CC SR 20220920 05 - ARPA FY22-23 Spending Plan
CITY COUNCIL MEETING DATE: 09/20/2022
AGENDA REPORT AGENDA HEADING: Regular Business
AGENDA TITLE:
Consideration and possible action to receive and file the FY 2022-23 spending plan for
the American Rescue Plan Act (ARPA).
RECOMMENDED COUNCIL ACTION:
(1) Receive and file the FY 2022-23 spending plan for ARPA; and
(2) Provide Staff with direction for funding priorities for the remaining unallocated
amount of $200,000 and the ARPA Fund’s interest earnings. The funding priorities,
as recommended by the Finance Advisory Committee, may include:
1. Allocating the amount to the Ladera Linda Community Park Project.
2. Allocating the amount for the security component to the Eastview
Restrooms and Remodel Project.
FISCAL IMPACT: None.
Amount Budgeted: $9,721,400
Additional Appropriation: N/A
Account Number(s): 333-400-XXXX-XXXX
(ARPA Fund – Various Accounts)
ORIGINATED BY: Vina Ramos, Deputy Director of Finance
REVIEWED BY: Trang Nguyen, Director of Finance
APPROVED BY: Ara Mihranian, AICP, City Manager
ATTACHED SUPPORTING DOCUMENTS:
A. ARPA Projects – Financial Status Report as of August 19, 2022 (page A-1)
B. October 5, 2021 staff report
C. FY 2022-23 CIP Project List (page C-1)
BACKGROUND:
On October 5, 2021, the City Council approved the City’s ARPA spending plan of $9.9
million. At that time, of the $9.9 million, almost $6.6 million had been allocated and
approved by the City Council, of which $4 million was encumbered. Afterward, Staff
presented proposed changes at the Capital Improvement Program Budget Workshop in
April 2022. The purpose of the changes was to advance eligible capital projects that are
shovel ready to ensure that funds are spent by ARPA’s deadline of December 31, 2026.
1
Subsequently, the FY 2022-23 Five-Year Capital Improvement Program was adopted by
the City Council on June 21, 2022. The summary of the changes that were adopted for
ARPA funding are as follows:
• Allocations were approved for $9.7 million (remaining ba lance of $0.2
million is to be determined)
• Allocations were estimated to be spent beginning FY 2022 -23 through FY
2024-25;
• Removed Abalone Cove Sanitary Sewer Rehabilitation for $1.5 million (to
be funded by the Capital Infrastructure Program (CIP) Fund instead);
• Removed Park Playground Improvements for $350,000 (to be funded by
CIP Fund instead);
• Added Pavement Management Program Arterial Roadway Rehab (Silver
Spur – North of Hawthorne) $1,717,000; and
• Added City Roadway/Park Monument Signs for $336,400.
In October 2021, when the City Council approved the ARPA’s spending plan, Staff
indicated that financial progress reports would be presented to the City Council annually.
This evening, the City Council is receiving the financial progress of the approved projects.
Additionally, in accordance with ARPA’s guidelines, the recommended changes are being
presented to the City Council for its consideration and approval.
DISCUSSION:
Financial Status Report – August 2022
As of August 19, 2022, the expenditures for ARPA are $1.8 million and $2.4 million of
encumbrances, for a total of $4.2 million or 44% of the $9.7 million. Of this amount,
approximately $4 million has been spent and encumbered for the Ladera Linda
Community Park Project. Table 1 below is a summary of the expenditure (project)
categories and the financial status report as of August 19, 2022. A comprehensive list
that includes financial status and project status is presented in Attachment B.
Table 1: Summary of ARPA’s Expenditures and Encumbrances
Expenditure Category
Approved ARPA
Allocation
Expenditures
08/19/2022
Encumbered
08/19/2022
% of Exp + Enc
08/19/2022 Balance
Investment in Capital
Infrastructure 8,876,400 1,633,683 2,399,917 45%4,842,800
Investment in
Information Technology 520,000 184,764 18,056 39%317,180
Investment in Public
Safety 325,000 0 0 0%325,000
Grand Total $9,721,400 $1,818,447 $2,417,973 44%$5,484,980
2
The following Tables 2, 3, and 4 are a summary of the financial status for each project by
expenditure category and sorted by estimated completion date as of August 19, 2022.
Table 2: Capital Infrastructure
Project Name
Estimated
Completion
Date
Approved
ARPA
Allocation
Expenditures
& Encumbered
08/19/2022
% of Exp +
Enc
08/19/2022 Balance
INVESTMENT IN CAPITAL INFRASTRUCTURE
City Entrance Roadway/Park
Signage Project Dec-22 336,400 0 0%336,400
Restroom Improvements at
Point Vicente Interpretive
Center Jan-23 385,000 35,600 9%349,400
Pavement Management
Program Arterial Roadway
Rehabilitation (Crenshaw
Blvd)Jun-23 500,000 0 0%500,000
Ladera Linda Community Park
Project Aug-23 3,953,000 3,953,000 100%0
Stormwater Drainage
Improvements – Palos Verdes
Drive South at Peppertree
Drive Dec-23 1,035,000 0 0%1,035,000
Pavement Management
Program Arterial Roadway
Rehabilitation (Silver Spur
Road - North of Hawthorne
Blvd.)Jun-24 1,717,000 45,000 3%1,672,000
Western Ave Beautification
(*partial funding)Jun-24 600,000 0 0%600,000
Eastview Restroom Remodel
& Additional Office Space TBD 350,000 0 0%350,000
TOTAL CAPITAL INFRASTRUCTURE $8,876,400 $4,033,600 45%$4,842,800
3
Table 3: Information Technology
Table 4: Public Safety
Interest Allocation
As of August 19, 2022, the estimated cash balance for the ARPA Fund is $8.1 million ,
and it is estimated to earn approximately $35,000 of interest. Since the City received the
first payment of $4.9 million in July 2021 and the remaining $4.9 million in July 2022, the
average interest earned every quarter is approximately $7,500. At the City Council’s
discretion, the interest amount earned may be allocated to the projects.
Finance Advisory Committee
On June 2, 2022, the Finance Advisory Committee (FAC) received and filed the financial
status report for the City’s ARPA’s spending plan of $9.9 million . Additionally, Staff
presented the FAC with an updated spending plan and financial status report at its
September 8, 2022 meeting. The following is a summary of the FAC’s feedback:
i. Recommended allocating the remaining balance of $200,000 and interest
earnings to the Ladera Linda Community Park Project. Based on the project’s
Project Name
Estimated
Completion
Date
Approved
ARPA
Allocation
Expenditures &
Encumbered
08/19/2022
% of Exp +
Enc
08/19/2022 Balance
INVESTMENT IN INFORMATION TECHNOLOGY
Hesse Park Upgrades Mar-23 270,000 6,000 2%264,000
IT Infrastructure
Upgrades May-23 250,000 196,820 79%53,180
TOTAL INFORMATION TECHNOLOGY $520,000 $202,820 39%$317,180
Project Name
Estimated
Completion
Date
Approved
ARPA
Allocation
Expenditures &
Encumbered
08/19/2022
% of Exp +
Enc
08/19/2022 Balance
PUBLIC SAFETY
Development of a
Peninsula-wide
Evacuation Plan Mar-23 100,000 0 0%100,000
Wildfire Monitoring
Cameras Apr-23 125,000 0 0%125,000
Replenish the City
Emergency Supplies May-23 100,000 0 0%100,000
TOTAL PUBLIC SAFETY $325,000 $0 0%$325,000
4
current status, allocating this amount would help meet the time requirements for
ARPA’s deadline of December 31, 2026.
ii. Recommended including a security component to the Eastview Restrooms and
Remodel Project.
iii. Reiterated the importance for the City to continue moving forward with the
Wildfire Monitoring Cameras Project.
ADDITIONAL INFORMATION:
In accordance with the U.S. Department of the Treasury (DOT), Staff submitted the first
compliance report in April 2022. The subsequent annual reports will cover one calendar
year and must be submitted to DOT by April 30.
Prior to submitting reports to DOT, Staff will continue to monitor the spending plan, provide
financial status reports, and present any proposed changes to the Financial Advisory
Committee and City Council. The next report will be included in the FY 2021-22 Year-End
Unaudited Financial Report and FY 2022-23 First Quarter Report in December.
CONCLUSION:
Overall, since the City received the $9.9 million of ARPA funds, the City Council has
committed $9.6 million or 97%. Based on these commitments and once completed, the
utilization of ARPA funds would relieve the General Fund for needed one-time costs and
deferred maintenance projects and generate available funds in the CIP that can be used
for future projects and initiatives. Based on the financial status report presented to the City
Council tonight, the spending plan is trending to meet the requirements of spending the
entire $9.9 million by December 31, 2026.
Based on the feedback and recommendations received from the FAC, Staff recommends
the City Council to receive and file the FY 2022-23 ARPA spending plan. Additionally,
Staff seeks City Council direction on the funding priorities for the remaining unallocated
amount of $200,000 and ARPA Fund’s interest earnings, which may include the following:
i. Allocating the amount to the Ladera Linda Community Park Project.
ii. Allocating the amount for the security component to the Eastview Restrooms
and Remodel Project.
ALTERNATIVES:
In addition to the Staff recommendation, the following alternative action is available for
the City Council’s consideration:
1. Consider allocating the $200,000 in available ARPA funds to other CIP projects
such as the Western Avenue Beautification project, see Attachment C for a
complete list of CIP projects.
2. Take other action, as deemed appropriate.
5
ATTACHMENT A
ARPA PROJECTS - FINANCIAL STATUS REPORT
AUGUST 19, 2022
(By Estimated Completion Date)
Project Name
Estimated
Completion
Date
Approved
ARPA
Allocation
Expenditures
08/19/2022
Encumbered
08/19/2022
% of Exp + Enc
08/19/2022 Balance Status Notes
INVESTMENT IN CAPITAL INFRASTRUCTURE
City Entrance Roadway/Park Signage
Project Dec-22 336,400 0 0 0%336,400
City Entry Signs Project merged with City
Parks Signage Project approved by City
Council June 7 and August 15, 2022
Restroom Improvements at Point
Vicente Interpretive Center Jan-23 385,000 12,400 23,200 9%349,400 Design is at 60%
Pavement Management Program
Arterial Roadway Rehabilitation
(Crenshaw Blvd)Jun-23 500,000 0 0 0%500,000 Design is at 90%
Ladera Linda Community Park
Project Aug-23 3,953,000 1,621,283 2,331,717 100%0 Construction in-progress
Stormwater Drainage Improvements
– Palos Verdes Drive South at
Peppertree Drive Dec-23 1,035,000 0 0 0%1,035,000 Design is at 60%
Pavement Management Program
Arterial Roadway Rehabilitation
(Silver Spur Road - North of
Hawthorne Blvd.)Jun-24 1,717,000 0 45,000 3%1,672,000 Design is at 90%
Western Ave Beautification
(*partial funding)Jun-24 600,000 0 0 0%600,000
Included in the Capital Improvement
Program for $140,000 in FY 2022-23 and
$460,000 in FY 2023-24. A contract project
manager has been onboarded and scoping is
currently in-progress
Eastview Restroom Remodel &
Additional Office Space TBD 350,000 0 0 0%350,000
Included in the Capital Improvement
Program for $90,000 in FY23-24 and
$260,000 in FY24-25
TOTAL CAPITAL INFRASTRUCTURE $8,876,400 $1,633,683 $2,399,917 45%$4,842,800
A-1
ATTACHMENT A
ARPA PROJECTS - FINANCIAL STATUS REPORT
AUGUST 19, 2022
(By Completion Date)
Project Name
Estimated
Completion
Date
Approved
ARPA
Allocation
Expenditures
08/19/2022
Encumbered
08/19/2022
% of Exp + Enc
08/19/2022 Balance Status Notes
INVESTMENT IN INFORMATION TECHNOLOGY
Hesse Park Upgrades Mar-23 270,000 6,000 0 2%264,000
RFP for the design will be issued in
September 2022
IT Infrastructure Upgrades May-23 250,000 178,764 18,056 79%53,180 3 out of 4 Phases completed
TOTAL INFORMATION TECHNOLOGY $520,000 $184,764 $18,056 39%$317,180
A-2
ATTACHMENT A
ARPA PROJECTS - FINANCIAL STATUS REPORT
AUGUST 19, 2022
(By Completion Date)
Project Name
Estimated
Completion
Date
Approved
ARPA
Allocation
Expenditures
08/19/2022
Encumbered
08/19/2022
% of Exp + Enc
08/19/2022 Balance Status Notes
INVESTMENT IN PROTECTION OF LIFE AND PROPERTY
Development of a Peninsula-wide
Evacuation Plan Mar-23 100,000 0 0 0%100,000
This amount is a portion of the
Peninsulawide project for wildfire
detection services
Wildfire Monitoring Cameras Apr-23 125,000 0 0 0%125,000 RFP in early 2023
Replenish the City Emergency
Supplies May-23 100,000 0 0 0%100,000
Currently assesing the current
status of the City's emergency
supplies
TOTAL PROTECTION OF
LIFE AND PROPERTY $325,000 $0 $0 0%$325,000
GRAND TOTAL $9,721,400 $1,818,447 $2,417,973 44%$5,484,980
A-3
Project CodeProject NameFundExpenses/Commitments to date FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 8200 Series Abalone Cove Santitary Sewer System Maintenance225 (Ab Cove sewer maint.)48,005$ -$ -$ -$ -$ -$ 330 (CIP)-$ 3,300,000$ 930,000$ -$ -$ -$ 333 (ARPA Federal Grant)-$ -$ -$ -$ -$ -$ 8300 Series Landslide Improvements8301Palos Verdes Drive South Realignment - East End330 (CIP)111,425$ -$ -$ 75,000$ 1,845,000$ -$ 215 (Prop. C)N/A - ongoing program900,000$ -$ -$ -$ -$ 330 (CIP)N/A - ongoing program30,000$ 975,000$ 1,000,000$ 1,040,000$ 1,060,000$ 220 (Meas. R)292,300$ -$ -$ -$ -$ -$ 330 (CIP)804,387$ 535,000$ 6,180,000$ 2,135,000$ -$ -$ 8400 Series Parks, Open Space & Recreation Facilities8404Fence Replacement Program330 (CIP)-$ -$ 250,000$ -$ -$ -$ 330 (CIP)13,111,229$ -$ -$ -$ -$ -$ 333 (ARPA Federal Grant)3,953,000$ -$ -$ -$ -$ -$ 334 (Quimby park development)1,705,855$ -$ -$ -$ -$ -$ 8420Palos Verdes Nature Preserve Signs Program330 (CIP)248,405$ -$ -$ -$ -$ -$ 8423Palos Verdes Nature Preserve Gate for the Rattlesnake Trail330 (CIP)-$ 210,000$ -$ -$ -$ -$ 330 (CIP)-$ -$ -$ -$ -$ -$ 333 (ARPA Federal Grant)-$ 350,000$ -$ -$ -$ -$ 330 (CIP)-$ -$ 350,000$ -$ -$ -$ 333 (ARPA Federal Grant)-$ -$ -$ -$ -$ -$ 8500 Series Building Improvements8503 New Civic Center Complex330 (CIP)316,034$ 340,000$ 450,000$ -$ -$ -$ 330 (CIP)-$ -$ -$ -$ -$ -$ 333 (ARPA Federal Grant)35,000$ 350,000$ -$ -$ -$ -$ 8509 Facilities Asset Management Program330 (CIP)107,311$ 250,000$ TBDTBDTBDTBD330 (CIP)-$ -$ -$ TBD-$ -$ 333 (ARPA Federal Grant)-$ -$ 90,000$ 260,000$ -$ -$ 8700 Series Sewer & Storm Drain Improvements8701 Storm Drain Asset Management Program & Master Plan Update330 (CIP)115,000$ 450,000$ TBDTBDTBDTBD8708 Altamira Canyon Improvements (Erosion)330 (CIP)365,727$ 450,000$ TBDTBDTBDTBD330 (CIP)236,243$ 160,000$ -$ -$ -$ -$ 333 (ARPA Federal Grant)-$ 1,035,000$ -$ -$ -$ -$ 87New2 Lift Station Improvements at Lower Point Vicente330 (CIP)-$ -$ 40,000$ 290,000$ -$ -$ 84Pot1 Park Monument SignsPark Playground Improvements85Pot184Pot2Restroom Improvements and New Office Space at Eastview ParkPalos Verdes Drive South Landslide Area Resurfacing Program8302City of Rancho Palos VerdesPublic Works DepartmentProposed Five Year CIP Budget for Fiscal Years 2022-23, 2023-24, 2024-25, 2025-26 and 2026-278405 Ladera Linda Community Park Project8715Stormwater Drainage Improvements- Palos Verdes Drive South at Peppertree DriveRestroom Improvements at Point Vicente Interpretive Center85088202 Abalone Cove Sanitary Sewer Rehabilitation Program8304 Portuguese Bend Landslide RemediationC-1
Project CodeProject NameFundExpenses/Commitments to date FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 City of Rancho Palos VerdesPublic Works DepartmentProposed Five Year CIP Budget for Fiscal Years 2022-23, 2023-24, 2024-25, 2025-26 and 2026-278800 Series Right-of-Way Improvements8004 Traffic Signs Replacement Program330 (CIP)N/A - ongoing program215,000$ 225,000$ 110,000$ 130,000$ 155,000$ 330 (CIP) N/A - ongoing program350,000$ -$ 500,000$ -$ 520,000$ 340 (Bicycle & Ped access) N/A - ongoing program110,000$ -$ -$ -$ -$ 202 (Gas Tax - SB1) 170,000$ -$ -$ -$ -$ -$ 330 (CIP) -$ 1,020,000$ -$ -$ -$ -$ 333 (ARPA Federal Grant)-$ 500,000$ -$ -$ -$ -$ 215 (Prop. C)200,000$ -$ -$ -$ -$ -$ 220 (Meas. R)150,000$ -$ -$ -$ -$ -$ 221 (Meas. M - Grant)-$ 385,000$ 505,000$ 3,110,000$ -$ -$ 310 (CDBG) N/A - ongoing program150,000$ 150,000$ 150,000$ 150,000$ 150,000$ 330 (CIP) N/A - ongoing program-$ -$ -$ -$ -$ 202 (Gas Tax) N/A - ongoing program-$ -$ -$ 735,000$ -$ 220 (Meas. R) N/A - ongoing program-$ -$ -$ 530,000$ -$ 330 (CIP)N/A - ongoing program-$ -$ -$ 1,805,000$ 100,000$ 202 (Gas Tax)-$ 500,000$ -$ -$ -$ -$ 202 (Gas Tax - SB1)-$ 1,200,000$ -$ -$ -$ -$ 220 (Meas. R)38,500$ 1,400,000$ -$ -$ -$ -$ 330 (CIP)-$ 1,045,000$ 100,000$ -$ -$ -$ 202 (Gas Tax)N/A - ongoing program-$ -$ 925,000$ -$ -$ 220 (Meas. R)N/A - ongoing program-$ -$ 520,000$ -$ -$ 330 (CIP)N/A - ongoing program-$ -$ 1,270,000$ 100,000$ -$ 202 (Gas Tax)N/A - ongoing program-$ 530,000$ -$ -$ -$ 220 (Meas. R)N/A - ongoing program-$ 525,000$ -$ -$ -$ 330 (CIP)N/A - ongoing program-$ 1,405,000$ 100,000$ -$ -$ 215 (Prop. C)70,394$ -$ -$ -$ -$ -$ 330 (CIP)8,200$ -$ -$ 100,000$ 1,075,000$ -$ 202 (Gas Tax)N/A - ongoing program-$ -$ -$ -$ 700,000$ 220 (Meas. R)N/A - ongoing program-$ -$ -$ -$ 530,000$ 330 (CIP)N/A - ongoing program-$ -$ -$ -$ 1,420,000$ 8837Traffic Signal at intersection of Palos Verdes Drive South and Palos Verdes Drive East330 (CIP)361,618$ -$ -$ -$ -$ -$ 330 (CIP)-$ -$ 2,100,000$ -$ -$ -$ 333 (ARPA Federal Grant)-$ 140,000$ 460,000$ -$ -$ -$ 202 (Gas Tax)-$ -$ -$ -$ -$ -$ 333 (ARPA Federal Grant)45,000$ 1,672,000$ -$ -$ -$ -$ 330 (CIP)54,749$ 143,000$ -$ -$ -$ -$ 202 (Gas Tax)198,718$ -$ -$ -$ -$ -$ 330 (CIP)-$ -$ -$ 160,000$ -$ -$ 8845 Traffic Calming - PV Nature Preserve Parking Solutions330 (CIP)75,000$ TBD-$ -$ -$ -$ Palos Verdes Drive South Intersection ImprovementsPavement Management Program- Residential Roadway Rehabilitation - Area 6Pavement Management Program - Triennial Update8815Pavement Management Program- Residential Roadway Rehabilitation - Area 58816Pavement Management Program- Residential Roadway Rehabilitation - Area 1Community Development Block Grant Americans with Disabilities Act Infrastructure Improvements88108843Pavement Management Program- Arterial Roadway Rehabilitation(Silver Spur Road - North of Hawthorne Boulevard)88368840 Western Avenue Beautification88288826Pavement Management Program- Residential Roadway Rehabilitation - Area 28819Pavement Management Program- Residential Roadway Rehabilitation - Area 988448801 Sidewalk Repair and Replacement Program8808Pavement Management Program- Arterial Roadway Rehabilitation(Crenshaw Boulevard)8809 Western Avenue Traffic Flow ImprovementsC-2
Project CodeProject NameFundExpenses/Commitments to date FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 City of Rancho Palos VerdesPublic Works DepartmentProposed Five Year CIP Budget for Fiscal Years 2022-23, 2023-24, 2024-25, 2025-26 and 2026-27220 (Meas. R)-$ -$ -$ -$ -$ -$ 330 (CIP)-$ 535,000$ 430,000$ 450,000$ 460,000$ 465,000$ 330 (CIP)-$ -$ -$ -$ -$ -$ 331 (Federal Grants)-$ 105,000$ 894,900$ -$ -$ -$ 202 (Gas Tax) 140,000$ -$ -$ -$ -$ -$ 220 (Meas. R) 315,000$ -$ -$ -$ -$ -$ 330 (CIP) -$ -$ -$ -$ -$ -$ 88LY1Pavement Management Program- Arterial Roadway Rehabilitation(Palos Verdes Drive South)330 (CIP) -$ -$ 35,000$ 585,000$ -$ -$ 220 (Meas. R) -$ -$ -$ -$ -$ -$ 330 (CIP) -$ -$ -$ 70,000$ 545,000$ -$ 88LY4Pavement Management Program- Arterial Roadway Rehabilitation(Palos Verdes Drive East)330 (CIP)-$ -$ -$ -$ 210,000$ 4,825,000$ 88New4 Arterial Roadway Beautification Program330 (CIP)-$ 100,000$ -$ -$ -$ -$ 330 (CIP)-$ -$ -$ -$ -$ -$ 333 (ARPA Federal Grant)-$ 200,000$ -$ -$ -$ -$ 88New6 Retaining Wall Repairs at 3001 Crest Road330 (CIP)-$ 100,000$ -$ -$ -$ -$ 88New7Palos Verdes Drive East Traffic Improvements(from Bronco Drive to Headland Drive)330 (CIP)-$ 50,000$ TBDTBDTBDTBD23,277,100$ 18,280,000$ 16,624,900$ 11,810,000$ 8,625,000$ 9,925,000$ Funding Summary FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 202 (Gas Tax)338,718$ 500,000$ 530,000$ 925,000$ 735,000$ 700,000$ 202 (Gas Tax - SB1)170,000$ 1,200,000$ -$ -$ -$ -$ 211 (1911 Act)-$ -$ -$ -$ -$ -$ 215 (Prop. C)270,394$ 900,000$ -$ -$ -$ -$ 220 (Meas. R)795,800$ 1,400,000$ 525,000$ 520,000$ 530,000$ 530,000$ 221 (Meas. M)-$ -$ -$ -$ -$ -$ 221 (Meas. M - Grant)-$ 385,000$ 505,000$ 3,110,000$ -$ -$ 310 (CDBG)-$ 150,000$ 150,000$ 150,000$ 150,000$ 150,000$ 330 (CIP)15,915,328$ 9,283,000$ 13,470,000$ 6,845,000$ 7,210,000$ 8,545,000$ 331 (Federal Grants)-$ 105,000$ 894,900$ -$ -$ -$ 333 (ARPA Federal Grant)4,033,000$ 4,247,000$ 550,000$ 260,000$ -$ -$ 334 (Quimby park development)1,705,855$ -$ -$ -$ -$ -$ 340 (Bicycle & Ped access)-$ 110,000$ -$ -$ -$ -$ 23,229,095$ 18,280,000$ 16,624,900$ 11,810,000$ 8,625,000$ 9,925,000$ Guardrail Improvements along Palos Verdes Drive East8846 Traffic Calming - Citywide88LY2Pavement Management Program- Arterial Roadway Rehabilitation(Indian Peak Road)8847884888New5 City Entrance Roadway Monument SignsPavement Management Program- Arterial Roadway Rehabilitation(Silver Spur Road - South of Hawthorne Boulevard)C-3
