CC SR 20230404 02 - FY2023-24 Council Goals
CITY COUNCIL MEETING DATE: 04/04/2023
AGENDA REPORT AGENDA HEADING: Regular Business
AGENDA TITLE:
Consideration and possible action to review the proposed draft City Council Goals for
FY2023-24.
RECOMMENDED COUNCIL ACTION:
(1) Review the proposed draft City Council Goals for FY 2023-24, formatted in a Gantt
chart with milestones and tasks supporting each project, based on feedback
provided at the March 15 City Council Goals workshop;
(2) Prioritize the top 12 to 14 projects for FY 2023 -24; and,
(3) If deemed acceptable, direct Staff to return with the final draft of the FY 2023-24 City
Council Goals for approval at the June 20, 2023 meeting.
FISCAL IMPACT: The final City Council-approved Goals for FY 2023-24 may require
funding to support implementing certain goals. Such funding would
have a fiscal impact that would be proposed for consideration as part
of the final budget for FY 2023-24.
Amount Budgeted: N/A
Additional Appropriation: N/A
Account Number(s): N/A
ORIGINATED BY: Karina Bañales, Deputy City Manager
REVIEWED BY: Same as above
APPROVED BY: Ara Mihranian, AICP, City Manager
ATTACHED SUPPORTING DOCUMENTS:
A. Draft FY 2023-24 City Council Goals Worksheet (page A-1)
B. March 15, 2023 staff report
BACKGROUND:
On March 15, 2023, the City Council held its first in a series of budget workshops for FY
2023-24. At the workshop, the City Council received a quarterly status report on FY 2022-
23 City Council Goals and a presentation on the proposed FY 2023-24 City Council Goals
inclusive of Staff, Planning Commission, and advisory board recommendations
(Attachment B). A discussion ensued regarding the proposed FY 2023 -24 City Council
Goals, including considering a concise and reduced number of goals, removing those
considered day-to-day tasks, and focusing on realistic and attainable goals.
1
This evening, the City Council is being asked to review and provide direction on the
proposed draft City Council Goals for FY 2023-24, updated to incorporate the Gantt chart
with concise milestones and tasks supporting each project (Attachment A). As discussed
at the workshop, the proposed goals derive from FY 2022-23 City Council Goals and have
been modified based on the March 15 workshop discussion (Attachment B). The goals
utilize the "SMART" rubric: Specific, Measurable, Achievable, Realistic, and Timely.
DISCUSSION:
Proposed Updated FY 2023-24 City Council Goals
Based on the feedback provided at the workshop, Staff has prepared an updated Gantt
chart for the City Council’s review (Attachment A). The Gantt Chart has been simplified
by removing excessive and superfluous tasks and subtasks to maintain a high -level
working document. It should be noted that projects not described in the Gantt chart do
not necessarily mean that they are not being completed but may be considered routine
business.
Below are FY 2023-24 City Council Goals listed by category followed by assigned projects
as discussed at the March 15 workshop. There are a total of 19 projects presented below.
Public Safety: Maintain a high level of public safety with public engagement.
• Enhance public safety through crime reduction and traffic safety engagement
strategies.
• Allocate resources to establish certain public safety services in-house.
• Implement strategies enhancing resident readiness and response during an
emergency.
Infrastructure: Maintain and improve all public infrastructure (including transportation
systems, parking, utilities, storm drains, and sewers).
• Complete the Portuguese Bend Landslide Remediation Project plans for Council
review.
• Create a detailed inventory and maintenance schedule of the City’s public
infrastructure and assets.
• Complete project plans to improve traffic flow on Western Avenue.
• Prepare a financial plan for Abalone Cove’s annual sewer rates.
• Secure grant funding to underground one mile of utility lines within the City’s open
space areas.
• Develop a Citywide Small Wireless Facilities Master Plan.
City Land and Facilities: Maintain and improve all City-owned properties.
• Implement the remaining components of the Natural Communities Conservation
Plan/Habitat Conservation Plan (NCCP/HCP)
• Adopt the updated Trails Network Plan (TNP).
