AMG and Associates Inc (Change Order 085)City of Rancho Palos Verdes
Department of Public Works
30940 Hawthorne Blvd, Rancho Palos Verdes, CA 90275
(310)544-5252
CHANGE ORDER MEMORANDUM
TO: RAMZI AWWAD, DIRECTOR OF PUBLIC WORKS
FROM: ALAN BRAATVEDT, SUNBEAM CONSULTING
DATE: FEBRUARY 1, 2024
SUBJECT: LADERA LINDA COMMUNITY PARK
CONSTRUCTION CHANGE ORDER NUMBER: 85
Description of Construction Change Order
Contractor shall accommodate the utility company’s (Southern California Edison, SCE)
transformer installation schedule by completing work out of sequence from the contract’s
baseline schedule, and in turn mitigating impacts to the project completion schedule as
follows:
(1) re-mobilize paving equipment to the project’s driveway following completion of SCE’s
scope of work
(2) provide a partial load of hot mix asphalt to pave over the backfilled trench associated
with SCE’s transformer installation within the remaining portion of unpaved driveway.
This out-of-sequence approach to paving the driveway in two mobilizations instead of one
provides for providing permanent power to the project while mitigating delays to the
overall project schedule.
Justification
Part of SCE’s transformer installation work required the Contractor’s trench from the
temporary power connection (also the location of the property’s previous permanent
power source) to remain open until the permanent power was energized and the
temporary power disconnected.
The project’s baseline schedule, a contract document, identified the following related
activities:
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
City of Rancho Palos Verdes
Department of Public Works
30940 Hawthorne Blvd, Rancho Palos Verdes, CA 90275
(310)544-5252
The full completion of activity nos. 273, 310, 311 and 519 relied on SCE’s transformer
installation to complete. Relative to the baseline schedule, SCE’s work was delayed
without any communicated timeframe when they would be on site to perform their work.
In other words, the total duration of SCE’s delay was not known by any party. In the
meantime, critical path work (i.e. the sequence of activities on the schedule that if delayed,
impacts the construction contract completion date) following the above-tabulated
activities relied on the driveway being paved (activity #519). Ultimately, a decision had
to be made whether to suspend all remaining schedule critical path work until SCE
completed their work at an unknown future date or consider resequencing the driveway
pavement work to allow for successive critical path activities to progress.
Any delay associated with SCE’s (a third party) work that could impact the project
schedule was outside of the Contractor’s control (not the fault of the Contractor), and
therefore is considered at minimum, a non-compensable excusable delay. However, this
delay would ultimately delay the overall completion of the Park. The City wanted to
eliminate this risk to the completion date of the park and direct the Contractor to pave
areas of the driveway not in conflict with SCE’s pending transformer installation and
associated trench within the driveway limits. The open trench would be protected until
SCE completed their work and the trench could be backfilled and paved. This work re-
sequencing approach would allow for successive critical path construction activities to
continue without construction delays being associated with SCE’s delay in completing
their work within the limits of the driveway.
The City’s directed change to the sequence of work required:
(1) a second (additional) mobilization by the paving subcontractor to pave the remaining
section of driveway following SCE’s (delayed) installation of the transformer and
successive back-fill of the trench within the driveway.
(2) a partial/short-load of hot mix asphalt as part of the second mobilization, which
resulted in a higher unit cost for paving the small remaining section of driveway.
SCE’s actual finish date for installing the transformer was 9/8/22 (+2 months from
baseline). Schedule delays exclusively associated with utility companies’ performance
are not the fault of the Contractor, unless explicitly specified in the contract (in this project
it was not). Further, the above-described City-directed, out-of-sequence work was not a
part of the original contract documents, including the approved baseline schedule and the
contractor’s associated bid. Therefore, a change order needs to be issued to account for
this change to the sequence of work in the project schedule and the associated additional
cost to complete the driveway paving work in a less cost-efficient manner.
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
City of Rancho Palos Verdes
Department of Public Works
30940 Hawthorne Blvd, Rancho Palos Verdes, CA 90275
(310)544-5252
Cost Analysis
Negotiations between the City and Contractor resulted in a reduction to their original
proposal, as reflected in PCO 67 R1.
A detailed breakdown of labor, equipment and materials was provided by the
subcontractor Act 1 Construction for a total cost of $8,200.00.
