AMG and Associates Inc (Change Order 097)City of Rancho Palos Verdes
Department of Public Works
30940 Hawthorne Blvd, Rancho Palos Verdes, CA 90275
(310)544-5252
CHANGE ORDER MEMORANDUM
TO: RAMZI AWWAD, DIRECTOR OF PUBLIC WORKS
FROM: ALAN BRAATVEDT, SUNBEAM CONSULTING
D DAVID COPP, DEPUTY DIRECTOR OF PUBLIC WORKS
DATE: May 29, 2024
SUBJECT: LADERA LINDA COMMUNITY PARK
CONSTRUCTION CHANGE ORDER NUMBER: #97 (PCO 43R1)
Description of Construction Change Order
Provide a 99- working day (WD) time extension to the project, accounting for unavoidable
delays, City-caused delays, and the associated compensable component of the time
extension, leading up to the date the City issued the Notice of Substantial Completion
(2/23/24) to the Contractor (AMG).
Justification and Background
Background:
The following are the project’s milestone dates and associated durations:
- Notice to proceed (NTP) date: 3/28/22
- Original contract duration: 330 working days (WD)
- Original contract completion date: 7/27/23
- Approved time extensions: CO#03 (11 WD), CO#35 (2 WD), CO# 47 (6 WD),
CO#48 (1 WD) and CO#67 (24 WD) = 44 WD Total
- Revised completion date: 9/28/23 (+44 WD)
- Notice of Substantial Completion (NOSC) date: 2/23/24
- Difference between revised completion date and date of NOSC: +99 WD
Prior to the date of notice of substantial completion (NOSC), AMG claimed by way of
PCO 43 (issued 4/10/23) and an accompanying time impact analysis that the project
was delayed by 134 WD and an associated compensable time extension was due.
AMG’s PCO claimed that the difference in the actual vs baseline completion dates for
the activities associated with providing permanent power to the facility affected the
project schedule critical path, meaning that there were other activities that could not be
started or completed by AMG until permanent power was available.
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
City of Rancho Palos Verdes
Department of Public Works
30940 Hawthorne Blvd, Rancho Palos Verdes, CA 90275
(310)544-5252
In response, the City hired the services of Sunbeam Consulting to perform a schedule
analysis against AMG’s time impact analysis associated with PCO 43. Sunbeam’s
analysis was used to determine the appropriate time extension to grant as part of a
change order, including any potential compensable component of the time extension
relating to City-caused delays. Reference the attached Schedule Analysis for more
information. A summary of that analysis is provided in the “Schedule Analysis” section
below.
The analysis was also used to support a series of negotiation meetings between the
City and AMG. On 4/25/2024, the City and AMG reached a negotiated agreement for
the share of the delays (unavoidable vs City-caused). See justification sub-section
below for the relative breakdown.
Justification:
The contract specifies that (1) owner-caused delays to the project schedule critical path
allow for compensable time extensions, and (2) unavoidable delays (ie. at no fault of the
City or Contractor) allow for non-compensable time extensions.
The cost of a compensable time extension represents the additional field resources
(“extended field overhead”) and general conditions the Contractor had to provide to
support the project for duration of the City-caused delay. Reference the Cost Analysis
and attached cost estimate for how the cost is determined.
The sum of unavoidable and City-caused delays resulted in the actual date of
completion date (2/23/24) being later than the revised contract completion (9/28/23) as
accounted for in previous change orders.
Therefore, a change order needs to be issued to account for the sum of unavoidable (62
WD) and City-caused (37 WD) delays totaling 99 WD between 9/28/23 and the date of
NOSC (2/23/24), as well as the City’s share of compensable time.
Cost Analysis
Sunbeam’s cost estimate is based on AMG’s approved daily field overhead rate of
$1,717.91, as applied to the negotiated and justified portion of the 99 WD time
extension that was a result of City -caused (compensable) delays (37 WD). Appropriate
additional costs for general conditions (insurance, markup, and bond) were applied to
that subtotal, for a grand total CO 97 cost of $69,500. See attached cost estimate for
reference.
Schedule Analysis Summary
The following table summarizes Sunbeam’s attached schedule analysis and breakdown
of the recommended time extension (continued on next page).
