Consideration and possible action to approve the Storm Drain Improvements at Peacock
Ridge Project.
RECOMMENDED COUNCIL ACTION:
(1) Approve the plans, specifications, and construction documents for the Storm Drain
Improvements at Peacock Ridge Project;
(2) Award a construction contract for the Storm Drain Improvements at Peacock Ridge
Project to OrangeBlue, in the amount of $203,600, with a contingency of 10%, or
$20,400, for a total amount of up to $224,000; and
(3) Authorize the Mayor and City Clerk to execute the contracts, in forms approved by
the City Attorney.
FISCAL IMPACT: If approved, the recommendations will result in a fiscal impact of up
to $224,000, which is included in the approved Fiscal Year (FY)
2024-25 Capital Improvement Program (CIP) budget. VR
Amount Budgeted: $285,000
Additional Appropriation: Not Applicable
Account Number(s): 330-400-8723-8802 (CIP Fund – Storm Drain Improvements - Construction)
330-400-8723-8001 (CIP Fund – Storm Drain Improvements – Prof/Tech)
330-400-8723-8006
(CIP Fund – Storm Drain Improvements - Inspection) VR
ORIGINATED BY: Jeremiah Sunwoo, Associate Engineer
REVIEWED BY: Ramzi Awwad, Public Works Director
APPROVED BY: Ara Mihranian, AICP, City Manager
ATTACHED SUPPORTING DOCUMENTS:
A. Construction Contract with OrangeBlue for the Peacock Ridge Drainage
Improvements Project (page A-1)
1
B. Construction Proposal by OrangeBlue for the Storm Drain Improvements at
Peacock Ridge Project (Page B-1)
C. Plans, Specifications, and Construction Documents for the Storm Drain
Improvements at Peacock Ridge Project (Page C-1)
D. CIP Sheet for the Storm Drain Improvements at Peacock Ridge Project
(Page D-1)
BACKGROUND:
The existing 12-inch storm drain situated within
a cul-de-sac in the 5900 block of Peacock Ridge
Road collects runoff from Peacock Ridge Road
and channels it downstream onto Scotmist Drive,
south of Peacock Ridge Road. The segment of
storm drain that connects Peacock Ridge Road
to Scotmist Drive is approximately 150 linear
feet. Based on initial investigation by the City, the
lower pipe segment has collapsed and is no
longer effectively managing runoff on Peacock
Ridge Road, as shown in Figure 1.
To restore proper drainage to the area, the City
Council approved the Storm Drain
Improvements at Peacock Ridge Project as part
of the FY 2024-25 CIP (Attachment D).
On January 16, 2024, the City Council awarded
a Professional Services Agreement (PSA) to
BKF Engineers for the preparation of plans,
specifications, and construction cost estimates
to replace the storm drain (Attachment C).
Since the early stages of design development, Staff have conducted outreach to residents
living in close vicinity of the project, including the homeowners association of the Peacock
Ridge Condominium complex. Staff will continue to provide regular project status updates
to residents, including any necessary coordination during construction .
DISCUSSION:
On July 25, 2024, the City issued a Notice Inviting Bids on the PlanetBids platform for a
cost to construct the Storm Drain Improvements at Peacock Ridge Project. Seven bids
were received by the deadline of August 23, 2024, as shown in Table 1.
Figure 1: Photograph of localized
flooding at the inlet at the side located
on 5900 block of Peacock Ridge Road
2
Table 1: Peacock Ridge Drainage Improvements Bid Results
Bidder Bid Amount
Asad Holdings, LLC (dba OrangeBlue) $ 203,600
TTS Engineering, Inc. $ 245,163
Mendoza Engineering Company $ 259,414
HZS Engineering, Inc. $ 297,312
Clarke Constracting Corporation $ 299,271
ISSA Electric, Inc. $ 307,000
Grbcon, Inc. $ 693,750
The lowest apparent responsible and responsive bidder was OrangeBlue with a bid in the
amount of $203,600 (Attachment B). The City evaluated the bid and found OrangeBlue
to be a qualified firm. Table 2 shows a budget summary of the project.
Table 2: Peacock Ridge Drainage Improvements Project Budget Summary
8723 - Storm Drain Improvements at Peacock Ridge Road
Project Budget Summary Fund Budget Notes
Revised Budget FY23-24 330 42,605.00
Adopted Budget FY24-25 330 285,000.00
Budget Total 327,605.00
Project Cost Summary Fund Budget
Project-to-Date
Actuals (as of
9-6-2024)
Project-to-
Date
Committed
Remaining
Balance
8001 Professional/Technical 330 52,605.00
26,222.65
16,382.35
10,000.00 CIP
8006 Inspection Services 330 20,000.00
-
-
20,000.00 CIP
8802 Other Improvements 330 255,000.00
-
-
255,000.00 CIP
Project Total $ 327,605.00 $26,222.65 $16,382.35 $285,000.00
Staff expects work to be complete by November 2024, barring unforeseen circumstances.
A draft of the Public Works Agreement (Contract) for the proposed work is currently being
reviewed by the winning firm and will be made available as late correspondence
(Attachment A).
CONCLUSION:
Staff recommends the City Council award a construction contract to OrangeBlue in the
amount of $203,600, with a contingency of 10%, or $20,300, for a total amount of up to
$224,000 to construct the Storm Drain Improvements at Peacock Ridge Project.
ALTERNATIVES:
In addition to Staff recommendation, the following alternative action s are available for the
City Council’s consideration:
1. Do not award the contract and direct Staff to re-solicit construction bids.
2. Take other action, as deemed appropriate.
3
Project Name/No.: Peacock Ridge Drainage Imp Contract No.:
Project Manager: Approved:
01203.0006/993143.2 1
PUBLIC WORKS AGREEMENT
BETWEEN THE CITY OF RANCHO PALOS VERDES AND
ORANGEBLUE
THIS PUBLIC WORKS AGREEMENT (“Agreement”) is made and entered into
__________________, 2024 by and between the City of Rancho Palos Verdes, a California charter
city (“City”) and [NAME OF COMPANY], a [FORM OF COMPANY] (“Contractor”). City and
Contractor may sometimes be referred to herein as a “Party” or collectively as the “Parties.”
RECITALS
A. City has sought, by issuance of an Invitation for Bids, the performance of the
services defined and described particularly in Article 1 of this Agreement.
B. Contractor, following submission of a bid for the performance of the services
defined and described particularly in Article 1 of this Agreement, was selected by the City to
perform those services.
C. Pursuant to the City of Rancho Palos Verdes Municipal Code, City has authority to
enter into and execute this Agreement.
D. The Parties desire to formalize the selection of Contractor for performance of those
services defined and described particularly in Article 1 of this Agreement and desire that the terms
of that performance be as particularly defined and described herein.
AGREEMENT
NOW, THEREFORE, in consideration of the mutual promises and covenants made by the
Parties and contained herein and other consideration, the value and adequacy of which are hereby
acknowledged, the Parties agree as follows:
ARTICLE 1. CONTRACTOR SERVICES
1.1 Scope of Work.
The Contractor shall perform all of the work, furnish all labor, materials, equipment, tools,
utility services, and transportation, and comply with all of the specifications and requirements set
forth in the Bid Documents for the project entitled STORM DRAIN IMPROVEMENTS AT
PEACOCK RIDGE (“Project”), in accordance with the terms and conditions of Agreement
Special Provisions (the “Scope of Work”), which may be referred to herein as the “services” or
“work” hereunder. All such work shall be performed in a good and workmanlike manner, as
reasonably determined by the City, and shall be performed in strict compliance with the Bid
Documents and all local, state, and federal laws and regulations. As used herein, “Bid Documents”
refers to all of the documents included in the solicitation of bids for the Project and Contractor’s
bid proposal(s), including but not limited to, the Notice Inviting Bids, Summary of Work,
Instructions to Bidders, Bid or Bid Proposal, General Provisions, Special Provisions, Plans,
A-1
-2-
01203.0006/993143.2
Drawings, and Addenda, and any other documents included, referenced, or incorporated therein.
The Bid Documents are incorporated into this Agreement. In the event of any conflict or
inconsistency between the terms of the Bid Documents and this Agreement, the terms of this
Agreement shall govern.
1.2 Incorporation of Greenbook.
The provisions 2021 Edition of the Standard Specifications for Public Works Construction
(“Greenbook” including any updates, amendments, or addenda thereto ) are incorporated herein,
except as explicitly modified by the Bid Documents. In the event of any conflict or inconsistency
between the provisions of the Greenbook and this Agreement, the terms of this Agreement shall
govern.
1.3 Compliance with Labor and Wage Laws.
(a) Public Work. The Parties acknowledge that the work to be performed under
this Agreement is a “public work” as defined in Labor Code Section 1720 and that this Agreement
is therefore subject to the requirements of Division 2, Part 7, Chapter 1 (commencing with Section
1720) of the California Labor Code relating to public works contracts and the rules and regulations
established by the Department of Industrial Relations (“DIR”) implementing such statutes. The
work performed under this Agreement is subject to compliance monitoring and enforcement by
the DIR. Contractor shall post job site notices, as prescribed by state law and DIR regulations.
(b) Registration with DIR. Pursuant to Labor Code Section 1771.1, Contractor
and all subcontractors must be registered with, and pay an annual fee to, the DIR prior to and
during the performance of any work under this Agreement. Contractor shall notify the City in
writing immediately, and in no case more than 24 hours, after receiving any information that
Contractor’s or any of its Subcontractors’ DIR registration status has been suspended, revoked,
expired, or otherwise changed.
(c) Prevailing Wages. Contractor shall pay prevailing wages as required by
Labor Code Section 1771. Pursuant to Labor Code Section 1773.2, copies of the prevailing rate of
per diem wages are on file at City Hall and will be made available to any interested party on
request. By initiating any work under this Agreement, Contractor acknowledges receipt of a copy
of the DIR determination of the prevailing rate of per diem wages, and Contractor shall post a copy
of the same at each job site where work is performed under this Agreement. If this Agreement is
subject to the payment of federal prevailing wages under the Davis-Bacon Act (40 U.S.C. § 3141
et seq.), then Contractor shall pay the higher of either the state for federal prevailing wage
applicable to each laborer.
(d) Penalty for Failure to Pay Prevailing Wages. Contractor shall comply with
and be bound by the provisions of Labor Code Sections 1774 and 1775 concerning the payment
of prevailing rates of wages to workers and the penalties for failure to pay prevailing wages. The
Contractor shall, as a penalty to the City, forfeit $200 for each calendar day, or portion thereof, for
each worker paid less than the prevailing rates as determined by the DIR for the work or craft in
which the worker is employed for any public work done pursuant to this Agreement by Contractor
or by any subcontractor.
A-2
-3-
01203.0006/993143.2
(e) Payroll Records. Contractor shall comply with and be bound by the
provisions of Labor Code Section 1776, which requires Contractor and each subcontractor to: keep
accurate payroll records and verify such records in writing under penalty of perjury, as specified
in Section 1776; certify and make such payroll records available for inspection as provided by
Section 1776; and inform the City of the location of the records.
(f) Apprentices. Contractor shall comply with and be bound by the provisions
of Labor Code Sections 1777.5, 1777.6, and 1777.7 and California Code of Regulations Title 8,
Section 200 et seq. concerning the employment of apprentices on public works projects. Contractor
shall be responsible for compliance with these aforementioned Sections for all apprenticeable
occupations. Prior to commencing work under this Agreement, Contractor shall provide City with
a copy of the information submitted to any applicable appr enticeship program. Within 60 days
after concluding work pursuant to this Agreement, Contractor and each of its subcontractors shall
submit to the City a verified statement of the journeyman and apprentice hours performed under
this Agreement.
(g) Eight-Hour Work Day. Contractor acknowledges that 8 hours labor
constitutes a legal day’s work. Contractor shall comply with and be bound by Labor Code Sections
1810 and 1811. As required under Labor Code Section 1812, Contractor and each of its
subcontractors shall keep an accurate record showing the name of and actual hours worked each
calendar day and each calendar week by each worker employed by them in connection with the
work performed under the terms of this Agreement. Failure to comply with these sections of the
Labor Code will subject the Contractor to penalty and forfeiture provisions of the Labor Code
Section 1813.
(h) Penalties for Excess Hours. Contractor shall comply with and be bound by
the provisions of Labor Code Section 1813 concerning penalties for workers who work excess
hours. The Contractor shall, as a penalty to the City, forfeit $25 for each worker employed in the
performance of this Agreement by the Contractor or by any subcontractor for each calendar day
during which such worker is required or permitted to work more than eight 8 hours in any one
calendar day and 40 hours in any one calendar week in violation of the provisions of Division 2,
Part 7, Chapter 1, Article 3 of the Labor Code. Pursuant to Labor Code Section 1815, work
performed by employees of Contractor in excess of 8 hours per day, and 40 hours during any one
week shall be permitted upon public work upon compensation for all hours worked in excess of 8
hours per day at not less than 1.5 times the basic rate of pay.
(i) Workers’ Compensation. California Labor Code Sections 1860 and 3700
provide that every employer will be required to secure the payment of compensation to its
employees if it has employees. In accordance with the provisions of California Labor Code Section
1861, Contractor certifies as follows:
“I am aware of the provisions of Section 3700 of the Labor Code which require
every employer to be insured against liability for workers’ compensation or to
undertake self-insurance in accordance with the provisions of that code, and I will
comply with such provisions before commencing the performance of the work of
this contract.”
A-3
-4-
01203.0006/993143.2
(j) Contractor’s Responsibility for Subcontractors. For every subcontractor
who will perform work under this Agreement, Contractor shall be responsible for such
subcontractor’s compliance with Division 2, Part 7, Chapter 1 (commencing with Section 1720)
of the California Labor Code, and shall make such compliance a requirement in any contract with
any subcontractor for work under this Agreement. Contractor shall be required to take all actions
necessary to enforce such contractual provisions and ensure subcontractor’s compliance, including
without limitation, conducting a review of the certified payroll records of the subcontractor on a
periodic basis or upon becoming aware of the failure of the subcontractor to pay his or her workers
the specified prevailing rate of wages. Contractor shall diligently take corrective action to halt or
rectify any such failure by any subcontractor.
1.4 Licenses, Permits, Fees and Assessments.
Contractor shall obtain at its sole cost and expense such licenses, permits, registrations,
and approvals as may be required by law for the performance of the services required by this
Agreement. Contractor shall have the sole obligation to pay for any fees, assessments and taxes,
plus applicable penalties and interest, which may be imposed by law and arise from or are
necessary for the Contractor’s performance of the services required by this Agreement, and shall
indemnify, defend and hold harmless City, its officers, employees or agents of City, against any
such fees, assessments, taxes, penalties or interest levied, assessed or imposed against City
hereunder.
1.5 Familiarity with Work.
By executing this Agreement, Contractor warrants that Contractor (i) has thoroughly
investigated and considered the Scope of Work to be performed, (ii) has carefully considered how
the services should be performed, and (iii) fully understands the facilities, difficulties and
restrictions attending performance of the services under this Agreement. Contractor warrants that
Contractor has or will investigate the Project site and is or will be fully acquainted with the
conditions there existing, prior to commencement of services hereunder.
1.6 Discovery of Unknown Conditions.
(a) Pursuant to Public Contract Code Section 7104, Contractor shall promptly,
and before the following conditions are disturbed, notify the City, in writing, of any: (i) material
Contractor believes may be hazardous waste as defined in Section 25117 of the Health & Safety
Code required to be removed to a Class I, II, or III disposal site in accordance with existing law;
(ii) subsurface, unknown, or latent physical conditions at the Project site, materially different from
those indicated by information about the Project site made available to bidders prior to the deadline
for submitting bids on the Project; or (iii) unknown physical conditions at the Project site of any
unusual nature, different from those ordinarily encountered and generally recognized as inherent
in work of the character provided for in this Agreement, and will materially affect the performance
of Contractor’s services hereunder.
(b) City shall promptly investigate the conditions, and if it finds that the
conditions do materially differ, or do involve hazardous waste, and cause a decrease or increase in
A-4
-5-
01203.0006/993143.2
Contractor’s cost of, or the time required for, the performance of any part of the work, the City
shall issue a Change Order in accordance with Section 1.11 of this Agreement.
(c) In the event that a dispute arises between City and Contractor whether the
conditions materially differ, or involve hazardous waste, or cause a decrease or increase in
Contractor’s cost of, or time required for, performance of any part of the work, Contractor shall
not be excused from any scheduled completion date set, but shall proceed with all work to be
performed under this Agreement. Contractor shall retain any and all rights provided either by
contract or by law, which pertain to the resolution of disputes and protests between the Parties.
1.7 Unidentified Utilities.
To the extent required by Government Code Section 4215, City will compensate Contractor
for the cost of locating, repairing damage not due to the failure of Contractor to exercise reasonable
care, and removing or relocating utility facilities not identified by City in the Bid Documents with
reasonable accuracy, and for equipment on the Project necessarily idled during such work. Nothing
herein shall be deemed to require City to indicate the presence of existing service laterals or
appurtenances whenever the presence of such utilities on the Project site can be inferred from the
presence of other visible facilities, such as buildings, meters, and junction boxes, on or adjacent to
the Project site of the construction; provided, however, nothing herein shall relieve City from
identifying main or trunklines in the plans and specifications. If Contractor, while performing the
work, discovers utility facilities not identified by City in the plans or specifications, Contractor
shall immediately notify City and the utility in writing. This Agreement is subject to Government
Code Sections 4126 through 4216.9. Contractor must notify utilities and obtain an identification
number before excavation or be subject to liability for damages to subsurface installations.
1.8 Trench Excavation.
Pursuant to Labor Code Section 6705, if this Agreement is for more than $25,000 and
requires the excavation of any trench or trenches five feet or more in depth, Contractor shall
submit, in advance of such excavation, a detailed plan showing the design of shoring, bracing,
sloping, or other provisions to be made for worker protection from the hazard of caving ground
during the excavation of such trench or trenches. The plan shall be reviewed and accepted by the
City, or a registered civil or structural engineer employed by the City to whom authority has been
delegated, prior to the excavation. If the plan varies from the shoring system standards, the plan
shall be prepared by a registered civil or structural engineer. This Section 1.8 shall not be deemed
to allow the use of a shoring, sloping, or protective system less effective than that required by the
Construction Safety Orders (set forth in the California Code of Regulations, Title 8, Subchapter
4). This Section 1.8 shall not be construed to impose tort liability on the City or any of its
employees. Full compensation for sheeting, shoring, bracing, sloping, and all other provisions
required for worker protection shall be considered as included in the contract price shown in the
appropriate Bid item in the Bid Documents, and no additional compensation will be allowed
therefor.
A-5
-6-
01203.0006/993143.2
1.9 Protection and Care of Work and Materials.
The Contractor shall adopt reasonable methods, including providing and maintaining
storage facilities, during the life of this Agreement to furnish continuous protection to the work,
and the equipment, materials, papers, documents, plans, studies and/or other components thereof
to prevent losses or damages, and shall be responsible for all such damages, to persons or property,
until acceptance of the work by City, except such losses or damages as caused by City’s own
negligence. Stored materials shall be reasonably accessible for inspection. Contractor shall not,
without City’s consent, assign, sell, mortgage, hypothecate, or remove equipment or materials
which have been installed or delivered and which may be necessary for the completion of the work.
1.10 Warranty.
Contractor warrants all work under this Agreement (which for purposes of this Section
1.10 shall be deemed to include unauthorized work which has not been removed or corrected and
any non-conforming construction or materials incorporated into the work) to be of good quality
and free from any defective or faulty material and workmanship. Contractor agrees that for a period
of one year (or the period of time specified elsewhere in this Agreement, or the Bid Documents,
or in any guarantee or warranty provided by any manufacturer or supplier of equipment or
materials incorporated into the work, whichever is later) after the date of final acceptance by the
City for the Project, Contractor shall within 10 days after being notified in writing by the City of
any defect in the work or non-conformance of the work to the requirements under this Agreement,
commence and prosecute with due diligence all work necessary to fulfill the terms of the warranty
at its sole cost and expense. Notwithstanding the foregoing, Contractor shall act as soon as
requested by the City in response to any emergency condition or situation. In addition, Contractor
shall, at its sole cost and expense, repair, remove and replace any portions of the work (or work of
its sub-contractors) damaged by its defective work or which becomes damaged in the course of
repairing or replacing defective work. For any work so corrected, Contractor’s obligation
hereunder to correct defective work shall be reinstated for an additional one year period,
commencing with the date of acceptance of such corrected work. Contractor shall perform such
tests as the City may require to verify that any corrective actions, including, without limitation,
redesign, repairs, and replacements comply with the requirements of this Agreement. All costs
associated with such corrective actions and testing, including the removal, replacement, and
reinstitution of equipment and materials necessary to gain access, shall be the sole responsibility
of the Contractor. All warranties and guarantees of subcontractors, suppliers and manufacturers
with respect to any portion of the work, whether express or implied, are deemed to be obtained by
Contractor for the benefit of the City, regardless of whether or not such warranties and guarantees
have been transferred or assigned to the City by separate agreement and Contractor agrees to
enforce such warranties and guarantees, if necessary, on behalf of the City. In the event that
Contractor fails to perform its obligations under this Section, or under any other warranty or
guaranty under this Agreement or the Bid Documents, to the reasonable satisfaction of the City,
the City shall have the right to correct and replace any defective or non -conforming work at
Contractor’s sole expense. Contractor shall be obligated to fully reimburse the City for any
expenses incurred hereunder upon demand.
A-6
-7-
01203.0006/993143.2
1.11 Inspection by City.
In connection with the performance of this Agreement, the City shall have the authority to
enter the worksite at any time for the purpose of identifying the existence of conditions, either
actual or threatened, that may present a danger or hazard to any and all employees. The Contractor
agrees that the City, in its sole authority and discretion, may order the immediate abatement of any
and all conditions that may present an actual or threatened danger or hazard to any and all
employees at the worksite.
The Contractor acknowledges the provisions of Section 6400 of the Labor Code, which
requires that employers shall furnish employment and a place of employment that is safe and
healthful for all employees working therein. In the event the City identifies the existence of any
condition that presents an actual or threatened danger or hazard to any or all employees at the
worksite the City is hereby authorized to order the immediate abatement of that actual or threatened
condition pursuant to this section.
The City may also, at its sole authority and discretion, issue an immediate stop work order
to the Contractor to ensure that no employee working at the worksite is exposed to a dangerous or
hazardous condition. Any stop work order issued by the City to the Contractor in accordance with
the provisions of this section shall not give rise to any claim or cause of action for delay damages
by the Contractor or the Contractor’s agents or subcontractors against the City.
1.12 Additional Work and Change Orders.
(a) City shall have the right at any time during the performance of the services,
without invalidating this Agreement, to order extra work beyond that specified in the Scope of
Work or make changes to the work by altering, adding to or deducting from said work. No such
extra work may be undertaken unless a written change order is first given by the Project Manager
to the Contractor, incorporating therein any adjustment in (i) the Contract Sum (as defined below),
and/or (ii) the time to perform this Agreement, which said adjustments are subject to the written
approval of the Contractor (“Change Order(s)”). All Change Orders must be signed by the
Contractor and Project Manager (or his or her designee) prior to commencing the extra work
thereunder.
(b) Any increase in compensation of up to 10% of the Contract Sum or $25,000,
whichever is less; or any increase in the time to perform of up to one hundred eighty 18035 (thirty
five) days may be approved by the Project Manager, provided that such increase does not
materially affect the work in a detrimental manner or materially and detrimentally affect the
interest of the City. Any greater increases, taken either separately or cumulatively, must be
approved by the City Council.
(c) Any adjustment in the Contract Sum for a Change Order must be in
accordance with the rates set forth in the Contractor’s Bid attached hereto as Exhibit A. If the rates
in the Contractor’s Bid do not cover the type of work in the Change Order, the cost of such work
shall not exceed an amount agreed upon in writing and signed by Contractor and the Project
Manager. If the cost of the Change Order cannot be agreed upon, the City will pay for actual work
of the Change Order that is completed to the satisfaction of the City, as follows:
A-7
-8-
01203.0006/993143.2
(i) Labor: The cost of labor shall be the actual cost for the wages of
workers and subcontractors performing the work for the Change Order at the time such work is
performed. The use of labor classifications that would increase the cost of such work shall not be
permitted.
(ii) Materials and Equipment: The cost of materials and equipment shall
be at cost to Contractor or the lowest current price for which such materials and equipment are
reasonably available at the time the work is performed, whichever is lower.
(iii) Daily Reporting: Contractor must provide a daily report that
includes all invoices for labor, materials and equipment costs for the work under the Change Order.
The daily report must include the following: list of names of workers, classifications, and hours
worked; description and list of quantities of materials used; type of equipment, size, identification
number, and hours of operation, including loading and transportation, if applicable; description of
other City authorized services and expenditures in such detail as the City may require. Failure to
submit a daily report by the close of the next working day may, at the City’s sole and absolute
discretion, waive the Contractor’s rights to payment for the work performed for that day.
(d) It is expressly understood by Contractor that the provisions of this section
shall not apply to services specifically set forth in the Scope of Work. Contractor hereby
acknowledges that it accepts the risk that the services to be provided pursuant to the Scope of Work
may be more costly or time consuming than Contractor anticipates and that Contractor shall not
be entitled to additional compensation therefor. City may in its sole and absolute discretion have
similar work done by other contractors.
(e) No claim for an increase in the Contract Sum or time for performance shall
be valid unless the procedures established in this section are followed.
1.13 Special Requirements.
Additional terms and conditions of this Agreement, if any, which are made a part hereof
are set forth in the “Special Requirements,” attached hereto as Exhibit B and incorporated herein
by this reference. In the event of a conflict between the provisions of Exhibit B and any other
provisions of this Agreement, the provisions of Exhibit B shall govern.
ARTICLE 2. COMPENSATION AND METHOD OF PAYMENT.
2.1 Contract Sum.
Subject to any limitations set forth in this Agreement, City agrees to pay Contractor the
amounts set forth in Contractor’s Bid, attached hereto as Exhibit A and incorporated herein by this
reference. Subject to any additions or deductions that may be made by Change Order (as defined
below) or amendment, and any penalties or damages that may be assessed against Contractor,
Contractor shall receive total compensation, including reimbursement of Contractor’s expenses,
of $203,600 (Two Hundred Thousand Six Hundred Dollars) (“Contract Sum”) for completion of
the work. The Contract Sum shall constitute full compensation for furnishing all materials and for
doing all the work contemplated and embraced in this Agreement; and also for all loss or damage
arising out of the nature of the work, or from the action of the elements, or from any unforeseen
A-8
-9-
01203.0006/993143.2
difficulties or obstructions which may arise or be encountered in the prosecution of the work until
its acceptance by the City, and for all risks of every description connected with the work; also for
all expenses incurred by or in consequence of the suspension or discontinuance of work and for
well and faithfully completing the work, and the whole thereof, in the manner and according to the
plans and specifications, and the requirements of the Bid Documents and this Agreement.
Compensation shall be made in the form of progress payments and a final payment as
provided in this Section 2 and the Bid Documents.
Compensation may include reimbursement for actual and necessary expenditures for
reproduction costs, telephone expenses, and travel expenses approved by the Project Manager in
advance, or actual subcontractor expenses of an approved subcontractor pursuant to Section 4.5,
and only if specified in Exhibit Athe Contractor’s Bid. The Contract Sum shall include the
attendance of Contractor at all project meetings reasonably deemed necessary by the City.
Coordination of the performance of the work with City is a critical component of the services. If
Contractor is required to attend additional meetings to facilitate such coordination, Contractor shall
not be entitled to any additional compensation for attending said meetings.
2.2 Invoices.
Each month Contractor shall furnish to City an original invoice for all work performed and
expenses incurred during the preceding month in a form approved by City’s Director of Finance.
By submitting an invoice for payment under this Agreement, Contractor is certifying compliance
with all provisions of this Agreement.
All invoices shall include a copy of Contractor’s Certified Payroll and proof that Certified
Payroll has been submitted to the DIR. Contractor shall also submit a list of the prevailing wage
rates (including federal prevailing wage rates, if applicable) for all employees and subcontractors
providing services under this Agreement, as applicable, with Contractor’s first invoice. If these
rates change at any time during the term of this Agreement, Contractor shall submit a new list of
rates to the City with its first invoice following the effective date of the rate change.
2.3 Payment.
City shall independently review each invoice submitted by the Contractor to determine
whether the work performed and expenses incurred are in compliance with the provisions of this
Agreement. Except as to any charges for work performed or expenses incurred by Contractor
which are disputed by City, City will cause Contractor to be paid within 45 days of receipt of
Contractor’s correct and undisputed invoice; however, Contractor acknowledges and agrees that
due to City’s warrant run procedures, the City cannot guarantee that payment will occur within
this time period. In the event that City does not cause Contractor to be paid within 45 (days of
receipt of an undisputed and properly submitted invoice, Contractor shall be entitled to the
payment of interest to the extent allowed under Public Contract Code Section 20104.50. In the
event any charges or expenses are disputed by City, the original invoice shall be returned by City
to Contractor, not later than 7 days after receipt by the City, for correction and resubmission.
Returned invoices shall be accompanied by a document setting forth in writing the reasons why
the payment request was rejected. Review and payment by the City of any invoice provided by the
A-9
-10-
01203.0006/993143.2
Contractor shall not constitute a waiver of any rights or remedies provided herein or any applicable
law (with respect to any defects in the work performed by Contractor, or otherwise).
2.4 Retention.
City will deduct a 5% retention from all progress payments. In accordance with Public
Contract Code Section 22300, which is hereby incorporated into this Agreement, City shall permit
the substitution of securities for any moneys withheld by City to ensure performance under this
Agreement. The retention held by the City shall be released within 60 days after the date of
completion of the work and the Project, as required by Government Code Section 7107. In the
event of a dispute between City and Contractor, City may withhold from the final payment an
amount not to exceed 150% of the disputed amount.
ARTICLE 3. PERFORMANCE SCHEDULE
3.1 Time is of the essence.
If the work is not completed within the Schedule of Performance, liquidated damages shall
apply as set forth below.
3.2 Schedule of Performance.
Contractor shall begin work within 5 (five) days after receiving a Notice to Proceed from
the City and the work shall be completed within the Contractor’s schedule, prepared in
accordance with the Special Provisions, Section A-21consecutive working days from the date on
which Contractor received the Notice to Proceed, or otherwise in accordance with any schedule
contained in or required to be provided by the Bid Documents, and any revisions thereof approved
by the City in writing via change order.
3.3 Force Majeure
The time period(s) specified in the Schedule of Performance for performance of the
services rendered pursuant to this Agreement shall be extended because of any delays due to
unforeseeable causes beyond the control and without the fault or negligence of the Contractor,
including, but not restricted to, acts of God or of the public enemy, unusually severe weather, fires,
earthquakes, floods, epidemics, quarantine restrictions, riots, strikes, freight embargoes, wars,
litigation, and/or acts of any governmental agency, including the City, if the Contractor shall within
10 days of the commencement of such delay notify the Project Manager in writing of the causes
of the delay. The Project Manager shall ascertain the facts and the extent of delay, and extend the
time for performing the services for the period of the enforced delay when and if in the judgment
of the Project Manager such delay is justified. The Project Manager’s determination shall be final
and conclusive upon the parties to this Agreement. In no event shall Contractor be entitled to
recover damages against the City for any delay in the performance of this Agreement, however
caused, Contractor’s sole remedy being extension of the Agreement pursuant to this Section.
A-10
-11-
01203.0006/993143.2
3.4 Liquidated Damages.
Since the determination of actual damages for any delay in performance of this Agreement
would be extremely difficult or impractical to determine in the event of a breach of this Agreement,
the Contractor and its sureties shall be liable for and shall pay to the City the sum of $2,000 as
liquidated damages for each working day of delay in the performance of any service required
hereunder. The City may withhold any accrued liquidated damages from any monies payable on
account of services performed by the Contractor. To the extent required by Government Code
Section 4215, Contractor shall not be assessed liquidated damages for delay in completion of the
work when such delay was caused by the failure of the City or owner of the utility to provide for
removal or relocation of utility facilities.
3.5 Inspection and Final Acceptance.
City may inspect and accept or reject any of Contractor’s work under this Agreement, either
during performance or when completed. If City finds that Contractor’s work does not meet the
requirements and standards provided in the Bid Document, Contractor shall remedy any defects in
the work at Contractor’s sole expense following notice by the City. City shall accept work by a
timely written acceptance, otherwise work shall be deemed to have been rejected. City’s
acceptance shall be conclusive as to such work except with respect to latent defects, fraud and such
gross mistakes as to amount to fraud. Acceptance of any work by City shall not constitute a waiver
of any of the provisions of this Agreement including, but not limited to, Articles 1 and 5, pertaining
to warranty and indemnification and insurance, respectively.
ARTICLE 4. COORDINATION OF WORK
4.1 Representatives and Personnel of Contractor.
The following principals of Contractor (“Principals”) are hereby designated as being the
principals and representatives of Contractor authorized to act on its behalf with respect to the work
specified herein and make all decisions in connection therewith:
________________________ ________________________
(Name) (Title)
________________________ ________________________
(Name) (Title)
________________________ ________________________
(Name) (Title)
It is expressly understood that the experience, knowledge, capability and reputation of the
foregoing Principals were a substantial inducement for City to enter into this Agreement.
Therefore, the Principals shall be responsible during the term of this Agreement for directing all
activities of Contractor and devoting sufficient time to personally supervise the services hereunder.
All personnel of Contractor, and any authorized agents, shall at all times be under the exclusive
direction and control of the Principals. For purposes of this Agreement, the Principals may not be
A-11
-12-
01203.0006/993143.2
replaced nor may their responsibilities be substantially reduced by Contractor without the express
written approval of City. Additionally, Contractor shall make every reasonable effort to maintain
the stability and continuity of Contractor’s staff and subcontractors, if any, assigned to perform
the services required under this Agreement. Contractor shall notify City of any changes in
Contractor’s staff and subcontractors, if any, assigned to perform the services required under this
Agreement, prior to and during any such performance.
4.2 Status of Contractor.
Contractor shall have no authority to bind City in any manner, or to incur any obligation,
debt or liability of any kind on behalf of or against City, whether by contract or otherwise, unless
such authority is expressly conferred under this Agreement or is otherwise expressly conferred in
writing by City. Contractor shall not at any time or in any manner represent that Contractor or any
of Contractor’s officers, employees, or agents are in any manner officials, officers, employees or
agents of City. Neither Contractor, nor any of Contractor’s officers, employees or agents, shall
obtain any rights to retirement, health care or any other benefits which may otherwise accrue to
City’s employees. Contractor expressly waives any claim Contractor may have to any such rights.
4.3 Project Manager.
The “Project Manager” for the City shall be David Copp, Deputy Director of Public
Works, or any other person as may be designated by the Director of Public Works. It shall be the
Contractor’s responsibility to assure that the Project Manager is kept informed of the progress of
the performance of the services and the Contractor shall refer any decisions which must be made
by City to the Project Manager. Unless otherwise specified herein, any approval of City required
hereunder shall mean the approval of the Project Manager. The Project Manager shall have
authority, if specified in writing by the City Manager or his/her designee, to sign all documents on
behalf of the City required hereunder to carry out the terms of this Agreement.
4.4 Independent Contractor.
Neither the City nor any of its employees shall have any control over the manner, mode or
means by which Contractor, its agents or employees, perform the services required herein, except
as otherwise set forth herein. City shall have no voice in, or authority over, the selection, discharge,
supervision or control of Contractor’s employees, servants, representatives or agents, or in fixing
their number, compensation or hours of service. Contractor shall perform all services required
herein as an independent contractor of City and shall remain at all times as to City a wholly
independent contractor with only such obligations as are consistent with that role. Contractor shall
not at any time or in any manner represent that it or any of its agents or employees are agents or
employees of City. City shall not in any way or for any purpose become or be deemed to be a
partner of Contractor in its business or otherwise or a joint venturer or a member of any joint
enterprise with Contractor.
4.5 Prohibition Against Subcontracting or Assignment.
The experience, knowledge, capability and reputation of Contractor, its principals and
employees were a substantial inducement for the City to enter into this Agreement. Therefore,
Contractor shall not contract with any other entity to perform in whole or in part the services
A-12
-13-
01203.0006/993143.2
required hereunder without the express written approval of the City. All subcontractors shall
obtain, at its or Contractor’s expense, such licenses, permits, registrations and approvals (including
from the City) as may be required by law for the performance of any services or work under this
Agreement. In addition, neither this Agreement nor any interest herein may be transferred,
assigned, conveyed, hypothecated or encumbered voluntarily or by operation of law, whether for
the benefit of creditors or otherwise, without the prior written approval of City. Transfers restricted
hereunder shall include the transfer to any person or group of persons acting in concert of more
than 25% of the present ownership and/or control of Contractor, taking all transfers into account
on a cumulative basis. This limitation shall not apply to assignments to any company that is a
subsidiary or parent company of Contractor. In the event of any such unapproved transfer,
including any bankruptcy proceeding, this Agreement shall be void. No approved transfer shall
release the Contractor or any surety of Contractor of any liability hereunder without the express
consent of City.
ARTICLE 5. INSURANCE, INDEMNIFICATION AND BONDS
5.1 Insurance Coverages.
Without limiting Contractor’s indemnification obligation to the City (as set forth below),
and prior to commencement of any services under this Agreement, Contractor shall obtain, provide
and maintain at its own expense during the term of this Agreement, policies of insurance of the
type and amounts described below and in a form satisfactory to City.
(a) General liability insurance. Contractor shall maintain commercial general
liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in
an amount not less than $2,000,000$1,000,000 per occurrence, $4,000,000$2,000,000 general
aggregate, for bodily injury, personal injury, and property damage. The policy must include
contractual liability that has not been amended. Any endorsement restricting standard ISO “insured
contract” language will not be accepted. The Product and Completed Operations coverage under
the policy shall extend a minimum of three years after completion of the Project. Coverage shall
be included on behalf of the insured for covered claims arising out of the actions of independent
contractors. If the insured is using subcontractors, the policy must include work performed “by or
on behalf” of the insured. The policy shall contain no language that would invalidate or remove
the insurer’s duty to defend or indemnify for claims or suits expressly excluded from coverage.
The policy shall specifically provide for a duty to defend on the part of the insurer.
(b) Automobile liability insurance. Contractor shall maintain automobile
insurance at least as broad as Insurance Services Office form CA 00 01 covering bodily injury and
property damage for all activities of the Contractor arising out of or in connection with Services
to be performed under this Agreement, including coverage for any owned, hired, non-owned or
rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident.
(c) Professional liability (errors & omissions) insurance. Contractor shall
maintain professional liability insurance that covers the services to be performed in connection
with this Agreement, in the minimum amount of $1,000,000 per claim and in the aggregate. Any
policy inception date, continuity date, or retroactive date must be before the effective date of this
A-13
-14-
01203.0006/993143.2
Agreement and Contractor agrees to maintain continuous coverage through a period no less than
three (3) years after completion of the services required by this Agreement.
(d) Workers’ compensation insurance. Contractor shall maintain Workers’
Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance (with limits of at
least $1,000,000).
(e) Builder’s Risk Insurance. Contractor shall maintain Builder’s Risk (Course
of Construction) insurance utilizing an “All Risk” (Special Perils) coverage form, with limits equal
to the completed value of the Project and no coinsurance penalty provisions or provisional limit
provisions. The policy must include: (1) coverage for any ensuing loss from faulty workmanship,
nonconforming work, omission or deficiency in design or specifications; (2) coverage against
machinery accidents and operational testing; (3) coverage for removal of debris, and insuring the
buildings, structures, machinery, equipment, materials, facilities, fixtures and all other properties
constituting a part of the Project; (4) ordinance or law coverage for contingent rebuilding,
demolition, and increased costs of construction; (5) transit coverage (unless insured by the supplier
or receiving contractor), with sub-limits sufficient to insure the full replacement value of any key
equipment item; (6) ocean marine cargo coverage insuring any Project materials or supplies, if
applicable; (7) coverage with sub-limits sufficient to insure the full replacement value of any
property or equipment stored either on or off the Project site or any staging area.
(f) Pollution Liability Insurance. Contractor shall maintain Environmental
Impairment Liability insurance, written on a Contractor’s Pollution Liability form or other form
acceptable to City providing coverage for liability arising out of sudden, accidental, and gradual
pollution and remediation. The policy limit shall be no less than $1,000,000 per claim and in the
aggregate. All activities contemplated in this Agreement shall be specifically scheduled on the
policy as “covered operations.” The policy shall provide coverage for the hauling of waste from
the Project site to the final disposal location, including non-owned disposal sites.
5.2 General Insurance Requirements.
(a) Subcontractors. Contractor shall include all subcontractors as insureds
under its policies or shall furnish separate certificates and certified endorsements for each
subcontractor. All coverages for subcontractors shall include all of the requirements stated herein.
(b) Proof of Insurance. Contractor shall provide certificates of insurance to City
as evidence of the insurance coverage required herein, along with a waiver of subrogation
endorsement for workers’ compensation. Insurance certificates and endorsements must be
approved by City’s Risk Manager prior to commencement of performance. Current certification
of insurance shall be kept on file with City at all times during the term of this Agreement. City
reserves the right to require complete, certified copies of all required insurance policies, at any
time.
(c) Duration of Coverage. Contractor shall procure and maintain for the
duration of this Agreement insurance against claims for injuries to persons or damages to property,
which may arise from or in connection with the performance of the services hereunder by
Contractor, its agents, representatives, employees or subcontractors.
A-14
-15-
01203.0006/993143.2
(d) Products/completed operations coverage. Products/completed operations
coverage shall extend a minimum of three (3)one (1) year(s) after project completion. Coverage
shall be included on behalf of the insured for covered claims arising out of the actions of
independent contractors. If the insured is using subcontractors, the Policy must include work
performed “by or on behalf” of the insured. Policy shall contain no language that would invalidate
or remove the insurer’s duty to defend or indemnify for claims or suits expressly excluded from
coverage. Policy shall specifically provide for a duty to defend on the part of the insurer. The City,
its officials, officers, agents, and employees, shall be included as additional insureds under the
Products and Completed Operations coverage.
(e) Primary/noncontributing. Coverage provided by Contractor shall be
primary and any insurance or self-insurance procured or maintained by City shall not be required
to contribute with it. The limits of insurance required herein may be satisfied by a combination of
primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be
endorsed to contain a provision that such coverage shall also apply on a primary and non-
contributory basis for the benefit of City before the City’s own insurance or self-insurance shall
be called upon to protect it as a named insured.
(f) City’s Rights of Enforcement. In the event any policy of insurance required
under this Agreement does not comply with these specifications or is canceled and not replaced,
City has the right but not the duty to obtain the insurance it deems necessary, and any premium
paid by City will be promptly reimbursed by Contractor or City will withhold amounts sufficient
to pay the premium from any payments due to the Contractor. In the alternative, City may cancel
this Agreement.
(g) Waiver of Subrogation. All insurance coverage maintained or procured
pursuant to this agreement shall be endorsed to waive subrogation against City, its elected or
appointed officers, agents, officials, employees and volunteers or shall specifically allow
Contractor or others providing insurance evidence in compliance with these specifications to waive
their right of recovery prior to a loss. Contractor hereby waives its own right of recovery against
City, and shall require similar written express waivers and insurance clauses from each of its
subcontractors.
(h) Enforcement of Contract Provisions (non-estoppel). Contractor
acknowledges and agrees that any actual or alleged failure on the part of the City to inform
Contractor of non-compliance with any requirement imposes no additional obligations on the City
nor does it waive any rights hereunder.
(i) Requirements Not Limiting. Requirements of specific coverage features or
limits contained in this Section are not intended as a limitation on coverage, limits or other
requirements, or a waiver of any coverage normally provided by any insurance. Specific reference
to a given coverage feature is for purposes of clarification only as it pertains to a given issue and
is not intended by any Party or insured to be all inclusive, or to the exclusion of other coverage, or
a waiver of any type. If the Contractor maintains higher limits than the minimums shown above,
the City requires and shall be entitled to coverage for the higher limits maintained by the
Contractor. Any available insurance proceeds in excess of the specified minimum limits of
insurance and coverage shall be available to the City.
A-15
-16-
01203.0006/993143.2
(j) Notice of Cancellation. Contractor agrees to oblige its insurance agent or
broker and insurers to provide to City with a 30 day notice of cancellation (except for nonpayment
for which a 10 day notice is required) or nonrenewal of coverage for each required coverage.
(k) Additional Insured Status. General liability policies shall provide or be
endorsed to provide that City and its officers, officials, employees, and agents, and volunteers shall
be additional insureds under such policies. This provision shall also apply to any excess/umbrella
liability policies.
(l) Prohibition of Undisclosed Coverage Limitations. None of the coverages
required herein will be in compliance with these requirements if they include any limiting
endorsement of any kind that has not been first submitted to City and approved of in writing.
(m) Separation of Insureds. A severability of interests provision must apply for
all additional insureds ensuring that Contractor’s insurance shall apply separately to each insured
against whom claim is made or suit is brought, except with respect to the insurer’s limits of
liability. The policy(ies) shall not contain any cross-liability exclusions.
(n) Pass Through Clause. Contractor agrees to ensure that its subconsultants,
subcontractors, and any other party involved with the Project who is brought onto or involved in
the Project by Contractor, provide the same minimum insurance coverage and endorsements
required of Contractor. Contractor agrees to monitor and review all such coverage and assumes all
responsibility for ensuring that such coverage is provided in conformity with the requirements of
this Section. Contractor agrees that upon request, all agreements with consultants, subcontractors,
and others engaged in the Project will be submitted to City for review.
(o) Agency’s Right to Revise Specifications. The City reserves the right at any
time during the term of this Agreement to change the amounts and types of insurance required by
giving the Contractor 90 days advance written notice of such change. If such change results in
substantial additional cost to the Contractor, the City and Contractor may renegotiate Contractor’s
compensation.
(p) Self-Insured Retentions. Any self-insured retentions must be declared to
and approved by City. City reserves the right to require that self-insured retentions be eliminated,
lowered, or replaced by a deductible. Self-insurance will not be considered to comply with these
specifications unless approved by City.
(q) Timely Notice of Claims. Contractor shall give City prompt and timely
notice of claims made or suits instituted that arise out of or result from Contractor’s performance
under this Agreement, and that involve or may involve coverage under any of the required liability
policies.
(r) Additional Insurance. Contractor shall also procure and maintain, at its own
cost and expense, any additional kinds of insurance, which in its own judgment may be necessary
for its proper protection and prosecution of the work.