Project CodeProject NameFundExpenses/Commitments to date FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 City of Rancho Palos VerdesPublic Works DepartmentProposed Five Year CIP Budget for Fiscal Years 2022-23, 2023-24, 2024-25, 2025-26 and 2026-27Wants/Needs List (Projects not recommended for funding in Fiscal Years 2022-23 through 2026-27)8200 Series Abalone Cove Santitary Sewer System Maintenance8300 Series Landslide Improvements8400 Series Parks, Open Space & Recreation Facilities8411Lower Point Vicente Parking Lot Lighting Improvements211 (1911 Act) -$ 8418Hesse Park Parking Lot & Lighting Improvements330 (CIP) -$ 8419Hesse Park Athletic Field Improvements330 (CIP) -$ 8421Lower Point Vicente Park Improvements330 (CIP) -$ 84LY1Lower Hesse Park Improvements330 (CIP) -$ 84LY2Point Vicente Interpretive Center "Bubbles" Statue Marquee Sign330 (CIP) -$ 8500 Series Building Improvements85LY2Replacement of the Civic Center Storm Room330 (CIP) -$ 8700 Series Sewer & Storm Drain Improvements8711 Bayend Drive Catch Basin Inlets and Storm Drain Lateral 330 (CIP)-$ 8713 Upper Point Vicente Stormwater Runoff Control Project (Helipad) 330 (CIP)-$ 8714Crest Road to Crestridge Canyon Stormwater Drainage Improvements330 (CIP)-$ 8718Stormwater Drainage Improvements- 6415 Corsini Place330 (CIP) 60,000.00$ 87New1Stormwater Drainage Improvements- Hawthorne Boulevard at Hawkhurst Drive330 (CIP) -$ 8800 Series Right-of-Way Improvements8811Arterial Walls and Fences Aesthetic Improvements Program - Citywide330 (CIP) -$ -$ -$ -$ -$ -$ 202 (Gas Tax) -$ 220 (Meas. R) -$ 330 (CIP) -$ 202 (Gas Tax) -$ 220 (Meas. R) -$ 330 (CIP) -$ 202 (Gas Tax) -$ 220 (Meas. R) -$ 330 (CIP) -$ 8839Palos Verdes Drive East Path Improvements (from Bronco Drive to Sunnyside Ridge Road)330 (CIP) 99,942.00$ 8849 Walking Path Improvements Program 330 (CIP) -$ 88LY3 Palos Verdes Drive West Pedestrian Crossing330 (CIP) -$ 88LY6 Ganado Drive Parkway Area Aesthetic Improvements330 (CIP) -$ 8834Pavement Management Program- Residential Roadway Rehabiitation - Areas 3 & 48817Pavement Management Program- Residential Roadway Rehabilitation - Area 78818Pavement Management Program- Residential Roadway Rehabilitation - Area 8Estimated cost of $260,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $3,925,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $225,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $1,830,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $515,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost TBDEstimated cost of $3,535,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $3,030,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $5,195,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $1,750,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $80,000 (accounting for inflation through Fiscal Year 2027-28)N/A due to scope of work not clearly defined yetEstimated cost of $1,985,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $715,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $360,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $200,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $335,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $1,365,000 (accounting for inflation through Fiscal Year 2027-28)Estimated cost of $1,785,000 (accounting for inflation through Fiscal Year 2027-28)C-4
Hawthorne Boulevard Median Beautification Project
(Completed in December 2020)
Capital Improvement Program
Fiscal Years 2022-23 through 2026-27
C-5
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
TABLE OF CONTENTS
INTRODUCTION ...................................................................................................................................
NEW CAPITAL PROJECTS ..................................................................................................................
CONTINUING CAPITAL PROJECTS ...................................................................................................
SUMMARY OF ALL CAPITAL PROJECTS ..........................................................................................
PROJECT SHEETS
ABALONE COVE SANITARY SEWER SYSTEM PROJECTS ...................................................
PORTUGUESE BEND LANDSLIDE PROJECTS .......................................................................
PARKS, OPEN SPACE AND RECREATIONAL FACILITIES PROJECTS .................................
PUBLIC BUILDINGS PROJECTS ...............................................................................................
SANITARY SEWER AND STORM DRAIN PROJECTS .............................................................
RIGHT-OF-WAY AREA PROJECTS ...........................................................................................
C-6
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
INTRODUCTION
In support of the City’s long term strategic planning tool, the General Plan, the City’s Capital
Improvement Program (CIP) is a five year planning tool, prioritizing capital programs and projects to
be accomplished within the next five fiscal years. Capital projects include rehabilitation, improvement,
or construction of utility systems, parks, open spaces, facilities, roadways, or other infrastructure; and
associated activities such as planning, engineering, land acquisition, or other support activities.
(Maintenance, repair and replacement of other assets, such as City automobiles, equipment and
furniture are accounted for in the operating budget, including the Equipment Replacement Fund, and
are not included in the CIP).
IMPORTANCE
Developing and maintaining infrastructure is one of the City's most important and critical
responsibilities. It is important to all residents of the community to have roadways that meet current
standards, functional utility systems, and quality recreation spaces and facilities. These improvements
can be very expensive, and there is a long list of competing needs throughout the City. The projects
range from trail improvements, street improvements, building improvements, to development of parks
and athletic fields. With such a long list, and limited funding from year to year, it is important to have a
plan in place that looks out to the future and provides a strategic approach to implementing these
projects. This is the reason for developing a CIP. The CIP is a guide to efficiently allocate resources
for improving and maintaining public infrastructure and facilities.
Programming capital improvements over time allows for the financial planning necessary to allocate
the City’s limited financial resources. Additionally, the CIP process is valuable as a means of
coordinating public and private development where possible. By looking beyond year-to-year
budgeting and projecting what, where, when, and how capital investments should be made; capital
planning enables public organizations to maintain an effective level of service for the present and future
population. It serves as the “blueprint” for the future of the community and is a management and
planning tool, rather than a binding document. The CIP provides the framework for the City’s
management team and the City Council with respect to investment planning, project planning, and the
managing of any City debt.
BACKGROUND
In 2008, the City Council established a goal in its tactical plan to identify infrastructure deficiencies and
develop a plan to construct, renew, improve, and maintain the City's infrastructure and facilities. Since
then, needs have been identified over the years through the development of various documents such
as the General Plan, Vision Plan, Public Use Master Plan, Pavement Management Plan, Storm Drain
Master Plan and many others. The needs identified in those plans were then combined with others
identified by staff, community members, and elected officials and ultimately included in the initial draft
Capital Improvement Program Plan, which was presented to the City Council during the 2010 budget
process. Since then, the CIP has been updated annually as a 5-year plan.
On July 15, 2014, the City Council established the Infrastructure Management Advisory Committee
(IMAC) to focus on the City’s infrastructure needs and advise the City Council on CIP projects.
C-7
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
DEVELOPMENT OF THE FIVE-YEAR CIP
The comprehensive CIP planning process has the following essential components:
The General Plan (Long-term Plan - 10 Years)
City Council Goals (Long-term and Short-term evaluated each year)
The Capital Improvement Program (Mid-term Plan - 5 Years)
The Capital Budget (Short-term Plan - 1 Year)
Annually, the City formally reviews the current CIP, removes completed programs and projects,
considers adding new programs and projects, makes adjustments, and schedules projects based on
available funding and resources.
Although infrastructure needs and other department requests may be identified and discussed at any
point in a fiscal year, potential new projects are compiled by the Public Works Department in the second
quarter of a fiscal year (October – December).
In the third quarter of a fiscal year (January – March), a list of current and proposed programs and
projects, along with cost estimates, is presented to IMAC for review and input. This process typically
involves multiple iterations where IMAC provides input and Public Works staff makes adjustments.
In April of each year, Staff presents a draft proposed CIP to the City Council at CIP budget workshop.
The City Council provides direction and staff revised the proposed CIP accordingly.
The proposed CIP is presented to the Planning Commission to verify that it is consistent with the goals
and policies of the City’s General Plan. Once verified, the Planning Commission adopts a resolution
to document its finding. Planning Commission Resolution No. 2022-04 was adopted on May 10, 2022
for the FY 2022-23 CIP.
In May and June of each year, the proposed CIP is presented to the City Council for consideration,
approval, and adoption. After adoption by the City Council during the budget process, the CIP becomes
the City’s plan for capital improvements for the next five years, with annual adjustments as needed.
C-8
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
Typical CIP Timeline
October-December Public Works compiles CIP project requests
January-March IMAC reviews projects/programs and provides input
April City Council CIP Workshop
May Planning Commission Review
May-June CIP presented to the City Council for consideration and approval
PW Prepares
CIP Requests
October -
December
PW/IMAC
Reviews Requests
January -
March
City Council CIP
WorkshopApril
Planining
Commission ReviewMay
City Council
Consideration & AdoptionMay/June
C-9
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
CAPITAL IMPROVEMENT PROGRAM POLICIES
The following policies are used in the evaluation and development of potential CIP programs and
projects:
Green Building Standards
The City of Rancho Palos Verdes requires the incorporation of green building principles and practices
into the design, construction, and operation of all City facilities, and to evaluate all land purchases for
future development on the basis of reducing environmental impacts whenever feasible.
Project Change Orders
Project change orders will be made in accordance with the policy stated in Section 02.44 of the
Municipal Code.
Cost Estimating
Planning – typically estimated to be 5% of construction costs
Engineering – typically estimated to be 10% of construction costs
Environmental – typically estimated to be 5% of construction costs
Management – typically estimated to be 5% of construction costs
Construction – based on formal Engineering estimates (if available), or recent and relevant unit pricing
Contingency Amount – varies from 10% when engineering is complete and construction is expected
within the next year, up to 30% when engineering is not complete and/or construction
is not expected in the next year
Inspection – typically estimated to be 10% of construction costs
The above are guidelines and vary based on the type of project, judgement of Staff, or unique
conditions.
All sub-budgets are rounded to the nearest $5,000
THE CAPITAL BUDGET
Although funding for the programs and projects is identified for each of the five years of the CIP, the
CIP is funded for one year, which runs concurrent with the operating budget fiscal year (beginning July
1st and ending June 30th of the following calendar year).
C-10
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
CIP programs and projects are scheduled based on available funding and resources, with priority given
to programming the use of grants and restricted funding in order to best utilize the Capital Improvement
Fund.
The CIP Fund (Fund 330)
Based on City Council Policy 41, last updated on March 16, 2021, revenue from the City’s Transient
Occupancy Tax (TOT) collected from the Terranea Resort is transferred to the Capital Improvement
Program Fund (Fund 330, or the CIP Fund) to fund CIP programs and projects, unless the City
Council elects to reduce that amount to offset a portion or all of the increases in the public safety
contract. Per that same policy, the City will maintain a minimum of $5 million in the CIP Fund as a
reserve for major projects related to roadways, storm drains, parks, buildings, rights-of-way, and the
sewer system.
For Fiscal Year 2021-22, expected TOT revenue is is estimated to be approximately $5.8 million.
Grants and Restricted Funding
To reserve the CIP Fund for projects that do not qualify for restricted funding, the City will budget the
use of grants and revenues and accumulated balances of restricted funding to the extent allowed by
applicable restrictions for CIP programs and projects. Examples of such funding includes:
Fund 202 (Gas tax)
Fund 211 (1911 Act)
Fund 215 (Proposition C)
Fund 220 (Measure R)
Fund 221 (Measure M and Measure M grants)
Fund 225 (Abalone Cove Sewer Maintenance)
Fund 310 (Community Development Block Grant)
Fund 331 (Federal Grants)
Fund 332 (State Grants)
Fund 334 (Quimby park development)
Fund 340 (Bicycle and Pedestrian Access)
* brief descriptions of the funds, and their restrictions, can be found in the City’s Annual
Comprehensive Financial Report
Detailed project sheets are contained in this program document for all projects included in the CIP.
Cost estimates have been included for each project based on project descriptions.
C-11
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
NEW CAPITAL PROJECTS
The following projects are those which have been identified as capital needs through various planning
processes along with a proposed funding source. Because the City Council approves CIP projects for
the upcoming year, proposed funding sources could change in subsequent years.
Project Code Project Name Fund
Expenses/
Commitments
to date FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
8400 Series Parks, Open Space & Recreation Facilities
330 (CIP)-$ -$ -$ -$ -$ -$
333 (ARPA Federal Grant)-$ 350,000$ -$ -$ -$ -$
330 (CIP)-$ -$ 350,000$ -$ -$ -$
333 (ARPA Federal Grant)-$ -$ -$ -$ -$ -$
8500 Series Building Improvements
330 (CIP)-$ -$ -$ TBD -$ -$
333 (ARPA Federal Grant)-$ -$ 90,000$ 260,000$ -$ -$
8800 Series Right-of-Way Improvements
88New6 Retaining Wall Repairs at 3001 Crest Road 330 (CIP)-$ 100,000$ -$ -$ -$ -$
88New7 Palos Verdes Drive East Traffic Improvements
(from Bronco Drive to Headland Drive)330 (CIP)-$ 50,000$ TBD TBD TBD TBD
84Pot1 Park Monument Signs
Park Playground Improvements
85Pot1
84Pot2
Restroom Improvements and New Office Space at Eastview Park
C-12
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
CONTINUING CAPITAL PROJECTS
The following projects are those which have been budgeted in prior fiscal years and are currently
underway. The funds are being continued so that the project can be completed, or work continued,
during this current fiscal year.
Project Code Project Name Fund
Expenses/
Commitments
to date FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
8200 Series Abalone Cove Santitary Sewer System Maintenance
225 (Ab Cove sewer maint.)48,005$ -$ -$ -$ -$ -$
330 (CIP)-$ 3,300,000$ 930,000$ -$ -$ -$
333 (ARPA Federal Grant)-$ -$ -$ -$ -$ -$
8300 Series Landslide Improvements
8301 Palos Verdes Drive South Realignment - East End 330 (CIP)111,425$ -$ -$ 75,000$ 1,845,000$ -$
215 (Prop. C)N/A - ongoing program 900,000$ -$ -$ -$ -$
330 (CIP)N/A - ongoing program 30,000$ 975,000$ 1,000,000$ 1,040,000$ 1,060,000$
220 (Meas. R)292,300$ -$ -$ -$ -$ -$
330 (CIP)804,387$ 535,000$ 6,180,000$ 2,135,000$ -$ -$
8400 Series Parks, Open Space & Recreation Facilities
8404 Fence Replacement Program 330 (CIP)-$ -$ 250,000$ -$ -$ -$
330 (CIP)13,111,229$ -$ -$ -$ -$ -$
333 (ARPA Federal Grant)3,953,000$ -$ -$ -$ -$ -$
334 (Quimby park development)1,705,855$ -$ -$ -$ -$ -$
8420 Palos Verdes Nature Preserve Signs Program 330 (CIP)248,405$ -$ -$ -$ -$ -$
8423 Palos Verdes Nature Preserve Gate for the Rattlesnake Trail 330 (CIP)-$ 210,000$ -$ -$ -$ -$
8500 Series Building Improvements
8503 New Civic Center Complex 330 (CIP)316,034$ 340,000$ 450,000$ -$ -$ -$
330 (CIP)-$ -$ -$ -$ -$ -$
333 (ARPA Federal Grant)35,000$ 350,000$ -$ -$ -$ -$
8509 Facilities Asset Management Program 330 (CIP)107,311$ 250,000$ TBD TBD TBD TBD
8700 Series Sewer & Storm Drain Improvements
8701 Storm Drain Asset Management Program & Master Plan Update 330 (CIP)115,000$ 450,000$ TBD TBD TBD TBD
8708 Altamira Canyon Improvements (Erosion)330 (CIP)365,727$ 450,000$ TBD TBD TBD TBD
330 (CIP)236,243$ 160,000$ -$ -$ -$ -$
333 (ARPA Federal Grant)-$ 1,035,000$ -$ -$ -$ -$
87New2 Lift Station Improvements at Lower Point Vicente 330 (CIP)-$ -$ 40,000$ 290,000$ -$ -$
Palos Verdes Drive South Landslide Area Resurfacing Program8302
8405 Ladera Linda Community Park Project
8715 Stormwater Drainage Improvements
- Palos Verdes Drive South at Peppertree Drive
Restroom Improvements at Point Vicente Interpretive Center8508
8202 Abalone Cove Sanitary Sewer Rehabilitation Program
8304 Portuguese Bend Landslide Remediation
C-13
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
C-14
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
SUMMARY OF ALL CAPITAL PROJECTS
The following table is a comprehensive list of all continuing and newly-funded projects, with project
status and identified funding sources.