AMG listed the subcontractor quote of $8,200.00 and added 7% Overhead, 1.5%
Insurance, and 1% Bond markups for a total of $8,985.97.
The Contractor’s revised cost proposal is within 5% of SunBeam’s independently
estimated cost. SunBeam recommends that the City authorize the costs proposed by
AMG.
Schedule Analysis
As agreed with the Contractor, an analysis of the schedule impact of this work will be
addressed as part of a meet and confer process for overall completion of the project.
This approach is consistent with the changes to the standard change order provisions
as approved by the City Attorney.
Attachments:
Construction Contract Change Order Form
Construction Contract Change Order Summary Sheet
Contractor’s Change Order Proposal
Independent Cost Analysis
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
8405
44
0
0
11
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
CONSTRUCTION CHANGE ORDER SUMMARY SHEET
PROJECT NAME:Ladera Linda Community Park DATE:02/12/24
PROJECT CODE:
PURCHASE ORDER NUMBER:20220215
ACCOUNT NUMBER:330-400-8405-8403
ORIGINAL CONTRACT AMOUNT:$13,721,000.00 ORIGINAL CONTINGENCY AMOUNT:
PREPARED BY:JAMES O'NEILL
CONTRACTOR NAME:AMG & Associates, Inc.
CONTRACT NUMBER:FY2022-050
$1,029,075.00
TOTAL CHANGE ORDERS COST:$999,597.62 REVISED CONTINGENCY AMOUNT:$1,208,194.98
NEW CONTRACT AMOUNT:$14,720,597.62 REMAINING CONTINGENCY AMOUNT:$208,597.36
CHANGE ORDER
NUMBER COST AMOUNT SCHEDULE
EXTENSION DATE
CO#1 $54,534.52 Working Days 05/27/22
ORIGINAL COMPLETION DATE:07/27/23
TOTAL SCHEDULE CHANGE ORDERS:Working Days
NEW CONTRACT COMPLETION DATE:08/24/23
CO#4 $8,558.42 Working Days 09/01/22
CO#5 -$5,378.25 Working Days 09/01/22
CO#2 $12,628.58 Working Days 08/09/22
CO#3 $53,526.25 Working Days 08/31/22
CO#8 $6,437.02 Working Days 09/27/22
CO#9 $1,818.52 Working Days 11/09/22
CO#6 $824.34 Working Days 09/01/22
CO#7 $10,202.36 Working Days 09/27/22
CO#11 $33,868.27 Working Days 12/01/22
CO#12 $9,052.32 Working Days 12/01/22
CO#10 $42,918.80 Working Days 11/09/22
CO#15 -$3,117.01 Working Days 01/17/23
CO#16 $59,788.90 Working Days 02/02/23
CO#13 $0.00 Working Days 12/30/22
CO#14 -$20,112.42 Working Days 12/30/22
CO#19 $17,562.82 Working Days 02/09/23
CO#20 $3,679.17 Working Days 02/16/23
CO#17 $12,582.87 Working Days 02/03/23
CO#18 $16,546.62 Working Days 02/09/23
CO#23 $4,094.67 Working Days 02/23/23
CO#24 $19,573.51 Working Days 03/07/23
CO#21 $10,075.07 Working Days 02/21/23
CO#22 $3,178.42 Working Days 02/22/23
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
4/17/2024
0
0
0
0
0
0
0
0
0
0
2
0
0
0
0
0
0
0
0
0
0
0
6
1
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
24
0
0
0
0
0
0
0
0
0
0
0
0
CHANGE ORDER
NUMBER COST AMOUNT SCHEDULE
EXTENSION DATE
CO#27 $136,226.21 Working Days 05/03/23
CO#28 $10,819.96 Working Days 05/05/23
CO#25 $8,909.82 Working Days 04/06/23
CO#26 $21,061.12 Working Days 04/25/23
CO#31 $2,104.03 Working Days 05/18/23
CO#32 $2,291.43 Working Days 05/19/23
CO#29 $1,055.31 Working Days 05/09/23
CO#30 $3,682.06 Working Days 05/18/23
CO #35 $3,765.15 Working Days 06/08/23
CO #36 $697.56 Working Days 06/16/23
CO #33 $10,095.54 Working Days 05/31/23
CO #34 $179,119.98 Working Days 06/08/23
CO #39 $24,530.09 Working Days 07/25/23
CO #40 $11,002.33 Working Days 07/26/23
CO # 37 $3,561.51 Working Days 06/16/23
CO #38 $23,527.90 Working Days 07/12/23
