CC SR 20200616 01 - Budget Adoption
PUBLIC HEARING
Date: June 16, 2020
Subject:
Consideration and possible action to adopt the Fiscal Year 2020-21 Budget for all City funds and the
Five-Year Capital Improvement Program.
Recommendation:
(1) Reopen the public hearing opened on June 2, 2020;
(2) Accept the changes to the FY 2020-21 Budget as it relates to the 1911 Act Street Lighting, Fund
211; and
(3) Adopt Resolution No. 2020-___, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO
PALOS VERDES APPROVING A BUDGET APPROPRIATION AND ADOPTING THE OPERATING AND
CAPITAL IMPROVEMENT BUDGET FOR FISCAL YEAR 2020-21.
1. Report of Notice Given: Deputy City Clerk
2. Declare Public Hearing Open: Mayor Cruikshank
3. Request for Staff Report: Mayor Cruikshank
4. Staff Report & Recommendation: Trang Nguyen, Director of Finance
5. Council Questions of Staff (factual and without bias):
6. Testimony from members of the public:
The normal time limit for each speaker is three (3) minutes. The Presiding Officer may grant additional time to a representative speaking
for an entire group. The Mayor also may adjust the time limit for individual speakers depending upon the number of speakers who
intend to speak.
7. Declare Hearing Closed/or Continue the Public Hearing to a later date: Mayor Cruikshank
8. Council Deliberation:
The Council may ask staff to address questions raised by the testimony, or to clarify matters. Staff and/or Council may also answer
questions posed by speakers during their testimony. The Council will then debate and/or make motions on the matter.
9. Council Action:
The Council may: vote on the item; offer amendments or substitute motions to decide the matter; reopen the hearing for additional
testimony; continue the matter to a later date for a decision.
CITY COUNCIL MEETING DATE: 06/16/2020
AGENDA REPORT AGENDA HEADING: Public Hearing
AGENDA TITLE:
Consideration and possible action to adopt the Fiscal Year 2020-21 Budget for all City
funds and the Five-Year Capital Improvement Program.
RECOMMENDED COUNCIL ACTION:
(1) Reopen the public hearing opened on June 2, 2020;
(2) Accept the changes to the FY 2020-21 Budget as it relates to the 1911 Act Street
Lighting, Fund 211; and
(3) Adopt Resolution No. 2020-___, A RESOLUTION OF THE CITY COUNCIL OF
THE CITY OF RANCHO PALOS VERDES APPROVING A BUDGET
APPROPRIATION AND ADOPTING THE OPERATING AND CAPITAL
IMPROVEMENT BUDGET FOR FISCAL YEAR 2020-21.
FISCAL IMPACT: The Citywide FY 2020-21 Budget includes total revenues of about
$35.1 million and total expenditures of almost $35.8 million,
excluding transfers and Improvement Authorities. The total General
Fund includes revenues of almost $29 million and expenditures of
$26.8 million, excluding transfers.
Amount Budgeted: N/A
Additional Appropriation: N/A
Account Number(s): N/A
ORIGINATED BY: Vina Ramos, Interim Deputy Director of Finance
REVIEWED BY: Trang Nguyen, Director of Finance
APPROVED BY: Ara Mihranian, AICP, City Manager
ATTACHED SUPPORTING DOCUMENTS:
A. Resolution No. 2020-___ (page A-1)
B. FY 2020-21 Budget Summary (page B-1)
C. FY 2020-21 Fund Balance Summary (page C-1)
D. June 2, 2020, City Council Staff Report (page D-1)
E. CIP Project Description (page E-1)
BACKGROUND AND DISCUSSION:
1
The City Council is being presented this evening, as a second public hearing in the
budget process, the consideration of the adoption of the FY 2020-21 Budget. The
required notice of the public hearing was published in the Palos Verdes Peninsula News
on May 14 and May 21, 2020. In summary, the City Council’s budget process consists
of the following steps:
The FY 2020-21 Budget includes City Council direction provided on April 13, April 27,
May 19, and June 2, 2020. At the duly noticed public hearing on June 2, the City
Council unanimously approved the budget recommendations with no further
modifications or changes, as well as determined that the utility users’ tax (UUT) rate of
3% should continue for FY 2020-2021 as a necessary revenue source for the City’s
operating and capital improvements. The comprehensive staff report for the FY 2020-21
Draft Budget presented at the June 2 meeting and the Capital Improvement Program
(CIP) project description are attached (Attachment D and E). Additionally, the staff
reports and presentations for the budget workshops are published on the City’s Meeting
Video, Agenda and Minutes Portal at http://www.rpvca.gov/772/City-Meeting-Video-and-
Agendas.
Subsequent to the June 2 public hearing, Staff noticed that the budget for the annual
maintenance services of the traffic lights and traffic signals was inadvertently excluded
from the FY 2020-21 operating budget. Therefore, Staff is requesting to include a
budget of $115,100 in the 1911 Act Street Lighting, Fund 211. The table below
summarizes the change to the Draft Budget as presented on June 2, 2020.
The proposed changes have no impact to the General Fund expenditures and fund
balance because the change is an increase to the operating expenditure budget in the
Budget
Adoption
June 16
Budget Public
Hearing
June 2
Preliminary
Budget
May19
Budget
Workshops
April 13 (GF)
April 27 (CIP)
1911 Act Street Lighting Draft Budget Adopted Budget Variances
Street Lights Maintenance 347,100 462,200 115,100
Capital Improvement 342,000 342,000 -
689,100 804,200 115,100
2
Special Revenue, 1911 Act Street Lighting Fund . Staff has also included the updated
FY 2020-21 Budget Summary (Attachment B) and the updated Fund Balance Summary
(Attachment C).
CONCLUSION:
In conclusion, to legally adopt the FY 20210-21 Budget, as amended, Staff
recommends that the City Council adopt the attached resolution (Attachment A)
approving the FY 2020-21 Budget.
ALTERNATIVES:
In addition to the Staff recommendation, the following alternative actions are available
for the City Council’s consideration:
1) Do not adopt the Fiscal Year 2020-21 Budget for all City funds and the Five-
Year Capital Improvement Program, and provide direction to Staff on
recommended changes.
2) Take other action, as deemed appropriate.
3
Resolution No. 2020-__
Page 1 of 6
RESOLUTION NO. 2020-___
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
RANCHO PALOS VERDES APPROVING A BUDGET
APPROPRIATION AND ADOPTING THE OPERATING AND
CAPITAL IMPROVEMENT BUDGET FOR FISCAL YEAR
2020-2021.
WHEREAS, on April 13, 2020, the City Council conducted a public workshop to
consider the assumptions and estimates that would be used to develop the FY 2020 -2021
General Fund Operating budget;
WHEREAS, on April 27, 2020, the City Council conducted a second public
workshop to review and discuss the FY 2020-2021 Capital Improvement Program (CIP)
budget and the City’s 5-year CIP Program;
WHEREAS, on May 19, 2020, the City Council reviewed the FY2020 -2021
Preliminary Budget based on third quarter figures, including the CIP, Special Revenue
Funds, and the Equipment Replacement Fund. The Preliminary Budget presented to the
City Council included a structurally balanced budget for the General Fund, where recurring
revenues are greater than or equal to recurring expenditures;
WHEREAS, on June 2, 2020, the City Council conducted a duly noticed public
hearing to receive a comprehensive report and public input on the FY 2020-2021 Budget
based on estimated year-end results. That evening, the City Council also determined that
the utility users’ tax (UUT) rate of 3% should continue for FY 2020-2021 as a necessary
revenue source for the City’s operating and capital improvements ;
WHEREAS, on June 16, 2020, the City Council conducted an advertised Public
Hearing to receive public input regarding the budget for FY 2020-21;
BE IT, THEREFORE, RESOLVED BY THE CITY COUNCIL OF THE CITY OF
RANCHO PALOS VERDES:
Section 1: That a revenue and expenditure/expense budget is hereby adopted. The
adopted budget, by fund, is per Attachment A with a total Estimated Ending Fund Balance
of $44,340,441 for all City funds as of June 30, 2021, exclusive of the City’s Improvement
Authorities.
A. The City Manager is authorized to transfer certain Budget Appropriation
Balances within functions and/or programs when deem ed necessary to do so in
accordance with Chapter 3.32 of the Rancho Palos Verdes Municipal Code.
B. City Council approval will be required for any significant changes involving
increased or decreased service levels.
A-1
Resolution No. 2020-__
Page 2 of 6
C. The Director of Finance shall be responsible for constant monitoring of the
budget and shall establish and implement appropriate control mechanisms necessary for
said purpose, after approval by the City Manager.
Section 2: The FY 2020-21 Revenue Budget is hereby adopted, establishing the
following Governmental and Internal Service Fund contribution levels:
GENERAL 28,969,900$
CIP 460,000
GAS TAX 1,462,000
EL PRADO LIGHTING 2,500
CDBG 217,700
1911 ACT 628,200
WASTE REDUCTION 131,000
AIR QUALITY MANAGEMENT 55,000
PROPOSITION C 702,400
PROPOSITION A 849,400
PUBLIC SAFETY GRANTS 157,700
MEASURE R 545,400
MEASURE M 530,000
HABITAT RESTORATION 12,400
SUBREGION 1 MAINTENANCE 14,000
MEASURE A 91,000
ABALONE COVE SEWER DISTRICT 52,000
DONOR RESTRICTED CONTRIBUTIONS 25,000
QUIMBY 25,000
LOW-MODERATE INCOME HOUSING 46,200
AFFORDABLE HOUSING IN LIEU 15,000
ENVIRONMENTAL EXCISE TAX 10,000
TOTAL GOVERNMENTAL FUND REVENUES 35,001,800$
EQUIPMENT REPLACEMENT 138,300$
TOTAL INTERNAL SERVICE FUND REVENUES 138,300$
Section 3: The FY 2020-21 Budget is hereby adopted, establishing the following
transfers into the following funds:
A-2
Resolution No. 2020-__
Page 3 of 6
GENERAL 230,000$
CIP 1,934,000
SUBREGION 1 MAINTENANCE 10,000
ABALONE COVE SEWER MAINTENANCE -
*TOTAL OPERATING TRANSFERS IN 2,174,000$
*Does not include $30,000 transfer in for Improvement Authority - Portuguese
Bend
Section 4: The FY 2020-21 Budget is hereby adopted, establishing the following
transfers from the following funds:
GENERAL 1,964,000$
PUBLIC SAFETY GRANTS 130,000
MEASURE A 100,000
TOTAL OPERATING TRANSFERS OUT 2,194,000$
*Does not include $30,000 transfer out for Improvement Authority - Portuguese
Bend
Section 5: The FY 2020-21 Operating and Capital Improvement Budget Programs
are hereby adopted, establishing the following allocations.
A-3
Resolution No. 2020-__
Page 4 of 6
City Council 102,900$
Legal Services 975,000
Public Safety - Sheriff Services 7,222,400
Special Safety Programs 160,300
City Manager 795,300
City Clerk 638,700
Community Outreach 68,300
Emergency Preparedness 158,400
RPV TV 229,700
Human Resources 316,000
Information Technology - Data 1,081,800
Information Technology - Voice 110,000
Finance 1,565,100
Non-departmental 1,874,700
Community Development Administration 604,200
Planning 840,000
Building & Safety Services 787,200
Code Enforcement 295,600
View Restoration/Preservation 359,300
NCCP 50,000
Geology 100,000
Animal Control 109,000
Public Works Administration 2,095,500
Traffic Management 304,800
Storm Water Quality 506,000
Public Building Maintenance 529,000
Parks Maintenance 702,000
Street Landscape Maintenance 181,000
Trails & Open Space Maintenance 334,800
Fuel Modification 554,500
Vehicle Maintenance 47,000
Sewer Maintenance 35,000
Recreation Administration 1,088,000
Other Recreation Facilities 1,000
Fred Hesse Jr. Park 181,800
Robert E. Ryan Park 86,700
Ladera Linda Community Center 67,600
Abalone Cove Shoreline Park 155,300
Special Events 209,700
Point Vicente Interpretive Center 550,400
REACH 71,700
Recreation Support Services 21,000
City Run Sports & Activities 4,900
Contract Classes 50,000
Volunteer Program 7,000
Park Rangers 308,300
Eastview Park 67,900
Open Space Management 232,100
SUBTOTAL GENERAL FUND EXPENDITURES 26,836,900$
A-4
Resolution No. 2020-__
Page 5 of 6
Street Maintenance - Pavement Management 150,000$
Street Maintenance - Non-Pavement 942,000
Portuguese Bend Rd. Maintenance 70,000
SUBTOTAL GAS TAX FUND EXPENDITURES 1,162,000$
CIP 2,521,000$
EL PRADO LIGHTING 800
1911 ACT 804,200
WASTE REDUCTION 287,500
AIR QUALITY MANAGEMENT 57,000
PROPOSITION C 945,000
PROPOSITION A 776,600
MEASURE R 450,000
MEASURE M 536,000
HABITAT RESTORATION 184,900
SUBREGION 1 MAINTENANCE 41,600
ABALONE COVE SEWER MAINTENANCE 146,000
DONOR RESTRICTED CONTRIBUTIONS 25,000
COMMUNITY DEVELOPMENT BLOCK GRANT 150,600
ENVIRONMENTAL EXCISE TAX 210,000
SUBTOTAL OTHER FUNDS EXPENDITURES 7,136,200$
EQUIPMENT REPLACEMENT 650,000$
SUBTOTAL INTERNAL SERVICE FUNDS EXPENDITURES 650,000$
A-5
Resolution No. 2020-__
Page 6 of 6
PASSED, APPROVED and ADOPTED the 16th day of June 2020.
___________________________
ATTEST: MAYOR
_____________________
CITY CLERK
State of California )
County of Los Angeles )
City of Rancho Palos Verdes )
I, EMILY COLBORN, City Clerk of The City of Rancho Palos Verdes, hereby certify that the
above Resolution No. 2020-__ was duly and regularly passed and adopted by the said City
Council at regular meeting thereof held on June 16, 2020.