Project Code Project Name Fund
Expenses/
Commitments
to date FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
8200 Series Abalone Cove Santitary Sewer System Maintenance
225 (Ab Cove sewer maint.)48,005$ -$ -$ -$ -$ -$
330 (CIP)-$ 3,300,000$ 930,000$ -$ -$ -$
333 (ARPA Federal Grant)-$ -$ -$ -$ -$ -$
8300 Series Landslide Improvements
8301 Palos Verdes Drive South Realignment - East End 330 (CIP)111,425$ -$ -$ 75,000$ 1,845,000$ -$
215 (Prop. C)N/A - ongoing program 900,000$ -$ -$ -$ -$
330 (CIP)N/A - ongoing program 30,000$ 975,000$ 1,000,000$ 1,040,000$ 1,060,000$
220 (Meas. R)292,300$ -$ -$ -$ -$ -$
330 (CIP)804,387$ 535,000$ 6,180,000$ 2,135,000$ -$ -$
8400 Series Parks, Open Space & Recreation Facilities
8404 Fence Replacement Program 330 (CIP)-$ -$ 250,000$ -$ -$ -$
330 (CIP)13,111,229$ -$ -$ -$ -$ -$
333 (ARPA Federal Grant)3,953,000$ -$ -$ -$ -$ -$
334 (Quimby park development)1,705,855$ -$ -$ -$ -$ -$
8420 Palos Verdes Nature Preserve Signs Program 330 (CIP)248,405$ -$ -$ -$ -$ -$
8423 Palos Verdes Nature Preserve Gate for the Rattlesnake Trail 330 (CIP)-$ 210,000$ -$ -$ -$ -$
330 (CIP)-$ -$ -$ -$ -$ -$
333 (ARPA Federal Grant)-$ 350,000$ -$ -$ -$ -$
330 (CIP)-$ -$ 350,000$ -$ -$ -$
333 (ARPA Federal Grant)-$ -$ -$ -$ -$ -$
8500 Series Building Improvements
8503 New Civic Center Complex 330 (CIP)316,034$ 340,000$ 450,000$ -$ -$ -$
330 (CIP)-$ -$ -$ -$ -$ -$
333 (ARPA Federal Grant)35,000$ 350,000$ -$ -$ -$ -$
8509 Facilities Asset Management Program 330 (CIP)107,311$ 250,000$ TBD TBD TBD TBD
330 (CIP)-$ -$ -$ TBD -$ -$
333 (ARPA Federal Grant)-$ -$ 90,000$ 260,000$ -$ -$
8700 Series Sewer & Storm Drain Improvements
8701 Storm Drain Asset Management Program & Master Plan Update 330 (CIP)115,000$ 450,000$ TBD TBD TBD TBD
8708 Altamira Canyon Improvements (Erosion)330 (CIP)365,727$ 450,000$ TBD TBD TBD TBD
330 (CIP)236,243$ 160,000$ -$ -$ -$ -$
333 (ARPA Federal Grant)-$ 1,035,000$ -$ -$ -$ -$
87New2 Lift Station Improvements at Lower Point Vicente 330 (CIP)-$ -$ 40,000$ 290,000$ -$ -$
84Pot1 Park Monument Signs
Park Playground Improvements
85Pot1
84Pot2
Restroom Improvements and New Office Space at Eastview Park
Palos Verdes Drive South Landslide Area Resurfacing Program8302
8405 Ladera Linda Community Park Project
8715 Stormwater Drainage Improvements
- Palos Verdes Drive South at Peppertree Drive
Restroom Improvements at Point Vicente Interpretive Center8508
8202 Abalone Cove Sanitary Sewer Rehabilitation Program
8304 Portuguese Bend Landslide Remediation
C-15
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
Project Code Project Name Fund
Expenses/
Commitments
to date FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
8800 Series Right-of-Way Improvements
8004 Traffic Signs Replacement Program 330 (CIP)N/A - ongoing program 215,000$ 225,000$ 110,000$ 130,000$ 155,000$
330 (CIP)N/A - ongoing program 350,000$ -$ 500,000$ -$ 520,000$
340 (Bicycle & Ped access) N/A - ongoing program 110,000$ -$ -$ -$ -$
202 (Gas Tax - SB1)170,000$ -$ -$ -$ -$ -$
330 (CIP)-$ 1,020,000$ -$ -$ -$ -$
333 (ARPA Federal Grant)-$ 500,000$ -$ -$ -$ -$
215 (Prop. C)200,000$ -$ -$ -$ -$ -$
220 (Meas. R)150,000$ -$ -$ -$ -$ -$
221 (Meas. M - Grant)-$ 385,000$ 505,000$ 3,110,000$ -$ -$
310 (CDBG)N/A - ongoing program 150,000$ 150,000$ 150,000$ 150,000$ 150,000$
330 (CIP)N/A - ongoing program -$ -$ -$ -$ -$
202 (Gas Tax)N/A - ongoing program -$ -$ -$ 735,000$ -$
220 (Meas. R)N/A - ongoing program -$ -$ -$ 530,000$ -$
330 (CIP)N/A - ongoing program -$ -$ -$ 1,805,000$ 100,000$
202 (Gas Tax)-$ 500,000$ -$ -$ -$ -$
202 (Gas Tax - SB1)-$ 1,200,000$ -$ -$ -$ -$
220 (Meas. R)38,500$ 1,400,000$ -$ -$ -$ -$
330 (CIP)-$ 1,045,000$ 100,000$ -$ -$ -$
202 (Gas Tax)N/A - ongoing program -$ -$ 925,000$ -$ -$
220 (Meas. R)N/A - ongoing program -$ -$ 520,000$ -$ -$
330 (CIP)N/A - ongoing program -$ -$ 1,270,000$ 100,000$ -$
202 (Gas Tax)N/A - ongoing program -$ 530,000$ -$ -$ -$
220 (Meas. R)N/A - ongoing program -$ 525,000$ -$ -$ -$
330 (CIP)N/A - ongoing program -$ 1,405,000$ 100,000$ -$ -$
215 (Prop. C)70,394$ -$ -$ -$ -$ -$
330 (CIP)8,200$ -$ -$ 100,000$ 1,075,000$ -$
202 (Gas Tax)N/A - ongoing program -$ -$ -$ -$ 700,000$
220 (Meas. R)N/A - ongoing program -$ -$ -$ -$ 530,000$
330 (CIP)N/A - ongoing program -$ -$ -$ -$ 1,420,000$
8837 Traffic Signal at intersection of Palos Verdes Drive South and
Palos Verdes Drive East 330 (CIP)361,618$ -$ -$ -$ -$ -$
330 (CIP)-$ -$ 2,100,000$ -$ -$ -$
333 (ARPA Federal Grant)-$ 140,000$ 460,000$ -$ -$ -$
202 (Gas Tax)-$ -$ -$ -$ -$ -$
333 (ARPA Federal Grant)45,000$ 1,672,000$ -$ -$ -$ -$
330 (CIP)54,749$ 143,000$ -$ -$ -$ -$
202 (Gas Tax)198,718$ -$ -$ -$ -$ -$
330 (CIP)-$ -$ -$ 160,000$ -$ -$
8845 Traffic Calming - PV Nature Preserve Parking Solutions 330 (CIP)75,000$ TBD -$ -$ -$ -$
220 (Meas. R)-$ -$ -$ -$ -$ -$
330 (CIP)-$ 535,000$ 430,000$ 450,000$ 460,000$ 465,000$
330 (CIP)-$ -$ -$ -$ -$ -$
331 (Federal Grants)-$ 105,000$ 894,900$ -$ -$ -$
202 (Gas Tax)140,000$ -$ -$ -$ -$ -$
220 (Meas. R)315,000$ -$ -$ -$ -$ -$
330 (CIP)-$ -$ -$ -$ -$ -$
88LY1
Pavement Management Program
- Arterial Roadway Rehabilitation
(Palos Verdes Drive South)
330 (CIP)-$ -$ 35,000$ 585,000$ -$ -$
220 (Meas. R)-$ -$ -$ -$ -$ -$
330 (CIP)-$ -$ -$ 70,000$ 545,000$ -$
88LY4
Pavement Management Program
- Arterial Roadway Rehabilitation
(Palos Verdes Drive East)
330 (CIP)-$ -$ -$ -$ 210,000$ 4,825,000$
88New4 Arterial Roadway Beautification Program 330 (CIP)-$ 100,000$ -$ -$ -$ -$
330 (CIP)-$ -$ -$ -$ -$ -$
333 (ARPA Federal Grant)-$ 200,000$ -$ -$ -$ -$
88New6 Retaining Wall Repairs at 3001 Crest Road 330 (CIP)-$ 100,000$ -$ -$ -$ -$
88New7 Palos Verdes Drive East Traffic Improvements
(from Bronco Drive to Headland Drive)330 (CIP)-$ 50,000$ TBD TBD TBD TBD
Guardrail Improvements along Palos Verdes Drive East
Palos Verdes Drive South Intersection Improvements
Pavement Management Program
- Residential Roadway Rehabilitation - Area 6
Pavement Management Program - Triennial Update
8815 Pavement Management Program
- Residential Roadway Rehabilitation - Area 5
8816 Pavement Management Program
- Residential Roadway Rehabilitation - Area 1
Community Development Block Grant Americans with Disabilities
Act Infrastructure Improvements8810
8843
Pavement Management Program
- Arterial Roadway Rehabilitation
(Silver Spur Road - North of Hawthorne Boulevard)
8846 Traffic Calming - Citywide
8836
8840 Western Avenue Beautification
88LY2
Pavement Management Program
- Arterial Roadway Rehabilitation
(Indian Peak Road)
8847
8848
88New5 City Entrance Roadway Monument Signs
8828
Pavement Management Program
- Arterial Roadway Rehabilitation
(Silver Spur Road - South of Hawthorne Boulevard)
8826 Pavement Management Program
- Residential Roadway Rehabilitation - Area 2
8819 Pavement Management Program
- Residential Roadway Rehabilitation - Area 9
8844
8801 Sidewalk Repair and Replacement Program
8808
Pavement Management Program
- Arterial Roadway Rehabilitation
(Crenshaw Boulevard)
8809 Western Avenue Traffic Flow Improvements
C-16
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
WANTS/NEEDS LIST
(Projects not recommended for funding in Fiscal Years 2022-23 through 2026-27)
The following table is a list of projects for which funding is not recommended in Fiscal Years 2022-23
through 2026-28, with estimated costs and potential funding sources.
Wants/Needs List (Projects not recommended for funding in Fiscal Years 2022-23 through 2026-27)
8200 Series Abalone Cove Santitary Sewer System Maintenance
8300 Series Landslide Improvements
8400 Series Parks, Open Space & Recreation Facilities
8411 Lower Point Vicente Parking Lot Lighting Improvements 211 (1911 Act)-$
8418 Hesse Park Parking Lot & Lighting Improvements 330 (CIP)-$
8419 Hesse Park Athletic Field Improvements 330 (CIP)-$
8421 Lower Point Vicente Park Improvements 330 (CIP)-$
84LY1 Lower Hesse Park Improvements 330 (CIP)-$
84LY2 Point Vicente Interpretive Center "Bubbles" Statue Marquee Sign 330 (CIP)-$
8500 Series Building Improvements
85LY2 Replacement of the Civic Center Storm Room 330 (CIP)-$
8700 Series Sewer & Storm Drain Improvements
8711 Bayend Drive Catch Basin Inlets and Storm Drain Lateral 330 (CIP)-$
8713 Upper Point Vicente Stormwater Runoff Control Project (Helipad)330 (CIP)-$
8714 Crest Road to Crestridge Canyon Stormwater Drainage
Improvements 330 (CIP)-$
8718 Stormwater Drainage Improvements
- 6415 Corsini Place 330 (CIP)60,000.00$
87New1 Stormwater Drainage Improvements
- Hawthorne Boulevard at Hawkhurst Drive 330 (CIP)-$
8800 Se ries Right-of-Way Improvements
8811 Arterial Walls and Fences Aesthetic Improvements Program -
Citywide 330 (CIP)-$
202 (Gas Tax)-$
220 (Meas. R)-$
330 (CIP)-$
202 (Gas Tax)-$
220 (Meas. R)-$
330 (CIP)-$
202 (Gas Tax)-$
220 (Meas. R)-$
330 (CIP)-$
8839 Palos Verdes Drive East Path Improvements
(from Bronco Drive to Sunnyside Ridge Road)330 (CIP)99,942.00$
8849 Walking Path Improvements Program 330 (CIP)-$
88LY3 Palos Verdes Drive West Pedestrian Crossing 330 (CIP)-$
88LY6 Ganado Drive Parkway Area Aesthetic Improvements 330 (CIP)-$
8834 Pavement Management Program
- Residential Roadway Rehabiitation - Areas 3 & 4
8817 Pavement Management Program
- Residential Roadway Rehabilitation - Area 7
8818 Pavement Management Program
- Residential Roadway Rehabilitation - Area 8
Estimated cost of $260,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $3,925,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $225,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $1,830,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $515,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost TBD
Estimated cost of $3,535,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $3,030,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $5,195,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost TBD
Estimated cost of $1,750,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $80,000 (accounting for inflation through Fiscal Year 2027-28)
N/A due to scope of work not clearly defined yet
Estimated cost of $1,985,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $715,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $360,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $200,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $335,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $1,365,000 (accounting for inflation through Fiscal Year 2027-28)
Estimated cost of $1,785,000 (accounting for inflation through Fiscal Year 2027-28)
C-17
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8200 SERIES PROJECTS – ABALONE COVE SANITARY SEWER SYSTEM
The Abalone Cove Sewer Maintenance is a unique system serving approximately 113 developed
parcels in an active landslide area, and is maintained by the City.
Sewer user fees are collected from property owners that provide for maintenance and rehabilitation of
the system.
The Abalone Cove Sewer System is currently subsidized by the City in accordance with Municipal
Code Section 13.06.010.
C-18
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8200 Series Abalone Cove Sanitary Sewer System Projects Project Code: 8202 Abalone Cove Sanitary Sewer System Rehabilitation Program
This project is intended to improve the Abalone Cove Sanitary Sewer
system and consists of:
- Replacing existing galvanized pipes
- Installing new pumps at four lift stations
- Installing new railings
- Installing new linings
- Installing a SCADA (Supervisory Control And Data Acquisition) system
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $48,005 $220,000 $65,000 $0 $0 $0 $333,005
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $330,000 $95,000 $0 $0 $0 $425,000
Construction $0 $2,200,000 $610,000 $0 $0 $0 $2,810,000
Contingency $0 $330,000 $95,000 $0 $0 $0 $425,000
Inspection $0 $220,000 $65,000 $0 $0 $0 $285,000
$48,005 $3,300,000 $930,000 $0 $0 $0 $4,278,005
Funding
225 (Ab Cove) $48,005 $0 $0 $0 $0 $0 $48,005
330 (CIP) $0 $3,300,000 $930,000 $0 $0 $0 $4,230,000
333 (ARPA) $0 $0 $0 $0 $0 $0 $0
$48,005 $3,300,000 $930,000 $0 $0 $0 $4,278,005
Estimated annual operating cost $8,000 Estimated Schedule:
Replacement of existing galvanized pipes in Fiscal Year 2022-23.
All other work in Fiscal Year 2023-24.
Project Location Map Background and Justification:
The City is obligated to maintain and improve the existing sewer system
to minimize the risk of overflows, as the State of California has adopted
a zero tolerance of such overflows. The project consists of two projects:
replacing the galvanized pipes and rehabilitating the lift stations.
Additional maintenance costs and possible fines for overflows will be
incurred if the described improvements are not installed.
Pipes are being scheduled to be replaced in FY 2021-22, as they are more
susceptible to failure and therefore are prioritized over the replacement
of the pumps and the lift stations.
C-19
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8300 SERIES PROJECTS – PORTUGUESE BEND LANDSLIDE PROJECTS
The Palos Verdes Drive South Landslide Projects refer to projects that lessen the effect of ground
movement in the Portuguese Bend Landslide, which is a continuously active landslide. These
projects are intended to address landslide movement and public safety risks by using proven
methods, such as reducing water infiltration, water percolation, eliminating water ponds, runoff
management, dewatering, and GPS monitoring.
C-20
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8300 Series Portuguese Bend Landslide Projects Project Code: 8301 Palos Verdes Drive South Realignment – East End
This project is intended to realign and reconstruct of Palos Verdes Drive
South at the east end of the Portuguese Bend Landslide and consists of:
- Relocating pavement to within the public right of way
- Install striping and pavement markings
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $111,425 $0 $0 $75,000 $0 $0 $186,425
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $75,000 $0 $75,000
Construction $0 $0 $0 $0 $1,470,000 $0 $1,470,000
Contingency $0 $0 $0 $0 $150,000 $0 $150,000
Inspection $0 $0 $0 $0 $150,000 $0 $150,000
$111,425 $0 $0 $75,000 $1,845,000 $0 $2,031,425
Funding
330 (CIP) $111,425 $0 $0 $75,000 $1,845,000 $0 $2,031,425
$111,425 $0 $0 $75,000 $1,845,000 $0 $2,031,425
Estimated annual operating cost None Estimated Schedule:
Engineering in Fiscal Year 2024-25
Construction in Fiscal Year 2025-26
Project Location Map Background and Justification:
Due to land movement associated with the Portuguese Bend Landslide,
this portion of the road has encroached onto private property. The
current configuration of the roadway needs to be modified to allow for a
more direct travel path. This project will result in an improved driving
experience when passing through the area.
C-21
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8300 Series Portuguese Bend Landslide Projects Project Code: 8302 Palos Verdes Drive South Landslide Area Resurfacing Program
This project is intended to repair and maintain Palos Verdes Drive South
through the Landslide and consists of:
- repairing and maintaining the asphalt roadway
- repairing and maintaining storm drain lines
- repairing and maintaining curbs and gutters
- installing and maintaining signs and roadway striping
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 $0 $0 $0 TBD
Engineering N/A – ongoing program $40,000 $40,000 $40,000 $45,000 $45,000 TBD
Environmental N/A – ongoing program $0 $0 $0 $0 $0 TBD
Management N/A – ongoing program $75,000 $80,000 $80,000 $85,000 $85,000 TBD
Construction N/A – ongoing program $740,000 $775,000 $800,000 $825,000 $845,000 TBD
Contingency N/A – ongoing program $0 $0 $0 $0 $0 TBD
Inspection N/A – ongoing program $75,000 $80,000 $80,000 $85,000 $85,000 TBD
N/A – ongoing program $930,000 $975,000 $1,000,000 $1,040,000 $1,060,000 TBD
Funding
215 (Prop. C) N/A – ongoing program $900,000 $0 $0 $0 $0 TBD
330 (CIP) N/A – ongoing program $30,000 $975,000 $1,000,000 $1,040,000 $1,060,000 TBD
N/A – ongoing program $930,000 $975,000 $1,000,000 $1,040,000 $1,060,000 TBD
Estimated annual operating cost N/A – ongoing program Estimated Schedule:
Routine resurfacing occurs in response to damage caused by the Portuguese Bend Landslide and is an annual budget item (Fiscal Years 2021-22, 2022-23, 2023-24, 2024-25 and 2025-26 are shown here).
Project Location Map Background and Justification:
The City is required to properly maintain the roadway; performing repairs,
resurfacing and patching to mitigate impacts to the traveling public caused
by the land movement in this area. The program is expected to continue
until landslide movement in this area can be slowed. Work is performed
an as-needed basis, and weekly inspection of the landslide is required to
discover and repair defects in a timely fashion.