A-16
-17-
01203.0006/993143.2
5.3 Indemnification.
Contractor shall indemnify, defend with legal counsel approved by City, and hold harmless
City, its officers, officials, employees, agents, representatives, and volunteers (collectively,
“Indemnitees”) from and against all liability, loss, damage, expense, cost (including, without
limitation, reasonable legal counsel fees, expert fees and all other costs and fees of litigation) of
every nature arising out of or in connection with Contractor’s (or its employees’, officers’, agents’,
or subcontractors’; collectively, “Contractor”) performance of the work hereunder or its failure to
comply with any of its obligations contained in this Agreement, including any injuries to or death
of any person (including, but not limited to, workers and the public), or damage to property
resulting from the construction of the work or by or in consequence of any negligence regarding
the work, use of improper materials or equipment in construction of the work, neglect or refusal
of Contractor to faithfully perform the work and all of Contractor’s obligations under this
Agreement, or by or on account of any act or omission by the Contractor during the progress of
the work or at any time before the completion and final acceptance of the Project by the City,
except with respect to any loss or damage which is caused by the sole or active negligence or
willful misconduct of the Indemnitees as determined by a court of competent jurisdiction. Should
conflict of interest principles preclude a single legal counsel from representing both City and
Contractor, or should City otherwise find Contractor’s legal counsel unacceptable, then Contractor
shall reimburse the City its costs of defense, including, without limitation, reasonable attorneys’
fees, expert fees and all other costs and fees of litigation. Contractor shall promptly pay any final
judgment rendered against the Indemnitees with respect to claims determined by a trier of fact to
have been the result of the Contractor’s negligent, reckless or wrongful performance. It is expressly
understood and agreed that the foregoing provisions are intended to be as broad and inclusive as
is permitted by the law of the State of California and will survive termination of this Agreement.
Contractor’s obligations under this section apply regardless of whether or not such claim,
charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine
or penalty, or liability was caused in part or contributed to by the City or any Indemnitees. In
instances where City or its Indemnitees is shown to have been actively negligent and where City’s
active negligence accounts for only a percentage of the liability involved, the obligation of
Contractor will be for that entire portion or percentage of liability not attributable to the active
negligence of the City.
Contractor shall ensure that the performance of any work hereunder is done in compliance
with all applicable state, local and federal rules, laws and regulations related to accessibility and
reasonable accommodations and modifications for persons with disabilities, including but not
limited to the Americans with Disabilities Act as amended, 42 U.S.C. § 12101 et seq., and its
implementing regulations at 28 C.F.R. Parts 35 and 36 (ADA), and § 504 of the Rehabilitation Act
of 1973, as amended, and as applicable, 29 U.S.C. 701 and the implementing regulations at 24
C.F.R. Parts 8, the Fair Housing Act as amended, 42 U.S.C. 3601, et seq. and its implementing
regulations at 24 CFR Parts 100, the Fair Employment and Housing Act, California Government
Code § 12926, Title 24 of the California Building Code, and any requirements of the City.
Contractor hereby agrees to indemnify, defend, and hold City and all City Representatives free
and harmless against any and all Losses and Liabilities arising from its failure to perform any work
hereunder in accordance with all applicable disability access requirements and requirements under
the Americans with Disability Act and its implementing regulations.
A-17
-18-
01203.0006/993143.2
5.4 Notification of Third-Party Claims.
City shall timely notify Contractor of the receipt of any third-party claim relating to the
work under this Agreement. City shall be entitled to recover from Contractor its reasonable costs
incurred in providing such notification.
5.5 Performance, Labor, and Warranty Bonds.
Concurrently with execution of this Agreement, Contractor shall deliver to the City the
following bonds in the form required under the Bid Documents or otherwise by the City Clerk:
(a) A performance bond securing the faithful performance of this Agreement,
in an amount not less than 100% of the Contract Sum, as stated in Section 2.1 (“Performance
Bond”).
(b) A labor and materials bond, securing the payment of all persons furnishing
labor and/or materials in connection with the work under this Agreement, in an amount not less
than 100% of the Contract Sum, as stated in Section 2.1 (“Payment Bond”).
(c) A warranty bond, guaranteeing the Contractor’s warranty under Section
1.10 of this Agreement, in an amount not less than ___% of the total compensation for this
Agreement, as stated in Section 2.1.
(d) Bonds for all work involving an expenditure in excess of $25,000 shall not
be waived, in accordance with Section 9550 and 9552 of the Civil Code.
The bonds shall each contain the original notarized signature of an authorized officer of
the surety and affixed thereto shall be a certified and current copy of his/her power of attorney.
The bonds shall be unconditional and remain in force during the entire term of this Agreement.
City shall release the Performance Bond and Payment Bond when the following have
occurred: (a) Contractor has made a written request for release and provided evidence of
satisfaction of all other requirements under Article 5 of this Agreement, (b) the work for the Project
has be finally accepted by the City, and (c) after passage of the time within which lien claims are
required to be made pursuant to applicable laws; if lien claims have been timely filed, City shall
hold the Payment Bond until such claims have been resolved, Contractor has provided statutory
bond, or otherwise as required by applicable law.
5.6 Sufficiency of Insurer or Surety.
Insurance and bonds required by this Agreement shall be satisfactory only if issued by
companies qualified to do business in California, rated “A” or higher in the most recent edition of
Best’s Rating Guide, The Key Rating Guide or in the Federal Register, and only if they are of a
financial category Class VII or larger, unless otherwise approved by the City’s Risk Manager due
to unique circumstances. In addition, the insurance carrier must be currently authorized by the
Insurance Commissioner to transact business of insurance or be on the List of Approved Surplus
Line Insurers issued by the State of California. If the City determines that the work to be performed
under this Agreement creates an increased or decreased risk of loss to the City, the Contractor
A-18
-19-
01203.0006/993143.2
agrees that the minimum limits of the insurance policies and the bonds required in Section 5.5 may
be changed accordingly upon receipt of written notice from the City.
ARTICLE 6. RECORDS, REPORTS, AND RELEASE OF INFORMATION
6.1 Records.
Contractor shall keep, and require subcontractors to keep, such ledgers, books of accounts,
invoices, vouchers, canceled checks, reports, studies, certified and accurate copies of payroll
records in compliance with all applicable laws, or other documents relating to the disbursements
charged to City and services performed hereunder (the “books and records”), as shall be
necessary to perform the services required by this Agreement and enable the Project Manager to
evaluate the performance of such services. Any and all such documents shall be maintained in
accordance with generally accepted accounting principles and shall be complete and detailed. The
Project Manager shall have full and free access to such books and records at all times during
normal business hours of City, including the right to inspect, copy, audit and make records and
transcripts from such records. Such records shall be maintained for a period of 3 years following
completion of the services hereunder, and the City shall have access to such records in the ev ent
any audit is required. In the event of dissolution of Contractor’s business, custody of the books
and records may be given to City, and access shall be provided by Contractor’s successor in
interest. Notwithstanding the above, the Contractor shall fully cooperate with the City in providing
access to the books and records if a public records request is made and disclosure is required by
law including but not limited to the California Public Records Act.
6.2 Reports.
Contractor shall periodically prepare and submit to the Project Manager such reports
concerning the performance of the services required by this Agreement as the Project Manager
shall require. Contractor hereby acknowledges that the City is greatly concerned about the cost of
work and services to be performed pursuant to this Agreement. For this reason, Contractor agrees
that if Contractor becomes aware of any facts, circumstances, techniques, or events that may or
will materially increase or decrease the cost of the work or services contemplated herein,
Contractor shall promptly notify the Project Manager of said fact, circumstance, technique or event
and the estimated increased or decreased cost(s) related thereto.
6.3 Ownership of Documents.
All drawings, specifications, maps, designs, photographs, studies, surveys, data, notes,
computer files, reports, records, documents and other materials (the “documents and materials”)
prepared by Contractor, its employees, subcontractors and agents in the performance of this
Agreement shall be the property of the City and shall be delivered to the City upon request of the
Project Manager or upon the termination of this Agreement, and Contractor shall have no claim
for further employment or additional compensation as a result of the exercise by City of its full
rights of ownership use, reuse, or assignment of the documents and materials. Any use, reuse or
assignment of such completed documents for other projects and/or use of uncompleted documents
without specific written authorization by the Contractor will be at the City’s sole risk and without
liability to Contractor, and Contractor’s guarantee and warranties shall not extend to such use,
A-19
-20-
01203.0006/993143.2
reuse or assignment. Contractor may retain copies of such documents for its own use. Contractor
shall have an unrestricted right to use the concepts embodied therein. All subcontractors shall
provide for assignment to City of any documents or materials prepared by them, and in the event
Contractor fails to secure such assignment, Contractor shall indemnify City for all damages
resulting therefrom. Moreover, Contractor with respect to any documents and materials that may
qualify as “works made for hire” as defined in 17 U.S.C. § 101, such documents and materials are
hereby deemed “works made for hire” for the City.
6.4 Confidentiality and Release of Information.
(a) Information gained or work product produced by Contractor in its
performance of this Agreement shall be considered confidential, unless such information is in the
public domain or already known to Contractor. Contractor shall not release or disclose any such
information or work product to persons or entities other than City without prior written
authorization from the Project Manager.
(b) Contractor, its officers, employees, agents or subcontractors, shall not,
without prior written authorization from the Project Manager or unless requested by the City
Attorney, voluntarily provide documents, declarations, letters of support, testimony at depositions,
response to interrogatories or other information concerning the work performed under this
Agreement. Response to a subpoena or court order shall not be considered “voluntary” provided
Contractor gives City notice of such court order or subpoena.
(c) If Contractor, or any officer, employee, agent or subcontractor of
Contractor, provides any information or work product in violation of this Agreement, then City
shall have the right to reimbursement and indemnity from Contractor for any damages, costs and
fees, including attorneys’ fees, caused by or incurred as a result of Contractor’s conduct.
(d) Contractor shall promptly notify City should Contractor, its officers,
employees, agents or subcontractors be served with any summons, complaint, subpoena, notice of
deposition, request for documents, interrogatories, request for admissions or other discovery
request, court order or subpoena from any party regarding this Agreement and the work performed
with respect to the Project. City retains the right, but has no obligation, to represent Contractor or
be present at any deposition, hearing or similar proceeding. Contractor agrees to cooperate fully
with City and to provide City with the opportunity to review any response to discovery requests
provided by Contractor. However, this right to review any such response does not imply or mean
the right by City to control, direct, or rewrite said response.
ARTICLE 7. ENFORCEMENT OF AGREEMENT AND TERMINATION
7.1 California Law.
This Agreement shall be interpreted, construed and governed both as to validity and to
performance of the Parties in accordance with the laws of the State of California. Legal actions
concerning any dispute, claim or matter arising out of or in relation to this Agreement shall be
instituted in the Superior Court of the County of Los Angeles, State of California, or any other
appropriate court in such county, and Contractor covenants and agrees to submit to the personal
jurisdiction of such court in the event of such action. In the event of litigation in a U.S. District
A-20
-21-
01203.0006/993143.2
Court, venue shall lie exclusively in the Central District of California, in the County of Los
Angeles, State of California.
7.2 Termination.
This Agreement may be terminated in accordance with Sections 6-7 and 6-8 of the
Greenbook.
7.3 Dispute Resolution Process.
Section 20104 et seq. of the California Public Contract Code prescribes a process utilizing
informal conferences, non-binding judicial-supervised mediation, and judicial arbitration to
resolve disputes on construction claims of $375,000 or less. Additionally, Section 9204 of the
Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on
construction claims. The intent of this Section is to implement Sections 20104 et seq. and Section
9204 of the California Public Contract Code. This Section shall be construed to be consistent with
said statutes.
For purposes of these procedures, “claim” means a separate demand by the Contractor,
after the City has denied Contractor’s timely and duly made request for payment for ext ra work
and/or a time extension, for (A) a time extension, (B) payment of money or damages arising from
work done by or on behalf of the Contractor pursuant to this Agreement and payment of which is
not otherwise expressly provided for or the Contractor is not otherwise entitled to, or (C) an amount
the payment of which is disputed by the City.
The following requirements apply to all claims to which this Section applies:
(a) Claim Submittal. The claim shall be in writing and include the documents
necessary to substantiate the claim. Claims governed by this procedure must be filed on or before
the date of final payment. Nothing in this Section is intended to extend the time limit or supersede
notice requirements otherwise provided in this Agreement for the filing of claims, including all
requirements pertaining to compensation or payment for extra work, disputed work, and/or
changed conditions. Failure to follow such contractual requirements shall bar any claims or
subsequent lawsuits for compensation or payment thereon.
(b) Supporting Documentation. The Contractor shall submit all claims in the
following format:
(i) Summary of the claim, including references to the specific Bid
Document provisions or provisions under this Agreement upon which the claim is based.
(ii) List of documents relating to claim: (a) Specifications, (b)
Drawings, (c) Clarifications (Requests for Information), (d) Schedules, and (e) Other.
(iii) Chronology of events and correspondence related to the claim.
(iv) Statement of grounds for the claim.
A-21
-22-
01203.0006/993143.2
(v) Analysis of the claim’s cost, if any.
(vi) Analysis of the claim’s time/schedule impact, if any.
(c) City’s Response. Upon receipt of a claim pursuant to this Section, City shall
conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide
the Contractor a written statement identifying what portion of the claim is disputed and what
portion is undisputed. Any payment due on an undisputed portion of the claim will be processed
and made within 60 days after the City issues its written statement.
(i) If the City needs approval from the City Council to provide the
Contractor a written statement identifying the disputed portion and the undisputed portion of the
claim, and the City Council does not meet within the 45 days or within the mutually agreed to
extension of time following receipt of a claim sent by registered mail or certified mail, return
receipt requested, the City shall have up to three days following the next duly publicly noticed
meeting of the City Council after the 45-day period, or extension, expires to provide the Contractor
a written statement identifying the disputed portion and the undisputed portion.
(ii) Within 30 days of receipt of a claim, the City may request in writing
additional documentation supporting the claim or relating to defenses or claims the City may have
against the Contractor. If additional information is thereafter required, it shall be requested and
provided pursuant to this subdivision, upon mutual agreement of City and the Contractor.
(iii) The City’s written response to the claim, as further documented,
shall be submitted to the Contractor within 30 days (if the claim is less than $50,000, within 15
days) after receipt of the further documentation, or within a period of time no greater than that
taken by the Contractor in producing the additional information or requested documentation,
whichever is greater.
(d) Meet and Confer. If the Contractor disputes the City’s written response, or
the City fails to respond within the time prescribed, the Contractor may so notify the City, in
writing, either within 15 days of receipt of the City’s response or within 15 days of the City’s
failure to respond within the time prescribed, respectively, and demand an informal conference to
meet and confer for settlement of the issues in dispute. Upon receipt of a demand, the City shall
schedule a meet and confer conference within 30 days for settlement of the dispute.
(e) Mediation. Within 10 business days following the conclusion of the meet
and confer conference, if the claim or any portion of the claim remains in dispute, the City shall
provide the Contractor a written statement identifying the portion of the claim that remains in
dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim
shall be processed and made within 60 days after the City issues its written statement. Any disputed
portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding
mediation, with the City and the Contractor sharing the associated costs equally. The City and
Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of
the claim has been identified in writing, unless the Parties agree to select a mediator at a later time.
(i) If the Parties cannot agree upon a mediator, each Party shall select a
mediator and those mediators shall select a qualified neutral third party to mediate with regard to
A-22
-23-
01203.0006/993143.2
the disputed portion of the claim. Each Party shall bear the fees and costs charged by its respective
mediator in connection with the selection of the neutral mediator.
(ii) For purposes of this section, mediation includes any nonbinding
process, including, but not limited to, neutral evaluation or a dispute review board, in which an
independent third party or board assists the Parties in dispute resolution through negotiation or by
issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this Section.
(iii) Unless otherwise agreed to by the City and the Contractor in writing,
the mediation conducted pursuant to this Section shall excuse any further obligation under Public
Contract Code Section 20104.4 to mediate after litigation has been commenced.
(iv) All unresolved claims shall be considered jointly in a single
mediation, unless a new unrelated claim arises after mediation is completed.
(f) City’s Responses. The City’s failure to respond to a claim from the
Contractor within the time periods described in this Section or to otherwise meet the time
requirements of this Section shall result in the claim being deemed rejected in its entirety. A claim
that is denied by reason of the City’s failure to have responded to a claim, or its failure to otherwise
meet the time requirements of this Section, shall not constitute and adverse finding with regard to
the merits of the claim or the responsibility of qualifications of the Contractor. City’s failure to
respond shall not waive City’s rights to any subsequent procedures for the resolution of disputed
claims.
(g) Government Code Claims. If following the mediation, the claim or any
portion remains in dispute, the Contractor must comply with the claim procedures set forth in
Government Code Section 900 et seq. prior to filing any lawsuit against the City. Such Government
Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited
to those matters that remain unresolved after all procedures pertaining to extra work, disputed
work, construction claims, and/or changed conditions, including any required mediation, have
been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite
contractual requirements are not satisfied, no action against the City may be filed. A Government
Code claim must be filed no earlier than the date that Contractor completes all contractual
prerequisites to filing a Government Code claim, including any required mediation. A Government
Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the
Government Code claim is submitted. For purposes of Government Code Section 900 et seq., the
running of the period of time within which a claim must be filed shall be tolled from the time the
Contractor submits his or her written claim to the City until the time the claim is denied, including
any period of time utilized by the meet and confer conference or mediation that does not result in
a complete resolutions of all claims.
(h) Civil Actions for Claims of $375,000 or Less. The following procedures are
established for all civil actions filed to resolve claims totaling $375,000 or less:
(i) Within 60 days, but no earlier than 30 days, following the filing or
responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by
mutual stipulation of both Parties or unless mediation was held prior to commencement of the
A-23
-24-
01203.0006/993143.2
action in accordance with Public Contract Code Section 9204 and the procedures in this Section.
The mediation process shall provide for the selection within 15 days by both Parties of a
disinterested third person as mediator, shall be commenced within 30 days of the submittal, and
shall be concluded within 15 days from the commencement of the mediation unless a time
requirement is extended upon a good cause showing to the court.
(ii) If the matter remains in dispute, the case shall be submitted to
judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part
3 of the Code of Civil Procedure, notwithstanding Section 1141.11 of that code. The Civil
Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part
4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision
consistent with the rules pertaining to judicial arbitration.
(iii) Upon stipulation of the Parties, arbitrators appointed for these
purposes shall be experienced in construction law, and, upon stipulation of the Parties, mediators
and arbitrators shall be paid necessary and reasonable hourly rates of pay not to exceed their
customary rate, and such fees and expenses shall be paid equally by the Parties, except in the case
of arbitration where the arbitrator, for good cause, determines a different division.
(iv) In addition to Chapter 2.5 (commencing with Section 1141.10) of
Title 3 of Part 3 of the Code of Civil Procedure, any Party who after receiving an arbitration award
requests a trial de novo but does not obtain a more favorable judgment shall, in addition to payment
of costs and fees under that chapter, pay the reasonable attorneys’ fees of the other Party arising
out of the trial de novo.
7.4 Waiver.
Waiver by any Party to this Agreement of any term, condition, or covenant of this
Agreement shall not constitute a waiver of any other term, condition, or covenant. Waiver by any
Party of any breach of the provisions of this Agreement shall not constitute a waiver of any other
provision or a waiver of any subsequent breach or violation of any provision of this Agreement.
Acceptance by City of any work or services by Contractor shall not constitute a waiver of any of
the provisions of this Agreement. No delay or omission in the exercise of any right or remedy by
a non-defaulting party on any default shall impair such right or remedy or be construed as a waiver.
Any waiver by either Party of any default must be in writing and shall not be a waiver of any other
default concerning the same or any other provision of this Agreement.
7.5 Rights and Remedies Are Cumulative.
Except with respect to rights and remedies expressly declared to be exclusive in this
Agreement, the rights and remedies of the Parties are cumulative and the exercise by either Party
of one or more of such rights or remedies shall not preclude the exercise by it, at the same or
different times, of any other rights or remedies for the same default or any other default by the
other Party.
A-24
-25-
01203.0006/993143.2
7.6 Unfair Business Practices Claims.
Pursuant to Public Contract Code Section 7103.5, in entering into this Agreement,
Contractor offers and agrees to assign to the City all rights, title, and interest in and to all causes
of action it may have under Section 4 of the Clayton Act (15 U.S.C. § 15) or under the Cartwright
Act (Chapter 2, (commencing with Section 16700) of Part 2 of Division 7 of the Business and
Professions Code), arising from purchases of goods, services or materials related to this
Agreement. This assignment shall be made and become effective at the time the City tenders final
payment to the Contractor without further acknowledgment by the Parties.
ARTICLE 8. CITY OFFICERS AND EMPLOYEES: NON-DISCRIMINATION
8.1 Non-liability of City Officers and Employees.
No officer or employee of the City shall be personally liable to the Contractor, or any
successor in interest, in the event of any default or breach by the City or for any amount which
may become due to the Contractor or to its successor, or for breach of any obligation of the terms
of this Agreement.
8.2 Conflict of Interest.
Contractor covenants that neither it, nor any officer or principal of its firm, has or shall
acquire any interest, directly or indirectly, which would conflict in any manner with the interests
of City or which would in any way hinder Contractor’s performance of services under this
Agreement. Contractor further covenants that in the performance of this Agreement, no person
having any such interest shall be employed by it as an officer, employee, agent or subcontractor
without the express written consent of the Project Manager. Contractor agrees to at all times avoid
conflicts of interest or the appearance of any conflicts of interest with the interests of City in the
performance of this Agreement.
No officer or employee of the City shall have any financial interest, direct or indirect, in
this Agreement nor shall any such officer or employee participate in any decision relating to this
Agreement which effects his financial interest or the financial interest of any corporation,
partnership or association in which he is, directly or indirectly, interested, in violation of any State
statute or regulation. The Contractor warrants that it has not paid or given and will not pay or give
any third party any money or other consideration for obtaining this Agreement.
8.3 Covenant Against Discrimination.
Contractor covenants that, by and for itself, its heirs, executors, assigns, and all persons
claiming under or through them, there shall be no discrimination against or segregation of, any
person or group of persons on account of race, color, creed, religion, sex, gender, sexual
orientation, marital status, national origin, ancestry, or other protected class in the performance of
this Agreement. Contractor shall take affirmative action to insure that applicants are employed and
that employees are treated during employment without regard to their race, color, creed, religion,
sex, gender, sexual orientation, marital status, national origin, ancestry, or other protected class.
A-25
-26-
01203.0006/993143.2
8.4 Unauthorized Aliens.
Contractor hereby promises and agrees to comply with all of the provisions of the Federal
Immigration and Nationality Act, 8 U.S.C. § 1101 et seq., as amended, and in connection
therewith, shall not employ unauthorized aliens as defined therein. Should Contractor so employ
such unauthorized aliens for the performance of work and/or services covered by this Agreement,
and should any liability or sanctions be imposed against City for such use of unauthorized aliens,
Contractor hereby agrees to and shall reimburse City for the cost of all such liabilities or sanctions
imposed, together with any and all costs, including attorneys’ fees, incurred by City.
ARTICLE 9. MISCELLANEOUS PROVISIONS
9.1 Provisions Required By Law.
Each and every provision of law and clause required by law to be inserted in this Agreement
shall be deemed to be inserted herein, and this Agreement shall be read and enforced as though it
were included herein. If through mistake or otherwise any such provision is not inserted, or is not
correctly inserted, then upon application of either Party, this Agreement shall forthwith be
amended to make such insertion or correction.
9.2 Notices.
Any notice, demand, request, document, consent, approval, or communication either Party
desires or is required to give to the other Party or any other person shall be in writing and either
served personally or sent by prepaid, first-class mail, in the case of the City’s Project Manager,
City of Rancho Palos Verdes, 30940 Hawthorne Boulevard, Rancho Palos Verdes, CA 90275, and
in the case of the Contractor, to the person(s) at the address designated on the execution page of
this Agreement. Either Party may change its address by notifying the other Party of the change of
address in writing. Notice shall be deemed communicated at the time personally delivered or in 72
hours from the time of mailing if mailed as provided in this Section.
9.3 Interpretation.
The terms of this Agreement shall be construed in accordance with the meaning of the
language used and shall not be construed for or against either Party by reason of the authorship of
this Agreement or any other rule of construction which might otherwise apply.
9.4 Counterparts.
This Agreement may be executed in counterparts, each of which shall be deemed to be an
original, and such counterparts shall constitute one and the same instrument.
9.5 Integration; Amendment.
This Agreement, together with the documents incorporated herein (including the
Greenbook and the Bid Documents) and the exhibits attached hereto constitutes the entire,
complete and exclusive expression of the understanding of the Parties with respect to the subject
matter hereof. It is understood that there are no oral agreements between the Parties hereto
A-26
-27-
01203.0006/993143.2
affecting this Agreement and this Agreement supersedes and cancels any and all previous
negotiations, arrangements, agreements and understandings, if any, between the Parties, and none
shall be used to interpret this Agreement. No amendment to or modification of this Agreement
shall be valid unless made in writing and approved by the Contractor and by the City Council. The
Parties agree that this requirement for written modifications cannot be waived and that any
attempted waiver shall be void.
9.6 Severability.
In the event that any one or more of the phrases, sentences, clauses, paragraphs, or sections
contained in this Agreement shall be declared invalid or unenforceable by a valid judgment or
decree of a court of competent jurisdiction, such invalidity or unenforceability shall not affect any
of the remaining phrases, sentences, clauses, paragraphs, or sections of this Agreement which are
hereby declared as severable and shall be interpreted to carry out the intent of the Parties hereunder
unless the invalid provision is so material that its invalidity deprives either Party of the basic
benefit of their bargain or renders this Agreement meaningless.
9.7 Warranty & Representation of Non-Collusion.
No official, officer, or employee of City has any financial interest, direct or indirect, in this
Agreement, nor shall any official, officer, or employee of City participate in any decision relating
to this Agreement which may affect his/her financial interest or the financial interest of any
corporation, partnership, or association in which they are directly or indirectly interested, or in
violation of any corporation, partnership, or association in which they are directly or indirectly
interested, or in violation of any State or municipal statute or regulation. The determination of
“financial interest” shall be consistent with State law and shall not include interests found to be
“remote” or “noninterests” pursuant to Government Code Sections 1091 or 1091.5. Contractor
warrants and represents that it has not paid or given, and will not pay or give, to any third party
including, but not limited to, any City official, officer, or employee, any money, consideration, or
other thing of value as a result or consequence of obtaining or being awarded any agreement.
Contractor further warrants and represents that they have not engaged in any act(s), omission(s),
or other conduct or collusion that would result in the payment of any money, consideration, or
other thing of value to any third party including, but not limited to, any City official, officer, or
employee, as a result of consequence of obtaining or being awarded any agreement. Contractor is
aware of and understands that any such act(s), omission(s) or other conduct resulting in such
payment of money, consideration, or other thing of value will render this Agreement void and of
no force or effect.
9.8 Corporate Authority; Successors & Assigns.
The persons executing this Agreement on behalf of the Parties hereto warrant that (i) such
Party is duly organized and existing, (ii) they are duly authorized to execute and deliver this
Agreement on behalf of said Party, (iii) by so executing this Agreement, such Party is formally
bound to the provisions of this Agreement, and (iv) the entering into this Agreement does not
violate any provision of any other agreement to which said Party is bound. This Agreement shall
be binding upon the heirs, executors, administrators, successors and assigns of the Parties.
A-27
-28-
01203.0006/993143.2
IN WITNESS WHEREOF, the Parties hereto have executed this Agreement on the date
and year first-above written.
CITY:
CITY OF RANCHO PALOS VERDES, a
municipal corporation
Mayor
ATTEST:
City Clerk
APPROVED AS TO FORM:
Aleshire & Wynder, LLP
_____________________________
City Attorney
CONTRACTOR:
___________________________________,
a ___________________________
By:
Name:
Title:
By:
Name:
Title:
Address:
Two corporate officer signatures required when Contractor is a corporation, with one signature required from
each of the following groups: 1) Chairman of the Board, President or any Vice President; and 2) Secretary, any
Assistant Secretary, Chief Financial Officer or any Assistant Treasurer. CONTRACTOR ’S SIGNATURES
SHALL BE DULY NOTARIZED, AND APPROPRIATE ATTESTATIONS SHALL BE INCLUDED AS
MAY BE REQUIRED BY THE BYLAWS, ARTICLES OF INCORPORATION, OR OTHER RULES OR
REGULATIONS APPLICABLE TO CONTRACTOR’S BUSINESS ENTITY.
A-28
01203.0006/993143.2
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
STATE OF CALIFORNIA
COUNTY OF LOS ANGELES
On __________, 2024 before me, ________________, personally appeared ________________, proved to me on the
basis of satisfactory evidence to be the person(s) whose names(s) is/are subscribed to the within instrument and
acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by
his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted,
executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true
and correct.
WITNESS my hand and official seal.
Signature: _____________________________________
OPTIONAL
Though the data below is not required by law, it may prove valuable to persons relying on the document and could
prevent fraudulent reattachment of this form
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT
INDIVIDUAL
CORPORATE OFFICER
_______________________________
TITLE(S)
PARTNER(S) LIMITED
GENERAL
ATTORNEY-IN-FACT
TRUSTEE(S)
GUARDIAN/CONSERVATOR
OTHER_______________________________
______________________________________
SIGNER IS REPRESENTING:
(NAME OF PERSON(S) OR ENTITY(IES))
_____________________________________________
_____________________________________________
___________________________________
TITLE OR TYPE OF DOCUMENT
___________________________________
NUMBER OF PAGES
___________________________________
DATE OF DOCUMENT
___________________________________
SIGNER(S) OTHER THAN NAMED ABOVE
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy or validity of that document.
A-29
01203.0006/993143.2
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
STATE OF CALIFORNIA
COUNTY OF LOS ANGELES
On __________, 2024 before me, ________________, personally appeared ________________, proved to me on the
basis of satisfactory evidence to be the person(s) whose names(s) is/are subscribed to the within instrument and
acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by
his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted,
executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true
and correct.
WITNESS my hand and official seal.
Signature: _____________________________________
OPTIONAL
Though the data below is not required by law, it may prove valuable to persons relying on the document and could
prevent fraudulent reattachment of this form
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT
INDIVIDUAL
CORPORATE OFFICER
_______________________________
TITLE(S)
PARTNER(S) LIMITED
GENERAL
ATTORNEY-IN-FACT
TRUSTEE(S)
GUARDIAN/CONSERVATOR
OTHER_______________________________
______________________________________
SIGNER IS REPRESENTING:
(NAME OF PERSON(S) OR ENTITY(IES))
_____________________________________________
_____________________________________________
___________________________________
TITLE OR TYPE OF DOCUMENT
___________________________________
NUMBER OF PAGES
___________________________________
DATE OF DOCUMENT
___________________________________
SIGNER(S) OTHER THAN NAMED ABOVE
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy or validity of that document.
A-30
01203.0006/993143.2
BOND FORMS
A-31
01203.0006/993143.2
PERFORMANCE BOND
WHEREAS, the CITY OF RANCHO PALOS VERDES, (“City”), has awarded to
__________________________________, as Contractor (“Principal”), a Contract for the
work entitled and described as
follows:__________________________________________________;
WHEREAS, the Contractor is required under the terms of said Contract to furnish a
bond for the faithful performance of the Contract;
NOW, THEREFORE, we the undersigned Contractor and Surety, are held and firmly
bound unto the City in the sum of ________________________________________
($______________), this amount being not less than one hundred percent (100%) of the total
Contract price, lawful money of the United States of America, for payment of which sum well
and truly be made we bind ourselves, our heirs, executors, administrators, and successors,
jointly and severally, firmly by these presents. In case suit is brought upon this bond, the Surety
will pay a reasonable attorney’s fee to the City in an amount to be fixed by the court.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bound
Contractor, or its heirs, executors, administrators, successors, or assigns, shall in all things
stand and abide by, well and truly keep and perform all undertakings, terms, covenants,
conditions, and agreements in the said Contract and any alteration thereof, made as therein
provided, all within the time and in the manner designated and in all respects according to their
true intent and meaning, then this obligation shall become null and void; otherwise it shall be
and remain in full force and effect.
FURTHER, the said Surety, for value received, hereby stipulates and agrees that no
change, extension of time, alteration, or modification of the Contract Documents or of the work
to be performed thereunder shall in any way affect its obligations on this bond, and it does
hereby waive notice of such change, extension of time, alteration, or modification of the
Contract Documents or of the work to be performed thereunder.
Executed on 20___.
PRINCIPAL
(Seal if Corporation) By
Title
(Attach Acknowledgment of Authorized Representative of Principal)
A-32
01203.0006/993143.2
Any claims under this bond may be addressed to:
(name and address of Surety)
(name and address of Surety's agent for service
of
process in California, if different from above)
(telephone number of Surety's agent in
California)
(Attach Acknowledgment)
SURETY
By
(Attorney-in-Fact)
APPROVED:
(Attorney for CITY)
NOTICE:
No substitution or revision to this bond form will be accepted. Sureties must be authorized to
do business in and have an agent for service of process in California. Certified copy of Power
of Attorney must be attached.
A-33
01203.0023/976055.4
PAYMENT BOND
(Labor and Material Bond)
WHEREAS, the CITY OF RANCHO PALOS VERDES, (“City”), has awarded to
__________________________________, as Contractor (“Principal”), a Contract for the
work entitled and described as
follows:__________________________________________________;
WHEREAS, said Contractor is required to furnish a bond in conjunction with said
Contract, to secure the payment of claims of laborers, mechanics, material men, and other
persons as provided by law;
NOW, THEREFORE, we the undersigned Contractor and Surety, are held and firmly
bound unto the City in the sum of ________________________________________
($______________), this amount being not less than one hundred percent (100%) of the total
Contract price, lawful money of the United States of America, for payment of which sum well
and truly be made we bind ourselves, our heirs, executors, administrators, and successors,
jointly and severally, firmly by these presents. In case suit is brought upon this bond, the Surety
will pay a reasonable attorney’s fee to the City in an amount to be fixed by the court.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if said Contractor, its
heirs, executors, administrators, successors, assigns, or subcontractor fails to pay: (1) for any
work, materials, services, provisions, provender, or other supplies, or for the use of implements
of machinery, used in, upon, for, or about the performance of the work to be done, or for any
work or labor thereon of any kind; (2) for work performed by any of the persons named in
Civil Code Section 9100; (3) for any amounts due under the Unemployment Insurance Code
with respect to work or labor performed under the contract; and/or (4) for any amounts required
to be deducted, withheld, and paid over to the Employment Development Department from the
wages of employees of the Contractor and/or its subcontractors pursuant to Section 13020 of
the Unemployment Insurance Code with respect to such work and labor, then the Surety herein
will pay for the same in an amount not exceeding the sum specified in this bond, otherwise the
above obligation shall be void.
This bond shall inure to the benefit of any of the persons named in Civil Code Section
9100 so as to give a right of action to such persons or their assigns in any suit brought upon
the bond. Moreover, if the City or any entity or person entitled to file stop payment notices is
required to engage the services of an attorney in connection with the enforcement of this bond,
each shall be liable for the reasonable attorney's fees incurred, with or without suit, in addition
to the above sum.
Said Surety, for value received, hereby stipulates and agrees that no change, extension
of time, alteration, or modification of the Contract Documents or of the work to be performed
thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice
of such change, extension of time, alteration, or modification of the Contract Documents or of
the work to be performed thereunder.
A-34
01203.0023/976055.4
Executed on , 20____.
PRINCIPAL
(Seal if Corporation) By
Title
(Attach Acknowledgment of Authorized Representative of Principal)
Any claims under this bond may be addressed to:
(name and address of Surety)
(name and address of Surety's agent for service
of process in California, if different from above)
(telephone number of Surety's agent in
California)
(Attach Acknowledgment)
SURETY
By
(Attorney-in-Fact)
APPROVED:
(Attorney for CITY)
NOTICE:
No substitution or revision to this bond form will be accepted. Sureties must be authorized to
do business in and have an agent for service of process in California. Certified copy of Power
of Attorney must be attached.
A-35
01203.0023/976055.4
INSURANCE FORMS
A-36
01203.0023/976055.4
WORKERS COMPENSATION INSURANCE CERTIFICATE
Description of Contract: City of Rancho Palos Verdes
Project: _____________________________________________
Type of Insurance: Workers' Compensation and
Employers' Liability Insurance
THIS IS TO CERTIFY that the following policy has been issued by the below-stated company in
conformance with the requirements of Article 5 of the Contract and is in force at this time, and is
in a form approved by the Insurance Commissioner.
The Company will give at least 30 days' written notice to the City and Engineer/Architect prior to
any cancellation of said policy.
POLICY NUMBER EXPIRATION DATE LIMITS OF LIABILITY
Workers' Compensation:
Statutory Limits Under the Laws
of the State of California
Employers' Liability:
$_________________ Each Accident
$_________________ Disease - Policy Limit
$_________________ Disease - Each Employee
Named Insured (Contractor) Insurance Company
Street Number Street Number
City and State City and State
By
(Company Representative)
(SEE NOTICE ON NEXT PAGE)
A-37
01203.0023/976055.4
Insurance Company Agent for Service
of Process in California:
Name
Agency
Street Number
City and State
Telephone Number
This certificate is issued as a matter of information only and confers no rights upon the certificate
holder. This certificate does not amend, extend, or alter the coverage afforded by the policy listed
herein.
This is to certify that the policy has been issued to the named insured for the policy period
indicated, notwithstanding any requirement, term, or condition of any contract or other document
with respect to which this certificate may be issued or may pertain, the insurance afforded by the
policy described herein is subject to all the terms, exclusions, and conditions of such policy.
NOTICE:
No substitution or revision to the above certificate form will be accepted. If the insurance called
for is provided by more than one insurance company, a separate certificate in the exact above form
shall be provided for each insurance company.
A-38
01203.0023/976055.4
ADDITIONAL INSURED ENDORSEMENT
COMPREHENSIVE GENERAL LIABILITY
Name and address of named insured (“Named Insured”)
Name and address of Insurance Company (“Company”)
General description of agreement(s), permit(s), license(s), and/or activity(ies) insured
Notwithstanding any inconsistent statement in the policy to which this endorsement is attached (the
“Policy”) or in any endorsement now or hereafter attached thereto, it is agreed as follows:
1. The
(“Public Agency”), its elected officials, officers, attorneys, agents, employees, and volunteers are additional
insureds (the above named additional insureds are hereafter referred to as the “Additional Insureds”) under
the Policy in relation to those activities described generally above with regard to operations performed by
or on behalf of the Named Insured. The Additional Insureds have no liability for the payment of any
premiums or assessments under the Policy.
2. The insurance coverages afforded the Additional Insureds under the Policy shall be primary
insurance, and no other insurance maintained by the Additional Insureds shall be called upon to contribute
with the insurance coverages provided by the Policy.
3. Each insurance coverage under the Policy shall apply separately to each Additional Insured
against whom claim is made or suit is brought except with respect to the limits of the Company's liability.
4. Nothing in this contract of insurance shall be construed to preclude coverage of a claim by
one insured under the policy against another insured under the policy. All such claims shall be covered as
third-party claims, i.e., in the same manner as if separate policies had been issued to each insured. Nothing
contained in this provision shall operate to increase or replicate the Company's limits of liability as provided
under the policy.
5. The insurance afforded by the Policy for contractual liability insurance (subject to the
terms, conditions and exclusions applicable to such insurance) includes liability assumed by the Named
Insured under the indemnification and/or hold harmless provision(s) contained in or executed in conjunction
with the written agreement(s) or permit(s) designated above, between the Named Insured and the Additional
Insureds.
6. The policy to which this endorsement is attached shall not be subject to cancellation,
change in coverage, reduction of limits (except as the result of the payment of claims), or non -renewal
except after written notice to Public Agency, by certified mail, return receipt requested, not less than thirty
(30) days prior to the effective date thereof. In the event of Company's failure to comply with this notice
provision, the policy as initially drafted will continue in full force and effect until compliance with this
notice requirement.
7. Company hereby waives all rights of subrogation and contribution against the Additional
Insureds, while acting within the scope of their duties, from all claims, losses and liabilities arising out of
or incident to the perils insured against in relation to those activities described generally above with regard
A-39
01203.0023/976055.4
to operations performed by or on behalf of the Named Insured regardless of any prior, concurrent, or
subsequent active or passive negligence by the Additional Insureds.
8. It is hereby agreed that the laws of the State of California shall apply to and govern the
validity, construction, interpretation, and enforcement of this contract of insurance.
9. This endorsement and all notices given hereunder shall be sent to Public Agency at:
City Manager, City of Rancho Palos Verdes, 30940 Hawthorne Boulevard, Rancho Palos Verdes, California
90275.
10. Except as stated above and not in conflict with this endorsement, nothing contained herein
shall be held to waive, alter or extend any of the limits, agreements, or exclusions of the policy to which
this endorsement is attached.
TYPE OF COVERAGES TO WHICH POLICY PERIOD LIMITS OF
THIS ENDORSEMENT ATTACHES FROM/TO LIABILITY
11. Scheduled items or locations are to be identified on an attached sheet. The following
inclusions relate to the above coverages. Includes:
□ Contractual Liability □ Explosion Hazard
□ Owners/Landlords/Tenants □ Collapse Hazard
□ Manufacturers/Contractors □ Underground Property Damage
□ Products/Completed Operations □ Pollution Liability
□ Broad Form Property Damage □ Liquor Liability
□ Extended Bodily Injury □
□ Broad Form Comprehensive □
General Liability Endorsement □
12. A □ deductible or □ self-insured retention (check one) of $
applies to all coverage(s) except:
(if none, so state). The deductible is applicable □ per claim or □ per occurrence (check one).
13. This is an □ occurrence or □ claims made policy (check one).
14. This endorsement is effective on at 12:01 a.m. and forms a part of
Policy Number .
(signatures on following page)
A-40
01203.0023/976055.4
I, (print name), hereby
declare under penalty of perjury under the laws of the State of California, that I have the authority to bind
the Company to this endorsement and that by my execution hereof, I do so bind the Company.
Executed , 20
Signature of Authorized Representative
(Original signature only; no facsimile signature
Telephone No.: ( ) or initialed signature accepted)
A-41
01203.0023/976055.4
ADDITIONAL INSURED ENDORSEMENT
AUTOMOBILE LIABILITY
Name and address of named insured (“Named Insured”)
Name and address of Insurance Company (“Company”)
General description of agreement(s), permit(s), license(s), and/or activity(ies) insured
Notwithstanding any inconsistent statement in the policy to which this endorsement is attached (the
“Policy”) or in any endorsement now or hereafter attached thereto, it is agreed as follows:
1. The
(“Public Agency”), its elected officials, officers, attorneys, agents, employees, and volunteers are additional
insureds (the above named additional insureds are hereafter referred to as the “Additional Insureds”) under
the Policy in relation to those activities described generally above with regard to operations performed by
or on behalf of the Named Insured. The Additional Insureds have no liability for the payment of any
premiums or assessments under the Policy.
2. The insurance coverages afforded the Additional Insureds under the Policy shall be primary
insurance, and no other insurance maintained by the Additional Insureds shall be called upon to contribute
with the insurance coverages provided by the Policy.
3. Each insurance coverage under the Policy shall apply separately to each Additional Insured
against whom claim is made or suit is brought except with respect to the limits of the Company's liability.
4. Nothing in this contract of insurance shall be construed to preclude coverage of a claim by
one insured under the policy against another insured under the policy. All such claims shall be covered as
third-party claims, i.e., in the same manner as if separate policies had been issued to each insured. Nothing
contained in this provision shall operate to increase or replicate the Company's limits of liability as provided
under the policy.
5. The insurance afforded by the Policy for contractual liability insurance (subject to the
terms, conditions and exclusions applicable to such insurance) includes liability assumed by the Named
Insured under the indemnification and/or hold harmless provision(s) contained or executed in conjunction
with the written agreement(s) or permit(s) designated above, between the Named Insured and the Additional
Insureds.
6. The policy to which this endorsement is attached shall not be subject to cancellation,
change in coverage, reduction of limits (except as the result of the payment of claims), or non-renewal
except after written notice to Public Agency, by certified mail, return receipt requested, not less than thirty
(30) days prior to the effective date thereto. In the event of Company's failure to comply with this notice
provision, the policy as initially drafted will continue in full force and effect until compliance with this
notice requirement.
7. Company hereby waives all rights of subrogation and contribution against the Additional
Insureds, while acting within the scope of their duties, from all claims, losses and liabilities arising out of
or incident to the perils insured against in relation to those activities described generally above with regard
A-42
01203.0023/976055.4
to operations performed by or on behalf of the Named Insured regardless of any prior, concurrent, or
subsequent active or passive negligence by the Additional Insureds.
8. It is hereby agreed that the laws of the State of California shall apply to and govern the
validity, construction, interpretation, and enforcement of this contract of insurance.
9. This endorsement and all notices given hereunder shall be sent to Public Agency at:
City Manager
City of Rancho Palos Verdes
30940 Hawthorne Boulevard
Rancho Palos Verdes, California 90275
10. Except as stated above and not in conflict with this endorsement, nothing contained herein
shall be held to waive, alter or extend any of the limits, agreements, or exclusions of the policy to which
this endorsement is attached.
TYPE OF COVERAGES TO WHICH POLICY PERIOD LIMITS OF
THIS ENDORSEMENT ATTACHES FROM/TO LIABILITY
11. Scheduled items or locations are to be identified on an attached sheet. The following
inclusions relate to the above coverages. Includes:
□ Any Automobiles □ Truckers Coverage
□ All Owned Automobiles □ Motor Carrier Act
□ Non-owned Automobiles □ Bus Regulatory Reform Act
□ Hired Automobiles □ Public Livery Coverage
□ Scheduled Automobiles □
□ Garage Coverage □
12. A □ deductible or □ self-insured retention (check one) of $
applies to all coverage(s) except: (if none, so state). The deductible is applicable □
per claim or □ per occurrence (check one).
13. This is an □ occurrence or □ claims made policy (check one).
14. This endorsement is effective on at 12:01 a.m. and forms a part of Policy
Number .
(signatures on following page)
A-43
01203.0023/976055.4
I, (print name), hereby
declare under penalty of perjury under the laws of the State of California, that I have the authority to bind
the Company to this endorsement and that by my execution hereof, I do so bind the Company.
Executed , 20
Signature of Authorized Representative
(Original signature only; no facsimile signature
Telephone No.: ( ) or initialed signature accepted)
A-44
01203.0023/976055.4
ADDITIONAL INSURED ENDORSEMENT
EXCESS LIABILITY
Name and address of named insured (“Named Insured”)
Name and address of Insurance Company (“Company”)
General description of agreement(s), permit(s), license(s), and/or activity(ies) insured
Notwithstanding any inconsistent statement in the policy to which this endorsement is attached (the
“Policy”) or in any endorsement now or hereafter attached thereto, it is agreed as follows:
1. The
(“Public Agency”), its elected officials, officers, attorneys, agents, employees, and volunteers are additional
insureds (the above named additional insureds are hereafter referred to as the “Additional Insureds”) under
the Policy in relation to those activities described generally above with regard to operations performed by
or on behalf of the Named Insured. The Additional Insureds have no liability for the payment of any
premiums or assessments under the Policy.
