CC RES 2023-029 RESOLUTION NO. 2023-29
A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF RANCHO PALOS VERDES APPROVING
THE ROADWAY ASSET MANAGEMENT PROGRAM
— RESIDENTIAL STREETS AND THE CITYWIDE
STREET SWEEPING PROJECTS TO RECEIVE
FUNDING FOR FISCAL YEAR 2023-24 FROM
SENATE BILL NO. 1, THE ROAD REPAIR AND
ACCOUNTABILITY ACT OF 2017.
WHEREAS, Senate Bill No. 1 (SB 1), the Road Repair and Accountability Act of
2017 (Chapter 5, Statutes of 2017), was passed by the Legislature and Signed into law
by the Governor in April 2017 to address the significant multi-modal transportation funding
shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will
ensure the residents of Rancho PalosVerdes are aware of the projects proposed for
funding in our community and which projects have been completed each fiscal year; and
WHEREAS, the City of Rancho Palos Verdes must adopt by resolution a list of
projects proposed to receive fiscal year funding from the Road Maintenance and
Rehabilitation Account (RMRA), created by SB 1, which must include a description and
the location of each proposed project, a proposed schedule for the project's completion,
and the estimated useful life of the improvement; and
WHEREAS, the City of Rancho Palos Verdes will receive an estimated $918,020
in RMRA funding in Fiscal Year 2023-24 from SB 1; and
WHEREAS, this is the seventh year in which the City of Rancho Palos Verdes is
receiving SB 1 funding and will enable the City to continue essential road maintenance
and rehabilitation projects, safety improvements, and increasing access and mobility
options for the traveling public that would not have otherwise been possible without SB'
1; and
WHEREAS, the City of Rancho Palos Verdes has undergone a robust public
process to ensure public input into our community's transportation priorities/the project
list; and
WHEREAS, the City of Rancho Palos Verdes used a Pavement Management
System to develop the SB 1 project list to ensure revenues are being used on the most
high-priority and cost-effective projects that also meet the community's priorities for
transportation investment; and
WHEREAS, the funding from SB 1 will help the City of Rancho Palos Verdes
maintain and rehabilitate streets/roads this year and many similar projects in the future;
and
WHEREAS, the 2018 California Statewide Local Streets and Roads Needs
Assessment found that the City's streets and roads are in "good" condition, and this
revenue will help us increase the overall quality of our road system and, over the next
decade, will bring our streets and roads into an "excellent" condition; and
WHEREAS, the SB 1 project list and overall investment in our local streets and
roads infrastructure with a focus on basic maintenance and safety, investing in complete
streets infrastructure, and using cutting-edge technology, materials, and practices, will
have significant positive co-benefits statewide.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO PALOS
VERDES DOES HEREBY FIND, DETERMINE, AND RESOLVE AS FOLLOWS:
Section 1: The foregoing recitals are true and correct, and incorporated herein by
reference.
Section 2: The following list of projects will be funded in part or solely with Fiscal Year
2023-24 Road Maintenance and Rehabilitation Account revenues:
Project Title: Roadway Asset Management Program — Residential
Streets
Project Description: The Residential Roadways Rehabilitation Program
rehabilitates residential roadways as assessed and
prioritized in the. Pavement Management Program,
updated every 3 years. The scope of work generally
consists of:
• Sealing, resurfacing, and/or repairing existing asphalt
• Repairing damaged curbs, gutters, and sidewalks;
installing curb ramps as needed
• Replacing deteriorated signs, pavement markings, and
curb address numbers
Project Location: Various Residential Streets within City Boundaries.
Amount and Phase: Amount: $1,000,000 Phase: Construction
Estimated Project Schedule: Start: July 2023 Completion: July 2024
Estimated Project Useful Life: 8 years
111
Resolution No 2023-29
Page 2 of 3
Project Title: Street Sweeping - Citywide
Project Description: Mechanical sweeping of residential and arterial/collector
streets, 24 times a year. Western Avenue, a state
highway, will be swept 52 times per year.
Project Location: • Arterial/collector and residential streets throughout the
City.
Amount and Phase: • Amount: $437,900 Phase: Maintenance
Estimated Project Schedule: Start: July 2023 Completion: June 2024
Estimated Project Useful Life: • N/A
PASSED, APPROVED AND ADOPTED this 20st day of June, 2023.
0
I ,
r -erraro,
Barbara ` e Mayor a
Attest
A ,
"eresa =kaoka, City Cler
State of California )
County of Los Angeles ) ss
City of Rancho Palos Verdes )
I, Teresa Takaoka, City Clerk of the City of Rancho Palos Verdes, hereby certify
that the above Resolution No. 2023-29 was duly and regularly passed and adopted
by the said City Council at a regular meeting thereof held on June 20, 2023.
res. = .oka, City Clerk
Resolution No. 2023-29
Page 3 of 3