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
City of Rancho Palos Verdes
Department of Public Works
30940 Hawthorne Blvd, Rancho Palos Verdes, CA 90275
(310)544-5252
Although the total time justifiable amounts to more than the 99 days between the current
approved contract completion date and the date of notice of substantial completion, the
City’s decision to occupy the facility on 2/23/24 effectively served, from a negotiation
standpoint, as the project completion date, understanding that some minor activities
were pending completion by the Contractor.
Recommendation:
It is recommended that the contractual completion date be revised to 2/23/2024 , which
equates to a total time extension of 99 days, 37 days of which are a result of City-
caused delays and therefore compensable for a total amount of $69,500.
Attachments:
Construction Contract Change Order Form
Construction Contract Change Order Summary Sheet
Contractor’s Change Order Proposal
SunBeam’s Cost Assessment
Sunbeam’s Schedule Analysis
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
6/19/2024
6/19/2024
6/20/2024
8405
143
0
0
11
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
CONSTRUCTION CHANGE ORDER SUMMARY SHEET
PROJECT NAME:Ladera Linda Community Park DATE:05/13/24
PROJECT CODE:
ORIGINAL COMPLETION DATE:07/27/23
TOTAL SCHEDULE CHANGE ORDERS:Working Days
PURCHASE ORDER NUMBER:20220215
ACCOUNT NUMBER:330-400-8405-8403
PREPARED BY:JAMES O'NEILL
CONTRACTOR NAME:AMG & Associates, Inc.
CONTRACT NUMBER:FY2022-050
NEW CONTRACT COMPLETION DATE:02/23/24
$1,029,075.00
TOTAL CHANGE ORDERS COST:$1,080,412.90 REVISED CONTINGENCY AMOUNT:$1,208,194.98
NEW CONTRACT AMOUNT:$14,801,412.90 REMAINING CONTINGENCY AMOUNT:$127,782.08
ORIGINAL CONTRACT AMOUNT:$13,721,000.00 ORIGINAL CONTINGENCY AMOUNT:
CO#2 $12,628.58 Working Days 08/09/22
CO#3 $53,526.25 Working Days 08/31/22
CHANGE ORDER
NUMBER COST AMOUNT SCHEDULE
EXTENSION DATE
CO#1 $54,534.52 Working Days 05/27/22
CO#6 $824.34 Working Days 09/01/22
CO#7 $10,202.36 Working Days 09/27/22
CO#4 $8,558.42 Working Days 09/01/22
CO#5 -$5,378.25 Working Days 09/01/22
CO#10 $42,918.80 Working Days 11/09/22
CO#8 $6,437.02 Working Days 09/27/22
CO#9 $1,818.52 Working Days 11/09/22
CO#13 $0.00 Working Days 12/30/22
CO#14 -$20,112.42 Working Days 12/30/22
CO#11 $33,868.27 Working Days 12/01/22
CO#12 $9,052.32 Working Days 12/01/22
CO#17 $12,582.87 Working Days 02/03/23
CO#18 $16,546.62 Working Days 02/09/23
CO#15 -$3,117.01 Working Days 01/17/23
CO#16 $59,788.90 Working Days 02/02/23
CO#21 $10,075.07 Working Days 02/21/23
CO#22 $3,178.42 Working Days 02/22/23
CO#19 $17,562.82 Working Days 02/09/23
CO#20 $3,679.17 Working Days 02/16/23
CO#23 $4,094.67 Working Days 02/23/23
CO#24 $19,573.51 Working Days 03/07/23
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
6/20/2024
0
0
0
0
0
0
0
0
0
0
2
0
0
0
0
0
0
0
0
0
0
0
6
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
24
0
0
0
0
0
0
0
0
0
0
0
0
CO#25 $8,909.82 Working Days 04/06/23
CO#26 $21,061.12 Working Days 04/25/23
CHANGE ORDER
NUMBER COST AMOUNT SCHEDULE
EXTENSION DATE
CO#29 $1,055.31 Working Days 05/09/23
CO#30 $3,682.06 Working Days 05/18/23
CO#27 $136,226.21 Working Days 05/03/23
CO#28 $10,819.96 Working Days 05/05/23
CO #33 $10,095.54 Working Days 05/31/23
CO #34 $179,119.98 Working Days 06/08/23
CO#31 $2,104.03 Working Days 05/18/23
CO#32 $2,291.43 Working Days 05/19/23
CO # 37 $3,561.51 Working Days 06/16/23
CO #38 $23,527.90 Working Days 07/12/23
CO #35 $3,765.15 Working Days 06/08/23
CO #36 $697.56 Working Days 06/16/23
CO #41 $630.12 Working Days 07/26/23
CO #42 $6,466.62 Working Days 08/03/23
CO #39 $24,530.09 Working Days 07/25/23