2. The insurance coverages afforded the Additional Insureds under the Policy shall be primary
insurance, and no other insurance maintained by the Additional Insureds shall be called upon to contribute
with the insurance coverages provided by the Policy.
3. Each insurance coverage under the Policy shall apply separately to each Additional Insured
against whom claim is made or suit is brought, except with respect to the limits of the Company's liability.
4. Nothing in this contract of insurance shall be construed to preclude coverage of a claim by
one insured under the policy against another insured under the policy. All such claims shall be covered as
third-party claims, i.e., in the same manner as if separate policies had been issued to each insured. Nothing
contained in this provision shall operate to increase or replicate the Company's limits of liability as provided
under the policy.
5. The insurance afforded by the Policy for contractual liability insurance (subject to the
terms, conditions and exclusions applicable to such insurance) includes liability assumed by the Named
Insured under the indemnification and/or hold harmless provision(s) contained in or executed in conjunction
with the written agreement(s) or permit(s) designated above, between the Named Insured and the Additional
Insureds.
6. The policy to which this endorsement is attached shall not be subject to cancellation,
change in coverage, reduction of limits (except as the result of the payment of claims), or non-renewal
except after written notice to Public Agency, by certified mail, return receipt requested, not less than thirty
(30) days prior to the effective date thereto. In the event of Company's failure to comply with this notice
provision, the policy as initially drafted will continue in full force and effect until compliance with this
notice requirement.
7. Company hereby waives all rights of subrogation and contribution against the Additional
Insureds, while acting within the scope of their duties, from all claims, losses and liabilities arising out of
or incident to the perils insured against in relation to those activities described generally above with regard
to operations performed by or on behalf of the Named Insured regardless of any prior, concurrent, or
subsequent active or passive negligence by the Additional Insureds.
A-45
01203.0023/976055.4
8. It is hereby agreed that the laws of the State of California shall apply to and govern the
validity, construction, interpretation, and enforcement of this contract of insurance.
9. This endorsement and all notices given hereunder shall be sent to Public Agency at:
City Manager
City of Rancho Palos Verdes
30940 Hawthorne Boulevard
Rancho Palos Verdes, California 90275
10. Except as stated above and not in conflict with this endorsement, nothing contained herein
shall be held to waive, alter or extend any of the limits, agreements, or exclusions of the policy to which
this endorsement is attached.
TYPE OF COVERAGES TO WHICH POLICY PERIOD LIMITS OF
THIS ENDORSEMENT ATTACHES FROM/TO LIABILITY
□ Following Form
□ Umbrella Liability
□
11. Applicable underlying coverages:
INSURANCE COMPANY POLICY NO. AMOUNT
12. The following inclusions, exclusions, extensions or specific provisions relate to the above
coverages:
13. A □ deductible or □ self-insured retention (check one) of $
applies to all coverage(s) except:
(if none, so state). The deductible is applicable □ per claim or □ per occurrence (check one).
14. This is an □ occurrence or □ claims made policy (check one).
15. This endorsement is effective on at 12:01 a.m. and forms a part of Policy
Number .
A-46
01203.0023/976055.4
(signatures on following page)
I, (print name), hereby
declare under penalty of perjury under the laws of the State of California, that I have the authority to bind
the Company to this endorsement and that by my execution hereof, I do so bind the Company.
Executed , 20
Signature of Authorized Representative
(Original signature only; no facsimile signature
Telephone No.: ( ) or initialed signature accepted)
A-47
B-1
B-2
B-3
B-4
B-5
B-6
B-7
B-8
B-9
B-10
B-11
B-12
B-13
B-14
B-15
B-16
B-17
B-18
B-19
B-20
B-21
B-22
B-23
B-24
B-25
B-26
C-1
C-2
C-3
C-4
C-5
C-6
STORM DRAIN IMPROVEMENTS AT
PEACOCK RIDGE ROAD
PROJECT NO. 8723
TABLE OF CONTENTS
NOTICE INVITING SEALED BIDS
1. BACKGROUND/DESCRIPTION OF WORK ............................................................................... NC – 01
2. COMPLETION OF WORK ........................................................................................................ NC – 01
3. REQUEST FOR CLARIFICATION .............................................................................................. NC – 01
4. PREVAILING WAGES ............................................................................................................... NC – 01
5. LICENSE ................................................................................................................................. NC – 02
6. REGISTRATION WITH THE DEPARTMENT OF INDUSTRIAL RELATIONS ................................. NC – 02
7. RETENTION SUBSTITUTION ................................................................................................... NC – 02
8. LIQUIDATED DAMAGES ......................................................................................................... NC – 02
9. BIDDING PROCESS ................................................................................................................. NC – 02
INSTRUCTIONS TO BIDDERS
1. FORM OF PROPOSAL ................................................................................................................ i – 01
2. DELIVERY OF PROPOSALS ......................................................................................................... i – 01
3. MODIFICATIONS AND ALTERNATIVE PROPOSALS ................................................................... i – 01
4. WITHDRAWAL OF PROPOSAL .................................................................................................. i – 01
5. BIDDER’S SECURITY .................................................................................................................. i – 01
6. APPROXIMATE ESTIMATE ........................................................................................................ i – 01
7. ADDENDA ................................................................................................................................. i – 02
8. DISCREPANCIES IN PROPOSALS ................................................................................................ i – 02
9. COMPETENCY OF BIDDERS ...................................................................................................... i – 02
10. BIDDER’S EXAMINATION OF SITE AND CONTRACT DOCUMENTS ........................................... i – 02
11. DISQUALIFICATION OF BIDDERS .............................................................................................. i – 03
12. RETURN OF BID SECURITY ........................................................................................................ i – 03
13. AWARD OF CONTRACT ............................................................................................................. i – 03
14. ALTERNATES ............................................................................................................................. i – 03
15. LISTING SUBCONTRACTORS ..................................................................................................... i – 03
C-7
C. PROSECUTION AND PROGRESS OF THE WORK .............................................................. GP – 05
1. WORK SCHEDULE ................................................................................................................... GP – 05
2. SUBLETTING AND ASSIGNMENT ............................................................................................ GP – 05
3. CHARACTER OF WORKERS ..................................................................................................... GP – 05
4. AGENTS OR FOREMAN ........................................................................................................... GP – 05
5. TEMPORARY STOPPAGE OF CONSTRUCTION ACTIVITIES ...................................................... GP – 05
6. TIME OF COMPLETION AND LIQUIDATED DAMAGES ............................................................ GP – 06
7. SUSPENSION OF CONTRACT .................................................................................................. GP – 06
D. MEASUREMENT AND PAYMENT ................................................................................... GP – 07
1. MEASUREMENT AND PAYMENT ............................................................................................ GP – 07
2. FINAL INVOICE AND PAYMENT .............................................................................................. GP – 07
3. EXTRA WORK .......................................................................................................................... GP – 08
4. UNPAID CLAIMS ..................................................................................................................... GP – 08
5. ACCEPTANCE .......................................................................................................................... GP – 08
E. CONTROL OF WORK ..................................................................................................... GP – 09
1. AUTHORITY OF THE DIRECTOR OF PUBLIC WORKS ............................................................... GP – 09
2. CONFORMITY WITH PLANS AND ALLOWABLE VARIATION .................................................... GP – 09
3. PROGRESS OF THE WORK ...................................................................................................... GP – 09
4. SAMPLES ................................................................................................................................ GP – 09
5. TRADE NAMES AND ALTERNATIVES ....................................................................................... GP – 09
6. PROTECTION OF WORK .......................................................................................................... GP – 10
7. CONFLICT OF TERMS .............................................................................................................. GP – 10
8. INTERPRETATION OF PLANS AND SPECIFICATIONS ............................................................... GP – 10
9. INCREASES AND DECREASES OF THE WORK TO BE DONE ..................................................... GP – 10
10. ALTERATIONS OF THE WORK TO BE DONE ............................................................................ GP – 11
11. EXTRA WORK .......................................................................................................................... GP – 11
12. PUBLIC UTILITIES .................................................................................................................... GP – 11
13. PROCEDURE IN CASE OF DAMAGE TO PUBLIC PROPERTY ..................................................... GP – 12
14. REMOVAL OF INTERFERING OBSTRUCTIONS ......................................................................... GP – 12
15. QUALITY OF MATERIAL .......................................................................................................... GP – 12
16. REMOVAL OF DEFECTIVE OR UNAUTHORIZED WORK ........................................................... GP – 12
17. SUPERVISION.......................................................................................................................... GP – 12
C-8
16. EXECUTION OF AGREEMENT .................................................................................................... i – 03
17. INSURANCE AND BONDS .......................................................................................................... i – 04
18. TELEPHONES ............................................................................................................................ i – 04
19. INTERPRETATION OF PLANS AND DOCUMENTS ...................................................................... i – 04
20. SALES AND/OR USE TAXES ....................................................................................................... i – 04
21. NON-COLLUSION AFFIDAVIT ..................................................................................................... i – 04
22. EXECUTION OF THE CONTRACT ................................................................................................ i – 04
23. CONTRACT BONDS .................................................................................................................... i – 05
24. INSURANCE ............................................................................................................................... i – 05
25. COMPLIANCE WITH PROVISIONS OF THE PUBLIC CONTRACT .................................................. i – 05
26. REJECTION OF BIDS ................................................................................................................... i – 05
GENERAL PROVISIONS
A. PROJECT PROVISIONS .................................................................................................. GP – 01
1. UNITS OF MEASURE ............................................................................................................... GP – 01
B. LEGAL RELATIONS AND RESPONSIBILITY TO THE CITY .................................................... GP – 01
1. LAWS TO BE OBSERVED ......................................................................................................... GP – 01
2. SOCIAL SECURITY REQUIREMENTS ........................................................................................ GP – 01
3. REGISTRATION WITH THE DEPARTMENT OF INDUSTRIAL RELATIONS .................................. GP – 01
4. COMPLIANCE MONITORING AND POSTING JOB SITES .......................................................... GP – 02
5. PREVAILING WAGES ............................................................................................................... GP – 02
6. PENALTIES .............................................................................................................................. GP – 02
7. WORKING HOURS .................................................................................................................. GP – 02
8. APPRENTICES ......................................................................................................................... GP – 02
9. LICENSE OF CONTRACTORS .................................................................................................... GP – 03
10. PERMITS AND LICENSES ......................................................................................................... GP – 03
11. PATENTS ................................................................................................................................. GP – 03
12. INDEMNITY ............................................................................................................................. GP – 03
13. NOTICE ................................................................................................................................... GP – 03
14. CONTRACTOR’S RESPONSIBILITY FOR WORK ........................................................................ GP – 03
15. MAINTENANCE AND GUARANTEE ......................................................................................... GP – 04
16. COOPERATION ....................................................................................................................... GP – 04
C-9
18. SOIL COMPACTION TESTING .................................................................................................. GP – 13
19. PRESERVATION OF PROPERTY ............................................................................................... GP – 13
20. DUST CONTROL ...................................................................................................................... GP – 13
21. SELECTED MATERIALS ............................................................................................................ GP – 14
22. SURPLUS MATERIALS ............................................................................................................. GP – 14
23. CLEAN UP ............................................................................................................................... GP – 14
24. EQUIPMENT REQUIREMENTS ................................................................................................ GP – 14
25. PROTECTION OF WORK AND PUBLIC ..................................................................................... GP – 14
26. SPRINKLER SYSTEMS & LANDSCAPING .................................................................................. GP – 15
27. CONTRACTOR’S SUPERINTENDENT AND PROJECT MANAGER .............................................. GP – 15
28. WORK AFTER REGULAR HOURS ............................................................................................. GP – 16
29. CONTRACTOR’S DAILY REPORTS ............................................................................................ GP – 16
30. REQUEST FOR WORKING DAYS .............................................................................................. GP – 16
31. DEFECTIVE MATERIALS .......................................................................................................... GP – 16
32. SOUND AND VIBRATION CONTROL REQUIREMENTS ............................................................ GP – 17
33. AIR POLLUTION CONTROL ...................................................................................................... GP – 17
34. FINAL CLEAN UP ..................................................................................................................... GP – 17
35. CONTRACTOR’S REQUEST FOR FINAL INSPECTION ................................................................ GP – 17
36. RESOLUTION OF PUBLIC WORKS CLAIMS .............................................................................. GP – 18
37. TRENCHES AND EXCAVATIONS ...............................................................................................GP - 18
38. CONSTRUCTION & DEMOLITION MATERIALS RECYCLING REQUIREMENTS .......................... GP – 19
SPECIAL PROVISIONS
A. GENERAL PROJECT INFORMATION ................................................................................. SP – 01
1. REQUIREMENTS ..................................................................................................................... SP – 01
2. DEFINITION OF TERMS ........................................................................................................... SP – 01
3. PROJECT PLANS ...................................................................................................................... SP – 02
4. SCOPE OF WORK .................................................................................................................... SP – 02
5. NOTICE TO PROCEED ............................................................................................................. SP – 02
6. UTILITIES ................................................................................................................................ SP – 03
7. STREET CLOSURES .................................................................................................................. SP – 03
8. CONFERENCE.......................................................................................................................... SP – 04
9. PUBLIC CONVENIENCE AND SAFETY ...................................................................................... SP – 04
C-10
10. SANITARY CONVENIENCE ....................................................................................................... SP – 07
11. CONSTRUCTION YARD............................................................................................................ SP – 08
12. EQUIPMENT REQUIREMENTS ................................................................................................ SP – 08
13. PRESERVATION OF PROPERTY ............................................................................................... SP – 08
14. NPDES COMPLIANCE/WATER POLLUTION CONTROL ............................................................ SP – 08
15. SAFETY, SANITARY AND MEDICAL REQUIREMENTS............................................................... SP – 11
16. ELECTRICAL POWER ............................................................................................................... SP – 11
17. PROTECTION OF UNDERGROUND FACILITIES ........................................................................ SP – 11
18. AIR POLLUTION CONTROL ...................................................................................................... SP – 12
19. PROJECT APPEARANCE ........................................................................................................... SP – 12
20. WORK HOURS ........................................................................................................................ SP – 13
21. SCHEDULE AND PUBLIC NOTICES ........................................................................................... SP – 13
22. PHOTOGRAPHIC SURVEY OF ALL EXISTING CONDITIONS ...................................................... SP – 15
23. MOBILIZATION ....................................................................................................................... SP – 16
24. PROJECT MONUMENT SURVEYS AND CONSTRUCTION STAKING ......................................... SP – 17
B. PROJECT SPECIAL PROVISIONS ...................................................................................... SP – 19
1. GENERAL ................................................................................................................................ SP – 19
2. FURNISH AND APPLY WATER ................................................................................................. SP – 20
3. UNCLASSIFIED EXCAVATION .................................................................................................. SP – 20
4. REMOVE EXISTING CSP STORM DRAIN .................................................................................. SP – 21
5. CLEARING AND GRUBBING .................................................................................................... SP – 21
6. SUBGRADE PREPARATION ..................................................................................................... SP – 22
7. CONCRETE STRUCTURES ........................................................................................................ SP – 22
8. UNDERGROUND CONDUIT CONSTRUCTION .......................................................................... SP – 22
9. BEST MANAGEMENT PRACTICES ............................................................................................ SP - 25
10. PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS ......................................... SP – 25
11. REMOVAL OF DEFECTIVE OR UNAUTHORIZED WORK ............................................................ SP –26
12. APPURTENANT WORK ............................................................................................................ SP – 27
13. INSPECTION BY CITY ............................................................................................................... SP – 27
14. CLEANUP ................................................................................................................................ SP – 27
15. CONSTRUCTION WATER ........................................................................................................ SP – 27
16. STORAGE SITES ....................................................................................................................... SP – 27
17. SITE RESTORATION AND MEDIAN PROTECTION .................................................................... SP – 28
C-11
18. LARGE TREE REMOVALS AT PEACOCK RIDGE ROAD .............................................................. SP – 28
TECHNICAL PROVISIONS
1. COMPACTION TESTING: ........................................................................................................ TP – 01
2. MATERIAL TESTING ................................................................................................................ TP – 01
3. CRUSHED MISCELLANEOUS BASE/CLASS 2 AGGREGATE BASE .............................................. TP – 01
4. PORTLAND CEMENT CONCRETE (PCC) CONSTRUCTION ........................................................ TP – 02
5. SAWCUT, EXCAVATION, REMOVAL AND REPLACEMENT ASPHALT CONCRETE ..................... TP – 02
6. HIGH DENSITY POLYETHYLENE (HDPE) PIPE PLACEMENT...................................................... TP – 03
7. CONTRACT UNIT PRICES ......................................................................................................... TP – 04
PROPOSAL PACKAGE & CHECKLIST
1. PROPOSAL PRICES ....................................................................................................................... P-01
2. BID SHEET ................................................................................................................................... P-03
3. BID SCHEDULE ............................................................................................................................ P-04
4. INFORMATION REQUIRED OF BBIDDER ..................................................................................... P-05
5. REFERENCES ............................................................................................................................... P-07
6. STATEMENT REGARDING CONTRACTOR LICENSING LAWS ....................................................... P-11
7. RESUME ...................................................................................................................................... P-13
8. DESIGNATION OF SUBCONTRACTORS ....................................................................................... P-14
9. INDUSTRIAL SAFETY RECORD FORM .......................................................................................... P-15
10. BID BOND ................................................................................................................................... P-16
11. NONCOLLUSION DECLARATION ................................................................................................. P-18
12. ACKNOWLEDGMENT OF ADDENDA ............................................................................................ P-19
13. BIDDER STATISTICAL INFORMATION ......................................................................................... P-20
CONTRACT PACKAGE
PUBLIC WORKS AGREEMENT ............................................................................................................... C-01
INSTRUCTIONS FOR EXECUTION OF INSTRUMENTS ............................................................................ C-12
INSURANCE REQUIREMENTS FOR CITY OF RANCHO PALOS VERDES .................................................. C-13
PAYMENT BOND .................................................................................................................................. C-14
PERFORMANCE BOND ......................................................................................................................... C-16
WORKERS’ COMPENSATION CERTIFICATE OF INSURANCE ................................................................. C-18
COMPLAINCE WITH CA LABOR LAWS AGREEMENT ............................................................................ C-19
C-12
INDEMNIFICATION AND HOLD HARMLESS AGREEMENT .................................................................... C-21
ADDITIONAL INSURED ENDORSEMENT - COMPREHENSIVE GENERAL LIABILITY ................................ C-22
ADDITIONAL INSURED ENDORSEMENT - AUTOMOBILE LIABILITY ...................................................... C-24
ADDITIONAL INSURED ENDORSEMENT - EXCESS LIABILITY .................................................................. C-26
APPENDICES
APPENDIX I: STREET SWEEPING SCHEDULE
APPENDIX II: TRASH PICK UP SCHEDULE
APPENDIX III: DOOR HANDERS, LETTERS/NOTIFICATIONS
APPENDIX IV: MATERIAL RECYCLE PACKET
APPENDIX V: CONCRETE AND ASPHALT REMOVAL FORM
APPENDIX VI: SCHOOL DISTRICT CALENDAR
APPENDIX VII: PROPOSED IMPROVEMENT PLANS
C-13
NC - 1
NOTICE INVITING CONSTRUCTION BIDS
CITY OF RANCHO PALOS VERDES
BIDS MUST BE RECEIVED BY: August 23, 2024 at 4:30 PM
PLACE OF QUOTE: PlanetBids
RECEIPT: https://vendors.planetbids.com/portal/48551/bo/bo-search
NOTICE IS HEARBY GIVEN that the City of Rancho Palos Verdes, County of Los
Angeles, California, will receive up to, but not later than the time set forth above, quotes
for the Peacock Ridge Road Drainage Improvements Project. All quotes shall be made
using PlanetBids via the link provided above.
PROJECT IDENTIFICATION NAME: Storm Drain Improvements at Peacock Ridge Road
(Project No. 8723)
BACKGROUND/DESCRIPTION OF WORK: In general, the work comprises without
limitation, furnishing all necessary labor, materials, equipment and other incidental and
appurtenant Work necessary to construct the Storm Drain Improvements which includes
removing existing storm drain, installing new HDPE and concrete storm drain facilities,
catch basins, incidental removal and reconstruction of asphalt concrete pavement,
removing and reinstalling concrete curb and gutter, removing and reconstructing
miscellaneous concrete structures, temporary traffic control measures, large tree
removals, grading, and other appurtenant items not mentioned that are required to
complete the work between Scotmist Drive and Peacock Ridge Road including work within
the private residential property at 6037 Scotmist Drive as more clearly described in the
Contract Documents. This work will be performed in strict conformance with the Contract
Documents, permits from regulatory agencies with jurisdiction, and applicable regulations.
The quantity of work to be performed and materials to be furnished are approximate only,
being given as a basis for the comparison of Bids. The actual quantities of work to be
performed may vary at the discretion of the Director of Public Works.
COMPLETION OF WORK: Work shall be completed within thirty-five (35) working days
from the start of the project.
REQUEST FOR CLARIFICATION: If you discover any error, omission, ambiguity or
conflict in the Plans or Specifications and wish to have a clarification, please fax or email
your request for clarification to the Director of Public Works at publicworks@rpvca.gov
such that it is received by him/her no later than close of business on August 2, 2024.
Requests for clarification received after this date will be disregarded. Please indicate the
Project in your request for clarification.
PREVAILING WAGES: Pursuant to the Labor Code of the State of California, the
Director of Industrial Relations has determined the general prevailing rate of wages and
employer payments for health and welfare, vacation, pension and similar purposes
C-14
C-15
i - 1
INSTRUCTIONS TO BIDDERS
FORM OF PROPOSAL: The proposal shall be made on the bidding schedule
(“proposal”) herein.
DELIVERY OF PROPOSALS: The proposal shall be delivered by the time and to the
place stipulated in the Notice Inviting Construction Bids. It is the bidder’s sole
responsibility to see that his proposal is received within the deadline. Any proposal
received after the scheduled closing time for receipt of proposals will not be opened.
Bidders or their authorized agents are invited to be present.
MODIFICATIONS AND ALTERNATIVE PROPOSALS: Unauthorized conditions,
limitations or provisos attached to a proposal will render it informal and may be cause for
rejection. The complete proposal forms shall be without interlineations, alterations or
erasures, unless each such correction is suitably authenticated by affixing in the margin
immediately opposite the correction the surname or surnames of the person or persons
signing the bid. No hard copy, oral, telegraphic or telephonic proposals or modifications
will be considered.
WITHDRAWAL OF PROPOSAL: The proposal may be withdrawn upon request by the
bidder without prejudice to himself prior to, but not after, the time fixed for opening of bids,
provided that the request is in writing, has been executed by the bidder or his duly
authorized representative, and is filed with the DIRECTOR OF PUBLIC WORKS. No
proposal may be withdrawn during the period of ninety (90) calendar days after the
opening of proposals.
BIDDER’S SECURITY: Each bid shall be accompanied by cash, certified or cashier’s
check payable to the City, or a satisfactory bid bond in favor of the City executed by the
bidder as principal and a California admitted surety as surety, in an amount not less than
ten percent (10%) of the amount set forth in the bid. The check or bid bond shall be given
as a guarantee that the bidder shall execute the contract if it is awarded to him in
conformity with the contract documents and shall provide the evidence o f insurance and
furnish the necessary bonds as specified in the contract documents, within ten (10)
calendar days after written notice of the award. In case of the bidder’s refusal or failure
to do so, the cash, check, or bond, as the case may be, shall be forfeited to the City. No
bidder’s bond will be accepted unless it conforms substantially to th e form set forth as
required.
APPROXIMATE ESTIMATE: The quantities shown in the proposal form shall be
considered as approximate only, being listed therein for the purpose of serving as a
general indication of the amount of work or materials to be performed or furnished, and
as a basis for the comparison of bids; and the City does not guarantee nor agree, either
expressly or by implication, that the actual amount required will correspond therewith, but
reserves the right to increase or decrease the amount of any item or portion of work or
material to be performed or furnished, or to omit any such item or portion, in accordance
with the Special Provisions or Standard Specifications, under which the work is to be
constructed, without any way invalidating the contract, should such increase , decrease or
C-16
i - 2
omission be deemed necessary or expedient. The quantity distribution tables included in
the Appendix are provided to generally assist in defining the work and should be
considered to be approximate only.
ADDENDA: The Director of Public Works may issue Addenda to the Contract
Documents. Parties that have obtained the Contract Documents and are on the list of
Plan Holders shall be notified of and furnished with copies of such Addenda, either by
email, personal delivery, or facsimile, during the period of advertising at no additional
cost. The City may determine, in its sole discretion, whether an Addendum requires the
postponement of the date set for opening Bids. The announcement of the new date, if
any, shall be made within the Addenda. Please Note: Bidders are primarily and ultimately
responsible for ensuring that they have received any and all Addenda. To this end, each
Bidder should contact the City to verify that he or she has received all Addenda issued, if
any. Bidders must acknowledge receipt of all Addenda, if any, in its Proposal. Failure to
acknowledge receipt of all Addenda may cause a Proposal to be deemed incomplete and
non-responsive.
DISCREPANCIES IN PROPOSALS: The bidder shall set forth each item of work, in
clearly legible figures, a unit or line-item bid for the item in the respective spaces provided
for this purpose.
In case of discrepancy between the unit price and the total set forth for the item, the unit
price shall prevail, provided, however, if the amount set forth as a unit price is ambiguous,
unintelligible or uncertain for any cause, or is omitted, or in the case where the unit price
is the same amount as the entry in the “Total” column, then the amount set forth in the
“Total” column for the item shall prevail in accordance with the following:
(1) As to lump sum items, the amount set forth in the “Total” column shall be the
unit price.
(2) As to unit price items, the amount set forth in the “Total” column shall be divided
by the estimated quantity for the item and the price thus obtained shall be the
unit price.
In case of discrepancy between words and figures, the words shall prevail.
COMPETENCY OF BIDDERS: In selecting the lowest responsible bidder, consideration
will be given to the general competency of the bidder for the performance of the work
covered by the proposal. No agreement for the work will be executed with a contractor
who is not licensed in accordance with the laws of the State of California under applicable
provisions of the Business and Professions Code and registered with the DIR. The
licensing requirements for contractors shall apply also to subcontractors.
Contractors and subcontractors must sign the “Statement Acknowledging Penal & Civil
Penalties Concerning the Contractor’s Licensing Laws.”
BIDDER’S EXAMINATION OF SITE AND CONTRACT DOCUMENTS: Bidders must
satisfy themselves by personal examination of the location of the proposed work and by
C-17
i - 3
such other means as they may prefer as to the proposal, plans, specifications, contract
form and actual conditions and requirements of the work, and shall not at any time after
submission of the bid, dispute, complain, or assert that there was any misunder standing
in regard to the conditions to be encountered, the character, quality, and quantities of
work to be performed and materials to be furnished, and the requirements of the proposal,
plans, specifications, and the contract form. The submission of a p roposal shall be
considered conclusive evidence that the bidder has made such examination.
DISQUALIFICATION OF BIDDERS: No person, firm, or corporation shall be allowed to
make, file or be interested in more than one bid for the same work, unless alternate bids
are specifically called for. A person, firm or corporation that has submitted a sub-proposal
to a bidder, or that has quoted prices of materials to a bidder is not hereby disqualified
from submitting a sub-proposal or quoting prices to other bidders or making a prime
proposal. If there is a reason to believe that collusion exists among the bidders, all bids
will be rejected.
RETURN OF BID SECURITY: The successful bidder’s proposal guarantee shall be held
until the contract is executed. Bid security shall be returned to the three (3) lowest bidders
within twenty (20) calendar days after the successful bidder has signed the contract. All
other securities shall be returned immediately.
AWARD OF CONTRACT: The City reserves the right to reject any or all bids or any parts
thereof or to waive any irregularities or informalities in any bid or in the bidding. The
award of the contract, if made by the City, will be to the lowest responsible and qualified
bidder. The award, if made, will be within ninety (90) calendar days after the opening of
the proposals; provided that the award may be made after said period if the successful
bidder has not given the City written notice of the withdrawal of his bid.
ALTERNATES: If alternate bids are called for, the contract shall be awarded to the lowest
responsible bidder on the base bid.
LISTING SUBCONTRACTORS: Each bidder shall submit a list of the proposed
subcontractors on this project, as required by the Subletting and Subcontracting Fair
Practices Act (Public Contract Code Sections 4100, et seq.). Forms for this purpose are
furnished with the contract documents.
EXECUTION OF AGREEMENT: The bidder to whom award is made shall execute a
written contract with the City in the form included in these contract documents and shall
secure and provide to City all insurance and bonds as herein specified within ten (10)
calendar days from the date of mailing of written notice of the award. Failure or refusal
to enter into the agreement or to conform to any of the stipulated requirements shall be
just cause for the annulment of the award and forfeiture of the bidder’s s ecurity. In the
event the bidder to whom an award is made fails or refuses to execute the Agreement
within said time, the City may declare the bidder’s security forfeited, and it may award the
work to the next lowest bidder, or may call for new bids.
C-18
i - 4
If the successful bidder refuses or fails to execute the contract, the City may award the
contract to the second lowest responsible bidder. If the second lowest responsible bidder
refuses to execute the contract, the City may award the contract to the third lowest
responsible bidder to execute the contract; such bidder’s securities shall be likewise
forfeited to the City.
INSURANCE AND BONDS: The Contractor shall not begin Work under the Contract
until it has given the City evidence of all required insurance coverage, including all
additional insured endorsements. The Contractor also shall not begin Work under the
Contract until it has furnished to the City two Bonds: one guaranteeing the Contractor’s
faithful performance of the Contract, and other securing the payment of claims for labor
and material. Each of these Bonds shall be executed in a sum equal to the Contract
amount. Before acceptance of the Project, the Contractor shall submit warranty/
maintenance Bond(s) that are valid for one year from acceptance, as further described in
the General Provisions.
TELEPHONES: Bidders are hereby notified that City will not provide telephones for their
use at the time of receipt of bids.
INTERPRETATION OF PLANS AND DOCUMENTS: If any person contemplating
submitting a bid for the proposed contract is in doubt as to the true meaning of any part
of the drawings, specifications or other contract documents, or finds discrepancies in or
omissions from the drawings and specifications, he or she may submit to the DIRECTOR
OF PUBLIC WORKS a written request for an interpretation or correction by seven (7)
calendar days prior to bid opening. The person submitting the request will be responsible
for its prompt delivery. Any interpretation or correction of the contract document will be
made only by an Addendum duly issued, and a copy of such Addendum will be mailed,
delivered or faxed to each person receiving a set of the contract documents. No oral
interpretation of any provision in the contract documents shall be binding.
SALES AND/OR USE TAXES: Except as may be otherwise specifically provided herein,
all sales and/or use taxes assessed by federal, state or local authorities on materials used
or furnished by the Contractor in performing the work hereunder shall be paid by the
Contractor.
NON-COLLUSION AFFIDAVIT: The Contractor shall execute and return a “Non -
collusion Affidavit” with its bid in the form attached herein.
EXECUTION OF THE CONTRACT: The contract, in the form set forth in the Contract
Section shall be executed by the successful bidder in accordance with the Instruction for
Execution of Documents, and returned to the City for execution by the City, and shall be
accompanied by bonds as described in paragraph GP-B-4 and the evidence of insurance
required by paragraph GP-B-5, all within fifteen (15) calendar days from the date written
notice of the award is mailed to bidder. No bidder proposal shall be considere d binding
upon the City until such time as it has been executed by the City.
C-19
i - 5
CONTRACT BONDS: The successful bidder shall furnish to the City at his own expense
two surety bonds. One bond shall be in the amount of 100 percent of the contract price
in the form set forth in the Contract Section to guarantee faithful performance of the
contract work. The other bond, in an amount not less than 100 percent of the contract
price in the form set forth in the Contract Section shall be furnished to secure payment of
those supplying labor and materials as required by the California Civil Code. Each bond
shall be executed in accordance with the instruction set forth in the Proposal Section and
each bond shall be executed by a California admitted surety insurer acceptable to, and
approved by the City Attorney.
INSURANCE: The Contractor shall at all times, during the term of this contract, carry,
maintain and keep in full force and effect, a policy or policies of comprehensive public
liability insurance with an insurance company admitted to write insurance in California, or
carriers with a rating of, or equivalent to, A:VII by A. M. Best & Company to, and approved
by, the Director of Public Works and City Attorney, within minimum limits of Two Million
Dollars ($2,000,000.00) combined single limit coverage against any injury, death, loss or
damage as a result of wrongful or negligent acts or o missions by the Contractor, together
with an endorsement in substantially the form set forth in the Contract Section attached
hereto. The Contractor shall also at all times during the term of this contract carry,
maintain and keep in full force and effect a policy or policies of Workers’ Compensation
insurance and shall provide to the City evidence of such coverage in the form set forth
herein.
COMPLIANCE WITH PROVISIONS OF THE PUBLIC CONTRACT: All Contracts shall
conform to the provisions of Sections 4100 through 4114, inclusive, of the Public Contract
Code, as amended, concerning subcontractors and subcontracts.
REJECTION OF BIDS: Proposals may be rejected by the City Council where, upon
evidence of a prior performance of the bidder, the City Council has made a finding that
the bidder is not a responsible bidder because of unsatisfactory performance within the
past three (3) years with the City or with other public entities. The City reserves the right
to reject any or all bids and to waive any irregularity or informality in any bid to the extent
permitted by law.
C-20
GP-1
R6876-0001\1800410v2.doc
GENERAL PROVISIONS
A. PROJECT PROVISIONS
1. UNITS OF MEASURE
The U.S. Standard Measures also called U.S. Customary System is the principal
measurement system in these specifications and shall be used for construction, unless
otherwise stated in the Contract Documents.
The project provisions applicable to this contract shall be those set forth in California
Building Code (CBC), California Mechanical Code (CMC), California Plumbing Code
(CPC), and 2007 California Electrical Code (CEC) & City Ordinance, the 2005 California
Energy Standards and the Standard Specifications for Public Works Construction, the
latest edition, including all supplements, published by Building News, Inc., 1612 South
Clementine Street, Anaheim, California 92802, hereinafter referred to as “Standard
Specifications.” The Standard Specifications are referred to and by this reference are
made a part hereof as though set forth at length. The Contractor is required to comply
with the Standard Specifications in addition to the conditions set forth in these General
Provisions and Special Provisions.
B. LEGAL RELATIONS AND RESPONSIBILITY TO THE CITY
1. LAWS TO BE OBSERVED
The Contractor shall keep himself or herself fully informed on all existing and pending
State and national laws and all municipal ordinances and regulations of the City, which
in any manner affect those employed in the work, or the material used in the work, or
which in any way affect the conduct of the work, and of all such orders and decrees of
bodies or tribunals having jurisdiction or authority over the same. The Contractor shall
particularly observe all ordinances of the City in relations to the obstruction of streets or
conduct of the work, keeping open passageways and protecting the same where they
are exposed or dangerous to traffic.
2. SOCIAL SECURITY REQUIREMENTS
The Contractor shall furnish to the City satisfactory evidence that he and all
subcontractors working for him are complying with all requirements of the Federal and
State Social Security legislation. The Contractor, at any time on request, shall satisfy
the City that the Social Security and Withholding taxes are being properly reported and
paid.
3. REGISTRATION WITH THE DEPARTMENT OF INDUSTRIAL RELATIONS (DIR)
The Contractor’s attention is directed to Labor Code Section 1725.5, which provides that
a contractor or subcontractor shall not be qualified to bid on, be listed in a Bid proposal,
subject to the requirements of Public Contract Code Section 4104, or engage in the
performance of any contract that is subject to Labor Code Section 1720 et seq., unless
currently registered and qualified to perform public work pursuant to Labor Code Section
1725.5. This requirement applies to any bid proposal submitted on or after March 1,
2015, and any contract for public work entered into on or after April 1, 2015.
C-21
GP-2
R6876-0001\1800410v2.doc
4. COMPLIANCE MONITORING AND POSTING JOB SITES
This Project is subject to compliance monitoring and enforcement by the DIR. The
Contractor shall post job site notices, as prescribed by regulation.
5. PREVAILING WAGES
Contractor shall pay prevailing wages as required by Labor Code Section 1771.
Pursuant to Labor Code Section 1773.2, copies of the prevailing rate of per diem wages
are on file at City Hall and will be made available to any interested party on request. By
initiating any work under this Agreement, Contractor acknowledges receipt of a copy of
the DIR determination of the prevailing rate of per diem wages, and Contractor shall post
a copy of the same at each job site where work is performed under this Agreement. If
this Agreement is subject to the payment of federal prevailing wages under the Davis-
Bacon Act (40 U.S.C. § 3141 et seq.), then Contractor shall pay the higher of either the
state for federal prevailing wage applicable to each laborer.
A copy of said documents is on file and may be inspected in the office of the Director of
Public Works. The Contractor shall post a copy of the prevailing wage rates at each job
site.
6. PENALTIES
Contractor shall comply with and be bound by the provisions of Labor Code Sections
1774 and 1775 concerning the payment of prevailing rates of wages to workers and the
penalties for failure to pay prevailing wages. The Contractor shall, as a penalty to the
City, forfeit $200 for each calendar day, or portion thereof, for each worker paid less than
the prevailing rates as determined by the DIR for the work or craft in which the worker is
employed for any public work done pursuant to this Agreement by Contractor or by any
subcontractor.
7. WORKING HOURS
Contractor shall comply with and be bound by the provisions of Labor Code Section
1813 concerning penalties for workers who work excess hours. The Contractor shall, as
a penalty to the City, forfeit $25 for each worker employed in the performance of this
Agreement by the Contractor or by any subcontractor for each calendar day during
which such worker is required or permitted to work more than eight 8 hours in any one
calendar day and 40 hours in any one calendar week in violation of the provisions of
Division 2, Part 7, Chapter 1, Article 3 of the Labor Code. Pursuant to Labor Code
Section 1815, work performed by employees of Contractor in excess of 8 hours per day,
and 40 hours during any one week shall be permitted upon public work upon
compensation for all hours worked in excess of 8 hours per day at not less than 1.5
times the basic rate of pay.
8. APPRENTICES
Contractor shall comply with and be bound by the provisions of Labor Code Sections
1777.5, 1777.6, and 1777.7 and California Code of Regulations Title 8, Section 200 et
seq. concerning the employment of apprentices on public works projects. Contractor
shall be responsible for compliance with these aforementioned Sections for all
C-22
GP-3
R6876-0001\1800410v2.doc
apprenticeable occupations. Prior to commencing work under this Agreement,
Contractor shall provide City with a copy of the information submitted to any applicable
apprenticeship program. Within 60 days after concluding work pursuant to this
Agreement, Contractor and each of its subcontractors shall submit to the City a verified
statement of the journeyman and apprentice hours performed under this Agreement.
Information relative to apprenticeship standards and administration of the apprenticeship
program may be obtained from the Department of Industrial Relations, San Francisco,
California, or from the Division of Apprenticeship Standards and its branch offices.
9. LICENSE OF CONTRACTORS
Only a Contractor licensed in accordance with the provisions of Chapter 9, Division 3, of
the Business and Professions Code shall be permitted to enter into a contract with the
City for any public improvements.
10. PERMITS AND LICENSES
The Contractor shall procure all permits and licenses, (including a Rancho Palos Verdes
business license), pay all charges and fees and give all notices necessary and incidental
to the due and lawful prosecution of the work.
11. PATENTS
The Contractor shall assume all responsibility arising from the use of any patented, or
allegedly patented materials, equipment, devices or processes used on or incorporated
in the work, and shall defend, indemnify, and hold harmless the City, and each of its
officers, agents, and employees from and against any and all liabilities, demands,
claims, damages, losses, costs, and expenses, of whatsoever kind or nature, arising
from such use.
12. INDEMNITY
The Contractor agrees to indemnify and hold harmless the City and others and to waive
subrogation as set forth in the Indemnification and Hold Harmless Agreement and
Waiver of Subrogation and Contribution executed concurrently herewith, a copy of which
is attached hereto and incorporated herein by this reference.
13. NOTICE
The address given in the Contractor’s proposal is the place to which all notices to the
Contractor shall be mailed or delivered. The mailing to or delivering at the above-named
place of any notice shall be deemed sufficient service thereof upon the Contractor, and
the date of that service shall be the date of such mailing or delivery. Such address may
be changed at any time by written notice signed by the Contractor and delivered to the
Director of Public Works.
14. CONTRACTOR’S RESPONSIBILITY FOR WORK
Until the final acceptance of the work by the City, by written action of the Director of
Public Works, the Contractor shall have the charge and care thereof and shall bear the
C-23
GP-4
R6876-0001\1800410v2.doc
risk of injury or damage to any part of the work by the action of the elements or any other
cause. The Contractor shall rebuild, repair, restore and make good all injuries or
damages to any portion of the work occasioned by any cause before its completion and
acceptance and shall bear the expense thereof, except for such injuries or damages
arising from the sole negligence of willful misconduct of the City, its officers, agents or
employees. In the case of suspension of work from any cause whatever, the Contractor
shall be responsible for all materials and the protection of work already completed and
shall properly store and protect them if necessary and shall provide suitable drainage
and erect temporary structures where necessary.
15. MAINTENANCE AND GUARANTEE
(a) The Contractor hereby guarantees that the entire work constructed by
Contractor under the contract will meet fully all requirements as to quality
of workmanship and materials. The Contractor hereby agrees to make at
Contractor’s own expense any repairs or replacements made necessary
by defects in materials or workmanship that become evident within one
(1) year after the date of the City’s acceptance of the entire project, which
is when the City Council directs staff to file a Notice of Completion, and to
restore to full compliance with the requirements of these specifications,
including any test requirements set forth herein for any part of the project
or work constructed hereunder, which during said one (1) year period is
found to be deficient with respect to any provisions of the specifications.
The Contractor shall make all repairs and replacements promptly upon
receipt of written orders for the same from the Director of Public Works.
The Contractor and Contractor’s sureties shall be liable to the City for the
cost thereof.
(b) The guarantees and agreements set forth in subsection (a) shall be
secured by a surety bond which shall be delivered by the Contractor to
the City before the City’s acceptance of the project. Said bond shall be in
the form approved by the City Attorney and executed by a surety
company or companies admitted in the State of California and satisfactory
to the City, in the amount of 100 percent of the contract. Said bond shall
remain in force for a period of one (1) year after the date that the City
accepts the project. Alternatively, the Contractor may provide for the
Faithful Performance Bond furnished under the contract to remain in force
and effect for said amount until the expiration of said one (1) year period.
If the Contractor wishes to pursue the option of extending the Faithful
Performance Bond for an additional one (1) year period in lieu of a
separate surety bond, the Contractor shall provide written evidence from
the surety of such Faithful Performance Bond extension before the City’s
acceptance of the project. Delivery of the one-year surety bond or proof of
Faithful Performance Bond extension shall be a condition precedent to
the City Council’s approval of the Notice of Completion.
16. COOPERATION
The Contractor is hereby notified that additional work within the work site may be
scheduled during the course of this contract.
C-24
GP-5
R6876-0001\1800410v2.doc
The Contractor shall cooperate with these and other projects in accordance with
Sections 5-6 and 7-7 of the Standard Specifications. Compensation for compliance shall
be included in the various items of work, and no additional compensation shall be
allowed therefor.
C. PROSECUTION AND PROGRESS OF THE WORK
1. WORK SCHEDULE
Prior to the Notice to Proceed, the Contractor shall submit a work schedule to the
Director of Public Works or his authorized representative for approval. Said schedule
must show the dates of the expected start and completion of the various items of the
contract work. This schedule will be used as a controlling document throughout the
construction period.
2. SUBLETTING AND ASSIGNMENT
The Contractor shall give Contractor’s personal attention to the fulfillment of the contract
and shall keep the work under Contractor’s control. The Contractor shall not assign,
transfer nor sublet any part of the work without the written consent of the City by the
Director of Public Works or his authorized representative and of the surety of the
Contractor’s bond, and such consent of Surety, together with a copy of the subcontract,
shall be filed with the Director of Public Works. No assignment, transfer or subletting,
even though consented to, shall relieve the Contractor of Contractor’s liabilities under
the contract. Subcontractors shall not be recognized as such, and all persons engaged
in the project will be considered as employees of the Contractor, their work being subject
to the provisions of the contract and the specifications. Should any subcontractor fail to
perform the work undertaken by him to the satisfaction of the Director of Public Works or
his authorized representative, said subcontractor shall be removed immediately from the
project upon request by the Director of Public Works, shall not again be employed on the
work, and the Contractor shall be held liable for the deficient work. The Contractor shall
submit to the City a list with the names, addresses and telephone numbers of all
subcontractors who will work under Contractor.
3. CHARACTER OF WORKERS
The Contractor shall employ none but competent foremen, laborers and mechanics.
Any overseer, superintendent, laborer or other person employed on the work by the
Contractor who is intemperate, incompetent, troublesome or otherwise undesirable, or
who fails or refuses to perform the work in the manner specified herein, shall be
removed from jobsite immediately and such person shall not again be employed on the
work.
4. AGENTS OR FOREMAN
In the absence of the Contractor from the site of the project, even if such is only of a
temporary duration, Contractor must provide and leave at the site a competent and
reliable English-speaking agent or foreman in charge. All notices, communications,
orders or instructions given, sent to, or served upon, such agent or foreman by the
Director of Public Works shall be considered as having been served upon the
Contractor.
C-25
GP-6
R6876-0001\1800410v2.doc
5. TEMPORARY STOPPAGE OF CONSTRUCTION ACTIVITIES
The Director of Public Works shall have the authority to suspend the contract work,
wholly or in part, for such a period of time as the Director may deem necessary, due to
unsuitable weather, or to such other conditions as the Director considers unfavorable for
the proper prosecution of the work, or for such time as the Director may deem necessary
due to failure on the part of the Contractor or Contractor ’s workers to carry out orders or
to perform any of the requirements of the contract. The Contractor shall immediately
comply with such an order from the Director of Public Works and shall not resume
operations until so ordered in writing.
6. TIME OF COMPLETION AND LIQUIDATED DAMAGES
If all the contract work is not completed in all parts and requirements within the time
specified in the contract documents, the City shall have the right to grant or deny an
extension of time for completion, as may seem best to serve the interest of the City. The
Contractor shall not be assessed with liquidated damages during any delay in the
completion of the work caused by acts of God or of the Public Enemy, acts of the State,
fire not due to acts of contractors, of subcontractors, floods, epidemics, quarantine,
restrictions, strikes, freight embargo or unusually severe weather, delays of
subcontractors due to such causes, or work suspensions directed by the Director of
Public Works or his authorized representative provided that the Contractor shall, within
ten (10) days from the beginning of such delay, notify the City, in writing, of the cause of
the delay. The City will ascertain the facts and the extent of the delay, if any, and the
finding thereon shall be final and conclusive. If the City deems it appropriate to assess
the contractor liquidated damages, such damages shall be in the amount specified in
this bid documents. Delay claims by the Contractor will be precluded for those damages
caused exclusively by the City. The Contractor is entitled only to delay damages caused
by others.