___________________________
CITY CLERK
A-6
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
GENERAL FUND
PROPERTY TAXES
3102-3103 Property Tax 7,114,319 7,840,208 8,236,989 8,338,300 8,553,800
3107 Property Tax in Lieu of Sales 332,296 - - - -
3107 Property Tax in Lieu of VLF 4,432,363 4,663,495 4,920,186 5,117,200 5,275,900
3108 Redevelopment Property Tax Trust 23,668 33,760 50,255 55,600 25,000
3110 Property Transfer Tax 443,174 490,796 359,706 330,600 275,000
TOTAL PROPERTY TAXES 12,345,820 13,028,259 13,567,136 13,841,700 14,129,700
OTHER TAXES
3101 Golf Tax 365,259 402,732 429,049 323,300 300,300
3111 Franchise Taxes 1,984,878 2,128,727 2,149,743 2,150,000 2,167,500
3112 Sales and Use Tax 2,383,705 2,437,988 2,575,202 2,180,000 2,240,000
3113 Sales Tax - PW (PSAF)78,743 82,079 85,979 80,300 72,300
3114-3117 Utility Users Tax 1,775,433 1,837,690 1,917,107 2,099,700 2,099,700
3120-3121 Transient Occupancy Tax 5,600,867 5,615,044 5,645,497 4,181,700 3,762,500
3210 Business License Tax 904,107 887,276 945,792 800,300 865,300
TOTAL OTHER TAXES 13,092,992 13,391,536 13,748,369 11,815,300 11,507,600
OTHER LICENSE & PERMIT
3202 Building & Safety Permits 1,063,530 1,209,868 1,152,758 969,500 969,500
3203 Building & Safety Plan Check 360,349 353,155 393,433 308,400 308,400
3205 Film Permits 43,724 37,125 2,930 30,700 30,700
3206 Animal Control Fees 36,470 31,835 31,365 27,400 27,400
3207 Building & Safety Fees 1,912 858 1,367 3,000 3,000
3208 Building & Safety State Building Standard 79 660 (521) 4,300 4,300
3209 Building & Safety Geology Fees 173,041 132,649 128,272 112,900 112,900
3212 Business License Penalty - 5,784 12,501 18,300 17,900
3213 Parking Permits 690 330 440 500 500
3214 Parking Decals 683 665 988 300 300
3215 Plan & Zone Permits 345,749 341,424 401,764 271,200 271,200
3216 Plan - Investigation 16,165 3,076 - - -
3217 View Restoration Fees 7,719 - 5,106 4,800 4,800
3218 Plan - Misc. Fees - 8,572 7,769 8,000 8,000
3218 Plan - Historical Data Fees 17,176 - - - -
3219 Right of Way Permits 72,142 77,689 74,329 74,600 74,600
3220 Dumpster Permits 1,078 4,018 4,606 3,600 3,600
TOTAL OTHER LICENSE & PERMIT 2,140,507 2,207,708 2,217,106 1,837,500 1,837,100
FINES & FORFEITURES
3501 Tow Fees - 8,383 6,225 5,800 5,800
3502 False Alarm Fines 2,500 11,400 18,200 4,800 4,800
3503 Misc. Court Fines 140,414 91,165 91,460 61,800 61,800
4140-3504 Code Enforcement Citations - 32,805 12,674 15,100 15,000
TOTAL FINES & FORFEITURES 142,914 143,753 128,558 87,500 87,400
RENTALS
3602 Rent - Rec & Parks 2,157 - - - -
5120-3602 Rent - Other Recreational Facilities - 1,314 1,421 5,000 4,800
5130-3602 Rent - Hesse Park 52,013 15,431 44,485 28,600 14,600
5140-3602 Rent - Ryan Park 14,346 43,647 19,595 10,800 4,600
5150-3602 Rent - Ladera Linda 19,132 8,799 6,971 3,100 3,100
5180-3602 Rent - PVIC 199,233 208,603 235,056 152,900 152,900
0000-3602 Rent - Citywide 173,140 226,798 171,200 141,300 141,300
TOTAL RENTALS 460,021 504,592 478,729 341,700 321,300
INTERESTS 107,867 206,893 366,409 323,200 280,000
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
B-1
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
CHARGES FOR SERVICES
3401 Engineering Fees 2,706 198 - - -
5160-3411 Shoreline Parking Lot Fees 261,692 245,941 215,341 154,400 138,000
5120-3412 Program/Event Fees - 5,799 8,374 6,200 5,200
5131-3412 Program/Event Fees - 30,410 63,361 38,800 34,600
5170-3412 Program Fees 7,364 5,557 5,972 8,000 8,000
5190-3412 REACH - Program Fees 7,918 10,456 13,305 2,800 1,000
3906 Sale of Signs/Services 1,150 150 - - -
TOTAL CHARGES FOR SERVICES 280,830 298,511 306,353 210,200 186,800
INTERGOVERNMENTAL REVENUE
3301 Federal Grant Income - 64,483 - - -
3302 Grant Income - - 1,359 - -
3302 Motor Vehicle in Lieu 19,282 17,121 - - -
TOTAL INTERGOVERNMENTAL 19,282 81,604 1,359 - -
OTHER REVENUE
3801 Special Fund Administration 155,800 89,700 169,356 139,700 150,000
5120-3901 Donations - Britton Memorial 132 - - - -
5170-3901 Donations - Special Events - 5,400 4,700 3,800 3,800
5180-3901 Donations - PVIC 14,166 11,667 8,411 8,500 5,400
5190-3901 Donations - REACH 2,946 372 1,244 1,000 800
3901 Donations - General - 1 - - -
3902 CASP Fees 1,215 4,253 7,604 4,500 4,500
3904 RDA Loan Payment 177,186 117,694 139,938 193,100 298,800
3908 Successor Agency Adminstration 6,807 50,000 - - 16,000
5180-3701 PVIC Gift Shop 26,677 136,013 137,551 79,200 79,200
1430-3999 Misc. Revenues - 1,640 2,600 1,500 1,500
3999 Misc. Revenues 284,500 173,007 405,626 150,000 60,000
TOTAL OTHER REVENUE 669,429 589,747 877,030 581,300 620,000
TOTAL OPERATING REVENUE 29,259,662 30,452,603 31,691,049 29,038,400 28,969,900
INTER-FUND TRANSFERS
Transfer In Public Safety Grant 100,000 140,000 130,000 175,000 140,000
Transfer in Measure A Maintenance 90,000 90,000 90,000 100,000 90,000
TOTAL TRANSFERS IN 190,000 230,000 220,000 275,000 230,000
TOTAL GENERAL FUND 29,449,662 30,682,603 31,911,049 29,313,400 29,199,900
ALL OTHER FUNDS
STATE GAS TAX FUND
INTERGOVERNMENTAL REVENUE
3304 State Gas Tax - 2103 114,879 167,001 142,726 291,520 291,500
3305 State Gas Tax - 2105 241,844 232,717 234,405 190,160 190,200
3306 State Gas Tax - 2106 145,849 144,561 144,587 116,080 116,100
3307 State Gas Tax - 2107 306,619 302,867 294,790 249,680 249,700
3308 State Gas Tax - 2107.5 6,000 6,000 6,000 4,800 4,800
3309 State Gas Tax - 2031 - 197,680 837,064 565,680 565,700
TOTAL INTERGOVERNMENTAL REVENUE 815,191 1,050,826 1,659,572 1,417,920 1,418,000
CHARGES FOR SERVICE
3404 Sidewalk Repair - - - - -
OTHER REVENUE
3999 Misc. Revenues 17,653 63,892 48,179 38,560 38,600
INTEREST -
3601 Interest on Investments 6,870 918 7,466 5,440 5,400
TOTAL STATE GAS TAX FUND 839,714 1,115,636 1,715,217 1,461,920 1,462,000
B-2
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
1972 ACT FUND
OTHER TAXES
3102 Assessments 260,037 - - - -
INTEREST -
3601 Interest on Investments 545 333 541 - -
TOTAL 1972 ACT FUND 260,582 333 541 - -
EL PRADO FUND
OTHER TAXES
3102 Assessments 2,402 2,564 2,782 2,300 2,300
INTEREST
3601 Interest on Investments 180 345 600 200 200
TOTAL EL PRADO FUND 2,582 2,909 3,382 2,500 2,500
1911 ACT FUND
OTHER TAXES
3102 Assessments 632,874 659,534 694,107 606,800 606,800
INTEREST
3601 Interest on Investments 13,292 24,921 37,878 21,200 21,400
TOTAL 1911 ACT FUND 646,166 684,455 731,985 628,000 628,200
BEAUTIFICATION FUND
INTEREST
3601 Interest on Investments 3,268 5,652 - - -
TOTAL EL PRADO FUND 3,268 5,652 - - -
WASTE REDUCTION FUND
INTERGOVERNMENTAL REVENUE
3302 Used Oil Payment 33,973 10,920 22,644 22,100 22,100
3705 Reimbursement LA County TRAP - - - - -
TOTAL INTERGOVERNMENTAL 33,973 10,920 22,644 22,100 22,100
CHARGES FOR SERVICE
3406 AB 939 Fees 187,036 219,802 188,142 93,300 104,300
INTEREST
3601 Interest on Investments 3,144 5,281 8,680 4,600 4,600
TOTAL WASTE REDUCTION FUND 224,153 236,003 219,466 120,000 131,000
AIR QUALITY MANAGEMENT FUND
INTERGOVERNMENTAL REVENUE
3303 AB 2766 Revenue 54,963 54,916 55,414 50,000 50,000
INTEREST
3601 Interest on Investments 613 949 1,413 5,000 5,000
TOTAL AQMD FUND 55,576 55,865 56,827 55,000 55,000
PROPOSITION "C" TRANSPORTATION FUND
INTERGOVERNMENTAL REVENUE
3303 Proposition "C" Sales Tax 645,099 665,051 714,128 696,200 696,200
INTEREST
3601 Interest on Investments 3,835 8,257 15,733 6,200 6,200
TOTAL PROPOSITION "C" FUND 648,934 673,308 729,861 702,400 702,400
B-3
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
PROPOSITION "A" TRANSPORTATION FUND
INTERGOVERNMENTAL REVENUE
3303 Proposition "A" Sales Tax 776,681 802,855 860,943 839,400 839,400
OTHER REVENUE
3999 Misc Revenues 1,675,000 - - - -
INTEREST
3601 Interest on Investments 8,012 26,968 38,887 10,000 10,000
TRANSFERS IN
9101 Transfer in from State Grants - - 300,000 - -
TOTAL PROPOSITION "A" FUND 2,459,693 829,823 1,199,830 849,400 849,400
PUBLIC SAFETY FUND
INTERGOVERNMENTAL REVENUE
3302 CA Brulte (COPS)129,324 139,416 148,747 150,000 150,000
INTEREST
3601 Interest on Investments 603 1,227 2,116 7,700 7,700
TOTAL PUBLIC SAFETY FUND 129,927 140,643 150,863 157,700 157,700
MEASURE "R" TRANSIT SALES TAX FUND
INTERGOVERNMENTAL REVENUE
3303 Measure "R" Sales Tax 483,294 498,787 535,750 522,200 522,200
INTEREST
3601 Interest on Investments 13,110 27,599 34,139 23,200 23,200
TOTAL MEASURE "R" FUND 496,404 526,386 569,889 545,400 545,400
MEASURE "M" TRANSIT SALES TAX FUND
INTERGOVERNMENTAL REVENUE
3303 Measure "M" Sales Tax - 452,015 603,557 529,500 529,500
INTEREST
3601 Interest on Investments - 1,205 1,365 500 500
TOTAL MEASURE "M" FUND - 453,220 604,922 530,000 530,000
HABITAT RESTORATION FUND
INTERGOVERNMENTAL REVENUE
3302 State Grant Income 6,729 433 - - -
INTEREST
3601 Interest on Investments 8,682 13,707 19,953 15,000 12,400
OTHER REVENUES
3999 Misc Revenues 4,769 - - - -
TOTAL HABITAT RESTORATION FUND 20,180 14,140 19,953 15,000 12,400
SUBREGION 1 FUND
INTEREST
3601 Interest on Investments 5,307 9,364 14,969 15,000 14,000
CHARGES FOR SERVICE
3907 Developer Fees - 22,716 - - -
TRANSFERS IN
9101 Transfer in from General Fund - 41,500 - 35,000 10,000
TOTAL SUBREGION 1 FUND 5,307 73,580 14,969 50,000 24,000
B-4
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
MEASURE A FUND
INTERGOVERNMENTAL REVENUE
3303 Measure A 192,598 46,848 86,634 90,000 90,000
INTEREST
3601 Interest on Investments 295 1,184 1,648 1,100 1,000
TOTAL MEASURE A FUND 192,893 48,032 88,282 91,100 91,000
ABALONE COVE SEWER MAINTENANCE FUND
OTHER TAXES
3102 Assessments 54,836 56,578 50,672 61,100 50,000
INTEREST
3601 Interest on Investments 786 2,856 6,407 2,000 2,000
TRANSFERS IN
9101 Transfer in from General Fund 208,000 208,000 - - -
9330 Transfer in from Infrastructure - - - - -
TOTAL ABALONE COVE SEWER MAINT. FUND 263,622 267,434 57,079 63,100 52,000
GINSBURG CULTURAL ARTS BUILDING
INTEREST
3601 Interest on Investments 587 1,045 - - -
TOTAL GINSBURG CULTURAL ARTS FUND 587 1,045 - - -
DONOR RESTRICTED DONATIONS FUND
INTEREST
3601 Interest on Investments 5,966 10,738 16,090 25,000 25,000
OTHER REVENUE
3901 Donations - Restricted 10,500 20,500 44,523 - -
2999-3901 Donations - City's Anniversary - 15,000 - - -
TOTAL DONOR RESTRICTED DONATIONS FUND 16,466 46,238 60,613 25,000 25,000
COMMUNITY DEVELOPMENT BLOCK GRANT FUND
INTERGOVERNMENTAL REVENUE
3301 Grant Income 142,317 223,613 178,591 139,300 217,700
TOTAL CDBG FUND 142,317 223,613 178,591 139,300 217,700
CAPITAL IMPROVEMENT FUND
INTERGOVERNMENTAL REVENUE
3301 Federal Grant - - 5,007 - -
3302 State Grant - - - - -
3303 Local Grant 143,064 - - - -
TOTAL INTERGOVERNMENTAL REVENUE 143,064 - 5,007 - -
INTEREST
3601 Interest on Investments 191,721 303,781 508,963 506,200 460,000
OTHER REVENUE
3999 Misc Revenues - - - - -
TRANSFERS IN
9101 Transfer in from General Fund 4,141,397 4,526,000 4,301,852 2,617,300 1,934,000
9331 Transfer in from Federal Grants - - 1,087,318 98,300 -
TOTAL TRANSFERS IN 4,141,397 4,526,000 5,389,170 2,715,600 1,934,000
TOTAL CAPITAL IMPROVEMENT FUND 4,476,182 4,829,781 5,903,140 3,221,800 2,394,000
B-5
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
FEDERAL GRANTS
INTERGOVERNMENTAL REVENUE
3301 Federal Grant - 1,235,012 141,442 - -
INTEREST
3601 Interest on Investments - 6,799 - - -
TOTAL FEDERAL GRANTS FUND - 1,241,811 141,442 - -
STATE GRANTS
INTERGOVERNMENTAL REVENUE
3302 State Grant - - 144,320 - -
TOTAL STATE GRANTS FUND - - 144,320 - -
QUIMBY FUND
CHARGES FOR SERVICE
3907 Quimby Developer Fee 50,929 38,223 - - -
INTEREST
3601 Interest on Investments 16,505 21,048 33,272 52,000 25,000
TOTAL QUIMBY FUND 67,434 59,271 33,272 52,000 25,000
CITY LOW-MOD INCOME HOUSING FUND
INTEREST
3601 Interest on Investments 764 1,770 2,956 1,500 3,000
OTHER REVENUES
3904 RDA Loan Payment - - - 43,200 43,200
3999 Misc Revenues 36,860 - - - -
PROPERTY TAX
3108 Redevelopment Property Tax Trust 5,917 14,712 34,984 - -
TOTAL CITY LOW-MOD INCOME HOUSING FUND 43,541 16,482 37,940 44,700 46,200
AFFORDABLE HOUSING PROJECTS FUND
INTEREST
3601 Interest on Investments 4,034 7,457 15,961 15,000 15,000