CO #40 $11,002.33 Working Days 07/26/23
CO #45 $35,792.08 Working Days 10/10/23
CO #46 -$6,270.83 Working Days 10/10/23
CO #43 $1,647.09 Working Days 08/24/23
CO #44 $23,867.61 Working Days 08/29/23
CO #49 -$3,253.37 Working Days 10/10/23
CO #50 $246.57 Working Days 10/10/23
CO #47 $0.00 Working Days 10/10/23
CO #48 $0.00 Working Days 10/10/23
CO #53 -$2,446.03 Working Days 10/10/23
CO #54 $1,807.98 Working Days 10/10/23
CO #51 -$44,040.60 Working Days 10/10/23
CO #52 $6,575.10 Working Days 10/12/23
CO #57 $8,575.63 Working Days 10/10/23
CO #58 $982.98 Working Days 10/10/23
CO #55 -$19,277.91 Working Days 10/10/23
CO #56 -$35,244.14 Working Days 10/10/23
CO #61 $5,590.13 Working Days 10/10/23
CO #62 $2,674.08 Working Days 10/10/23
CO #59 $8,890.83 Working Days 10/10/23
CO #60 $9,524.04 Working Days 10/10/23
CO #65 $251.55 Working Days 10/10/23
CO #66 $47,423.41 Working Days 10/10/23
CO #63 $690.91 Working Days 10/10/23
CO #64 $2,200.00 Working Days 10/10/23
CO #69 $4,599.28 Working Days 02/12/24
CO #70 $5,364.69 Working Days 02/12/24
CO #67 $36,343.87 Working Days 02/12/24
CO #68 $3,203.68 Working Days 02/12/24
CO #73 $1,376.77 Working Days 02/12/24
CO #74 $4,408.47 Working Days 02/12/24
CO #71 $9,892.05 Working Days 02/12/24
CO #72 $10,556.39 Working Days 02/12/24
CO #77 $7,240.93 Working Days 02/12/24
CO #78 $7,616.16 Working Days 02/12/24
CO #75 $11,058.04 Working Days 02/12/24
CO #76 $5,111.88 Working Days 02/12/24
CO #79 $4,979.68 Working Days 02/12/24
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
99
CO #81 $1,532.95 Working Days 02/12/24
CO #82 $4,861.51 Working Days 02/12/24
CO #80 $1,284.55 Working Days 02/12/24
CHANGE ORDER
NUMBER COST AMOUNT SCHEDULE
EXTENSION DATE
CO #85 $8,985.97 Working Days 02/12/24
CO #86 $8,604.89 Working Days 02/12/24
CO #83 $8,438.05 Working Days 02/12/24
CO #84 $14,145.08 Working Days 02/12/24
CO #89 VOID Working Days 02/24/24
CO #90 $0.00 Working Days 02/24/24
CO #87 $4,895.73 Working Days 02/12/24
CO #88 $12,307.50 Working Days 02/24/24
CO # 93 $15,295.33 Working Days 02/24/24
CO #94 $20,070.50 Working Days 02/24/24
CO #91 $8,378.63 Working Days 02/24/24
CO #92 $1,279.29 Working Days 02/24/24
CO #97 $69,500.00 Working Days 02/24/24
CO # Working Days
CO #95 $75,483.41 Working Days 05/13/24
CO #96 -$135,000.00 Working Days 05/13/24
CO # Working Days
CO # Working Days
CO # Working Days
CO # Working Days
CO # Working Days
CO # Working Days
CO # Working Days
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Cost Estimate - Sunbeam Consulting
CO #97 - Time Extension - PCO#43
Days Rate
99 -$ -$
62 -$ -$
37 1,717.91$ 63,562.67$
-$ -$
-$ -$
-$ -$
63,562.67$
7%4,449.39$
1.50%953.44$
68,965.50$
1%689.65$
69,655.15$
(155.15)$
69,500.00$
Insurance
TOTAL AGREED COST OF CO 97
Negotiated adjustment (credit)
Sub-total
Bond
Markup
General Conditions Costs
Extension of time due to delay
Unavoidable (Non-Compensable) Days
City-Caused (Compensable) Delays
Subtotal
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Sunbeam Consulting
1817 Josie Avenue
Long Beach, California 90815
Ladera Linda Schedule Assessment 1 | P a g e o f 7
SCHEDULE ANALYSIS REPORT
TO: RAMZI AWWAD, DIRECTOR OF PUBLIC WORKS
FROM: ALAN BRAATVEDT, SUNBEAM CONSULTING
REVIEWED AND
EDITED BY: DAVID COPP, DEPUTY DIRECTOR OF PUBLIC WORKS
DATE: MAY 29, 2024
SUBJECT: LADERA LINDA COMMUNITY PARK
EVALUATION OF THE PROJECT SCHEDULE
Executive Summary
The City of Rancho Palos Verdes contracted with Sunbeam Consulting to investigate the
reasons for late completion of the project and to establish a revised contractual
completion date for the project based on the analysis of the available information and