7. SUSPENSION OF CONTRACT
If at any time, in the opinion of the Director of Public Works, the Contractor fails to supply
an adequate working force, manufactured articles, or material of proper quality, or has
failed in any other respect to prosecute the work with the diligence and force specified
and intended in any by the terms of the contract, notice thereof in writing will be served
upon Contractor, and should Contractor neglect or refuse to provide means for a
satisfactory compliance with the contract within the time specified in said notice and as
directed by the Director of Public Works, the Director of Public Works shall have the
power to suspend the operation of the contract and discontinue all work or any part
thereof, subject to review by the City Council. Thereupon the Contractor shall
discontinue such work, or such part thereof as the City may designate, and the City may
thereupon, by contract or otherwise, as it may determine, complete the work or such part
thereof, and charge the entire expense of so completing the work or any part thereof to
the Contractor, and for such completion the City itself or its Contractors may take
possession of and use, or cause to be used in the completion of the work, or any part
thereof, any such materials, implements and tools of every description as may be found
at the place of such work. All expenses charged under this paragraph shall be deducted
and paid for by the City out of any moneys then due or to become due the Contractor
under the contract, or any part thereof, and in such accounting the City shall not be held
to obtain the lowest figure for the work for completing the contract, or any part thereof, or
C-26
GP-7
R6876-0001\1800410v2.doc
for ensuring its proper completion, but all sums paid therefor shall be charged to the
Contractor. In case the expenses so charged are less than sum which would have been
payable under the contract, if the same had been completed by the Contractor, the
Contractor shall be entitled to receive the difference, and in case such expense shall
exceed the amount payable under the contract, then the Contractor shall pay the amount
of the excess to the City, upon completion of the work, without further demand being
made therefor. In the determination of the question as to whether or not there has been
any such noncompliance with the contract as to warrant the suspension or annulment
thereof, the decision of the City Council shall be binding on all parties to the contract.
D. MEASUREMENT AND PAYMENT
1. MEASUREMENT AND PAYMENT
Measure of the quantities of work and payments therefor shall be in accordance with
Section 9 of the Standard Specifications. In accordance with Subsection 9-3.2 of the
Standard Specifications, the monthly payment date shall be the last calendar day of
each month. A measurement of work performed, and a progress estimate of the value
thereof based on the contract and of the monthly payment shall be prepared by the
Contractor and submitted to the Director of Public Works or his authorized
representative before the tenth day of the following month for verification and payment
consideration. A five percent (5%) retention shall be withheld from each payment.
2. FINAL INVOICE AND PAYMENT
Whenever in the opinion of the Director of Public Works, the Contractor shall have
completely performed the contract, the Director of Public Works or his authorized
representative shall notify the City Clerk that the contract has been completed in its
entirety. The Contractor shall then submit to the Director of Public Works or his
authorized representative for approval of a written statement of the final quantities of
contract items for inclusion in the final invoice. Upon receipt of such statement, the
Director of Public Works or his authorized representative shall check the quantities
included therein and shall authorize the Contractor to submit an invoice which in the
Director of Public Works’ opinion shall be just and fair, covering the amount and value of
the total amount of work done by the Contractor, less five percent (5%) of the total work
done. The Director of Public Works shall then request that the City accept the work and
that the City Clerk be authorized to file, on behalf of the City in the office of the Los
Angeles County Recorder, a Notice of Completion of the work herein agreed to be done
by the Contractor.
On the expiration of thirty-five (35) days after the date of recording the Notice of
Completion, the City shall pay to the Contractor the amount remaining after deducting
from the amount of value stated in the invoice all prior payments to the Contractor and
all amounts to be kept and retained under the provisions of the contract and shall
release the Faithful Performance Bond and Labor and Material Bond.
The Contractor may, at Contractor’s sole cost and expense, substitute securities
equivalent to any monies withheld by the Owner as provided in California Public
Contract Code Section 22300. No such substitution shall be accepted until all
documents related to such substitution are reviewed and found acceptable by the
Owner’s attorney.
C-27
GP-8
R6876-0001\1800410v2.doc
3. EXTRA WORK
Extra work, when ordered in writing by the Director of Public Works or his authorized
representative and accepted by the Contractor, shall be paid for under a written work
order in accordance with the terms therein provided. Payment for extra work will be
made at the unit price or lump sum previously agreed upon between the Contractor and
the Director of Public Works. All extra work shall be adjusted daily upon report sheets
prepared for the Director of Public Works or his authorized representative, furnished by
the Contractor, and signed by both parties, and said daily report shall be considered
thereafter the true records of extra work done.
The first sentence of Subsection 3-3.2.2.2 Basis for Establishing Costs, (a) Labor, of the
Standard Specifications, is hereby deleted and replaced with the following:
The costs of labor will be the actual cost of wages of workers performing the extra work
at the time the extra work is done, plus the applicable labor surcharge as set forth in the
California Department of Transportation publication entitled “Labor Surcharge and
Equipment Rental Rates,” which is in effect on the date upon which the work is
accomplished, as well as assessments or benefits required by lawful collective
bargaining agreements.
4. UNPAID CLAIMS
If upon or before the completion of the work herein agreed to be performed or at any
time prior to the expiration of the period within which claims of lien may be filed for
record as prescribed by the Code of Civil Procedure of the State of California, any
person or persons claiming to have performed any labor or furnished any materials,
supplies or services towards the performance of completion of this contract or if they
have agreed to do so, shall file with the City a verified statement of such claim, or if any
person shall bring against the City or any of its agents any action to enforce such claim,
the City shall until the discharge thereof, withhold from the moneys that are under its
control, as much as shall be sufficient to satisfy and discharge the amount in such notice
or under such action claimed to be due, together with the cost thereof; provided, that if
the City shall in its discretion permit the Contractor to file such additional bond as is
authorized by the Code of Civil Procedure in a penal sum equal to one and one-quarter
times the amount of said claim, said money shall not thereafter be withheld on account
of such claim.
5. ACCEPTANCE
The parties agree that no certificate given shall be conclusive evidence of the faithful
performance of the contract, either in whole or in part, and that no payment shall be
construed to be in acceptance of any defective work or improper materials. Further, the
certificate or final payment shall not terminate the Contractor’s obligations under the
warranty here in above. The Contractor agrees that payment of the amount due under
the contract and the adjustments and payments due for any work done in accordance
with any alterations of the same, shall release the City, the City Council and its officers
and employees from any and all claims or liability on account of work performed under
the contract or any alteration thereof.
C-28
GP-9
R6876-0001\1800410v2.doc
E. CONTROL OF WORK
1. AUTHORITY OF THE DIRECTOR OF PUBLIC WORKS
The Director of Public Works shall decide any and all questions that may arise as to the
quality and acceptability of materials furnished and work performed as to the manner of
performance and rate of progress of the work, and any and all questions, which may
arise as to the interpretation of the plans and specifications. The Director of Public
Works shall likewise decide any and all questions as to the acceptable fulfillment of the
contract on the part of the Contractor, and all questions as to claims and compensations.
The decision of the Director of Public Works shall be final, and he shall have relative
authority to enforce and make effective such decisions and actions as the Contractor
fails to carry out promptly.
For the purposes of routine and normal supervision and coordination of work, the
Director of Public Works is the City’s authorized representative for all work within the
scope of this agreement.
2. CONFORMITY WITH PLANS AND ALLOWABLE VARIATION
Finished surfaces shall in all cases conform to the lines, grades, cross-sections and
dimensions shown on the plans. Minor deviations from approved plans, whenever
required by the exigencies of construction, shall be determined in all cases by the
Director of Public Works and authorized in writing. All such deviation shall be recorded
on “as–built” plans and submitted to the Director of Public Works or his authorized
representative, upon project completion.
3. PROGRESS OF THE WORK
The Contractor’s working days shall begin on the date stated in the Notice To Proceed,
which will be issued following the scheduling conference. The Contractor shall diligently
prosecute the work to completion before the expiration of the time limit appearing in the
specifications.
4. SAMPLES
The Contractor shall furnish all products and materials required to complete the work.
All materials and products must be of the specified quality and fully equal to samples,
when samples are required. Whenever required, the Contractor shall submit to the
Director of Public Works or his authorized representative for test, and free of charge,
samples of any one of the materials or products proposed to be used in the work. Said
samples shall be delivered by the Contractor to the place within the City designated by
the Director of Public Works. Rejected materials must be immediately removed from the
work by the Contractor and shall not be brought back to the site.
5. TRADE NAMES AND ALTERNATIVES
For convenience in designation on the plans or in the specifications, certain equipment
or articles or materials to be incorporated in the work may be designated under a trade
name of manufacturer and the catalog information. The use of an alternative equipment
or an article or equipment which is of equal quality and of the required characteristics for
C-29
GP-10
R6876-0001\1800410v2.doc
the purpose intended will be permitted, subject to the approval of the Director of Public
Works or his authorized representative, in accordance with the following required by
Section 3400 of the Public Contract Code of the State of California:
The burden of proof as to the comparative quality and suitability of alternative equipment
or articles or materials shall be upon the Contractor, and Contractor shall furnish, at
Contractor’s own expense, all information necessary or related thereto as required by
the Director of Public Works or his authorized representative. The Director of Public
Works shall be the sole judge as to the comparative quality and suitability of alternative
equipment or articles or materials and the Director’s decision shall be final. All requests
for substitution shall be submitted, together with all documentation necessary for the
Director to determine equality, within 20 days following the award of the contract.
6. PROTECTION OF WORK
The Contractor shall continuously maintain adequate protection of all Contractor’s work
from damage, and the City will not be held responsible for the care or protection of any
material, equipment or parts of work, except as expressly provided for in the
specifications.
7. CONFLICT OF TERMS
The notice to bidders, proposal, plans, specifications and General Provisions are
essential parts of the contract for a given project. These documents, together with the
necessary bonds and bidder’s guarantee, constitute the contract as defined herein, and
a requirement included in one document shall be as binding as though included in all, as
they are intended to be cooperative and to provide a description of the work to be done.
Should there be any conflict or discrepancy between terms used, then the specifications
shall govern over plans, and change orders and supplemental agreements shall govern
over any other contract document.
8. INTERPRETATION OF PLANS AND SPECIFICATIONS
Should it appear that the work to be done, or any matter relative thereto, is not
sufficiently detailed or explained on the plans or in the specifications, the Contractor
shall request the Director of Public Works or his authorized representative for such
further explanation as may be necessary and shall conform to such explanation or
interpretation as part of the contract, so far as may be consistent with the intent of the
original specifications. In the event or doubt of questions relative to the true meaning of
the specifications, reference shall be made to the City Council, whose decision thereon
shall be final.
9. INCREASES AND DECREASES OF THE WORK TO BE DONE
The City reserves the right to increase or decrease the quantity of any item or portion of
the work described on the plans, the specifications or the proposal form or to omit
portions of the work so described, as may be deemed necessary or expedient by the
Director of Public Works and the Contractor shall agree not to claim or bring suit for
damages, whether for loss of profits or otherwise, on account of any decrease or
omission of any kind of work to be done.
C-30
GP-11
R6876-0001\1800410v2.doc
10. ALTERATIONS OF THE WORK TO BE DONE
By mutual consent of the parties signatory to the contract, alterations, modifications or
deviations from the type of work may be described on the plans, specifications or on the
proposal form may be made without in any way making the contract void. The price to
be paid by the City to the Contractor for such altered or modified work shall be agreed
upon in writing, endorsed upon the original contract and signed by the proper parties to
said contract.
Whenever, during the progress of the work, such changes or modifications are deemed
necessary by the Director of Public Works and agreed upon, as aforesaid, said
deviations shall be considered and treated as though originally contracted for, and shall
be subject to all the terms, conditions and provisions of the original contract.
11. EXTRA WORK
New and unforeseen work will be classed as extra work only when said work is not
covered and cannot be paid for under any of the various items or combination of items
for which a bid price appears on the proposal form. The Contractor shall not do any extra
work except upon written order from the Director of Public Works or his authorized
representative. Compensation for such extra work shall be previously agreed upon in
writing between the Contractor and the Director of Public Works or his authorized
representative.
12. PUBLIC UTILITIES
(a) All of the existing utility facilities except those to be relocated as shown on
the plans will remain in place and the Contractor will be required to work
around said facilities. In case it should be necessary to remove the
property of a public utility or franchise, such owner will, upon proper
application by the Contractor, be notified by the Director of Public Works
or his authorized representative to move such property within a
reasonable time, and the Contractor shall not interfere with said property
until after the expiration of the time specified. The right is reserved to the
owners of public utilities or franchises to enter upon the project site for the
purpose of making repairs or changes in their property, which may be
necessary as a result of the work. The Contractor shall also schedule
and allow adequate time for those relocations or modifications necessary
for the project by the respective utility owners. Employees and agents of
the City shall likewise have the privilege of entering upon the street for the
purpose of making any necessary repairs or replacements.
(b) The Contractor shall employ and use only qualified persons, as
hereinafter defined, to work in proximity to Southern California Edison
secondary, primary and transition facilities. The term “qualified person”
shall mean one, who by reason of experience or instruction, is familiar
with the operation to be performed and the hazards involved, as more
specifically defined in Section 2700 of Title 8 of the California
Administrative Code. The Contractor shall take such steps as are
necessary to assure compliance by any subcontractors.
C-31
GP-12
R6876-0001\1800410v2.doc
13. PROCEDURE IN CASE OF DAMAGE TO PUBLIC PROPERTY
Any portions of curb, gutter, sidewalk or any other City improvement damaged by the
Contractor during the course of construction shall be replaced by the Contractor at
Contractor’s own cost, free of charges to the City. The cost of additional replacement of
curb, gutter or sidewalk in excess of the estimated quantities shown in the proposal form
and specifications, and found necessary during the process of construction, (but not due
to damage resulting from carelessness on the part of the Contractor during Contractor ’s
operation), shall be paid to the Contractor at the unit prices submitted in his bid.
14. REMOVAL OF INTERFERING OBSTRUCTIONS
The Contractor shall remove and dispose of all debris, abandoned structures, tree roots
and obstructions of any character met during the process of excavation, it is understood
that the cost of said removals are made a part of the unit price bid to the Contractor
under the item for Clearing and Grubbing.
15. QUALITY OF MATERIAL
Materials shall be new, and of specified kind and quality, and fully equal to samples
when samples are required. When the quality or kind of material or articles shown
required under the contract is not particularly specified, the Contractor shall estimate that
the City will require articles and materials representing the best of their class or kind or
at least equal to the class or quality of similar articles, existing articles or materials when
specified. Materials shall be furnished in such quantities and kinds and at such times as
to ensure uninterrupted progress of the work. They shall be stored properly and
protected as required. The Contractor shall be entirely responsible for damage or loss
by weather or any other cause.
16. REMOVAL OF DEFECTIVE OR UNAUTHORIZED WORK
It is the intent of the specifications that only first-class work, materials and workmanship
will be acceptable. All work which is defective in its construction or deficient in any of the
requirements of the specifications shall be remedied or removed and replaced by the
Contractor in an acceptable manner, and no compensation will be allowed for such
correction. Any work done beyond the lines shown on the plans or established by the
Director of Public Works or his authorized representative, or any extra work done without
written authority will be considered as unauthorized and will not be paid for. Upon failure
on the part of the Contractor to comply forthwith with any order of the Director of Public
Works made under the provisions of this paragraph, the Director of Public Works shall
have authority to cause defective work to be remedied or removed and replaced, and
unauthorized work to be removed, and to deduct the costs thereof from any moneys due
or to become due the Contractor. If the work is found to be in compliance with these
specifications, the Director of Public Works will furnish the Contractor with a certificate to
that effect.
17. SUPERVISION
All manufactured products, materials and appliances used and installed and all details of
the work shall at all times be subject to the supervision, test and approval of the Director
of Public Works or his authorized representatives. The Director of Public Works or his
C-32
GP-13
R6876-0001\1800410v2.doc
authorized representatives shall have access to the work at all times during construction,
and shall be furnished with every reasonable facility for securing full knowledge with
regard to the progress, workmanship and character of the materials used or employed in
the work.
Whenever the Contractor varies the period during which work is carried on each day, he
shall give adequate notice to the Director of Public Works or his authorized
representative so that proper inspection may be provided. Any work done in the absence
of the Director of Public Works or the Director of Public Works’ agent will be subject to
rejection. The inspection of the work shall not relieve the Contractor of any of his
obligations to fulfill the contract as prescribed. Defective work shall be made good, and
unsuitable materials may be rejected, notwithstanding the fact that such defective work
and unsuitable materials have previously been accepted or estimated for payment.
The Contractor shall prosecute work on any State highway or with any railroad right-of-
way only in the presence of an inspector representing the State Division of Highways or
the railroad company, and any work done in the absence of such inspectors will be
subject to rejection. The Contractor shall make the appropriate notification according to
the instructions given on the State Encroachment Permit or railroad permit for all
inspections, and shall post all bonds and certificates required by the permit. The permit
shall be acquired by the Contractor at the Contractor’s expense. The Contractor shall
pay for all testing and inspections required by a State Encroachment Permit or railroad
permit.
18. SOIL COMPACTION TESTING
Any soil compaction testing, geotechnical observation and certification shall be provided
by a Geotechnical Testing Company and paid for by the City.
19. PRESERVATION OF PROPERTY
Existing improvements in areas adjoining the property whereon demolition and removal
is being performed shall be protected from injury or damage resulting from operations of
the Contractor and the Contractor shall be responsible for such damage. In like manner
any building, structure, tree, shrub, or other item designated for preservation on the
property where demolition and removal is being performed shall be similarly protected
and preserved. When necessary, roots of trees to be preserved must be pruned in an
acceptable manner to maximize the probability of recovery of the said tree.
20. DUST CONTROL
The Contractor shall provide such dust laying equipment and methods as may be
required to protect adjacent property from annoyance or damage from dust caused by
his operations, and failure to control such dust shall be cause for the Director of Public
Works or his authorized representative to stop the work until said dust is controlled, and
the Contractor shall have no recourse to collect from the City for any loss of time or
expense sustained by him due to such suspension of work.
The contractor shall clean all areas affected by his/her work in a manner which is
acceptable by the Director of the Public Work or his/her designee. If the City is not
satisfied with the cleaning work, the city may urgently hire another cleaning crew to
C-33
GP-14
R6876-0001\1800410v2.doc
clean the area and back charge the contractor for all cost incurred to the City including
City staff time.
21. SELECTED MATERIALS
Existing materials excavated within the project limits that meet the specifications for
trench backfill, topsoil, or other selected materials may be used to fulfill all or a portion of
the requirements for such materials. No additional compensation will be allowed for
excavation, stockpiling, overhaul, or placing selected materials encountered in the
excavation. The Contractor shall stipulate a reasonable price for additional quantities of
import, that may be needed, in their proposal, that is acceptable with the Director of
Public Works or his/her designee.
22. SURPLUS MATERIALS
The Contractor shall furnish written consent from the owner of the property where it is
intended to dispose of the surplus material. Surplus excavation shall become the
property of the Contractor.
23. CLEAN UP
During all phases of construction, the Contractor shall maintain a clean work site; the
Contractor shall be responsible for the removal and disposal of all concrete, asphalt, tree
roots, and any other debris resulting from the work performed on a daily basis. Full
compensation for clean-up shall be considered as included in the prices for the various
contract items.
24. EQUIPMENT REQUIREMENTS
The Contractor shall provide a lead car with a “Wide Load” warning sign to lead the
movement of any equipment exceeding 7 feet in maximum horizontal dimension over
any street to the location of the scheduled work site. Equipment will be subject to a fine
of one hundred dollars for each violation as determined by the Director of Public Works
or his authorized representative. Any other violations shall be subject to the vehicle
code of the State of California. Full compensation for the cost of furnishing the lead
vehicles and adhering to the requirements of this section shall be considered as included
in the prices for the various contract items of work, and no additional compensation will
be allowed therefor.
25. PROTECTION OF WORK AND PUBLIC
The Contractor shall take all necessary measures to protect work and prevent accidents
during any and all phases of the work. The Contractor shall repair all damaged parts of
the project as a result of vandalism (i.e., vehicle tracks, footprints, writing, etc.) and will
respond to alleged damage to private property and/or vehicles within twenty four (24)
hours of notification. If deemed necessary by the City, the Contractor shall repair the
defective area in accordance with these Special Provisions.
C-34
GP-15
R6876-0001\1800410v2.doc
26. SPRINKLER SYSTEMS & LANDSCAPING
Any sprinkler system damaged during the Contract shall be repaired by the Contractor
at no additional cost within 24 hours of notification. All damaged sprinkler and irrigation
parts shall be replaced in-kind. If repair is not completed within said limit, the City shall
have the authority to complete such work and deduct cost plus 20 percent administration
thereof from any moneys due or to become due to the Contractor. Furthermore, a
penalty of $500 per day shall be applied for each day beyond the 24-hour period that the
damaged irrigation system has not been repaired to function properly (as determined by
the City’s inspector).
27. CONTRACTOR’S SUPERINTENDENT AND PROJECT MANAGER
The Contractor shall designate in writing and keep on the work at all times during its
process a competent, full-time, technically qualified superintendent, who shall not be
replaced without written notice to the Director of Public Works or his authorized
representative except under extraordinary circumstances. The Contractor’s
superintendent shall be present at the site of the work at all times while work is in
progress. The Superintendent’s sole duties shall be to supervise a full work crew and
coordinate activities pertaining to any work performed by the Contractor or its
subcontractors, including but not limited to concrete repairs, crack sealing, AC repairs,
traffic control and public notifications. Failure to observe this requirement shall be
considered as suspension of the work by the Contractor until such time as such
superintendent is again present at the site. The Director of Public Works or his
authorized representative shall have the right, at any time, to direct a change in the
Contractor’s superintendent, if the performance is unsatisfactory, as determined by the
Director of Public Works or his authorized representative, in its sole discretion.
The Contractor shall designate in writing and keep on the work at all times during its
process a competent, full-time, technically qualified project manager, who shall not be
replaced without written notice to the Director of Public Works or his authorized
representative except under extraordinary circumstances. The Contractor’s project
manager shall be responsible for overall administration and coordination of the work
including, but not limited to processing of schedules, discussion of change orders and
extra work and coordination and distribution of the Daily Reports. The Director of Public
Works or his authorized representative shall have the right, at any time, to direct a
change in the Contractor’s project manager, if the performance is unsatisfactory, as
determined by the Director of Public Works or his authorized representative, in its sole
discretion.
The Contractor’s superintendent shall have a working multi frequency two-way radio with
adequate range for City-wide communication on him/her at all times during the course of
the project. The Contractor shall provide to the City’s Construction Observers, a small
portable working, multi frequency two-way radio compatible for communication with that
of the Contractor’s Superintendent’s communication device and a charger. The
Contractor shall also provide to each of the City’s Construction Observers a portable
cellular telephone, two cell telephone batteries and charger and pay for service for the
duration of the project. The Contractor shall only choose a carrier that has adequate
coverage in the area. All telephone calls will only be project related. Failure to observe
this requirement shall be considered as suspension of the work by the Contractor until
such time as said radio communication is re-established. The cost for furnishing radios
C-35
GP-16
R6876-0001\1800410v2.doc
and phones shall be considered as included in the bid price paid for the various contract
items of work, no additional compensation will be made therefor. Said radios and cellular
telephones will be returned to the Contractor after the completion of the project. The City
will endeavor to safeguard the Contractor’s communication devices but assumes no
responsibility or liability for any possible damage to the cellular telephones or radios.
28. WORK AFTER REGULAR HOURS
No work shall be performed after regular working hours, or work in excess of 8 hours a
day, or on Saturday, Sunday, or any legal holiday and if approved by the City, the
Contractor shall pay the City any additional cost incurred by the City as a result of such
work.
Any of the additional costs incurred by the City due to afterhours work by the Contractor
will be deducted from any monies due or to become due to the Contractor.
29. CONTRACTOR’S DAILY REPORTS
The Contractor shall complete consecutively numbered legible daily reports indicating
the number of people working, their names, a narrative description of work performed,
the individual locations of the work, serviceable major equipment in use, serviceable
major equipment idled, serviceable major equipment down for repairs, sub-contractors
working at site, weather conditions, temperature, start time, finish time, and the date.
The Contractor’s Superintendent shall sign each report. The daily report shall be
completed on forms prepared by the Contractor and acceptable to the Director of Public
Works or his authorized representative. No progress payments will be processed or
made to the Contractor unless all daily reports are completed to the date of submittal of
application for payment.
30. REQUEST FOR WORKING DAYS
The Contractor shall notify the Director of Public Works or his authorized representative
separately in writing within 7 calendar days after the occurrence of a delay, when the
Contractor believes that it is entitled to an additional working day per any day the
Contractor is prevented from working at the beginning of the workday, for cause defined
in Section 6-6.1 of the Standard Specifications, or any day the Contractor is prevented
from working during the first 5 hours with at least 60 percent of the normal work force for
cause as defined in Section 6-6.1 of the Standard Specifications. The Contractor’s
failure to give written notice in the time period specified above shall constitute a waiver
of all claims for an additional work day, whether direct or consequential in nature and
that day will be counted as a working day. Upon receipt of the Contractor ’s written
request, the Director of Public Works or his authorized representative will then make a
determination of whether the day or days the Contractor is requesting shall be counted
as working days.
31. DEFECTIVE MATERIALS
All materials not conforming to the requirements of these specifications shall be
considered as defective and all such materials shall be removed immediately from the
site of the work unless otherwise permitted by the Director of Public Works or his
authorized representative. Upon failure on the part of the Contractor to comply with any
C-36
GP-17
R6876-0001\1800410v2.doc
order by the Director of Public Works or his authorized representative made under the
provisions of this article, the Director of Public Works shall have the authority to remove
and replace defective material and to deduct the cost of removal and replacement from
any moneys due or to become due to the Contractor.
32. SOUND AND VIBRATION CONTROL REQUIREMENTS
The Contractor shall comply with all local sound control and noise level rules, regulations
and ordinances. No internal combustion engine shall operate on the project without a
muffler of the type recommended by the manufacturer. Should any muffler or other
control device sustain damage, the Contractor shall promptly remove the equipment and
shall not return said equipment to the job until the device is repaired or replaced. Said
noise and vibration level requirements shall apply to all equipment on the job or related
to the job, including, but not limited to truck, transit mixers or transit equipment that may
or may not be owned by the Contractor.
33. AIR POLLUTION CONTROL
Contractor shall comply with all air pollution control rules, regulations, ordinances and
statutes. All containers of paint, thinner, curing compound, solvent or liquid asphalt shall
be labeled to indicate the contents, fully complying with the applicable material
requirements.
34. FINAL CLEAN UP
Upon completion of the project and before making application to the Director of Public
Works or his authorized representative for acceptance of the work, the Contractor shall
clean all the streets and ground occupied by Contractor in connection with the project, of
all rubbish, debris, excess material, temporary structures and equipment, leaving the
entire site of the work in a neat and presentable condition. This clean-up by the
Contractor shall include removal of all USA dig-alert markings and construction markings
of all kinds by power-washing or other method approved by the Director of Public Works,
or his authorized representative. Painting over the USA dig-alert markings is not
considered an acceptable method of removal.
A list of final punchlist items shall be provided to the Contractor by the City. Upon
Contractor’s receipt of this final punchlist, the Contractor shall have 14 calendar days to
complete all items on the punchlist. PENALTIES FOR NONCOMPLIANCE: $500 for
each day after the 20-calendar-day period that there are still remaining punchlist items to
be completed by the Contractor.
35. CONTRACTOR’S REQUEST FOR FINAL INSPECTION
When the Contractor believes all the contract work is complete in all parts and
requirements, the Contractor will notify the Director of Public Works or his authorized
representative in writing through a certificate of completion form, which will be provided
to the Contractor at the pre-construction conference.
After the City receives the Contractor’s certificate of completion, the Director of Public
Works or his authorized representative will review the Contractor’s work for substantial
performance with the contract documents. If the Director of Public Works or his
C-37
GP-18
R6876-0001\1800410v2.doc
authorized representative deems the work substantially performed, the Public Works
Director will prepare a list of any minor remaining items of work to be completed. The
Contractor shall complete all work on the list to the satisfaction of the Director of Public
Works or his authorized representative within 30 calendar days after the date of the list
or the Contractor waives any and all claims to all monies withheld by the City under the
Contract to cover the value of all such uncompleted or uncorrected items, including any
additional engineering, administration, or inspection costs. If the work was not
substantially performed, working days will continue to accrue against the Contractor.
36. RESOLUTION OF PUBLIC WORKS CLAIMS
This contract is subject to the provisions of Article 1.5 (commencing at Section 20104) of
Division 2, Part 3 of the California Public Contract Code regarding the resolution of
public works claims of less than $375,000. Article 1.5 mandates certain procedures for
the filing of claims and supporting documentation by the contractor, for the response to
such claims by the contracting public agency, for a mandatory meet and confer
conference upon the request of the contractor, for mandatory judicial arbitration upon the
failure to resolve the dispute through mediation. This contract hereby incorporates the
provisions of Article 1.5 as through fully set forth herein.
This contract is also subject to Public Contract Code Section 9204, which establishes
procedures for claims and responses to claims made by a contractor in connection with
a public works project.
37. TRENCHES AND EXCAVATIONS
In accordance with Public Contract Code Section 7104, whenever the digging of
trenches or other excavations extend deeper than 4 feet below the surface, the
Contractor shall promptly, and before the following conditions are disturbed, notify the
City in writing of any: 1) Material that the Contractor believed may be material that is
hazardous waste, as defined in Health and Safety Code Section 25117, that is required
to be removed to a Class I, Class II, or Class III disposal site in accordance with
provisions of existing law: 2) Subsurface or latent physical conditions at the site differing
from those indicated; or 3) Unknown physical conditions at the site of any unusual
nature, different materially from those ordinarily encountered and generally recognized
as inherent in work of the character provided for in the contract. The City shall promptly
investigate the conditions, and if it finds that the conditions do materially so differ, or do
involve hazardous waste and cause a decrease or increase in the Contractor’s cost of,
or the time required for, performance of any part of the work, the City shall issue a
change order under the procedures described in the Contract. In the unlikely event that
a dispute arises between the City and the Contractor regarding whether the conditions
materially differ, or involve hazardous waste, or cause a decrease or increase in the
Contractor’s cost of, or time required for, performance of any part of the work, the
Contractor shall not be excused from any scheduled completion date provided for by the
Contract, but shall proceed with all work to be performed under the Contract.
The Contractor shall retain any and all rights provided either by contract or by law, which
pertain to the resolution of disputes and protests between the contracting parties.
Where applicable, Contractor shall comply with the trench or excavation permit
requirement found in Labor Code Section 6500 and the excavation safety requirements
found in Labor Code Section 6705. No excavation shall be left open during the
C-38
GP-19
R6876-0001\1800410v2.doc
weekends or Holidays.
38. CONSTRUCTION & DEMOLITION MATERIALS RECYCLING
REQUIREMENTS
Subsection 7-15 is hereby added to the Standard Specifications:
PART 1 GENERAL
7-15.1.1 SUMMARY
A. This Section includes the following: procedures for ensuring optimal diversion of
construction and demolition (C&D) waste materials generated by the Work within the
limits of the Construction Schedule and Contract Sum.
1. The Integrated Solid Waste Management Act of 1989 (“AB 939”), requires that
localities throughout the state develop source reduction, reuse, recycling, and
composting programs to reduce the tonnage of solid waste disposed in landfills
by 50%; this requirement may increase in the future. C&D waste materials
generated by the Work are targeted to achieve these diversion rates.
2. A minimum of 50% by weight of the solid wastes generated in the Work shall be
diverted from landfill disposal through a combination of reuse, recycling, and
composting activities.
3. This section includes requirements for submittal of C&D Debris Management
Plan prior to the commencement of the Work, and during the project, submittal of
Contractor’s quantitative reports for construction and demolition waste materials
generated by the Contractor as a condition of approval of progress payments
submitted to the Contracting Officer, and following completion of the project, as a
condition of the release of final project retention.
7-15.1.2 DEFINITIONS
A. Class III Landfill. A landfill that accepts non-hazardous waste such as household,
commercial, and industrial waste, resulting from construction, remodeling, repair, and
demolition operations. A Class III landfill must have a solid waste facility permit from the
California Department of Resources Recycling and Recovery (CalRecycle) and is
regulated by the Enforcement Agency (EA).
B. Construction and Demolition Debris/Materials or C&D Debris/Materials. Building
materials and solid waste resulting from construction, remodeling, repair, cleanup, or
demolition operations that are not hazardous as defined in California Code of
Regulations, Title 22, Section 66261.3 et seq. This term includes, but is not limited to,
asphalt, concrete, Portland cement, brick, lumber, gypsum wallboard, cardboard and
other associated packaging, roofing material, ceramic tile, carpeting, plastic pipe, and
steel. The debris may be commingled with rock, soil, tree stumps, and other vegetative
matter resulting from land clearing and landscaping for construction or land development
projects.
C. Contracting Officer. The City of Rancho Palos Verdes Director of Public Works or
designee.
C-39
GP-20
R6876-0001\1800410v2.doc
D. C&D Recycling Center. A facility that receives only C&D material that has been
separated for reuse prior to receipt, in which the residual (disposed) amount of waste in
the material is less than 10% of the amount separated for reuse or recycling, by weight.
E. Disposal. Final deposition of C&D or inert debris into land, including stockpiling onto
land of construction and demolition debris that has not been sorted for further processing
or resale, if such stockpiling is for a period of time greater than 30 days; and construction
and demolition debris that has been sorted for further processing or resale, if such
stockpiling is for a period of time greater than one year, or stockpiling onto land of inert
debris that is for a period of time greater than one year.
F. Diversion or Divert. The reuse, recycling or composting of construction and demolition
debris to avoid disposal in a landfill.
G. Enforcement Agency (EA). Enforcement agency as defined in Public Resources Code
40130.
H. Inert Disposal Facility or Inert Waste Landfill. A disposal facility that accepts only inert
waste such as soil and rock, fully cured asphalt paving, uncontaminated concrete
(including fiberglass or steel reinforcing rods embedded in the concrete), brick, glass,
and ceramics, for land disposal.
I. Inert Solids or Inert Waste. Non-liquid solid wastes including, but not limited to, soil and
concrete that do not contain hazardous waste or soluble pollutants at concentrations in
excess of water quality objectives established by a regional Water Board pursuant to
Division 7 (Sections 13000, et seq) of the California Water Code and does not contain
significant quantities of decomposable solid resources.
J. Mixed C&D Debris. Loads that include commingled recyclable and non-recyclable C&D
debris generated at the construction site.
K. Mixed Debris Recycling Facility. A processing facility that accepts loads of solid waste
and/or recycling materials for the purpose of recovering reusable, recyclable, and
compostable materials and disposing the non-recyclable residual materials.
L. Recycling. The process of sorting, cleansing, treating and reconstituting materials for the
purpose of using the altered form in the manufacture of a new product. Recycling does
not include burning, incinerating or thermally destroying solid waste.
M. Reuse. The use of a material that might otherwise be discarded, in the same or similar
form as it was produced.
N. Separated for Reuse. Materials, including commingled recyclables, that have been
separated or kept separate from the solid waste stream for the purpose of additional
sorting or processing of those materials for reuse or recycling in order to return them to
the economic mainstream in the form of raw material for new, reused, or reconstituted
products which meet the quality standards necessary to be used in the marketplace, and
includes materials that have been “source separated.”
O. Solid Waste. Refer to Public Resources Code Section 40191.
C-40
GP-21
R6876-0001\1800410v2.doc
P. Source-Separated. Materials, including commingled recyclables, that have been
separated or kept separate from the solid waste stream at the point of generation, for the
purpose of additional sorting or processing of those materials for reuse or recycling in
order to return them to the economic mainstream in the form of raw materials for new,
reused, or reconstituted products which meet the quality standards necessary to be used
in the marketplace.
Q. Waste Hauler. A company that possesses a valid permit from the City of Rancho Palos
Verdes to collect and transport solid wastes from individuals or businesses for the
purpose of recycling or disposal.
7-15.1.3 SUBMITTALS (see Appendix for submittal forms and other information)
A. The C&D Waste Management Plan consists of two submittals: prior to commencement
of work (Project Information and Pre-Project Worksheet), and following completion of the
project (Post-Project Worksheet). The Contractor may be required to submit interim
progress reports during the project.
B. The C&D Debris Waste Management Plan requirements, resources and forms are
contained in the Appendix.
C. Project Information Form and Pre-Project Information Worksheet (Prior to
commencement of work).
1. Prior to commencing the Work, submit the completed Project Information (Form
A) and Pre-Project Worksheet (Form B). Submit on forms included in Appendix.
Forms A and B must include, but not be limited to, the following information:
(a) Contractor’s name and project information.
(b) Estimated quantities of materials to be generated, diverted and disposed.
Review Contract Documents and estimate the types and quantities of
materials under the Work that are anticipated to be feasible for on-site
processing, or source separation for reuse or recycling. Indicate the
procedures that will be implemented to effect jobsite source separation,
such as identifying a convenient location where dumpsters would be
located, putting signage to identify materials to be placed in dumpsters,
etc.
(c) Names of haulers and names and locations of re-use, recycling,
processing and disposal facilities/sites.
(d) Tonnage calculations that demonstrate that Contractor will divert a
minimum 50% by weight of the construction and demolition waste
materials generated in the Work, and 100% of the land clearing debris.
2. Forms A & B must be approved by the Contracting Officer prior to the Start of
Work.
C-41
GP-22
R6876-0001\1800410v2.doc
3. Contractor’s C&D Debris Waste Management Plan will not otherwise relieve the
Contractor of responsibility for adequate and continuing control of pollutants and
other environmental protection measures.
4. Requests for exemptions to the diversion requirements must be submitted to the
City prior to commencement of Work. Contractor must provide adequate
information to support the request for exemption and explanation of why the
diversion requirements cannot be achieved. Requests for exemptions will be
considered on a case-by-case basis by the City, and a determination will be
made to accept or reject the request for an exemption.
D. C&D Debris Post-Project Summary (After completion of project).
1. Submit the completed Post-Project Summary (Form C) on the form attached with
each application for progress payment. Failure to submit the form and its
supporting documentation will render the application for progress payment
incomplete and delay progress payments. If applicable, include manifests,
weight tickets, receipts, and invoices specifically identifying the processes and/or
facilities used for reuse and recycled materials, including but not limited to the
following:
(a) On-site crushing of asphalt and concrete for use on-site or off-site.
(b) Reuse of building materials or salvageable items.
(c) Source separated recycling facilities.
(d) Mixed debris recycling facilities.
(e) Recycling of C&D debris, including soils, as landfill alternative daily cover.
(f) Delivery of soils or mixed inerts to an inert landfill or other use.
(g) Disposal of soils or other materials at a landfill or transfer station.
(h) Other (describe).
2. The Post-Project Summary (Form C) must quantify all materials generated in the
Work, disposed in Class III Landfills, or diverted from disposal through recycling.
Indicate zero (0) if there is no quantity to report for a type of material. Include the
following information on the form:
(a) Indicate project name and address, name of the Contractor completing
the Summary Report and compiling backup documentation, the printed
name and signature of the person completing the form, and the date that
the Post-Project Summary is completed.
(b) Report disposal or recycling either in tons or in cubic yards. If scales are
available at disposal or recycling facility, report in tons; otherwise, report
in cubic yards. Report in units for salvage items when no tonnage or cubic
yard measurement is feasible.
C-42
GP-23
R6876-0001\1800410v2.doc
(c) Indicate locations to which materials are delivered for reuse, salvage,
recycling, accepted as daily cover, inert backfill, or disposal in landfills or
transfer stations.
(d) Provide legible copies of weigh tickets, receipts, or invoices that
specifically identify the project generating the material. The documents
must be from recyclers and/or disposal site operators that can legally
accept the materials for the purpose of reuse, recycling, or disposal.
PART 2 PRODUCTS
(Not used.)
PART 3 EXECUTION
7-15.3.1 SALVAGE, REUSE, RECYCLING AND PROCEDURES
A. Identify reuse, salvage, and recycling facilities. Contact your Project Manager for a list of
local organizations and companies.
B. Develop and implement procedures to reuse, salvage, and recycle new construction,
demolition, and excavation materials, based on the Contract Documents, the C&D
Debris Waste Management Plan, estimated quantities of available materials, and
availability of recycling facilities. Procedures may include on-site recycling, source
separated recycling, and/or mixed debris recycling efforts.
1. Identify materials that are feasible for salvage, determine requirements for site
storage, and transportation of materials to a salvage facility.
2. Explore the possibility of reusing project job-site inert materials, such as rock,
concrete, dirt and aggregate, on-site for road base or other similar uses.
3. Source separate new construction, excavation and demolition materials
including, but not limited to the following types:
(a) Asphalt.
(b) Concrete, concrete block, slump stone (decorative concrete block), and
rocks.
(c) Red Clay Brick.
(d) Soils.
(e) Other materials, as appropriate, such as wood and corrugated cardboard.
4. Develop and implement a program to transport loads of mixed (commingled)
construction and demolition materials that cannot be feasibly source separated to
a mixed materials recycling facility.
7-15.3.2 DISPOSAL OPERATIONS AND WASTE HAULING
C-43
GP-24
R6876-0001\1800410v2.doc
A. Legally transport and dispose of materials that cannot be delivered to a source
separated or mixed recycling facility to a transfer station or disposal facility that can
legally accept the materials for the purpose of disposal.
B. Use a permitted waste hauler or Contractor’s trucking services and personnel. To
confirm valid permitted status of waste haulers, contact the City of Rancho Palos Verdes
Public Works Department at (310) 544-5245.
C. Become familiar with the conditions for acceptance of new construction, excavation and
demolition materials at recycling facilities, prior to delivering materials.
D. Legally transport and deliver to facilities that can legally accept new construction,
excavation and demolition materials for purpose of re-use, recycling, or composting
E. Do not burn, bury or otherwise dispose of solid waste on the project job-site.
7-15.3.3 REUSE AND DONATION OPTIONS
A. Implement a reuse program to the greatest extent feasible. Options for reuse may
include, but are not limited to:
1. Los Angeles County Materials Exchange (LACoMax) LACoMAX is a free service
provided by the Los Angeles County Department of Public Works, Environmental
Programs Division, designed to help residents, businesses, and organizations in
Los Angeles County find markets for their industrial by-products, surplus
materials, and other would-be discards. All exchanges are coordinated between
the parties. The site can be accessed at www.ladpw.org/epd/lacomax.
2. California Materials Exchange (CalMAX) is a free service provided by the State
of California, Department of Resources Recycling and Recovery (CalRecycle)
that connects businesses, organizations, manufacturers, schools, and individuals
with online resources for exchanging materials. The site can be accessed at
www.calrecycle.ca.gov/CalMAX.
3. Habitat for Humanity ReStore resale outlets accept donated home improvement
goods like furniture, home accessories, building materials and appliances. The
materials are sold to the general public. The proceeds help local Habitat affiliates
fund the construction of Habitat homes within their communities. Locations of
ReStores can be found at: www.habitat.org/restores.
7-15.3.4 REVENUE
A. Revenues or other savings obtained from recycled, re-used, or salvaged materials shall
accrue to Contractor unless otherwise noted in the Contract Documents.
C-44
SP - 1
R6876-0001\1800412v2.doc
SPECIAL PROVISIONS
A. GENERAL PROJECT INFORMATION
1. REQUIREMENTS
All work embraced herein shall be accomplished in accordance with the applicable
portions of the “Standard Specifications for Public Works Construction,” the 2012 edition,
including all supplements, herein referred to as “Standard Specifications, except as
modified by these Special Provisions and the Project Plans.
The U.S. Standard Measures also called U.S. Customary System is the principal
measurement system in these specifications and shall be used for construction, unless
otherwise stated in the Contract Documents.
In addition to the above, the Contractor shall comply with the requirements of the
following:
(a) Notice Inviting Sealed Bids
(b) Instructions to Bidders
(c) Proposal
(d) Bid Bond
(e) Information Required of Bidders
(f) Contract Agreement
(g) Faithful Performance Bond
(h) Labor and Material Bond (Payment Bond)
(i) Statement Acknowledging Penal and Civil Penalties Concerning the
Contractor’s Licensing Laws.
2. DEFINITION OF TERMS
Wherever in the “Standard Specifications” terms are used, they shall be understood to
mean and refer to the following:
C-45
SP - 2
R6876-0001\1800412v2.doc
Agency City of Rancho Palos Verdes
Board City Council, City of Rancho Palos Verdes
Engineer The Director of Public Works, acting either
directly or through the properly authorized
agents, such agents acting within the scope of
the particular duties entrusted to them.
Special Provisions All Contract Documents, including the Special
and Technical Provisions.
3. PROJECT PLANS
The location of the work, its general nature, extent, form and detail of the various
features are listed as a part of these Specifications.
4. SCOPE OF WORK
In general, the work comprises without limitation, furnishing all necessary labor, materials,
equipment and other incidental and appurtenant Work necessary to construct the Storm
Drain Improvements which includes removing existing storm drain, installing new HDPE
and concrete storm drain facilities, catch basins, incidental removal and reconstruction of
asphalt concrete pavement, removing and reinstalling concrete curb and gutter, removing
and reconstructing miscellaneous concrete structures, temporary traffic control measures,
large tree removals, grading, and other appurtenant items not mentioned that are required
to complete the work between Scotmist Drive and Peacock Ridge Road including work
within the private residential property at 6037 Scotmist Drive as more clearly described in
the Contract Documents.
This work shall be performed in strict conformance with the Contract Documents, permits
from regulatory agencies with jurisdiction, and applicable regulations. The quantity of
work to be performed and materials to be furnished are approximate only, being given as
a basis for the comparison of Bids. Actual quantities of work to be performed may vary at
the discretion of the Director of Public Works.
The work to be done shall include furnishing all materials, equipment, tools, labor, and
incidentals as required by the Specifications, and Contract Documents, in the City of
Rancho Palos Verdes, California.
5. NOTICE TO PROCEED
Upon award of this contract and signing the contract documents, the City shall issue the
Contractor a Notice to Proceed. Contract period shall commence on the date in the
Notice to Proceed. Working days are defined as Monday through Friday, with the
exception that no work may take place on the following City holidays:
• Memorial Day
• Independence Day & day before Independence Day
• Labor Day
• Election Day
C-46
SP - 3
R6876-0001\1800412v2.doc
• Thanksgiving Day
• Day after Thanksgiving Day
• December 25 to January 2
In addition, no work will be allowed on any special election day which may be declared.
Should a special day be declared, a time extension of one working day will be granted
for each day.