CO #43 $1,647.09 Working Days 08/24/23
CO #44 $23,867.61 Working Days 08/29/23
CO #41 $630.12 Working Days 07/26/23
CO #42 $6,466.62 Working Days 08/03/23
CO #47 $0.00 Working Days 10/10/23
CO #48 $0.00 Working Days 10/10/23
CO #45 $35,792.08 Working Days 10/10/23
CO #46 -$6,270.83 Working Days 10/10/23
CO #51 -$44,040.60 Working Days 10/10/23
CO #52 $6,575.10 Working Days 10/12/23
CO #49 -$3,253.37 Working Days 10/10/23
CO #50 $246.57 Working Days 10/10/23
CO #55 -$19,277.91 Working Days 12/14/23
CO #56 -$35,244.14 Working Days 12/21/23
CO #53 -$2,446.03 Working Days 12/05/23
CO #54 $1,807.98 Working Days 12/05/23
CO #59 $8,890.83 Working Days 01/02/24
CO #60 $9,524.04 Working Days 01/10/24
CO #57 $8,575.63 Working Days 12/28/23
CO #58 $982.98 Working Days 12/28/23
CO #63 $690.91 Working Days 02/12/24
CO #64 $2,200.00 Working Days 02/12/24
CO #61 $5,590.13 Working Days 01/11/24
CO #62 $2,674.08 Working Days 02/12/24
CO #67 $36,343.87 Working Days 02/12/24
CO #68 $3,203.68 Working Days 02/12/24
CO #65 $251.55 Working Days 02/12/24
CO #66 $47,423.41 Working Days 02/12/24
CO #71 $9,892.05 Working Days 02/12/24
CO #72 $10,556.39 Working Days 02/12/24
CO #69 $4,599.28 Working Days 02/12/24
CO #70 $5,364.69 Working Days 02/12/24
CO #75 $11,058.04 Working Days 02/12/24
CO #76 $5,111.88 Working Days 02/12/24
CO #73 $1,376.77 Working Days 02/12/24
CO #74 $4,408.47 Working Days 02/12/24
CO #79 $4,979.68 Working Days 02/12/24
CO #77 $7,240.93 Working Days 02/12/24
CO #78 $7,616.16 Working Days 02/12/24
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
0
0
0
0
0
0
CHANGE ORDER
NUMBER COST AMOUNT SCHEDULE
EXTENSION DATE
CO #80 $1,284.55 Working Days 02/12/24
CO #83 $8,438.05 Working Days 02/12/24
CO #84 $14,145.08 Working Days 02/12/24
CO #81 $1,532.95 Working Days 02/12/24
CO #82 $4,861.51 Working Days 02/12/24
CO #85 $8,985.97 Working Days 02/12/24
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
Contractor shall accommodate the utility company’s (Southern California Edison, SCE) transformer installation schedule by completing work out of sequence from the
contract’s baseline schedule as follows: re-mobilize paving equipment to the project’s driveway and provide a partial load of hot mix asphalt to pave over the backfilled
trench associated with SCE’s transformer installation within the remaining portion of unpaved driveway. This out-of-sequence approach to paving the driveway in two
mobilizations instead of one provides for providing permanent power to the project while mitigating delays to the overall project schedule.
TBD
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
4/16/2024
4/16/2024
4/19/2024
AMG & Associates Inc.
26535 Summit Circle
Santa Clarita, California 91350
Phone: (661) 251-7401
Project: 01-22-157 - Ladera Linda Community Center and Park
32201 Forrestal Dr.
Rancho Palos Verdes, California 90275
Prime Contract Potential Change Order #067: CE #135 - Driveway Patch
Back
TO: City of Rancho Palos Verdes
30940 Hawthorne Blvd.
Rancho Palos Verdes, California 90275
FROM: AMG & Associates, Inc.
26535 Summit Circle
Santa Clarita, California 91350
PCO NUMBER/REVISION: 067 / 1 CONTRACT:City Project No. 8405 - Ladera Linda
Community Park Project
REQUEST RECEIVED FROM: Alex Witham (ACT1 Construction)CREATED BY: Christopher Tumasone (AMG &
Associates, Inc.)