C-22
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8300 Series Portuguese Bend Landslide Projects Project Code: 8304 Portuguese Bend Landslide Remediation
Based on current council direction, this project is intended to evaluate and
analyze the Portuguese Bend landslide and engineer solutions to slow or minimize
the land movement, and includes:
- Infilling fractures (phase I)
- Installing/refurbishing drainage pipe, new surface swales and a flow reductions
area (phase II)
- (Potentially) Installing Hydraugers (dewatering devices – phase III)
Phases of construction may be modified based on alternatives selected from final
EIR. Current proposed funding only includes phases I and II, but funding may be
redirected depending on selected alternatives.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $3,380 $100,000 $100,000 $100,000 TBD TBD TBD
Engineering $772,060 $285,000 $110,000 $40,000 TBD TBD TBD
Environmental $12,250 $50,000 $0 $0 TBD TBD TBD
Management $308,997 $100,000 $640,000 $215,000 TBD TBD TBD
Construction $0 $0 $4,260,000 $1,420,000 TBD TBD TBD
Contingency $0 $0 $640,000 $215,000 TBD TBD TBD
Inspection $0 $0 $430,000 $145,000 TBD TBD TBD
$1,096,687 $535,000 $6,180,000 $2,135,000 TBD TBD TBD
Funding
220 (Meas. R) $292,300 $0 $0 $0 TBD TBD TBD
330 (CIP) $804,387 $535,000 $6,180,000 $2,135,000 TBD TBD TBD
$1,096,687 $535,000 $6,180,000 $2,135,000 TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Phase I Engineering in Fiscal Year 2022-23.
Phase I Construction in Fiscal Year 2023-24.
Phase II Engineering in Fiscal Year 2023-24.
Phase II Construction in Fiscal Year 2024-25. Project Location Map Background and Justification:
The landslide in the Portuguese Bend area creates a number of
challenges for the City and the community, including damage to the Palos
Verdes Drive South roadway and moving of public and private properties,
including homes. The completion of this project will help minimize
movement in the landslide, thereby minimizing potential impacts to the
surrounding environment including marine life in the event the existing
above-ground sewer lines are damaged. It will also minimize damage to
public and private properties, including the roadway, and will alleviate
the need for the Annual Portuguese Bend Landslide Area Resurfacing
Program.
Work will be coordinated with all applicable local, State and Federal
agencies, including the California Coastal Commission and Palos Verdes
Peninsula Land Conservancy (PVPLC).
C-23
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 SERIES PROJECTS – PARKS, OPEN SPACE & RECREATIONAL FACILITIES
The development and maintenance of community parks, recreational areas, and open space has
been established as a top priority for the City, as stated in the General Plan and various other
planning documents. The General Plan states,
“It is the goal of the City of Rancho Palos Verdes to conserve, protect, and enhance its natural
resources, beauty, and open space for the benefit and enjoyment of its residents and the
residents of the entire region. Future development shall recognize the sensitivity of the natural
environment and be accomplished in such a manner as to maximize the protection of it.”
Many park sites and open space areas have been acquired throughout the City and developed for
use. Some sites remain vacant or underutilized. The Public Use Master Plan has also outlined a
strategy for the development of trails. These recreational projects add to the vibrancy of the
community and are designed to contribute to all residents’ quality of life. Parks and other open
spaces have been carefully planned to take advantage of the beautiful coastline and natural
landscape of the peninsula.
The City Council approved an update to the 1989 Parks Master Plan on October 15, 2015. This
update, known as the Parks Master Plan Update (PMPU), provides a comprehensive strategy for
addressing the future use of the City’s parks, recreation and open space resources. The PMPU
serves as a long-range vision for the City’s recreation opportunities within a flexible framework than
can be adapted to changes in technology, demographics, economics, and shifting recreational
trends.
The PMPU consolidated plans that currently exist for a number of major park sites, while being
consistent and in compliance with the City’s General Plan and other guiding documents, including
the Parks Master Plan and Conceptual Trails Network Plan (CTN).
The Parks Master Plan’s precise impact to the CIP is not known at this time. A number of projects
that will likely be part of the final Master Plan document are probably already part of the current CIP’s
funded or unfunded categories, while other recommended projects may not reach the CIP threshold.
TRAILS
The City of Rancho Palos Verdes began planning for a non-motor vehicle transportation circulation
system for pedestrians, equestrians, and bicyclists, as early as the adoption of the City’s General
Plan in 1975. In the early years after the city’s formation, it was recognized that trails are an integral
part of the city’s circulation system and play an important role in contributing to the successful
interaction of residential, institutional, commercial and recreational zoning districts within the city,
while encouraging recreational and fitness opportunities.
As such, on November 27, 1984, the City Council adopted the Trails Network Plan, which was
intended to serve as an advisory tool for City decision-makers for the implementation and funding of
City trails. As a means of implementing the Trails Network Plan, on January 22, 1990, the City
Council adopted the Conceptual Trails Plan (CTP) and Conceptual Bikeways Plan (CBP) as two
separate documents. Collectively, the CTP and CBP serve as the City’s Trails Network Plan (TNP).
C-24
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
The CTP was revised on May 21, 1991, September 16, 1991, and October 26, 1991. The CBP was
revised on October 15, 1996.
The City is currently in the process of updating the TNP to consolidate all of its existing trails plans
and documents into a single, comprehensive plan. Trail projects will be developed using the updated
TNP as a guide as policy and funding permits.
C-25
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Projects Project Code: 8404 Fence Replacement Program
This project is intended to replace existing fencing at Frank A. Vanderlip,
Sr. Park & Del Cerro Park.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 $0 $0 $0 $0
Engineering N/A – ongoing program $0 $10,000 $0 $0 $0 $10,000
Environmental N/A – ongoing program $0 $0 $0 $0 $0 $0
Management N/A – ongoing program $0 $10,000 $0 $0 $0 $10,000
Construction N/A – ongoing program $0 $160,000 $0 $0 $0 $160,000
Contingency N/A – ongoing program $0 $50,000 $0 $0 $0 $50,000
Inspection N/A – ongoing program $0 $20,000 $0 $0 $0 $20,000
N/A – ongoing program $0 $250,000 $0 $0 $0 $250,000
Funding
330 (CIP) N/A – ongoing program $0 $250,000 $0 $0 $0 $250,000
N/A – ongoing program $0 $250,000 $0 $0 $0 $250,000
Estimated annual operating cost None Estimated Schedule:
Construction in FY 2023-24
Project Location Map Background and Justification:
Prior to establishing this program; the City was receiving a growing
number of complaints about the condition of the deteriorating existing
metal pipe coastal bluff fencing. The aesthetics of the public trails and
parks is improved through this program.
During budget discussions in February 2021, the Recreation and Parks
Department requested fencing at Del Cerro Park be replaced, and the
Coastal Bluff Fence Program was expanded to include this requested
area.
C-26
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Projects Project Code: 8405 Ladera Linda Community Park Project
This project is intended to replace the existing buildings located at the site
with a new community center, refurbish the grounds and consists of:
- removing the existing buildings and infrastructure
- building a new community center and associated infrastructure
- building a new parking lot
- building a new park and associated equipment
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 TBD TBD TBD TBD TBD TBD
Engineering $1,280,990 TBD TBD TBD TBD TBD TBD
Environmental $72,155 TBD TBD TBD TBD TBD TBD
Management $917,504 TBD TBD TBD TBD TBD TBD
Construction $15,081,544 TBD TBD TBD TBD TBD TBD
Contingency $1,172,000 TBD TBD TBD TBD TBD TBD
Inspection $245,891 TBD TBD TBD TBD TBD TBD
$18,770,084 TBD TBD TBD TBD TBD TBD
Funding
330 (CIP) $13,111,229 TBD TBD TBD TBD TBD TBD
333 (ARPA) $3,953,000 TBD TBD TBD TBD TBD TBD
334 (Quimby) $1,705,855 TBD TBD TBD TBD TBD TBD
$18,770,084 TBD TBD TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction (appropriated on March 1, 2022) to continue in Fiscal Year 2022-23.
Project Location Map Background and Justification:
On the 2013 Infrastructure Report Card, the existing Community Building,
Discovery Room, Multi-purpose Room, Classrooms and Restrooms all
received a grade of “F”. This grading was based on criteria such as
structural/seismic conditions, finishes, functionality of building systems
(plumbing, electrical, HVAC and firefighting), safety issues and
sustainability and energy saving.
Improvements to the Ladera Linda Park and Community Center are
needed to meet the existing and future needs of the community. The
facility has passed its useful life, and its uses are very limited in its current
condition.
C-27
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Projects Project Code: 8420 Palos Verdes Nature Preserve Signs Program This project consists of installing signs in eleven (11) of the twelve (12)
Reserves of the Palos Verdes Nature Preserve.
There are four types of signs for each Reserve
Reserve monument signs (larger, and on a stone foundation)
Reserve monument signs (smaller, and without stone)
Regulatory signs – which includes the Reserve name, map of trails
in the Reserve, interpretive information and a list of Preserve rules
Regulatory signs – list of Preserve rules
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0
Construction $249,000 $0 $0 $0 $0 $0 $249,000
Contingency $0 $0 $0 $0 $0 $0 $0
Inspection $0 $0 $0 $0 $0 $0 $0
$249,000 $0 $0 $0 $0 $0 $249,000
Funding
330 (CIP) $249,000 $0 $0 $0 $0 $0 $249,000
$249,000 $0 $0 $0 $0 $0 $249,000
Estimated annual operating cost None Estimated Schedule:
Construction in a Fiscal Year 2022-23
Project Location Map Background and Justification:
Signs for nine of the Reserves have been successfully installed.
Signs for the remaining two Reserves, the Ocean Trails Reserve and Malaga
Canyon Reserve, are pending as interpretive information for the larger
regulatory signs is developed. Additionally, creation of a map of trails for
Malaga Canyon is pending the adoption of trails for that recently acquired
Reserve.
Work related to this project is being performed in coordination with the
Palos Verdes Peninsula Land Conservancy (PVPLC), which manages the
habitat in the City’s property that comprises the Palos Verdes Nature
Preserve.
Signs for each Reserve will notify visitors as to which part of the Palos
Verdes Nature Preserve they are in, provide information to educate
visitors about the local habitat and native species, and contain trail maps.
C-28
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Projects Project Code: 8423 Palos Verdes Nature Preserve Gate for the Rattlesnake Trail
This project consists of improvements to secure the main entry point to
the Filiorum Reserve of the Palos Verdes Nature Preserve, and includes:
A new gate and fencing
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $15,000 $0 $0 $0 $0 $15,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $10,000 $0 $0 $0 $0 $10,000
Construction $0 $130,000 $0 $0 $0 $0 $130,000
Contingency $0 $40,000 $0 $0 $0 $0 $40,000
Inspection $0 $15,000 $0 $0 $0 $0 $15,000
$0 $210,000 $0 $0 $0 $0 $210,000
Funding
330 (CIP) $0 $210,000 $0 $0 $0 $0 $210,000
$0 $210,000 $0 $0 $0 $0 $210,000
Estimated annual operating cost None Estimated Schedule:
Engineering and Construction in a Fiscal Year 2022-23
Project Location Map Background and Justification:
It is important to control pedestrian traffic into the Filiorum Reserve at
times, such as after sunset at after heavy rainfall, to protect the Reserve
and the quality of life for neighboring residents. Access to the trailhead of
the Rattlesnake Trail is currently provided only by an opening in the fence
along Crenshaw Boulevard.
A new gate will enhance the security of the Filiorum Reserve of the Palos
Verdes Nature Preserve and will reduce the negative quality of life issues
for neighbors. The new gate will also enable City staff to better manage
the Preserve.
C-29
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Projects Project Code: 84Pot1 Park Monument Signs
This project is intended to redesign and install new park monument entry
signs, including lighting and landscaping, at various park locations
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $15,000 $0 $0 $0 $0 $15,000
Engineering $0 $40,000 $0 $0 $0 $0 $40,000
Environmental $0 $5,000 $0 $0 $0 $0 $5,000
Management $0 $10,000 $0 $0 $0 $0 $10,000
Construction $0 $200,000 $0 $0 $0 $0 $200,000
Contingency $0 $60,000 $0 $0 $0 $0 $60,000
Inspection $0 $20,000 $0 $0 $0 $0 $20,000
$0 $350,000 $0 $0 $0 $0 $350,000
Funding
330 (CIP) $0 $0 $0 $0 $0 $0 $0
333 (ARPA) $0 $350,000 $0 $0 $0 $0 $350,000
$0 $350,000 $0 $0 $0 $0 $350,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction in Fiscal Year 2022-23
Project Location Map Background and Justification:
Many existing monument signs are out of date, old and/or in need of
repair. The monument signage should have a fresh new look to boldly
identify RPV and the parks.
C-30
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Projects Project Code: 84Pot2 Park Playground Improvements
This project is intended to address areas of concern, identified by a
facilities assessment conducted by a Public Works consultant, by making
repairs and improvements to City Playgrounds.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $15,000 $0 $0 $0 $15,000
Engineering $0 $0 $25,000 $0 $0 $0 $25,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $15,000 $0 $0 $0 $15,000
Construction $0 $0 $205,000 $0 $0 $0 $205,000
Contingency $0 $0 $65,000 $0 $0 $0 $65,000
Inspection $0 $0 $25,000 $0 $0 $0 $25,000
$0 $0 $350,000 $0 $0 $0 $350,000
Funding
330 (CIP) $0 $0 $350,000 $0 $0 $0 $350,000
333 (ARPA) $0 $0 $0 $0 $0 $0 $0
$0 $0 $350,000 $0 $0 $0 $350,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction in Fiscal Year 2023-24
Project Location Map Background and Justification:
Based on the outcome of a facilities assessment, conducted by a Public
Works consultant, the City will address areas of concern and update the
playground structures and surfacing.
C-31
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
PUBLIC BUILDINGS PROJECTS
Buildings and other facility improvements may include any proposed new City facility, renovation, or
improvement of any existing City facilities. The City owns and maintains the following public
buildings:
City Hall Administration Building at Point Vicente Park
City Hall Community Development Building at Point Vicente Park
RPV TV Studio Building at Point Vicente Park
City Hall trailer leased by Palos Verdes on the Net at Point Vicente Park
City Hall Emergency Communications Center trailer at Point Vicente Park
Fred Hesse Jr. Community Center Building (John C. McTaggart Hall)
Pointe Vicente Interpretive Center (PVIC) at Lower Point Vicente Park
Robert Ryan Park Building
Ladera Linda Community Center Buildings (5)
Buildings at Abalone Cove Shoreline Park, currently used for staffing, public restrooms, and
a nursery school on the beach.
Pelican Cove Restroom Building
Eastview Park Restroom Buildings
Except for PVIC, these buildings are 25 years old or more and showing signs of daily use. Many of
the facilities were purchased from the school district or transferred to the City from the federal
government. In some cases, little to no improvements have been made since their acquisition. It is
important to perform adequate maintenance to extend the life of these facilities. It will be necessary
to renovate these buildings as they age to meet the needs of the community and ensure that all
building and safety guidelines are satisfied. PVIC, the most recently remodeled City facility, was built
in 1984 and expanded in 2005. The City Hall buildings and Ladera Linda Community Center
buildings are the best examples of buildings that are in need of renovation to meet organizational
needs, comply with safety and code requirements, and comply with all Americans with Disabilities
Act (ADA) guidelines. The projects listed on the following pages have been developed based on staff
assessments, input from the community, and professional consultants’ assessments and studies.
C-32
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8500 Series Public Buildings Projects Project Code: 8503 New Civic Center Complex
This project consists of preparing supporting documents and providing
services towards the future development of a Master Plan for the Upper
Point Vicente property for the purpose of the Civic Center and open space
improvements.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $327,662 $340,000 $450,000 TBD TBD TBD TBD
Engineering $0 $0 $0 TBD TBD TBD TBD
Environmental $0 $0 $0 TBD TBD TBD TBD
Management $0 $0 $0 TBD TBD TBD TBD
Construction $0 $0 $0 TBD TBD TBD TBD
Contingency $0 $0 $0 TBD TBD TBD TBD
Inspection $0 $0 $0 TBD TBD TBD TBD
$327,662 $340,000 $450,000 TBD TBD TBD TBD
Funding
330 (CIP) $327,662 $340,000 $450,000 TBD TBD TBD TBD
$327,662 $340,000 $450,000 TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Project management services continuing in Fiscal Years 2022-23 and 2023-24 Other services and construction to be determined
Project Location Map Background and Justification:
As part of the City’s update to the Parks Master Plan, site specific
workshops are being held to receive community input regarding desired
uses at the park. A Master Plan will be created that represents the
interests of the residents. The Civic Center Advisory Committee was
created to advise and to provide recommendations to the City Council.
A Master Plan serves as a framework to major components or elements
for the City Council’s consideration and could include a variety of uses as
recommended by the community through the advisory committee.
City Council has authorized hiring of consultant to provide
Planning/Project Management services.
C-33
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8500 Series Public Buildings Projects Project Code: 8508 Restroom Improvements at the Point Vicente Interpretive Center
This project is intended to improve the function and aesthetics of the
bathrooms (interior and exterior) at the Point Vicente Interpretive Center
and consists of:
- Replacing existing plumbing and fixtures
- Replacing wall and ceiling surfaces
- Replacing existing flooring
- Installing new stall dividers
- Installing new lighting fixtures, mirrors and accessory equipment
(hand dryers, toilet paper dispensers, etc.)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $35,000 $0 $0 $0 $0 $0 $35,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $15,000 $0 $0 $0 $0 $15,000
Construction $0 $235,000 $0 $0 $0 $0 $235,000
Contingency $0 $75,000 $0 $0 $0 $0 $75,000
Inspection $0 $25,000 $0 $0 $0 $0 $25,000
$35,000 $350,000 $0 $0 $0 $0 $385,000
Funding
330 (CIP) $0 $0 $0 $0 $0 $0 $0
333 (ARPA) $35,000 $350,000 $0 $0 $0 $0 $385,000
$35,000 $350,000 $0 $0 $0 $0 $385,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction in Fiscal Year 2022-23
Project Location Map Background and Justification:
The plumbing in the existing restrooms (both interior and exterior) often
clogs, requiring the bathrooms to be placed out of service and is a source
of regular complaints from the public.
Even when in service, the restrooms often smell bad as a result of poor
plumbing.
Bathroom improvements are needed at the PVIC to better represent the
City of Rancho Palos Verdes, and provide better facilities to the public and
those who rent the facility for weddings and special events.
C-34
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8500 Series Public Buildings Projects Project Code: 8509 Facilities Asset Management Program
This program is intended assess and maintain City Facilities regularly, and
consists of:
- Inspecting the existing facilities and determining their condition
- Recommending a schedule for needed maintenance, repairs and
replacement of components, with estimated costs
- Carrying out the work
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $107,311 $0 TBD TBD TBD TBD TBD
Engineering $0 $20,000 TBD TBD TBD TBD TBD
Environmental $0 $0 TBD TBD TBD TBD TBD
Management $0 $10,000 TBD TBD TBD TBD TBD
Construction $0 $155,000 TBD TBD TBD TBD TBD
Contingency $0 $45,000 TBD TBD TBD TBD TBD
Inspection $0 $20,000 TBD TBD TBD TBD TBD
$107,311 $250,000 TBD TBD TBD TBD TBD
Funding
330 (CIP) $107,311 $250,000 TBD TBD TBD TBD TBD
$107,311 $250,000 TBD TBD TBD TBD TBD
Estimated annual operating cost None Estimated Schedule:
Construction in Fiscal Year 2022-23
Project Location Map Background and Justification:
This is an asset management program for all City Facilities to create a
schedule of ongoing maintenance and repairs for the City’s five main
facilities:
- Civic Center
- Eastview Park
- Hesse Park
- Point Vicente Interpretive Center
- Ryan Park
C-35
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8500 Series Public Buildings Projects Project Code: 85Pot1 Restroom Improvements and New Office Space at Eastview Park
This project is intended to renovate or replace the existing restrooms, and
create new permanent office space at Eastview Park.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $75,000 $0 TBD TBD TBD
Engineering $0 $0 $0 $0 TBD TBD TBD
Environmental $0 $0 $15,000 $0 TBD TBD TBD
Management $0 $0 $0 $10,000 TBD TBD TBD
Construction $0 $0 $0 $175,000 TBD TBD TBD
Contingency $0 $0 $0 $55,000 TBD TBD TBD
Inspection $0 $0 $0 $20,000 TBD TBD TBD
$0 $0 $90,000 $260,000 TBD TBD TBD
Funding
330 (CIP) $0 $0 $0 $0 TBD TBD TBD
333 (ARPA) $0 $0 $90,000 $260,000 $0 $0 $350,000
$0 $0 $90,000 $260,000 TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Planning and Environmental in Fiscal Year 2023-24 Construction in a Fiscal Year TBD
Project Location Map Background and Justification:
The existing restrooms at Eastview Park are in poor condition and are a
poor reflection on the City of Rancho Palos Verdes and the community.