reasonable assumptions for the delays experienced and the apportioning of the
responsibility for those delays.
Sunbeam’s schedule analysis was performed by assessing the potential impact that any
changes or unforeseen conditions could have had on the critical path of the project.
Multiple circumstances affected the critical path, effectively delaying the project
completion date from 7/21/23 (original) to 2/23/24 (actual) (+99 working days). There
were several reasons for the sum of the delays, some of which were beyond the control
of the contractor, but others were due to poor management and foresight by the
contractor. Although multiple change orders have been issued as part of the project, much
of that changed/extra work had limited effect on the project completion date. The analysis
separated the delays into three categories:
1. Unavoidable delays - examples: weather events preventing construction, force
majeure events
2. Contractor-caused delays – examples: production inefficiencies, non-
performance of the general contractor or its subcontractors
3. City-caused delays – examples: unforeseen/latent site conditions, scope
changes, design errors & omissions
All durations and delays discussed in this analysis are based on working days. The
revised extended completion date is established after adding delays to the critical path,
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Sunbeam Consulting
1817 Josie Avenue
Long Beach, California 90815
Ladera Linda Schedule Assessment 2 | P a g e o f 7
deemed to be beyond the contractor’s ability to control (unavoidable and city-caused)
and then deducting Contractor-caused delays.
The schedule analysis ultimately forms the basis of issuing a change order as follows:
1. Granting a non-compensable time extension equating to the duration of the sum
of unavoidable delays (37 working days)
2. Granting a compensable time extension equating to the duration of the sum of city-
caused delays (99 working days) and applying the duration to a negotiated daily
rate of field office and general conditions, as allowed by the contract.
Schedule Analysis
The activities assessed for their impacts to the project schedule critical path included
the following:
1. Abatement and removal of existing unforeseen asbestos water pipe during
demolition phase of construction.
2. Additional days granted for City holidays and rain days.
3. Slow approval of the switchgear submittal.
4. Late delivery of the switchgear.
5. Long lead-time for the energizing of the switchgear.
6. Rain days that prevented work on critical path activities
7. Roll up door compatibility with existing main building frame.
8. Export of soils stop notice.
9. Reduction of the west perimeter fencing and adjacent vegetation.
10. Playground equipment procurement.
1. Abatement and Removal of the Unforeseen Asbestos Water Pipe
The discovery that the water main, scheduled for removal, was an asbestos pipe not
shown on the contract plans and delayed the grading of the building pad by 11-days.
At the time, that activity was on the critical path, which resulted in an 11-day
extension of time being granted as part of change order no. 3. Circumstances
related to the switchgear later established that the critical path shifted to the
procurement and installation of the switchgear and therefore the delay would not
have delayed the overall completion of the project. However, the grading of the pad
to enable the start of building work, was a key milestone, so no additional time
extension is deemed justifiable. The extension revised the contractual completion
date for the project to August 8, 2023.