STATUS: Pending - In Review CREATED DATE: 8/3/2023
REFERENCE: PRIME CONTRACT
CHANGE ORDER:
None
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED:No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $8,985.97
POTENTIAL CHANGE ORDER TITLE: CE #135 - Driveway Patch Back
CHANGE REASON: Client Request
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #135 - Driveway Patch Back
Cost for added mobilization and provide a short pour of AC paving at driveway once Edison scope is complete.
Revised package with cost backup. 1/24
ATTACHMENTS:
PCO #067 Driveway Patch Back.pdf , PCO#20 AC Patchback.pdf
#Budget Code Description Amount
1 03-100.S Concrete Formwork, Reinforcement and
Materials.Commitment AC patch back at driveway due to Edison delay $8,200.00
Subtotal:$8,200.00
Overhead (7.00% Applies to all line item types.):$574.00
Insurance (1.50% Applies to all line item types.):$123.00
Bonding (1.00% Applies to all line item types.):$88.97
Grand Total:$8,985.97
City of Rancho Palos Verdes AMG & Associates, Inc.
30940 Hawthorne Blvd. 26535 Summit Circle
Rancho Palos Verdes, California 90275 Santa Clarita, California 91350
ProcoreArchitectSignHere ProcoreArchitectSignedDate ProcoreOwnerSignHere ProcoreOwnerSignedDate ProcoreGeneralContractorSignHere ProcoreGeneralContractorSignedDate
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
AMG & Associates Inc.Page 1 of 1 Printed On: 1/24/2024 07:08 AM
PCO #067
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
PCO 20 Short Pour AC Patch Back
ACT 1 Construction, Inc. Date: 7/19/23
P.O. Box 5087 To: Tony Traverso
Norco, CA, 92860 Company: AMG & Associates
P: 951-735-1184 F: 951-737-5342
CA License: #657517
Project Ladera Linda Community Park ESTIMATOR Alex Witham
ITEM
#
DESCRIPTION
UNIT OF
MEASURE
EST
UNIT
PRICE
EXT
PRICE
1 Cost for added mobilization and provide a short pour of AC paving
@ driveway adjacent to SCE transformer due to demo of new AC
Paving at SCE transformer for Conduit and pad installation.
LS 1 $8,200.00 $8,200.00
2
3
4
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
Total $8,200.00
Exclusions:
Damage to underground lines not clearly marked and shown to contractor prior to start of excavation.
Removal or disposal of any foreign or deleterious materials encountered during excavation or objects,
either natural or man-made, larger than 2’x2’ which require a breaker.
Cost or responsibility of any surveying, soils testing, or engineering test of any type.
Responsibility for conditions to hardscape as a result of improper sub base or lack of compaction, unless
compaction and/or installation of sub base are quoted in this proposal.
Any damage to any concrete or asphalt in order to obtain access to working area.
Any item not specifically listed above.
Bid is based on 1 move-in & prevailing wages. Additional move -ins will be billed at $8,950.00 per move
Bid excludes Cut and/or Fill of subgrade unless specified in above line items of bid.
Bid Excludes Crack-Fill
Bid excludes Fog Seal, Street Clean up from Delivery Trucks Tracking “Tack” Material.
Water and Meter to be provided by customer.
* Concrete is a combination of natural and man-made materials which can result in slight variations,
although we take every measure to prevent it, cracking can naturally occur and we make no warranties against it.
We propose to furnish material and labor, complete in accordance with above specifications, for the
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
sum of: Eight Thousand Two Hundred Dollars
and 00/100 Dollars $ $8,200.00
Payments to be made as follows: As invoiced per contract
Contractor’s signature: Don Trenholm
Acceptance of proposal: The above price, specifications and conditions are satisfactory and are hereby
accepted. You are authorized to do the work as specified. Payment will be made as outlined above.
Owner’s signature: Date:
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
JOB NAME:JOB #: 01-22-157
UQTY.UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
COST COST COST COST COST COST COST COST
HR 30 69.49$ 2,084.70$ -$ -$ -$
Day 1 -$ -$ 1,200.00$ 1,200.00$ -$
HR 5 -$ -$ 42.27$ 211.35$ -$
HR 5 -$ -$ 35.00$ 175.00$ -$
HR 5 -$ -$ 285.00$ 1,425.00$ -$
LS 1 -$ 400.00$ 400.00$ -$ -$
HR 5 89.78$ 448.90$ -$ -$ -$
Day 1 -$ -$ 140.00$ 140.00$ -$
1-$ -$ -$ -$
1-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
TOTAL 2,533.60$ TOTAL 400.00$ TOTAL 3,151.35$ TOTAL -$
UQTY.COSTAS AS
%$
-$
-$
-$
-$
-$
-$
COMBINED TOTAL
AS %AS $
1)29.00% 734.74$
2)8.75% 35.00$
3)8.75% 275.74$
4)0.00% -$
AS %AS $
15% 490.25$
15% 579.31$
9% -$
9% -$
-$
-$
COMBINED TOTALS
-$
Operator
OTHER EXP.