The City will not authorize any work to be done under these Specifications before the
contract agreement has been fully executed; and any work that is done by the contractor
in advance of such time shall be considered as being done at Contractor’s own risk and
responsibility, and as a consequence will be subject to rejection by not having been
done in the presence of the Director of Public Works or Inspector as provided in Section
2-10 of the Standard Specifications.
In the event that the Director of Public Works shall be of the opinion that the work is
being inadequately or improperly executed in any respect, he/she may demand that the
Contractor improve or change the execution of the work in such manner as to assure
proper and timely completion.
6. UTILITIES
It is anticipated that these existing utilities will not interfere with the Contractor ’s
construction operations. However, the Contractor shall exercise due care to ensure that
these utility facilities are not damaged during his operations. The Contractor shall notify
the following utility companies prior to the beginning of any work:
AGENCY TELEPHONE NUMBER
City of Rancho Palos Verdes (310) 544-5252
Southern California Edison Company (310) 783-1156
Southern California Gas Company (310) 687-2020
Verizon (310) 793-4159
California Water Service Company (310) 541-2438
Cox Communications
EDCO (solid waste)
(310) 551-5020 x30
(310) 540-2977
LA County Department of Public Works (sewer) (626) 458-4357
Sanitation District of Los Angeles County (562) 699-7411 x1205
USPS (310) 541-0624
7. STREET CLOSURES
No closure of any street shall be allowed unless prior written permission is obtained from
the Director of Public Works or his authorized representative. If permission to close a
street is granted, then the Contractor is required to notify the Engineer in writing at least
five (5) working days in advance of street closures, and all emergency services, public
transportation services, garbage collections services, and school bus services, and other
agencies as determined by Department of Public Works shall be notified by the
contractor in writing of the locations, time and date of the closures a minimum four (4)
C-47
SP - 4
R6876-0001\1800412v2.doc
working days in advance of street closures. In case of schedule changes, the
emergency services, etc., shall be notified by telephone at least two (2) days in advance
of the street closure.
For construction in the vicinity of a school, the Contractor shall contact the Palos Verdes
Unified School District, obtain a school schedule, and school circulation plan and
incorporate information into the project’s schedule and traffic control, such that within
1,000 feet of the school on routes serving the school for student arrivals and departures
are not impacted between one hour before and one half hour after the school day start
time and one hour before or one half hour after school day end time.
AGENCY TELEPHONE NUMBER
Peninsula Fire Department #106 (310) 377-9523
LAC Sheriff’s Department (310) 539-1661
Western Waste Industries (310) 830-7100
MTA (bus) (213) 626-4455
LAC Fire Department (310) 830-3361
Los Angeles School District (818) 997-2455
PV Transit (310) 544-7108
Peninsula Dial-A-Ride (310) 544-7108
Waste Management (800) 669-6580
Postmaster (310) 377-6833
BFI (310) 329-4115
Palos Verdes Unified School District (310) 378-9966
Ivy Rubbish Disposal (310) 530-2899
8. CONFERENCE
The Contractor shall attend a pre-construction meeting with the Director of Public Works
or his authorized representative, which shall be held a minimum of five (5) working
days prior to commencement of any work.
The Contractor shall submit his 24-hour emergency telephone numbers to the Director of
Public Works or his authorized representative for approval a minimum of two (2)
working days prior to the pre-construction conference.
9. PUBLIC CONVENIENCE AND SAFETY
(a) General: Attention is directed to Section 7-10 of the Standard Specifications and
the Manual of Warning Signs, Lights and Devices for Use in Performing Work Upon
Highways, published by the California Department of Transportation. Public convenience
and traffic control shall conform to Section 7-10 of the Standard Specifications for Public
Works Construction, the California MUTCD and the MUTCD California Supplement,
latest edition, except as modified by these Special Provisions. Contractor to prepare
traffic control plans, as needed at various times, in compliance with the standard
specifications stated herein and with the City of Rancho Palos Verdes approvals and
directions.
(b) Warning and Protection Devices: The Contractor will be responsible for
providing, placing and maintaining approved signs, barricades, pedestals, flashers,
C-48
SP - 5
R6876-0001\1800412v2.doc
delineators, fences, barriers, non-skid steel trench plates, temporary asphalt concrete
and flagmen where needed, and other necessary facilities in the vicinity of the
construction area and where any dangerous conditions may be encountered as a result
thereof, for the protection of the motoring public per the traffic control plans. The
Contractor will not be allowed to proceed with the work until such time that a sufficient
number of these protection devices have been delivered to the project site. Where
parked vehicles are likely to interfere with the proposed work, the Contractor will supply
and post at no less than 200 feet intervals on each side of the street “Temporary No
Parking” signs 72 hours before the start of construction and to report the time of posting
to the Sheriff’s Station for the purpose of establishing “Tow Away” provisions. The
Contractor shall be responsible for the removal of the temporary signs upon the
completion of the work. Should the Contractor appear neglectful in furnishing warning
and protection devices as outlined above, the Director of Public Works may direct
attention to the existence of a hazard and the necessity of additional or different
measures, which shall be furnished and installed by the Contractor at Contractor’s own
expense, free of any cost to the City. Should the Contractor refuse or fail to act in a
timely manner to correct a hazardous condition, the Director of Public Works may direct
City forces to provide the necessary protective and warning devices as deemed
appropriate by the Director of Public Works or his authorized representative.
The cost accrued by the City in connection therewith will be deducted from the
Contractor’s contract payment. Any action or inaction on the part of the City in directing
attention to the inadequacy of warning and protective measures or in providing additional
protective and warning devices shall not relieve the Contractor from responsibility for
public safety or abrogate Contractor’s obligation to furnish and pay for these devices.
Should the Contractor fail to pick up signs either after the work has been performed, or
after the Contractor has failed to meet the schedule, the Contractor shall be charged a
penalty of $50 per sign left in the public right of way. Said monies will be deducted from
any monies due or to become due to the Contractor.
The Contractor shall be responsible for adequate barricading of the work area and
controlling of traffic in the vicinity of the projects as specified in Subsection 7-10, Public
Convenience and Safety, or as directed by the Director of Public Works or his authorized
representative. When necessary to provide vehicular or pedestrian crossings over the
fresh pavement, the Director of Public Works or his authorized representative may direct
the Contractor to spread sufficient sand or rock dust on the affected area to eliminate
tracking. Sand or rock dust used for this purpose shall be at the Contractor’s expense.
All necessary traffic control devices shall be in place prior to the start of work. The
Contractor shall field check all temporary traffic control signs, barricades and other
devices to ensure their continuous proper maintenance and conformance to the plans
and specifications (including weekends and holidays).
The Contractor shall so conduct his operations as to offer the least possible obstruction
and inconvenience to public traffic. Every effort shall be made to provide a clear and
unobstructed view of all traffic control signs, signals, or markers. Existing signs shall be
covered when directed by the Engineer. When construction signs are not in effect, they
shall be removed, covered, or relocated out of the driver’s view. Construction signing
shall be in place prior to the beginning of any workday. All signs shall be legible, clean
and free of graffiti.
C-49
SP - 6
R6876-0001\1800412v2.doc
The order of work and phasing requirements, except where otherwise specifically
required by the plans and specifications, shall be determined by the Contractor who shall
be solely responsible for coordinating all subcontract and prime contract work to
minimize delays during construction.
The Contractor shall maintain access for emergency vehicles at all times on all streets.
All traffic control layouts and work sequence instructions shall be developed to account
for continuous emergency vehicles access and driveway access.
There shall be a minimum of 5’ clearance from open excavations and 2’ from other
obstructions (curbs, k-rail, etc) for the motoring public. All lanes shall be open to traffic
during non-working / “non-lane restriction” hours.
No street restrictions shall be allowed without advanced written approval from the
Engineer. Certified flaggers with hand-held communication devices, proper safety vests
and signage shall be required at all times wherever the useable roadway is restricted, to
ensure for the safe passage of motorists at all times. Certified flaggers are required
where travel lanes in each direction cannot be maintained.
The Contractor shall be required to provide and maintain all necessary flaggers,
barricades, delineators, signs, flashers, and any other safety equipment as set forth in
the latest publication of the California MUTCD, or as required by the Engineer to insure
safe passage of traffic. Impacts to the right of way that remain overnight shall
incorporate appropriate flashers for barricades and reflective delineators.
Unless otherwise specifically provided in writing, the Contractor will not be allowed to
begin an excavation that cannot be successfully backfilled, temporarily repaved or plated
with non-skid steel plates, in the same working day. Non-skid steel plates must be
capable of carrying H-20 wheel loading. Plates shall have a minimum width equal to the
excavation width plus 24 inches and be securely fastened to the street surface. Asphalt
fillers, a minimum of 6 inches wide shall be placed around the perimeter of the plate.
When traffic is transferred to any type of temporary pavement surface good drivability of
the surfaces shall be maintained and shall be subject to approval by the Engineer prior
to allowing traffic to be transferred upon it.
In the unavoidable event that an open trench must be covered with steel plates over-
night then flasher equipped barricades and other barriers, shall be placed at the ends
and along the sides of these steel plate covered excavations from sunset to sunrise of
the next day, to warn all pedestrians and vehicular traffic of such excavations. Pipe
trenches and other hazardous excavations shall be filled in, securely enclosed, or
covered at the end of each working day, to the satisfaction of the Engineer. Flasher
equipped barricades and other barriers left in operation beyond the normal work hours
as prescribed, shall be solar/battery powered only.
The Contractor shall provide written notification to all public services including, but not
limited to, the LA County Sherriff / Dispatch, LA County Fire Department, Public Works
Department (City Engineer), UWS (trash pickup), California Water Service Company,
Los Angeles County Sanitation District, and USPS.
The Contractor shall provide written notification to all residents near the construction a
minimum of 10 working days prior to any work. A separate notification shall be provided
C-50
SP - 7
R6876-0001\1800412v2.doc
to residents at least 2 working days prior to blocking any access to a residence,
driveway, or work that will require the disruption of entry to private property or any utility
service (water, sewer, electrical, etc.). The notice will be provided by the City,
distributed by the Contractor, and will include a preliminary schedule, name of the job
superintendent/foreman and a telephone number where he/she can be reached 24
hours a day in case of emergency. Even if the required utility work is to be done by the
utility owner or a sub-contractor it is the Contractor’s responsibility to ensure that the
proper notification procedures are followed.
Failure or refusal by the Contractor to comply with the requirements of this section shall
be sufficient cause for the City to order the work done by City forces and all costs thereof
to be borne by the Contractor.
Continuous driveway access shall be required at all times, excepted when specific
written permission is provided to do otherwise. The City will enforce the work hours and
continuous driveway access requirements of this section. In order to ensure
compliance, an assessment of $250 for every 15 minutes of non-compliance or portion
thereof will be deducted from the Contractor’s payment for non-compliance. No
assessment will be made for emergency work, i.e. broken water line repair, gas leak
repair or similar emergency work as directed by the Engineer. This assessment shall be
deducted from the amount due the Contractor on this project.
If the Contractor is found to be negligent in furnishing warning and protective measures
as detailed above, the City may direct the Contractor’s attention to the hazard and it
shall be the Contractor’s responsibility to furnish and install the necessary warning and
protective measures at his/her expense. Should the City point out the inadequacy of
warning and protective measures, such action on the part of the City shall not relieve the
Contractor from responsibility for public safety or abrogate its obligation to furnish and
pay for these devices.
The Contractor shall use and maintain caution tape between barriers for all open
excavations.
The Contractor is notified that there are a significant number of bicycle riders,
pedestrians and joggers in the City. The Contractor shall develop and operate his traffic
control activities with this in mind. He shall conduct his operations in a safe manner for
cyclists and pedestrians as well as vehicles.
PAYMENT: Payment for Traffic Control implementation shall be made at the unit bid
price per lump sum. Payment for traffic control including equipment, materials, and labor
shall be included in the bid lump sum price.
10. SANITARY CONVENIENCE
Necessary sanitary facilities for the use of workmen on the job shall be provided and
maintained in an approved manner by the Contractor, properly secluded from public
observation and in compliance with health ordinances and laws, and their use shall be
strictly enforced by the Contractor. Any workman who fails to use the sanitary facilities
as intended shall be removed from the project site permanently at the sole discretion of
the Engineer.
C-51
SP - 8
R6876-0001\1800412v2.doc
11. CONSTRUCTION YARD
It shall be the Contractor's responsibility to locate any storage sites for materials and
equipment needed and such sites either located on public or private property must be
approved in advance by the Director of Public Works or his authorized representative. If
permission is given to use a City site, the Contractor shall repair any damage as a result
of his operations and any repairs will restore the site to new and not pre -existing
conditions.
When storage sites are to be located upon private property, the Contractor shall submit
to the Director of Public Works or his authorized representative, written approval from
the record owner authorizing the use of the property by the Contractor. The Contractor
shall contact the appropriate City Community Development Department to determine if
the using the site as a stockpile area is allowed. After the project is complete, the
Contractor shall supply a written release signed by the owner of record that said property
has been satisfactorily restored in order to provide assurance to the City that no later
property owner claims will be filed by residents whose property has allegedly damaged
by the Contractor and not repaired to their satisfaction.
The City will provide the Contractor with a sample release form upon request.
12. EQUIPMENT REQUIREMENTS
Contractor shall furnish all equipment required to safely complete the work and avoid, if
possible, conducting any on-site maintenance or repair of said equipment. Necessary
minor maintenance may be conducted on site; however, all maintenance and/or repairs
shall be completed Monday through Friday between the hours of 7:30 a.m. and 5:30
p.m. Fueling and minor maintenance shall be in compliance with the NPDES
requirements.
All equipment shall be in good repair. Equipment from which leaks of oil, hydraulic
fluids, coolant, etc., are observed shall be removed from service until the necessary
repairs have been completed.
13. PRESERVATION OF PROPERTY
Existing improvements in areas adjoining the locations whereon construction activities
are being performed shall be protected from injury or damage resulting from the
operations of the Contractor. In like manner any building, structure, tree, shrub, or other
item in the vicinity of the Contractor’s operation, shall be similarly protected and
preserved. Vegetation cleared during site preparation shall become the property of the
Contractor and shall be removed from the area unless otherwise directed by the Director
of Public Works or his authorized representative.
14. NPDES COMPLIANCE/WATER POLLUTION CONTROL
Contractor shall prepare a Storm Water Pollutants Protection Plan (SWPPP) in
compliance with the State of California Water Resources Control Board Construction
General Permit, Order No. 2012-0006-DWQ NPDES No. CAS000002. The SWPPP shall
be kept on site at all times and adhered to.
C-52
SP - 9
R6876-0001\1800412v2.doc
Water pollution control shall consist of constructing those facilities specified by these
Contract Documents, required by law, or as ordered by the Director of Public Works or
his authorized representative. Said work is intended to provided prevention, control and
abatement of water pollution to streams, oceans and other bodies of water. Full
compensation for conforming to the requirements in this entire section shall be
considered as included in the prices paid for the various contract items of work, and no
additional compensation will be allowed therefor.
Housekeeping/Cleanup: The Contractor shall prevent pollution of storm water from
cleanup and disposal operations by using best management practices and good
housekeeping methods. When fluids or dry materials spill, cleanup should be
immediate, thorough, and routine. The Contractor shall never attempt to “wash them
away” with water, or bury them. The Contractor shall report significant spills to the
appropriate spill response agencies immediately. The Contractor shall recognize that
different types of materials have different disposal requirements and follow appropriate
practices. The Contractor shall confine non-hazardous debris to dumpsters, covered at
night or during wet weather, and taken to a landfill for recycling or disposal. The
Contractor shall handle hazardous debris in accordance with specific laws and
regulations and dispose of as a hazardous waste. A separate permit is required.
Common hazardous debris found on construction sites are: (liquid residues from paints,
thinners, solvents, glues, and cleaning fluids. Leaching agents form lumber such as
formaldehyde, arsenic, copper, creosote and chromium, motor oil, gear oil, antifreeze
fluids, brake fluids, etc., unused pesticides.)
Sanitary Waste Management: The Contractor shall prevent the discharge of sanitary
waste to storm water by providing convenient, properly located, well maintained facilities.
The Contractor shall hire a licensed portable sanitary facility leasing company which will
clean the facilities regularly and keep them in good working order. The Contractor shall
make sure that portable sanitary facilities are located on relatively level ground away
from traffic areas, drainage courses, and storm drain courses, and storm drain inlets.
The Contractor shall regularly inspect the facilities for any leaks, and have defective
units replaced.
Vehicle and Equipment Management: The Contractor shall use and maintain
construction vehicles and equipment in a manner that prevents leaks and spills of fluids,
contains wash waters, and controls off-site tracking. The Contractor shall not allow
leaking vehicles and equipment on-site and shall inspect equipment and vehicles
frequently for leaks and repair them immediately. The Contractor shall clean up spills
and leaks promptly with absorbent materials, and shall not flush with water.
The Contractor shall fuel, maintain, and repair vehicles and equipment off-site whenever
possible, and on-site only in designated areas. The Contractor shall prevent run-on and
run-off from designated areas, provide containment devices and cover if necessary.
The Contractor shall wash vehicles and equipment on-site in designated, contained
areas, allowing wash waters to infiltrate into the ground. The Contractor shall use
phosphate-free, biodegradable soaps, steam clean in confined areas only.
When not in use, the Contractor shall store equipment and vehicles in designated areas
and place drip pans and absorbent material under stored equipment that is prone to
leaking and dripping (e.g. paving equipment).
C-53
SP - 10
R6876-0001\1800412v2.doc
If the Contractor must drain and replace motor oil, radiator coolant, or other fluids on -
site, use drip pans or drop cloths to catch drips and spills. The Contractor shall collect
all spent fluids, store in separate containers, and recycle whenever possible. Note: For
recycling purposes, such liquids must not be mixed with other fluids. Non-recycled fluids
generally must be disposed of as hazardous waste.
Surface and Subsurface Water Control: The Contractor shall prevent or reduce the
discharge of pollutants to storm water from surface and subsurface water control
operations by using all appropriate methods:
For surface water control operations where the flow is routed to bypass the construction
area, establish stable (erosion resistant) conveyance routes for the diverted flow. Trap
any significant sediment (e.g., mud) generated by the rerouted flow in a sediment trap,
filtering berm, or basin.
In subsurface pumping or other subsurface water control operations where significant
amounts of sediment (e.g., mud) are present in the removed water, capture the sediment
in a sediment trap, filtering berm, or basin.
If a sediment trap or basin is required for the surface or subsurface water control
operations, the facility should be designed such that the sediment is settled or trapped in
the facility prior to discharging of the water.
In areas suspected of groundwater pollution, sample the groundwater near the
excavation/pumping site and have the water tested for known or suspected pollutants at
a certified laboratory.
Any proposed discharge of groundwater may be subject to requirements of the Regional
Water Quality Control Board if water is discharged to groundwater or land.
Concrete and Mortar Products: The Contractor shall prevent or reduce the discharge of
pollutants to storm water from concrete waste by conducting washout at appropriate off-
site locations, performing on-site washout in a designated area, and training employees
and subcontractors.
The Contractor shall store and mix dry and wet materials either off -site or under cover,
away from drainage areas.
For washout of concrete trucks, the Contractor shall provide appropriate off-site
locations or designated contained areas, at least 50 feet away from storm drains, open
ditches, streets, or streams.
The Contractor shall prevent run-off from designated washout areas by constructing a
temporary pit or bermed area large enough for liquid and solid waste. When concrete is
set, breakup and dispose of it in construction fills per direction of soils engineer or as
solid waste or recycle.
The Contractor shall inform concrete suppliers of the designated washout locations and
disposal sites for concrete and mortar products.
Asphalt and Bituminous Products: The Contractor shall prevent or reduce the discharge
C-54
SP - 11
R6876-0001\1800412v2.doc
of pollutants from asphalt and bituminous operations, by preventing run-on and run-off
during the operation, properly disposing of waste, and training employees and
subcontractors. The Contractor shall:
Avoid prime or tack coating during wet weather. Store materials away from drainage
courses to prevent material from entering the run-off. Cover catch basins and manholes
when applying seal coat, tack coat, slurry seal, fog seal, etc. Make sure sand or gravel
placed over new asphalt does not wash into storm drains, streets, or creeks. Dispose of
old asphalt properly. Collect and remove all broken asphalt from the site and recycle
whenever possible. Do not dispose of asphalt products into waterways. Follow the
storm water permitting requirements for industrial activities if paving involves an on-site
mixing plant.
Construction Water: The Contractor shall reduce or eliminate excessive construction
water that may cause erosion and carry pollutants from the site. The Contractor shall:
Store construction water in leak-proof tanks, located away from the drainage system.
Use construction water conservatively. Whenever possible, dispose of excess water on-
site, by allowing it to soak into the ground.
PAYMENT: STORMWATER BEST MANAGEMENT PRACTICES shall be paid per lump
sum price and includes all material, labor, equipment, and BMP required to implement
the STORMWATER BEST MANAGEMENT PRACTICES.
15. SAFETY, SANITARY AND MEDICAL REQUIREMENTS
The Contractor, his employees, his subcontractors and their employees shall promptly
and fully carry out such safety, sanitary and medical requirements as may from time to
time be prescribed by the Industrial Safety Commission and by County or State Health
Departments to the end that proper work shall be done and the safety and health of the
employees and of the community may be conserved and safeguarded. In case any such
regulations and orders are not observed by the Contractor, they may be enforced by the
Director of Public Works or his authorized representative at the Contractor’s expense.
16. ELECTRICAL POWER
The Contractor shall provide, at his own expense, all necessary electrical power required
for his operations under the contract.
17. PROTECTION OF UNDERGROUND FACILITIES
Attention is directed to the possible existence of underground facilities not known to the
City or owner or in a location different from that which maybe indicated on the plans or in
these Special Provisions. The Contractor shall take steps to ascertain the exact location
of all underground facilities prior to doing work that may damage such facilities or
interfere with their service. If the Contractor discovers underground facilities not
indicated on the Plans or in these Special Provisions, Contractor shall immediately give
the Director of Public Works or his authorized representative written notification of the
existence of such facilities. Such previously unknown facilities shall be protected from
damage as directed by the Director of Public Works or his authorized representative and
the Contractor will be paid for such work as extra work as provided in Section 3-3 of the
C-55
SP - 12
R6876-0001\1800412v2.doc
Standard Specifications.
18. AIR POLLUTION CONTROL
Section 7-8.2, “Air Pollution,” of the Standard Specifications is supplemented by the
following:
Safety & Ventilation – Construction Activities shall be conducted in compliance with
OSHA requirements for confined space. The Contractor is responsible for providing a
method statement and implementing necessary practices to comply with OSHA Safety
and Ventilation standards.
The Contractor shall comply with all air pollution control rules, regulations, ordinances
and statutes which apply to any work performed pursuant to the contract, including any
air pollution control rules, regulations, ordinances and statutes specified in Section
11017 of the Government Code.
In the absence of any applicable air pollution control rules, regulations, ordinances or
statutes governing solvents, all solvents including, but not limited to the solvent portions
of paints, thinners, curing compounds, and liquid asphalt used on the project shall
comply with the applicable material requirements of the County Air Pollution Control
District.
19. PROJECT APPEARANCE
The Contractor shall maintain a neat appearance to the work. The project streets and
any street adversely affected by the Contractor’s activities shall be kept clean at all
times.
A motorized vacuum sweeper is required pursuant to the second paragraph of
Subsection 7-8.1 of the Standard Specifications.
In any area visible to the public, the following shall apply: When practicable, broken
concrete and debris developed shall be disposed of concurrently with its removal. If
stockpiling is required, the material shall be placed in an area which does not impact
public or private landscaping or irrigation and the material shall be removed or disposed
of daily.
Should the Contractor appear to be neglectful or negligent in maintaining a clean project
site, the Director of Public Works or his authorized representative may direct the
Contractor’s attention to the existence of such condition(s). The Contractor shall provide
all necessary measures immediately, at his expense. If attention is directed to the
existence of such condition(s), and the Contractor fails to provide an appropriate
remedy, any expense incurred by the City for providing correcting actions may be
deducted from the pay estimates and the total contract price for the work, including a
Fifty Dollar ($50.00) penalty per calendar day the condition(s) exist from date of
notification.
Full compensation for conforming to the provisions in this section not otherwise provided
for shall be considered as included in prices paid for the various contract items of work
involved, and no additional compensation will be allowed therefore.
C-56
SP - 13
R6876-0001\1800412v2.doc
20. WORK HOURS
The construction shall be conducted between the hours of 8:00 AM and 5:00 PM
Monday through Friday on non-school days and 9:00 AM and 4:00 PM on school days
excluding those listed in the Public Convenience and Safety-Traffic Control section, and
City holidays listed elsewhere in these specifications.
Deviation from normal working hours will not be allowed without prior written consent of
the Director of Public Works or his authorized representative.
In the event work is allowed by the Director of Public Works or his authorized
representative outside of the normal working hours, at the request of and for the benefit
of the Contractor, inspection service fees shall be levied against the Contractor at a rate
of $150.00 per hour, plus travel time where applicable. The above charge would be
levied for inspection services as necessary as a matter of public safety and to ensure the
quality of the work.
If Contractor anticipates that night work will be needed, it must be so stated in the
proposal and that it is understood that it will only be allowed by the written consent of the
Director of Public Works.
If work is permitted after sunset, the Contractor shall provide, at its expense, adequate
light for proper prosecution of the work for the safety of the workmen and the public, and
for proper inspection.
21. SCHEDULE AND PUBLIC NOTICES
Within five (5) calendar days of notification of award of the Contract, the Contractor shall
prepare and submit an overall work schedule, meeting the following criteria, to the
Director of Public Works or his designated representative: The Notice to Proceed will
not be issued until the schedule has been submitted in a substantially complete
form. Any delays, including postponement of preconstruction conference prior to start of
construction resulting from incomplete schedule submittal shall be cause for assignment
of liquidated damages of $1,000 per day. The preconstruction conference shall not be
considered viable without a work schedule.
Such schedules and maps shall include the exact address of each location where work
is to be performed and shall be subject to the review and approval of the Director of
Public Works or his authorized representative. Said schedule must show the dates of
the expected start and completion of all the various bid items, including but not limited to
street patching, ramp and curb construction, paving construction, and crack sealing.
The schedule shall be in the form of a Gantt/Bar Chart and a Critical Path Method
schedule, and both shall be in sufficient detail to show the chronological relationship of
all activities of the project including, but not limited to, estimated starting and completion
dates of various activities, scheduling of equipment and procurement of materials. No
work shall take place until the Director of Public Works or his authorized representative
and the Contractor have agreed to the schedule to be followed by the Contractor.
Upon commencement of work, that work shall be completed as soon as practical in each
project area. Locations with open construction or incomplete work shall not remain
inactive. The Contractor shall limit the extent of his operations as needed to ensure that
C-57
SP - 14
R6876-0001\1800412v2.doc
work areas are completed in each location in a diligent and expeditious manner. If a
location is left inactive, the City may assess a penalty of $500 per day for each specific
location of work for each day of inactivity. Concrete shall be placed within 3 days of
existing material removals, except that concrete for cross gutters, local depressions, and
spandrels shall be placed within 1 day of removal. Excavations within the street section
shall not be left open over weekends or holidays. Locations of AC repairs shall be placed
on the same day as removal of existing asphalt. AC for slot patches shall be placed
within 3 days of PCC placement.
During the conference between the Contractor and the Director of Public Works or his
authorized representative, the work schedule will be discussed and modified, if
necessary, by mutual agreement. Should it become necessary for the City to
temporarily delay the work schedule agreed upon during the scheduling conference,
every effort will be made to permit a new work schedule at the time most convenient to
the Contractor, thus permitting the project to proceed with the shortest intramural
movement of the equipment within the project.
Except as otherwise specified, Contractor shall submit requests for changes in the
schedule in writing to the Director of Public Works or his authorized representative for
approval at least 2 working days prior to the scheduled work on the affected streets. For
each calendar day a revised schedule is delinquent, Fifty Dollars ($50.00) may be
deducted from the pay estimates and the total contract price for the work.
The City of Rancho Palos Verdes strictly adheres to a policy whereby property owners
are kept fully informed as to potential inconveniences caused by construction activities
within the City. Every effort is made to minimize these inconveniences. Toward this
goal, the Contractor will be required to thoroughly schedule his work and to share that
schedule with the property owners affected by the project. This shall be accomplished
using door hangers and on-street posting placed 72 hours prior to the planned activity
which may cause an inconvenience at that particular location. The date of beginning of
closure shall be shown on the notice. In order to avoid unnecessary problems through
the construction period, it is mandatory that all schedules are prepared to fully-address
all of the known controls which must be scheduled around. The following list of controls
shall be incorporated into the schedules prepared by the Contractor:
Access to each drive shall be available unless the property owner has been
properly notified.
Parking restrictions will be allowed only when interfering work is underway on
any street.
Trash pickup is scheduled once each week for the streets within the project. The
Contractor may not perform any work on any street’s scheduled trash pickup day.
The Contractor shall provide access for trash pickup on streets not scheduled for
paving in the area. A list of streets with scheduled trash pickup days is included
in the Appendix.
C-58
SP - 15
R6876-0001\1800412v2.doc
Rescheduling shall be avoided if at all possible. Any rescheduling will require the
approval of the Public Works Department.
Street sweeping is scheduled once a month.
Door hangers and street posting shall be completed for any roadway where
construction activities impact parking or access.
Construction activities for which notification has been made, and have not been
completed within 72 hours of posting, will require a second posting and shall not
commence until 48 hours after the door hangers have been distributed.
Contractor may change the date of no parking on the posted no-parking signs,
but only after a new door hanger is delivered to all properties affected by the
signs and only if the date of construction is still within the original 72 hours from
date of the original posting. The new door hanger shall notify the occupant of the
change of date of work and state the date on the door hanger notice.
Order of Work: Order of work shall conform to the provisions of Section 6-1,
“Construction Schedule and Commencement of Work,” of the Standard
Specifications and these Special Provisions. The Contractor shall conduct his
operations so as to cause minimum obstruction and inconvenience to traffic,
schools, hikers and residences.
The following items shall be shown in the active schedule list:
Trash pickup
Street sweeping
Street posting (No Parking) (48 to 72 hours prior to any construction activities
in the street)
• Palos Verdes Drive South
• Peppertree Drive
PAYMENT: The cost for furnishing all schedules, notifications, posting, reposting
and any related items for their completion shall be considered as included in the
bid price paid for the various contract items of work, and no additional
compensation will be made therefor.
22. PHOTOGRAPHIC SURVEY OF ALL EXISTING CONDITIONS
The Contractor is encouraged to undertake an extensive photographic survey of all
existing improvements that could possibly be affected by the construction activities. This
survey will include, but is not limited to landscaping, streets, plants, and visible utilities.
In the event of a claim, the onus will be on the Contractor to be able to clearly
demonstrate that the photographic survey shows that it is a pre-existing condition of the
improvement(s). Should the Contractor not be able to disprove a claim from the public,
the Contractor will be responsible to reinstate the improvement into an acceptable
condition.
C-59
SP - 16
R6876-0001\1800412v2.doc
23. MOBILIZATION
Mobilization shall consist of preparatory work and operations including, but not limited to,
those necessary for the movement of personnel, equipment, materials, construction
trailer, portable toilets and incidentals to the project site necessary for work on the
project and for all other work and operations which must be performed or costs incurred
including bonds, insurance, City business license and financing prior to beginning work
on the various contract items on the project site.
The Contractor shall provide a detailed project schedule, both electronically and in hard
copy form (see previous item on Scheduling and Notices). Schedule updates shall be
provided monthly with each progress payment, and in accordance with these
specification requirements and as directed by the Engineer. The Contractor’s project
manager, superintendent and foreman are required to attend the pre-construction
meeting and weekly progress meetings.
The Contractor shall have on the work site at all times, as its agent, a competent English
speaking superintendent capable of reading and thoroughly understanding the plans,
specifications, other related documents, and directions from City’s Construction
Representative.
The Contractor is responsible for securing an adequate storage site for equipment and
materials (see separate items that detail these requirements elsewhere in these General
Provisions).
The cost of providing bonds, insurance, financing, moving equipment to the job site and
preparing an approved work schedule shall be per bid item Mobilization and will be at
the contract unit price per lump sum for the various items of work, and no additional
compensation will be allowed therefor.
PAYMENT: Payment for mobilization shall be made at the unit bid price per lump sum.
Payment for mobilization including equipment, materials, and labor shall be included in
the bid lump sum price.
The City of Rancho Palos Verdes shall waive its permit fee. The Contractor shall comply
with the requirements specified of each license.
Mobilization shall also include the cost, time and labor to move the necessary
construction equipment to and from the job site, supervisory time on the job by the
Contractor’s personnel to keep the construction site in a safe condition, the costs to set
up/maintain/vacate the staging area, the costs to set up/maintain/vacate the field office
and toilet facilities and all other related work as required for all non-working days during
the course of construction.
Mobilization shall also include all related “De-mobilization” costs, including the removal
of any remaining USA utility markings or other construction paint markings.
24. PROJECT MONUMENT SURVEYS AND CONSTRUCTION STAKING
24.1 Permanent Survey Markers
C-60
SP - 17
R6876-0001\1800412v2.doc
The Contractor shall not disturb permanent survey monuments or benchmarks without
the consent of the Engineer. Where the Engineer concurs, in writing, with the Contractor
that protecting an existing monument in place is impractical, the City will employ a
licensed land surveyor to establish the location of the monument before it is disturbed.
The City will have the monument replaced by a licensed land surveyor no later than
thirty (30) days after construction at the site of the replacement is completed. The
Licensed Land Surveyor will file corner record(s) as required by '' 8772 and 8773, et seq.
of the California Business and Professions Code. Copies will be provided to the City
within 10 days of replacement of any monuments.
When a change is made in the finished elevation of the pavement of any roadway in
which a permanent survey monument is located, the Contractor shall adjust the
monument frame and cover to the new grade. Documentation of any disturbance or
relocation, horizontal or vertical shall be provided to the City.
PAYMENT: Payment for adjustment of monument frame and cover to new grade shall
include documentation of any disturbance or relocation, horizontal or vertical and
providing such documentations to the City. Payment for this work shall be considered as
included in the prices paid for the various contract items of work, and no additional
compensation will be allowed therefor.
24.2 Center Line Ties
Center line ties and/or monuments will be inventoried, tied out and prepared by third
party survey crew assigned by the City of Rancho Palos Verdes. The Contractor is not
responsible to locate centerline ties and/or monuments at locations which are part of the
project as directed by the Director of Public Works or his authorized representative.
Contractor shall notify city staff if any monument or ties within the construction zone
appear to have been overlooked. The monuments will be inventoried, tied out, and a
centerline tie sheet will be prepared and submitted to the Engineer by the third party
survey crew.
Contractor shall continue to provide construction staking as needed.
24.3 Payment for Construction Staking
Payment for work performed to control the construction activities shall be included in the
actual bid items requiring the survey work, and no additional payment will be made.
Extension of unit prices for extra work shall include full compensation for attendant
survey work, and no additional payment will be made therefor.
24.4 Lines and Grades
Except when, as per orders from the Director of Public Works or his authorized
representative, minor changes in the work are to be made by the Contractor, all work
shall, during its progress upon completion, conform to the lines, grades, and elevations
shown on the Plans. All distances and measurements are given thereon and will be
made in a horizontal plane. Three (3) consecutive points shown on the same rate of
slope must be used in common in order to detect any variation from a straight line, and
in case any such discrepancy exists, it must be reported to the Director of Public Works
or his authorized representative. Failure to make this report shall make the Contractor
C-61
SP - 18
R6876-0001\1800412v2.doc
responsible for any such error in the finished work.
Payment - Except as otherwise provided in the Standard Specifications or elsewhere in
these Special Provisions, full compensation for conforming to the requirements in this
section shall be considered as included in the prices paid for the various contract items
of work, and no additional compensation will be allowed therefor.
[CONTINUED ON NEXT PAGE]
C-62
SP - 19
R6876-0001\1800412v2.doc
B. PROJECT SPECIAL PROVISIONS
PEACOCK RIDGE ROAD DRAINAGE IMPROVEMENTS
PROJECT NO. 8723
1- GENERAL
1.01 Work Included -- Work includes, but is not necessarily limited to:
Furnishing all necessary labor, materials, equipment and other incidental and appurtenant
Work necessary to construct the Storm Drain Improvements which includes removing
existing storm drain, installing new HDPE and concrete storm drain facilities, catch basins,
incidental removal and reconstruction of asphalt concrete pavement, removing and
reinstalling concrete curb and gutter, removing and reconstructing miscellaneous concrete
structures, temporary traffic control measures, large tree removals, grading, and other
appurtenant items not mentioned that are required to complete the work between
Scotmist Drive and Peacock Ridge Road including work within the private residential
property at 6037 Scotmist Drive as more clearly described in the Contract Documents.
1.02 Submittals - Except as provided in other bid items, no separate payment shall
be made for required project submittals. Submittals shall include all materials, plans,
diagrams, and drawings as called for in the specifications, and as may be required by
the work, and shall include at least the following:
Project Schedule
Concrete mix design per 201-1.1
Asphalt Concrete mix design 203-6.2
HDPE Storm Drain Pipe
Rebar
Grates
Sand Backfill
Contact List
Class “A” Top Soil (if used)
Notices
1.03 Product Handling
Use all means to protect all materials, before, during, and after installation. In the event
of damage, immediately make all repairs and replacements necessary to the approval of
the City’s designated representative at no additional cost to the Owner. Workmanship
must comply with printed instructions and recommendations of the manufacturer, and
with the highest standards of the industry.
1.04 Warranty
The contractor shall provide Owner a one-year warranty in writing that guarantees the
completed work to be free from defects in materials and workmanship. Contractor to
guarantee 72 hour call-out response to requests for warranty work during warranty
period.
C-63
SP - 20
R6876-0001\1800412v2.doc
2 - FURNISH AND APPLY WATER
Furnishing and applying water shall be considered as included in the unit prices paid for
the various bid items requiring water, and no additional compensation will be allowed
therefor.
Should the Contractor require water for construction operations, such as for compaction
and dust control, he shall apply for a water meter from, and follow the requirements of
California Water Service Company.
3 - UNCLASSIFIED EXCAVATION
General: Unclassified excavation shall consist of all excavation, including hardscaping,
landscaping, soils, rock, roadway, concrete pavement, curb, sidewalk, gutters, cross
gutters and driveways bituminous pavement, and all other existing materials as
necessary to complete the intended construction items.
Removal of Bituminous Pavement: Bituminous pavement shall be removed to neatly
sawed edges. Saw cuts shall be to a minimum depth of 3 inches. Where bituminous
pavement adjoins a trench, the edges adjacent to the trench shall be saw cut to neat
straight lines before permanent to ensure that all areas to be paved are accessible to the
rollers used to compact the sub grade or paving materials. Removal at flow line areas
shall include restoring pavement surface to flow line grade based on surrounding
conditions.
Existing utilities are not marked out. The Contractor shall be responsible for location and
determining the depths of all utilities and to provide adequate clearance. No additional
compensation shall be allowed for utility research.
Removal of all AC items shall be paid under their respective bid items, and no
additional payment shall be made therefor in this bid item.
Removal of Concrete Curb, Gutter, Sidewalks, Access Ramps and Driveways:
Concrete shall be removed to neatly sawed edges with saw cuts made to a minimum
depth of 1.5 inches. Concrete sidewalk or driveways to be removed shall be neatly
sawed in straight lines either parallel to the curb or at right angles to the alignment of the
sidewalk. No section to be replaced shall be smaller than 30 inches in either length or
width. If the saw cut would fall within 30 inches of a construction joint, functional
weakened plane joint, expansion joint or edge, the concrete shall be removed to the joint
or edge. In any case, the saw cut shall be made in and along a score mark if within the
30-inch zone. Curb and gutter shall be sawed to a depth of 1.5 inches on a neat line at
right angles to the curb face.
Removal of all PCC items shall be paid under their respective bid items, and no
additional payment shall be made therefor in this bid item.
C-64
SP - 21
R6876-0001\1800412v2.doc
Earthen Excavation
Following clearing and grubbing, the top six inches (6”) of soil in excavation at locations
not presently covered with concrete or AC shall be considered top soil. Top soil
excavations shall be set aside for replacement following trench backfill as required by
plans.
Any excavation performed as part of this work shall not be exposed for longer than 48
hours. Permanent concrete, where required by the plans, or finished earthen grades
must be placed or achieved over the excavated area by the end of the day on the Friday,
or the day before any City holiday, of the same work week that the excavation is
performed.
Where sensitive plants/bushes in parkway may be permanently damaged by excavation
equipment, the sidewalk shall be manually excavated to avoid damage to the
landscaping.
All open excavations must be protected with lighted barricades and caution tape.
All roots found within excavation area shall be removed per subsection 300-6.2 of the
Standard Specifications. The Contractor shall coordinate all root removals with the City
Arborist.
Payment: Full compensation for Unclassified Excavation shall be considered as included
in the various bid items requiring such, and shall include furnishing all labor, materials,
tools, equipment, incidentals, and appurtenant work required to complete the work as
shown on the plans and in accordance with the specifications. No additional
compensation will be allowed.
4 – REMOVE EXISTING CSP STORM DRAIN
The existing CMP storm drain pipe within the existing storm drain easement area and
the Peacock Ridge Drive right of way shall be removed as shown on plans and properly
disposed of off the project site.
Payment: Remove Existing CSP
Payment for removal of existing CSP shall include all work and materials as described
above necessary to remove the CSP, complete, to the limits shown on the plans.
5 – CLEARING AND GRUBBING
The Contractor shall clear and grub as necessary to provide access for equipment and
perform the noted construction work as shown on plans. Clearing and grubbing includes
the removal of existing trees within the easement area of 6037 Scotmist Drive.
Payment: Payment for clearing and grubbing shall be per the lump sum bid price for
Clearing and Grubbing, and no additional compensation will be allowed therefore.
C-65
SP - 22
R6876-0001\1800412v2.doc
6 - SUBGRADE PREPARATION
(a) General: The last sentence of the first paragraph of Subsection 301-1.2 of the
Standard Specifications is deleted and replaced by the following:
When unsuitable material due to excessive moisture content is found below the
processing depth for sub-grade specified herein, the Contractor shall make a
reasonable effort as directed by the Director of Public Works, to dry the material in
order to obtain compaction as specified in Subsection 301-1.3, Relative Compaction.
Such reasonable effort may include periodic cultivating and scarifying or allowing the
material to dry naturally or a combination of the above, for a period of time not to
exceed 2 weeks. After this time period, or earlier if so determined by the Director of
Public Works, the unsuitable material shall be treated in accordance with Subsection
300-2.2, Unsuitable Material. The Contractor will be allowed non-working days for
such work in accordance with Section 6-7, Time of Completion. An extension of time
for such work will be granted in accordance with Subsection 6-6 of the Standard
Specifications.
The last sentence of the first paragraph of Subsection 301-1.3 of the Standard
Specifications is deleted and replaced by the following:
When base or sub base material, curb, gutter, pavement, driveways, or sidewalks
are to be placed on the subgrade material, the top 6 inches (150mm) of such
subgrade material shall be compacted to a relative compaction of 95 percent.
Payment: Payment for preparation of sub-grade will be considered as included in
the item of work for which the sub-grade is prepared, and no additional payment will
be made therefor.
7 – CONCRETE STRUCTURES
General
Concrete culverts, catch basins, drainage structures, foundations and similar
structures shall be constructed in conformity with the plans and specifications.
Concrete for use in work constructed under this section shall conform to the
requirements of Section 201 of the Standard Specifications however, the minimum
strength shall be 3250 psi. Type V Portland cement shall be used.
Payment: Payment for concrete structures will be made in conformance with the
terms of the Contract and will be based on unit prices or lump sum amounts as set
forth in the bidding schedule.
8 - UNDERGROUND CONDUIT CONSTRUCTION
Trench Excavation: General
C-66
SP - 23
R6876-0001\1800412v2.doc
Excess Material - It shall be the Contractor’s responsibility to remove and dispose of
all excess material resulting from earthwork operations, including excavation material
of any character that is not suitable for use in fill or backfill. Unless otherwise
approved by the Engineer such material shall be removed from the work site
immediately after completion of work causing the surplus material.
The Contractor shall make his own arrangements for a disposal site, but in no
instance shall any material be wasted or dumped in any area until permission of the
owner of the property has been secured in writing, and a copy of the permit has been
furnished to the Engineer. The cost of disposal of excess or waste material shall be
borne by the Contractor.
The Contractor shall provide and maintain, at the construction site, ample means and
devices with which to remove and properly dispose of all water entering the
excavation.
Diversion of surface water from the excavation site shall be the responsibility of the
Contractor, and no separate compensation will be allowed for the removal of surface
water from the excavation site.
Maximum and Minimum Trench Width
Banks of open cut trenches shall be kept as nearly vertical as possible and, where
necessary in order to maintain the banks vertical, the trench shall be properly
sheeted and braced. For trenches exceeding a depth of four (4) feet, the sides of the
trench shall be cut back at a slope of 2:1 or properly supported with an adequate
trench shoring system. Trenches shall not be less than four (4”) inches or more than
six (6”) inches wider than the outside edge of the pipes to be laid therein, measured
at the springline of the pipe, and shall be excavated true to line.
In the event shoring is required, the width of the trench may be increased a
maximum of twelve (12”) inches to accommodate the sheeting. Bell holes, if
applicable, shall be excavated to ensure pipe barrel resting for its entire length upon
the bottom of the trench on undisturbed soil, thoroughly compacted backfill, or gravel
bedding.
Installation of Pipe: Bedding
Bedding should be installed to the specifications detailed in the Standard
Specifications.
The material excavated from the storm drain trench may be suitable as backfill in
allowable areas shown on the trench detail shown on the plans.
A minimum four (4”) inch thick layer of sand shall be placed under the pipe and
extend upwards to depth that is six (6”) inches below finished grade above the top of
the pipe. The sand material shall meet the requirements of Standard Specifications
Table 200-1.5.5 and be compacted to 95% relative compaction.
C-67
SP - 24
R6876-0001\1800412v2.doc
The trench bottom shall be graded to provide a smooth, straight, firm and stable
foundation at every point throughout the length of the pipe. At each join in the pipe,
the bottom of the trench shall be recessed in such a manner as to relieve the joint
from all load and to ensure continuous bearing along the pipe barrel. The recess
shall also be large enough to prevent foreign material from entering the pipe.
If any trench, through the neglect of the Contractor, is excavated below the grade
required by the Plans and these Special Provisions, it shall be refilled to grade with
additional bedding. The excess excavation and the additional bedding shall be at the
Contractors expense.
It is possible that soft, spongy, or unstable material will be encountered at pipeline
grade and that this material will not support the pipe or other indicated construction
properly. The Contractor shall remove said unsatisfactory material to an over-depth
and width as ordered by the Engineer. The Contractor shall be paid on a cost per
cubic yard basis as provided in the Standard Specifications. Said cost shall include
the cost for specific bedding material as required by the Engineer to replace the
over-excavated material.