Additionally, a small trailer on wheels is parked next to the restrooms for
Recreation and Parks staff to utilize for office space that is inadequate in
size and in poor condition.
C-36
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 SERIES PROJECTS – SEWER & STORM DRAIN IMPROVEMENTS
Projects in this section are to make improvements to existing infrastructure facilities of, or build
new facilities for, the City’s Sanitary Sewer, the Abalone Cover Sewer or Storm Water systems.
The Sanitary Sewer System
Although the City’s sanitary sewer system is owned by the City and, through an inter-local agreement
with the County of Los Angeles, the County is responsible for ongoing maintenance of the system,
with the exception of the Abalone Cove Sewer System. Maintenance of the sewer system (not
including the Abalone Cove Sewer System) is funded with fees collected by the County from property
owners that are connected to the sewer system. Funding for the maintenance of the Abalone Cove
Sewer System includes contributions from property owners connected to the Abalone Cove Sewer
System and the City.
The City maintains legal and regulatory responsibility (i.e., any state or federal fines resulting from
spillage) for the system, and retains responsibility for its operation, public safety, and welfare, and
any increases in pipe capacity required by the approval of private development. This also includes
responsibility for replacement of pipes due to capacity issues, as the County’s maintenance and
repair program does not provide such replacement.
The City developed a Sanitary Sewer Management Plan in 2004, which was created to help in the
management of this asset, and updated that Master Plan in 2009. The City also conducted an
evaluation of the Sanitary Sewer System and the Abalone Cove District Sewer System in 2013. With
no capacity limitations identified, no Sanitary Sewer System projects were proposed for this 5-year
CIP.
The County hired a contractor to perform a Closed-Circuit Televising (CCTV) inspection and cleaning
of the local sanitary sewer lines, which is expected to conclude in 2021.
The Storm Water System
The 2015 Master Plan of Drainage identified projects to correct pipes with deficient capacity, poor
physical condition, or both; using available data dating back to 2013. The Storm Drain Asset
Management Program will be a completion and update of the 2015 Master Plan.
C-37
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 8701 Storm Drain Asset Management Program
This program intended to assess and maintain the City’s Storm Drain assets
(specifically for larger pipes), and consists of:
- Inspecting the existing infrastructure and determining its condition
- Recommending a schedule for needed maintenance, repairs, and
replacement of components, with estimated costs
- Carrying out the work
This program will also include an update to the drainage master plan
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $115,000 $0 TBD TBD TBD TBD TBD
Engineering $0 $450,000 TBD TBD TBD TBD TBD
Environmental $0 $0 TBD TBD TBD TBD TBD
Management $0 $0 TBD TBD TBD TBD TBD
Construction $0 $0 TBD TBD TBD TBD TBD
Contingency $0 $0 TBD TBD TBD TBD TBD
Inspection $0 $0 TBD TBD TBD TBD TBD
$115,000 $450,000 TBD TBD TBD TBD TBD
Funding
330 (CIP) $115,000 $450,000 TBD TBD TBD TBD TBD
$115,000 $450,000 TBD TBD TBD TBD TBD
Estimated annual operating cost None Estimated Schedule:
Engineering in Fiscal Year 2022-23
Project Location Map Background and Justification:
This is an asset management program for the City’s drainage infrastructure
to create a schedule of ongoing maintenance and repairs.
C-38
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 8708 Altamira Canyon Improvements (Erosion)
This project is intended to prevent further erosion, and consists of:
Phase 1
- Reviewing a previous study of a portion of the water shed
- Performing an engineering analysis of the entire Altamira Canyon and its
tributaries
- Establishing a priority for improvements
Phase 2 - Preparing detailed plans for mitigation measures
Phase 3 - Constructing of the mitigation measures
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 TBD TBD TBD TBD TBD
Engineering $279,967 $0 TBD TBD TBD TBD TBD
Environmental $0 $350,000 TBD TBD TBD TBD TBD
Management $85,760 $100,000 TBD TBD TBD TBD TBD
Construction $0 $0 TBD TBD TBD TBD TBD
Contingency $0 $0 TBD TBD TBD TBD TBD
Inspection $0 $0 TBD TBD TBD TBD TBD
$365,727 $450,000 TBD TBD TBD TBD TBD
Funding
330 (CIP) $365,727 $450,000 TBD TBD TBD TBD TBD
$365,727 $450,000 TBD TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Environmental in Fiscal Year 2022-23 Engineering and Construction in Fiscal Years to be determined
Project Location Map Background and Justification:
The canyon has been eroding for the last several years
This study is needed to identify measures to mitigate the erosion of the
Altamira Canyon and control the water runoff percolating into the soil.
C-39
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 8715 Stormwater Drainage Improvements Palos Verdes Drive South at Peppertree Drive
This project is intended to repair storm drain systems, and consists of:
- Replacing and improving the existing underground storm drain system
(lateral pipes and main storm drain pipes)
- Installing new catch basins, drainage inlets and manholes
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $236,243 $40,000 $0 $0 $0 $0 $276,243
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $40,000 $0 $0 $0 $0 $40,000
Construction $0 $795,000 $0 $0 $0 $0 $795,000
Contingency $0 $240,000 $0 $0 $0 $0 $240,000
Inspection $0 $80,000 $0 $0 $0 $0 $80,000
$236,243 $1,195,000 $0 $0 $0 $0 $1,431,243
Funding
330 (CIP) $236,243 $160,000 $0 $0 $0 $0 $396,243
333 (ARPA) $0 $1,035,000 $0 $0 $0 $0 $1,035,00
$236,243 $1,195,000 $0 $0 $0 $0 $1,431,243
Estimated annual operating cost None Estimated Schedule:
Engineering and Construction in FY 2023-24
Project Location Map Background and Justification:
The 2015 Master Plan of Drainage identified needed improvements
throughout the City and this location was included in a list of areas to be
improved. Design work for improvements to these areas is being
completed in the 2019/2020 Fiscal Year.
This project controls erosion, manages the ground water and reduces the
likelihood of flooding.
C-40
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 87New2 Lift Station Improvements at Lower Point Vicente
This project consists of:
- Replacing existing pumps
- Replacing existing railings
- Installing new linings
- Installing a new SCADA (Supervisory Control And Data Acquisition)
system and control panel
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $40,000 $0 $0 $0 $40,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $10,000 $0 $0 $10,000
Construction $0 $0 $0 $200,000 $0 $0 $200,000
Contingency $0 $0 $0 $60,000 $0 $0 $60,000
Inspection $0 $0 $0 $20,000 $0 $0 $20,000
$0 $0 $40,000 $290,000 $0 $0 $330,000
Funding
330 (CIP) $0 $0 $40,000 $290,000 $0 $0 $330,000
$0 $0 $40,000 $290,000 $0 $0 $330,000
Estimated annual operating cost $2,600 Estimated Schedule:
Engineering in Fiscal Year 2023-24.
Construction in Fiscal Year 2024-25.
Project Location Map Background and Justification:
The lift station was rehabilitated in 2004 when PVIC was expanded and
remodeled. The wet well is aging and needs to have an epoxy coating
applied to extend its life. The pumps were replaced in 2013 and are
nearing the end of their useful life. The remaining mechanical
components need to be replaced and the electrical control system and
panel will need to be replaced due to age and exposure to the marine
environment. Installation of a SCADA system will provide additional
reliability to the system and allow for remote manipulation of pumps to
clear system jams. This capability will enhance maintenance operations if
problems arise during periods of heavy use such as occur when PVIC is
being used during a wedding.
C-41
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 SERIES PROJECTS – RIGHT-OF-WAY IMPROVEMENTS
Roadway infrastructure is one of the most widely used major capital investments of a municipality.
Without a well-maintained street system, the transportation needs of the public, business, industry,
and government cannot be met. Roads are also part of a critical public safety need, as they contribute
to the general health and welfare of the community. Maintaining quality roadway infrastructure is
also important for maintaining property values. Roadway infrastructure includes rehabilitation and
improvement of arterial and residential streets. In the City of Rancho Palos Verdes, there are 41.5
miles of arterial streets and 108.6 miles of residential streets. The total of all streets and alleys
mileage is 150.1 centerline miles.
The CIP includes the Pavement Management Program (PMP), which is an assessment of the
pavement condition of arterial and residential streets on a three-year cycle. The assessment
produces a pavement rating for each street, known as Pavement Condition Index (PCI). The City
prioritizes pavement rehabilitation based on the PCI. Since 1997, the City has maintained a
pavement rating between 80 and 90. For purposes of scheduling pavement rehabilitation, The City
has been divided into nine zones for residential streets. The upcoming PMP update will also include
a condition assessment of the City’s sidewalks.
C-42
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8000 Series Capital Improvement Program – Miscellaneous/Other Project Code: 8004 Traffic Signs Replacement Program
The Traffic Signs Replacement Program is intended to replace traffic signs
included in the Sign Inventory Report and consists of:
- Replacing existing traffic signs that have been determined to not meet
current, applicable standards
- Replacing associated posts, if the posts do not meet current, applicable
standards
A new assessment will be performed in FY2022-23 to determine future
program needs
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 TBD TBD TBD TBD
Engineering N/A – ongoing program $10,000 $10,000 $5,000 $5,000 $10,000 TBD
Environmental N/A – ongoing program $0 $0 $0 $0 $0 TBD
Management N/A – ongoing program $10,000 $10,000 $5,000 $5,000 $10,000 TBD
Construction N/A – ongoing program $155,000 $165,000 $80,000 $100,000 $105,000 TBD
Contingency N/A – ongoing program $20,000 $20,000 $10,000 $10,000 $15,000 TBD
Inspection N/A – ongoing program $20,000 $20,000 $10,000 $10,000 $15,000 TBD
N/A – ongoing program $215,000 $225,000 $110,000 $130,000 $155,000 TBD
Funding
330 (CIP) N/A – ongoing program $215,000 $225,000 $110,000 $130,000 $155,000 TBD
N/A – ongoing program $215,000 $225,000 $110,000 $130,000 $155,000 TBD
Estimated annual operating cost None Estimated Schedule:
Replacement is ongoing in Fiscal Years 2022-23 through 2026-27 and beyond
Project Location Map Background and Justification:
The signage replacement/update program was created based on an
assessment report on the City's sign inventory and is intended to replace
existing signs that do not meet current, applicable standards. Roadway
signs are required to comply with FHWA (Federal Highway Administration)
and California MUTCD (Manual on Uniform Traffic Control Devices)
standards, including retro-reflectivity standards. The signage
replacement/update program is necessary for the City’s roadway signs to
be in compliance with those applicable standards.
The budget was determined based on the number of signs that need to be
replaced per year, based on that report, and funding is included in FY2022-
23 for a future assessment to determine future needs.
C-43
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8801 Sidewalk Repair and Replacement Program
This program is citywide and consists of:
- Replacing damaged residential sidewalk
- Replacing damaged residential driveways
- Replacing damaged curb & gutter
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 $0 $0 $0 TBD
Engineering N/A – ongoing program $35,000 $0 $40,000 $0 $40,000 TBD
Environmental N/A – ongoing program $0 $0 $0 $0 $0 TBD
Management N/A – ongoing program $20,000 $0 $20,000 $0 $20,000 TBD
Construction N/A – ongoing program $335,000 $0 $360,000 $0 $380,000 TBD
Contingency N/A – ongoing program $35,000 $0 $40,000 $0 $40,000 TBD
Inspection N/A – ongoing program $35,000 $0 $40,000 $0 $40,000 TBD
N/A – ongoing program $460,000 $0 $500,000 $0 $520,000 TBD
Funding
330 (CIP) N/A – ongoing program $350,000 $0 $500,000 $0 $520,000 TBD
340 (Bike & Ped) N/A – ongoing program $110,000 $0 $0 $0 $0 TBD
N/A – ongoing program $460,000 $0 $500,000 $0 $520,000 TBD
Estimated annual operating cost None Estimated Schedule:
Construction in Fiscal Year 2022-23
Construction in Fiscal Year 2024-25
Construction in Fiscal Year 2026-27
Project Location Map Background and Justification:
Under this biennial program, the City removes and replaces identified
broken sections of sidewalk city-wide to mitigate potential tripping
hazards.
Needs will be assessed through the Triennial update to the Pavement
Management Program.
C-44
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8808 Pavement Management Program – Arterial Roadway Rehabilitation Crenshaw Boulevard
As part of the Arterial Roadways Rehabilitation Program, this project
consists of rehabilitating the section of Crenshaw Boulevard, from the city
limit to Seacrest Drive, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing pavement markings
- Improving drainage (if needed)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $170,000 $55,000 $0 $0 $0 $0 $225,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $55,000 $0 $0 $0 $0 $55,000
Construction $0 $1,080,000 $0 $0 $0 $0 $1,080,000
Contingency $0 $220,000 $0 $0 $0 $0 $220,000
Inspection $0 $110,000 $0 $0 $0 $0 $110,000
$170,000 $1,520,000 $0 $0 $0 $0 $1,690,00
Funding
202 (Gas Tax)
(SB1)
$170,000 $0 $0 $0 $0 $0 $170,000
330 (CIP) $0 $1,020,000 $0 $0 $0 $0 $1,020,000
333 (ARPA) $0 $500,000 $0 $0 $0 $0 $500,000
$170,000 $1,520,000 $0 $0 $0 $0 $1,690,000
Estimated annual operating cost None Estimated Schedule:
Construction in Fiscal Year 2022-23
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents and businesses.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
Road conditions are assessed through a triennial inspection and assigned
a calculated Pavement Condition Index (PCI) rating of Very Poor (0-40),
Poor (41-59), Fair (60-74), Good (75-85) or Very Good (86-100)
This section of road was inspected in 2019 and had segments with PCI
ratings from 72 to 85 (all within the “Good” classification).
C-45
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8809 Western Avenue Traffic Flow Improvements
This project is intended to improve traffic congestion on Western Avenue
from Palos Verdes Drive North to 25th Street and consists of:
- Traffic signal equipment updates and synchronizing the traffic signals
- Potential alterations to the existing intersection geometrics
- Access improvements and parking management
- Potential addition of right turn and left turn lanes
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $235,000 $0 $0 $0 $0 $235,000
Engineering $245,000 $0 $235,000 $60,000 $0 $0 $540,000
Environmental $0 $0 $120,000 $0 $0 $0 $120,000
Management $0 $150,000 $150,000 $235,000 $0 $0 $535,000
Construction $105,000 $0 $0 $2,345,000 $0 $0 $2,450,000
Contingency $0 $0 $0 $235,000 $0 $0 $235,000
Inspection $0 $0 $0 $235,000 $0 $0 $235,000
$350,000 $385,000 $505,000 $3,110,000 $0 $0 $4,350,000
Funding
215 (Prop. C) $200,000 $0 $0 $0 $0 $0 $200,000
220 (Meas. R) $150,000 $0 $0 $0 $0 $0 $150,000
221 (Meas. M Grant) $0 $385,000 $505,000 $3,110,000 $0 $0 $4,000,000
$350,000 $385,000 $505,000 $3,100,000 $0 $0 $4,350,000
Estimated annual operating cost None Estimated Schedule:
Planning in FY 2022-23.
Construction of a Right Turn Lane in FY2022-23.
Remaining scheduled is contingent on Caltrans approval
Project Location Map Background and Justification:
Traffic congestion and delays is an ongoing concern for area residents and
businesses, and has been for several years.
Although CalTrans owns this state highway and must approve any
improvements, the City is taking a lead role on this project.
Western Ave. traffic congestion improvements will work toward improving
traffic flow along Western Avenue.
C-46
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8810 Community Development Block Grant - Americans with Disabilities Act - Infrastructure Improvements
The City receives an annual Community Development Block Grant from the
United States Department of Housing and Urban Development (HUD), with
restricted uses. Accessibility improvements are an approved use and the
City has traditionally used these grants for install Americans with
Disabilities Act (ADA) compliant curb ramps, and associated
improvements, at existing sidewalk areas.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 $0 $0 $0 TBD
Engineering N/A – ongoing program $20,000 $20,000 $20,000 $20,000 $20,000 TBD
Environmental N/A – ongoing program $0 $0 $0 $0 $0 TBD
Management N/A – ongoing program $5,000 $5,000 $5,000 $5,000 $5,000 TBD
Construction N/A – ongoing program $100,000 $100,000 $100,000 $100,000 $100,000 TBD
Contingency N/A – ongoing program $15,000 $15,000 $15,000 $15,000 $15,000 TBD
Inspection N/A – ongoing program $10,000 $10,000 $10,000 $10,000 $10,000 TBD
N/A – ongoing program $150,000 $150,000 $150,000 $150,000 $150,000 TBD
Funding
310 (CDBG) N/A – ongoing program $150,000 $150,000 $150,000 $150,000 $150,000 TBD
330 (CIP) N/A – ongoing program $0 $0 $0 $0 $0 TBD
N/A – ongoing program $150,000 $150,000 $150,000 $150,000 $150,000 TBD
Estimated annual operating cost N/A – ongoing program Estimated Schedule:
This in an ongoing, annual program
Project Location Map Background and Justification:
Construction of the ADA improvements, such as curb ramps, removes a
barrier that would otherwise make it more difficult people using
wheelchairs, scooters, walkers or other mobility devices to cross a street.
C-47
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8815 Pavement Management Program – Residential Roadway Rehabilitation - Area 5
As part of the Residential Roadways Rehabilitation Program, this project
consists of rehabilitating the roadways in Area 5, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing deteriorated signs, pavement markings and curb address
numbers
- Improving drainage (if needed)
- Installing ADA compliant ramps (when necessary)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 $0 $0 $0 $0
Engineering N/A – ongoing program $0 $0 $0 $135,000 $100,000 $235,000
Environmental N/A – ongoing program $0 $0 $0 $0 $0 $0
Management N/A – ongoing program $0 $0 $0 $120,000 $0 $120,000
Construction N/A – ongoing program $0 $0 $0 $2,345,000 $0 $2,345,000
Contingency N/A – ongoing program $0 $0 $0 $235,000 $0 $235,000
Inspection N/A – ongoing program $0 $0 $0 $235,000 $0 $235,000
N/A – ongoing program $0 $0 $0 $3,070,000 $100,000 $3,170,000
Funding
202 (Gas Tax) N/A – ongoing program $0 $0 $0 $735,000 $0 $0
220 (Meas. R) N/A – ongoing program $0 $0 $0 $530,000 $0 $0
330 (CIP) N/A – ongoing program $0 $0 $0 $1,805,000 $100,000 $3,170,000
N/A – ongoing program $0 $0 $0 $3,070,000 $100,000 $3,170,000
Estimated annual operating cost None Estimated Schedule:
Engineering and Construction in Fiscal Year 2025-26
Engineering (Final Survey) in Fiscal Year 2026-27
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
The City has established a rehabilitation program to make repairs and
improvements to the residential streets on a recurring basis to maintain
them in good condition. The City is divided into nine areas for this
purpose, and the program is designed to rehabilitate each area every eight
years according to a rotating schedule.
1
2 3
4
5
6
7
8 9
C-48
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8816 Pavement Management Program – Residential Roadway Rehabilitation - Area 1
As part of the Residential Roadways Rehabilitation Program, this project
consists of rehabilitating the roadways in Area 1, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing deteriorated signs, pavement markings and curb address
numbers
- Improving drainage (if needed)
- Installing ADA compliant ramps (when necessary)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $38,500 $215,000 $100,000 $0 $0 $0 $353,500
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $160,000 $0 $0 $0 $0 $160,000
Construction $0 $3,140,000 $0 $0 $0 $0 $3,140,000
Contingency $0 $315,000 $0 $0 $0 $0 $315,000
Inspection $0 $315,000 $0 $0 $0 $0 $315,000
$38,500 $4,145,000 $100,000 $0 $0 $0 $4,283,500
Funding
202 (Gas Tax) $0 $500,000 $0 $0 $0 $0 $500,000
202 (Gas Tax –
SB1)
$0 $1,200,000 $0 $0 $0 $0 $1,200,000
220 (Meas. R) $38,500 $1,400,000 $0 $0 $0 $0 $1,438,500
330 (CIP) $0 $1,045,000 $100,000 $0 $0 $0 $1,145,000
$38,500 $4,145,000 $100,000 $0 $0 $0 $4,283,500
Estimated annual operating cost None Estimated Schedule:
Engineering and Construction in Fiscal Year 2022-23
Engineering (Final Survey) in Fiscal Year 2023-24
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
The City has established a rehabilitation program to make repairs and
improvements to the residential streets on a recurring basis to maintain
them in good condition. The City is divided into nine areas for this
purpose, and the program is designed to rehabilitate each area every eight
years according to a rotating schedule.