DESCRIPTION
LABOR
MATERIAL
OTHER EXPENDITURES
SUBCONTRACTOR
7,130.44$
G.C. COSTS (ITEM 1)
TOTAL
3,758.60$
PRIME CONTRACTOR MARKUPSUBTOTAL
3,268.34$
TOTAL
3,268.34$
RENTAL EQUIPMENT
435.00$ 400.00$
3,427.09$
DESCRIPTION SUBTOTAL
2,533.60$
-$
LINE ITEM
SUB CONTRACTOR (EXCESS OF $5000)
DIRECT PRIME CONTRACTOR TOTALS
MARKUP
TOTALS
-$
Roller
PRIME CONTRACTOR
-$
-$
6,084.95$
4,441.41$ 3,862.09$
-$
-$ -$
1.00% -$
G.C. COSTS (ITEM 2,3,4)
Ladera Linda Community Center and Park
BONDING
GENERAL CONTRACTORS COSTS
SUMMARY OF PROFIT AND OVERHEAD
SUB CONTRACTOR (UP TO $5000)-$
Change Order Request
Laborer GP3 6 men 5HR each
MATERIAL EQUIPMENT RENTAL
-$
LINE ITEM
DESCRIPTION:
LABOR
Ccrew Truck with hand tools
Bob Cat
Vibe Plate
-$
Short Pour Asphalt
Dump truck W/ Trailer
Cost for additional movin in due to SCE and utilities being in the way not allowing for completion of the work in 1 move in.
Added calendar days this request
# 20
8,200.00$
3,151.35$
CSLB# 657517, A, B, C‐8, C‐12, C‐29 444 Sixth St. Norco CA 92860 * 951‐735‐1184
10/23/2023---2:07 PM
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
Sunbeam Consulting
1817 Josie Avenue
Long Beach, California
Cost Estimate - Sunbeam Consulting
CO #85 - AC paving at driveway
SUBCONTRACTOR 1-Act 1 Hrs Rate
AC paving at driveway 3,500.00$ 1,000.00$ 40 86.30$ 3,452.00$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
3,500.00$ 1,000.00$ 3,452.00$
Subtotal 7,952.00$
Mobilization 250.00$
Sales Tax 97.50$
Insurance 119.28$
Markup 1,192.80$
Bond 79.52$
Total Subcontractor Cost 9,691.10$
CONTRACTOR - AMG
Hrs Rate
-$ -$ 86.30$ -$
-$ -$ 86.30$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$ -$
-$ -$ -$
Subtotal -$
Subcontractor Cost 9,691.10$
Subtotal 9,691.10$
Mobilization -$
Sales Tax -$
Insurance 145.37$
Markup 1,453.67$
Bond 96.91$
Total Cost 11,387.04$
Proposed PCO cost 10,885.97$
Difference ($)(501.07)$
Difference (%)-4.60%
Equipment cost
Equipment cost Material cost Lab cost
Material cost Labor cost
DocuSign Envelope ID: FDC4BC25-92E3-4F5E-A844-C2679C6A3C33
Certificate Of Completion
Envelope Id: FDC4BC2592E34F5EA844C2679C6A3C33 Status: Completed
Subject: Complete with DocuSign: LL_CO.85_Compiled_2024.04.03.pdf
Source Envelope:
Document Pages: 14 Signatures: 3 Envelope Originator:
Certificate Pages: 5 Initials: 1 James O'Neill
AutoNav: Enabled
EnvelopeId Stamping: Enabled
Time Zone: (UTC-08:00) Pacific Time (US & Canada)