2. City Holidays and Rain Days
Two additional City holidays were added to the calendar, prohibiting the contractor
from working on those days. The 2-days were granted as an extension of time to the
project as part of change order no. 35. The complete allowance of 25-rain days
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Sunbeam Consulting
1817 Josie Avenue
Long Beach, California 90815
Ladera Linda Schedule Assessment 3 | P a g e o f 7
provided for in the baseline schedule, were accounted for and in addition 6-days in
March and 1-day on August 21 were approved as time extensions as part of change
order nos. 47 and 48. Those additional days shifted the contractual completion date
for the project to August 21, 2023.
3. Approval of the Switchgear Submittal
The baseline schedule showed the switchgear submittal being submitted on 4/27/22,
with a 10-day allowance for review and approval, equating to an anticipated
submittal approval 37 days after NTP. The actual submittal was made on 4/18/22
and returned to AMG in 5-days, on 4/25/22. However, the submittal was rejected
and returned, noting that the “Overcurrent Protective Device Short-Circuit Study”
was missing. The “Overcurrent Protective Device Short-Circuit Study” was
eventually submitted on 7/7/22 for review and was approved and returned on
7/14/22. However, the complete switchgear submittal was not resubmitted until
7/27/22. The submittal was reviewed and returned to AMG as approved on 8/1/22.
The switchgear specification requirements are very clear and the responsibility for
the submittal delays was entirely under the control of AMG. The order for the
switchgear was scheduled to be placed on 5/19/22, but was only placed on 8/2/22, a
delay of 53-days. In total the submittal approval process took 90 days. We view that
delay to be entirely within the control of AMG and was therefore deducted from the
revised completion date.
4. Late delivery of the switchgear
The baseline schedule showed a duration of 150-days for the fabrication and
delivery of the switchgear. The actual delivery was on 6/23/23, which was 234-days
after the placing of the order. Despite the supply chain delivery issues that have
been experienced by the industry since 2019 and the likelihood that the delivery
would be delayed, we do not consider the use of the 150-day duration in the
baseline schedule to be unreasonably short and so have not made any adjustments
for the additional 84-days in the Assessment Schedule. This activity added 84-days
to the revised schedule.
5. Long lead-time for the energizing of the switchgear
Spec Section 262413 Part 3.5 Field Quality Control, which details field testing
requirements after installation, indicates a significant time requirement for the
acceptance and approval of the equipment by the electrical utility company (SCE).
The contractor only provided a 1-day duration for installation and those activities in
the baseline schedule. This failure meant that advanced planning that may have
minimized the impacts of those milestones, was probably not done. Electrical utility
companies require inspections of the installed switchgear, conduits, and utility
enclosure by their own inspectors. The installation and inspections were not
completed until 7/20/23, 17-working days more than provided for in the schedule.
This activity is a shared responsibility with the contractor being liable for 60% of the
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Sunbeam Consulting
1817 Josie Avenue
Long Beach, California 90815
Ladera Linda Schedule Assessment 4 | P a g e o f 7
additional time.
In addition, the application for permanent power from SCE, which was included in
the bid documents for reference, states that there will be a 45 calendar-day
scheduling window after receiving inspection approval. No provision was made for
that activity in the baseline schedule, although it is not clear whether AMG would
have been able to mitigate impacts associated with the delay. The electrical system
was energized on 9/8/23, 52-days after the switchgear was received (+7 WD longer
than baselined in the bid documents). This activity is a shared responsibility with the
contractor being liable for 60% of the additional time.
Energizing the switchgear (and facility) was a predecessor activity to climatizing the
building. The only activities affected by the climatizing of the building are cabinetry
and tackboard. The other activities were delayed until after permanent power had
been established included: The testing the functioning of the electrically powered
devices and systems; and the commissioning of the building. The baseline schedule
shows that all other activities in the building and site-work, except for
commissioning, were to be completed by May 30, 2023.
The baseline schedule showed the total duration for the activities, viewed as those
that could not be done until the space had a functioning HVAC system are as
follows:
- Install casework: 17-days
- Install counter tops: 10-days
- Install acoustical wall panels and tackable wall surfaces: 6-days
- Electrical Finishes: 20-days
In the Assessment Schedule, the casework, counter tops and acoustical wall panels
were regarded as sequential work, totaling 33-days, however the electrical finishes
were regarded as concurrent work, being performed by a different trade.