1
2 3
4
5
6
7
8 9
C-49
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8819 Pavement Management Program – Residential Roadway Rehabilitation - Area 9
As part of the Residential Roadways Rehabilitation Program, this project
consists of rehabilitating the roadways in Area 9, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing deteriorated signs, pavement markings and curb address
numbers
- Improving drainage (if needed)
- Installing ADA compliant ramps (when necessary)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 $0 $0 $0 TBD
Engineering N/A – ongoing program $0 $0 $110,000 $100,000 $0 TBD
Environmental N/A – ongoing program $0 $0 $0 $0 $0 TBD
Management N/A – ongoing program $0 $0 $105,000 $0 $0 TBD
Construction N/A – ongoing program $0 $0 $2,080,000 $0 $0 TBD
Contingency N/A – ongoing program $0 $0 $210,000 $0 $0 TBD
Inspection N/A – ongoing program $0 $0 $210,000 $0 $0 TBD
N/A – ongoing program $0 $0 $2,715,000 $100,000 $0 TBD
Funding
202 (Gas Tax) N/A – ongoing program $0 $0 $925,000 $0 $0 TBD
220 (Meas. R) N/A – ongoing program $0 $0 $520,000 $0 $0 TBD
330 (CIP) N/A – ongoing program $0 $0 $1,270,000 $100,000 $0 TBD
N/A – ongoing program $0 $0 $2,715,000 $100,000 $0 TBD
Estimated annual operating cost None Estimated Schedule:
Construction and Engineering in Fiscal Year 2024-25
Engineering (Final Survey) in Fiscal Year 2025-26
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
The City has established a rehabilitation program to make repairs and
improvements to the residential streets on a recurring basis to maintain
them in good condition. The City is divided into nine areas for this
purpose, and the program is designed to rehabilitate each area every eight
years according to a rotating schedule.
1
2 3
4
5
6
7
8 9
C-50
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8826 Pavement Management Program – Residential Roadway Rehabilitation - Area 2
As part of the Residential Roadways Rehabilitation Program, this project
consists of rehabilitating the roadways in Area 2, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing deteriorated signs, pavement markings and curb address
numbers
- Improving drainage (if needed)
- Installing ADA compliant ramps (when necessary)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 $0 $0 $0 TBD
Engineering N/A – ongoing program $0 $90,000 $100,000 $0 $0 TBD
Environmental N/A – ongoing program $0 $0 $0 $0 $0 TBD
Management N/A – ongoing program $0 $95,000 $0 $0 $0 TBD
Construction N/A – ongoing program $0 $1,895,000 $0 $0 $0 TBD
Contingency N/A – ongoing program $0 $190,000 $0 $0 $0 TBD
Inspection N/A – ongoing program $0 $190,000 $0 $0 $0 TBD
N/A – ongoing program $0 $2,460,000 $100,000 $0 $0 TBD
Funding
202 (Gas Tax) N/A – ongoing program $0 $530,000 $0 $0 $0 TBD
220 (Meas. R) N/A – ongoing program $0 $525,000 $0 $0 $0 TBD
330 (CIP) N/A – ongoing program $0 $1,405,000 $100,000 $0 $0 TBD
N/A – ongoing program $0 $2,460,000 $100,000 $0 $0 TBD
Estimated annual operating cost None Estimated Schedule:
Engineering and Construction in Fiscal Year 2023-23
Engineering (Final Survey) in Fiscal Year 2024-25
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
The City has established a rehabilitation program to make repairs and
improvements to the residential streets on a recurring basis to maintain
them in good condition. The City is divided into nine areas for this
purpose, and the program is designed to rehabilitate each area every eight
years according to a rotating schedule.
1
2 3
4
5
6
7
8 9
C-51
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8828 Palos Verdes Drive South Intersection Improvements
This project is intended to improve traffic operations and consists of a pilot
roundabout at Forrestal Drive and potentially other intersections followed
by a study of the efficacy of the roundabout(s).
Based on the outcome of the study, a permanent roundabout or other
improvements may be made at the following cross streets:
- Schooner Drive (across from Yacht Harbor Drive)
- Seahill Drive (across from Tramonto Drive)
- Conqueror Drive
- Forrestal Drive (across from Trump National Drive) Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $78,594 $0 $0 $50,000 $50,000 $0 $178,594
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $5,000 $45,000 $0 $50,000
Construction $0 $0 $0 $30,000 $810,000 $0 $840,000
Contingency $0 $0 $0 $10,000 $85,000 $0 $95,000
Inspection $0 $0 $0 $5,000 $85,000 $0 $90,000
$78,594 $0 $0 $100,000 $1,075,000 $0 $1,253,594
Funding
215 (Prop. C) $70,394 $0 $0 $0 $0 $0 $70,394
330 (CIP) $8,200 $0 $0 $100,000 $1,075,000 $0 $1,183,200
$78,594 $0 $0 $100,000 $1,075,000 $0 $1,253,594
Estimated annual operating cost None Estimated Schedule:
Engineering and construction for pilot roundabout(s) in Fiscal Year 2024-25
Engineering and construction for a permanent roundabout or other improvements in Fiscal Year 2025-26
Project Location Map Background and Justification:
Concerns regarding the geometrics of these intersections were reviewed
by the Traffic Safety Committee and recommendations forwarded to the
City Council in 2018. Engineering of the improvements were authorized
by the City Council in 2019.
During the CIP Workshop in 2022, the City Council directed staff to
postpone making the improvements to these intersections until after the
completion of the Ladera Linda Community Park project.
Furthermore, staff is recommending that the effects of the recently
installed traffic signal at Palos Verdes Drive South and Palos Verdes Drive
East be evaluated, and the Infrastructure Management Advisory
Committee is requesting that a pilot roundabout be installed and its
affects on traffic flow along Palos Verdes Drive South be studied before
the originally anticipated improvements be constructed.
C-52
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8836 Pavement Management Program – Residential Roadway Rehabilitation - Area 6
As part of the Residential Roadways Rehabilitation Program, this project
consists of rehabilitating the roadways in Area 6, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing deteriorated signs, pavement markings and curb address
numbers
- Improving drainage (if needed)
- Installing ADA compliant ramps (when necessary)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning N/A – ongoing program $0 $0 $0 $0 $0 TBD
Engineering N/A – ongoing program $0 $0 $0 $0 $105,000 TBD
Environmental N/A – ongoing program $0 $0 $0 $0 $0 TBD
Management N/A – ongoing program $0 $0 $0 $0 $105,000 TBD
Construction N/A – ongoing program $0 $0 $0 $0 $2,030,000 TBD
Contingency N/A – ongoing program $0 $0 $0 $0 $205,000 TBD
Inspection N/A – ongoing program $0 $0 $0 $0 $205,000 TBD
N/A – ongoing program $0 $0 $0 $0 $2,650,000 TBD
Funding
202 (Gas Tax) N/A – ongoing program $0 $0 $0 $0 $700,000 TBD
220 (Meas. R) N/A – ongoing program $0 $0 $0 $0 $530,000 TBD
330 (CIP) N/A – ongoing program $0 $0 $0 $0 $1,420,000 TBD
N/A – ongoing program $0 $0 $0 $0 $2,650,000 TBD
Estimated annual operating cost None Estimated Schedule:
To be determined
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
The City has established a rehabilitation program to make repairs and
improvements to the residential streets on a recurring basis to maintain
them in good condition. The City is divided into nine areas for this
purpose, and the program is designed to rehabilitate each area every eight
years according to a rotating schedule.
1
2 3
4
5
6
7
8 9
C-53
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8837 New Traffic Signal at intersection of Palos Verdes Drive South and Palos Verdes Drive East
This project consists of engineering and installing a new traffic signal at the
intersection of Palos Verdes Drive South and Palos Verdes Drive East.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning - $0 $0 $0 $0 $0 TBD
Engineering - $0 $0 $0 $0 $0 TBD
Environmental - $0 $0 $0 $0 $0 TBD
Management - $0 $0 $0 $0 $0 TBD
Construction - $0 $0 $0 $0 $0 TBD
Contingency - $0 $0 $0 $0 $0 TBD
Inspection - $0 $0 $0 $0 $0 TBD
- $0 $0 $0 $0 $0 TBD
Funding
330 (CIP) $361,618 $0 $0 $0 $0 $0 TBD
$361,618 $0 $0 $0 $0 $0 TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Re-design and revise installation, per City Council direction on March 1, 2022
Project Location Map Background and Justification:
The design and construction of this project was initiated by the Traffic
Safety Committee and was approved subsequently by the City Council.
The installation of a new traffic signal will improve traffic operations at
this intersection.
The traffic signal has been installed, and based on direction from City
Council on March 1, 2022 will be redesigned to reduce the aesthetic
impacts to the surrounding area.
C-54
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8840 Western Avenue Beautification (long term)
This project is intended to enhance the aesthetics of the public right-of
way along Western Avenue corridor (from Peninsula Verde Drive to
Summerland Avenue), and consists of:
- New entrance features
- Lighting improvements (including up-lighting of landscaping)
- Hardscape improvements
- New Street furniture and trash receptacles
- Crosswalk improvements
- Landscape improvements Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 TBD TBD TBD TBD
Engineering $0 $120,000 $60,000 TBD TBD TBD TBD
Environmental $0 $20,000 $0 TBD TBD TBD TBD
Management $0 $0 $100,000 TBD TBD TBD TBD
Construction $0 $0 $2,000,000 TBD TBD TBD TBD
Contingency $0 $0 $200,000 TBD TBD TBD TBD
Inspection $0 $0 $200,000 TBD TBD TBD TBD
$0 $140,000 $2,560,000 TBD TBD TBD TBD
Funding
330 (CIP) $0 $0 $2,100,000 TBD TBD TBD TBD
333 (ARPA) $0 $140,000 $460,000 $0 $0 $0 $600,000
$0 $140,000 $2,560,000 TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Developing a Plan for Improvements in a Fiscal Year to be determined
Project Location Map Background and Justification:
For many years, there has been a general desire by the City to enhance
the aesthetics along the Western Avenue corridor.
Aesthetic improvements to the public right-of-way and adjacent areas
would enhance the appeal of the surrounding area, bolster commerce
with local businesses, and reflect positively on the entire City.
Existing commercial and residential developments along Western Ave.
would not be considered desirable or acceptable in today's built
environment. The vision for the Western Avenue corridor is to create a
safe and attractive street environment.
C-55
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8843 Pavement Management Program – Arterial Roadway Rehabilitation Silver Spur Road (North of Hawthorne Boulevard)
As part of the Arterial Roadways Rehabilitation Program, this project
consists of rehabilitating the section of Silver Spur Road, from Elkmont
Drive to the driveway entrance of Peninsula High School (as shown in the
picture to the left), and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing pavement markings
- Improving drainage (if needed)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $99,749 $120,000 $0 $0 $0 $0 $219,749
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $60,000 $0 $0 $0 $0 $60,000
Construction $0 $1,165,000 $0 $0 $0 $0 $1,165,000
Contingency $0 $350,000 $0 $0 $0 $0 $350,000
Inspection $0 $120,000 $0 $0 $0 $0 $120,000
$99,749 $1,815,000 $0 $0 $0 $0 $1,914,749
Funding
220 (Meas. R) $54,749 $0 $0 $0 $0 $0 $54,749
330 (CIP) $0 $143,000 $0 $0 $0 $0 $143,000
333 (ARPA) $45,000 $1,672,000 $0 $0 $0 $0 $1,717,000
$99,749 $1,815,000 $0 $0 $0 $0 $1,914,749
Estimated annual operating cost None Estimated Schedule:
Construction in Fiscal Year 2022-23.
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents and businesses.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
Road conditions are assessed through a triennial inspection and assigned
a calculated Pavement Condition Index (PCI) rating of Very Poor (0-40),
Poor (41-59), Fair (60-74), Good (75-85) or Very Good (86-100)
This section of road was inspected in 2019 and had segments with PCI
ratings from 49 (Poor) to 78 (Good).
C-56
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8844 Pavement Management Program - Triennial Update
The Pavement Management Plan (PMP) is updated every three years to
evaluate the condition of the City’s roadway system and to identify
Citywide Arterial and Residential Street Rehabilitation projects.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $198,718 $0 $0 $0 $0 $0 TBD
Engineering $0 $0 $0 $160,000 $0 $0 TBD
Environmental $0 $0 $0 $0 $0 $0 TBD
Management $0 $0 $0 $0 $0 $0 TBD
Construction $0 $0 $0 $0 $0 $0 TBD
Contingency $0 $0 $0 $0 $0 $0 TBD
Inspection $0 $0 $0 $0 $0 $0 TBD
$198,718 $0 $0 $160,000 $0 $0 TBD
Funding
202 (Gas Tax) $198,718 $0 $0 $160,000 $0 $0 TBD
330 (CIP) $0 $0 $0 $0 $0 $0 TBD
$198,718 $0 $0 $160,000 $0 $0 TBD
Estimated annual operating cost None Estimated Schedule:
The next update is scheduled for Fiscal Year 2024-25
Project Location Map Background and Justification:
The City uses the Pavement Management Program to determine the
condition of existing pavement and accordingly schedule the rehabilitation
of specific areas and roadways throughout the city.
The Metropolitan Transit Authority (Metro) requires the PMP update in
order for the City to continue receiving Proposition C funds. It must be
conducted every three years. Failure to complete will result in lost
funding.
C-57
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8845 Traffic Calming – PV Nature Preserve Parking Solutions
This project is located throughout the Preserve parking areas, and consists
of:
- Implementing traffic calming solutions to address Preserve parking area
concerns such as problematic driving behavior, increased traffic volumes
and speeding
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 TBD TBD TBD TBD TBD TBD
Engineering $75,000 TBD TBD TBD TBD TBD TBD
Environmental $0 TBD TBD TBD TBD TBD TBD
Management $0 TBD TBD TBD TBD TBD TBD
Construction $0 TBD TBD TBD TBD TBD TBD
Contingency $0 TBD TBD TBD TBD TBD TBD
Inspection $0 TBD TBD TBD TBD TBD TBD
$75,000 TBD TBD TBD TBD TBD TBD
Funding
330 (CIP) $75,000 TBD TBD TBD TBD TBD TBD
$75,000 TBD TBD TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Engineering in Fiscal Year 2023-24
Project Location Map Background and Justification:
Due to the Nature Preserve’s recent surge in popularity, demand for
parking has increased dramatically. As a result, problematic driving
behavior has been reported by area residents.
This project will provide solutions through traffic mitigation and parking
circulation measures.
C-58
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8846 Traffic Calming Program - Citywide
This program is is citywide, and consists of:
- Implementing traffic calming measures for city arterial and residential
roadways
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 TBD
Engineering $0 $200,000 $80,000 $85,000 $85,000 $85,000 TBD
Environmental $0 $0 $0 $0 $0 $0 TBD
Management $0 $10,000 $15,000 $15,000 $15,000 $15,000 TBD
Construction $0 $260,000 $270,000 $275,000 $285,000 $290,000 TBD
Contingency $0 $40,000 $40,000 $45,000 $45,000 $45,000 TBD
Inspection $0 $25,000 $25,000 $30,000 $30,000 $30,000 TBD
$0 $535,000 $430,000 $450,000 $460,000 $465,000 TBD
Funding
220 (Meas. R) $0 $0 $0 $0 $0 $0 TBD
330 (CIP) $0 $535,000 $430,000 $450,000 $460,000 $465,000 TBD
$0 $535,000 $430,000 $450,000 $460,000 $465,000 TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
This is an ongoing annual program
Project Location Map Background and Justification:
Traffic Calming is the management of traffic so that its negative impacts on
residents, pedestrians and schools are minimized.
One of the most persistent and emotional complaints that the City
receives is speeding on public streets.
This program will mitigate traffic and speed-related concerns.
C-59
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8847 Guardrail Improvements along Palos Verdes Drive East
This project consists of guardrail improvements along Palos Verdes Drive
East, within the City limits
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $105,000 $0 $0 $0 $0 $105,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $70,000 $0 $0 $0 $70,000
Construction $0 $0 $684,900 $0 $0 $0 $684,900
Contingency $0 $0 $70,000 $0 $0 $0 $70,000
Inspection $0 $0 $70,000 $0 $0 $0 $70,000
$0 $105,000 $894,900 $0 $0 $0 $999,900
Funding
331 (Fed. Grant) $0 $105,000 $894,900 $0 $0 $0 $999,900
$0 $105,000 $894,900 $0 $0 $0 $999,900
Estimated annual operating cost To Be Determined Estimated Schedule:
Engineering in Fiscal Year 2022-23
Construction in Fiscal Year 2023-24
Project Location Map Background and Justification:
On July 21, 2020, City Council authorized staff to apply for a federal
Highway Safety Improvement Program (HSIP) grant to fund guard rail
improvements along Palos Verdes Drive East.
In April 2021, staff was notified that the project was approved for HSIP
funding in the amount of $999,900 (with no requirement for City matching
funds)
C-60
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8848 Pavement Management Program – Arterial Roadway Rehabilitation Silver Spur Road (South of Hawthorne Boulevard)
As part of the Arterial Roadways Rehabilitation Program, this project
consists of rehabilitating the section of Silver Spur Road, from Hawthorne
Boulevard to the city limit, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing pavement markings
- Improving drainage (if needed)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $45,000 $0 $0 $0 $0 $0 $45,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $20,000 $0 $0 $0 $0 $0 $20,000
Construction $355,000 $0 $0 $0 $0 $0 $355,000
Contingency $0 $0 $0 $0 $0 $0 $0
Inspection $35,000 $0 $0 $0 $0 $0 $35,000
$455,000 $0 $0 $0 $0 $0 $455,000
Funding
202 (Gas Tax) $315,000 $0 $0 $0 $0 $0 $315,000
220 (Meas. R) $140,000 $0 $0 $0 $0 $0 $140,000
330 (CIP) $0 $0 $0 $0 $0 $0 $0
$455,000 $0 $0 $0 $0 $0 $455,000
Estimated annual operating cost None Estimated Schedule:
Construction in Fiscal Year 2022-23
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents and businesses.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
Road conditions are assessed through a triennial inspection and assigned
a calculated Pavement Condition Index (PCI) rating of Very Poor (0-40),
Poor (41-59), Fair (60-74), Good (75-85) or Very Good (86-100)
This section of road was inspected in 2019 and had segments with PCI
ratings ranging from 66 to 70 (all within the “Fair” category).
This project will be included in a larger project, in which the City will partner with Rolling Hills Estates and a segment in their city, to realize cost savings through economies of scale.
C-61
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88LY1 Pavement Management Program – Arterial Roadway Rehabilitation Palos Verdes Drive South
As part of the Arterial Roadways Rehabilitation Program, this project
consists of rehabilitating the section of Palos Verdes Drive South, from
Crestmont Lane to Seahill Drive, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing pavement markings
- Improving drainage (if needed)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $35,000 $0 $0 $0 $35,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $40,000 $0 $0 $40,000
Construction $0 $0 $0 $385,000 $0 $0 $385,000
Contingency $0 $0 $0 $120,000 $0 $0 $120,000
Inspection $0 $0 $0 $40,000 $0 $0 $40,000
$0 $0 $35,000 $585,000 $0 $0 $620,000
Funding
202 (Gas Tax) $0 $0 $0 $0 $0 $0 $0
330 (CIP) $0 $0 $35,000 $585,000 $0 $0 $620,000
$0 $0 $35,000 $585,000 $0 $0 $620,000
Estimated annual operating cost None Estimated Schedule:
Engineering in Fiscal Year 2023-24
Construction in Fiscal Year 2024-25
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents and businesses.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
Road conditions are assessed through a triennial inspection and assigned
a calculated Pavement Condition Index (PCI) rating of Very Poor (0-40),
Poor (41-59), Fair (60-74), Good (75-85) or Very Good (86-100)
This section of road was inspected in 2019 and had segments with PCI
ratings from 73 to 79 (all within the “Good” classification).