2
• Complete Civic Center Project Feasibility and Site Planning and Financing (Phase
I), Design Solicitation (Phase II) & Schematic Design (Phase III)Pursue acquisition
of Coast Guard properties of Battery Barnes and the Point Vicente Lighthouse.
Citizen Involvement and Public Outreach - Engage residents and community partners
in assisting the City Council, City Committees/Commissions, and City Staff facilitate the
decision-making process.
• Implement a Students in Local Government Program.
Quality of Life – Maintain and improve the quality of life for RPV residents.
• Complete the Arterial Fences and Walls Master Plan and identify implementation
strategies.
• Complete Streetscape Beautification Master Plan.
• Support local businesses and grow businesses with high-quality jobs in RPV.
• Continue Uniform Street Signs Project as signs deteriorate and need replacing.
Government Efficiency, Transparency, and Accountability - Maximize the use of
each tax dollar and optimize services delivered to RPV residents.
• Reimagine the City’s website utilizing intuitive tools and links to allow for a more
user-friendly experience.
Many of the FY 2022-23 City Council Goals' projects are carried over from previous fiscal
years for various reasons, including delays in beginning or implementing a task,
reprioritizing staff assignments, staff turnover, and/or because it is a significant capital
project that extends beyond one fiscal year. The FY 2022-23 City Council Goals are being
utilized as the framework for setting the goals for FY 2023-24, including feedback from
the City Council, Planning Commission, and Advisory Boards. Staff also retained the
status for most tasks and subtasks to reflect where they are today.
FY 2022-23 City Council Goals projects, tasks, and subtasks that were not carried over
or completed are hidden in the Gantt chart and will be retained for historical and
institutional knowledge purposes. New projects, tasks, and subtasks will be added and
renumbered under each category.
As discussed at the workshop, it has become increasingly evident over the past few years,
despite efforts to reduce the number of projects and tasks, that the list is too ambitious
for the degree of resources available, particularly staff levels and the amount of time
committed to completing everyday responsibilities. Although the compiled draft goals list
consists of 19 projects, Staff remains concerned that the list may still be too ambitious to
make tangible results in FY 2023-24. Thus, Staff respectfully requests that the City
Council consider reducing the list by prioritizing the top 12-14 projects. By prioritizing what
is desired to be completed within the coming year, the remaining projects and tasks may
be deferred to subsequent years after staffing conditions improve.
3
CONCLUSION:
Staff Review and approve the proposed draft City Council Goals for FY 2023-24 City
Council Goals and return with a final draft for approval on June 20, 2022.
ALTERNATIVES:
In addition to the Staff recommendations, the following alternatives are available for the
City Council's consideration:
1. Do not approve FY 2023-24 City Council Goals.
2. Direct Staff to return to the City Council with alternative City Council Goals.
3. Take other action as deemed appropriate.
4
City of Rancho Palos Verdes
Start Date:July 1, 2023
Status Report:City Council Proposed FY 2023-2024 Goals
Updated:March 28, 2023
