that the underground option was feasible because o f the grade and proximity of houses and pools to the property lines. Dauntless Drive Undergrounding – Option C (Attachment D) Building upon discussions with SCE, the City is proposing an undergrounding option, as shown in Attachment C. This option involves interconnecting to the existing primary wires, installing a new underground primary conductor with a new pole and riser which then interconnects to the exiting primary wires. City Staff believes that this alternative would save SCE money from their original proposal. Further, the City is willing to provide all necessary easements required to install this underground alternative. Considering the recent wildfires, the City is formally requesting SCE pay for the undergrounding alternative (Option C as shown in Exhibit C) as this has been done in other high-fire communities. Undergrounding approximately 220 lineal feet is likely less expensive than SCE’s originally proposed overhead solution (10 poles + covered conductor) and should not financially impact SCE’s rate payers. B-3 4 I look forward to hearing from you as soon as possible and resolving this matter by the end of this month as I must report SCE’s final decision to the City Council and community at the June 17, 2025 City Council meeting. Best Regards, Ara Michael Mihranian, AICP City Manager cc: Pedro J. Pizarro, President and Chief Executive Officer, Edison International Caroline Choi, Senior Vice President of Corporate Affairs and Public Policy, SCE Larry Chung, Vice President, Customer Engagement Division, SCE Haig Kartounian, Senior Advisor of Local Public Affairs, SCE Celina Luna, Government Relations Manager, SCE Jeremy Califano, PE, PMP, Senior Manager, SCE Rancho Palos Verdes City Council William Wynder, City Attorney Catherine Jun, Deputy City Manager Ramzi Awwad, Public Works Director B-4 5 Attachment A – Heat Map Displaying Movement B-5 6 Attachment B – Existing Circuit B-6 7 Attachment C – SCE Proposed Circuit Route Options B-7 8 Attachment D – City Proposed Alternative 1 – City Preferred Route B-8 May 30, 2025 Delivered via email Ara Mihranian City Manager Rancho Palos Verdes 30940 Hawthorne Boulevard Rancho Palos Verdes, CA 90275 Dear Mr. Mihranian, Thank you for your letter dated May 23, 2025. Steve Powell asked me to review and respond on behalf of Southern California Edison (SCE). We understand the ongoing challenges faced by your city and its residents, and we appreciate the close collaboration between the City of Rancho Palos Verdes and SCE. Your letter requests that SCE reconsider its land movement threshold for re-energizing the Portuguese Bend area. Based on conditions in that vicinity, SCE does not believe it would be safe or prudent to do so. While the land movement in the Portuguese Bend area has slowed since its peak last summer, the current rate of movement still poses a safety risk if SCE power lines were to be re-energized at this time. This is consistent with the letter that SCE’s Palos Verdes Peninsula Project Management Office (PMO) sent to the City and residents last month. With the safety of our customers top of mind, a continued and sustained reduction in land movement near our electrical infrastructure to less than one inch per week (i.e., pre-2023 rates) is necessary for SCE to consider re-energizing in this area. If land movement slows to that rate for an extended duration, and barring any other safety concerns, SCE will install engineering solutions and then evaluate the next steps for re-energization. We appreciate your team’s willingness to meet with the PMO regarding the Ladera Linda Box Loop and redesign options for serving the Seaview area. The PMO team has consulted with subject matter experts, and after thorough analysis by planning and construction teams, determined that the City’s preferred Option C (undergrounding the Box Loop) is not the most feasible alternative when considering the constructability and long-term maintenance associated with underground infrastructure on the proposed steep hillside. As an alternative, SCE is prepared to proceed with the overhead design version of Option C. This overhead alternative design is more cost-effective, Jill C. Anderson Executive Vice President Chief Operating Officer C-1 feasible to install and maintain long-term, and relocates the pole outside of the park and beyond the line of sight from the Ladera Linda Community Center. The safety of our customers, communities, and team members is our top priority. We remain committed to working closely with the City to find the best solutions that ensure the safety and reliability of