Should over-excavation of soft, spongy, or unstable trench bottom material be the
result of the Contractor’s failure to remove groundwater in a timely and continuous
manner or failure to divert surface water flow away from the excavation site, the
Contractor shall be required to over- excavate and re-establish the trench bottom line
and grade at his own cost per these Special Provisions.
In the case where an existing utility is a sewer or water line, sand bedding shall be
required to a minimum of twelve (12”) inches above the existing pipe.
Backfill and Densification: General
Backfill shall be placed as specified in the Standard Specifications Subsection 306-
1.3.2 or 306-1.3.3, and compaction requirements shall be in accordance with the
following:
The trench from the top of the bedding material to the subgrade shall be backfilled,
compacted, and/or consolidated by approved methods to obtain relative density of
ninety-five percent (95%).
The entire trench backfill and all transverse trench operations on streets may be
backfilled with a sand-cement slurry mix comprised of 100 lb. of cement per cubic
yard to sand. Sand shall conform to “Grading E” of the Standard Specifications as
indicated in Section 201-1.3.2 of the Standard Specifications.
Basis for Payment for Open Trench Installation
C-68
SP - 25
R6876-0001\1800412v2.doc
The price per foot for pipe in place, in addition to those items as noted in the
Standard Specifications shall include: groundwater and surface water control,
excavation, shoring, bracing of utility lines as required, any pipe removal, bedding
and backfill material, placement and compaction, sand slurry mix, imported backfill
material as may be required, removal of excess excavated material and/or native
material unsuitable for backfill, subgrade material, preparation and compaction,
temporary resurfacing materials, miscellaneous concrete except as otherwise shown
on the plans, and all other items as specified in these Special Provisions and Section
306-1.6 of the Greenbook Standard Specifications for Public Works Construction.
Payment for HDPE pipe shall include all work and materials as described above
necessary to install this facility, complete in place, to the limits shown on the plans.
9 – BEST MANAGEMENT PRACTICES
Best Management Practices/ NPDES Compliance shall be as specified in the Special
Provisions of these specifications, and shall be paid per lump sum under bid item
Stormwater Best Management Practices, and no additional compensation shall be
allowed.
10 - PROTECTION AND RESTORATION OF EXISTING IMPROVEMENTS
General: Except as may otherwise be provided in specific instances, nothing in the
Contract shall be constructed as vesting in the Contractor any property right in any
material, article or structure existing at the time of award of Contract within the area in
which the work is to be done; or in any material or article subsequently furnished for the
work by the Contractor after having been accounted for on an approved estimate
supporting the Contractor's demand for payment as provided in Section 9. In the latter
event any such material, article, structure or work shall become the property of the
agency after being so accounted for.
The Contractor shall maintain all existing signs including, but not limited to directional,
warning, advisory, regulatory, bus stop, and street markers, in an erect and functional
position and condition all times during the construction period in temporary locations as
designated by the Director of Public Works. Any of these facilities which are damaged
or lost shall be replaced by the Contractor at no cost to the Agency.
Contractor shall restore curb markers, curb and roof drains, landscaping, irrigation,
natural and artificial turf, reflective raised markers, etc. interfering with PCC construction.
Contractor shall submit video documentation with a log of existing damages prior to
commencing with work. Should a resident claim existing improvements were damaged
by construction, and Contractor did not confirm status per above, Contractor shall
restore existing improvements at no cost to the City.
When an interfering portion of a privately owned sprinkler system is removed, heads and
other salvable material shall be carefully removed and stored. Any of the materials not
wanted by the owner shall be removed from the site by the Contractor. Removal, repair,
or capping shall be as directed by the Director of Public Works. Protection and
restoration of existing improvements shall be considered part of the various items of
work and no separate compensation will be allowed therefor.
C-69
SP - 26
R6876-0001\1800412v2.doc
Contractor shall protect under-sidewalk yard drain pipes during construction and replace
pipes which are in subpar condition.
Contractor shall protect existing concrete adjacent to proposed improvement area.
Damage to existing concrete shall be removed and replaced to existing score line at
Contractor’s expense.
Contractor shall confirm operational status of all affected irrigation with inspector and
resident prior to commencing work. Should resident claim their system was damaged by
construction, and Contractor did not confirm status per above, Contractor shall restore
system to operation at his own cost.
All spray paint and markings used for locating utility lines, identifying work locations, or
any other purpose, shall be completely removed by power-washing. Any residual
discoloration left from temporary A.C. cold mix patches in the sidewalk and curb area
shall also be removed by power-washing. All NPDES guidelines shall be followed when
power-washing, including vacuuming of water (or other method approved by the Director
of Public Works or his authorized representative) to prevent it from entering any storm
drain. Payment for this work shall be included in the cost of the bid items for replacement
of PCC sidewalk and PCC curb and gutter, respectively.
The Contractor shall be responsible to protect all new concrete work from being etched,
scratched or otherwise marked or having wet slough material deposited thereon. If new
concrete work is marked, the Contractor shall replace it at its expense.
The Contractor shall perform all private lawn, hardscape, and parkway restorations
including restoration of irrigation systems and existing curb drains, adjacent to sidewalk,
driveway, curb and gutter repairs, not included in the Project Quantities, within fourteen
(14) calendar days after the adjacent improvements have been constructed. Contractor
may not proceed with removals if restoration slows to more than fourteen (14) calendar
days. If the repairs have not been completed within 14 calendar days, the City shall have
the authority to complete such work and deduct cost plus 20 percent administration
thereof from any moneys due or to become due to the Contractor. Furthermore, a
penalty of $500 per day shall be applied for each day beyond the 14 day period that the
restoration has not been completed (as determined by the City’s inspector). Irrigation
damaged by construction outside of restoration areas shall be repaired per General
Provision 26.
11 - REMOVAL OF DEFECTIVE OR UNAUTHORIZED WORK
All work which is defective in its construction or deficient in any of the requirements of
these Special Provisions or the Standard Specifications shall be remedied, or removed
and replaced by the Contractor in a manner acceptable to the City and no compensation
will be allowed for such correction.
The minimum length for removal and replacement of unsatisfactory work shall be to the
nearest joints on both sides of the area to be removed, or as required by the Engineer.
Saw cutting is required for all removals of defective concrete work at no additional cost.
Upon failure on the part of the Contractor to comply forthwith with any order the
Engineer makes under the provisions of this section, the Public Works Department shall
C-70
SP - 27
R6876-0001\1800412v2.doc
have authority to cause defective work to be removed and replaced and deduct the costs
thereof from any monies due or to become due to the Contractor.
12 - APPURTENANT WORK
All items in the Bid Schedule are for construction completed in place, including all
incidentals, appurtenant work and materials necessary for the satisfactory completion of
the work. Full payment shall be considered as the bid prices for the items of work, and
no additional compensation will be made therefor.
13 - INSPECTION BY CITY
The City shall inspect the quality and completeness of the Contractor's work and report
any deficiencies to the Contractor.
14 - CLEANUP:
During all phases of construction, the Contractor shall maintain a clean work site, the
Contractor shall be responsible for the immediate removal and disposal of all concrete,
asphalt concrete, tree roots, and any other debris resulting from the work performed. Full
compensation shall be considered as included in the prices for the various contract
items.
15 - CONSTRUCTION WATER:
The Contractor shall make his own provisions for water necessary for construction,
drilling, backfill consolidation and cleanup.
Note: The Contractor shall not use any private property water paid for by the property
owner. The Contractor shall obtain and pay for all costs incurred for any
necessary water meter permits. No extra compensation shall be allowed for the
permit and/or water meter.
For a permit contact:
California Water Service
5837 Crest Road
Rancho Palos Verdes, CA 90275
(310) 377-5525
16 - STORAGE SITES:
The Contractor may be allowed to store materials and equipment in designated areas at
City Hall or at the work site during the course of construction. The Contractor is required
to obtain permission for such storage from the Engineer.
The City may permit the Contractor to store certain materials and equipment on City
property provided that (1) The storage area has a gate which shall be closed by a lock at
the end of each day. (2) The site and access road must be kept clean at all times during
the period of the contract and (3) The Contractor complies to City requirements
regarding cleanup.
The allowable materials to be stored by the Contractor are: Vehicles, equipment, pipes,
C-71
SP - 28
R6876-0001\1800412v2.doc
wooden forms and tools. All storage materials must be first approved by the City. The
Contractor will not be allowed to store broken concrete, asphalt concrete or any debris
on City property.
If the site becomes unacceptable to the City for any reason, after notice by the City, the
Contractor shall correct the problem immediately. In the event that the City requests
removal of the materials from City property prior to the end of the construction period,
the Contractor shall not receive any additional compensation. The Contractor shall
maintain and clean the storage area on a daily basis.
The Contractor shall repair at no cost to the City, any damage to the asphalt concrete
access road resulting from the Contractor's vehicle traffic.
Upon failure on the part of the Contractor to comply with any of these Special Provisions,
the City shall have authority to cause defective work to be corrected and deduct the cost
of said corrections from any monies due or to become due to the Contractor.
The Contractor shall hold the City harmless in the event of damage, vandalism or injury
to the Contractor's equipment, materials, etc., resulting from the use of this site.
17 - SITE RESTORATION AND MEDIAN PROTECTION
The Contractor shall be responsible for protection and preservation of existing
vegetation and improvements including necessary removal and storage of such
improvements and subsequent replacement to obtain to the fullest extent possible, the
undisturbed condition.
The Contractor shall restore or replace, any property damaged or affected by its work,
equipment or employees to the original undisturbed condition. This includes but is not
limited to the proper restoration of artificial turf and natural turf.
The Contractor shall thoroughly clean all areas affected by the contractor and the
subcontractors including areas and improvements affected by their equipment and
employees, upon completion of the work.
Payment: Full compensation for complying with the work contained in this section shall
be included in the bid unit price for various bid items and no additional compensation will
be allowed therefor.
18 - LARGE TREE REMOVALS AT PEACOCK RIDGE ROAD
Remove all large trees indicated by the plans and specifications, as requiring removal, in
a manner that will not damage adjacent trees, structures, remaining asphalt concrete
paving, remaining curb and gutter, or surrounding compacted soil.
Remove trees that are adjacent to trees or structures to remain, in sections, to limit the
opportunity of damage to adjacent crowns, trunks, ground plane elements and
structures.
Do not drop trees with a single cut.
C-72
SP - 29
R6876-0001\1800412v2.doc
Protect adjacent paving, walls, fencing, curb and gutter, soil, trees, shrubs, ground cover
plantings and understory plants to remain from damage during all tree removal
operations, and from construction operations. Protection shall include the root system,
trunk, limbs, and crown from breakage or scarring, and the soil from decompaction.
Remove stumps and immediate root plate from existing trees to be removed from within
the removal area bounded by existing features and improvements to remain. Grind trunk
bases and large buttress roots to a depth of the largest buttress root or at least 18
inches below the top most roots whichever is less and over the removal area.
For trees where the stump will fall under paved areas or other features to remain, grind
roots to a total depth of 18 inches below the existing grade. If the sides of the stump hole
still have greater than approximately 20% wood visible, continue grinding operation
deeper and or wider until the resulting hole has less than 20% wood. Remove all wood
chips produced by the grinding operation. The Public Works Director or his
representative shall approve each hole at the end of the grinding operation.
Back fill holes in 8-inch layers with earthen fill. Fill may be obtained from project trench
excavations, excluding top soil as defined in Section 3 of these Project Special
Provisions, or be Class “A” Topsoil per Section 212-1.1.2 of the Standard Specifications.
Fill shall be compacted to 85% of the maximum dry density standard proctor.
[END OF SECTION]
C-73
TP - 01
TECHNICAL PROVISIONS
A. GENERAL
Contractor shall construct the Storm Drain Improvements which includes removing existing storm
drain pipe, installing new HDPE and concrete storm drain facilities, catch basins, incidental
removal and reconstruction of asphalt concrete pavement, removing and reinstalling concrete
curb and gutter, removing and reconstructing miscellaneous concrete structures, temporary traffic
control measures, large tree removals, grading, and other appurtenant items of work not
mentioned that are required to complete the work.
1 - COMPACTION TESTING
The City of Rancho Palos Verdes will provide all necessary soils compaction testing for this
contract, except for work that has to be redone as noted below.
The Contractor's requests for compaction testing shall be made to the Director of Public Works
or his authorized representative a minimum of 2 working days prior to the time required for such
work.
The Contractor, at his expense, shall excavate the holes for all of the tests, backfill the holes and
compact this backfill, and pave the surface, if required, after the test.
Compaction tests on the subgrade which meet the specified requirements will be at the City's
expense. All compaction tests which do not meet the specified compaction requirements shall be
at the Contractor's expense, with no compensation therefor.
2 - MATERIAL TESTING
The City of Rancho Palos Verdes will provide all necessary material sampling and testing for this
contract, except for work that has to be redone as noted below.
The Contractor's requests for testing shall be made to the Director of Public Works or his
authorized representative a minimum of 2 working days prior to the time required for such work.
The Contractor, at his expense, shall provide access to materials and locations for all of the
sampling and testing.
Tests which meet the specified requirements will be at the City's expense. All tests which do not
meet the specified requirements shall be at the Contractor's expense, with no compensation
therefore.
3 - CRUSHED MISCELLANEOUS BASE/CLASS 2 AGGREGATE BASE
Except as specifically noted, no separate payment shall be made for crushed miscellaneous base
(CMB) or Class 2 aggregate base (AB). Either CMB or Class 2 aggregate base is acceptable
material for base. Base shall be placed at locations as needed for the restoration of asphalt
concrete surfaces at a thickness that matches existing conditions. CMB shall be fine grade (3/4”).
Base shall be compacted to 95% relative compaction per the Standard Specifications
requirements. All CMB and Class 2 aggregate base will be considered as included in the unit
price per ton for Construct AC over AB, Match Existing Section bid item, and no separate payment
will be made therefore.
C-74
TP - 02
4 - PORTLAND CEMENT CONCRETE (PCC) CONSTRUCTION
Per the Standard Specifications, Section 201-1.4.3, the contractor shall deliver and place the
concrete within 90 minutes from mixing at the batch plant. Should this time criteria be significantly
exceeded, it will be up to the discretion of the Engineer to determine if the concrete is sufficiently
workable, without adding excess water, to continue with the work. Any concrete accepted and
placed after 90 minutes from batch plant mixing shall be used at the Contractors risk and
maintained under the contractor’s warranty against defects, per the contract documents. The
Contractor may use a plasticizer to extend the workable life of the concrete upon approval of the
Engineer. The Contractor shall monitor concrete until is sufficiently hard to prevent damage or
vandalism.
All sub-grade and/or adjacent fill to match finished surface where new concrete is to be placed,
shall be compacted to a relative compaction of at least 90%. Bedding material in the pipe trench
and blow the replaced concrete slab/paving shall be compacted to a relative compaction of at
least 95%.
Payment: Payment for construction of PCC catch basins and replacement slab paving shall be
at contract bid price for these items and shall include full compensation for all labor and materials
to construct, furnish, and place Portland cement concrete including equipment and incidentals
required to complete the work.
5 - SAWCUT, EXCAVATION, REMOVAL AND REPLACEMENT ASPHALT CONCRETE
Description - This work shall consist of sawcut and removal of existing pavement edge where
shown on the plans, and disposing of existing pavement, aggregate base, cement treated base,
and native material; the preparation of subgrade and furnishing, spreading, placing, and
compacting of materials for Asphalt Concrete. This work shall include applying paint binder (tack
coat) to all vertical and horizontal surfaces to be joined by new pavement, and a sand/emulsion
seal for all joints after paving.
Materials
Asphalt Concrete
All excavated pavement areas shall be filled to match the existing thickness of adjacent existing
Asphalt Concrete, Type III-C2, 1/2" maximum aggregate conforming to the provisions of Section
400 of the Standard Specifications . Placement of AC shall be done in multiple lifts. The Contractor
shall submit the batch plant mix design (including stability test results) to the Engineer for review
and approval at least fourteen (14) calendar days prior to commencing any associated work.
Asphalt Binder
The Asphalt Binder and tack coat shall be PG 64-10 and shall conform to section 92 “Asphalts”
of the State standard Specifications and as determined by the Engineer.
The Contractor shall prevent the formation of carbonized particles caused by overheating Asphalt
during manufacturing or construction.
Aggregate
The provisions of Section 400-4.2.2 “Aggregate”, of the Standard Specifications shall have the
following additional requirement:
C-75
TP - 03
At least 75 percent, by weight, of the material retained on the No. 4 sieve shall have
at least one fractured face as determined by California Test Method No. 205.
Construction
Areas to be sawcut and removed shall be marked in the field with paint by the Contractor for
approval by the Engineer.. The depth of cut shall be deep enough to provide a clean, straight
break without loosening, cracking or damaging adjoining asphalt or concrete.
Contractor shall sawcut pavement around all areas to be removed prior to the start of any
excavation. All excavated materials shall be immediately removed from the site and recycled or
disposed of at the Contractor's expense at a legal dumpsite see Section 38 – CONSTRUCTION
AND DEMOLITION MATERIALS RECYCLING REQUIREMENTS of these General Provisions.
All excavated areas shall be immediately repaired with deep lift AC as specified in these Special
Provisions.
Streets shall not be washed to the extent that debris may enter storm drain system. All streets,
gutters and local depression areas of catch basins shall be kept free of dirt, rocks or other debris
at all times. During removal and replacement, grinding and paving operations all catch basin
inlets shall be covered with a fabric which will allow passage of water but will not allow debris t o
enter storm drain. During sawcutting operations all excess water and mud shall be removed from
surface by wet vacuum method. Material may be shoveled or broomed onto adjacent subgrade
or dirt area provided it cannot get into storm drain.
Construction shall conform to applicable provisions of Sections 302 and 400 of the Standard
Specifications and these Special Provisions. Full depth asphalt concrete pavement repairs shall
be constructed in equal lifts to the total overall after compaction thickness per the Plans or as
ordered by the City Engineer.
6 - HIGH DENSITY POLYETHYLENE (HDPE) PIPE PLACEMENT
Pipe Joining
The HDPE pipe shall be butt fused/welded together by applying heat to prepared pipe ends and
then pushing the pipe ends together with required force using properly sized butt fusion machine
for the pipe size to be joined. Butt fusing shall be performed in accordance with the pipe
manufacturer’s recommendations for such work. The Contractor shall verify pipe condition, joint
integrity, and join angles in the field.
Material
The HDPE pipe to be used on this project shall meet the requirements of Section 209-5 of the
latest edition of the Standard Specifications for Public Works Construction, shall be DR17, with
markings conforming to American Water Works Association C901, have a dimension ratio of 17
(DR-17), and have thermal butt fused joints.
Contractor shall submit certification of pipe from manufacturer indicating compliance to the
Engineer for approval prior to construction.
Payment
Payment for HDPE pipe construction and appurtenant fixtures shall be at the contract unit price
for Trench and Construct Dbl. 10” HDPE Pipes per linear foot of double pipe and shall include full
C-76
TP - 04
compensation for all labor and materials and equipment to construct, furnish, butt weld, and place
the HDPE pipe including incidentals required to complete the work.
7 - CONTRACT UNIT PRICES
Delete Standard Specifications Section 3-2.2.1 through 3-2.2.3. The City reserves the right to
adjust unit quantities and scope of work as necessary to meet project and budgetary
requirements.
C-77
CHECKLIST FOR BIDDERS
The following information is required of all Bidders at the time of the bid:
____ Completed and Signed Proposal
____ Completed and Signed Bid Sheets
____ Completed Information Required of Bidders Form
____ Completed References Sheet(s)
____ Executed Statement Acknowledging Penal and Civil Penalties
Concerning the Contractor’s Licensing Law
____ Attached Resume of General Construction Superintendent or on-site
Construction Manager for the Contractor
____ Completed Designation of Subcontractors Form
____ Completed and Signed Contractor’s Industrial Safety Record
____ Completed, Signed and Notarized Bid Bond or Other Security
____ Signed and Notarized Non-Collusion Declaration
____ Completed and Signed Acknowledgement of Addenda
____ Completed Bidder Statistical Information Form
____ All Addenda (if applicable)
Failure of the Bidder to provide all required information in a complete and accurate manner may
be considered non-responsive.
C-78
P - 1
PROPOSAL
CITY OF RANCHO PALOS VERDES
PEACOCK RIDGE ROAD DRAINAGE IMPROVEMENTS
PROJECT No. 8723
TO THE DIRECTOR OF PUBLIC WORKS, CITY OF RANCHO PALOS VERDES:
The undersigned, as bidder, declares that: (1) this proposal is made without collusion with any
other person, firm or corporation, and that the only persons or parties interested as principals
are those named herein; (2) bidder has carefully examined the project plans, specifications,
instructions to bidders, proposal, notice to contractors and all other information furnished
therefore and the site of the proposed work; (3) bidder has investigated and is satisfied as to the
conditions to be encountered, the character, quality and quantities of work to be performed and
materials to be furnished. Furthermore, bidder agrees that submission of this proposal shall be
conclusive evidence that such examination and investigation have been made and agrees, in
the event this contract be awarded to bidder, to enter into a contract with the CITY OF
RANCHO PALOS VERDES, to perform said proposed work in accordance with the plans, if any,
and the terms of the specifications, in the time and manner therein prescribed, and to furnish or
provide all materials, labor, tools, equipment, apparatus and other means necessary so to do,
except such thereof as may otherwise be furnished or provided under the terms of said
specifications, for the following stated unit prices or lump-sum price as submitted on the
Schedule attached hereto:
The bidder shall submit as part of this proposal a completed copy of the Contractor’s Industrial
Safety Record.
Accompanying this proposal is _______________ (Insert) “$_______________ “cash,”
“Cashier’s Check,” “certified check,” or “Bid Bond,” as the case may be) in the amount equal to
at least ten percent (10%) of the total aggregate bid price hereof based on the quantities shown
and the unit prices quoted in the Bid Schedule.
The undersigned further agrees that should he/she be awarded the contract on the basis hereof
and thereafter, defaults in executing the required contract, with necessary bonds and
documents, within ten (10) days, not including Sundays and legal holidays, after having
received notice that the contract has been awarded and is ready for signature, the proceeds of
the security accompanying his bid shall become the property of the CITY OF RANCHO PALOS
VERDES and this proposal and the acceptance thereof may be considered null and void.
The undersigned certifies to have a minimum of five (5) consecutive years of current experience
in the type of Work related to this Project and that this experience is in actual operation of the
firm with permanent employees performing a part of the Work as distinct from a firm operating
entirely by subcontracting all phases of the Work. The undersigned also certifies to be properly
licensed by the State as a contractor to perform this type of Work and further certifies to have
been so licensed for the five (5) years immediately preceding the date of receipt of Bids. The
undersigned possesses California Contractor’s License Number ____________, Class _____,
which expires on ___________________.
Signature(s) of bidder:
____________________________________________________________________________
If an individual, so state. If a firm or co-partnership, state the firm name and give the names of
all individual co-partners composing the firm. If a corporation, state legal name of corporation,
C-79
P - 2
also names of president, secretary, treasurer, and manager thereof. Two notarized officer’s
signatures and the corporate seal are required for corporations.
Legal Business Name:
Address:
Telephone:
Contact:
Proposals which do not show the Contractor’s License Number and expiration date of the
Bidder’s License under the provisions of Chapter 9 of Division 3 of the Business & Professional
Code will be rejected.
Bid Date
This information must include all construction work undertaken in the State of California by the
bidder and partnership joint venture or corporation that any principal of the bidder participated in
as a principal or owner for the last five calendar years and the current calendar year prior to the
date of bid submittal. Separate information shall be submitted for each particular partnership,
joint venture, corporate or individual bidder. The bidder may attach any additional information or
explanation of data which bidder would like to be taken into consideration in evaluating the
safety record. An explanation must be attached of the circumstances surrounding any and all
fatalities.
C-80
P - 3
CITY OF RANCHO PALOS VERDES
BID SHEET
STORM DRAIN IMPROVEMENTS
AT PEACOCK RIDGE ROAD
CIP No. 8723
Bidder’s Name:_________________________________________________________
To the Honorable Mayor and Members of the City Council:
In compliance with the Notice Inviting Sealed Bids, the undersigned hereby agrees to enter into
a contract to furnish all labor, materials, equipment and supplies for the project identified as
PEACOCK RIDGE ROAD DRAINAGE IMPROVEMENTS, PROJECT No. 8723 in accordance
with the specifications and plans for demolition, construction and installation in the Contract
Documents which are on file in the office of the Director of Public Works of the City of Rancho
Palos Verdes to the satisfaction and under the direction of the Director of Public Works at the
following prices:
LUMP SUM ITEMS SHALL INCLUDE PROVIDING AND INSTALLATION OF ALL
COMPONENTS STIPULATED WITHIN THE CONTRACT DOCUMENTS AND NECESSARY
INCIDENTALS TO FACILITATE PROVIDING SAID COMPONENTS. SURVEY,
EXCAVATIONS, AND BMPS SHALL BE CONSIDERED INCLUDED IN THE INDIVIDUAL BID
ITEMS. NO ADDITIONAL PAYMENTS WILL BE MADE.
The quantities reflected on the plans and in the bid-sheets are representative of the amount of
work for each item on the project but are not final quantities to be used for computing payment.
Payment will be based on the measurement of actual work completed. The contractor must
notify in writing to the project manager of all discrepancies between actual bid quantities and
those shown in the bid document prior to commencement of work in any area of the project.
C-81
P - 4
BID SCHEDULE
ITEM
NO. DESCRIPTION ESTIMATED
QUANTITY UNIT PRICE UNIT EXTENDED
AMOUNT
1 Traffic Control
Complete
LS
2 Mobilization
Complete LS
3 Stormwater Best Management Practices
Complete LS
4 Clear and Grub Complete LS
5 Sawcut and Remove AC Pavement 205 SF
6 Large Tree Removal No. 1 on Peacock Ridge Rd. Complete LS
7 Large Tree Removal No. 2 on Peacock Ridge Rd. Complete LS
8 Large Tree Removal No. 3 on Peacock Ridge Rd. Complete LS
9 Remove Concrete Inlet Structure 1 EA
10 Excavate, Remove and Dispose of Existing CSP 103 LF
11 Sawcut and Remove Existing Curb and Gutter 179 LF
12 Sawcut and Remove Existing Concrete Pavement 239 SF
13 Connection of DBL HDPE Pipes to Existing Outlet Complete LS
14 Trench and Construct Double-10” HDPE Pipes 115 LF
15 Construct 6” Thick Reinforced Concrete Pavement 4 CY
16 Construct Alley Inlet Per SPPWC 304-3 1 EA
17 Construct Curb Opening Catch Basin with 2 Grates 1 EA
18 Plant Sod Landscaping in Private Disturbed Area Complete LS
C-82
P - 5
ITEM
NO. DESCRIPTION ESTIMATED
QUANTITY UNIT PRICE
UNIT
EXTENDED
AMOUNT
19 Construct 8” Curb and Gutter Transition 2 EA
20 Construct 8” Curb and Gutter Per SPPWC 120-2 53 LF
21 Construct AC over AB, Match Existing Section 4 TON
22 Place Fill in Large Tree Removal Area 1 LS
TOTAL BASE BID SCHEDULE IN NUMBERS: $____________________
TOTAL BASE BID SCHEDULE IN WORDS: ____________________________________
The contract shall be awarded to the lowest responsible bidder based on the TOTAL
BASE BID.
Note: Some items may be adjusted or deleted. Any changes to the quantities for these items
shall not classify as a substantial change as stipulated in Section 3-2.2.1 of the Standard
Specifications. Therefore, regardless of total actual amount (percentage) compared to
estimated quantities, the unit prices provided above by the Bidder shall be applied to the final
quantity when payment is calculated for these items. No adjustment in the unit prices will be
allowed. The City reserves the right to not use any of the estimated quantities, and if this right is
exercised, the Contractor will not be entitled to any additional compensation. Cost of all export
of material shall be included in the above unit costs; no additional compensation will be granted
for such expenses. The Contract shall be awarded to the lowest responsible Bidder based on
the total Bid price. This proposal shall include provision for at-risk youth employment per
specification and grant requirements.
INFORMATION REQUIRED OF BIDDER
Fill out all of the following information. Attach additional sheets if necessary.
(1) Bidder’s name:
(2) If the Bidder’s name is a fictitious name, who or what is the full name of the registered
owner? If the Bidder’s name is not a fictitious name, write “N/A” in the response to this
question. If you are doing business under a fictitious name, provide a copy of the filed
valid Fictitious Business Name Statement.
______________________________________________________________________
(3) Business address:
(4) Telephone: Facsimile:
C-83
P - 6
(5) Type of firm - Individual, Partnership, LLC or Corporation:
(6) Corporation organized under the laws of the state of:
(7) California State Contractor’s License Number and Class:
(8) DIR Contractor Registration Number:
(9) List the name and title of the person(s) who inspected the site of the proposed Work for
your firm:
(10) Number of years’ experience the company has as a contractor in construction work:
(11) List the names, titles, addresses and telephone numbers of all individuals, firm
members, partners, joint venturers, and company or corporate officers having a principal
interest in this Proposal:
List at least three similar projects completed as of recent date:
Contract
Amount Class of Work
Date
Completed
Name, Address of Owner, & Telephone
No.
(12) NOTE: Upon request of the CITY, the bidder shall furnish evidence showing a notarized
financial statement, financial data, construction experience, or other information.
(13) “Bidder shall be properly licensed at the time of bid submission or the bid shall be
considered non-responsive and shall be rejected.”
C-84
P - 7
REFERENCES
For all public agency projects in excess of $300,000 you are currently working on or have
worked on in the past five (5) years, provide the following information:
Project 1 Name/ Number
Project Description
Approximate Construction Dates From: _______________ To: ____________ ___ _
Agency Name:
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
If final amount is different from original amount, please explain (change orders, extra work, etc.)
Did you file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No
If you answered yes to either of the above two questions, please explain and indicate outcome
of claims.
Project 2 Name/ Number
Project Description
Approximate Construction Dates From: _______________ To: _________ _____ __
Agency Name: _ _____
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
C-85
P - 8
If final amount is different from original amount, please explain (change orders, extra work, etc.)
Did you file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No
If you answered yes to either of the above two questions, please explain and indicate outcome
of claims.
Project 3 Name/ Number
Project Description
Approximate Construction Dates From: _______________ To: ___ _____________
Agency Name:
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
If final amount is different from original amount, please explain (change orders, extra work, etc.)
Did you file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No
If you answered yes to either of the above two questions, please explain and indicate outcome
of claims.
C-86
P - 9
Project 4 Name/ Number
Project Description
Approximate Construction Dates From: _______________ To: ________ ________
Agency Name:
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
If final amount is different from original amount, please explain (change orders, extra work, etc.)
Did you file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No
If you answered yes to either of the above two questions, please explain and indicate outcome
of claims.
Project 5 Name/ Number
Project Description
Approximate Construction Dates From: _______________ To: _________ _______
Agency Name:
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
If final amount is different from original amount, please explain (change orders, extra work, etc.)
C-87
P - 10
Did you file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No
If you answered yes to either of the above two questions, please explain and indicate outcome
of claims.
Project 6 Name/ Number
Project Description
Approximate Construction Dates From: _______________ To: ________ ________
Agency Name: ______
Contact Person: Telephone:
Address:
Original Contract Amount: $ Final Contract Amount: $
If final amount is different from original amount, please explain (change orders, extra work, etc.)
Did you file any claims against the Agency? Circle one: Yes No
Did the Agency file any claims against you? Circle one: Yes No
If you answered yes to either of the above two questions, please explain and indicate outcome
of claims.
C-88
P - 11
STATEMENT ACKNOWLEDGING PENAL AND CIVIL PENALTIES
CONCERNING THE CONTRACTORS’ LICENSING LAWS
[Business & Professions Code 7028.15]
[Public Contract Code 20103.5]
I, the undersigned, certify that I am aware of the following provisions of California law and that I,
or the entity on whose behalf this certification is given, hold a currently valid California
contractor’s license as set forth below:
Business & Professions Code 7028.15:
(a) It is a misdemeanor for any person to submit a bid to a public agency in order to
engage in the business or act in the capacity of a contractor within this state
without having a license therefore, except in any of the following cases:
(1) The person is particularly exempted from this chapter.
(2) The bid is submitted on a state project governed by Section 10164 of the
Public Contract Code or on any local agency project governed by Section
20104 [now ‘ 20103.5] of the Public Contract Code.
(b) If a person has been previously convicted of the offense described in this section,
the court shall impose a fine of 20 percent of the price of the contract under
which the unlicensed person performed contracting work, or four thousand five
hundred dollars ($4,500), whichever is greater, or imprisonment in the county jail
for not less than 10 days nor more than six months, or both.
In the event the person performing the contracting work has agreed to furnish
materials and labor on an hourly basis, “the price of the contract” for the
purposes of this subdivision means the aggregate sum of the cost of materials
and labor furnished and the cost of completing the work to be performed.
(c) This section shall not apply to a joint venture license, as required by Section
7029.1. However, at the time of making a bid as a joint venture, each person
submitting the bid shall be subject to this section with respect to his or her
individual licensure.
(d) This section shall not affect the right or ability of a licensed architect, land
surveyor, or registered professional engineer to form joint ventures with licensed
contractor to render services within the scope of their respective practices.
(e) Unless one of the foregoing exceptions applies, a bid submitted to a public
agency by a contractor who is not licensed in accordance with this chapter shall
be considered non-responsive and shall be rejected by the public agency.
Unless one of the foregoing exceptions applies, a local public agency shall,
before awarding a contract or issuing a purchase order, verify that the contractor
was properly licensed when the contractor submitted the bid. Notwithstanding
any other provision of law, unless one of the foregoing exceptions applies, the
registrar may issue a citation to any public officer or employee of a public entity
who knowingly awards a contract or issues a purchase order to a contractor who
is not licensed pursuant to this chapter. The amount of civil penalties, appeal,
C-89
P - 12
and finality of such citations shall be subject to Sections 7028.7 to 7028.13
inclusive. Any contract awarded to, or any purchase order issued to, a contractor
who is not licensed pursuant to this chapter is void.
(f) Any compliance or noncompliance with subdivision (e) of this section, as added
by Chapter 863 of the Statutes of 1989, shall not invalidate any contract or bid
awarded by a public agency during which time that subdivision was in effect.
(g) A public employee or officer shall not be subject to a citation pursuant to this
section if the public employee, officer, or employing agency made an inquiry to
the board for the purposes of verifying the license status of any person or
contractor and the board failed to respond to the inquiry within three business
days. For purposes of this section, a telephone response by the board shall be
deemed sufficient.
Public Contract Code 20103.5:
In all contracts subject to this part where federal funds are involved, no bid submitted
shall be invalidated by the failure of the bidder to be licensed in accordance with the
laws of this state. However, at the time the contract is awarded, the contractor shall be
properly licensed in accordance with the laws of this state. The first payment for work or
material under any contract shall not be made unless and until the Registrar of
Contractors verifies to the agency that the records of the Contractor ’s State License
Board indicate that the contractor was properly licensed at the time the contract was
awarded. Any bidder or contractor not so licensed shall be subject to all legal penalties
imposed by law including, but not limited to, any appropriate disciplinary action by the
Contractor’s State License Board. The agency shall include a statement to that effect in
the standard form of prequalification questionnaire and financial statement. Failure of
the bidder to obtain proper and adequate licensing for an award of a contract shall
constitute a failure to execute the contract and shall result in the forfeiture of the security
of the bidder.
License No.:
Class:
Expiration Date:
Date:
Signature:
C-90
P - 13
RESUME(S)
Attach to this Bid the experience resume of the person(s) who will be designated as General
Construction Superintendent or on-site Construction Manager for the Contractor.
C-91
P - 14
DESIGNATION OF SUBCONTRACTORS
[Public Contract Code Section 4104]
List all Subcontractors who will perform Work or labor or render service to the Contractor in or about the construction of th e Work or
improvement, or a Subcontractor licensed by the State of California who, under subcontract to the Contractor, specially fabricates and installs
a portion of the Work or improvement according to detailed drawings contained in the Plans and Specifications, in an amount in excess of one-
half percent (0.5%) of the Contractor’s total Bid or, in the case of bids or offers for the construction of streets or highwa ys, including bridges, in
excess of one-half percent (0.5%) of the Contractor’s total Bid or $10,000, whichever is greater. If all Subcontractors do not fit on this page,
attach another page listing all information for all other Subcontractors.
Name under which
Subcontractor is Licensed
and Registered
California
Contractor’s License
Number(s) and
Class(es)
California DIR
Contractor
Registration
Number
Address and Phone Number Type of Work
(e.g., Electrical)
Percentage
of Total Bid
(e.g., 10%)1
1 The percentage of the total Bid shall represent the “portion of the work” for the purposes of Public Contract Code Section 4104(b).
C-92
P - 15
Contractor’s INDUSTRIAL SAFETY RECORD FORM
Bidder’s Name _______________________________________
Current
Year of
Record
2021 2020 2019 2018 2017 Total
Number of contracts
Total dollar amount of contracts
(in thousands of dollars)
Number of fatalities
Number of lost workday cases
Number of lost workday cases
involving permanent transfer to
another job or termination of
employment
The above information was compiled from the records that are available to me at this time and I declare under penalty of perjury that
the information is true and accurate within the limitations of those records.
Signature:
Title:
Date:
Signature:
Title:
Date:
C-93
P - 16
BID BOND
KNOW ALL PERSONS BY THESE PRESENTS that:
WHEREAS the (“Public
Agency”), has issued an invitation for bids for the work described as follows:
PEACOCK RIDGE ROAD DRAINAGE IMPROVEMENTS, PROJECT No. 8723
WHEREAS
(Name and address of Bidder)
(“Principal”), desires to submit a bid to Public Agency for the work.
WHEREAS, bidders are required under the provisions of the California Public Contract Code to
furnish a form of bidder’s security with their bid.
NOW, THEREFORE, we, the undersigned Principal, and
(Name and address of Surety)
(“Surety”) a duly admitted surety insurer under the laws of the State of California, as Surety, are
held and firmly bound unto the Public Agency in the penal sum of
Dollars ($ ), being not less than ten percent (10%) of the total bid price, in
lawful money of the United States of America, for the payment of which sum well and truly to be
made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly
and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bounded Principal is
awarded a contract for the work by the Public Agency and, within the time and in the manner
required by the bidding specifications, enters into the written form of contract included with
bidding specifications, furnishes the required bonds, one to guarantee faithful performance and
the other to guarantee payment for labor and materials, and furnishes the required insurance
coverage, then this obligation shall become null and void; otherwise, it shall be and remain in
full force and effect.
In case suit is brought upon this bond, Surety further agrees to pay all court costs incurred by
the Public Agency in the suit and reasonable attorneys’ fees in an amount fixed by the court.
Surety hereby waives the provisions of California Civil Code 2845.
C-94
P - 17
IN WITNESS WHEREOF, this instrument has been duly executed by Principal and Surety, on
the date set forth below, the name of each corporate party being hereto affixed and these
presents duly signed by its undersigned representative(s) pursuant to authority of its governing
body.
Dated:
“Principal”
By:
Its:
By:
Its:
“Surety”
By:
Its:
By:
Its:
(Seal) (Seal)
Note: This bond must be dated, all signatures must be notarized, and evidence of the authority
of any person signing as attorney-in-fact must be attached.
C-95
P - 18
NONCOLLUSION DECLARATION
TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID
[Public Contract Code § 7106]
State of California )
County of ____________ ) ss.
City of _______________ )
The undersigned declares:
I am the ___________________ of ___________________, the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership,
company, association, organization, or corporation. The bid is genuine and not collusive or
sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a
false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or
agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The
bidder has not in any manner, directly or indirectly, sought by agreement, communication, or
conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any
overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements
contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid
price or any breakdown thereof, or the contents thereof, or divulged information or data relative
thereto, to any corporation, partnership, company association, organization, bid depository, or to
any member or agent thereof to effectuate a collusive or sham bid, and has not paid, and will
not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership,
joint venture, limited liability company, limited liability partnership, or any other entity, hereby
represents that he or she has full power to execute, and does execute, this declaration on
behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is
true and correct and that this declaration is executed on ____________________[date], at
_________________________________[city], _____________________[state].
Signature ________________________________
Subscribed and sworn to before me on ________________________________.
(Date)
(Notary Seal) Signature ________________________________
Notary Public
C-96
P - 19
ACKNOWLEDGMENT OF ADDENDA
Bidder’s Name: ____________________________________
The Bidder shall signify receipt of all Addenda here, if any:
Addendum Number Date Received Signature
If there are more Addenda than there is room in the chart above, attach another page
acknowledging receipt of the Addenda.
Signature:
Title:
Date:
C-97
P - 20
This form shall be submitted with the Bid
C-98
C - 1
R6871-0001\1800726v2.doc
CHECKLIST FOR EXECUTION OF
PUBLIC WORKS AGREEMENT
TO BE SUBMITTED BY SUCCESSFUL BIDDER:
Two Executed Notarized Copies of the Agreement (Attached)
Payment Bond in Amount of Contract
Performance Bond in Amount of Contract
Workers Compensation Insurance Certificate in the amount required by law (Attached)
General Liability Insurance Certificate in the Amount of $1 Million, Naming the City as a Co-
insured
Automobile Insurance Certificate in the Amount of $1 Million
General Aggregate Insurance Certificate in the Amount of $2 Million, Naming the City as a Co -
insured
Agreement to Comply with California Labor Law Requirements (Attached)
Business License with the City of Rancho Palos Verdes
Indemnification and Hold Harmless Agreement (Attached)
Additional Insured Endorsement - Comprehensive General Liability (Attached)
Additional Insured Endorsement - Automobile Liability (Attached)
Additional Insured Endorsement - Excess Liability (Attached)
C-99
Project Name/No.: ________________ Contract No.: ______________
Project Manager: ________________ Approved: ______________
01203.0006/993143.2 1
PUBLIC WORKS AGREEMENT
BETWEEN THE CITY OF RANCHO PALOS VERDES AND
__________________________________________
THIS PUBLIC WORKS AGREEMENT (“Agreement”) is made and entered into
__________________, 2024 by and between the City of Rancho Palos Verdes, a California charter
city (“City”) and [NAME OF COMPANY], a [FORM OF COMPANY] (“Contractor”). City and
Contractor may sometimes be referred to herein as a “Party” or collectively as the “Parties.”
RECITALS
A. City has sought, by issuance of an Invitation for Bids, the performance of the
services defined and described particularly in Article 1 of this Agreement.
B. Contractor, following submission of a bid for the performance of the services
defined and described particularly in Article 1 of this Agreement, was selected by the City to
perform those services.
C. Pursuant to the City of Rancho Palos Verdes Municipal Code, City has authority to
enter into and execute this Agreement.
D. The Parties desire to formalize the selection of Contractor for performance of those
services defined and described particularly in Article 1 of this Agreement and desire that the terms
of that performance be as particularly defined and described herein.
AGREEMENT
NOW, THEREFORE, in consideration of the mutual promises and covenants made by the
Parties and contained herein and other consideration, the value and adequacy of which are hereby
acknowledged, the Parties agree as follows:
ARTICLE 1. CONTRACTOR SERVICES
1.1 Scope of Work.
The Contractor shall perform all of the work, furnish all labor, materials, equipment, tools,
utility services, and transportation, and comply with all of the specifications and requirements set
forth in the Bid Documents for the project entitled STORM DRAIN IMPROVEMENTS AT
PEACOCK RIDGE (“Project”), in accordance with the terms and conditions of Agreement
Special Provisions (the “Scope of Work”), which may be referred to herein as the “services” or
“work” hereunder. All such work shall be performed in a good and workmanlike manner, as
reasonably determined by the City, and shall be performed in strict compliance with the Bid
Documents and all local, state, and federal laws and regulations. As used herein, “Bid Documents”
refers to all of the documents included in the solicitation of bids for the Project and Contractor’s
bid proposal(s), including but not limited to, the Notice Inviting Bids, Summary of Work,
Instructions to Bidders, Bid or Bid Proposal, General Provisions, Special Provisions, Plans,
Drawings, and Addenda, and any other documents included, referenced, or incorporated therein.
C-100
-2-
01203.0006/993143.2
The Bid Documents are incorporated into this Agreement. In the event of any conflict or
inconsistency between the terms of the Bid Documents and this Agreement, the terms of this
Agreement shall govern.
1.2 Incorporation of Greenbook.
The provisions 2021 Edition of the Standard Specifications for Public Works Construction
(“Greenbook” including any updates, amendments, or addenda thereto ) are incorporated herein,
except as explicitly modified by the Bid Documents. In the event of any conflict or inconsistency
between the provisions of the Greenbook and this Agreement, the terms of this Agreement shall
govern.
1.3 Compliance with Labor and Wage Laws.
(a) Public Work. The Parties acknowledge that the work to be performed under
this Agreement is a “public work” as defined in Labor Code Section 1720 and that this Agreement
is therefore subject to the requirements of Division 2, Part 7, Chapter 1 (commencing with Section
1720) of the California Labor Code relating to public works contracts and the rules and regulations
established by the Department of Industrial Relations (“DIR”) implementing such statutes. The
work performed under this Agreement is subject to compliance monitoring and enforcement by
the DIR. Contractor shall post job site notices, as prescribed by state law and DIR regulations.
(b) Registration with DIR. Pursuant to Labor Code Section 1771.1, Contractor
and all subcontractors must be registered with, and pay an annual fee to, the DIR prior to and
during the performance of any work under this Agreement. Contractor shall notify the City in
writing immediately, and in no case more than 24 hours, after receiving any information that
Contractor’s or any of its Subcontractors’ DIR registration status has been suspended, revoked,
expired, or otherwise changed.
(c) Prevailing Wages. Contractor shall pay prevailing wages as required by
Labor Code Section 1771. Pursuant to Labor Code Section 1773.2, copies of the prevailing rate of
per diem wages are on file at City Hall and will be made available to any interested party on
request. By initiating any work under this Agreement, Contractor acknowledges receipt of a copy
of the DIR determination of the prevailing rate of per diem wages, and Contractor shall post a copy
of the same at each job site where work is performed under this Agreement. If this Agreement is
subject to the payment of federal prevailing wages under the Davis-Bacon Act (40 U.S.C. § 3141
et seq.), then Contractor shall pay the higher of either the state for federal prevailing wage
applicable to each laborer.
(d) Penalty for Failure to Pay Prevailing Wages. Contractor shall comply with
and be bound by the provisions of Labor Code Sections 1774 and 1775 concerning the payment
of prevailing rates of wages to workers and the penalties for failure to pay prevailing wages. The
Contractor shall, as a penalty to the City, forfeit $200 for each calendar day, or portion thereof, for
each worker paid less than the prevailing rates as determined by the DIR for the work or craft in
which the worker is employed for any public work done pursuant to this Agreement by Contractor
or by any subcontractor.