CHARGES FOR SERVICE
3907 Developer Fees - 221,818 - - -
TOTAL AFFORDABLE HOUSING PROJECTS FUND 4,034 229,275 15,961 15,000 15,000
ENVIRONMENTAL EXCISE TAX (EET)
CHARGES FOR SERVICE
3907 EET Developer Fee 95,991 156,065 39,020 - -
INTEREST
3601 Interest on Investments 1,899 4,655 9,399 25,000 10,000
TOTAL QUIMBY FUND 97,890 160,720 48,419 25,000 10,000
TDA ARTICLE 3 - SB 821 BIKEWAY FUND
INTERGOVERNMENTAL REVENUE
3303 TDA Article 3 - SB 821 - 82,500 - - -
TOTAL TDA ARTICLE 3 FUND - 82,500 - - -
B-6
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
WATER QUALITY/FLOOD PROTECTION FUND
INTEREST
3601 Interest on Investments 35,274 28,934 - - -
CHARGES FOR SERVICES
3402 Storm Drain User Fees 14,436 - - - -
INTERGOVERNMENTAL REVENUE
3302 State Grant Income - - 200,000 - -
TOTAL WATER QUALITY FUND 49,710 28,934 200,000 - -
EQUIPMENT REPLACEMENT FUND
CHARGES FOR SERVICE
3803 Interfund Charges 82,050 300,900 300,900 84,800 93,300
TOTAL CHARGES FOR SERVICE 82,050 300,900 300,900 84,800 93,300
INTEREST
3601 Interest on Investments 19,164 29,919 50,259 52,150 45,000
TOTAL EQUIPMENT REPLACEMENT FUND 101,214 330,819 351,159 136,950 138,300
TOTAL OTHER FUNDS REVENUES 11,248,376 12,377,908 13,277,923 8,931,270 8,114,200
TOTAL CITY REVENUES 40,698,038 43,060,511 45,188,972 38,244,670 37,314,100
B-7
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
TRANSFERS OUT 4,387,397 4,813,500 4,346,852 2,757,300 1,964,000
CITY COUNCIL 139,806 107,310 96,251 98,459 102,900
CITY ATTORNEY 1,173,168 1,157,585 1,160,193 1,089,916 975,000
PUBLIC SAFETY
Sheriff 5,451,056 6,223,715 6,407,659 6,820,500 7,222,400
Special Programs 821,653 1,029,299 703,365 590,527 160,300
TOTAL PUBLIC SAFETY 6,272,709 7,253,014 7,111,024 7,411,027 7,382,700
CITY ADMINISTRATION
City Manager 783,077 899,709 802,974 708,621 795,300
City Clerk 484,381 595,565 449,731 764,119 638,700
Community Outreach 74,448 74,465 62,246 63,900 68,300
Emergency Preparedness 161,607 145,801 103,417 61,900 158,400
Emergency Operation Center - - - 269,798 -
RPVtv 169,004 203,701 179,549 193,108 229,700
Human Resources 364,246 373,704 302,545 357,866 316,000
Information Technology - Data 889,924 1,012,124 928,886 1,032,740 1,081,800
Information Technology - Voice 100,933 93,138 96,277 112,000 110,000
TOTAL CITY ADMINISTRATION 3,027,620 3,398,207 2,925,625 3,564,052 3,398,200
FINANCE
Finance 1,265,590 1,349,974 1,502,164 1,616,603 1,565,100
TOTAL FINANCE 1,265,590 1,349,974 1,502,164 1,616,603 1,565,100
NON-DEPARTMENT
Non-departmental 2,400,364 1,166,153 1,133,907 1,207,209 1,874,700
TOTAL NON-DEPARTMENT 2,400,364 1,166,153 1,133,907 1,207,209 1,874,700
COMMUNITY DEVELOPMENT
Administration 547,072 670,903 525,754 604,200
Planning 1,322,813 688,279 835,015 775,043 840,000
Building & Safety 773,627 791,009 826,228 664,723 787,200
Code Enforcement 116,264 183,129 184,457 227,087 295,600
View Restoration 302,403 394,012 321,836 372,028 359,300
NCCP - 16,870 11,445 15,000 50,000
Geology 148,448 115,578 107,253 100,000 100,000
Animal Control - - 89,842 120,000 109,000
TOTAL COMMUNITY DEVELOPMENT 2,663,555 2,735,949 3,046,979 2,799,635 3,145,300
PUBLIC WORKS
Public Works Administration 2,175,728 2,157,495 2,155,312 2,070,095 2,095,500
Traffic Management 391,742 485,705 418,941 270,500 304,800
Storm Water Quality 230,695 310,929 535,921 529,700 506,000
Building Maintenance 448,843 597,137 453,631 548,100 529,000
Parks Maintenance 585,191 670,000 702,000
Street Landscape Maintenance 425,073 573,849 181,000 181,000
Trails & Open Space Maintenance 838,107 935,465 404,279 546,550 334,800
Fuel Modification 1,010,000 554,500
Vehicles Maintenance 418 40,694 41,641 49,500 47,000
Sewer Maintenance 951 1,554 22,550 45,000 35,000
TOTAL PUBLIC WORKS 4,086,484 4,954,052 5,191,315 5,920,445 5,289,600
CITY OF RANCHO PALOS VERDES
STATEMENT OF EXPENDITURES - ALL FUNDS
FISCAL YEAR 2020-2021
B-8
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF EXPENDITURES - ALL FUNDS
FISCAL YEAR 2020-2021
RECREATION AND PARKS
Recreation Administration 873,450 1,042,367 1,026,224 942,604 1,088,000
Other Recreational Facilities 166,130 34,650 64,466 5,697 1,000
Fred Hesse Jr. Park 158,196 215,126 187,970 182,085 181,800
Robert E. Ryan Park 99,820 83,568 92,393 84,967 86,700
Ladera Linda Community Center 75,109 76,440 86,410 73,353 67,600
Abalone Cove Shoreline Park 91,173 139,626 135,175 136,179 155,300
Special Events and Programs 146,374 188,264 194,344 156,173 209,700
Point Vicente Interpretive Center 447,107 471,653 513,920 462,256 550,400
REACH 39,683 64,370 69,327 23,179 71,700
Support Services 74,468 40,978 29,084 20,026 21,000
City Run Sports - 5,659 3,066 4,518 4,900
Contract Classes - 21,649 41,695 55,000 50,000
Volunteer Program - - - 6,000 7,000
Park Rangers - - - 142,661 308,300
Eastview - 4,952 7,354 62,609 67,900
Open Space Management 3,592 104,013 235,721 206,859 232,100
TOTAL RECREATION & PARKS 2,175,102 2,493,315 2,687,149 2,564,166 3,103,400
TOTAL GENERAL FUND 27,591,795 29,429,059 29,201,459 29,028,812 28,800,900
ALL OTHER FUNDS
STATE GAS TAX
Street Pavement Maintenance 365,074 205,666 256,454 150,000 150,000
Street Landscape Maintenance 1,121,909 676,964 508,460 656,460 942,000
Traffic Signal Maintenance 10,175 10,000 16,770 - -
Portuguese Bend Rd. Maintenance - - 48,867 50,000 70,000
Street Maintenance (CIP)442,622 471,592 - 1,395,380 -
TOTAL STATE GAS TAX 1,939,780 1,364,222 830,551 2,251,840 1,162,000
1972 ACT
Street Lights Maintenance 264,903 - - - -
Transfers Out - - - - -
TOTAL 1972 ACT 264,903 - - - -
EL PRADO 237 493 593 800 800
1911 ACT
Street Lights Maintenance 459,441 566,480 536,861 399,902 462,200
Capital Improvements - 48,105 856,683 516,902 342,000
Transfers Out - - - - -
TOTAL 1911 ACT 459,441 614,585 1,393,544 916,804 804,200
BEAUTIFICATION
Operating Expenses - - - - -
Street Maintenance - - - - -
Capital Improvements - 106,283 383,737 - -
Transfers Out - - - - -
TOTAL BEAUTIFICATION - 106,283 383,737 - -
WASTE REDUCTION
Operating Expenses 231,578 244,656 212,991 239,578 287,500
Transfers Out - - - - -
TOTAL WASTE REDUCTION 231,578 244,656 212,991 239,578 287,500
B-9
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF EXPENDITURES - ALL FUNDS
FISCAL YEAR 2020-2021
AIR QUALITY
Operating Expenses 78,284 49,995 50,000 50,000 57,000
Transfers Out - - - - -
TOTAL AIR QUALITY 78,284 49,995 50,000 50,000 57,000
PROP "C" TRANSPORTATION
Street Maintenance - - - - -
Traffic Maintenance 66,699 9,081
Street Maintenance (CIP)539,740 599,924 572,312 640,000 945,000
Transfers Out - - - - -
TOTAL PROPOSITION "C"539,740 599,924 639,011 649,081 945,000
PROP "A" TRANSPORTATION
Dial-a-Ride 613,003 630,334 705,644 774,100 776,600
Capital Projects 10,581 496,443 44,108 454,852 -
Transfers out - - - - -
TOTAL PROPOSITION "A"623,584 1,126,777 749,752 1,228,952 776,600
PUBLIC SAFETY
Transfers out 100,000 140,000 130,000 175,000 130,000
TOTAL PUBLIC SAFETY 100,000 140,000 130,000 175,000 130,000
MEASURE R
Street Landscape Maintenance 169,952 - 28,032 250,000
Capital Projects - 2,036,294 113,705 450,000
Transfers out - - - - -
TOTAL MEASURE R 169,952 - 2,064,326 363,705 450,000
MEASURE M
Repairs & Maintenance - 448,464 565,972 536,000 536,000
Capital Projects - - - -
Transfers out - - - - -
TOTAL MEASURE M - 448,464 565,972 536,000 536,000
HABITAT RESTORATION 140,825 150,633 149,499 179,500 184,900
SUBREGION 1 35,107 36,228 43,831 41,400 41,600
MEASURE A
Transfers out 90,000 90,000 90,000 100,000 100,000
TOTAL MEASURE A 90,000 90,000 90,000 100,000 100,000
ABALONE COVE SEWER MAINTENANCE 163,615 118,188 49,925 221,570 146,000
GINSBURG CULTURAL ARTS BUILDING - 86,344 1,045 -
DONOR RESTRICTED DONATIONS
Operating Expenses 9,760 46,724 31,259 28,000 25,000
Capital Improvements - - 137,683 4,331 -
Transfers out - - - - -
TOTAL DONOR RESTRICTED DONATIONS 9,760 46,724 168,942 32,331 25,000
COMMUNITY DEVELOPMENT BLOCK GRANT 142,317 194,556 193,586 281,861 150,600
B-10
PROJECTED ADOPTED
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF EXPENDITURES - ALL FUNDS
FISCAL YEAR 2020-2021
CAPITAL IMPROVEMENT PROGRAM FUND
Administration 15,341 - - 35,313
Street Improvements 6,385,358 6,911,774 1,862,690 4,193,214 200,000
Parks, Trails & Open Space Improvements 231,565 425,485 215,942 373,324 450,000
Sewer Improvements 198,900 - - 41,291 -
Building Improvements 31,423 9,000 135,649 266,450 301,000
Storm Water Quality Improvements - - 157,319 598,270 370,000
Landslide Improvements 242,935 157,349 37,132 388,138 1,200,000
Transfers Out - - - - -
TOTAL CAPITAL IMPROVEMENT 7,105,522 7,503,608 2,408,733 5,896,000 2,521,000
FEDERAL GRANTS
Capital Improvements - 197,621 - -
Transfers Out - - 1,087,318 98,315 -
TOTAL FEDERAL GRANTS - 197,621 1,087,318 98,315 -
STATE GRANTS
Capital Improvements - - 163,796 200,428 -
Transfers Out - - 300,000 - -
TOTAL STATE GRANTS - - 463,796 200,428 -
QUIMBY
Capital Improvements 80,550 562,680 142,004 475,259 -
Transfers Out - - - - -
TOTAL QUIMBY 80,550 562,680 142,004 475,259 -
ENVIRONMENTAL EXCISE TAX (EET)
Street Landscape Maintenance 75 - - 300,000 210,000
Transfers Out - - - - -
TOTAL ENVIRONMENTAL EXCISE TAX (EET)75 - - 300,000 210,000
TDA ARTICLE 3 - SB 821 BIKEWAY FUND
Capital Improvements - 82,500 - - -
Transfers Out - - - - -
TOTAL TDA ARTICLE 3 - SB 821 BIKEWAY - 82,500 - - -
WATER QUALITY/FLOOD PROTECTION
Operating Expenses - - - - -
Capital Improvements 1,399,913 1,070,747 811,110 - -
Transfers Out - - - - -
TOTAL WATER QUALITY/FLOOD PROTECTION 1,399,913 1,070,747 811,110 - -
EQUIPMENT REPLACEMENT 734,172 203,283 452,376 529,170 650,000
EMPLOYEE BENEFITS - - - - -
TOTAL ALL OTHER FUNDS 14,309,355 14,952,167 13,167,941 14,768,639 9,178,200
TOTAL ALL FUNDS 41,901,150 44,381,226 42,369,400 43,797,451 37,979,100
B-11
Fund Balance Fund Balance
Fund 6/30/2020 Revenues Transfers In Expenditures Transfers Out 6/30/2021
General Fund Balance 21,073,135 28,969,900 230,000 26,836,900 1,964,000 21,472,135
Restricted Amount (Policy Reserve)(13,135,756) (13,418,450)
General Fund Unrestricted Balance 7,937,380 28,969,900 230,000 26,836,900 1,964,000 8,053,685
Restricted by Council Action
CIP 24,342,991 460,000 1,934,000 2,521,000 - 24,215,991
EQUIPMENT REPLACEMENT 2,679,042 138,300 - 650,000 - 2,167,342
Subtotal of Restricted by Council Action 27,022,033 598,300 1,934,000 3,171,000 - 26,383,333
Restricted by Law or External Agencies
GAS TAX 94,814 1,462,000 - 1,162,000 - 394,814
1972 ACT 28,384 - - - - 28,384
EL PRADO LIGHTING 34,475 2,500 - 800 - 36,175
CDBG (131,103) 217,700 150,600 - (64,003)
1911 ACT 1,170,808 628,200 - 804,200 - 994,808
WASTE REDUCTION 334,497 131,000 - 287,500 - 177,997
AIR QUALITY MANAGEMENT 102,012 55,000 - 57,000 - 100,012
PROPOSITION C 630,419 702,400 945,000 - 387,819
PROPOSITION A 1,999,772 849,400 - 776,600 - 2,072,572
PUBLIC SAFETY GRANTS 76,041 157,700 - - 130,000 103,741
MEASURE R 984,844 545,400 - 450,000 - 1,080,244
MEASURE M 37,707 530,000 - 536,000 - 31,707
HABITAT RESTORATION 785,018 12,400 - 184,900 - 612,518
SUBREGION 1 MAINTENANCE 773,920 14,000 10,000 41,600 - 756,320
MEASURE A 57,918 91,000 - - 100,000 48,918
ABALONE COVE SEWER DISTRICT 178,484 52,000 146,000 - 84,484
GINSBURG CULTURAL ARTS BUILDING - - - - - -
DONOR RESTRICTED CONTRIBUTIONS 767,832 25,000 - 25,000 - 767,832
QUIMBY 1,277,833 25,000 - - - 1,302,833
LOW-MOD INCOME HOUSING 235,060 46,200 - - - 281,260
AFFORDABLE HOUSING IN LIEU 853,837 15,000 - - - 868,837
ENVIRONMENTAL EXCISE TAX 236,563 10,000 - 210,000 - 36,563
BIKEWAYS - - - - - -
Subtotal Restricted by Law 10,328,723 5,571,900 10,000 5,777,200 230,000 9,903,423
GRAND TOTAL GOVERNMENT FUNDS 45,288,135 35,140,100 2,174,000 35,785,100 2,194,000 44,340,441
CITY OF RANCHO PALOS VERDES
FY 2020-21 FUND SUMMARY
FY20-21 Estimated Resources FY20-21 Estimated Appropriations
C-1
CITY COUNCIL MEETING DATE: 06/02/2020
AGENDA REPORT AGENDA HEADING: Public Hearing
AGENDA TITLE:
Consideration and possible action to conduct a public hearing on the Fiscal Year 2020-