Week Starting 6/26/237/3/237/10/237/17/237/24/237/31/238/7/238/14/238/21/238/28/239/4/239/11/239/18/239/25/2310/2/2310/9/23#####################11/6/23#####################12/4/23#####################1/1/241/8/241/15/241/22/241/29/242/5/242/12/242/19/242/26/243/4/243/11/243/18/243/25/244/1/244/8/244/15/244/22/244/29/245/6/245/13/245/20/245/27/246/3/246/10/246/17/246/24/247/1/247/8/247/15/247/22/247/29/248/5/248/12/248/19/248/26/249/2/249/9/249/16/249/23/24Assigned To Start End # of Days Status % Complete
Public Safety - Maintain a High Level of Public Safety with Public Engagement
2 2/1/22 6/30/24 629 In progress 18%u
2-1 Establish RPV Evacuation Zones (EVZ) and Safe Refuge Areas (SRA)Administration 2/1/22 6/30/24 629 In progress 25%u
2-2 Inform residents of their EVZ and SRA Administration 4/1/23 6/30/24 325 In progress 35%u
2-3 Double the number of residents registered for Alert SouthBay and MyRPV Administration 7/1/22 6/30/24 521 In progress 45%u
2-4 Engage an experienced vendor to develop emergency evacuation plans in collaboration with staff and Public Safety Agencies. Administration 7/1/23 6/30/24 260 Not started 0%l u
3 7/1/23 6/30/24 260 Not started 0%l u
3-1 Manage overtime patrols by LASD for crime enforcement and traffic suppression Administration 7/1/23 6/30/24 260 Not started 0%l u
3-2 Implement public safety reimbursement program Administration 7/1/23 6/30/24 260 Not started 0%l u
3-3 Engage residents in Driver Safety Week Administration 7/1/23 1/31/24 153 Not started 0%l u
4 6/29/23 6/30/24 262 Not started 0%l u
4-1 Establish a Public Safety Division within the Administration Department Administration 7/1/23 6/30/24 260 Not started 0%l u
Comments:
CITY COUNCIL GOAL
Jul Aug Sep
Tasks
Jan Feb Mar Apr May JunSepOctNovDecJulAug
THIRD QUARTER FY 2023-24 FOURTH QUARTER FY 2023-24 FIRST QUARTER FY 2024-25
2024 2024 2024 202420242024202420242024202320232023
FIRST QUARTER FY 2023-24 SECOND QUARTER FY 2023-24
202320232023
PROJECT: Implement strategies enhancing resident readiness and response during an emergency
PROJECT: Enhance public safety through crime reduction and traffic safety engagement strategies
PROJECT: Allocate resources to establish certain public safety services in-house
P:\7 City Council\Draft Staff Report Review 20230404\4. Final\2. CLERK COMPLETE - CC Goals\FY23-24 City Council Goals Gantt Charts\1. FY23_24 City Council goals GANTT chart - Public Safety_KB.xlsx 1 of 1
A-1
City of Rancho Palos Verdes
Start Date:July 1, 2023
Status Report:City Council Proposed FY 2023-2024 Goals
Updated:March 28, 2023
Week Starting 6/26/237/3/237/10/237/17/237/24/237/31/238/7/238/14/238/21/238/28/239/4/239/11/239/18/239/25/2310/2/2310/9/2310/16/2310/23/2310/30/2311/6/2311/13/2311/20/2311/27/2312/4/2312/11/2312/18/2312/25/231/1/241/8/241/15/241/22/241/29/242/5/242/12/242/19/242/26/243/4/243/11/243/18/243/25/244/1/244/8/244/15/244/22/244/29/245/6/245/13/245/20/245/27/246/3/246/10/246/17/246/24/247/1/247/8/247/15/247/22/247/29/248/5/248/12/248/19/248/26/249/2/249/9/249/16/249/23/24Assigned To Start End # of Days Status % Complete
CITY COUNCIL GOAL Maintain and Improve all Public Infrastructure (including transportation systems, paring, utilities, storm drains, and sewers)
1 10/4/22 3/31/27 1,172 In progress 27%
1-1 Certify EIR Public Works 10/4/22 8/30/23 237 In progress 75%u
1-2 Public Works 7/1/23 6/30/24 260 In progress 60%l u
1-3 Public Works 7/1/24 6/30/25 261 Not started 0%l