C-101
-3-
01203.0006/993143.2
(e) Payroll Records. Contractor shall comply with and be bound by the
provisions of Labor Code Section 1776, which requires Contractor and each subcontractor to: keep
accurate payroll records and verify such records in writing under penalty of perjury, as specified
in Section 1776; certify and make such payroll records available for inspection as provided by
Section 1776; and inform the City of the location of the records.
(f) Apprentices. Contractor shall comply with and be bound by the provisions
of Labor Code Sections 1777.5, 1777.6, and 1777.7 and California Code of Regulations Title 8,
Section 200 et seq. concerning the employment of apprentices on public works projects. Contractor
shall be responsible for compliance with these aforementioned Sections for all apprenticeable
occupations. Prior to commencing work under this Agreement, Contractor shall provide City with
a copy of the information submitted to any applicable appr enticeship program. Within 60 days
after concluding work pursuant to this Agreement, Contractor and each of its subcontractors shall
submit to the City a verified statement of the journeyman and apprentice hours performed under
this Agreement.
(g) Eight-Hour Work Day. Contractor acknowledges that 8 hours labor
constitutes a legal day’s work. Contractor shall comply with and be bound by Labor Code Sections
1810 and 1811. As required under Labor Code Section 1812, Contractor and each of its
subcontractors shall keep an accurate record showing the name of and actual hours worked each
calendar day and each calendar week by each worker employed by them in connection with the
work performed under the terms of this Agreement. Failure to comply with these sections of the
Labor Code will subject the Contractor to penalty and forfeiture provisions of the Labor Code
Section 1813.
(h) Penalties for Excess Hours. Contractor shall comply with and be bound by
the provisions of Labor Code Section 1813 concerning penalties for workers who work excess
hours. The Contractor shall, as a penalty to the City, forfeit $25 for each worker employed in the
performance of this Agreement by the Contractor or by any subcontractor for each calendar day
during which such worker is required or permitted to work more than eight 8 hours in any one
calendar day and 40 hours in any one calendar week in violation of the provisions of Division 2,
Part 7, Chapter 1, Article 3 of the Labor Code. Pursuant to Labor Code Section 1815, work
performed by employees of Contractor in excess of 8 hours per day, and 40 hours during any one
week shall be permitted upon public work upon compensation for all hours worked in excess of 8
hours per day at not less than 1.5 times the basic rate of pay.
(i) Workers’ Compensation. California Labor Code Sections 1860 and 3700
provide that every employer will be required to secure the payment of compensation to its
employees if it has employees. In accordance with the provisions of California Labor Code Section
1861, Contractor certifies as follows:
“I am aware of the provisions of Section 3700 of the Labor Code which require
every employer to be insured against liability for workers’ compensation or to
undertake self-insurance in accordance with the provisions of that code, and I will
comply with such provisions before commencing the performance of the work of
this contract.”
C-102
-4-
01203.0006/993143.2
(j) Contractor’s Responsibility for Subcontractors. For every subcontractor
who will perform work under this Agreement, Contractor shall be responsible for such
subcontractor’s compliance with Division 2, Part 7, Chapter 1 (commencing with Section 1720)
of the California Labor Code, and shall make such compliance a requirement in any contract with
any subcontractor for work under this Agreement. Contractor shall be required to take all actions
necessary to enforce such contractual provisions and ensure subcontractor’s compliance, including
without limitation, conducting a review of the certified payroll records of the subcontractor on a
periodic basis or upon becoming aware of the failure of the subcontractor to pay his or her workers
the specified prevailing rate of wages. Contractor shall diligently take corrective action to halt or
rectify any such failure by any subcontractor.
1.4 Licenses, Permits, Fees and Assessments.
Contractor shall obtain at its sole cost and expense such licenses, permits, registrations,
and approvals as may be required by law for the performance of the services required by this
Agreement. Contractor shall have the sole obligation to pay for any fees, assessments and taxes,
plus applicable penalties and interest, which may be imposed by law and arise from or are
necessary for the Contractor’s performance of the services required by this Agreement, and shall
indemnify, defend and hold harmless City, its officers, employees or agents of City, against any
such fees, assessments, taxes, penalties or interest levied, assessed or imposed against City
hereunder.
1.5 Familiarity with Work.
By executing this Agreement, Contractor warrants that Contractor (i) has thoroughly
investigated and considered the Scope of Work to be performed, (ii) has carefully considered how
the services should be performed, and (iii) fully understands the facilities, difficulties and
restrictions attending performance of the services under this Agreement. Contractor warrants that
Contractor has or will investigate the Project site and is or will be fully acquainted with the
conditions there existing, prior to commencement of services hereunder.
1.6 Discovery of Unknown Conditions.
(a) Pursuant to Public Contract Code Section 7104, Contractor shall promptly,
and before the following conditions are disturbed, notify the City, in writing, of any: (i) material
Contractor believes may be hazardous waste as defined in Section 25117 of the Health & Safety
Code required to be removed to a Class I, II, or III disposal site in accordance with existing law;
(ii) subsurface, unknown, or latent physical conditions at the Project site, materially different from
those indicated by information about the Project site made available to bidders prior to the deadline
for submitting bids on the Project; or (iii) unknown physical conditions at the Project site of any
unusual nature, different from those ordinarily encountered and generally recognized as inherent
in work of the character provided for in this Agreement, and will materially affect the performance
of Contractor’s services hereunder.
(b) City shall promptly investigate the conditions, and if it finds that the
conditions do materially differ, or do involve hazardous waste, and cause a decrease or increase in
C-103
-5-
01203.0006/993143.2
Contractor’s cost of, or the time required for, the performance of any part of the work, the City
shall issue a Change Order in accordance with Section 1.11 of this Agreement.
(c) In the event that a dispute arises between City and Contractor whether the
conditions materially differ, or involve hazardous waste, or cause a decrease or increase in
Contractor’s cost of, or time required for, performance of any part of the work, Contractor shall
not be excused from any scheduled completion date set, but shall proceed with all work to be
performed under this Agreement. Contractor shall retain any and all rights provided either by
contract or by law, which pertain to the resolution of disputes and protests between the Parties.
1.7 Unidentified Utilities.
To the extent required by Government Code Section 4215, City will compensate Contractor
for the cost of locating, repairing damage not due to the failure of Contractor to exercise reasonable
care, and removing or relocating utility facilities not identified by City in the Bid Documents with
reasonable accuracy, and for equipment on the Project necessarily idled during such work. Nothing
herein shall be deemed to require City to indicate the presence of existing service laterals or
appurtenances whenever the presence of such utilities on the Project site can be inferred from the
presence of other visible facilities, such as buildings, meters, and junction boxes, on or adjacent to
the Project site of the construction; provided, however, nothing herein shall relieve City from
identifying main or trunklines in the plans and specifications. If Contractor, while performing the
work, discovers utility facilities not identified by City in the plans or specifications, Contractor
shall immediately notify City and the utility in writing. This Agreement is subject to Government
Code Sections 4126 through 4216.9. Contractor must notify utilities and obtain an identification
number before excavation or be subject to liability for damages to subsurface installations.
1.8 Trench Excavation.
Pursuant to Labor Code Section 6705, if this Agreement is for more than $25,000 and
requires the excavation of any trench or trenches five feet or more in depth, Contractor shall
submit, in advance of such excavation, a detailed plan showing the design of shoring, bracing,
sloping, or other provisions to be made for worker protection from the hazard of caving ground
during the excavation of such trench or trenches. The plan shall be reviewed and accepted by the
City, or a registered civil or structural engineer employed by the City to whom authority has been
delegated, prior to the excavation. If the plan varies from the shoring system standards, the plan
shall be prepared by a registered civil or structural engineer. This Section 1.8 shall not be deemed
to allow the use of a shoring, sloping, or protective system less effective than that required by the
Construction Safety Orders (set forth in the California Code of Regulations, Title 8, Subchapter
4). This Section 1.8 shall not be construed to impose tort liability on the City or any of its
employees. Full compensation for sheeting, shoring, bracing, sloping, and all other provisions
required for worker protection shall be considered as included in the contract price shown in the
appropriate Bid item in the Bid Documents, and no additional compensation will be allowed
therefor.
C-104
-6-
01203.0006/993143.2
1.9 Protection and Care of Work and Materials.
The Contractor shall adopt reasonable methods, including providing and maintaining
storage facilities, during the life of this Agreement to furnish continuous protection to the work,
and the equipment, materials, papers, documents, plans, studies and/or other components thereof
to prevent losses or damages, and shall be responsible for all such damages, to persons or property,
until acceptance of the work by City, except such losses or damages as caused by City’s own
negligence. Stored materials shall be reasonably accessible for inspection. Contractor shall not,
without City’s consent, assign, sell, mortgage, hypothecate, or remove equipment or materials
which have been installed or delivered and which may be necessary for the completion of the work.
1.10 Warranty.
Contractor warrants all work under this Agreement (which for purposes of this Section
1.10 shall be deemed to include unauthorized work which has not been removed or corrected and
any non-conforming construction or materials incorporated into the work) to be of good quality
and free from any defective or faulty material and workmanship. Contractor agrees that for a period
of one year (or the period of time specified elsewhere in this Agreement, or the Bid Documents,
or in any guarantee or warranty provided by any manufacturer or supplier of equipment or
materials incorporated into the work, whichever is later) after the date of final acceptance by the
City for the Project, Contractor shall within 10 days after being notified in writing by the City of
any defect in the work or non-conformance of the work to the requirements under this Agreement,
commence and prosecute with due diligence all work necessary to fulfill the terms of the warranty
at its sole cost and expense. Notwithstanding the foregoing, Contractor shall act as soon as
requested by the City in response to any emergency condition or situation. In addition, Contractor
shall, at its sole cost and expense, repair, remove and replace any portions of the work (or work of
its sub-contractors) damaged by its defective work or which becomes damaged in the course of
repairing or replacing defective work. For any work so corrected, Contractor’s obligation
hereunder to correct defective work shall be reinstated for an additional one year period,
commencing with the date of acceptance of such corrected work. Contractor shall perform such
tests as the City may require to verify that any corrective actions, including, without limitation,
redesign, repairs, and replacements comply with the requirements of this Agreement. All costs
associated with such corrective actions and testing, including the removal, replacement, and
reinstitution of equipment and materials necessary to gain access, shall be the sole responsibility
of the Contractor. All warranties and guarantees of subcontractors, suppliers and manufacturers
with respect to any portion of the work, whether express or implied, are deemed to be obtained by
Contractor for the benefit of the City, regardless of whether or not such warranties and guarantees
have been transferred or assigned to the City by separate agreement and Contractor agrees to
enforce such warranties and guarantees, if necessary, on behalf of the City. In the event that
Contractor fails to perform its obligations under this Section, or under any other warranty or
guaranty under this Agreement or the Bid Documents, to the reasonable satisfaction of the City,
the City shall have the right to correct and replace any defective or non -conforming work at
Contractor’s sole expense. Contractor shall be obligated to fully reimburse the City for any
expenses incurred hereunder upon demand.
C-105
-7-
01203.0006/993143.2
1.11 Inspection by City.
In connection with the performance of this Agreement, the City shall have the authority to
enter the worksite at any time for the purpose of identifying the existence of conditions, either
actual or threatened, that may present a danger or hazard to any and all employees. The Contractor
agrees that the City, in its sole authority and discretion, may order the immediate abatement of any
and all conditions that may present an actual or threatened danger or hazard to any and all
employees at the worksite.
The Contractor acknowledges the provisions of Section 6400 of the Labor Code, which
requires that employers shall furnish employment and a place of employment that is safe and
healthful for all employees working therein. In the event the City identifies the existence of any
condition that presents an actual or threatened danger or hazard to any or all employees at the
worksite the City is hereby authorized to order the immediate abatement of that actual or threatened
condition pursuant to this section.
The City may also, at its sole authority and discretion, issue an immediate stop work order
to the Contractor to ensure that no employee working at the worksite is exposed to a dangerous or
hazardous condition. Any stop work order issued by the City to the Contractor in accordance with
the provisions of this section shall not give rise to any claim or cause of action for delay damages
by the Contractor or the Contractor’s agents or subcontractors against the City.
1.12 Additional Work and Change Orders.
(a) City shall have the right at any time during the performance of the services,
without invalidating this Agreement, to order extra work beyond that specified in the Scope of
Work or make changes to the work by altering, adding to or deducting from said work. No such
extra work may be undertaken unless a written change order is first given by the Project Manager
to the Contractor, incorporating therein any adjustment in (i) the Contract Sum (as defined below),
and/or (ii) the time to perform this Agreement, which said adjustments are subject to the written
approval of the Contractor (“Change Order(s)”). All Change Orders must be signed by the
Contractor and Project Manager (or his or her designee) prior to commencing the extra work
thereunder.
(b) Any increase in compensation of up to 10% of the Contract Sum or $25,000,
whichever is less; or any increase in the time to perform of up to one hundred eighty 18035 (thirty
five) days may be approved by the Project Manager, provided that such increase does not
materially affect the work in a detrimental manner or materially and detrimentally affect the
interest of the City. Any greater increases, taken either separately or cumulatively, must be
approved by the City Council.
(c) Any adjustment in the Contract Sum for a Change Order must be in
accordance with the rates set forth in the Contractor’s Bid attached hereto as Exhibit A. If the rates
in the Contractor’s Bid do not cover the type of work in the Change Order, the cost of such work
shall not exceed an amount agreed upon in writing and signed by Contractor and the Project
Manager. If the cost of the Change Order cannot be agreed upon, the City will pay for actual work
of the Change Order that is completed to the satisfaction of the City, as follows:
C-106
-8-
01203.0006/993143.2
(i) Labor: The cost of labor shall be the actual cost for the wages of
workers and subcontractors performing the work for the Change Order at the time such work is
performed. The use of labor classifications that would increase the cost of such work shall not be
permitted.
(ii) Materials and Equipment: The cost of materials and equipment shall
be at cost to Contractor or the lowest current price for which such materials and equipment are
reasonably available at the time the work is performed, whichever is lower.
(iii) Daily Reporting: Contractor must provide a daily report that
includes all invoices for labor, materials and equipment costs for the work under the Change Order.
The daily report must include the following: list of names of workers, classifications, and hours
worked; description and list of quantities of materials used; type of equipment, size, identification
number, and hours of operation, including loading and transportation, if applicable; description of
other City authorized services and expenditures in such detail as the City may require. Failure to
submit a daily report by the close of the next working day may, at the City’s sole and absolute
discretion, waive the Contractor’s rights to payment for the work performed for that day.
(d) It is expressly understood by Contractor that the provisions of this section
shall not apply to services specifically set forth in the Scope of Work. Contractor hereby
acknowledges that it accepts the risk that the services to be provided pursuant to the Scope of Work
may be more costly or time consuming than Contractor anticipates and that Contractor shall not
be entitled to additional compensation therefor. City may in its sole and absolute discretion have
similar work done by other contractors.
(e) No claim for an increase in the Contract Sum or time for performance shall
be valid unless the procedures established in this section are followed.
1.13 Special Requirements.
Additional terms and conditions of this Agreement, if any, which are made a part hereof
are set forth in the “Special Requirements,” attached hereto as Exhibit B and incorporated herein
by this reference. In the event of a conflict between the provisions of Exhibit B and any other
provisions of this Agreement, the provisions of Exhibit B shall govern.
ARTICLE 2. COMPENSATION AND METHOD OF PAYMENT.
2.1 Contract Sum.
Subject to any limitations set forth in this Agreement, City agrees to pay Contractor the
amounts set forth in Contractor’s Bid, attached hereto as Exhibit A and incorporated herein by this
reference. Subject to any additions or deductions that may be made by Change Order (as defined
below) or amendment, and any penalties or damages that may be assessed against Contractor,
Contractor shall receive total compensation, including reimbursement of Contractor’s expenses,
of $________ (_______________ Dollars) (“Contract Sum”) for completion of the work. The
Contract Sum shall constitute full compensation for furnishing all materials and for doing all the
work contemplated and embraced in this Agreement; and also for all loss or damage arising out of
the nature of the work, or from the action of the elements, or from any unforeseen difficulties or
C-107
-9-
01203.0006/993143.2
obstructions which may arise or be encountered in the prosecution of the work until its acceptance
by the City, and for all risks of every description connected with the work; also for all expenses
incurred by or in consequence of the suspension or discontinuance of work and for well and
faithfully completing the work, and the whole thereof, in the manner and according to the plans
and specifications, and the requirements of the Bid Documents and this Agreement.
Compensation shall be made in the form of progress payments and a final payment as
provided in this Section 2 and the Bid Documents.
Compensation may include reimbursement for actual and necessary expenditures for
reproduction costs, telephone expenses, and travel expenses approved by the Project Manager in
advance, or actual subcontractor expenses of an approved subcontractor pursuant to Section 4.5,
and only if specified in Exhibit Athe Contractor’s Bid. The Contract Sum shall include the
attendance of Contractor at all project meetings reasonably deemed necessary by the City.
Coordination of the performance of the work with City is a critical component of the services. If
Contractor is required to attend additional meetings to facilitate such coordination, Contractor shall
not be entitled to any additional compensation for attending said meetings.
2.2 Invoices.
Each month Contractor shall furnish to City an original invoice for all work performed and
expenses incurred during the preceding month in a form approved by City’s Director of Finance.
By submitting an invoice for payment under this Agreement, Contractor is certifying compliance
with all provisions of this Agreement.
All invoices shall include a copy of Contractor’s Certified Payroll and proof that Certified
Payroll has been submitted to the DIR. Contractor shall also submit a list of the prevailing wage
rates (including federal prevailing wage rates, if applicable) for all employees and subcontractors
providing services under this Agreement, as applicable, with Contractor’s first invoice. If these
rates change at any time during the term of this Agreement, Contractor shall submit a new list of
rates to the City with its first invoice following the effective date of the rate change.
2.3 Payment.
City shall independently review each invoice submitted by the Contractor to determine
whether the work performed and expenses incurred are in compliance with the provisions of this
Agreement. Except as to any charges for work performed or expenses incurred by Contractor
which are disputed by City, City will cause Contractor to be paid within 45 days of receipt of
Contractor’s correct and undisputed invoice; however, Contractor acknowledges and agrees that
due to City’s warrant run procedures, the City cannot guarantee that payment will occur within
this time period. In the event that City does not cause Contractor to be paid within 45 (days of
receipt of an undisputed and properly submitted invoice, Contractor shall be entitled to the
payment of interest to the extent allowed under Public Contract Code Section 20104.50. In the
event any charges or expenses are disputed by City, the original invoice shall be returned by City
to Contractor, not later than 7 days after receipt by the City, for correction and resubmission.
Returned invoices shall be accompanied by a document setting forth in writing the reasons why
the payment request was rejected. Review and payment by the City of any invoice provided by the
C-108
-10-
01203.0006/993143.2
Contractor shall not constitute a waiver of any rights or remedies provided herein or any applicable
law (with respect to any defects in the work performed by Contractor, or otherwise).
2.4 Retention.
City will deduct a 5% retention from all progress payments. In accordance with Public
Contract Code Section 22300, which is hereby incorporated into this Agreement, City shall permit
the substitution of securities for any moneys withheld by City to ensure performance under this
Agreement. The retention held by the City shall be released within 60 days after the date of
completion of the work and the Project, as required by Government Code Section 7107. In the
event of a dispute between City and Contractor, City may withhold from the final payment an
amount not to exceed 150% of the disputed amount.
ARTICLE 3. PERFORMANCE SCHEDULE
3.1 Time is of the essence.
If the work is not completed within the Schedule of Performance, liquidated damages shall
apply as set forth below.
3.2 Schedule of Performance.
Contractor shall begin work within 5 (five) days after receiving a Notice to Proceed from
the City and the work shall be completed within the Contractor’s schedule, prepared in
accordance with the Special Provisions, Section A-21consecutive working days from the date on
which Contractor received the Notice to Proceed, or otherwise in accordance with any schedule
contained in or required to be provided by the Bid Documents, and any revisions thereof approved
by the City in writing via change order.
3.3 Force Majeure
The time period(s) specified in the Schedule of Performance for performance of the
services rendered pursuant to this Agreement shall be extended because of any delays due to
unforeseeable causes beyond the control and without the fault or negligence of the Contractor,
including, but not restricted to, acts of God or of the public enemy, unusually severe weather, fires,
earthquakes, floods, epidemics, quarantine restrictions, riots, strikes, freight embargoes, wars,
litigation, and/or acts of any governmental agency, including the City, if the Contractor shall within
10 days of the commencement of such delay notify the Project Manager in writing of the causes
of the delay. The Project Manager shall ascertain the facts and the extent of delay, and extend the
time for performing the services for the period of the enforced delay when and if in the judgment
of the Project Manager such delay is justified. The Project Manager’s determination shall be final
and conclusive upon the parties to this Agreement. In no event shall Contractor be entitled to
recover damages against the City for any delay in the performance of this Agreement, however
caused, Contractor’s sole remedy being extension of the Agreement pursuant to this Section.
C-109
-11-
01203.0006/993143.2
3.4 Liquidated Damages.
Since the determination of actual damages for any delay in performance of this Agreement
would be extremely difficult or impractical to determine in the event of a breach of this Agreement,
the Contractor and its sureties shall be liable for and shall pay to the City the sum of $2,000 as
liquidated damages for each working day of delay in the performance of any service required
hereunder. The City may withhold any accrued liquidated damages from any monies payable on
account of services performed by the Contractor. To the extent required by Government Code
Section 4215, Contractor shall not be assessed liquidated damages for delay in completion of the
work when such delay was caused by the failure of the City or owner of the utility to provide for
removal or relocation of utility facilities.
3.5 Inspection and Final Acceptance.
City may inspect and accept or reject any of Contractor’s work under this Agreement, either
during performance or when completed. If City finds that Contractor’s work does not meet the
requirements and standards provided in the Bid Document, Contractor shall remedy any defects in
the work at Contractor’s sole expense following notice by the City. City shall accept work by a
timely written acceptance, otherwise work shall be deemed to have been rejected. City’s
acceptance shall be conclusive as to such work except with respect to latent defects, fraud and such
gross mistakes as to amount to fraud. Acceptance of any work by City shall not constitute a waiver
of any of the provisions of this Agreement including, but not limited to, Articles 1 and 5, pertaining
to warranty and indemnification and insurance, respectively.
ARTICLE 4. COORDINATION OF WORK
4.1 Representatives and Personnel of Contractor.
The following principals of Contractor (“Principals”) are hereby designated as being the
principals and representatives of Contractor authorized to act on its behalf with respect to the work
specified herein and make all decisions in connection therewith:
________________________ ________________________
(Name) (Title)
________________________ ________________________
(Name) (Title)
________________________ ________________________
(Name) (Title)
It is expressly understood that the experience, knowledge, capability and reputation of the
foregoing Principals were a substantial inducement for City to enter into this Agreement.
Therefore, the Principals shall be responsible during the term of this Agreement for directing all
activities of Contractor and devoting sufficient time to personally supervise the services hereunder.
All personnel of Contractor, and any authorized agents, shall at all times be under the exclusive
direction and control of the Principals. For purposes of this Agreement, the Principals may not be
C-110
-12-
01203.0006/993143.2
replaced nor may their responsibilities be substantially reduced by Contractor without the express
written approval of City. Additionally, Contractor shall make every reasonable effort to maintain
the stability and continuity of Contractor’s staff and subcontractors, if any, assigned to perform
the services required under this Agreement. Contractor shall notify City of any changes in
Contractor’s staff and subcontractors, if any, assigned to perform the services required under this
Agreement, prior to and during any such performance.
4.2 Status of Contractor.
Contractor shall have no authority to bind City in any manner, or to incur any obligation,
debt or liability of any kind on behalf of or against City, whether by contract or otherwise, unless
such authority is expressly conferred under this Agreement or is otherwise expressly conferred in
writing by City. Contractor shall not at any time or in any manner represent that Contractor or any
of Contractor’s officers, employees, or agents are in any manner officials, officers, employees or
agents of City. Neither Contractor, nor any of Contractor’s officers, employees or agents, shall
obtain any rights to retirement, health care or any other benefits which may otherwise accrue to
City’s employees. Contractor expressly waives any claim Contractor may have to any such rights.
4.3 Project Manager.
The “Project Manager” for the City shall be David Copp, Deputy Director of Public
Works, or any other person as may be designated by the Director of Public Works. It shall be the
Contractor’s responsibility to assure that the Project Manager is kept informed of the progress of
the performance of the services and the Contractor shall refer any decisions which must be made
by City to the Project Manager. Unless otherwise specified herein, any approval of City required
hereunder shall mean the approval of the Project Manager. The Project Manager shall have
authority, if specified in writing by the City Manager or his/her designee, to sign all documents on
behalf of the City required hereunder to carry out the terms of this Agreement.
4.4 Independent Contractor.
Neither the City nor any of its employees shall have any control over the manner, mode or
means by which Contractor, its agents or employees, perform the services required herein, except
as otherwise set forth herein. City shall have no voice in, or authority over, the selection, discharge,
supervision or control of Contractor’s employees, servants, representatives or agents, or in fixing
their number, compensation or hours of service. Contractor shall perform all services required
herein as an independent contractor of City and shall remain at all times as to City a wholly
independent contractor with only such obligations as are consistent with that role. Contractor shall
not at any time or in any manner represent that it or any of its agents or employees are agents or
employees of City. City shall not in any way or for any purpose become or be deemed to be a
partner of Contractor in its business or otherwise or a joint venturer or a member of any joint
enterprise with Contractor.
4.5 Prohibition Against Subcontracting or Assignment.
The experience, knowledge, capability and reputation of Contractor, its principals and
employees were a substantial inducement for the City to enter into this Agreement. Therefore,
Contractor shall not contract with any other entity to perform in whole or in part the services
C-111
-13-
01203.0006/993143.2
required hereunder without the express written approval of the City. All subcontractors shall
obtain, at its or Contractor’s expense, such licenses, permits, registrations and approvals (including
from the City) as may be required by law for the performance of any services or work under this
Agreement. In addition, neither this Agreement nor any interest herein may be transferred,
assigned, conveyed, hypothecated or encumbered voluntarily or by operation of law, whether for
the benefit of creditors or otherwise, without the prior written approval of City. Transfers restricted
hereunder shall include the transfer to any person or group of persons acting in concert of more
than 25% of the present ownership and/or control of Contractor, taking all transfers into account
on a cumulative basis. This limitation shall not apply to assignments to any company that is a
subsidiary or parent company of Contractor. In the event of any such unapproved transfer,
including any bankruptcy proceeding, this Agreement shall be void. No approved transfer shall
release the Contractor or any surety of Contractor of any liability hereunder without the express
consent of City.
ARTICLE 5. INSURANCE, INDEMNIFICATION AND BONDS
5.1 Insurance Coverages.
Without limiting Contractor’s indemnification obligation to the City (as set forth below),
and prior to commencement of any services under this Agreement, Contractor shall obtain, provide
and maintain at its own expense during the term of this Agreement, policies of insurance of the
type and amounts described below and in a form satisfactory to City.
(a) General liability insurance. Contractor shall maintain commercial general
liability insurance with coverage at least as broad as Insurance Services Office form CG 00 01, in
an amount not less than $2,000,000$1,000,000 per occurrence, $4,000,000$2,000,000 general
aggregate, for bodily injury, personal injury, and property damage. The policy must include
contractual liability that has not been amended. Any endorsement restricting standard ISO “insured
contract” language will not be accepted. The Product and Completed Operations coverage under
the policy shall extend a minimum of three years after completion of the Project. Coverage shall
be included on behalf of the insured for covered claims arising out of the actions of independent
contractors. If the insured is using subcontractors, the policy must include work performed “by or
on behalf” of the insured. The policy shall contain no language that would invalidate or remove
the insurer’s duty to defend or indemnify for claims or suits expressly excluded from coverage.
The policy shall specifically provide for a duty to defend on the part of the insurer.
(b) Automobile liability insurance. Contractor shall maintain automobile
insurance at least as broad as Insurance Services Office form CA 00 01 covering bodily injury and
property damage for all activities of the Contractor arising out of or in connection with Services
to be performed under this Agreement, including coverage for any owned, hired, non-owned or
rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident.
(c) Professional liability (errors & omissions) insurance. Contractor shall
maintain professional liability insurance that covers the services to be performed in connection
with this Agreement, in the minimum amount of $1,000,000 per claim and in the aggregate. Any
policy inception date, continuity date, or retroactive date must be before the effective date of this
C-112
-14-
01203.0006/993143.2
Agreement and Contractor agrees to maintain continuous coverage through a period no less than
three (3) years after completion of the services required by this Agreement.
(d) Workers’ compensation insurance. Contractor shall maintain Workers’
Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance (with limits of at
least $1,000,000).
(e) Builder’s Risk Insurance. Contractor shall maintain Builder’s Risk (Course
of Construction) insurance utilizing an “All Risk” (Special Perils) coverage form, with limits equal
to the completed value of the Project and no coinsurance penalty provisions or provisional limit
provisions. The policy must include: (1) coverage for any ensuing loss from faulty workmanship,
nonconforming work, omission or deficiency in design or specifications; (2) coverage against
machinery accidents and operational testing; (3) coverage for removal of debris, and insuring the
buildings, structures, machinery, equipment, materials, facilities, fixtures and all other properties
constituting a part of the Project; (4) ordinance or law coverage for contingent rebuilding,
demolition, and increased costs of construction; (5) transit coverage (unless insured by the supplier
or receiving contractor), with sub-limits sufficient to insure the full replacement value of any key
equipment item; (6) ocean marine cargo coverage insuring any Project materials or supplies, if
applicable; (7) coverage with sub-limits sufficient to insure the full replacement value of any
property or equipment stored either on or off the Project site or any staging area.
(f) Pollution Liability Insurance. Contractor shall maintain Environmental
Impairment Liability insurance, written on a Contractor’s Pollution Liability form or other form
acceptable to City providing coverage for liability arising out of sudden, accidental, and gradual
pollution and remediation. The policy limit shall be no less than $1,000,000 per claim and in the
aggregate. All activities contemplated in this Agreement shall be specifically scheduled on the
policy as “covered operations.” The policy shall provide coverage for the hauling of waste from
the Project site to the final disposal location, including non-owned disposal sites.
5.2 General Insurance Requirements.
(a) Subcontractors. Contractor shall include all subcontractors as insureds
under its policies or shall furnish separate certificates and certified endorsements for each
subcontractor. All coverages for subcontractors shall include all of the requirements stated herein.
(b) Proof of Insurance. Contractor shall provide certificates of insurance to City
as evidence of the insurance coverage required herein, along with a waiver of subrogation
endorsement for workers’ compensation. Insurance certificates and endorsements must be
approved by City’s Risk Manager prior to commencement of performance. Current certification
of insurance shall be kept on file with City at all times during the term of this Agreement. City
reserves the right to require complete, certified copies of all required insurance policies, at any
time.
(c) Duration of Coverage. Contractor shall procure and maintain for the
duration of this Agreement insurance against claims for injuries to persons or damages to property,
which may arise from or in connection with the performance of the services hereunder by
Contractor, its agents, representatives, employees or subcontractors.
C-113
-15-
01203.0006/993143.2
(d) Products/completed operations coverage. Products/completed operations
coverage shall extend a minimum of three (3)one (1) year(s) after project completion. Coverage
shall be included on behalf of the insured for covered claims arising out of the actions of
independent contractors. If the insured is using subcontractors, the Policy must include work
performed “by or on behalf” of the insured. Policy shall contain no language that would invalidate
or remove the insurer’s duty to defend or indemnify for claims or suits expressly excluded from
coverage. Policy shall specifically provide for a duty to defend on the part of the insurer. The City,
its officials, officers, agents, and employees, shall be included as additional insureds under the
Products and Completed Operations coverage.
(e) Primary/noncontributing. Coverage provided by Contractor shall be
primary and any insurance or self-insurance procured or maintained by City shall not be required
to contribute with it. The limits of insurance required herein may be satisfied by a combination of
primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be
endorsed to contain a provision that such coverage shall also apply on a primary and non-
contributory basis for the benefit of City before the City’s own insurance or self-insurance shall
be called upon to protect it as a named insured.
(f) City’s Rights of Enforcement. In the event any policy of insurance required
under this Agreement does not comply with these specifications or is canceled and not replaced,
City has the right but not the duty to obtain the insurance it deems necessary, and any premium
paid by City will be promptly reimbursed by Contractor or City will withhold amounts sufficient
to pay the premium from any payments due to the Contractor. In the alternative, City may cancel
this Agreement.
(g) Waiver of Subrogation. All insurance coverage maintained or procured
pursuant to this agreement shall be endorsed to waive subrogation against City, its elected or
appointed officers, agents, officials, employees and volunteers or shall specifically allow
Contractor or others providing insurance evidence in compliance with these specifications to waive
their right of recovery prior to a loss. Contractor hereby waives its own right of recovery against
City, and shall require similar written express waivers and insurance clauses from each of its
subcontractors.
(h) Enforcement of Contract Provisions (non-estoppel). Contractor
acknowledges and agrees that any actual or alleged failure on the part of the City to inform
Contractor of non-compliance with any requirement imposes no additional obligations on the City
nor does it waive any rights hereunder.
(i) Requirements Not Limiting. Requirements of specific coverage features or
limits contained in this Section are not intended as a limitation on coverage, limits or other
requirements, or a waiver of any coverage normally provided by any insurance. Specific reference
to a given coverage feature is for purposes of clarification only as it pertains to a given issue and
is not intended by any Party or insured to be all inclusive, or to the exclusion of other coverage, or
a waiver of any type. If the Contractor maintains higher limits than the minimums shown above,
the City requires and shall be entitled to coverage for the higher limits maintained by the
Contractor. Any available insurance proceeds in excess of the specified minimum limits of
insurance and coverage shall be available to the City.
C-114
-16-
01203.0006/993143.2
(j) Notice of Cancellation. Contractor agrees to oblige its insurance agent or
broker and insurers to provide to City with a 30 day notice of cancellation (except for nonpayment
for which a 10 day notice is required) or nonrenewal of coverage for each required coverage.
(k) Additional Insured Status. General liability policies shall provide or be
endorsed to provide that City and its officers, officials, employees, and agents, and volunteers shall
be additional insureds under such policies. This provision shall also apply to any excess/umbrella
liability policies.
(l) Prohibition of Undisclosed Coverage Limitations. None of the coverages
required herein will be in compliance with these requirements if they include any limiting
endorsement of any kind that has not been first submitted to City and approved of in writing.
(m) Separation of Insureds. A severability of interests provision must apply for
all additional insureds ensuring that Contractor’s insurance shall apply separately to each insured
against whom claim is made or suit is brought, except with respect to the insurer’s limits of
liability. The policy(ies) shall not contain any cross-liability exclusions.
(n) Pass Through Clause. Contractor agrees to ensure that its subconsultants,
subcontractors, and any other party involved with the Project who is brought onto or involved in
the Project by Contractor, provide the same minimum insurance coverage and endorsements
required of Contractor. Contractor agrees to monitor and review all such coverage and assumes all
responsibility for ensuring that such coverage is provided in conformity with the requirements of
this Section. Contractor agrees that upon request, all agreements with consultants, subcontractors,
and others engaged in the Project will be submitted to City for review.
(o) Agency’s Right to Revise Specifications. The City reserves the right at any
time during the term of this Agreement to change the amounts and types of insurance required by
giving the Contractor 90 days advance written notice of such change. If such change results in
substantial additional cost to the Contractor, the City and Contractor may renegotiate Contractor’s
compensation.
(p) Self-Insured Retentions. Any self-insured retentions must be declared to
and approved by City. City reserves the right to require that self-insured retentions be eliminated,
lowered, or replaced by a deductible. Self-insurance will not be considered to comply with these
specifications unless approved by City.
(q) Timely Notice of Claims. Contractor shall give City prompt and timely
notice of claims made or suits instituted that arise out of or result from Contractor’s performance
under this Agreement, and that involve or may involve coverage under any of the required liability
policies.
(r) Additional Insurance. Contractor shall also procure and maintain, at its own
cost and expense, any additional kinds of insurance, which in its own judgment may be necessary
for its proper protection and prosecution of the work.
C-115
-17-
01203.0006/993143.2
5.3 Indemnification.
Contractor shall indemnify, defend with legal counsel approved by City, and hold harmless
City, its officers, officials, employees, agents, representatives, and volunteers (collectively,
“Indemnitees”) from and against all liability, loss, damage, expense, cost (including, without
limitation, reasonable legal counsel fees, expert fees and all other costs and fees of litigation) of
every nature arising out of or in connection with Contractor’s (or its employees’, officers’, agents’,
or subcontractors’; collectively, “Contractor”) performance of the work hereunder or its failure to
comply with any of its obligations contained in this Agreement, including any injuries to or death
of any person (including, but not limited to, workers and the public), or damage to property
resulting from the construction of the work or by or in consequence of any negligence regarding
the work, use of improper materials or equipment in construction of the work, neglect or refusal
of Contractor to faithfully perform the work and all of Contractor’s obligations under this
Agreement, or by or on account of any act or omission by the Contractor during the progress of
the work or at any time before the completion and final acceptance of the Project by the City,
except with respect to any loss or damage which is caused by the sole or active negligence or
willful misconduct of the Indemnitees as determined by a court of competent jurisdiction. Should
conflict of interest principles preclude a single legal counsel from representing both City and
Contractor, or should City otherwise find Contractor’s legal counsel unacceptable, then Contractor
shall reimburse the City its costs of defense, including, without limitation, reasonable attorneys’
fees, expert fees and all other costs and fees of litigation. Contractor shall promptly pay any final
judgment rendered against the Indemnitees with respect to claims determined by a trier of fact to
have been the result of the Contractor’s negligent, reckless or wrongful performance. It is expressly
understood and agreed that the foregoing provisions are intended to be as broad and inclusive as
is permitted by the law of the State of California and will survive termination of this Agreement.
Contractor’s obligations under this section apply regardless of whether or not such claim,
charge, damage, demand, action, proceeding, loss, stop notice, cost, expense, judgment, civil fine
or penalty, or liability was caused in part or contributed to by the City or any Indemnitees. In
instances where City or its Indemnitees is shown to have been actively negligent and where City’s
active negligence accounts for only a percentage of the liability involved, the obligation of
Contractor will be for that entire portion or percentage of liability not attributable to the active
negligence of the City.
Contractor shall ensure that the performance of any work hereunder is done in compliance
with all applicable state, local and federal rules, laws and regulations related to accessibility and
reasonable accommodations and modifications for persons with disabilities, including but not
limited to the Americans with Disabilities Act as amended, 42 U.S.C. § 12101 et seq., and its
implementing regulations at 28 C.F.R. Parts 35 and 36 (ADA), and § 504 of the Rehabilitation Act
of 1973, as amended, and as applicable, 29 U.S.C. 701 and the implementing regulations at 24
C.F.R. Parts 8, the Fair Housing Act as amended, 42 U.S.C. 3601, et seq. and its implementing
regulations at 24 CFR Parts 100, the Fair Employment and Housing Act, California Government
Code § 12926, Title 24 of the California Building Code, and any requirements of the City.
Contractor hereby agrees to indemnify, defend, and hold City and all City Representatives free
and harmless against any and all Losses and Liabilities arising from its failure to perform any work
hereunder in accordance with all applicable disability access requirements and requirements under
the Americans with Disability Act and its implementing regulations.
C-116
-18-
01203.0006/993143.2
5.4 Notification of Third-Party Claims.
City shall timely notify Contractor of the receipt of any third-party claim relating to the
work under this Agreement. City shall be entitled to recover from Contractor its reasonable costs
incurred in providing such notification.
5.5 Performance, Labor, and Warranty Bonds.
Concurrently with execution of this Agreement, Contractor shall deliver to the City the
following bonds in the form required under the Bid Documents or otherwise by the City Clerk:
(a) A performance bond securing the faithful performance of this Agreement,
in an amount not less than 100% of the Contract Sum, as stated in Section 2.1 (“Performance
Bond”).
(b) A labor and materials bond, securing the payment of all persons furnishing
labor and/or materials in connection with the work under this Agreement, in an amount not less
than 100% of the Contract Sum, as stated in Section 2.1 (“Payment Bond”).
(c) A warranty bond, guaranteeing the Contractor’s warranty under Section
1.10 of this Agreement, in an amount not less than ___% of the total compensation for this
Agreement, as stated in Section 2.1.
(d) Bonds for all work involving an expenditure in excess of $25,000 shall not
be waived, in accordance with Section 9550 and 9552 of the Civil Code.
The bonds shall each contain the original notarized signature of an authorized officer of
the surety and affixed thereto shall be a certified and current copy of his/her power of attorney.
The bonds shall be unconditional and remain in force during the entire term of this Agreement.
City shall release the Performance Bond and Payment Bond when the following have
occurred: (a) Contractor has made a written request for release and provided evidence of
satisfaction of all other requirements under Article 5 of this Agreement, (b) the work for the Project
has be finally accepted by the City, and (c) after passage of the time within which lien claims are
required to be made pursuant to applicable laws; if lien claims have been timely filed, City shall
hold the Payment Bond until such claims have been resolved, Contractor has provided statutory
bond, or otherwise as required by applicable law.
5.6 Sufficiency of Insurer or Surety.
Insurance and bonds required by this Agreement shall be satisfactory only if issued by
companies qualified to do business in California, rated “A” or higher in the most recent edition of
Best’s Rating Guide, The Key Rating Guide or in the Federal Register, and only if they are of a
financial category Class VII or larger, unless otherwise approved by the City’s Risk Manager due
to unique circumstances. In addition, the insurance carrier must be currently authorized by the
Insurance Commissioner to transact business of insurance or be on the List of Approved Surplus
Line Insurers issued by the State of California. If the City determines that the work to be performed
under this Agreement creates an increased or decreased risk of loss to the City, the Contractor
C-117
-19-
01203.0006/993143.2
agrees that the minimum limits of the insurance policies and the bonds required in Section 5.5 may
be changed accordingly upon receipt of written notice from the City.
ARTICLE 6. RECORDS, REPORTS, AND RELEASE OF INFORMATION
6.1 Records.
Contractor shall keep, and require subcontractors to keep, such ledgers, books of accounts,
invoices, vouchers, canceled checks, reports, studies, certified and accurate copies of payroll
records in compliance with all applicable laws, or other documents relating to the disbursements
charged to City and services performed hereunder (the “books and records”), as shall be
necessary to perform the services required by this Agreement and enable the Project Manager to
evaluate the performance of such services. Any and all such documents shall be maintained in
accordance with generally accepted accounting principles and shall be complete and detailed. The
Project Manager shall have full and free access to such books and records at all times during
normal business hours of City, including the right to inspect, copy, audit and make records and
transcripts from such records. Such records shall be maintained for a period of 3 years following
completion of the services hereunder, and the City shall have access to such r ecords in the event
any audit is required. In the event of dissolution of Contractor’s business, custody of the books
and records may be given to City, and access shall be provided by Contractor’s successor in
interest. Notwithstanding the above, the Contractor shall fully cooperate with the City in providing
access to the books and records if a public records request is made and disclosure is required by
law including but not limited to the California Public Records Act.
6.2 Reports.
Contractor shall periodically prepare and submit to the Project Manager such reports
concerning the performance of the services required by this Agreement as the Project Manager
shall require. Contractor hereby acknowledges that the City is greatly concerned about the cost of
work and services to be performed pursuant to this Agreement. For this reason, Contractor agrees
that if Contractor becomes aware of any facts, circumstances, techniques, or events that may or
will materially increase or decrease the cost of the work or services contemplated herein,
Contractor shall promptly notify the Project Manager of said fact, circumstance, technique or event
and the estimated increased or decreased cost(s) related thereto.
6.3 Ownership of Documents.
All drawings, specifications, maps, designs, photographs, studies, surveys, data, notes,
computer files, reports, records, documents and other materials (the “documents and materials”)
prepared by Contractor, its employees, subcontractors and agents in the performance of this
Agreement shall be the property of the City and shall be delivered to the City upon request of the
Project Manager or upon the termination of this Agreement, and Contractor shall have no claim
for further employment or additional compensation as a result of the exercise by City of its full
rights of ownership use, reuse, or assignment of the documents and materials. Any use, reuse or
assignment of such completed documents for other projects and/or use of uncompleted documents
without specific written authorization by the Contractor will be at the City’s sole risk and without
liability to Contractor, and Contractor’s guarantee and warranties shall not extend to such use,
C-118
-20-
01203.0006/993143.2
reuse or assignment. Contractor may retain copies of such documents for its own use. Contractor
shall have an unrestricted right to use the concepts embodied therein. All subcontractors shall
provide for assignment to City of any documents or materials prepared by them, and in the event
Contractor fails to secure such assignment, Contractor shall indemnify City for all damages
resulting therefrom. Moreover, Contractor with respect to any documents and materials that may
qualify as “works made for hire” as defined in 17 U.S.C. § 101, such documents and materials are
hereby deemed “works made for hire” for the City.
6.4 Confidentiality and Release of Information.
(a) Information gained or work product produced by Contractor in its
performance of this Agreement shall be considered confidential, unless such information is in the
public domain or already known to Contractor. Contractor shall not release or disclose any such
information or work product to persons or entities other than City without prior written
authorization from the Project Manager.
(b) Contractor, its officers, employees, agents or subcontractors, shall not,
without prior written authorization from the Project Manager or unless requested by the City
Attorney, voluntarily provide documents, declarations, letters of support, testimony at depositions,
response to interrogatories or other information concerning the work performed under this
Agreement. Response to a subpoena or court order shall not be considered “voluntary” provided
Contractor gives City notice of such court order or subpoena.
(c) If Contractor, or any officer, employee, agent or subcontractor of
Contractor, provides any information or work product in violation of this Agreement, then City
shall have the right to reimbursement and indemnity from Contractor for any damages, costs and
fees, including attorneys’ fees, caused by or incurred as a result of Contractor’s conduct.
(d) Contractor shall promptly notify City should Contractor, its officers,
employees, agents or subcontractors be served with any summons, complaint, subpoena, notice of
deposition, request for documents, interrogatories, request for admissions or other discovery
request, court order or subpoena from any party regarding this Agreement and the work performed
with respect to the Project. City retains the right, but has no obligation, to represent Contractor or
be present at any deposition, hearing or similar proceeding. Contractor agrees to cooperate fully
with City and to provide City with the opportunity to review any response to discovery requests
provided by Contractor. However, this right to review any such response does not imply or mean
the right by City to control, direct, or rewrite said response.