The baseline schedule showed the total duration for the commissioning activities for
the building were viewed as sequential activities that were done only after all other
functions were complete. The sequence of tasks and durations was left untouched in
the Assessment Schedule, except for the testing of the irrigation system, which
should be a concurrent activity, performed by a different trade. The total duration of
the commissioning shown in the Assessment Schedule is 18-days. It should be
noted that the December 4, 2023 schedule shows the total of all commissioning
activities as 5-days
Had the contractor been on schedule, with the contractual completion date of
7/24/23, plus granted extensions of time (8/21/23), the punch list items would have
been completed and signed off by that date. The only punch list exceptions would
have been for cabinetry and commissioning, so only an additional 2-days of the
original 10-days to address punch list issues was assigned in the Assessment
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Sunbeam Consulting
1817 Josie Avenue
Long Beach, California 90815
Ladera Linda Schedule Assessment 5 | P a g e o f 7
Schedule.
6. Rain days that prevented work on critical path activities
In terms of Specification section: 1.3.G.6 Construction Progress Schedule, 25-days
were included in the baseline schedule for rain days, to provide time extension to the
project completion date for inclement weather-related days, for critical path work.
The delays in the procurement and energizing of the switchgear became the critical
path for the project. The shifting of the critical path to the switchgear activities meant
that no weather-related time was lost to critical path work during the project up to the
date of permanent energizing.
7. Roll-up Door compatibility Issues associated with the main building frame
(Contractor PCOs 53A & 53B and City Change Order No. 98)
There have been several issues related to the roll-up doors including the conflict with
the door handles, power, disconnect switches and operating signal. Each of the
issues was addressed in RFI responses. The plan details were incomplete and did
not address critical issues that had to be dealt with through extensive discussions
between the architect and installers, which led to several changes, addressed in RFI
53, however some of the extended delays point to poor management of the issues.
In reference to the timeline of events analyzed as part of change order no. 98, that
were necessary to resolve design conflicts between the roll-up doors and building
frame, the City’s exposure was in exceedance of a month, approximately 20 working
days. Accounting for intermediate actions within that timeframe in the contractor’s
court, the City’s minimum exposure to this delay is approximately 16 working days.
8. Export of Dirt Stop Notice
The City directed the suspension of the export of dirt stockpile on April 18. It is
acknowledged that there was a cost impact related to those stoppages, however the
delays had limited impact to the final completion date of the project as that and
successive activities were not shown to be on the critical path and the suspension of
work had little effect to the critical path.
9. Reduction of the height of the west perimeter fence and adjacent vegetation
There were delays by the city in the decisions that were made to reduce the height
of the fencing and adjacent landscape. It appears that the City council made a
decision in December and then reversed it and issued a new directive in March
2023. Although this was out of sequence work and executed in several phases, it
appears that directives were provided no later than in May 2023. This provided
sufficient time to schedule the work well before the extended completion date of
August 21, therefore no extension of time for the changed scope of work was
considered.
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Sunbeam Consulting
1817 Josie Avenue
Long Beach, California 90815
Ladera Linda Schedule Assessment 6 | P a g e o f 7
10. Playground Equipment Procurement
The submittal and procurement of the playground equipment were significant items
that were not identified on the baseline schedule. Had the submittal process begun
in April or May, the issue of availability would have become apparent sooner and the
issue could have been resolved within a couple of months. The equipment was
finally installed 15-months later than originally scheduled. This extensive delay can
only be attributed to poor planning.
Summary of Project Impacts
The table below summarizes the impacts analyzed above, and their relative share of
exposure between the City and the Contractor
Conclusions:
It is recommended that the Contractor be granted compensation only relative to the
City’s total share of delays it caused to the schedule critical path (37 days). Although
the total time justifiable amounts to more than the 99 days between the current
approved contract completion date and the date of notice of substantial completion, the
City’s decision to occupy the facility on 2/23/24 effectively served as project completion
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Sunbeam Consulting
1817 Josie Avenue
Long Beach, California 90815
Ladera Linda Schedule Assessment 7 | P a g e o f 7
date, understanding that some minor activities were pending completion by the
Contractor.