electrical infrastructure. We appreciate your understanding and cooperation as we navigate these complex issues. I encourage you to continue working with the PMO, including Celina Luna, SCE’s dedicated Government Relations Manager for your area. Best regards, Jill C. Anderson cc: Rancho Palos Verdes (RPV) City Council William Wynder, City Attorney, RPV Catherine Jun, Deputy City Manager, RPV Ramzi Awwad, Public Works Director, RPV Caroline Choi, EVP, Public Policy & Corporate Affairs, SCE & Edison International Larry J. Chung, Vice President, Customer Solutions, SCE Jeremy Califano, PE, PMP, Senior Manager, SCE Celina Luna, Government Relations Manager, SCE Haig Kartounian, Senior Advisor, Local Public Affairs, SCE C-2 CITY COUNCIL MEETING DATE: 03/04/2025 AGENDA REPORT AGENDA HEADING: Regular Business AGENDA TITLE: Consideration and possible action to grant a time extension to Southern California Edison (SCE) for its temporary power pole located at the Ladera Linda Community Center. RECOMMENDED COUNCIL ACTION: (1) Authorize a three-month extension to the terms and conditions of the City- approved encroachment permit, reviewed by the City Council at its September 3, 2024, thereby allowing SCE’s temporary power pole to continue to be located at the Ladera Linda Community Center while a permanent box circuit is designed and constructed. FISCAL IMPACT: There is no fiscal impact to the City for the recommended action. Amount Budgeted: N/A Additional Appropriation: N/A Account Number(s): N/A ORIGINATED BY: Robert Quintero, Transtech Project Manager REVIEWED BY: Catherine Jun, Deputy City Manager APPROVED BY: Ara Mihranian, AICP, City Manager ATTACHED SUPPORTING DOCUMENTS: A. SCE’s Proposed Box Loop Design Options (page A-1) B. September 3, 2024 Terms and Conditions of the City-Issued Encroachment Permit with SCE (page B-1) C. September 3, 2024 City Council Staff Report BACKGROUND: On Wednesday, August 21, 2024, Staff at the Ladera Linda Community Center encountered an SCE crew initiating unpermitted and unannounced work to install a power pole and guy wire in the outdoor recreational area east of the Community Center building (see map below). The pole itself was intended to be placed in the bioswale directly to the south of the guy wire. It was confirmed shortly thereafter that SCE had neither obtained permits, approvals, or easements/licenses to install equipment on City property nor communicated their intent to City Staff in advance . On that same day, the City D-1 immediately halted work and issued a formal stop work order, while initiating calls and email communication with SCE to demand an explanation. In a series of email communications between SCE and City Staff, SCE indicated the need to expeditiously install a power pole at Ladera Linda to continue providing power to approximately 40 homes along the landward side of Dauntless Drive, of which a portion lies in the west side of Seaview, which has been severely impacted by land movement. SCE also cited that it had sufficient rights to place a pole in any public place, pursuant to its Franchise Agreement with the City – although that interpretation has been strongly contended by City Staff. Given the importance of resolving the matter quickly and ensuring continued electrical service to the Seaview community, the City called a meeting with SCE at Ladera Linda Community Center on August 28, 2024. It was during the meeting that the intent and purpose of the power pole was clarified. Starting location of unpermitted SCE work for a guy wire D-2 SCE explained the need to decommission electrical infrastructure on the west end of Dauntless Drive (near where it turns into Admirable Drive), because it is experiencing extreme stress from active land movement; doing so would mitigate potential wildfire risks in the event of a line break and reduce safety risk to SCE’s crews who repair equipment on these poles. Currently, that infrastructure feeds power to approximately 40 homes along the landward side of Dauntless Drive. To avoid a permanent outage, SCE developed plans to connect them to existing infrastructure from the east end of Dauntless Drive, within the vicinity of Ladera Linda Community Center. To do this expeditiously, SCE planned to install 1 pole at Ladera Linda and 5 more along the right-of-way on Dauntless Drive. These new poles would provide the Dauntless Drive homes with a connection to a power source that runs along Forrestal Drive down to Palos Verdes Drive South. Establishing this connection would then enable SCE to de-energize the failing electrical infrastructure on the west end of Dauntless, thereby avoiding an outage for