ARTICLE 7. ENFORCEMENT OF AGREEMENT AND TERMINATION
7.1 California Law.
This Agreement shall be interpreted, construed and governed both as to validity and to
performance of the Parties in accordance with the laws of the State of California. Legal actions
concerning any dispute, claim or matter arising out of or in relation to this Agreement shall be
instituted in the Superior Court of the County of Los Angeles, State of California, or any other
appropriate court in such county, and Contractor covenants and agrees to submit to the personal
jurisdiction of such court in the event of such action. In the event of litigation in a U.S. District
C-119
-21-
01203.0006/993143.2
Court, venue shall lie exclusively in the Central District of California, in the County of Los
Angeles, State of California.
7.2 Termination.
This Agreement may be terminated in accordance with Sections 6-7 and 6-8 of the
Greenbook.
7.3 Dispute Resolution Process.
Section 20104 et seq. of the California Public Contract Code prescribes a process utilizing
informal conferences, non-binding judicial-supervised mediation, and judicial arbitration to
resolve disputes on construction claims of $375,000 or less. Additionally, Section 9204 of the
Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on
construction claims. The intent of this Section is to implement Sections 20104 et seq. and Section
9204 of the California Public Contract Code. This Section shall be construed to be consistent with
said statutes.
For purposes of these procedures, “claim” means a separate demand by the Contractor,
after the City has denied Contractor’s timely and duly made request for payment for ext ra work
and/or a time extension, for (A) a time extension, (B) payment of money or damages arising from
work done by or on behalf of the Contractor pursuant to this Agreement and payment of which is
not otherwise expressly provided for or the Contractor is not otherwise entitled to, or (C) an amount
the payment of which is disputed by the City.
The following requirements apply to all claims to which this Section applies:
(a) Claim Submittal. The claim shall be in writing and include the documents
necessary to substantiate the claim. Claims governed by this procedure must be filed on or before
the date of final payment. Nothing in this Section is intended to extend the time limit or supersede
notice requirements otherwise provided in this Agreement for the filing of claims, including all
requirements pertaining to compensation or payment for extra work, disputed work, and/or
changed conditions. Failure to follow such contractual requirements shall bar any claims or
subsequent lawsuits for compensation or payment thereon.
(b) Supporting Documentation. The Contractor shall submit all claims in the
following format:
(i) Summary of the claim, including references to the specific Bid
Document provisions or provisions under this Agreement upon which the claim is based.
(ii) List of documents relating to claim: (a) Specifications, (b)
Drawings, (c) Clarifications (Requests for Information), (d) Schedules, and (e) Other.
(iii) Chronology of events and correspondence related to the claim.
(iv) Statement of grounds for the claim.
C-120
-22-
01203.0006/993143.2
(v) Analysis of the claim’s cost, if any.
(vi) Analysis of the claim’s time/schedule impact, if any.
(c) City’s Response. Upon receipt of a claim pursuant to this Section, City shall
conduct a reasonable review of the claim and, within a period not to exceed 45 days, shall provide
the Contractor a written statement identifying what portion of the claim is disputed and what
portion is undisputed. Any payment due on an undisputed portion of the claim will be processed
and made within 60 days after the City issues its written statement.
(i) If the City needs approval from the City Council to provide the
Contractor a written statement identifying the disputed portion and the undisputed portion of the
claim, and the City Council does not meet within the 45 days or within the mutually agreed to
extension of time following receipt of a claim sent by registered mail or certified mail, return
receipt requested, the City shall have up to three days following the next duly publicly noticed
meeting of the City Council after the 45-day period, or extension, expires to provide the Contractor
a written statement identifying the disputed portion and the undisputed portion.
(ii) Within 30 days of receipt of a claim, the City may request in writing
additional documentation supporting the claim or relating to defenses or claims the City may have
against the Contractor. If additional information is thereafter required, it shall be requested and
provided pursuant to this subdivision, upon mutual agreement of City and the Contractor.
(iii) The City’s written response to the claim, as further documented,
shall be submitted to the Contractor within 30 days (if the claim is less than $50,000, within 15
days) after receipt of the further documentation, or within a period of time no greater than that
taken by the Contractor in producing the additional information or requested documentation,
whichever is greater.
(d) Meet and Confer. If the Contractor disputes the City’s written response, or
the City fails to respond within the time prescribed, the Contractor may so notify the City, in
writing, either within 15 days of receipt of the City’s response or within 15 days of the City’s
failure to respond within the time prescribed, respectively, and demand an informal conference to
meet and confer for settlement of the issues in dispute. Upon receipt of a demand, the City shall
schedule a meet and confer conference within 30 days for settlement of the dispute.
(e) Mediation. Within 10 business days following the conclusion of the meet
and confer conference, if the claim or any portion of the claim remains in dispute, the City shall
provide the Contractor a written statement identifying the portion of the claim that remains in
dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim
shall be processed and made within 60 days after the City issues its written statement. Any disputed
portion of the claim, as identified by the contractor in writing, shall be submitted to nonbinding
mediation, with the City and the Contractor sharing the associated costs equally. The City and
Contractor shall mutually agree to a mediator within 10 business days after the disputed portion of
the claim has been identified in writing, unless the Parties agree to select a mediator at a later time.
(i) If the Parties cannot agree upon a mediator, each Party shall select a
mediator and those mediators shall select a qualified neutral third party to mediate with regard to
C-121
-23-
01203.0006/993143.2
the disputed portion of the claim. Each Party shall bear the fees and costs charged by its respective
mediator in connection with the selection of the neutral mediator.
(ii) For purposes of this section, mediation includes any nonbinding
process, including, but not limited to, neutral evaluation or a dispute review board, in which an
independent third party or board assists the Parties in dispute resolution through negotiation or by
issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this Section.
(iii) Unless otherwise agreed to by the City and the Contractor in writing,
the mediation conducted pursuant to this Section shall excuse any further obligation under Public
Contract Code Section 20104.4 to mediate after litigation has been commenced.
(iv) All unresolved claims shall be considered jointly in a single
mediation, unless a new unrelated claim arises after mediation is completed.
(f) City’s Responses. The City’s failure to respond to a claim from the
Contractor within the time periods described in this Section or to otherwise meet the time
requirements of this Section shall result in the claim being deemed rejected in its entirety. A claim
that is denied by reason of the City’s failure to have responded to a claim, or its failure to otherwise
meet the time requirements of this Section, shall not constitute and adverse finding with regard to
the merits of the claim or the responsibility of qualifications of the Contractor. City’s failure to
respond shall not waive City’s rights to any subsequent procedures for the resolution of disputed
claims.
(g) Government Code Claims. If following the mediation, the claim or any
portion remains in dispute, the Contractor must comply with the claim procedures set forth in
Government Code Section 900 et seq. prior to filing any lawsuit against the City. Such Government
Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited
to those matters that remain unresolved after all procedures pertaining to extra work, disputed
work, construction claims, and/or changed conditions, including any required mediation, have
been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite
contractual requirements are not satisfied, no action against the City may be filed. A Government
Code claim must be filed no earlier than the date that Contractor completes all contractual
prerequisites to filing a Government Code claim, including any required mediation. A Government
Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the
Government Code claim is submitted. For purposes of Government Code Section 900 et seq., the
running of the period of time within which a claim must be filed shall be tolled from the time the
Contractor submits his or her written claim to the City until the time the claim is denied, including
any period of time utilized by the meet and confer conference or mediation that does not result in
a complete resolutions of all claims.
(h) Civil Actions for Claims of $375,000 or Less. The following procedures are
established for all civil actions filed to resolve claims totaling $375,000 or less:
(i) Within 60 days, but no earlier than 30 days, following the filing or
responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by
mutual stipulation of both Parties or unless mediation was held prior to commencement of the
C-122
-24-
01203.0006/993143.2
action in accordance with Public Contract Code Section 9204 and the procedures in this Section.
The mediation process shall provide for the selection within 15 days by both Parties of a
disinterested third person as mediator, shall be commenced within 30 days of the submittal, and
shall be concluded within 15 days from the commencement of the mediation unless a time
requirement is extended upon a good cause showing to the court.
(ii) If the matter remains in dispute, the case shall be submitted to
judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part
3 of the Code of Civil Procedure, notwithstanding Section 1141.11 of that code. The Civil
Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part
4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision
consistent with the rules pertaining to judicial arbitration.
(iii) Upon stipulation of the Parties, arbitrators appointed for these
purposes shall be experienced in construction law, and, upon stipulation of the Parties, mediators
and arbitrators shall be paid necessary and reasonable hourly rates of pay not to exceed their
customary rate, and such fees and expenses shall be paid equally by the Parties, except in the case
of arbitration where the arbitrator, for good cause, determines a different division.
(iv) In addition to Chapter 2.5 (commencing with Section 1141.10) of
Title 3 of Part 3 of the Code of Civil Procedure, any Party who after receiving an arbitration award
requests a trial de novo but does not obtain a more favorable judgment shall, in addition to payment
of costs and fees under that chapter, pay the reasonable attorneys’ fees of the other Party arising
out of the trial de novo.
7.4 Waiver.
Waiver by any Party to this Agreement of any term, condition, or covenant of this
Agreement shall not constitute a waiver of any other term, condition, or covenant. Waiver by any
Party of any breach of the provisions of this Agreement shall not constitute a waiver of any other
provision or a waiver of any subsequent breach or violation of any provision of this Agreement.
Acceptance by City of any work or services by Contractor shall not constitute a waiver of any of
the provisions of this Agreement. No delay or omission in the exercise of any right or remedy by
a non-defaulting party on any default shall impair such right or remedy or be construed as a waiver.
Any waiver by either Party of any default must be in writing and shall not be a waiver of any other
default concerning the same or any other provision of this Agreement.
7.5 Rights and Remedies Are Cumulative.
Except with respect to rights and remedies expressly declared to be exclusive in this
Agreement, the rights and remedies of the Parties are cumulative and the exercise by either Party
of one or more of such rights or remedies shall not preclude the exercise by it, at the same or
different times, of any other rights or remedies for the same default or any other default by the
other Party.
C-123
-25-
01203.0006/993143.2
7.6 Unfair Business Practices Claims.
Pursuant to Public Contract Code Section 7103.5, in entering into this Agreement,
Contractor offers and agrees to assign to the City all rights, title, and interest in and to all causes
of action it may have under Section 4 of the Clayton Act (15 U.S.C. § 15) or under the Cartwright
Act (Chapter 2, (commencing with Section 16700) of Part 2 of Division 7 of the Business and
Professions Code), arising from purchases of goods, services or materials related to this
Agreement. This assignment shall be made and become effective at the time the City tenders final
payment to the Contractor without further acknowledgment by the Parties.
ARTICLE 8. CITY OFFICERS AND EMPLOYEES: NON-DISCRIMINATION
8.1 Non-liability of City Officers and Employees.
No officer or employee of the City shall be personally liable to the Contractor, or any
successor in interest, in the event of any default or breach by the City or for any amount which
may become due to the Contractor or to its successor, or for breach of any obligation of the terms
of this Agreement.
8.2 Conflict of Interest.
Contractor covenants that neither it, nor any officer or principal of its firm, has or shall
acquire any interest, directly or indirectly, which would conflict in any manner with the interests
of City or which would in any way hinder Contractor’s performance of services under this
Agreement. Contractor further covenants that in the performance of this Agreement, no person
having any such interest shall be employed by it as an officer, employee, agent or subcontractor
without the express written consent of the Project Manager. Contractor agrees to at all times avoid
conflicts of interest or the appearance of any conflicts of interest with the interests of City in the
performance of this Agreement.
No officer or employee of the City shall have any financial interest, direct or indirect, in
this Agreement nor shall any such officer or employee participate in any decision relating to this
Agreement which effects his financial interest or the financial interest of any corporation,
partnership or association in which he is, directly or indirectly, interested, in violation of any State
statute or regulation. The Contractor warrants that it has not paid or given and will not pay or give
any third party any money or other consideration for obtaining this Agreement.
8.3 Covenant Against Discrimination.
Contractor covenants that, by and for itself, its heirs, executors, assigns, and all persons
claiming under or through them, there shall be no discrimination against or segregation of, any
person or group of persons on account of race, color, creed, religion, sex, gender, sexual
orientation, marital status, national origin, ancestry, or other protected class in the performance of
this Agreement. Contractor shall take affirmative action to insure that applicants are employed and
that employees are treated during employment without regard to their race, color, creed, religion,
sex, gender, sexual orientation, marital status, national origin, ancestry, or other protected class.
C-124
-26-
01203.0006/993143.2
8.4 Unauthorized Aliens.
Contractor hereby promises and agrees to comply with all of the provisions of the Federal
Immigration and Nationality Act, 8 U.S.C. § 1101 et seq., as amended, and in connection
therewith, shall not employ unauthorized aliens as defined therein. Should Contractor so employ
such unauthorized aliens for the performance of work and/or services covered by this Agreement,
and should any liability or sanctions be imposed against City for such use of unauthorized aliens,
Contractor hereby agrees to and shall reimburse City for the cost of all such liabilities or sanctions
imposed, together with any and all costs, including attorneys’ fees, incurred by City.
ARTICLE 9. MISCELLANEOUS PROVISIONS
9.1 Provisions Required By Law.
Each and every provision of law and clause required by law to be inserted in this Agreement
shall be deemed to be inserted herein, and this Agreement shall be read and enforced as though it
were included herein. If through mistake or otherwise any such provision is not inserted, or is not
correctly inserted, then upon application of either Party, this Agreement shall forthwith be
amended to make such insertion or correction.
9.2 Notices.
Any notice, demand, request, document, consent, approval, or communication either Party
desires or is required to give to the other Party or any other person shall be in writing and either
served personally or sent by prepaid, first-class mail, in the case of the City’s Project Manager,
City of Rancho Palos Verdes, 30940 Hawthorne Boulevard, Rancho Palos Verdes, CA 90275, and
in the case of the Contractor, to the person(s) at the address designated on the execution page of
this Agreement. Either Party may change its address by notifying the other Party of the change of
address in writing. Notice shall be deemed communicated at the time personally delivered or in 72
hours from the time of mailing if mailed as provided in this Section.
9.3 Interpretation.
The terms of this Agreement shall be construed in accordance with the meaning of the
language used and shall not be construed for or against either Party by reason of the authorship of
this Agreement or any other rule of construction which might otherwise apply.
9.4 Counterparts.
This Agreement may be executed in counterparts, each of which shall be deemed to be an
original, and such counterparts shall constitute one and the same instrument.
9.5 Integration; Amendment.
This Agreement, together with the documents incorporated herein (including the
Greenbook and the Bid Documents) and the exhibits attached hereto constitutes the entire,
complete and exclusive expression of the understanding of the Parties with respect to the subject
matter hereof. It is understood that there are no oral agreements between the Parties hereto
C-125
-27-
01203.0006/993143.2
affecting this Agreement and this Agreement supersedes and cancels any and all previous
negotiations, arrangements, agreements and understandings, if any, between the Parties, and none
shall be used to interpret this Agreement. No amendment to or modification of this Agreement
shall be valid unless made in writing and approved by the Contractor and by the City Council. The
Parties agree that this requirement for written modifications cannot be waived and that any
attempted waiver shall be void.
9.6 Severability.
In the event that any one or more of the phrases, sentences, clauses, paragraphs, or sections
contained in this Agreement shall be declared invalid or unenforceable by a valid judgment or
decree of a court of competent jurisdiction, such invalidity or unenforceability shall not affect any
of the remaining phrases, sentences, clauses, paragraphs, or sections of this Agreement which are
hereby declared as severable and shall be interpreted to carry out the intent of the Parties hereunder
unless the invalid provision is so material that its invalidity deprives either Party of the basic
benefit of their bargain or renders this Agreement meaningless.
9.7 Warranty & Representation of Non-Collusion.
No official, officer, or employee of City has any financial interest, direct or indirect, in this
Agreement, nor shall any official, officer, or employee of City participate in any decision relating
to this Agreement which may affect his/her financial interest or the financial interest of any
corporation, partnership, or association in which they are directly or indirectly interested, or in
violation of any corporation, partnership, or association in which they are directly or indirectly
interested, or in violation of any State or municipal statute or regulation. The determination of
“financial interest” shall be consistent with State law and shall not include interests found to be
“remote” or “noninterests” pursuant to Government Code Sections 1091 or 1091.5. Contractor
warrants and represents that it has not paid or given, and will not pay or give, to any third party
including, but not limited to, any City official, officer, or employee, any money, consideration, or
other thing of value as a result or consequence of obtaining or being awarded any agreement.
Contractor further warrants and represents that they have not engaged in any act(s), omission(s),
or other conduct or collusion that would result in the payment of any money, consideration, or
other thing of value to any third party including, but not limited to, any City official, officer, or
employee, as a result of consequence of obtaining or being awarded any agreement. Contractor is
aware of and understands that any such act(s), omission(s) or other conduct resulting in such
payment of money, consideration, or other thing of value will render this Agreement void and of
no force or effect.
9.8 Corporate Authority; Successors & Assigns.
The persons executing this Agreement on behalf of the Parties hereto warrant that (i) such
Party is duly organized and existing, (ii) they are duly authorized to execute and deliver this
Agreement on behalf of said Party, (iii) by so executing this Agreement, such Party is formally
bound to the provisions of this Agreement, and (iv) the entering into this Agreement does not
violate any provision of any other agreement to which said Party is bound. This Agreement shall
be binding upon the heirs, executors, administrators, successors and assigns of the Parties.
C-126
-28-
01203.0006/993143.2
IN WITNESS WHEREOF, the Parties hereto have executed this Agreement on the date
and year first-above written.
CITY:
CITY OF RANCHO PALOS VERDES, a
municipal corporation
Mayor
ATTEST:
City Clerk
APPROVED AS TO FORM:
Aleshire & Wynder, LLP
_____________________________
City Attorney
CONTRACTOR:
___________________________________,
a ___________________________
By:
Name:
Title:
By:
Name:
Title:
Address:
Two corporate officer signatures required when Contractor is a corporation, with one signature required from
each of the following groups: 1) Chairman of the Board, President or any Vice President; and 2) Secretary, any
Assistant Secretary, Chief Financial Officer or any Assistant Treasurer. CONTRACTOR ’S SIGNATURES
SHALL BE DULY NOTARIZED, AND APPROPRIATE ATTESTATIONS SHALL BE INCLUDED AS
MAY BE REQUIRED BY THE BYLAWS, ARTICLES OF INCORPORATION, OR OTHER RULES OR
REGULATIONS APPLICABLE TO CONTRACTOR’S BUSINESS ENTITY.
C-127
01203.0006/993143.2
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
STATE OF CALIFORNIA
COUNTY OF LOS ANGELES
On __________, 2024 before me, ________________, personally appeared ________________, proved to me on the
basis of satisfactory evidence to be the person(s) whose names(s) is/are subscribed to the within instrument and
acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by
his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted,
executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true
and correct.
WITNESS my hand and official seal.
Signature: _____________________________________
OPTIONAL
Though the data below is not required by law, it may prove valuable to persons relying on the document and could
prevent fraudulent reattachment of this form
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT
INDIVIDUAL
CORPORATE OFFICER
_______________________________
TITLE(S)
PARTNER(S) LIMITED
GENERAL
ATTORNEY-IN-FACT
TRUSTEE(S)
GUARDIAN/CONSERVATOR
OTHER_______________________________
______________________________________
SIGNER IS REPRESENTING:
(NAME OF PERSON(S) OR ENTITY(IES))
_____________________________________________
_____________________________________________
___________________________________
TITLE OR TYPE OF DOCUMENT
___________________________________
NUMBER OF PAGES
___________________________________
DATE OF DOCUMENT
___________________________________
SIGNER(S) OTHER THAN NAMED ABOVE
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy or validity of that document.
C-128
01203.0006/993143.2
CALIFORNIA ALL-PURPOSE ACKNOWLEDGMENT
STATE OF CALIFORNIA
COUNTY OF LOS ANGELES
On __________, 2024 before me, ________________, personally appeared ________________, proved to me on the
basis of satisfactory evidence to be the person(s) whose names(s) is/are subscribed to the within instrument and
acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by
his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted,
executed the instrument.
I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true
and correct.
WITNESS my hand and official seal.
Signature: _____________________________________
OPTIONAL
Though the data below is not required by law, it may prove valuable to persons relying on the document and could
prevent fraudulent reattachment of this form
CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT
INDIVIDUAL
CORPORATE OFFICER
_______________________________
TITLE(S)
PARTNER(S) LIMITED
GENERAL
ATTORNEY-IN-FACT
TRUSTEE(S)
GUARDIAN/CONSERVATOR
OTHER_______________________________
______________________________________
SIGNER IS REPRESENTING:
(NAME OF PERSON(S) OR ENTITY(IES))
_____________________________________________
_____________________________________________
___________________________________
TITLE OR TYPE OF DOCUMENT
___________________________________
NUMBER OF PAGES
___________________________________
DATE OF DOCUMENT
___________________________________
SIGNER(S) OTHER THAN NAMED ABOVE
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the
document to which this certificate is attached, and not the truthfulness, accuracy or validity of that document.
C-129
01203.0006/993143.2
BOND FORMS
C-130
01203.0006/993143.2
PERFORMANCE BOND
WHEREAS, the CITY OF RANCHO PALOS VERDES, (“City”), has awarded to
__________________________________, as Contractor (“Principal”), a Contract for the
work entitled and described as
follows:__________________________________________________;
WHEREAS, the Contractor is required under the terms of said Contract to furnish a
bond for the faithful performance of the Contract;
NOW, THEREFORE, we the undersigned Contractor and Surety, are held and firmly
bound unto the City in the sum of ________________________________________
($______________), this amount being not less than one hundred percent (100%) of the total
Contract price, lawful money of the United States of America, for payment of which sum well
and truly be made we bind ourselves, our heirs, executors, administrators, and successors,
jointly and severally, firmly by these presents. In case suit is brought upon this bond, the Surety
will pay a reasonable attorney’s fee to the City in an amount to be fixed by the court.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the hereby bound
Contractor, or its heirs, executors, administrators, successors, or assigns, shall in all things
stand and abide by, well and truly keep and perform all undertakings, terms, covenants,
conditions, and agreements in the said Contract and any alteration thereof, made as therein
provided, all within the time and in the manner designated and in all respects according to their
true intent and meaning, then this obligation shall become null and void; otherwise it shall be
and remain in full force and effect.
FURTHER, the said Surety, for value received, hereby stipulates and agrees that no
change, extension of time, alteration, or modification of the Contract Documents or of the work
to be performed thereunder shall in any way affect its obligations on this bond, and it does
hereby waive notice of such change, extension of time, alteration, or modification of the
Contract Documents or of the work to be performed thereunder.
Executed on 20___.
PRINCIPAL
(Seal if Corporation) By
Title
(Attach Acknowledgment of Authorized Representative of Principal)
C-131
01203.0006/993143.2
Any claims under this bond may be addressed to:
(name and address of Surety)
(name and address of Surety's agent for service
of
process in California, if different from above)
(telephone number of Surety's agent in
California)
(Attach Acknowledgment)
SURETY
By
(Attorney-in-Fact)
APPROVED:
(Attorney for CITY)
NOTICE:
No substitution or revision to this bond form will be accepted. Sureties must be authorized to
do business in and have an agent for service of process in California. Certified copy of Power
of Attorney must be attached.
C-132
01203.0023/976055.4
PAYMENT BOND
(Labor and Material Bond)
WHEREAS, the CITY OF RANCHO PALOS VERDES, (“City”), has awarded to
__________________________________, as Contractor (“Principal”), a Contract for the
work entitled and described as
follows:__________________________________________________;
WHEREAS, said Contractor is required to furnish a bond in conjunction with said
Contract, to secure the payment of claims of laborers, mechanics, material men, and other
persons as provided by law;
NOW, THEREFORE, we the undersigned Contractor and Surety, are held and firmly
bound unto the City in the sum of ________________________________________
($______________), this amount being not less than one hundred percent (100%) of the total
Contract price, lawful money of the United States of America, for payment of which sum well
and truly be made we bind ourselves, our heirs, executors, administrators, and successors,
jointly and severally, firmly by these presents. In case suit is brought upon this bond, the Surety
will pay a reasonable attorney’s fee to the City in an amount to be fixed by the court.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if said Contractor, its
heirs, executors, administrators, successors, assigns, or subcontractor fails to pay: (1) for any
work, materials, services, provisions, provender, or other supplies, or for the use of implements
of machinery, used in, upon, for, or about the performance of the work to be done, or for any
work or labor thereon of any kind; (2) for work performed by any of the persons named in
Civil Code Section 9100; (3) for any amounts due under the Unemployment Insurance Code
with respect to work or labor performed under the contract; and/or (4) for any amounts required
to be deducted, withheld, and paid over to the Employment Development Department from the
wages of employees of the Contractor and/or its subcontractors pursuant to Section 13020 of
the Unemployment Insurance Code with respect to such work and labor, then the Surety herein
will pay for the same in an amount not exceeding the sum specified in this bond, otherwise the
above obligation shall be void.
This bond shall inure to the benefit of any of the persons named in Civil Code Section
9100 so as to give a right of action to such persons or their assigns in any suit brought upon
the bond. Moreover, if the City or any entity or person entitled to file stop payment notices is
required to engage the services of an attorney in connection with the enforcement of this bond,
each shall be liable for the reasonable attorney's fees incurred, with or without suit, in addition
to the above sum.
Said Surety, for value received, hereby stipulates and agrees that no change, extension
of time, alteration, or modification of the Contract Documents or of the work to be performed
thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice
of such change, extension of time, alteration, or modification of the Contract Documents or of
the work to be performed thereunder.
C-133
01203.0023/976055.4
Executed on , 20____.
PRINCIPAL
(Seal if Corporation) By
Title
(Attach Acknowledgment of Authorized Representative of Principal)
Any claims under this bond may be addressed to:
(name and address of Surety)
(name and address of Surety's agent for service
of process in California, if different from above)
(telephone number of Surety's agent in
California)
(Attach Acknowledgment)
SURETY
By
(Attorney-in-Fact)
APPROVED:
(Attorney for CITY)
NOTICE:
No substitution or revision to this bond form will be accepted. Sureties must be authorized to
do business in and have an agent for service of process in California. Certified copy of Power
of Attorney must be attached.
C-134
01203.0023/976055.4
INSURANCE FORMS
C-135
01203.0023/976055.4
WORKERS COMPENSATION INSURANCE CERTIFICATE
Description of Contract: City of Rancho Palos Verdes
Project: _____________________________________________
Type of Insurance: Workers' Compensation and
Employers' Liability Insurance
THIS IS TO CERTIFY that the following policy has been issued by the below-stated company in
conformance with the requirements of Article 5 of the Contract and is in force at this time, and is
in a form approved by the Insurance Commissioner.
The Company will give at least 30 days' written notice to the City and Engineer/Architect prior to
any cancellation of said policy.
POLICY NUMBER EXPIRATION DATE LIMITS OF LIABILITY
Workers' Compensation:
Statutory Limits Under the Laws
of the State of California
Employers' Liability:
$_________________ Each Accident
$_________________ Disease - Policy Limit
$_________________ Disease - Each Employee
Named Insured (Contractor) Insurance Company
Street Number Street Number
City and State City and State
By
(Company Representative)
(SEE NOTICE ON NEXT PAGE)
C-136
01203.0023/976055.4
Insurance Company Agent for Service
of Process in California:
Name
Agency
Street Number
City and State
Telephone Number
This certificate is issued as a matter of information only and confers no rights upon the certificate
holder. This certificate does not amend, extend, or alter the coverage afforded by the policy listed
herein.
This is to certify that the policy has been issued to the named insured for the policy period
indicated, notwithstanding any requirement, term, or condition of any contract or other document
with respect to which this certificate may be issued or may pertain, the insurance afforded by the
policy described herein is subject to all the terms, exclusions, and conditions of such policy.
NOTICE:
No substitution or revision to the above certificate form will be accepted. If the insurance called
for is provided by more than one insurance company, a separate certificate in the exact above form
shall be provided for each insurance company.
C-137
01203.0023/976055.4
ADDITIONAL INSURED ENDORSEMENT
COMPREHENSIVE GENERAL LIABILITY
Name and address of named insured (“Named Insured”)
Name and address of Insurance Company (“Company”)
General description of agreement(s), permit(s), license(s), and/or activity(ies) insured
Notwithstanding any inconsistent statement in the policy to which this endorsement is attached (the
“Policy”) or in any endorsement now or hereafter attached thereto, it is agreed as follows:
1. The
(“Public Agency”), its elected officials, officers, attorneys, agents, employees, and volunteers are additional
insureds (the above named additional insureds are hereafter referred to as the “Additional Insureds”) under
the Policy in relation to those activities described generally above with regard to operations performed by
or on behalf of the Named Insured. The Additional Insureds have no liability for the payment of any
premiums or assessments under the Policy.
2. The insurance coverages afforded the Additional Insureds under the Policy shall be primary
insurance, and no other insurance maintained by the Additional Insureds shall be called upon to contribute
with the insurance coverages provided by the Policy.
3. Each insurance coverage under the Policy shall apply separately to each Additional Insured
against whom claim is made or suit is brought except with respect to the limits of the Company's liability.
4. Nothing in this contract of insurance shall be construed to preclude coverage of a claim by
one insured under the policy against another insured under the policy. All such claims shall be covered as
third-party claims, i.e., in the same manner as if separate policies had been issued to each insured. Nothing
contained in this provision shall operate to increase or replicate the Company's limits of liability as provided
under the policy.
5. The insurance afforded by the Policy for contractual liability insurance (subject to the
terms, conditions and exclusions applicable to such insurance) includes liability assumed by the Named
Insured under the indemnification and/or hold harmless provision(s) contained in or executed in conjunction
with the written agreement(s) or permit(s) designated above, between the Named Insured and the Additional
Insureds.
6. The policy to which this endorsement is attached shall not be subject to cancellation,
change in coverage, reduction of limits (except as the result of the payment of claims), or non -renewal
except after written notice to Public Agency, by certified mail, return receipt requested, not less than thirty
(30) days prior to the effective date thereof. In the event of Company's failure to comply with this notice
provision, the policy as initially drafted will continue in full force and effect until compliance with this
notice requirement.
7. Company hereby waives all rights of subrogation and contribution against the Additional
Insureds, while acting within the scope of their duties, from all claims, losses and liabilities arising out of
or incident to the perils insured against in relation to those activities described generally above with regard
C-138
01203.0023/976055.4
to operations performed by or on behalf of the Named Insured regardless of any prior, concurrent, or
subsequent active or passive negligence by the Additional Insureds.
8. It is hereby agreed that the laws of the State of California shall apply to and govern the
validity, construction, interpretation, and enforcement of this contract of insurance.
9. This endorsement and all notices given hereunder shall be sent to Public Agency at:
City Manager, City of Rancho Palos Verdes, 30940 Hawthorne Boulevard, Rancho Palos Verdes, California
90275.
10. Except as stated above and not in conflict with this endorsement, nothing contained herein
shall be held to waive, alter or extend any of the limits, agreements, or exclusions of the policy to which
this endorsement is attached.
TYPE OF COVERAGES TO WHICH POLICY PERIOD LIMITS OF
THIS ENDORSEMENT ATTACHES FROM/TO LIABILITY
11. Scheduled items or locations are to be identified on an attached sheet. The following
inclusions relate to the above coverages. Includes:
□ Contractual Liability □ Explosion Hazard
□ Owners/Landlords/Tenants □ Collapse Hazard
□ Manufacturers/Contractors □ Underground Property Damage
□ Products/Completed Operations □ Pollution Liability
□ Broad Form Property Damage □ Liquor Liability
□ Extended Bodily Injury □
□ Broad Form Comprehensive □
General Liability Endorsement □
12. A □ deductible or □ self-insured retention (check one) of $
applies to all coverage(s) except:
(if none, so state). The deductible is applicable □ per claim or □ per occurrence (check one).
13. This is an □ occurrence or □ claims made policy (check one).
14. This endorsement is effective on at 12:01 a.m. and forms a part of
Policy Number .
(signatures on following page)
C-139
01203.0023/976055.4
I, (print name), hereby
declare under penalty of perjury under the laws of the State of California, that I have the authority to bind
the Company to this endorsement and that by my execution hereof, I do so bind the Company.
Executed , 20
Signature of Authorized Representative
(Original signature only; no facsimile signature
Telephone No.: ( ) or initialed signature accepted)
C-140
01203.0023/976055.4
ADDITIONAL INSURED ENDORSEMENT
AUTOMOBILE LIABILITY
Name and address of named insured (“Named Insured”)
Name and address of Insurance Company (“Company”)
General description of agreement(s), permit(s), license(s), and/or activity(ies) insured
Notwithstanding any inconsistent statement in the policy to which this endorsement is attached (the
“Policy”) or in any endorsement now or hereafter attached thereto, it is agreed as follows:
1. The
(“Public Agency”), its elected officials, officers, attorneys, agents, employees, and volunteers are additional
insureds (the above named additional insureds are hereafter referred to as the “Additional Insureds”) under
the Policy in relation to those activities described generally above with regard to operations performed by
or on behalf of the Named Insured. The Additional Insureds have no liability for the payment of any
premiums or assessments under the Policy.
2. The insurance coverages afforded the Additional Insureds under the Policy shall be primary
insurance, and no other insurance maintained by the Additional Insureds shall be called upon to contribute
with the insurance coverages provided by the Policy.
3. Each insurance coverage under the Policy shall apply separately to each Additional Insured
against whom claim is made or suit is brought except with respect to the limits of the Company's liability.
4. Nothing in this contract of insurance shall be construed to preclude coverage of a claim by
one insured under the policy against another insured under the policy. All such claims shall be covered as
third-party claims, i.e., in the same manner as if separate policies had been issued to each insured. Nothing
contained in this provision shall operate to increase or replicate the Company's limits of liability as provided
under the policy.
5. The insurance afforded by the Policy for contractual liability insurance (subject to the
terms, conditions and exclusions applicable to such insurance) includes liability assumed by the Named
Insured under the indemnification and/or hold harmless provision(s) contained or executed in conjunction
with the written agreement(s) or permit(s) designated above, between the Named Insured and the Additional
Insureds.
6. The policy to which this endorsement is attached shall not be subject to cancellation,
change in coverage, reduction of limits (except as the result of the payment of claims), or non-renewal
except after written notice to Public Agency, by certified mail, return receipt requested, not less than thirty
(30) days prior to the effective date thereto. In the event of Company's failure to comply with this notice
provision, the policy as initially drafted will continue in full force and effect until compliance with this
notice requirement.
7. Company hereby waives all rights of subrogation and contribution against the Additional
Insureds, while acting within the scope of their duties, from all claims, losses and liabilities arising out of
or incident to the perils insured against in relation to those activities described generally above with regard
C-141
01203.0023/976055.4
to operations performed by or on behalf of the Named Insured regardless of any prior, concurrent, or
subsequent active or passive negligence by the Additional Insureds.
8. It is hereby agreed that the laws of the State of California shall apply to and govern the
validity, construction, interpretation, and enforcement of this contract of insurance.
9. This endorsement and all notices given hereunder shall be sent to Public Agency at:
City Manager
City of Rancho Palos Verdes
30940 Hawthorne Boulevard
Rancho Palos Verdes, California 90275
10. Except as stated above and not in conflict with this endorsement, nothing contained herein
shall be held to waive, alter or extend any of the limits, agreements, or exclusions of the policy to which
this endorsement is attached.
TYPE OF COVERAGES TO WHICH POLICY PERIOD LIMITS OF
THIS ENDORSEMENT ATTACHES FROM/TO LIABILITY
11. Scheduled items or locations are to be identified on an attached sheet. The following
inclusions relate to the above coverages. Includes:
□ Any Automobiles □ Truckers Coverage
□ All Owned Automobiles □ Motor Carrier Act
□ Non-owned Automobiles □ Bus Regulatory Reform Act
□ Hired Automobiles □ Public Livery Coverage
□ Scheduled Automobiles □
□ Garage Coverage □
12. A □ deductible or □ self-insured retention (check one) of $
applies to all coverage(s) except: (if none, so state). The deductible is applicable □
per claim or □ per occurrence (check one).
13. This is an □ occurrence or □ claims made policy (check one).
14. This endorsement is effective on at 12:01 a.m. and forms a part of Policy
Number .
(signatures on following page)
C-142
01203.0023/976055.4
I, (print name), hereby
declare under penalty of perjury under the laws of the State of California, that I have the authority to bind
the Company to this endorsement and that by my execution hereof, I do so bind the Company.
Executed , 20
Signature of Authorized Representative
(Original signature only; no facsimile signature
Telephone No.: ( ) or initialed signature accepted)
C-143
01203.0023/976055.4
ADDITIONAL INSURED ENDORSEMENT
EXCESS LIABILITY
Name and address of named insured (“Named Insured”)
Name and address of Insurance Company (“Company”)
General description of agreement(s), permit(s), license(s), and/or activity(ies) insured
Notwithstanding any inconsistent statement in the policy to which this endorsement is attached (the
“Policy”) or in any endorsement now or hereafter attached thereto, it is agreed as follows:
1. The
(“Public Agency”), its elected officials, officers, attorneys, agents, employees, and volunteers are additional
insureds (the above named additional insureds are hereafter referred to as the “Additional Insureds”) under
the Policy in relation to those activities described generally above with regard to operations performed by
or on behalf of the Named Insured. The Additional Insureds have no liability for the payment of any
premiums or assessments under the Policy.
2. The insurance coverages afforded the Additional Insureds under the Policy shall be primary
insurance, and no other insurance maintained by the Additional Insureds shall be called upon to contribute
with the insurance coverages provided by the Policy.
3. Each insurance coverage under the Policy shall apply separately to each Additional Insured
against whom claim is made or suit is brought, except with respect to the limits of the Company's liability.
4. Nothing in this contract of insurance shall be construed to preclude coverage of a claim by
one insured under the policy against another insured under the policy. All such claims shall be covered as
third-party claims, i.e., in the same manner as if separate policies had been issued to each insured. Nothing
contained in this provision shall operate to increase or replicate the Company's limits of liability as provided
under the policy.
5. The insurance afforded by the Policy for contractual liability insurance (subject to the
terms, conditions and exclusions applicable to such insurance) includes liability assumed by the Named
Insured under the indemnification and/or hold harmless provision(s) contained in or executed in conjunction
with the written agreement(s) or permit(s) designated above, between the Named Insured and the Additional
Insureds.
6. The policy to which this endorsement is attached shall not be subject to cancellation,
change in coverage, reduction of limits (except as the result of the payment of claims), or non -renewal
except after written notice to Public Agency, by certified mail, return receipt requested, not less than thirty
(30) days prior to the effective date thereto. In the event of Company's failure to comply with this notice
provision, the policy as initially drafted will continue in full force and effect until compliance with this
notice requirement.
7. Company hereby waives all rights of subrogation and contribution against the Additional
Insureds, while acting within the scope of their duties, from all claims, losses and liabilities arising out of
or incident to the perils insured against in relation to those activities described generally above with regard
to operations performed by or on behalf of the Named Insured regardless of any prior, concurrent, or
subsequent active or passive negligence by the Additional Insureds.
C-144
01203.0023/976055.4
8. It is hereby agreed that the laws of the State of California shall apply to and govern the
validity, construction, interpretation, and enforcement of this contract of insurance.
9. This endorsement and all notices given hereunder shall be sent to Public Agency at:
City Manager
City of Rancho Palos Verdes
30940 Hawthorne Boulevard
Rancho Palos Verdes, California 90275
10. Except as stated above and not in conflict with this endorsement, nothing contained herein
shall be held to waive, alter or extend any of the limits, agreements, or exclusions of the policy to which
this endorsement is attached.
TYPE OF COVERAGES TO WHICH POLICY PERIOD LIMITS OF
THIS ENDORSEMENT ATTACHES FROM/TO LIABILITY
□ Following Form
□ Umbrella Liability
□
11. Applicable underlying coverages:
INSURANCE COMPANY POLICY NO. AMOUNT
12. The following inclusions, exclusions, extensions or specific provisions relate to the above
coverages:
13. A □ deductible or □ self-insured retention (check one) of $
applies to all coverage(s) except:
(if none, so state). The deductible is applicable □ per claim or □ per occurrence (check one).
14. This is an □ occurrence or □ claims made policy (check one).
15. This endorsement is effective on at 12:01 a.m. and forms a part of Policy
Number .
C-145
01203.0023/976055.4
(signatures on following page)
I, (print name), hereby
declare under penalty of perjury under the laws of the State of California, that I have the authority to bind
the Company to this endorsement and that by my execution hereof, I do so bind the Company.
Executed , 20
Signature of Authorized Representative
(Original signature only; no facsimile signature
Telephone No.: ( ) or initialed signature accepted)
C-146
RPVAPPENDIX I:
STREET SWEEPING SCHEDULE
C-147
APPENDIX II:
TRASH COLLECTION SCHEDULE
Note: The multi-family condominium complex located at 5987 Peacock Ridge Road differs
as follows - Trash (Monday/Friday), Recycling (Wednesday), and Organic Waste (Friday)
C-148
APPENDIX III:
DOOR HANGERS, LETTERS/NOTIFICATIONS
C-149
Exhibit D-7
APPENDIX IV:
MATERIAL RECYCLING PACKET
C-150
Exhibit D-8
C-151
Exhibit D-9
C-152
Exhibit D-10
C-153
Exhibit D-11
C-154
Exhibit D-12
Conversion Factors for C&D Reporting
Material Size LBS
Asphalt, crushed 1 cubic foot 45
Asphalt/paving, crushed 1 cubic yard 1,380
Asphalt/shingles comp, loose 1 cubic yard 418.5
Asphalt/shingles comp 400 sq. ft. coverage 225
Asphalt/shingles comp Square 56.25
Asphalt/tar roofing 1 cubic yard 2,919
Brick, common hard 1 cubic foot 112-125
Brick, whole 1 cubic yard 3,024
Cement, bulk 1 cubic foot 100
Cement, mortar 1 cubic foot 145
Ceramic tile, loose 6"x6" 1 cubic yard 1,214
Chalk, lumpy 1 cubic foot 75-85
Charcoal 1 cubic foot 15-30
Clay, kaolin 1 cubic foot 22-33
Clay, potter's dry 1 cubic foot 119
Concrete, cinder 1 cubic foot 90-110
Concrete, scrap, loose 1 cubic yard 1,855
Cork, dry 1 cubic foot 15
Earth, common, dry 1 cubic foot 70-80
Earth, loose 1 cubic foot 76
Earth, moist, loose 1 cubic foot 78
Earth, mud 1 cubic foot 104-112
Earth, wet, containing clay 1 cubic foot 100-110
Granite, broken or crushed 1 cubic foot 95-100
Granite, solid 1 cubic foot 130-166
Gravel, dry 1 cubic foot 100
Gravel, loose 1 cubic yard 2,565
Gravel, wet 1 cubic foot 100-120
C-155
Exhibit D-13
Material Size LBS
Mortar, hardened 1 cubic foot 100
Mortar, wet 1 cubic foot 150
Mud, dry close 1 cubic foot 110
Mud, wet fluid 1 cubic foot 120
Pebbles 1 cubic foot 90-100
Pumice, ground 1 cubic foot 40-45
Pumice, stone 1 cubic foot 39
Quartz, sand 1 cubic foot 70-80
Quartz, solid 1 cubic foot 165
Rock, loose 1 cubic yard 2,570
Rock, soft 1 cubic foot 100-110
Sand, dry 1 cubic foot 90-110
Sand, loose 1 cubic yard 2,441
Sand, moist 1 cubic foot 100-110
Sand, wet 1 cubic foot 110-130
Sheetrock scrap, loose 1 cubic yard 393.5
Slate, fine ground 1 cubic foot 80-90
Slate, granulated 1 cubic foot 95
Slate, solid 1 cubic foot 165-175
Soil/sandy loam, loose 1 cubic yard 2,392
Stone or gravel 1 cubic foot 95-100
Stone, crushed 1 cubic foot 100
Stone, crushed, size reduced 1 cubic yard 2,700
Stone, large 1 cubic foot 100
C-156
APPENDIX V:
CONCRETE AND ASPHALT REMOVAL FORM
CITY OF RANCHO PALOS VERDES
PEACOCK RIDGE STORM DRAIN IMPROVEMENTS PROJECT NO. 8723
Street Name: Sheet of
Address
AC Street
R&R
(SF)
PCC
R&R
(SF)
Curb Ramp
R&R
(EA)
TOTAL
The total quantities as shown above are correct and shall be considered final for terms of payment under this contract.
Contractor, Title Date
City Inspector Date
C-157
APPENDIX VI:
SCHOOL DISTRICT CALENDAR
C-158
APPENDIX VII:
PROPOSED IMPROVEMENT PLANS
(SEE ATTACHED PLAN SET)
C-159
CI
T
Y
F
U
N
D
S
S
U
M
M
A
R
Y
GE
N
E
R
A
L
F
U
N
D
S
U
M
M
A
R
Y
AP
P
E
N
D
I
X
BU
D
G
E
T
P
R
O
G
R
A
M
S
BU
D
G
E
T
O
V
E
R
V
I
E
W
356 City of Rancho Palos Verdes | Adopted Budget | Capital Improvement Program (Fiscal Years 2024-2025 through 2028-29)
-$ -$
-$ -$
-$ -$ -$
-$ -$ -$
-$ -$ -$ -$ -$
-$ -$
The existing storm drain pipe, collecting stormwater runoff from Peacock Ridge Road
and conveying it to an outlet on Scotmist Drive, has collapsed and needs to be
replaced.
Estimated annual operating / maintenance cost TBD
ESTIMATED SCHEDULE
Engineering and environmental in FY 23/24
Construction in FY 24/25
Project Location Map Background and Justification
-$ -$
42,605$ 285,000$ -$ -$ -$ -$
-$ -$ -$ -$
-$
-$
FUNDING
-$ -$ 330 (CIP Fund)
-$ -$ -$ -$
Currently
FY24/25 FY25/26 FY26/27 FY27/28 FY28/29
Future
Fiscal YearsBudgeted
42,605$ 285,000$ -$ -$ -$
42,605$ 285,000$ -$ -$ -$ -$ 285,000$
Inspection $ 20,000 $ - $ - $ - $ - 20,000$
Construction $ 195,000 $ - $ - $ - $ - 195,000$
Project Contingency $ 60,000 $ - $ - $ - $ - 60,000$
$ - -$
Management $ 10,000 $ - $ - $ - $ -
Engineering $ - $ - $ - $ -
10,000$
Environmental $ - $ - $ - $ - $ - -$
Overall
Planning $ - $ - $ - $ - $ - -$
FY24/25 FY25/26 FY26/27 FY27/28 FY28/29
Committed
as of 3/22/24
Insert Descriptive Photo
PROJECT DESCRIPTION
This project is intended to remove and replace a collapsed storm drain pipe at Peacock
Ridge Road and install associated infrastructure, including a new catch basin and storm
drain outlet located at Scotmist Drive.
PROJECT COST ESTIMATES
8700 Series Sewer & Storm Drain Improvements Projects 8723
Storm Drain Improvements at Peacock Ridge Road
D-1