As such it is recommended that the contractual completion date be revised to
2/23/2024, which equates to a total time extension of 99 days, 37 days of which are
City-caused and therefore compensable.
Alan Braatvedt
Sunbeam Consulting
DocuSign Envelope ID: 5DECB5FA-314D-494E-A13E-489BB2C77F38
Certificate Of Completion
Envelope Id: 5DECB5FA314D494EA13E489BB2C77F38 Status: Completed
Subject: Complete with Docusign: Change Order 97 packet.pdf
Source Envelope:
Document Pages: 17 Signatures: 3 Envelope Originator:
Certificate Pages: 5 Initials: 1 James O'Neill
AutoNav: Enabled
EnvelopeId Stamping: Enabled
Time Zone: (UTC-08:00) Pacific Time (US & Canada)
30940 Hawthorne Blvd.
Rancho Palos Verdes, CA 90275
joneill@rpvca.gov
IP Address: 72.34.97.146
Record Tracking
Status: Original
6/18/2024 5:52:46 PM
Holder: James O'Neill
joneill@rpvca.gov
Location: DocuSign
Signer Events Signature Timestamp
David Copp
dcopp@rpvca.gov
Deputy Director of Public Works
City of Rancho Palos Verdes
Security Level: Email, Account Authentication
(None)
Signature Adoption: Uploaded Signature Image
Using IP Address: 72.34.97.146
Sent: 6/18/2024 5:54:50 PM
Viewed: 6/19/2024 8:43:40 AM
Signed: 6/19/2024 8:44:24 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Ramzi Awwad
rawwad@rpvca.gov
Director of Public Works
City of Rancho Palos Verdes
Security Level: Email, Account Authentication
(None)
Signature Adoption: Drawn on Device
Using IP Address: 72.34.97.146
Sent: 6/19/2024 8:44:25 AM
Viewed: 6/19/2024 10:06:23 AM
Signed: 6/19/2024 10:06:35 AM
Electronic Record and Signature Disclosure:
Accepted: 3/2/2023 10:45:19 AM
ID: 3242b72d-4755-489d-8e5f-7c62dc360470
Vina Ramos
vramos@rpvca.gov
Director of Finance
City of Rancho Palos Verdes
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 172.117.19.238
Sent: 6/19/2024 10:06:37 AM
Viewed: 6/20/2024 1:20:49 AM
Signed: 6/20/2024 1:20:55 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Ara Mihranian
aram@rpvca.gov
City Manager
City of Rancho Palos Verdes
Security Level: Email, Account Authentication
(None)
Signature Adoption: Uploaded Signature Image
Using IP Address: 72.34.97.146
Sent: 6/20/2024 1:20:56 AM
Viewed: 6/20/2024 10:03:27 AM
Signed: 6/20/2024 10:03:47 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
City Clerk
cityclerk@rpvca.gov
Security Level: Email, Account Authentication
(None)
Sent: 6/20/2024 10:03:49 AM
Viewed: 6/27/2024 6:13:20 PM
Electronic Record and Signature Disclosure:
Accepted: 2/1/2023 3:10:58 PM
ID: 505eed45-7ed0-4db8-aae6-ef6eedfef03d
Lorna Cloke
lornac@rpvca.gov
Security Level: Email, Account Authentication
(None)
Sent: 6/20/2024 10:03:50 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Alan Braatvedt
alan@sunbeamtech.net
Security Level: Email, Account Authentication
(None)
Sent: 6/20/2024 10:03:51 AM
Viewed: 6/20/2024 9:09:31 PM
Electronic Record and Signature Disclosure:
Accepted: 6/20/2024 1:00:55 PM
ID: 91787e6f-c521-4e94-8b58-4ce75cc5cd89
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 6/18/2024 5:54:50 PM
Certified Delivered Security Checked 6/20/2024 10:03:27 AM
Signing Complete Security Checked 6/20/2024 10:03:47 AM
Completed Security Checked 6/20/2024 10:03:51 AM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, City of Rancho Palos Verdes (we, us or Company) may be required by law to
provide to you certain written notices or disclosures. Described below are the terms and
conditions for providing to you such notices and disclosures electronicall y through the DocuSign
system. Please read the information below carefully and thoroughly, and if you can access this
information electronically to your satisfaction and agree to this Electronic Record and Signature
Disclosure (ERSD), please confirm your agreement by selecting the check-box next to ‘I agree to
use electronic records and signatures’ before clicking ‘CONTINUE’ within the DocuSign
system.