1-4 Bid and award Public Works 7/1/25 9/30/25 66 Not started 0%
1-5 Construction Public Works 10/1/25 3/31/27 391 Not started 0%
2 7/1/21 6/30/24 782 In progress 5%u
2-1 Create a Detailed Inventory and Maintenance Schedule of City's Transportation Infrastructure Public Works 7/1/21 12/31/23 652 In progress 0%u
2-2 Create a Detailed Inventory and Maintenance Schedule of City's Storm Drain Infrastructure Public Works 7/1/22 6/30/24 521 In progress 0%u
2-3 Create a detailed Inventory and Maintenance Schedule of City’s Sanitary Sewer Infrastructure Public Works 7/1/22 6/30/24 521 In progress 0%u
2-4 Create a detailed Inventory and Maintenance Schedule of City’s Facilities Public Works 7/1/21 12/31/23 652 In progress 0%u
4 7/1/21 6/30/25 1,043 In progress 0%
4-1 Update Neighborhood Traffic Calming Program Public Works 7/1/21 6/30/24 782 Not started 0%u
4-2 Develop speed management plans for arterials Public Works 7/1/21 6/30/25 1,043 Not started 0%
5 10/6/20 12/31/28 2,149 In progress 0%
5-1 Complete Altamira Canyon Concept Report Public Works 10/6/20 12/31/28 2,149 In progress 0%
6 9/30/22 9/30/26 1,044 In progress 15%
6-1 Procure traffic study/concept plan and environmental consultant Public Works 9/30/22 4/30/23 151 In progress 25%
6-2 Complete traffic study/concept plan and environmental review Public Works 5/1/23 12/31/23 175 In progress 10%u
6-3 Procure final design consultant Public Works 1/1/24 4/30/24 87 Not started 0%l u
6-4 Complete final design Public Works 5/1/23 12/31/24 437 Not started 0%
6-5 Obtain Caltrans permit and interagency agreements Public Works 1/1/25 4/30/25 86 Not started 0%
6-6 Procure construction contractor Public Works 4/30/25 4/30/26 262 Not started 0%
6-7 Construction Public Works 9/30/25 9/30/26 262 Not started 0%
7 11/18/20 6/30/24 943 In progress 25%u
7-2 Assessment of the sewer system Public Works 11/18/20 6/30/24 943 In progress 25%u
7-3 FAC and Finance Department review and prepare a new financial plan Finance 4/26/22 6/30/24 569 In progress 25%u
8 7/1/23 6/30/24 260 Not started 0%l u
8-1 Apply for Federal Hazard Mitigation Grant Program (HMGP) Funding Administration 7/1/23 6/30/24 260 Not started 0%l u
9 12/31/20 6/30/24 912 Not started 0%u
9-1 Identify needed equipment for cell sites with cellular companies and their consultants Public Works 12/31/20 6/30/24 912 Not started 0%u
9-2 Meet with HOA's to review equipment requirements and preferences.Public Works 7/1/23 6/30/24 260 Not started 0%
9-3 Develop a Master Deployment Plan with cellular companies and there consultants Public Works 7/1/23 6/30/24 260 Not started 0%
9-4 Identify any needed changes to the Municipal Code Public Works 1/31/24 12/31/24 240 Not started 0%
Comments:
Develop Citywide Small Wireless Facilities Master Plan
Jul Aug Sep
Tasks
Jan Feb Mar Apr May JunSepOctNovDec
THIRD QUARTER FY 2023-24 FOURTH QUARTER FY 2023-24 FIRST QUARTER FY 2024-25
2024 2024 2024 20242024202420242024202420232023
Jul Aug
Final engineering and construction documents
Partnering agreements and permitting
PROJECT: Establish a Citywide Speed Mitigation Plan
PROJECT: Identify Altamira Canyon Improvements (erosion)
PROJECT: Complete project plans to improve traffic flow on Western Avenue
PROJECT: Prepare a Financial Plan for Abalone Cove Annual Sewer Rates
PROJECT: Secure grant funding to underground one mile of utility lines within the City’s open space areas.