21 Draft Budget for all City’s funds and the Five-Year Capital Improvement Program.
RECOMMENDED COUNCIL ACTION:
(1) Conduct a public hearing on the possible adoption of the FY 2020-21 Draft
Budget of all City’s funds, excluding the Improvement Authorities, and the Five-
Year Capital Improvement Program;
(2) Determine that the utility users’ tax (UUT) rate of 3% should continue to be
maintained for FY 2020-21 as a necessary revenue source for the City’s
operating and capital improvements; and
(3) Continue the public hearing to June 16, 2020.
FISCAL IMPACT: The Draft Citywide FY 2020-21 Budget includes total revenues of
about $35.1 million and total expenditures of almost $35.7 million,
excluding transfers and Improvement Authorities. The total General
Fund revenues of almost $29 million and expenditures of $26.8
million, excluding transfers.
Amount Budgeted: N/A
Additional Appropriation: N/A
Account Number(s): None
ORIGINATED BY: Christopher Browning, Senior Administrative Analyst
Vina Ramos, Interim Deputy Director of Finance
REVIEWED BY: Trang Nguyen, Director of Finance
APPROVED BY: Ara Mihranian, AICP, City Manager
ATTACHED SUPPORTING DOCUMENTS:
A. FY 2020-21 Draft Budget Summary (page A-1)
B. FY 2020-21 Draft CIP Budget and 5-year CIP (page B-1)
C. Public Comment from Ms. Sunshine (page C-1)
D-1
BACKGROUND:
The City’s budget is a financial plan based on anticipated revenues and expenditures in
a fiscal year starting July 1 through June 30. Each year, the City’s budget is prepared
applying the City’s long tradition of fiscal responsibility, prioritizing public safety, and
providing the highest possible service levels to the community. Like other local
governments across the country, this year’s budget process incorporated the projected
financial impacts from the COVID-19 pandemic. One of the City’s main sources of
revenues estimated to be impacted the most is Transient Occupancy Tax (TOT). The
sudden and unprecedented drop in these revenues have resulted in reassessment of
the Capital Improvement Program (CIP), focusing on projects that were ranked the
highest. The rankings on projects were based on available funding sources in FY 2020 -
21, immediate needs centered on public safety concerns, mandated by
federal/state/local governments, and supports the City Council Goals.
Attributed to the City’s solid financial foundation, f inancially conservative approach, and
stable Property Tax revenues, the City’s operating fund, the General Fund, is estimated
to end FY 2020-21 with a surplus of approximately $8 million, after applying the 50%
City Council’s Policy Reserve of $13.4 million. Due to the recent economic downturn,
although the FY 2020-21 General Fund is estimated to remain with a healthy fund
balance, Staff recognizes that there will be fiscal challenges in the coming years that the
City will need to prepare for. In order to withstand the financial implications of COVID-
19, it is more crucial now, and in future years, for the City to continue to be fiscally
prudent and produce a structurally balanced operating budget. Additionally, it is
important to mention that the FY 2020-21 Draft Budget is a financial plan for one fiscal
year. The City’s long-term financial outlook is documented in the Five-Year Model,
which forecasts economic conditions including scenarios of future sources of revenues
and future spending. The Five-Year Model is an additional tool that the City utilizes
annually to engage discussions and provide guidance with decision making related to
the City’s future financial health. The Five-Year Model will be presented to the City
Council this evening as a separate agenda item.
After completing two FY 2020-21 Budget Workshops in April and the review of the
Preliminary Budget in May, the City Council is being presented this evening, as a public
hearing, the FY 2020-21 Draft Budget. In summary, the City Council’s budget process
consists of the following steps:
The Budget W orkshops document the budget assumptions based on mid-year figures
that frame the following year's budget. Prior to presenting to the City Council, Staff
reports the assumptions, projects, and programs to the City Council’s appointed
Committees – Finance Advisory Committee (FAC), Infrastructure Management
Budget
Workshops
April 13 (GF)
April 27 (CIP)
Budget
Adoption
June 16
Budget
Public
Hearing
June 2
Preliminary
Budget
May 19
D-2
Committee (IMAC), and the Planning Commission (PC). On April 13, 2020, during the
first Budget Workshop, Staff presented the year-end estimates for FY 2019-20 along
with assumptions and estimates that would be used to develop the proposed FY 2020-
21 General Fund Operating Budget. Staff reported an estimated revenue loss from
COVID-19 of $2.6 million, which is then offset by the identified savings of over $1.3
million, totaling a net negative impact of $1.2 million to the FY 2019-20 fund balance.
For the FY 2020-21 Proposed Budget, Staff projected revenues at $28.8 million, which
accounted for the declined revenues of $3.7 million. To mitigate the estimated revenue
loss in FY 2020-21, Staff also presented a total of estimated savings of $3 million in
expenditures, with the total budget of $29.5 million. Additionally, Staff presented the
Five-Year Model and reviewed the assumptions used, highlighting the areas of
concerns for further discussion relating to the General Fund forecasted revenues and
expenditures. Based on this discussion, the City Council directed Staff to further
identify savings and to prepare a balanced operating budget for FY 2020-21.
The second Budget Workshop was held on April 27, 2020, to review and discuss the FY
2020-21 CIP Budget and the City’s CIP 5-Year Program. At this workshop, Staff
presented the City Council a reassessed list of projects due to the estimated drop in
TOT revenue, reducing the General Fund transfers to CIP by $1.3 million in FY 2019-20
and $1.8 million in FY 2020-21. Staff also provided the City Council a status of the
different categories of the CIP Projects including Completed Projects (Category I), On -
going Projects (Category II), Proposed Deferred Projects (Category III), and Proposed
New Projects (Category IV). As a result, the City Council provided Staff with direction to
defer the Storm Room Improvement (City Hall) project to a future date and to identify
funding sources to bring forward the Palos Verdes Drive East Widening and Path
Improvement Project in an earlier fiscal year because of public safety concerns. The
total proposed sixteen (16) projects in CIP for FY 2020-21 is almost $4.5 million
supported by CIP Fund, Measure R, Proposition C, and 1911 Act Lighting.
The Preliminary Budget meeting reports the changes from the Budget Workshops to the
Preliminary Budget based on third quarter figures, including the Capital Improvement
Program (CIP) Fund, Special Revenue Funds, and the Equipment Replacement Fund.
In accordance with City Council Policy No.45, the FY 2020 -21 Preliminary Budget
presented on May 19, 2020 to the City Council is a structurally balanced budget, where
recurring revenues are greater than or equal to recurring expenditures. Staff presented
the changes based on the discussion and additional direction provided by the City
Council at the two budget workshops held in April. Staff presented the FY 2020 -21
Proposed Budget with a positive change in revenues by $410,000 and an additional
budget savings of $721,500 in the General Fund. The revised estimated revenues
reported at this meeting was approximately $29.2 million and $28.8 million in
expenditures, net of transfers. The total changes to the budget since the budget
workshops have resulted in an increase of $1.1 million over estimates in the fund
balance, ending with a surplus of $8 million in FY 2020-21.
The final phase of the City Council’s budget process are two duly noticed public
hearings on the budget prior to its adoption, with the first hearing being presented this
D-3
evening. The budget public hearing is a comprehensive report that documents the
forthcoming year's budget. The analysis presented in the report are comparing between
the draft budgets to the estimated year-end results. Additionally, this report highlights
the summary for FY 2019-20 General Fund Balance and the FY 2020-21 Budget
Assumptions for General Fund, Capital Infrastructure Project Fund, Special Revenue
Funds, and Equipment Replacement Fund.
DISCUSSION:
FY 2019-20 General Fund Balance
As presented at the Preliminary Budget on May 19, 2020, the General Fund revenues
are estimated to end at approximately $29.3 million and expenditures are estimated to
end slightly over $29 million, net of transfers. The estimated results are inclusive of
almost $3.7 million in savings identified during midyear and third quarter reviews. The
majority of the estimated savings are from the unfilled vacant positions, cost
containment measures (i.e. reassessed contract services and program offered), and
reduced transfer to CIP from the revenues loss in TOT. The General Fund is projected
to end the year with an estimated fund balance of $21.1 million and after setting aside
the required 50% reserve of $13.1 million, there will be an excess reserve of over $7.9
million.
Table 1 – FY 2019-20 YE General Fund Balance Estimates
FY 2020-21 Draft Budget
On May 19, 2020, Staff presented the Preliminary Budget at a regular scheduled City
Council meeting. At this meeting, Staff reported on the budget changes based on
FY 19-20
Current Budget
Post COVID-19
FY 19-20 YE
Estimates
3rd Quarter FY 19-
20 YE Estimates
FY 19-20
Variances
Beginning Fund Balance - 7/1/2019 20,788,547 20,788,547 20,788,547 -
Add: Revenues 31,423,400 29,043,100 29,038,400 (2,385,000)
Add: Transfers In 275,000 275,000 275,000 -
Total Revenues 31,698,400 29,318,100 29,313,400 (2,385,000)
Less: Expenditures (28,638,409) (27,278,669) (26,271,512) 2,366,897
Less: Transfers to CIP (3,976,900) (2,617,300) (2,617,300) 1,359,600
Less: Other Transfers Out (140,000) (140,000) (140,000) -
Total Expenditures (32,755,309) (30,035,969) (29,028,812) 3,726,497
Ending Fund Balance - 6/30/2020 19,731,638 20,070,678 21,073,135 1,341,497
50% Reserve Policy 14,319,205 13,639,335 13,135,756 (1,183,449)
Unrestricted Excess/(Deficit) Reserve 5,412,434 6,431,344 7,937,379 2,524,946
D-4
direction received from the City Council from the two Budget Workshops that were held
in April. The results and direction from the Budget Workshops and the Preliminary
Budget meeting are combined to develop the FY 2020-21 Draft Budget. The following
sections of this report will present the detailed explanation of the budget assumptions
including General fund, CIP Fund, Special Revenue Funds, and Equipment
Replacement Fund.
FY 2020-21 General Fund Budget Assumptions/Changes
FY 2020-21 Revenues
For FY 2020-21, Staff is projecting an overall decrease of $68,500 or -0.2% in General
Fund operating revenues (net of transfers) over the FY 2019-20 updated year-end
estimates at third quarter.
Table 2 – General Fund FY 2019-20 Preliminary Revenue Budget
Below is the summary of the FY 2020-21 General Fund Preliminary Revenues
compared to the FY 2019-20 Current Budget and FY 2019-20 year-end estimates.