the 40 homes. The City expressed strong opposition to the pole at Ladera Linda and sought alternative routes that included undergrounding lines or obtaining easements from homeowners. However, SCE indicated that those alternatives would require additional time to implement and may result in indefinite outages for residents, and that SCE would be compelled to move forward with decommissioning and de-energizing the failing electrical infrastructure near the west side of Dauntless beginning the week of September 2, 2024. As a result, City Staff, on August 29, 2024, authorized SCE to begin installation of the pole at Ladera Linda Community Center outside of the bioswale (a location identified as Alternative 1, which is where the guy wire was originally planned) and agreed to issue a binding, retroactive encroachment permit holding SCE to the following term and conditions (Attachment B): • SCE shall provide City with a detailed scope of work for the temporary pole prior to construction, including the proposed location of the pole. • The temporary pole shall be made of treated wood. • The temporary pole shall not be installed in a bioswale or other sensitive use. • When the temporary pole is removed, SCE shall restore the site to its original condition, including but not limited to landscaping and pathway work. • SCE shall maintain and repair the temporary pole, as needed, and in consultation with City shall install signage to indicate the temporary nature of the installation. • SCE shall provide City with bi-weekly updates (Tues/Thurs meetings or at other times convenient to SCE and the City) on SCE’s work towards a permanent solution. • The temporary pole must be relocated within 6 months, with an option to extend for 2 additional 3 month extensions, provided SCE makes good faith progress is designing a permanent solution and maintains regular communication with the City. • City does not interpret the 1974 franchise agreement to apply to the location of the temporary pole. D-3 • SCE shall indemnify and hold harmless the City in accordance with the provisions of the Franchise Act of 1937. On August 29, SCE accepted the conditions, and City Staff notified the Seaview and Ladera Linda HOAs of the impending work (Attachment B). City Staff issued the encroachment permit with the conditions noted on the previous page. On September 3, 2024, the City Council directed staff to continue, retroactively, processing the encroachment permit for SCE to install a temporary power pole at the Ladera Linda Community Center for a period of six months with an option to extend for 2 additional 3 month extensions, provided SCE makes good faith progress is designing a permanent solution and maintains regular communication with the City (Attachment C). The City-issued encroachment permit is set to expire on March 5, 2025 unless a time extension is granted. The City Council is being asked to authorize a three-month extension. DISCUSSION: Since September 2024, City Staff and SCE have been meeting on a regular basis to identify a mutually agreeable final design for the box circuit that would provide power to the 40 homes on the landward side of Dauntless Drive. On January 23, 2025, SCE presented City Staff with its proposed two options to reroute the box circuit loop either along Schooner Drive or along Forrestal and Main Sail (also known as Intrepid) Drives (Attachment A). The City expressed a concern with the Forrestal and Main Sail Drive option because it would introduce new vertical poles at the edge of Forrestal Reserve, a subarea of the overall Palos Verdes Nature Preserve citing a higher risk for wildfires. City Staff preferred the Schooner Drive option provided that a portion of the reroute would be placed underground. SCE indicated that the Schooner Drive option would require new poles and easements which may be difficult to secure from affected property owners. City Staff emphasized the City’s desire to underground any new infrastructure for aesthetic reasons and wildfire risk concerns. SCE shared that the new re-route would maintain the SCE standard with covered conductor and poles designed to mitigate wildfire risk. SCE noted that the underground option has not been scoped or tested for feasibility, and they were skeptical about how undergrounding would work in this area due to the slope grade and proximity of houses and pools close to the property lines. SCE mentioned that their 3rd party crane companies may not operate in such close proximity to the land movement area. SCE indicated that an additional option would be to leave the pole in the Ladera Linda Park as-is. If none of the above-mentioned