FIRST QUARTER FY 2023-24 SECOND QUARTER FY 2023-24
2023202320232023
PROJECT: Complete the Portuguese Bend Landslide Remediation Project plans for Council review
PROJECT: Create a detailed inventory and maintenance schedule of the City’s public infrastructure and assets
P:\7 City Council\Draft Staff Report Review 20230404\4. Final\2. CLERK COMPLETE - CC Goals\FY23-24 City Council Goals Gantt Charts\2. FY23_24 City Council goals GANTT chart - Maintain and Improve Public Infrastructure_KB.xlsx 1 of 1
A-2
City of Rancho Palos Verdes
Start Date:July 1, 2023
Status Report:City Council Proposed FY 2023-2024 Goals
Updated:March 28, 2023
Week Starting 6/26/237/3/237/10/237/17/237/24/237/31/238/7/238/14/238/21/238/28/239/4/239/11/239/18/239/25/2310/2/2310/9/2310/16/2310/23/2310/30/2311/6/2311/13/2311/20/2311/27/2312/4/2312/11/2312/18/2312/25/231/1/241/8/241/15/241/22/241/29/242/5/242/12/242/19/242/26/243/4/243/11/243/18/243/25/244/1/244/8/244/15/244/22/244/29/245/6/245/13/245/20/245/27/246/3/246/10/246/17/246/24/247/1/247/8/247/15/247/22/247/29/248/5/248/12/248/19/248/26/249/2/249/9/249/16/249/23/24Assigned To Start End # of Days Status % Complete
CITY COUNCIL GOAL City Land & Facilities
2 4/30/20 6/4/24 1,069 In progress 18%u
2-1 Management Agreement amendment Recreation and Parks 12/31/21 7/18/23 403 In progress 15%u
2-3 Update Preserve Public Use Master Plan Recreation and Parks 1/3/22 6/4/24 632 In progress 25%u
2-4 Preserve access protocol creation Recreation and Parks 12/31/21 6/4/24 633 In progress 15%u
3 7/18/23 8/15/23 21 Not started 0%l u
3-5 Planning Commission approval Recreation and Parks 7/18/23 7/25/23 6 Not started 0%l u
3-6 City Council approval Recreation and Parks 8/8/23 8/15/23 6 Not started 0%l u
4 4/1/22 3/30/24 521 In progress 24%u
4.1 Review of revised site plan by federal agencies Administration 7/28/22 5/15/23 208 In progress 40%
4.2 Project scheduling Administration 4/1/22 7/30/23 346 In progress 15%u
4.3 Delivery analysis Administration 4/1/22 7/30/23 346 In progress 15%u
4.4 Revise and prepare site plan for City Council Administration 8/16/22 9/30/23 294 In progress 50%u
4.5 Project estimate and budgeting Administration 8/16/22 9/30/23 294 In progress 50%u
4.6 Present budget and site plan to City Council Administration 7/1/23 10/30/23 86 Not started 0%l u
4.7 Pending Council approval obtain services of architecture firm to work towards final design Administration 10/30/23 3/30/24 110 Not started 0%l u
4.8 Proceed with development of schematic design Administration 3/30/24 6/30/24 65 Not started 0%l u
5 2/23/23 6/30/24 352 In progress 18%u
5-1 Continue outreach to U.S. Coast Guard to explore possiblity of acquisition of either or both properties Administration 2/23/23 6/30/24 352 In progress 25%u
5-2 Conduct outreach campaign to elected officials to garner support for acquistion effort Administration 2/23/23 6/30/24 352 In progress 10%u
PROJECT: Implement the remaining components of the Natural Communities Conservation Plan/Habitat Conservation Plan (NCCP/HCP)
PROJECT: Adopt the Updated Trails Network Plan (TNP)
Jul Aug
2024 2024 2024202320242024
Sep
Tasks
Jan Feb Mar Apr May JunNovDec
FIRST QUARTER FY 2023-2024 SECOND QUARTER FY 2023-24 THIRD QUARTER FY 2023-24 FOURTH QUARTER FY 2023-24 FIRST QUARTER FY 2024-25
PROJECT : Complete Civic Center Project Feasibility and Site Planning and Financing (Phase I), Design Solicitation (Phase II) & Schematic Design (Phase III)
PROJECT: Pursue acquisition of Coast Guard properties of Battery Barnes and the Point Vicente Lighthouse
2023 2023 2023 2023 2023 2024 2024 2024 2024
Jul Aug Sep Oct
P:\7 City Council\Draft Staff Report Review 20230404\4. Final\2. CLERK COMPLETE - CC Goals\FY23-24 City Council Goals Gantt Charts\3. FY23_24 City Council goals GANTT chart - City Land and Facilities_KB.xlsx 1 of 1
A-3
City of Rancho Palos Verdes
Start Date:July 1, 2023
Status Report:City Council Proposed FY 2023-2024 Goals
Updated:March 28, 2023
Week Starting 6/26/237/3/237/10/237/17/237/24/237/31/238/7/238/14/238/21/238/28/239/4/239/11/239/18/239/25/2310/2/2310/9/2310/16/2310/23/2310/30/2311/6/2311/13/2311/20/2311/27/2312/4/2312/11/2312/18/2312/25/231/1/241/8/241/15/241/22/241/29/242/5/242/12/242/19/242/26/243/4/243/11/243/18/243/25/244/1/244/8/244/15/244/22/244/29/245/6/245/13/245/20/245/27/246/3/246/10/246/17/246/24/247/1/247/8/247/15/247/22/247/29/248/5/248/12/248/19/248/26/249/2/249/9/249/16/249/23/24Assigned To Start End # of Days Status % Complete
CITY COUNCIL GOAL Citizen Involvement & Public Outreach - Engage residents and community partners in assisting the City Council, City Committees/Commissions, and City Staff facilitate the decision-making process.