C-62
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88LY2 Pavement Management Program – Arterial Roadway Rehabilitation Indian Peak Road
As part of the Arterial Roadways Rehabilitation Program, this project
consists of rehabilitating the section of Indian Peak Road, from Crenshaw
Boulevard to the city limit, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing pavement markings
- Improving drainage (if needed)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $0 $70,000 $0 $0 $70,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $20,000 $0 $20,000
Construction $0 $0 $0 $0 $420,000 $0 $420,000
Contingency $0 $0 $0 $0 $65,000 $0 $65,000
Inspection $0 $0 $0 $0 $40,000 $0 $40,000
$0 $0 $0 $70,000 $545,000 $0 $615,000
Funding
220 (Meas. R) $0 $0 $0 $0 $0 $0 $0
330 (CIP) $0 $0 $0 $70,000 $545,000 $0 $615,000
$0 $0 $0 $70,000 $545,000 $0 $615,000
Estimated annual operating cost None Estimated Schedule:
Engineering in Fiscal Year 2024-25
Construction in Fiscal Year 2025-26
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents and businesses.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
Road conditions are assessed through a triennial inspection and assigned
a calculated Pavement Condition Index (PCI) rating of Very Poor (0-40),
Poor (41-59), Fair (60-74), Good (75-85) or Very Good (86-100)
This section of road was inspected in 2019 and had a PCI rating of 71
(Fair).
C-63
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88LY4 Pavement Management Program – Arterial Roadway Rehabilitation Palos Verdes Drive East
As part of the Arterial Roadways Rehabilitation Program, this project
consists of rehabilitating the section of Palos Verdes Drive East, from
approximately 1000’ south of Sunnyside Ridge Road to the city limit, and
consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing pavement markings
- Improving drainage (if needed)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $0 $0 $210,000 $0 $210,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $170,000 $170,000
Construction $0 $0 $0 $0 $0 $3,320,000 $3,320,000
Contingency $0 $0 $0 $0 $0 $1,000,000 $1,000,000
Inspection $0 $0 $0 $0 $0 $335,000 $335,000
$0 $0 $0 $0 $210,000 $4,825,000 $5,035,000
Funding
330 (CIP) $0 $0 $0 $0 $210,000 $4,825,000 $5,035,000
$0
$0 $0 $0 $0 $210,000 $4,825,000 $5,035,000
Estimated annual operating cost None Estimated Schedule:
Engineering in Fiscal Year 2025-26
Construction in Fiscal Year 2026-27
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents and businesses.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
Road conditions are assessed through a triennial inspection and assigned
a calculated Pavement Condition Index (PCI) rating of Very Poor (0-40),
Poor (41-59), Fair (60-74), Good (75-85) or Very Good (86-100)
This section of road was inspected in 2019 and had segments with PCI
ratings from 71 (Fair) to 84 (Good).
C-64
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88New4 Arterial Roadway Beautification Program
This project is intended to address sections of medians and parkway strips
along arterial roadways and consists of:
- Installing drought tolerant trees and shrubs
- Installing bio swale runoff treatment facilities
- Enhancing median appearances throughout the City
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $100,000 TBD TBD TBD TBD TBD
Engineering $0 $0 TBD TBD TBD TBD TBD
Environmental $0 $0 TBD TBD TBD TBD TBD
Management $0 $0 TBD TBD TBD TBD TBD
Construction $0 $0 TBD TBD TBD TBD TBD
Contingency $0 $0 TBD TBD TBD TBD TBD
Inspection $0 $0 TBD TBD TBD TBD TBD
$0 $100,000 TBD TBD TBD TBD TBD
Funding
330 (CIP) $0 $100,000 TBD TBD TBD TBD TBD
$0 $100,000 TBD TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Planning in Fiscal Year 2022-23
Project Location Map Background and Justification:
Most of the medians and parkway strips along arterial roadways in RPV are
in need of attention.
Beautifying arterials is appreciated by all who use our roadways; and tends
to enhance the overall experience of motorists and pedestrians. Aesthetic
improvements to medians and parkway strips enhances the appeal of the
surrounding area and reflect positively on the entire City.
C-65
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88New5 City Entrance Roadway Monument Signs
This project consists of installing new City entrance monument signs for
the arterial roadway entrances to the City, including the following
locations:
Hawthorne Blvd (near City limit with RHE)
Palos Verdes Drive West (at City limit with PVE)
Palos Verdes Drive South (at City limit with San Pedro)
Western Avenue (at City limit by Green Hills cemetery)
Palos Verdes Drive East (by Palos Verdes Drive North)
Miraleste Drive (by First Street)
Monero (by Granvia Altamira)
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $25,000 $0 $0 $0 $0 $25,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $10,000 $0 $0 $0 $0 $10,000
Construction $0 $115,000 $0 $0 $0 $0 $115,000
Contingency $0 $35,000 $0 $0 $0 $0 $35,000
Inspection $0 $15,000 $0 $0 $0 $0 $15,000
$0 $200,000 $0 $0 $0 $0 $200,000
Funding
330 (CIP) $0 $0 $0 $0 $0 $0 $0
333 (ARPA) $0 $200,000 $0 $0 $0 $0 $200,000
$0 $200,000 $0 $0 $0 $0 $200,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction in a Fiscal Year 2022-23
Project Location Map Background and Justification:
The City Council has expressed an interest in replacing existing “Welcome
to Rancho Palos Verdes” signs with new monument signs.
Such new signs might include stonework, landscape lighting and a flagpole
(with appropriate lighting per the U.S. Flag code) to accommodate a
continuation of patriotic displays of the American flag on holidays such as
Independence Day weekend.
New monument signs would reflect positively on the entire City and
enhance the surrounding areas.
C-66
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88New6 Retaining Wall at 3001 Crest Road
This project consists of repairing/rehabilitating/replacing the deteriorated
retaining wall which supports the driveway to the property at 3001 Crest
Road.
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 TBD TBD TBD TBD TBD
Engineering $0 $100,000 TBD TBD TBD TBD TBD
Environmental $0 $0 TBD TBD TBD TBD TBD
Management $0 $0 TBD TBD TBD TBD TBD
Construction $0 $0 TBD TBD TBD TBD TBD
Contingency $0 $0 TBD TBD TBD TBD TBD
Inspection $0 $0 TBD TBD TBD TBD TBD
$0 $100,000 TBD TBD TBD TBD TBD
Funding
330 (CIP) $0 $100,000 TBD TBD TBD TBD TBD
$0 $100,000 TBD TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Engineering in Fiscal Year 2022-23
Project Location Map Background and Justification:
As part of a project by Los Angeles County to widen Crest Road in the
1960s, a retaining wall was built to support the driveway leading to 3001
Crest Road. A portion of the retaining wall was within the public right-of-
way, and an easement was created for the remaining portion.
Maintenance of the retaining was wall subsequently transferred from the
County to the City upon its incorporation.
An inspection of the retaining wall in 2021 concluded that it was
deteriorating and needed to be repaired/rehabilitated/replaced.
C-67
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88New7 Palos Verdes Drive East Traffic Improvements (from Bronco Drive to Headland Drive)
This project is intended to implement traffic improvements on Palos
Verdes Drive East from approximately Bronco Drive to Headland Drive and
consists of:
- Installing a center turn lane
- Installing pavement markings and traffic control devices
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 TBD TBD TBD TBD TBD
Engineering $0 $50,000 TBD TBD TBD TBD TBD
Environmental $0 $0 TBD TBD TBD TBD TBD
Management $0 $0 TBD TBD TBD TBD TBD
Construction $0 $0 TBD TBD TBD TBD TBD
Contingency $0 $0 TBD TBD TBD TBD TBD
Inspection $0 $0 TBD TBD TBD TBD TBD
$0 $50,000 TBD TBD TBD TBD TBD
Funding
220 (Meas. R) $0 $0 TBD TBD TBD TBD TBD
330 (CIP) $0 $50,000 TBD TBD TBD TBD TBD
$0 $50,000 TBD TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Engineering in Fiscal Year 2022/23
Construction in Fiscal Year 2023/24
Project Location Map Background and Justification:
This project is derived from a broader project that was originally scoped to
provide a path in the public right-of-way and implement traffic
improvements recommended by the Traffic Safety Committee. The scope
was revised as part of the Fiscal Year 2022-23 CIP process to separate the
path improvements and the traffic improvements into two projects. This
project is the traffic improvements project.
C-68
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
C-69
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
PROJECTS NOT RECOMMENDED FOR FUNDING AT THIS TIME
The following projects were not recommended for funding at this time, but will remain in the CIP for
future consideration.
C-70
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Project Code: 8411 Lower Point Vicente Park Parking Lot Lighting Improvements
This project is intended to add new solar parking lights for the Point
Vicente Park parking lot, and consists of:
- Installing new parking lot lights
- Replacing the light by the main entrance gate with a new solar-powered
light
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $0
Engineering $0 TBD TBD TBD TBD TBD $5,000
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $5,000
Construction $0 TBD TBD TBD TBD TBD $50,000
Contingency $0 TBD TBD TBD TBD TBD $15,000
Inspection $0 TBD TBD TBD TBD TBD $5,000
$0 TBD TBD TBD TBD TBD $80,000
Funding
211 (1911 Act) $0 TBD TBD TBD TBD TBD $80,000
TBD TBD TBD TBD TBD $80,000
Estimated annual operating cost None Estimated Schedule:
Construction in Fiscal Year 2021-22.
Project Location Map Background and Justification:
New solar lighting was installed at the PVIC parking lot in 2018, but not at
the parking lot for the park.
The park parking lot is used at night for approximately 60 events (mostly
weddings) per year, as the PVIC parking lot does not have sufficient space
for those events.
New lighting, similar to that installed at the PVIC parking lot, will improve
visibility for guests to the facility after dusk.
C-71
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Project Code: 8418 Hesse Park Parking Lot and Lighting Improvements
This project is intended to replace the parking lot surface and improve
lighting at the Hesse Park parking lot and consists of:
- Removing existing tree wells in the parking area
- Replacing deteriorated asphalt
- Constructing a retaining wall to accommodate additional parking
- Replacing existing lighting with solar powered LED (Light Emitting Diode)
fixtures
- Replacing existing, deteriorating storage containers
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $23,869 TBD TBD TBD TBD TBD $0
Engineering $50,000 TBD TBD TBD TBD TBD $0
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $50,000
Construction $0 TBD TBD TBD TBD TBD $1,000,000
Contingency $0 TBD TBD TBD TBD TBD $300,000
Inspection $0 TBD TBD TBD TBD TBD $100,000
$73,869 TBD TBD TBD TBD TBD $1,450,000
Funding
330 (CIP) $73,869 TBD TBD TBD TBD TBD $1,450,000
TBD TBD TBD TBD TBD
$73,869 TBD TBD TBD TBD TBD $1,450,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction in a Fiscal Year to be determined.
Project Location Map Background and Justification:
Adopted as a CIP project for the 2018/19 Fiscal Year, the City Council
awarded a contract for developing design options for consideration on
October 16, 2018. A design option was selected by City Council on April 16,
2019 and a design contract was awarded August 6, 2019. Engineering was
completed in December 2020.
Existing pavement and concrete is failing and requires replacement.
Additionally, trees are outgrowing the existing wells at entrances to
parking stalls and present an obstacle to vehicles – which often hit the
trees.
C-72
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Project Code: 8419 Hesse Park Athletic Field Improvements
The goal of this project is to restore the existing field to a condition that is
suitable for recreational use and to establish a proper maintenance
program.
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD TBD
Engineering $21,239 TBD TBD TBD TBD TBD TBD
Environmental $0 TBD TBD TBD TBD TBD TBD
Management $0 TBD TBD TBD TBD TBD TBD
Construction $0 TBD TBD TBD TBD TBD TBD
Contingency $0 TBD TBD TBD TBD TBD TBD
Inspection $0 TBD TBD TBD TBD TBD TBD
$21,239 TBD TBD TBD TBD TBD TBD
Funding
330 (CIP) $21,239 TBD TBD TBD TBD TBD TBD
TBD TBD TBD TBD TBD
$21,239 TBD TBD TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Design in Fiscal Year 2018-19. Construction in a Fiscal Year to be determined.
Project Location Map Background and Justification:
An existing gopher population creates numerous holes in the field, and
often bring large quantities of large and small rocks to the surface. The
existing irrigation system does not appear to provide adequate coverage
for proper irrigation of the field, and there are signs of improper drainage
in parts of the field.
As such, the field is not suitable for use in its current condition. AYSO
(American Youth Soccer Organization) stopped using the field a few years
ago due to the condition of the field.
Engineering was completed on a limited version of this project; however,
the project needs to be re-scoped to better meet the needs of the
community. Cost information will added as the scope is further
developed.
C-73
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Project Code: 8421 Lower Point Vicente Park Improvements
This project consists of:
Creating a Master Plan for the upper section of the PVIC lot
Installing a new, paved parking lot (in the general area where the
“overflow” parking lot exists)
Constructing new outdoor restrooms
Creating new trails, picnic areas and outlooks
Planting grassland areas and additional landscaping
Establishing locations for an Interactive Exhibit Program (IEP) that
will include four exhibits and to be designed, constructed and paid
for by Los Serenos de Point Vicente
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $49,989 TBD TBD TBD TBD TBD $0
Engineering $0 TBD TBD TBD TBD TBD $130,000
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $65,000
Construction $0 TBD TBD TBD TBD TBD $1,275,000
Contingency $0 TBD TBD TBD TBD TBD $385,000
Inspection $0 TBD TBD TBD TBD TBD $130,000
$49,989 TBD TBD TBD TBD TBD $1,985,000
Funding
330 (CIP) $49,989 TBD TBD TBD TBD TBD $1,985,000
TBD TBD TBD TBD TBD
$49,989 TBD TBD TBD TBD TBD $1,985,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Engineering and Construction is deferred to a Fiscal Year to be determined.
Project Location Map Background and Justification:
On November 20, 2012, the City Council adopted amendments to the
RPV Coast Vision Plan (adopted 9/2/2008) which replaced the Annenberg
Foundation Project. An update to the Parks Master Plan was adopted in
October 2015, and the Los Serenos de Point Vicente Docents presented
a proposal for a Lower Point Vicente Concept Site Plan in 2016. On
August 2, 2016, the City Council directed staff to work with the Los
Serenos de Point Vicente Docents to seek public input. In April 2017, the
City Council modified the Parks and Recreation Vision Plan for Lower
Point Vicente and added the Interactive Outdoor Educational Exhibits
Concept Plan.
C-74
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Project Code: 84LY1 Lower Hesse Park Improvements
This project is intended to make aesthetic improvements to the lower
portion of Hesse Park, and includes:
- Paving the existing parking lot
- Installing new erosion control features
- Installing new park benches
- Installing new landscaping
- Installing a new irrigation system
- (potentially) improving existing trails or installing new trails
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $50,000
Engineering $0 TBD TBD TBD TBD TBD $95,000
Environmental $0 TBD TBD TBD TBD TBD $5,000
Management $0 TBD TBD TBD TBD TBD $50,000
Construction $0 TBD TBD TBD TBD TBD $1,000,000
Contingency $0 TBD TBD TBD TBD TBD $300,000
Inspection $0 TBD TBD TBD TBD TBD $100,000
$0 TBD TBD TBD TBD TBD $1,600,000
Funding
TBD $0 TBD TBD TBD TBD TBD TBD
TBD $0 TBD TBD TBD TBD TBD TBD
$0 TBD TBD TBD TBD TBD $1,600,000
Estimated annual operating cost To Be Determined Estimated Schedule:
To be determined.
Project Location Map Background and Justification:
The upper portion of Hesse Park has been improved, and some
improvements were made to a section of the lower portion of Hesse Park
in 2017.
Additional improvements will enhance the overall aesthetics and create a
more cohesive park.
C-75
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8400 Series Parks, Open Space and Recreational Facilities Projects Project Code: 84LY2 Point Vicente Interpretive Center “Bubbles” Statue Marquee Sign
This project is intended to restore the "Bubbles" statue and consists of:
- Restoring the "Bubbles" statue
- Installing the restored statue at a location to be determined in Lower
Point Vicente Park
Project Cost Estimates
Expenses/Commitments to date FY22/23 FY23/24 FY24/25 FY25/26 FY26/27 Totals
Planning $0 $0 $0 $0 $0 $0 $0
Engineering $0 $40,000 $0 $0 $0 $0 $40,000
Environmental $0 $0 $0 $0 $0 $0 $0
Management $0 $20,000 $0 $0 $0 $0 $20,000
Construction $0 $355,000 $0 $0 $0 $0 $355,000
Contingency $0 $110,000 $0 $0 $0 $0 $110,000
Inspection $0 $40,000 $0 $0 $0 $0 $40,000
$0 $565,000 $0 $0 $0 $0 $565,000
Funding
330 (CIP) $0 $565,000 $0 $0 $0 $0 $565,000
$0 $565,000 $0 $0 $0 $0 $565,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Engineering and Construction in Fiscal Year 2022-23
Project Location Map Background and Justification:
In 2014, the public requested that the statue be incorporated into a park
plan for Lower Point Vicente. Although not included at that time, in
November 2016, City Council directed staff to find an appropriate location
at PVIC and in March 2017 staff presented information on the location to
City Council.
There is significant affection and nostalgia for Marineland and its pioneering
work with marine mammals, including Bubbles. Bubbles was a performing
pilot whale at Marineland for 20 years, until it closed in 1987, and then at
SeaWorld until her death in June 2016. Restoration of this statue and
placement at a public park could bring visitors to the City and an increase in
commerce.
C-76
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8500 Series Public Buildings Projects Project Code: 85LY2 Replacement of the Civic Center Storm Room
This project is intended to replace the prefabricated trailer building
located at the Civic Center with a new, appropriately sized construction
trailer to meet the needs of city departments.
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $0
Engineering $0 TBD TBD TBD TBD TBD $0
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $0
Construction $0 TBD TBD TBD TBD TBD $100,000
Contingency $0 TBD TBD TBD TBD TBD $0
Inspection $0 TBD TBD TBD TBD TBD $0
$0 TBD TBD TBD TBD TBD $100,000
Funding
330 (CIP) $0 TBD TBD TBD TBD TBD $100,000
$0 TBD TBD TBD TBD TBD
$0 TBD TBD TBD TBD TBD $100,000
Estimated annual operating cost To Be Determined Estimated Schedule:
To be determined.
Project Location Map Background and Justification:
The “Storm Room” is in very poor condition is inadequate for use by staff.
The existing trailing building is in such poor condition that the cost of
repairs would far exceed the costs of obtaining a right-sized replacement.
C-77
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 8711 Bayend Drive Catch Basin Inlets and Storm Sewer Lateral
This project is intended to efficiently convey runoff from Bayend Drive and
consists of:
- Replacing the catch basin and pipes
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $0
Engineering $14,992 TBD TBD TBD TBD TBD $52,000
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $5,000
Construction $0 TBD TBD TBD TBD TBD $105,000
Contingency $0 TBD TBD TBD TBD TBD $30,000
Inspection $0 TBD TBD TBD TBD TBD $10,000
$14,992 TBD TBD TBD TBD TBD $202,000
Funding
330 (CIP) $14,992 TBD TBD TBD TBD TBD $202,000
TBD TBD TBD TBD TBD
$14,992 TBD TBD TBD TBD TBD $202,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction is deferred to a Fiscal Year to be determined.
Project Location Map Background and Justification:
The existing catch basin at this location is not properly conveying the
storm water runoff that is collected by the catch basin.
This project will properly collect the storm water runoff that is gathered by
the catch basin at this location.
C-78
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 8713 Upper Point Vicente Stormwater Runoff Control Project (Helipad)
This project is intended to improve the underground drainage system
around the Helipad at Upper Point Vicente, near the Civic Center and
consists of:
- Grading for new drainage swales
- Installing a new drainage pipe
- Installing a new driveway connecting the access path to the Helipad
- Relocating the fire hydrant located along the Civic Center entrance road
to the new driveway
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $0
Engineering $0 TBD TBD TBD TBD TBD $10,000
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $5,000
Construction $0 TBD TBD TBD TBD TBD $120,000
Contingency $0 TBD TBD TBD TBD TBD $35,000
Inspection $0 TBD TBD TBD TBD TBD $10,000
$0 TBD TBD TBD TBD TBD $180,000
Funding
330 (CIP) $0 TBD TBD TBD TBD TBD $180,000
$0 TBD TBD TBD TBD TBD
$0 TBD TBD TBD TBD TBD $180,000
Estimated annual operating cost To Be Determined Estimated Schedule:
To be determined.
Project Location Map Background and Justification:
During fire events, Los Angeles County Fire Department helicopters load
water from the fire hydrant at the Civic Center entrance, using a canvas
fire hose that runs across the entrance road to the Helipad.
Vehicles run over this fire hose while accessing the Civic Center. Relocating
the fire hydrant next to the new driveway will eliminate the need to run
the hose across the access drive to the Civic Center.