options move forward and the encroachment is set to expire with no further extensions, SCE will need to remove the pole in the park, leaving approximately 40 customers without power until another solution can be established. City Staff was informed that SCE is a steward of ratepayer funds, and any project that can be designed above ground would need to proceed with the most responsible and D-4 cost-effective method. Therefore, the City would have to pay for any undergrounding along either of the routes through a Rule 20C project. In response, City Staff indicated it would need a few weeks to review SCE’s proposed options and subsequently asked the City’s contracted firm, Transtech Engineers, to review SCE’s proposed box circuit loop options and to identify if alternative routes or designs could be considered. Transtech Engineers is expected to complete its review after the transmittal of this staff report but before the March 4 City Council meeting, and any new information will be reported at the City Council meeting . Thus, the City Council is being asked to authorize granting a three-month extension in order for the City to complete its review and provide SCE with its response. ADDITIONAL INFORMATION: In order for the temporary pole at Ladera Linda Community Center to be removed without disrupting service to Seaview residents, a new design would need to be mutually accepted by the City and SCE and the new box loop circuit constructed. This is likely to take several months, if not, a year. Thus, it is likely that the City will return to the City Council with periodic updates and further time extension requests. CONCLUSION: The City Council is being asked to grant SCE a three-month time extension to the City- issued encroachment permit for the placement of a temporary power pole at the Ladera Linda Community Center. ALTERNATIVES: In addition to Staff’s Recommendations, the following alternative actions are available for the City Council’s consideration: 1. Do not authorize the requested time extension and direct SCE to remove the temporary power pole from the Ladera Linda Community Center which will result in approximately 40 homes losing power indefinitely in the Seaview neighborhood. 2. Extend the Encroachment permit by six month allowing for more time to develop a design and to construct the new box loop circuit. 3. Take other action as the Council deems appropriate. D-5 D-6 1 Catherine Jun From:Celina Luna <CELINA.LUNA@SCE.COM> Sent:Thursday, August 29, 2024 3:16 PM To:Elena Gerli; Ara Mihranian Cc:Catherine Jun; Robert Pontelle; Mark Rothenberg Subject:Re: (External):SCE authorization for Ladera Linda pole at Alternate 1 location EXTERNAL EMAIL: Do not click links or open any attachments unless you recognize the sender and know the content is safe!!!. Hi Elena and Ara, This has been received and acknowledged. SCE accepts the conditions. Thank you again for all your hard work during this emergency, particularly for working with us on this temporary solution. We look forward to continuing to collaborate in this challenging, dynamic situation. Regards, Celina Celina Luna Government Relations Manager Local Public Affairs T. 626-302-5040 |PAX. 25040 | M. 213-523-8344| Email. celina.luna@sce.com From: Elena Gerli <egerli@awattorneys.com> Sent: Thursday, August 29, 2024 2:39 PM To: Celina Luna <CELINA.LUNA@SCE.COM>; Ara Mihranian <AraM@rpvca.gov> Cc: Catherine Jun <cjun@rpvca.gov>; Robert Pontelle <Robert.Pontelle@sce.com>; Mark Rothenberg <mark.a.rothenberg@sce.com> Subject: (External):SCE authorization for Ladera Linda pole at Alternate 1 location  CAUTION: This is an external email. Be careful when opening links or attachments This message was received from outside Edison. Report Suspicious Dear Celina, this email is to authorize SCE to begin installation of the pole at the site in Ladera Linda Community Center that we identified as Alternate 1 during the 8/28 meeting with the City. The City will issue a retroactive encroachment permit with the following conditions: D-7 2 SCE shall provide City with a detailed scope of work for the temporary pole prior to construction, including the proposed location of the pole. The temporary pole shall be made of treated wood. The temporary pole shall not be installed in a bioswale or other sensitive use. When the temporary pole is removed, SCE shall restore the site to its original condition, including but not limited to landscaping and pathway work. SCE shall maintain and repair the temporary pole, as needed, and in consultation with City shall install signage to indicate the temporary nature of the installation. SCE shall provide