3 PROJECT: Implement a Students in Local Government Program 7/1/23 6/30/24 260 Not started 0%l u
1-3 Administration 7/1/23 6/30/24 260 Not started 0%l u
Comments:
2023 2023 2023 2023 2023
FIRST QUARTER FY 2023-24 SECOND QUARTER FY 2023-24 THIRD QUARTER FY 2023-24 FOURTH QUARTER FY 2023-24 FIRST QUARTER FY 2024-25
2024 2024 2024 2024
Jul Aug Sep Oct Nov Dec
2023 2024 2024 2024 2024 2024
Jul Aug Sep
Tasks
Jan Feb Mar Apr May Jun
Implement a Youth Advisory Council
P:\7 City Council\Draft Staff Report Review 20230404\4. Final\2. CLERK COMPLETE - CC Goals\FY23-24 City Council Goals Gantt Charts\4. FY23_24 City Council goals GANTT chart - Citizen Involvement and Public Outreach_KB.xlsx 1 of 1
A-4
City of Rancho Palos Verdes
Start Date:July 1, 2023
Status Report:City Council Proposed FY 2023-2024 Goals
Updated:March 28, 2023
Week Starting 6/26/237/3/237/10/237/17/237/24/237/31/238/7/238/14/238/21/238/28/239/4/239/11/239/18/239/25/2310/2/2310/9/2310/16/2310/23/2310/30/2311/6/2311/13/2311/20/2311/27/2312/4/2312/11/2312/18/2312/25/231/1/241/8/241/15/241/22/241/29/242/5/242/12/242/19/242/26/243/4/243/11/243/18/243/25/244/1/244/8/244/15/244/22/244/29/245/6/245/13/245/20/245/27/246/3/246/10/246/17/246/24/247/1/247/8/247/15/247/22/247/29/248/5/248/12/248/19/248/26/249/2/249/9/249/16/249/23/24Assigned To Start End # of Days Status % Complete
CITY COUNCIL GOAL Quality of Life - Maintain and improve the quality of life for RPV residents
2 4/1/23 10/2/23 131 Not started 0%u
2-2 Public outreach to local homeowners associations Community Development 4/1/23 4/30/23 20 Not started 0%
2-3 Preparation of draft plan and materials Community Development 6/1/23 7/31/23 43 Not started 0%u
2-4 City Council approval Community Development 8/15/23 8/22/23 6 Not started 0%l u
2-5 Plan implementation Community Development 8/22/23 10/2/23 30 Not started 0%l u
5 7/1/22 6/30/23 261 Not started 0%u
5-1 Complete Streetscape Beautification Master Plan Public Works 7/1/22 6/30/23 261 Not started 0%u
6 9/12/22 6/30/24 470 In progress 3%u
Engage with Los Angeles County Economic Development Corporation (LAEDC) on economic development Administration 7/1/23 6/30/24 260 Not started 0%l u
Preparation of Draft MOUD Community Development 9/12/22 6/13/23 197 In progress 20%
In-person and virtual open house #2 Community Development 4/18/23 4/28/23 9 Not started 0%
Environmental review scoping meeting Community Development 5/13/23 5/23/23 7 Not started 0%
Planning Commission consideration Community Development 6/17/23 6/27/23 7 Not started 0%u
City Council consideration Community Development 7/11/23 7/18/23 6 Not started 0%l u
7 7/1/23 11/4/25 612 Not started 0%l
7-1 RFP to design project based on Retro reflectivity report Public Works 7/1/23 6/30/24 260 Not started 0%l u