Property Tax
This revenue category is projected to increase by 2.1%, or $288,000, over the FY 2019-
20 year-end estimate. Property Tax continues to be the largest and historically the most
stable revenue source in the City, growing by assessed values based on sales and
home remodeling, and capped at 2% annually once assessed. Its share of all General
Fund revenue has increased from 44% to roughly 49% with the decrease in TOT
revenue due to the COVID-19 pandemic. There was initial concern that property tax
Revenue Current Budget Year-End Estimate Draft Budget
Property Tax $13,975,500 $13,841,700 $14,129,700 $288,000 2.1%
Transient Occupancy Tax 5,541,300 4,181,700 3,762,500 (419,200) -10.0%
Sales Tax 2,529,000 2,260,300 2,312,300 52,000 2.3%
Permits & Fees 2,167,800 1,819,200 1,819,200 0 0.0%
Franchise Tax 2,044,400 2,150,000 2,167,500 17,500 0.8%
Utility Users Tax 1,942,300 2,099,700 2,099,700 0 0.0%
Other Taxes & Misc. Revenues 3,223,100 2,685,800 2,679,000 (6,800) -0.3%
Subtotal $31,423,400 $29,038,400 $28,969,900 ($68,500) -0.2%
Transfer 275,000 275,000 230,000 (45,000) -16.4%
Total Revenues $31,698,400 $29,313,400 $29,199,900 ($113,500) -0.4%
FY 2019-20 FY 2020-21
FY 20-21 Draft Budget vs.
FY 19-20 YE Estimate
D-5
revenue could be impacted by the pandemic, however, property tax receipts typically
lag events by 12 to 18 months which means that the effects of the pandemic may not be
seen until FY 2021-22. It appears that the value for homes that have sold this year are
holding, however, more data is still needed. Over the next 6 to 12 months more data
should be available to help staff revise property tax assumptions if necessary.
Property Taxes
FY 2019-20 Current Budget: $13,975,500
FY 2019-20 Year-End Estimate: $13,841,700
FY 2020-21 Draft Budget: $14,129,700
Transient Occupancy Tax (TOT)
TOT is projected to decrease by 10% or ($419,200) from the year-end estimate. The
COVID-19 pandemic forced the closure of Terranea Resort which contributes over 96%
of the City’s total TOT revenue. In mid-March Terranea announced the temporary
closure of their resort and all amenities beginning March 19, 2020. At the time of the
preparation of this staff report, June 12, 2020 is the current scheduled date for the
resumption of operations. However, once Terranea reopens to the public it is not
expected to return to capacity levels seen during similar periods in previous years.
Staff has made significant reductions to TOT revenue estimates for FY 2020 -21, cutting
revenue projections by 70% during the first quarter and 50% during the second quarter.
TOT revenue is not projected to return to normal levels until the start of the third quarter,
January 2021. The City’s TOT revenue estimate was reduced from $5.7 million to just
over $3.7 million, a decrease of nearly $2 million.
Transient Occupancy Tax
FY 2019-20 Current Budget: $5,541,300
FY 2019-20 Year-End Estimate: $4,181,700
FY 2020-21 Draft Budget: $3,762,500
Sales and Use Tax
This revenue category is projected to increase by 2.3% or $52,000 from the year-end
estimate. This projection was developed by staff with the help of the City's Sales Tax
consultant, HdL. All though sales tax revenue is projected to increase in FY 2020-21,
this is in comparison to FY 2019-20 year-end estimates which experienced a 10%
Q1 Q2 Q3 Q4
% of Original FY 19-20 Estimated Revenue 30% 50% 100% 100%
FY 2020-21
D-6
decrease due to the COVID-19 pandemic. The COVID-19 health crisis caused the
temporary closure of Terranea Resort, as mentioned above. Terranea and local
restaurants, which have been significantly impacted as well, comprise nearly half of all
sales tax revenue. A gradual recovery of sales tax revenue is expected as the Stay-at-
Home order is relaxed and as revenue continues to increase from the County Pool due
to increased online retail activity and the impact of the South Dakota v. Wayfair case
provides distribution of online sales tax revenue to local agencies.
Sales and Use Tax
FY 2019-20 Current Budget: $2,529,000
FY 2019-20 Year-End Estimate: $2,260,300
FY 2020-21 Draft Budget: $2,312,300
Permits & Fees
Revenue is projected to remain flat when compared to FY 2019-20 year-end estimates.
The COVID-19 pandemic, Stay-at-Home order, and social distancing measure resulted
in a significant decrease in the number of permits generated and therefore reducing
permit revenue. The Permits & Fees revenue estimates decreased by almost
$350,000.
Permits & Fees
FY 2019-20 Current Budget: $2,167,800
FY 2019-20 Year-End Estimate: $1,819,200
FY 2020-21 Draft Budget: $1,819,200
Franchise Tax
The City receives payments from franchisees for the use of municipal rights-of-way.
This revenue source is primarily received from Southern California Edison and Southern
California Gas Company. The main drivers for this revenue calculation are consumption
and the price of natural gas. Staff uses historical data and industry projections for this
revenue estimate. FY 2020-21 revenue is projected to increase slightly by 0.8% or
$17,500 primarily due to an increase in EDCO trash fees.
Franchise Taxes
FY 2019-20 Current Budget: $2,044,400
FY 2019-20 Year-End Estimate: $2,150,000
FY 2020-21 Draft Budget: $2,167,500
Utility User Tax (UUT)
UUT is projected to remain flat when compared to the FY 2019-20 year-end estimate.
UUT is dependent on outside factors including weather conditions, consumption of
D-7
utilities, natural gas prices and rate increases. It is difficult to predict the impact of these
factors over the long term. Staff used historical data, information available pertaining to
the price of natural gas and the projected increases estimated by the Bureau of Labor
Statistics for the Consumer Price Index for All Urban Consumers (CPI-U) in the
calculation of this projection.
UUT
FY 2019-20 Current Budget: $1,942,300
FY 2019-20 Year-End Estimate: $2,099,700
FY 2020-21 Draft Budget: $2,099,700
Other Taxes & Miscellaneous Revenues
An overall decrease of 0.3% or ($6,800) is projected for FY 2020-21. This revenue
category is comprised of twenty-eight separate revenue sources, the largest being
business license tax, golf tax, interest earnings, and rentals/leases. This is a revenue
source that can be difficult to predict due to the wide variety of revenue sources that are
included in this category. The largest decrease in year-over-year revenue from FY
2019-20 to FY 2020-21 was from miscellaneous revenue which is expected to decrease
by $90,000 due to the final payment from the Green Hills settlement agreement being
received in FY 2019-20. This decrease was expected to be partially offset by an
increases in revenue from program/event fees, traffic tickets, and redevelopment
agency loan repayments.
The Recreation and Parks departments is one of the largest contributors to this revenue
source through rentals/leases, programs/event fees, parking lot fees, and PVIC sales.
As with many of the other revenue sources mentioned in this staff report, it is still too
early to know the full impacts the COVID-19 health crisis will have on this revenue
source. However, revenues across the board in this category are projected to decrease
by over 25% as a result of the health crisis.
These losses were partially offset by a projected increase of $105,700 in the annual
payment received from the Successor Agency. Each fiscal year, the City receives a
portion of the property tax revenue from the area covered by the Successor Agency,
formerly known as the Redevelopment Area (RDA), for the repayment of the
consolidated loans that were made to the RDA for the Portuguese Bend and Abalone
Cove landslide areas. For FY 2020-21, staff provided documentation requesting an
increase in the annual payment which was approved. Staff will continue to monitor and
update the year-end estimates and next year budget accordingly.
Other Taxes & Miscellaneous Revenues
FY 2019-20 Current Budget: $3,223,100
FY 2019-20 Year-End Estimate: $2,685,800
D-8
FY 2020-21 Draft Budget: $2,679,000
Chart 1 – General Fund FY 2020-21 Revenue Budget
Chart 2 – General Fund FY 2020-21 Revenue Budget by Category
D-9
FY 2020-21 General Fund Expenditures
Overall, the General Fund expenditures, including transfers out, are anticipated to
decrease by 12% or ($3.9) million over the FY 2019-20 current budget or a decrease of
1% or ($227,900) over the FY 2019-20 year-end estimates. In light of the financial
impacts of COVID-19, the City’s cost saving measures were necessary to maintain a
healthy fund balance that will support financial sustainability for the City’s future. At the
May 19 meeting, Staff presented the FY 2020-21 Preliminary Budget with a combined
savings and reductions of over $3.9 million when compared to the FY 2019-20 Current
Budget. Of this amount, approximately $1.8 million savings would come from
contracting and consulting services, personnel vacancies, and deferring/suspending
non-essential services. The reduced budget of about $2 million is from decreasing TOT
Transfers to CIP and the remaining $110,000 is from the reduction of Transfers to
Subregion One Fund and Improvement Authority Portuguese Bend. Chart 3 and Table 3
below displays the comparison of the budget for FY 2019-20 Current Budget, FY 2019-
20 Year-End Estimates, and FY 2020-21 Draft Budget.
Chart 3 – Fiscal Year 2019-20 and 2019-20 Draft Budget Comparison
D-10
Table 3 – Fiscal Year 2019-20 and 2020-21 Draft Budget Comparison (Including
Transfers-Out)
Personnel Costs
Salaries and benefits are estimated to increase by 29% or $1.7 million over year-end
estimates. While the comparison between FY2020-21 Draft Budget to FY 2019-20
year-end estimates depicts a significant increase, this is mainly due to the additional
estimated savings of over $2 million identified to end FY 2019-20 as a result of the
COVID-19 health crisis. The majority of the projected personnel savings are a
combination of unspent budget from vacant full-time and part-time positions that were
not filled during the year, savings from the delayed recruitments due to the Stay-at-
Home Order, and savings from park closures and cancellation of special events.
Salaries and Benefits accounts for $11.1 million or $ 31% of the FY 2020-21 Draft
Budget. The City employs approximately 150 full-time and part-time employees, or 74
Full-Time Equivalent (FTE) positions. In FY 2020-21, there are 68 FTE proposed funded
FY 2020-21
Expenditure
FY 19-20
Current Budget
FY 19-20
Year-End
Estimates
FY 20-21
Draft Budget
Salaries 7,621,200$ 6,820,000$ 8,147,800$ 1,327,800$ 16%
Benefits 2,935,900 2,561,400 2,957,200 395,800$ 13%
Sheriff Contract 6,820,500 6,820,500 7,222,400 401,900$ 6%
Preserve 309,500 361,500 - (361,500)$ 0%
Legal Services 905,000 1,089,900 975,000 (114,900)$ -12%
Professional/Technical 3,877,500 3,183,300 2,700,500 (482,800)$ -18%
Repairs & Maintenance 3,632,900 3,192,000 2,780,400 (411,600)$ -15%
Supplies 826,900 666,800 557,600 (109,200)$ -20%
Training/Conference 396,500 244,900 311,400 66,500$ 21%
Emergency
Operation Center - 270,000 - (270,000)$ 0%
Misc. Expenses 1,272,800 1,061,200 1,184,600 123,400$ 10%
Total Operating
Expenditures 28,598,700 26,271,500 26,836,900 565,400 2%
CIP Transfers Out 3,976,900 2,617,300 1,934,000 (683,300)$ -35%
Misc. Transfers Out 140,000 140,000 30,000 (110,000)$ -367%
Total Expenditures 32,715,600$ 29,028,800$ 28,800,900$ (227,900)$ -1%
Variance
FY 20-21 Draft Budget
vs. FY 19-20 Year-End
FY 2019-20
D-11
positions, while freezing the remaining 6 full-time vacant positions for a one-time cost
savings. Additionally, to realize additional savings, of the 68 FTE proposed funded
positions, 6 would be partially funded by staggering the recruitments throughout the
year. In summary, the main assumptions used to develop the Salaries and Benefits in
FY 2020-21 are as follows:
$137,000 for COLA at 1.9%, and $165,400 for merit/merit bonus at an
average of 2.25% (based on the recently adopted MOU for the employee
association).
Savings of ($671,300) for the six (6) unfunded positions - Staff Assistant,
Permit Technician, Assistant Planner, Associate Engineer, Senior Engineer,
and Executive Assistant.
Savings of ($291,800) for the six (6) partially funded positions through
staggered recruitments - Assistant Planner, Associate Planner, Building
Official, Deputy Director of Community Development, Deputy Director of
Finance, and Deputy Director of Public Works.
Savings of ($109,000) for part-time employees by streamlining daily
operations.
Rate increase of 3% in benefits, which include health, dental, and vision.
CalPERS required payment of $683,200 for the Normal Rate. Of this amount,
$291,300 is for Tier 1, $188,800 for Tier 2, and $203,100 for Tier 3. The
amounts include increases of less than 1% for Tier 1 and about 0.7% for Tiers
2 and 3.
CalPERS required payment of $835,200 for Unfunded Liability. Of this
amount, $807,400 is for Tier 1, $15,400 for tier 2, and $12,400 for Tier 3. The
amounts include increases of about 10.7% for Tier 1 and less than 0.6% for
Tiers 2 and 3.
Personnel – Salaries and Benefits
FY 2019-20 Current Budget: $10,557,100
FY 2019-20 YE Estimates: $ 9,381,400
FY 2020-21 Draft Budget: $11,105,000
Public Safety
Public Safety is projected to increase by 6% or $401,900 when compared to both the
current budget and the year-end estimates. The increase would be offset by the savings
of $361,500 from changing the staffing in the Preserve from Deputy Sheriffs to Park
Rangers that started in the middle of FY 2019-20. The significant savings are a result of
ongoing efforts of the City in reducing operational costs. It should also be noted that
Contract Cities and the City have submitted letters to the Los Angeles County Board of
Supervisors requesting to freeze the rate increases of the Sheriff contract in the next
two (2) years because of the financial impacts incurred by cities due to current health
crisis. At this time, the estimated rate increase remains in the budget until the City
receives more information from the Sheriff Department. Staff will report and update the
budget accordingly when more information becomes available.