30940 Hawthorne Blvd.
Rancho Palos Verdes, CA 90275
joneill@rpvca.gov
IP Address: 72.34.97.146
Record Tracking
Status: Original
4/16/2024 3:53:06 PM
Holder: James O'Neill
joneill@rpvca.gov
Location: DocuSign
Signer Events Signature Timestamp
David Copp
dcopp@rpvca.gov
Deputy Director of Public Works
City of Rancho Palos Verdes
Security Level: Email, Account Authentication
(None)
Signature Adoption: Uploaded Signature Image
Using IP Address: 72.34.97.146
Sent: 4/16/2024 3:59:31 PM
Viewed: 4/16/2024 4:32:42 PM
Signed: 4/16/2024 4:33:20 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Ramzi Awwad
rawwad@rpvca.gov
Director of Public Works
City of Rancho Palos Verdes
Security Level: Email, Account Authentication
(None)
Signature Adoption: Drawn on Device
Using IP Address: 72.34.97.146
Sent: 4/16/2024 4:33:22 PM
Viewed: 4/16/2024 7:51:23 PM
Signed: 4/16/2024 7:51:41 PM
Electronic Record and Signature Disclosure:
Accepted: 3/2/2023 10:45:19 AM
ID: 3242b72d-4755-489d-8e5f-7c62dc360470
Vina Ramos
vramos@rpvca.gov
Director of Finance
City of Rancho Palos Verdes
Security Level: Email, Account Authentication
(None)
Signature Adoption: Pre-selected Style
Using IP Address: 172.117.19.238
Signed using mobile
Sent: 4/16/2024 7:51:43 PM
Viewed: 4/17/2024 7:21:48 AM
Signed: 4/17/2024 7:22:30 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Ara Mihranian
aram@rpvca.gov
City Manager
City of Rancho Palos Verdes
Security Level: Email, Account Authentication
(None)
Signature Adoption: Uploaded Signature Image
Using IP Address: 104.34.113.36
Sent: 4/17/2024 7:22:31 AM
Viewed: 4/19/2024 4:56:58 AM
Signed: 4/19/2024 4:57:30 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
City Clerk
cityclerk@rpvca.gov
Security Level: Email, Account Authentication
(None)
Sent: 4/19/2024 4:57:32 AM
Viewed: 4/22/2024 4:45:22 PM
Electronic Record and Signature Disclosure:
Accepted: 2/1/2023 3:10:58 PM
ID: 505eed45-7ed0-4db8-aae6-ef6eedfef03d
Lorna Cloke
lornac@rpvca.gov
Security Level: Email, Account Authentication
(None)
Sent: 4/19/2024 4:57:32 AM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Alan Braatvedt
alan@sunbeamtech.net
Security Level: Email, Account Authentication
(None)
Sent: 4/19/2024 4:57:33 AM
Electronic Record and Signature Disclosure:
Accepted: 2/27/2024 8:10:15 PM
ID: 0b746f99-ced5-4219-9c03-ed8862c26e90
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps
Envelope Sent Hashed/Encrypted 4/16/2024 3:59:31 PM
Certified Delivered Security Checked 4/19/2024 4:56:58 AM
Signing Complete Security Checked 4/19/2024 4:57:30 AM
Completed Security Checked 4/19/2024 4:57:33 AM
Payment Events Status Timestamps
Electronic Record and Signature Disclosure
ELECTRONIC RECORD AND SIGNATURE DISCLOSURE
From time to time, City of Rancho Palos Verdes (we, us or Company) may be required by law to
provide to you certain written notices or disclosures. Described below are the terms and
conditions for providing to you such notices and disclosures electronicall y through the DocuSign
system. Please read the information below carefully and thoroughly, and if you can access this
information electronically to your satisfaction and agree to this Electronic Record and Signature
Disclosure (ERSD), please confirm your agreement by selecting the check-box next to ‘I agree to
use electronic records and signatures’ before clicking ‘CONTINUE’ within the DocuSign
system.
Getting paper copies
At any time, you may request from us a paper copy of any record provided or made av ailable
electronically to you by us. You will have the ability to download and print documents we send
to you through the DocuSign system during and immediately after the signing session and, if you
elect to create a DocuSign account, you may access the documents for a limited period of time
(usually 30 days) after such documents are first sent to you. After such time, if you wish for us to
send you paper copies of any such documents from our office to you, you will be charged a
$0.00 per-page fee. You may request delivery of such paper copies from us by following the
procedure described below.