There is also an existing open ditch adjacent to the Helipad which often
floods during heavy rainfall and is boggy during most of the winter
months. Regarding the drainage ditch, installing a new driveway from the
access path to the helipad and a pipe under the driveway will correct the
access issue.
C-79
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 8714 Crest Road to Crestridge Canyon Stormwater Drainage Improvements
This project is intended to convey storm water runoff from Crest Road,
along Crestridge Road, to a natural Canyon and consists of:
- Constructing a new storm water detention chamber
- Replacing and upgrading the existing pipe
- Installing a new curb opening for the existing catch basin
- Restoring concrete curb, gutter and sidewalk
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $0
Engineering $129,941 TBD TBD TBD TBD TBD $184,877
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $45,000
Construction $0 TBD TBD TBD TBD TBD $880,000
Contingency $0 TBD TBD TBD TBD TBD $265,000
Inspection $0 TBD TBD TBD TBD TBD $90,000
$129,941 TBD TBD TBD TBD TBD $1,464,877
Funding
330 (CIP) $129,941 TBD TBD TBD TBD TBD $1,464,877
TBD TBD TBD TBD TBD
$129,941 TBD TBD TBD TBD TBD $1,464,877
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction is deferred to a Fiscal Year to be determined.
Project Location Map Background and Justification:
The existing road embankment is damaged, and the existing storm drain
and catch basin is under capacity. A new system is needed to reduce the
likelihood of flooding during heavy rainfall.
C-80
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 8718 Stormwater Drainage Improvements 6415 Corsini Place
This project is to implement a storm system solution to mitigate possible
land erosion that runs through the hillside of 6415 Corsini Place property.
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $60,000 TBD TBD TBD TBD TBD $60,000
Engineering $0 TBD TBD TBD TBD TBD TBD
Environmental $0 TBD TBD TBD TBD TBD TBD
Management $0 TBD TBD TBD TBD TBD TBD
Construction $0 TBD TBD TBD TBD TBD TBD
Contingency $0 TBD TBD TBD TBD TBD TBD
Inspection $0 TBD TBD TBD TBD TBD TBD
$60,000 TBD TBD TBD TBD TBD TBD
Funding
330 (CIP) $60,000 TBD TBD TBD TBD TBD TBD
TBD TBD TBD TBD TBD
$60,000 TBD TBD TBD TBD TBD TBD
Estimated annual operating cost None Estimated Schedule:
Planning in Fiscal Year 2021-22.
Project Location Map Background and Justification:
The City inherited many of its storm drains from LA County upon
incorporation in 1973. Since then the City has been working to upgrade
and repair its storm drain system to address needed maintenance and
meet current hydraulic demands.
The existing storm drain pipe at 6415 Corsini Place has been damaged and
the catch basin needs repairs. This project will make needed repairs and
will implement a storm system to properly convey runoff and reduce the
likelihood of land erosion.
A conceptual design and preliminary cost estimate will be developed in
Fiscal Year 2020 to 2021 After a concept design is finalized, the funding for
final engineering and construction will be requested.
C-81
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8700 Series Storm Water System Improvements Project Code: 87New1 Stormwater Drainage Improvements Hawthorne Boulevard at Hawkhurst
This project is intended to repair a storm drain system, and consists of:
- Replacing and improving the existing underground storm drain system
(lateral pipes, main storm drain pipes and box culverts)
- Installing new catch basins, drainage inlets and manholes
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $0
Engineering $0 TBD TBD TBD TBD TBD $243,000
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $70,000
Construction $0 TBD TBD TBD TBD TBD $1,350,000
Contingency $0 TBD TBD TBD TBD TBD $135,000
Inspection $0 TBD TBD TBD TBD TBD $135,000
$0 TBD TBD TBD TBD TBD $1,933,000
Funding
330 (CIP) $0 TBD TBD TBD TBD TBD $1,933,000
$0 TBD TBD TBD TBD TBD $1,933,000
Estimated annual operating cost None Estimated Schedule:
Construction in a Fiscal Year to be determined
Project Location Map Background and Justification:
The 2015 Master Plan of Drainage identified needed improvements
throughout the City and this location was included in a list of areas to be
improved. Design work for improvements to these areas is being
completed in the 2019/2020 Fiscal Year.
This project reduces the likelihood of flooding.
C-82
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8811 Arterial Walls and Fences Aesthetic Improvements Program – Citywide
This program is intended to improve the aesthetics of walls and fences
along arterial roadways, and consists of:
- Developing a master plan for walls and fences along arterial and
collector roads
- Developing standards for new walls and fences (including
height, design and material requirements)
- Replacing existing, or building new, walls and fences, at locations to be
selected by the City
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD TBD
Engineering $0 TBD TBD TBD TBD TBD TBD
Environmental $0 TBD TBD TBD TBD TBD TBD
Management $0 TBD TBD TBD TBD TBD TBD
Construction $0 TBD TBD TBD TBD TBD TBD
Contingency $0 TBD TBD TBD TBD TBD TBD
Inspection $0 TBD TBD TBD TBD TBD TBD
$0 TBD TBD TBD TBD TBD TBD
Funding
330 (CIP) $0 TBD TBD TBD TBD TBD TBD
$0 TBD TBD TBD TBD TBD TBD
Estimated annual operating cost None Estimated Schedule:
Master Plan and Standards Development in Fiscal Year 2022-23
Project Location Map Background and Justification:
Improvements to the walls and fences along arterial roadways reflects
positively on the entire City and enhances the surrounding areas.
Funding for development of an Arterial Walls and Fences Master Plan was
proposed as part of the April 13, 2022 City Council CIP Budget Workshop.
However, Staff determined that the Master Plan could be developed in-
house with relatively minor support from consultants funded through the
operating budget. Therefore, development of a Master Plan will move
forward in FY22-23 and the project will be placed on the Wants/Needs list
so that funding for implementation can be considered in future CIP cycles.
C-83
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8817 Pavement Management Program – Residential Roadway Rehabilitation - Area 7
As part of the Residential Roadways Rehabilitation Program, this project
consists of rehabilitating the roadways in Area 7, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing deteriorated signs, pavement markings and curb address
numbers
- Improving drainage (if needed)
- Installing ADA compliant ramps (when necessary)
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning N/A TBD TBD TBD TBD TBD $0
Engineering N/A TBD TBD TBD TBD TBD $355,000
Environmental N/A TBD TBD TBD TBD TBD $0
Management N/A TBD TBD TBD TBD TBD $75,000
Construction N/A TBD TBD TBD TBD TBD $2,000,000
Contingency N/A TBD TBD TBD TBD TBD $200,000
Inspection N/A TBD TBD TBD TBD TBD $200,000
N/A TBD TBD TBD TBD TBD $2,830,000
Funding
202 (Gas Tax) N/A TBD TBD TBD TBD TBD $0
220 (Meas. R) N/A TBD TBD TBD TBD TBD $355,000
330 (CIP) N/A TBD TBD TBD TBD TBD $2,475,000
N/A $0 $0 $0 $0 $2,830,000 $2,830,000
Estimated annual operating cost None Estimated Schedule:
Tentatively scheduled for:
Engineering in FY
Construction in FY
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
The City has established a rehabilitation program to make repairs and
improvements to the residential streets on a recurring basis to maintain
them in good condition. The City is divided into nine areas for this
purpose, and the program is designed to rehabilitate each area every eight
years according to a rotating schedule.
1
2 3
4
5
6
7
8 9
C-84
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8818 Pavement Management Program – Residential Roadway Rehabilitation - Area 8
As part of the Residential Roadways Rehabilitation Program, this project
consists of rehabilitating the roadways in Area 8, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing deteriorated signs, pavement markings and curb address
numbers
- Improving drainage (if needed)
- Installing ADA compliant ramps (when necessary)
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning N/A TBD TBD TBD TBD TBD $0
Engineering N/A TBD TBD TBD TBD TBD $355,000
Environmental N/A TBD TBD TBD TBD TBD $0
Management N/A TBD TBD TBD TBD TBD $75,000
Construction N/A TBD TBD TBD TBD TBD $2,000,000
Contingency N/A TBD TBD TBD TBD TBD $200,000
Inspection N/A TBD TBD TBD TBD TBD $200,000
N/A TBD TBD TBD TBD TBD $2,830,000
Funding
202 (Gas Tax) N/A TBD TBD TBD TBD TBD $0
220 (Meas. R) N/A TBD TBD TBD TBD TBD $355,000
330 (CIP) N/A TBD TBD TBD TBD TBD $2,475,000
N/A $0 $0 $0 $0 $2,830,000 $2,830,000
Estimated annual operating cost None Estimated Schedule:
Tentatively scheduled for:
Engineering in FY
Construction in FY
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
The City has established a rehabilitation program to make repairs and
improvements to the residential streets on a recurring basis to maintain
them in good condition. The City is divided into nine areas for this
purpose, and the program is designed to rehabilitate each area every eight
years according to a rotating schedule.
1
2 3
4
5
6
7
8 9
C-85
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8834 Pavement Management Program – Residential Roadway Rehabilitation - Areas 3 & 4
As part of the Residential Roadways Rehabilitation Program, this project
consists of rehabilitating the roadways in Areas 3 & 4, and consist of:
- Resurfacing the existing asphalt
- Replacing damaged asphalt
- Replacing damaged curbs, gutters and sidewalks
- Replacing deteriorated signs, pavement markings and curb address
numbers
- Improving drainage (if needed)
- Installing ADA compliant ramps (when necessary)
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning N/A TBD TBD TBD TBD TBD TBD
Engineering N/A TBD TBD TBD TBD TBD TBD
Environmental N/A TBD TBD TBD TBD TBD TBD
Management N/A TBD TBD TBD TBD TBD TBD
Construction N/A TBD TBD TBD TBD TBD TBD
Contingency N/A TBD TBD TBD TBD TBD TBD
Inspection N/A TBD TBD TBD TBD TBD TBD
N/A TBD TBD TBD TBD TBD TBD
Funding
202 (Gas Tax) N/A TBD TBD TBD TBD TBD TBD
220 (Meas. R) N/A TBD TBD TBD TBD TBD TBD
330 (CIP) N/A TBD TBD TBD TBD TBD TBD
N/A $0 $0 $0 $0 TBD TBD
Estimated annual operating cost None Estimated Schedule:
Tentatively scheduled for:
Engineering in FY
Construction in FY
Project Location Map Background and Justification:
Good road conditions with smooth pavement are expected by the City’s
residents.
Timely maintenance reduces the overall lifecycle costs of roadway
infrastructure.
The City has established a rehabilitation program to make repairs and
improvements to the residential streets on a recurring basis to maintain
them in good condition. The City is divided into nine areas for this
purpose, and the program is designed to rehabilitate each area every eight
years according to a rotating schedule.
1
2 3
4
5
6
7
8 9
C-86
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8839 Palos Verdes Drive East Path Improvements (from Bronco Drive to Sunnyside Ridge Road)
This project is intended to construct a decomposed granite (“DG”)
pedestrian/equestrian path in the public right-of-way
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD TBD
Engineering $99,942 TBD TBD TBD TBD TBD TBD
Environmental $0 TBD TBD TBD TBD TBD TBD
Management $0 TBD TBD TBD TBD TBD TBD
Construction $0 TBD TBD TBD TBD TBD TBD
Contingency $0 TBD TBD TBD TBD TBD TBD
Inspection $0 TBD TBD TBD TBD TBD TBD
$99,942 TBD TBD TBD TBD TBD TBD
Funding
220 (Meas. R) $99,942 TBD TBD TBD TBD TBD TBD
330 (CIP) $0 TBD TBD TBD TBD TBD TBD
$99,942 TBD TBD TBD TBD TBD TBD
Estimated annual operating cost To Be Determined Estimated Schedule:
Construction in a Fiscal Year to be determined.
Project Location Map Background and Justification:
The original project scope to provide a path in the public right-of-way and
implement traffic improvements recommended by the Traffic Safety
Committee. The scope was revised as part of the Fiscal Year 2022-23 CIP
process to separate the path improvements and the traffic improvements
into two projects. This project is the path improvements.
C-87
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 8849 Walking Paths Improvement Program
The City will assess arterial streets at various locations and will fund
improvements on an annual basis. Improvements will range in scope
depending on the location.
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $0
Engineering $0 TBD TBD TBD TBD TBD $30,000
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $15,000
Construction $0 TBD TBD TBD TBD TBD $290,000
Contingency $0 TBD TBD TBD TBD TBD $45,000
Inspection $0 TBD TBD TBD TBD TBD $30,000
$0 TBD TBD TBD TBD TBD $410,000
Funding
TBD $0 TBD TBD TBD TBD TBD TBD
TBD $0 TBD TBD TBD TBD TBD TBD
$0 TBD TBD TBD TBD TBD $410,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Engineering and construction in a Fiscal Year to be determined.
Project Location Map Background and Justification:
This program addresses concerns raised by the City Council at the
CIP Budget Workshop on April 12, 2021 to provide pedestrian path
improvements along arterial roads. This program will address
locations where arterial roadway rehabilitation is not scheduled to
occur.
C-88
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88LY3 Palos Verdes Drive West Pedestrian Crossing
This project is intended to create a pedestrian crossing at the intersection
of Palos Verdes Drive West (PVDW) and Berry Hill Drive as well as PVDW
and Calle Entradero, and consists of:
- Installation of a traffic signal at PVDW and Berry Hill Dr.
- Installation of a traffic signal at PVDW and Calle Entradero
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $0
Engineering $0 TBD TBD TBD TBD TBD $50,000
Environmental $0 TBD TBD TBD TBD TBD $0
Management $0 TBD TBD TBD TBD TBD $50,000
Construction $0 TBD TBD TBD TBD TBD $1,015,000
Contingency $0 TBD TBD TBD TBD TBD $300,000
Inspection $0 TBD TBD TBD TBD TBD $50,000
$0 TBD TBD TBD TBD TBD $1,465,000
Funding
TBD $0 TBD TBD TBD TBD TBD TBD
TBD $0 TBD TBD TBD TBD TBD TBD
$0 TBD TBD TBD TBD TBD $1,465,000
Estimated annual operating cost To Be Determined Estimated Schedule:
To be determined.
Project Location Map Background and Justification:
Currently, there is no defined pathway for pedestrians to connect between
the Berry Hill Drive neighborhood and the trail at the Vicente Bluffs
Reserve.
This project creates a safe travel path from the Berry Hill Drive area to the
Vicente Bluffs Reserve by connecting Berry Hill Drive to the trail entrance
at Calle Entradero.
C-89
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
8800 Series Right-of-Way Improvements Project Code: 88LY6 Ganado Drive Parkway Area Aesthetics Improvements
This project is intended to improve the aesthetics of the public right-of-
way and consists of:
- Constructing a new irrigation system
- Installing new landscaping
Project Cost Estimates
Expenses/Commitments to date FY TBD FY TBD FY TBD FY TBD FY TBD Totals
Planning $0 TBD TBD TBD TBD TBD $10,000
Engineering $0 TBD TBD TBD TBD TBD $15,000
Environmental $0 TBD TBD TBD TBD TBD $5,000
Management $0 TBD TBD TBD TBD TBD $5,000
Construction $0 TBD TBD TBD TBD TBD $75,000
Contingency $0 TBD TBD TBD TBD TBD $25,000
Inspection $0 TBD TBD TBD TBD TBD $10,000
$0 TBD TBD TBD TBD TBD $145,000
Funding
TBD $0 TBD TBD TBD TBD TBD TBD
TBD $0 TBD TBD TBD TBD TBD TBD
$0 TBD TBD TBD TBD TBD $145,000
Estimated annual operating cost To Be Determined Estimated Schedule:
Project Schedule to be determined
Project Location Map Background and Justification:
Residents in this area have requested new landscaping and irrigation in the
public right-of-way area along Ganado Drive.
C-90
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
APPENDIX
General Plan Goals
The goals stated below are included in the City’s General Plan, as adopted in September 2018,
which serves as the City’s long-term strategic planning tool. All CIP projects should contribute to
fulfilling one or more of the goals listed below.
Circulation Element
1. Ensure adequate public utilities and communication services to all residents, while
considering environmental, aesthetic, and view impacts.
2. Provide and maintain a safe, efficient, and comprehensive system of roads and trails, and
coordinate them with other jurisdictions and agencies.
3. Facilitate mobility of residents through an adequate public transportation system with
consideration of the City’s demographics.
4. Work with other jurisdictions and agencies to ensure that there are adequate storm drains,
water systems, and sewer systems to serve the residents.
5. Where appropriate, use complete street concepts to integrate the needs of all users of the
roadway system consistent with the California Complete Streets Act of 2008.
Conservation and Open Space Element
1. To conserve, protect, and enhance the City’s natural resources; beauty; and open space for
the benefit and enjoyment of its residents and the residents of the entire region. Future
development shall recognize the sensitivity of the natural environment and be accomplished
in such a manner as to maximize the protection of it.
2. To protect and preserve all significant archaeological, paleontological, and historical
resources within the City.
3. To protect the environment by reducing environmental hazards in the community.
Social Services Element
1. Promote public input and participation in the decision making process by all members of the
community.
2. Promote the efficient and equitable use of public facilities by all members of the community.
3. Promote healthy and affordable housing opportunities for all segments of the community.
4. Promote healthy food access and physical activities for all segments of the community.
5. Prioritize improvements and programs in the City to better address the needs of its senior
population.
Fiscal Element
1. Hold taxes and assessments to a minimum and continually explore and analyze the
advantages and disadvantages of alternate or new sources of revenue.
2. Explore cooperative financing strategies that might be undertaken in association with others.
3. Consider the use of regulatory legislation and other options to obtain contributions,
dedications, reservations (option to purchase) and rights-of-way (i.e., easements).
4. Plan for revenues generated by development to sufficiently cover costs related to such
development.
C-91
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
5. Thoroughly evaluate operation and maintenance costs in addition to capital asset
expenditures to ensure that available financing is sufficient to meet related ongoing operating
expenditures.
6. Maintain a prudent general fund reserve.
7. Consider all available funding sources for City expenditures.
8. Maintain competitive rates for taxes and fees charged for the use of community resources.
9. Adopt a balanced budget. 10. Control the growth of expenditures.
Land Use Element
1. Provide for land uses that will be sensitive to and enhance the natural environment and
character of the City; supply appropriate facilities to serve residents and visitors; promote
fiscal balance; and protect the general health, safety, and welfare of the City.
2. Carefully control and direct future growth towards making a positive contribution to all
elements of the community. Growth in Rancho Palos Verdes should be a cautious,
evolutionary process that considers the capacity limitations for the City, and the environmental
factors and quality of life on the Peninsula.
3. Preserve and enhance the visual character and physical quality of existing neighborhoods
and housing in a manner that serves the needs of the residents.
4. The City shall discourage industrial and major commercial activities that are not compatible
with the terrain and environmental characteristics of a respective region of the City. Activities
shall be carefully and strictly controlled and limited, giving consideration to the respective
neighboring residential or open space areas.
5. Encourage the development of institutional facilities to serve the needs of its residents.
6. Endeavor to provide, develop, and maintain recreational facilities and programs of various
types for a variety of activities for persons of all age groups and in all areas of the community.
7. Existing agricultural uses within the City shall be allowed so long as they are in concert with
the environmental objectives stated elsewhere in the General Plan.
8. Retain the present predominance of single-family residences found throughout the City. Allow
for the maintenance and replacement of existing non-conforming multifamily residential uses.
9. Control the alteration of natural terrain.
10. Preserve the rural and open character of the City through zoning, cooperation with other
jurisdictions, and acquisition of open space land.
Noise Element
1. Through proper land use planning and regulations, to provide for a quiet and serene
residential community with a minimum of restriction on citizen activity.
Safety Element
1. Provide for the protection of life and property from both natural and human-made hazards
within the community.
2. Provide for the protection of the public through effective law enforcement and fire protection
programs and volunteer programs such as Neighborhood Watch and the Community
Emergency Response Team.
3. Develop and enforce health and sanitation requirements and develop emergency
communications and disaster preparedness programs to ensure the overall health and safety
of all residents.
4. Protect life and property and reduce adverse economic, environmental, and social impacts
resulting from any geologic activity.
C-92
Capital Improvement Program (Fiscal Years 2022-2023 through 2026-27)
Visual Resources Element
1. Preserve views and vistas for the public benefit and, where appropriate, the City should strive
to enhance and restore these resources and the visual character of the City, and provide and
maintain access for the benefit and enjoyment of the public.
C-93