D-12
Sheriff Contract
FY 2019-20 Current Budget: $6,820,500
FY 2019-20 YE Estimates: $6,820,500
FY 2020-21 Draft Budget: $7,222,400
Sheriff Preserve
FY 2019-20 Current Budget: $309,500
FY 2019-20 YE Estimates: $361,500
FY 2020-21 Draft Budget: $0
Legal Services
The City contracts with the firm of Aleshire & Wynder, LLP for general legal services,
litigation, code enforcement, and labor negotiations. For FY 2020-21, the legal services
are projected to decrease by $12% or ($114,900) when compared to the year-end
estimates. The decreased amount over year-end estimates are mainly from anticipating
lower litigations in FY 2020-21. Additionally, Aleshire & Wynder, LLP have volunteered
to reduce City’s legal costs by rolling down their hourly rates that would save the City of
about $15,000 in FY 2020-21.
Legal Services
FY 2019-20 Current Budget: $905,000
FY 2019-20 YE Estimates: $1,089,900
FY 2020-21 Draft Budget: $975,000
Non-Personnel Costs
Non-personnel costs such as professional/technical services, repair and maintenance,
supplies, training and conferences, and miscellaneous/other expenses are projected to
decrease by 14% or ($1 million) over year-end estimates. The significant decrease is
another result from the City taking the necessary and prudent steps reviewing
operational spending to maximize budget that would not disrupt the current service level
to the community. Each department has carefully reviewed their non-personnel budgets
and identified areas where expenditures could be reduced further due to, among other
things, the decreased in activity caused by the Stay-at-Home Order. The savings are
combination of savings from professional and technical, repairs and maintenance,
supplies and equipment, special events, training, meetings, conferences, and election
costs. A portion of the savings are also from purchase orders that were carried over
from the prior year.
Professional/Technical Services
The Professional/Technical Services category includes specialized consulting services
such as election, grant management, emergency preparedness, information technology,
RPVtv, employment, financial, planning, and engineering. Additionally, this category
include staff augmentation services to address the staffing shortages from the unfilled
D-13
vacant positions. In FY 2019-20, the savings from salaries were offset by approximately
$617,000 from staff augmentation services.
In summary, the Professional/Technical Services is projected to have a net decrease of
18% or ($482,800) to the year-end estimates based on the following main assumptions:
City Clerk – estimated to decrease by $225,000 from year-end. The
decreased is from the lower election costs for the November 2020 election
when compared to the November 2019 election.
Public Works – estimated savings of $301,600 to year-end. The savings
are mainly attributed to augmenting of services including Fuel Modification
and Traffic Safety due to the number of vacancies in the department in FY
2019-20. Additionally, Staff anticipates decreased activity in inspections
and engineering due to the current economic downturn.
Community Development – expected to have a net decrease of $172,000
which is also attributed to the augmentation of planning and building
safety services in FY 2019-20 due to the number of vacancies in the
department. Staff also anticipates decreased permit activities.
The remaining savings are from City Administration and Recreation and
Parks from one-time services in FY2019-20 but will not be needed in FY
2020-21.
Professional/Technical Services
FY 2019-20 Current Budget: $3,877,500
FY 2019-20 YE Estimates: $3,183,300
FY 2020-21 Draft Budget: $2,700,500
Repair/Maintenance Services
This category includes repair and/or maintenance services for City owned properties
and public right-of-way, mainly managed by the Public Works Department. The services
budgeted in General Fund are generally routine repairs and maintenance and for
emergency services including service requests from residents. These services include
annual repairs and maintenance for hardware, software, City Hall, streets, parks, trails,
open space, trees, traffic, storm water, and vehicles. Additionally, the fuel modification
program and City-wide utilities are included in this category.
Overall, Repair/Maintenance is projected to decrease by 15% or ($411,600) to year-
end. The decrease from year-end estimates is primarily due to the one-time grant to
Palos Verdes Peninsula Land Conservancy (PVPLC) for the Fuel Modification program
approved in FY 2019-20 of about $500,000.
D-14
Repair/Maintenance Services
FY 2019-20 Current Budget: $3,632,900
FY 2018-20 YE Estimates: $3,192,100
FY 2020-21 Draft Budget: $2,780,400
Supplies
The Supplies category include office supplies, forms, postage, small tools and
equipment. Overall, Supplies are projected to decrease by 20% or (109,200) to the
year-end estimates. The decrease to both the year-end estimates and the current
budget are from cost saving measures, one-time purchases in the FY 2019-20, and the
purchase orders of carried forward from the prior year.
Supplies
FY 2019-20 Current Budget: $826,900
FY 2019-20 YE Estimates: $666,800
FY 2020-21 Draft Budget: $557,600
Trainings/Meetings/Conferences
This category include expenses related to City-wide trainings, meetings, and
conferences which is projected to increase of 21% or $66,500 to the year-end
estimates. The decrease to the current budget are from cost saving measures and t he
increase from year-end estimates is from cancelled trainings and events in FY 2019-20.
Trainings/Meetings/Conferences
FY 2019-20 Current Budget: $396,500
FY 2019-20 YE Estimates: $244,900
FY 2020-21 Draft Budget: $311,400
Miscellaneous/Other Expense
This category accounts for miscellaneous expense including property insurance
premium payment, one time claim settlements, and any other expenses that are not
categorized in other categories. Overall, Miscellaneous/Other Expenses is estimated to
increase by 10% or $123,400 to the year-end estimates. The decrease to current
budget is from one-time payments from claim settlements in FY 2019-20. The increase
to the year-end estimates is to account for the increase of the City’s California Joint
Powers Authority Property Insurance Premium.
Miscellaneous/Other Expense
FY 2019-20 Current Budget: $1,272,800
FY 2019-20 YE Estimates: $1,061,200
FY 2020-21 Draft Budget: $1,184,600
D-15
Transfers Out
In accordance with City Council Policy No. 41 Reserve Policies, the City transfers the
annual Terranea TOT taxes from General Fund to the CIP Fund. During the FY 2017-
18 Budget Adoption, with the goal to continue to enhance public safety services, the
City Council directed Staff to reduce the TOT transfer to the CIP Fund by the annual
increase in the public safety contract. The transfer for FY 2020-21 is calculated as
follows:
Overall, the CIP Transfers Out is projected to decrease by 35% or ($683,300) to the
year-end estimates mainly due to the closure of the Te rranea Resort as a result of the
Stay-at-Home Order since mid-March.
For the Miscellaneous Transfers Out, an estimated decrease of 367% or ($110,000) to
year-end estimates. The reductions are from the transfers to Subregion One Fund and
Improvement Authority Portuguese Bend due to the interest earned in these funds are
enough to cover the ongoing maintenance needs for FY 2020-21.
Transfers Out
FY 2019-20 Current Budget: $4,116,900
FY 2019-20 YE Estimates: $2,757,300
FY 2020-21 Draft Budget: $1,964,000
The following Charts illustrate the FY 2020-21 Draft Budget by Category in
Expenditures excluding Transfers-Out.
Projected TOT Revenue from Terranea 3,389,300$
Less FY 17-18 Public Safety Increase (893,000)
Less FY 18-19 Public Safety Increase (200,500)
Less FY 19-20 Public Safety Increase (260,800)
Less FY 20-21 Public Safety Increase (101,000)
Proposed TOT Transfer to CIP 1,934,000$
D-16
Chart 4 – Fiscal Year 2020-21 General Fund Draft Budget Expenditures by
Category (Excluding Transfers-Out)
Chart 5 – Fiscal Year 2020-21 General Fund Draft Budget Expenditures by
Department (Excluding Transfers-Out)
D-17
City Council No. 45 Balanced Operating Budget
In accordance with City Council Policy No. 45, the FY 2020-21 General Fund Draft
Budget presented this evening is structurally balanced, where recurring expenditures do
not exceed recurring revenues, and ongoing program expenditures are not funded with
one-time revenue sources. Table 4 below summarizes how one-time and recurring
revenues will offset one-time and recurring expenditures.
Table 4 – General Fund Recurring vs. One-time Revenues and Expenditures
101 - GENERAL FUND
Revenue Type Recurring One-time Total
Property Tax 14,129,700 - 14,129,700
Transient Occupancy Tax 3,762,500 - 3,762,500
Sales Tax 2,312,300 - 2,312,300
Franchise taxes 2,167,500 - 2,167,500
Utility Users Tax 2,099,700 - 2,099,700
Permits & Fees 1,819,200 - 1,819,200
Other Taxes & Misc. Revenues 2,679,000 - 2,679,000
TOTAL REVENUES 28,969,900 - 28,969,900
Expenditure by Program Recurring One-time Total
City Council 102,900 - 102,900
City Attorney 975,000 - 975,000
Public Safety/Law Enforcement 7,381,700 - 7,381,700
City Administration 3,382,000 - 3,382,000
Finance 1,563,500 1,563,500
Community Development 3,128,400 - 3,128,400
Public Works 5,276,400 - 5,276,400
Recreation & Parks 3,197,900 - 3,197,900
Non-department 1,829,100 - 1,829,100
TOTAL EXPENDITURES 26,836,900 - 26,836,900
STRUCTURAL SURPLUS/(DEFICITS) 2,133,000 - 2,133,000
Transfers in 230,000 - 230,000
Transfers out 1,964,000 - 1,964,000
SURPLUS/(DEFICITS) 399,000 - 399,000
FY 2020-21 RECURRING VS. ONE-TIME REVENUES AND EXPENDITURES
D-18
In summary, based on the financial implications of COVID-19, the FY 2020-21 General
Fund budget was prepared with additional attention by finding ways to reduce costs and
preserving a healthy fund balance. As a result, the estimated revenues is approximately
$29.2 million and $28.8 million in expenditures, net of transfers. At the end of June 30,
2021, the General Fund would have an ending balance of $21.4 million, and after
applying the City Council’s reserve policy of $13.4 million, the excess unrestricted
surplus is projected to be approximately $8 million. Table 5 is the summary of the
estimated fund balance by June 30, 2021.
Table 5: FY 2020-21 Estimated Fund Balance
Capital Improvement Program and Special Revenue Funds
Capital Improvement Program:
The City’s CIP is the City’s plan for the infrastructure projects in conjunction with the
City’s General Plan and the City Council’s Goals to identify needed capital projects
based on available sources of revenues. Additionally, the CIP provides the framework
for the City’s management team, Public Works, and the City Council. The City Council-
appointed Infrastructure Management Advisory Committee (IMAC) also assists in the
development and rankings of the CIP list. The CIP projects are funded by the General
Fund TOT transfers (net of public safety increase) and Special Revenue Funds. In light
of COVID-19, the FY 2020-21 budget and the City’s CIP 5-Year Program was prepared
differently based on the available funding sources. Due to the revenue loss in TOT
Taxes, the transfers from General Fund to Capital Infrastructure Projects (CIP) Fund
Post COVID-19
FY 20-21
Proposed Budget
FY 20-21
Draft Budget
FY 20-21
Variances
Beginning Fund Balance - 7/1/2020 20,070,678 21,073,135 1,002,457
Add: Revenues 28,560,300 28,969,900 409,600
Add: Transfers In 230,000 230,000 -
Total Revenues 28,790,300 29,199,900 409,600
Less: Expenditures (27,498,400) (26,836,900) 661,500
Less: Transfers to CIP (1,934,000) (1,934,000) -
Less: Other Transfers Out (90,000) (30,000) 60,000
Total Expenditures (29,522,400) (28,800,900) 721,500
Ending Fund Balance - 6/30/2021 19,338,578 21,472,135 1,131,100
50% Reserve Policy 13,749,200 13,418,450 (330,750)
Unrestricted Excess/(Deficit) Reserve 5,589,378 8,053,685 2,464,307
D-19
were reduced substantially by over $1.3 million in FY 2020-21 and almost $1.8 million in
FY 2020-21.
Based on the direction resulting from the Budget Workshops and the Preliminary
Budget Meeting, sixteen (16) projects are proposed to be funded in the FY 2020-21
Draft Budget. The estimated amount for the projects is approximately $4.3 million that
would be supported by the various funding sources consisting of CIP Fund, Measure R,
Proposition C, and 1911 Act Lighting as presented in the following tables below. No
reserve funds are proposed to fund the CIP projects. The detailed capital project listing
along with related project costs, funding sources and project data sheets are also
attached to this (Attachment B).
Table 6: FY 2020-21 Draft CIP Projects
Table 7: FY 2020-21 Draft CIP Projects – Total By Fund
Project
Code Project Name Fund Fund Name
FY 2020-21
Draft Budget
8301 PVDS Realignment – East End Construction 330 CIP 1,200,000$
8302 Annual Portuguese Vend Landslide Area Resurfacing Program 215 Prop. C 650,000$
8404 Coastal Bluff Fence Replacement Program 330 CIP 200,000$
8421 PVIC Park Improvement Master Plan 330 CIP 50,000$
TBD Nature Preserve Gate for Burma Road Trail 330 CIP 100,000$
TBD Nature Preserve Gate for Rattlesnake Trail 330 CIP 100,000$
8503 Civic Center Master Plan 330 CIP 151,000$
8504 Citywide ADA Transition Plan 330 CIP 150,000$
87xx Storm Drain Improvement at 6415 Corsini – Engineering 330 CIP 20,000$
87xx Altamira Canyon Drainage and Erosion Control Project 330 CIP 350,000$
8004 Public Signs Replacement Program 330 CIP 50,000$
8801 Sidewalk Repair and Replacement Program 220 Measure R 250,000$
8837 Traffic Signal Light at PVDS and PVDE 215 Prop. C 295,000$
8838 Traffic Signal Light at Hawthorne Blvd. and Via Riveria 211 1911 Act 342,000$
TBD Western Ave. Beautification – Engineering 330 CIP 150,000$
TBD PVDE Widening and Path Improvements at Bronco - Engineering 220 Measure R 200,000$
TOTAL FY 2020-21 CAPITAL IMPROVEMENT PROGRAM 4,258,000$
Fund Fund Name
FY 2020-21
Draft Budget
330 CIP 2,521,000$
215 Prop. C 945,000$
220 Measure R 450,000$
211 1911 Act 342,000$
Total 4,258,000$
D-20
The estimated CIP fund balance at June 30, 2021, is estimated to be over $24.2 million
less the Council Required Policy reserve of $3.0 million results in an estimated excess
surplus of $21.2 million (Table 8).