City with bi-weekly updates (Tues/Thurs meetings or at other times convenient to SCE and the City) on SCE’s work towards a permanent solution. The temporary pole must be relocated within 6 months, with an option to extend for 2 additional 3 month extensions, provided SCE makes good faith progress is designing a permanent solution and maintains regular communication with the City. City does not interpret the 1974 franchise agreement to apply to the location of the temporary pole. SCE shall indemnify and hold harmless the City in accordance with the provisions of the Franchise Act of 1937. Please confirm receipt and acceptance of the conditions for the encroachment permit. Best, Elena Q. Gerli City Attorney City of Rancho Palos Verdes Elena Q. Gerli | Partner she/her/hers Aleshire & Wynder, LLP | 3701 Wilshire Blvd, Suite 725, Los Angeles, CA 90010 Tel: (310) 527-6660 | Dir: (424) 269-3345 | egerli@awattorneys.com This email and any files transmitted with it may contain privileged or otherwise confidential information. If you are not the intended recipient, or believe that you may have received this communication in error, please advise the sender via email and delete the email you received. D-8 E-1 1 Catherine Jun From:Celina Luna <CELINA.LUNA@SCE.COM> Sent:Thursday, August 29, 2024 3:16 PM To:Elena Gerli; Ara Mihranian Cc:Catherine Jun; Robert Pontelle; Mark Rothenberg Subject:Re: (External):SCE authorization for Ladera Linda pole at Alternate 1 location EXTERNAL EMAIL: Do not click links or open any attachments unless you recognize the sender and know the content is safe!!!. Hi Elena and Ara, This has been received and acknowledged. SCE accepts the conditions. Thank you again for all your hard work during this emergency, particularly for working with us on this temporary solution. We look forward to continuing to collaborate in this challenging, dynamic situation. Regards, Celina Celina Luna Government Relations Manager Local Public Affairs T. 626-302-5040 |PAX. 25040 | M. 213-523-8344| Email. celina.luna@sce.com From: Elena Gerli <egerli@awattorneys.com> Sent: Thursday, August 29, 2024 2:39 PM To: Celina Luna <CELINA.LUNA@SCE.COM>; Ara Mihranian <AraM@rpvca.gov> Cc: Catherine Jun <cjun@rpvca.gov>; Robert Pontelle <Robert.Pontelle@sce.com>; Mark Rothenberg <mark.a.rothenberg@sce.com> Subject: (External):SCE authorization for Ladera Linda pole at Alternate 1 location  CAUTION: This is an external email. Be careful when opening links or attachments This message was received from outside Edison. Report Suspicious Dear Celina, this email is to authorize SCE to begin installation of the pole at the site in Ladera Linda Community Center that we identified as Alternate 1 during the 8/28 meeting with the City. The City will issue a retroactive encroachment permit with the following conditions: F-1 2 SCE shall provide City with a detailed scope of work for the temporary pole prior to construction, including the proposed location of the pole. The temporary pole shall be made of treated wood. The temporary pole shall not be installed in a bioswale or other sensitive use. When the temporary pole is removed, SCE shall restore the site to its original condition, including but not limited to landscaping and pathway work. SCE shall maintain and repair the temporary pole, as needed, and in consultation with City shall install signage to indicate the temporary nature of the installation. SCE shall provide City with bi-weekly updates (Tues/Thurs meetings or at other times convenient to SCE and the City) on SCE’s work towards a permanent solution. The temporary pole must be relocated within 6 months, with an option to extend for 2 additional 3 month extensions, provided SCE makes good faith progress is designing a permanent solution and maintains regular communication with the City. City does not interpret the 1974 franchise agreement to apply to the location of the temporary pole. SCE shall indemnify and hold harmless the City in accordance with the provisions of the Franchise Act of 1937. Please confirm receipt and acceptance of the conditions for the encroachment permit. Best, Elena Q. Gerli City Attorney City of Rancho Palos Verdes Elena Q. Gerli | Partner she/her/hers Aleshire & Wynder, LLP | 3701 Wilshire Blvd, Suite 725, Los Angeles, CA 90010 Tel: (310) 527-6660 | Dir: (424) 269-3345 | egerli@awattorneys.com This email and any files transmitted with it may contain privileged or otherwise confidential information. If you are not the intended recipient, or believe that you may have received this communication in error, please advise the sender via email and delete the email you received. F-2