Getting paper copies
At any time, you may request from us a paper copy of any record provided or made av ailable
electronically to you by us. You will have the ability to download and print documents we send
to you through the DocuSign system during and immediately after the signing session and, if you
elect to create a DocuSign account, you may access the documents for a limited period of time
(usually 30 days) after such documents are first sent to you. After such time, if you wish for us to
send you paper copies of any such documents from our office to you, you will be charged a
$0.00 per-page fee. You may request delivery of such paper copies from us by following the
procedure described below.
Withdrawing your consent
If you decide to receive notices and disclosures from us electronically, you may at any time
change your mind and tell us that thereafter you want to receive required notices and disclosures
only in paper format. How you must inform us of your decision to receive future notices and
disclosure in paper format and withdraw your consent to receive notices and disclosures
electronically is described below.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. Further, you will no longer be able to use the DocuSign system to
receive required notices and consents electronically from us or to sign electronically documents
from us.
All notices and disclosures will be sent to you electronically
Electronic Record and Signature Disclosure created on: 6/15/2021 5:55:39 PM
Parties agreed to: Ramzi Awwad, City Clerk, Alan Braatvedt
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through the DocuSign system all required notices, disclosures,
authorizations, acknowledgements, and other documents that are required to be provided or made
available to you during the course of our relationship with you. To reduce the chance of you
inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process, please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
How to contact City of Rancho Palos Verdes:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to: terit@rpvca.gov
To advise City of Rancho Palos Verdes of your new email address
To let us know of a change in your email address where we should send notices and disclosures
electronically to you, you must send an email message to us at terit@rpvca.gov and in the body
of such request you must state: your previous email address, your new email address. We do not
require any other information from you to change your email address.
If you created a DocuSign account, you may update it with your new email address through your
account preferences.
To request paper copies from City of Rancho Palos Verdes
To request delivery from us of paper copies of the notices and disclosures previously provided
by us to you electronically, you must send us an email to terit@rpvca.gov and in the body of
such request you must state your email address, full name, mailing address, and telephone
number. We will bill you for any fees at that time, if any.
To withdraw your consent with City of Rancho Palos Verdes
To inform us that you no longer wish to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your signing session, and on the subsequent page,
select the check-box indicating you wish to withdraw your consent, or you may;
ii. send us an email to terit@rpvca.gov and in the body of such request you must state your
email, full name, mailing address, and telephone number. We do not need any other information
from you to withdraw consent.. The consequences of your withdrawing consent for online
documents will be that transactions may take a longer time to process..
Required hardware and software
The minimum system requirements for using the DocuSign system may change over time. The
current system requirements are found here: https://support.docusign.com/guides/signer-guide-
signing-system-requirements.
Acknowledging your access and consent to receive and sign documents electronically
To confirm to us that you can access this information electronically, which will be similar to
other electronic notices and disclosures that we will provide to you, please confirm that you have
read this ERSD, and (i) that you are able to print on paper or electronically save this ERSD for
your future reference and access; or (ii) that you are able to email this ERSD to an email address
where you will be able to print on paper or save it for your future reference and access. Further,
if you consent to receiving notices and disclosures exclusively in electronic format as described
herein, then select the check-box next to ‘I agree to use electronic records and signatures’ before
clicking ‘CONTINUE’ within the DocuSign system.
By selecting the check-box next to ‘I agree to use electronic records and signatures’, you confirm
that:
You can access and read this Electronic Record and Signature Disclosure; and
You can print on paper this Electronic Record and Signature Disclosure, or save or send
this Electronic Record and Disclosure to a location where you can print it, for future
reference and access; and
Until or unless you notify City of Rancho Palos Verdes as described above, you consent
to receive exclusively through electronic means all notices, disclosures, authorizations,
acknowledgements, and other documents that are required to be provided or made
available to you by City of Rancho Palos Verdes during the course of your relationship
with City of Rancho Palos Verdes.