7-2 City Council award PSA for design; consultant to design project and produce a package for contractors to bid on Public Works 7/1/24 6/30/25 261 Not started 0%l
7-3 City Council award Construction Contract Public Works 7/1/25 11/4/25 91 Not started 0%
Comments:
PROJECT: Continue Uniform Street Signs Project as signs deteriorate and need replacing
PROJECT: Complete the Arterial Fences and Walls Master Plan and identify implementation strategies
PROJECT: Complete Streetscape Beautification Master Plan
PROJECT: Support local businesses and grow business with high-quality jobs in RPV
6-4
6-5
6-6
6-2
6-3
2023 2023
FIRST QUARTER FY 2023-24 SECOND QUARTER FY 2023-24
2023202320232023
6-1
THIRD QUARTER FY 2023-24 FOURTH QUARTER FY 2023-24 FIRST QUARTER FY 2024-25
2024 2024 2024 202420242024202420242024
Jul Aug Sep
Tasks
Jan Feb Mar Apr May JunSepOctNovDecJulAug
P:\7 City Council\Draft Staff Report Review 20230404\4. Final\2. CLERK COMPLETE - CC Goals\FY23-24 City Council Goals Gantt Charts\5. FY23_24 City Council goals GANTT chart - Quality of Life_KB.xlsx 1 of 1
A-5
City of Rancho Palos Verdes
Start Date:July 1, 2023
Status Report:City Council Proposed FY 2023-2024 Goals
Updated:March 28, 2023
Week Starting 6/26/237/3/237/10/237/17/237/24/237/31/238/7/238/14/238/21/238/28/239/4/239/11/239/18/239/25/2310/2/2310/9/2310/16/2310/23/2310/30/2311/6/2311/13/2311/20/2311/27/2312/4/2312/11/2312/18/2312/25/231/1/241/8/241/15/241/22/241/29/242/5/242/12/242/19/242/26/243/4/243/11/243/18/243/25/244/1/244/8/244/15/244/22/244/29/245/6/245/13/245/20/245/27/246/3/246/10/246/17/246/24/247/1/247/8/247/15/247/22/247/29/248/5/248/12/248/19/248/26/249/2/249/9/249/16/249/23/24Assigned To Start End # of Days Status % Complete
CITY COUNCIL GOAL Government Efficiency, Transparency, and Accountability - Maximize the use of each tax dollar and optimize services delivered to RPV residents
5 PROJECT: Reimagine the City’s website utilizing intuitive tools and links to allow for a more user-friendly experience 3/1/23 7/18/23 100 In progress u
5-1 Coordinate meetings with Departments on website/webpage content Administration 3/1/23 6/30/23 88 In progress u
5-2 Schedule one-on-one training with Departments on use of website/webpage Administration 4/3/23 5/30/23 42 Not started
5-3 Conduct website/webpage testing for content and visibility Administration 6/1/23 6/30/23 22 Not started u
5-4 Implement outreach campaign to promote launch of new website/webpage Administration 6/30/23 7/17/23 12 Not started l u
5-5 Go live with latest website/webpage content Administration 7/11/23 7/18/23 6 Not started
Comments:
2023 2023
Jul Aug
2023 2023 2023
Jul Aug Sep
Tasks
Jan Feb Mar
FIRST QUARTER FY 2022-23 SECOND QUARTER FY 2022-23
2023
THIRD QUARTER FY 2022-23 FOURTH QUARTER FY 2022-23
2024 2024 2024 2024 2024
FIRST QUARTER FY 2023-24
2024 2024 2024 2024
Apr May JunSepOctNovDec