Table 8 – Summary of FY 2020-21 Fund Balance - CIP Projects
Special Revenues:
Special Revenues are used to account for taxes and other revenues set aside for a
specific or restricted purposes. The City’s major special revenue funds are Gas Tax,
Proposition A, Proposition C, Measure R, and Measure M and Quimby. Most of the
funding for special revenues are designated fo r street maintenance, public right of way
maintenance, park upgrades, park maintenance, and transit related expenses. Staff
ensures that the special revenue funds are utilized for any qualified project before CIP
reserves are appropriated.
Equipment Replacement:
The Equipment Replacement Fund (ERF) is an internal service fund that is used to
accumulate funding to replace City equipment, furniture, and vehicles at the end of the
designated life cycle. The City Council policy for this fund is to maintain a fund balance
equivalent to the replacement value of all items that are at the end of their life cycle.
This fund continues to operate with a balanced budget and with an excess fund
balance, therefore Staff is recommending the annual charges for equipment
replacement in FY 2020-21 to be at 25% funding for a total of $93,300. The projected
fund balance at June 30, 2021, is almost $2.2 million and the replacement value at June
Capital
Infrastructure Measure R Proposition C 1911 Act
Beginning Fund Balance - 7/1/20 24,342,991 984,844 630,419 1,170,808
Add: Revenues 460,200 545,400 702,400 628,200
Add: Transfers In 1,934,000 - - -
Total Revenues 2,394,200 545,400 702,400 628,200
Less: Capital Projects (2,521,000) (450,000) (945,000) (342,000)
Less: Operating Expenses - - (347,100)
Less: Transfers Out - -
Total Expenditures (2,521,000) (450,000) (945,000) (689,100)
Estimated Ending Fund Balance - 6/30/21 24,216,191 1,080,244 387,819 1,109,908
Reserve Policy 3,000,000
Excess Reserve 21,216,191 1,080,244 387,819 1,109,908
D-21
30, 2021, is estimated to be $2 million for an excess accumulation of almost $138,000.
Based on this analysis the ERF will still be overfunded at the end of FY2020 -21. The
expenditures scheduled for replacement in FY 2020 -21 total approximately $650,000 or
32% of the total replacement value. Items aren’t replaced solely based on the schedule,
but are reviewed by Staff to determine their current status and the need for
replacement.
Below is a summary of the estimated FY 2020-21 fund balances for the Capital
Infrastructure Program Fund, Special Revenue Funds, and Equipment Replacement
Fund. These fund balance amounts are based on estimated project costs, equipment
needs and other non-General Fund expenditures expected next year.
Table 9 – Capital Improvement Program, Equipment Replacement, and Special
Revenues Fund Balance
Lastly, the next table is a budget summary of the City’s FY 2021-21 Draft Budget for all
funds.
Capital
Infrastructure
Equipment
Replacement Special Revenues
Beginning Fund Balance - 7/1/20 24,342,991 2,679,042 10,328,723
Add: Revenues 460,200 138,300 5,571,900
Add: Transfers In from General Fund 1,934,000 10,000
Total Revenues 2,394,200 138,300 5,581,900
Less: Expenditures (2,521,000) (650,000) (5,662,100)
Less: Transfers Out (230,000)
Total Expenditures (2,521,000) (650,000) (5,892,100)
Estimated Ending Fund Balance - 6/30/21 24,216,191 2,167,342 10,018,523
Reserve Policy 3,000,000 2,029,500 952,180
Excess Reserve 21,216,191 137,842 9,066,343
D-22
Table 10– FY 2020-21 Draft Budget Summary – All Funds
Review of Utility Users Tax
Municipal Code Section 3.30.190 requires that the City Manager submit to the City
Council analysis of the revenues derived from the Utility User Tax (UUT) annually.
Based on the needs of the City, the City Council shall determine if any modification to
the tax rate is appropriate, or if the UUT is unnecessary. The tax rate cannot be
increased without a majority vote of the residents of the City during a Municipal Election.
The projected FY 2020-21 UUT revenue is approximately $2.1 million (or approximately
7% of total General Fund revenue). Based upon the operating and capital needs of the
City, Staff recommends that the City Council accept that the current UUT rate of 3%
Fund Balance Fund Balance
Fund 6/30/2020 Revenues Transfers In Expenditures Transfers Out 6/30/2021
General Fund Balance 21,073,135 28,969,900 230,000 26,836,900 1,964,000 21,472,135
Restricted Amount (Policy Reserve)(13,135,756) (13,418,450)
General Fund Unrestricted Balance 7,937,380 28,969,900 230,000 26,836,900 1,964,000 8,053,685
Restricted by Council Action
CIP 24,342,991 460,000 1,934,000 2,521,000 - 24,215,991
EQUIPMENT REPLACEMENT 2,679,042 138,300 - 650,000 - 2,167,342
Subtotal of Restricted by Council Action 27,022,033 598,300 1,934,000 3,171,000 - 26,383,333
Restricted by Law or External Agencies
GAS TAX 94,814 1,462,000 - 1,162,000 - 394,814
1972 ACT 28,384 - - - - 28,384
EL PRADO LIGHTING 34,475 2,500 - 800 - 36,175
CDBG (131,103) 217,700 150,600 - (64,003)
1911 ACT 1,170,808 628,200 - 689,100 - 1,109,908
WASTE REDUCTION 334,497 131,000 - 287,500 - 177,997
AIR QUALITY MANAGEMENT 102,012 55,000 - 57,000 - 100,012
PROPOSITION C 630,419 702,400 945,000 - 387,819
PROPOSITION A 1,999,772 849,400 - 776,600 - 2,072,572
PUBLIC SAFETY GRANTS 76,041 157,700 - - 130,000 103,741
MEASURE R 984,844 545,400 - 450,000 - 1,080,244
MEASURE M 37,707 530,000 - 536,000 - 31,707
HABITAT RESTORATION 785,018 12,400 - 184,900 - 612,518
SUBREGION 1 MAINTENANCE 773,920 14,000 10,000 41,600 - 756,320
MEASURE A 57,918 91,000 - - 100,000 48,918
ABALONE COVE SEWER DISTRICT 178,484 52,000 146,000 - 84,484
GINSBURG CULTURAL ARTS BUILDING - - - - - -
DONOR RESTRICTED CONTRIBUTIONS 767,832 25,000 - 25,000 - 767,832
QUIMBY 1,277,833 25,000 - - - 1,302,833
LOW-MOD INCOME HOUSING 235,060 46,200 - - - 281,260
AFFORDABLE HOUSING IN LIEU 853,837 15,000 - - - 868,837
ENVIRONMENTAL EXCISE TAX 236,563 10,000 - 210,000 - 36,563
BIKEWAYS - - - - - -
Subtotal Restricted by Law 10,328,723 5,571,900 10,000 5,662,100 230,000 10,018,523
GRAND TOTAL GOVERNMENT FUNDS 45,288,135 35,140,100 2,174,000 35,670,000 2,194,000 44,455,541
CITY OF RANCHO PALOS VERDES
FY 2020-21 FUND SUMMARY
FY20-21 Estimated Resources FY20-21 Estimated Appropriations
D-23
continue for FY 2020-21.
ADDITIONAL INFORMATION:
On May 14 and 21, 2020, a public notice was published in the Peninsula News for
tonight’s and June 16 public hearings on the City Council’s consideration to adopt the
FY2020-21 budget and CIP. To date, we have received one public comment from Ms.
Sunshine regarding the FY 2020-21 draft budget. Ms. Sunshine inquired on what is and
isn’t in the draft budget. Staff has responded to the comment and a copy is attached to
this staff report, Attachment C. If comments are received after the transmittal of this staff
report, they will be provided to the City Council as late correspondence the night of the
public hearing.
CONCLUSION:
As a result of the City’s long history of fiscal responsibility and maintaining healthy fund
balances, the City would be able to continue to end FY 2019-20 with an excess
unrestricted surplus of $7.9 million. The surplus will increase to over $8 million at the
end of FY 2020-21, after applying the 50% City Council’s Policy Reserve of $13.1
million. This is an improvement of over $2.4 million since the Budget Workshops in April
and Preliminary Budget Meeting in May. The CIP Fund will end FY2019-20 with fund
balance of $24.3 and estimated to end FY 2020-21 at $24.2 million. The Equipment
Replacement Fund and all Special Revenues Funds are estimated to end FY 2019-20
with healthy fund balances and will be able to support operating expenditures. The
Equipment Replacement Fund is estimated to have a fund balance of almost $2.2
million and all other Special Revenue Funds are estimated at over $10.2 million at the
end FY 2020-21. In closing, it is important to note that while the City projects healthy
fund balances by June 30, 2021, there are still many unknown information today that
would predict actual future financial impacts from the COVID-19 pandemic. The City will
remain fiscally prudent and Staff will continue to monitor the financials and report any
updated information during the mid-year report in February/March of 2021.
Any direction from the City Council based on the figures presented in this report will be
incorporated in the FY 2020-21 Final Budget that Staff will be presenting at a duly
noticed public hearing to be held by the City Council on June 16, 2020.
ALTERNATIVES:
In addition to the Staff recommendation, the following alternative action is available for
the City Council’s consideration:
1. Discuss and take other action related to this item.
D-24
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
GENERAL FUND
PROPERTY TAXES
3102-3103 Property Tax 7,114,319 7,840,208 8,236,989 8,338,300 8,553,800
3107 Property Tax in Lieu of Sales 332,296 - - - -
3107 Property Tax in Lieu of VLF 4,432,363 4,663,495 4,920,186 5,117,200 5,275,900
3108 Redevelopment Property Tax Trust 23,668 33,760 50,255 55,600 25,000
3110 Property Transfer Tax 443,174 490,796 359,706 330,600 275,000
TOTAL PROPERTY TAXES 12,345,820 13,028,259 13,567,136 13,841,700 14,129,700
OTHER TAXES
3101 Golf Tax 365,259 402,732 429,049 323,300 300,300
3111 Franchise Taxes 1,984,878 2,128,727 2,149,743 2,150,000 2,167,500
3112 Sales and Use Tax 2,383,705 2,437,988 2,575,202 2,180,000 2,240,000
3113 Sales Tax - PW (PSAF)78,743 82,079 85,979 80,300 72,300
3114-3117 Utility Users Tax 1,775,433 1,837,690 1,917,107 2,099,700 2,099,700
3120-3121 Transient Occupancy Tax 5,600,867 5,615,044 5,645,497 4,181,700 3,762,500
3210 Business License Tax 904,107 887,276 945,792 800,300 865,300
TOTAL OTHER TAXES 13,092,992 13,391,536 13,748,369 11,815,300 11,507,600
OTHER LICENSE & PERMIT
3202 Building & Safety Permits 1,063,530 1,209,868 1,152,758 969,500 969,500
3203 Building & Safety Plan Check 360,349 353,155 393,433 308,400 308,400
3205 Film Permits 43,724 37,125 2,930 30,700 30,700
3206 Animal Control Fees 36,470 31,835 31,365 27,400 27,400
3207 Building & Safety Fees 1,912 858 1,367 3,000 3,000
3208 Building & Safety State Building Standard 79 660 (521) 4,300 4,300
3209 Building & Safety Geology Fees 173,041 132,649 128,272 112,900 112,900
3212 Business License Penalty - 5,784 12,501 18,300 17,900
3213 Parking Permits 690 330 440 500 500
3214 Parking Decals 683 665 988 300 300
3215 Plan & Zone Permits 345,749 341,424 401,764 271,200 271,200
3216 Plan - Investigation 16,165 3,076 - - -
3217 View Restoration Fees 7,719 - 5,106 4,800 4,800
3218 Plan - Misc. Fees - 8,572 7,769 8,000 8,000
3218 Plan - Historical Data Fees 17,176 - - - -
3219 Right of Way Permits 72,142 77,689 74,329 74,600 74,600
3220 Dumpster Permits 1,078 4,018 4,606 3,600 3,600
TOTAL OTHER LICENSE & PERMIT 2,140,507 2,207,708 2,217,106 1,837,500 1,837,100
FINES & FORFEITURES
3501 Tow Fees - 8,383 6,225 5,800 5,800
3502 False Alarm Fines 2,500 11,400 18,200 4,800 4,800
3503 Misc. Court Fines 140,414 91,165 91,460 61,800 61,800
4140-3504 Code Enforcement Citations - 32,805 12,674 15,100 15,000
TOTAL FINES & FORFEITURES 142,914 143,753 128,558 87,500 87,400
RENTALS
3602 Rent - Rec & Parks 2,157 - - - -
5120-3602 Rent - Other Recreational Facilities - 1,314 1,421 5,000 4,800
5130-3602 Rent - Hesse Park 52,013 15,431 44,485 28,600 14,600
5140-3602 Rent - Ryan Park 14,346 43,647 19,595 10,800 4,600