Withdrawing your consent
If you decide to receive notices and disclosures from us electronically, you may at any time
change your mind and tell us that thereafter you want to receive required notices and disclosures
only in paper format. How you must inform us of your decision to receive future notices and
disclosure in paper format and withdraw your consent to receive notices and disclosures
electronically is described below.
Consequences of changing your mind
If you elect to receive required notices and disclosures only in paper format, it will slow the
speed at which we can complete certain steps in transactions with you and delivering services to
you because we will need first to send the required notices or disclosures to you in paper format,
and then wait until we receive back from you your acknowledgment of your receipt of such
paper notices or disclosures. Further, you will no longer be able to use the DocuSign system to
receive required notices and consents electronically from us or to sign electronically documents
from us.
All notices and disclosures will be sent to you electronically
Electronic Record and Signature Disclosure created on: 6/15/2021 5:55:39 PM
Parties agreed to: Ramzi Awwad, City Clerk, Alan Braatvedt
Unless you tell us otherwise in accordance with the procedures described herein, we will provide
electronically to you through the DocuSign system all required notices, disclosures,
authorizations, acknowledgements, and other documents that are required to be provided or made
available to you during the course of our relationship with you. To reduce the chance of you
inadvertently not receiving any notice or disclosure, we prefer to provide all of the required
notices and disclosures to you by the same method and to the same address that you have given
us. Thus, you can receive all the disclosures and notices electronically or in paper format through
the paper mail delivery system. If you do not agree with this process, please let us know as
described below. Please also see the paragraph immediately above that describes the
consequences of your electing not to receive delivery of the notices and disclosures
electronically from us.
How to contact City of Rancho Palos Verdes:
You may contact us to let us know of your changes as to how we may contact you electronically,
to request paper copies of certain information from us, and to withdraw your prior consent to
receive notices and disclosures electronically as follows:
To contact us by email send messages to: terit@rpvca.gov
To advise City of Rancho Palos Verdes of your new email address
To let us know of a change in your email address where we should send notices and disclosures
electronically to you, you must send an email message to us at terit@rpvca.gov and in the body
of such request you must state: your previous email address, your new email address. We do not
require any other information from you to change your email address.
If you created a DocuSign account, you may update it with your new email address through your
account preferences.
To request paper copies from City of Rancho Palos Verdes
To request delivery from us of paper copies of the notices and disclosures previously provided
by us to you electronically, you must send us an email to terit@rpvca.gov and in the body of
such request you must state your email address, full name, mailing address, and telephone
number. We will bill you for any fees at that time, if any.
To withdraw your consent with City of Rancho Palos Verdes
To inform us that you no longer wish to receive future notices and disclosures in electronic
format you may:
i. decline to sign a document from within your signing session, and on the subsequent page,
select the check-box indicating you wish to withdraw your consent, or you may;
ii. send us an email to terit@rpvca.gov and in the body of such request you must state your
email, full name, mailing address, and telephone number. We do not need any other information
from you to withdraw consent.. The consequences of your withdrawing consent for online
documents will be that transactions may take a longer time to process..
Required hardware and software
The minimum system requirements for using the DocuSign system may change over time. The
current system requirements are found here: https://support.docusign.com/guides/signer-guide-
signing-system-requirements.
Acknowledging your access and consent to receive and sign documents electronically
To confirm to us that you can access this information electronically, which will be similar to
other electronic notices and disclosures that we will provide to you, please confirm that you have
read this ERSD, and (i) that you are able to print on paper or electronically save this ERSD for
your future reference and access; or (ii) that you are able to email this ERSD to an email address
where you will be able to print on paper or save it for your future reference and access. Further,
if you consent to receiving notices and disclosures exclusively in electronic format as described
herein, then select the check-box next to ‘I agree to use electronic records and signatures’ before
clicking ‘CONTINUE’ within the DocuSign system.
By selecting the check-box next to ‘I agree to use electronic records and signatures’, you confirm
that:
You can access and read this Electronic Record and Signature Disclosure; and
You can print on paper this Electronic Record and Signature Disclosure, or save or send
this Electronic Record and Disclosure to a location where you can print it, for future
reference and access; and
Until or unless you notify City of Rancho Palos Verdes as described above, you consent
to receive exclusively through electronic means all notices, disclosures, authorizations,
acknowledgements, and other documents that are required to be provided or made
available to you by City of Rancho Palos Verdes during the course of your relationship
with City of Rancho Palos Verdes.