5150-3602 Rent - Ladera Linda 19,132 8,799 6,971 3,100 3,100
5180-3602 Rent - PVIC 199,233 208,603 235,056 152,900 152,900
0000-3602 Rent - Citywide 173,140 226,798 171,200 141,300 141,300
TOTAL RENTALS 460,021 504,592 478,729 341,700 321,300
INTERESTS 107,867 206,893 366,409 323,200 280,000
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
D-25
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
CHARGES FOR SERVICES
3401 Engineering Fees 2,706 198 - - -
5160-3411 Shoreline Parking Lot Fees 261,692 245,941 215,341 154,400 138,000
5120-3412 Program/Event Fees - 5,799 8,374 6,200 5,200
5131-3412 Program/Event Fees - 30,410 63,361 38,800 34,600
5170-3412 Program Fees 7,364 5,557 5,972 8,000 8,000
5190-3412 REACH - Program Fees 7,918 10,456 13,305 2,800 1,000
3906 Sale of Signs/Services 1,150 150 - - -
TOTAL CHARGES FOR SERVICES 280,830 298,511 306,353 210,200 186,800
INTERGOVERNMENTAL REVENUE
3301 Federal Grant Income - 64,483 - - -
3302 Grant Income - - 1,359 - -
3302 Motor Vehicle in Lieu 19,282 17,121 - - -
TOTAL INTERGOVERNMENTAL 19,282 81,604 1,359 - -
OTHER REVENUE
3801 Special Fund Administration 155,800 89,700 169,356 139,700 150,000
5120-3901 Donations - Britton Memorial 132 - - - -
5170-3901 Donations - Special Events - 5,400 4,700 3,800 3,800
5180-3901 Donations - PVIC 14,166 11,667 8,411 8,500 5,400
5190-3901 Donations - REACH 2,946 372 1,244 1,000 800
3901 Donations - General - 1 - - -
3902 CASP Fees 1,215 4,253 7,604 4,500 4,500
3904 RDA Loan Payment 177,186 117,694 139,938 193,100 298,800
3908 Successor Agency Adminstration 6,807 50,000 - - 16,000
5180-3701 PVIC Gift Shop 26,677 136,013 137,551 79,200 79,200
1430-3999 Misc. Revenues - 1,640 2,600 1,500 1,500
3999 Misc. Revenues 284,500 173,007 405,626 150,000 60,000
TOTAL OTHER REVENUE 669,429 589,747 877,030 581,300 620,000
TOTAL OPERATING REVENUE 29,259,662 30,452,603 31,691,049 29,038,400 28,969,900
INTER-FUND TRANSFERS
Transfer In Public Safety Grant 100,000 140,000 130,000 175,000 140,000
Transfer in Measure A Maintenance 90,000 90,000 90,000 100,000 90,000
TOTAL TRANSFERS IN 190,000 230,000 220,000 275,000 230,000
TOTAL GENERAL FUND 29,449,662 30,682,603 31,911,049 29,313,400 29,199,900
ALL OTHER FUNDS
STATE GAS TAX FUND
INTERGOVERNMENTAL REVENUE
3304 State Gas Tax - 2103 114,879 167,001 142,726 291,520 291,500
3305 State Gas Tax - 2105 241,844 232,717 234,405 190,160 190,200
3306 State Gas Tax - 2106 145,849 144,561 144,587 116,080 116,100
3307 State Gas Tax - 2107 306,619 302,867 294,790 249,680 249,700
3308 State Gas Tax - 2107.5 6,000 6,000 6,000 4,800 4,800
3309 State Gas Tax - 2031 - 197,680 837,064 565,680 565,700
TOTAL INTERGOVERNMENTAL REVENUE 815,191 1,050,826 1,659,572 1,417,920 1,418,000
CHARGES FOR SERVICE
3404 Sidewalk Repair - - - - -
OTHER REVENUE
3999 Misc. Revenues 17,653 63,892 48,179 38,560 38,600
INTEREST -
3601 Interest on Investments 6,870 918 7,466 5,440 5,400
TOTAL STATE GAS TAX FUND 839,714 1,115,636 1,715,217 1,461,920 1,462,000
D-26
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
1972 ACT FUND
OTHER TAXES
3102 Assessments 260,037 - - - -
INTEREST -
3601 Interest on Investments 545 333 541 - -
TOTAL 1972 ACT FUND 260,582 333 541 - -
EL PRADO FUND
OTHER TAXES
3102 Assessments 2,402 2,564 2,782 2,300 2,300
INTEREST
3601 Interest on Investments 180 345 600 200 200
TOTAL EL PRADO FUND 2,582 2,909 3,382 2,500 2,500
1911 ACT FUND
OTHER TAXES
3102 Assessments 632,874 659,534 694,107 606,800 606,800
INTEREST
3601 Interest on Investments 13,292 24,921 37,878 21,200 21,400
TOTAL 1911 ACT FUND 646,166 684,455 731,985 628,000 628,200
BEAUTIFICATION FUND
INTEREST
3601 Interest on Investments 3,268 5,652 - - -
TOTAL EL PRADO FUND 3,268 5,652 - - -
WASTE REDUCTION FUND
INTERGOVERNMENTAL REVENUE
3302 Used Oil Payment 33,973 10,920 22,644 22,100 22,100
3705 Reimbursement LA County TRAP - - - - -
TOTAL INTERGOVERNMENTAL 33,973 10,920 22,644 22,100 22,100
CHARGES FOR SERVICE
3406 AB 939 Fees 187,036 219,802 188,142 93,300 104,300
INTEREST
3601 Interest on Investments 3,144 5,281 8,680 4,600 4,600
TOTAL WASTE REDUCTION FUND 224,153 236,003 219,466 120,000 131,000
AIR QUALITY MANAGEMENT FUND
INTERGOVERNMENTAL REVENUE
3303 AB 2766 Revenue 54,963 54,916 55,414 50,000 50,000
INTEREST
3601 Interest on Investments 613 949 1,413 5,000 5,000
TOTAL AQMD FUND 55,576 55,865 56,827 55,000 55,000
PROPOSITION "C" TRANSPORTATION FUND
INTERGOVERNMENTAL REVENUE
3303 Proposition "C" Sales Tax 645,099 665,051 714,128 696,200 696,200
INTEREST
3601 Interest on Investments 3,835 8,257 15,733 6,200 6,200
TOTAL PROPOSITION "C" FUND 648,934 673,308 729,861 702,400 702,400
D-27
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
PROPOSITION "A" TRANSPORTATION FUND
INTERGOVERNMENTAL REVENUE
3303 Proposition "A" Sales Tax 776,681 802,855 860,943 839,400 839,400
OTHER REVENUE
3999 Misc Revenues 1,675,000 - - - -
INTEREST
3601 Interest on Investments 8,012 26,968 38,887 10,000 10,000
TRANSFERS IN
9101 Transfer in from State Grants - - 300,000 - -
TOTAL PROPOSITION "A" FUND 2,459,693 829,823 1,199,830 849,400 849,400
PUBLIC SAFETY FUND
INTERGOVERNMENTAL REVENUE
3302 CA Brulte (COPS)129,324 139,416 148,747 150,000 150,000
INTEREST
3601 Interest on Investments 603 1,227 2,116 7,700 7,700
TOTAL PUBLIC SAFETY FUND 129,927 140,643 150,863 157,700 157,700
MEASURE "R" TRANSIT SALES TAX FUND
INTERGOVERNMENTAL REVENUE
3303 Measure "R" Sales Tax 483,294 498,787 535,750 522,200 522,200
INTEREST
3601 Interest on Investments 13,110 27,599 34,139 23,200 23,200
TOTAL MEASURE "R" FUND 496,404 526,386 569,889 545,400 545,400
MEASURE "M" TRANSIT SALES TAX FUND
INTERGOVERNMENTAL REVENUE
3303 Measure "M" Sales Tax - 452,015 603,557 529,500 529,500
INTEREST
3601 Interest on Investments - 1,205 1,365 500 500
TOTAL MEASURE "M" FUND - 453,220 604,922 530,000 530,000
HABITAT RESTORATION FUND
INTERGOVERNMENTAL REVENUE
3302 State Grant Income 6,729 433 - - -
INTEREST
3601 Interest on Investments 8,682 13,707 19,953 15,000 12,400
OTHER REVENUES
3999 Misc Revenues 4,769 - - - -
TOTAL HABITAT RESTORATION FUND 20,180 14,140 19,953 15,000 12,400
SUBREGION 1 FUND
INTEREST
3601 Interest on Investments 5,307 9,364 14,969 15,000 14,000
CHARGES FOR SERVICE
3907 Developer Fees - 22,716 - - -
TRANSFERS IN
9101 Transfer in from General Fund - 41,500 - 35,000 10,000
TOTAL SUBREGION 1 FUND 5,307 73,580 14,969 50,000 24,000
MEASURE A FUND
INTERGOVERNMENTAL REVENUE
3303 Measure A 192,598 46,848 86,634 90,000 90,000
INTEREST
3601 Interest on Investments 295 1,184 1,648 1,100 1,000
TOTAL MEASURE A FUND 192,893 48,032 88,282 91,100 91,000
D-28
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
ABALONE COVE SEWER MAINTENANCE FUND
OTHER TAXES
3102 Assessments 54,836 56,578 50,672 61,100 50,000
INTEREST
3601 Interest on Investments 786 2,856 6,407 2,000 2,000
TRANSFERS IN
9101 Transfer in from General Fund 208,000 208,000 - - -
9330 Transfer in from Infrastructure - - - - -
TOTAL ABALONE COVE SEWER MAINT. FUND 263,622 267,434 57,079 63,100 52,000
GINSBURG CULTURAL ARTS BUILDING
INTEREST
3601 Interest on Investments 587 1,045 - - -
TOTAL GINSBURG CULTURAL ARTS FUND 587 1,045 - - -
DONOR RESTRICTED DONATIONS FUND
INTEREST
3601 Interest on Investments 5,966 10,738 16,090 25,000 25,000
OTHER REVENUE
3901 Donations - Restricted 10,500 20,500 44,523 - -
2999-3901 Donations - City's Anniversary - 15,000 - - -
TOTAL DONOR RESTRICTED DONATIONS FUND 16,466 46,238 60,613 25,000 25,000
COMMUNITY DEVELOPMENT BLOCK GRANT FUND
INTERGOVERNMENTAL REVENUE
3301 Grant Income 142,317 223,613 178,591 139,300 217,700
TOTAL CDBG FUND 142,317 223,613 178,591 139,300 217,700
CAPITAL IMPROVEMENT FUND
INTERGOVERNMENTAL REVENUE
3301 Federal Grant - - 5,007 - -
3302 State Grant - - - - -
3303 Local Grant 143,064 - - - -
TOTAL INTERGOVERNMENTAL REVENUE 143,064 - 5,007 - -
INTEREST
3601 Interest on Investments 191,721 303,781 508,963 506,200 460,000
OTHER REVENUE
3999 Misc Revenues - - - - -
TRANSFERS IN
9101 Transfer in from General Fund 4,141,397 4,526,000 4,301,852 2,617,300 1,934,000
9331 Transfer in from Federal Grants - - 1,087,318 98,300 -
TOTAL TRANSFERS IN 4,141,397 4,526,000 5,389,170 2,715,600 1,934,000
TOTAL CAPITAL IMPROVEMENT FUND 4,476,182 4,829,781 5,903,140 3,221,800 2,394,000
FEDERAL GRANTS
INTERGOVERNMENTAL REVENUE
3301 Federal Grant - 1,235,012 141,442 - -
INTEREST
3601 Interest on Investments - 6,799 - - -
TOTAL FEDERAL GRANTS FUND - 1,241,811 141,442 - -
STATE GRANTS
INTERGOVERNMENTAL REVENUE
3302 State Grant - - 144,320 - -
TOTAL STATE GRANTS FUND - - 144,320 - -
D-29
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF REVENUES - ALL FUNDS
FISCAL YEAR 2020-2021
QUIMBY FUND
CHARGES FOR SERVICE
3907 Quimby Developer Fee 50,929 38,223 - - -
INTEREST
3601 Interest on Investments 16,505 21,048 33,272 52,000 25,000
TOTAL QUIMBY FUND 67,434 59,271 33,272 52,000 25,000
CITY LOW-MOD INCOME HOUSING FUND
INTEREST
3601 Interest on Investments 764 1,770 2,956 1,500 3,000
OTHER REVENUES
3904 RDA Loan Payment - - - 43,200 43,200
3999 Misc Revenues 36,860 - - - -
PROPERTY TAX
3108 Redevelopment Property Tax Trust 5,917 14,712 34,984 - -
TOTAL CITY LOW-MOD INCOME HOUSING FUND 43,541 16,482 37,940 44,700 46,200
AFFORDABLE HOUSING PROJECTS FUND
INTEREST
3601 Interest on Investments 4,034 7,457 15,961 15,000 15,000
CHARGES FOR SERVICE
3907 Developer Fees - 221,818 - - -
TOTAL AFFORDABLE HOUSING PROJECTS FUND 4,034 229,275 15,961 15,000 15,000
ENVIRONMENTAL EXCISE TAX (EET)
CHARGES FOR SERVICE
3907 EET Developer Fee 95,991 156,065 39,020 - -
INTEREST
3601 Interest on Investments 1,899 4,655 9,399 25,000 10,000
TOTAL QUIMBY FUND 97,890 160,720 48,419 25,000 10,000
TDA ARTICLE 3 - SB 821 BIKEWAY FUND
INTERGOVERNMENTAL REVENUE
3303 TDA Article 3 - SB 821 - 82,500 - - -
TOTAL TDA ARTICLE 3 FUND - 82,500 - - -
WATER QUALITY/FLOOD PROTECTION FUND
INTEREST
3601 Interest on Investments 35,274 28,934 - - -
CHARGES FOR SERVICES
3402 Storm Drain User Fees 14,436 - - - -
INTERGOVERNMENTAL REVENUE
3302 State Grant Income - - 200,000 - -
TOTAL WATER QUALITY FUND 49,710 28,934 200,000 - -
EQUIPMENT REPLACEMENT FUND
CHARGES FOR SERVICE
3803 Interfund Charges 82,050 300,900 300,900 84,800 93,300
TOTAL CHARGES FOR SERVICE 82,050 300,900 300,900 84,800 93,300
INTEREST
3601 Interest on Investments 19,164 29,919 50,259 52,150 45,000
TOTAL EQUIPMENT REPLACEMENT FUND 101,214 330,819 351,159 136,950 138,300
TOTAL OTHER FUNDS REVENUES 11,248,376 12,377,908 13,277,923 8,931,270 8,114,200
TOTAL CITY REVENUES 40,698,038 43,060,511 45,188,972 38,244,670 37,314,100
D-30
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
TRANSFERS OUT 4,387,397 4,813,500 4,346,852 2,757,300 1,964,000
CITY COUNCIL 139,806 107,310 96,251 98,459 102,900
CITY ATTORNEY 1,173,168 1,157,585 1,160,193 1,089,916 975,000
PUBLIC SAFETY
Sheriff 5,451,056 6,223,715 6,407,659 6,820,500 7,222,400
Special Programs 821,653 1,029,299 703,365 590,527 160,300
TOTAL PUBLIC SAFETY 6,272,709 7,253,014 7,111,024 7,411,027 7,382,700
CITY ADMINISTRATION
City Manager 783,077 899,709 802,974 708,621 795,300
City Clerk 484,381 595,565 449,731 764,119 638,700
Community Outreach 74,448 74,465 62,246 63,900 68,300
Emergency Preparedness 161,607 145,801 103,417 61,900 158,400
Emergency Operation Center - - - 269,798 -
RPVtv 169,004 203,701 179,549 193,108 229,700
Human Resources 364,246 373,704 302,545 357,866 316,000
Information Technology - Data 889,924 1,012,124 928,886 1,032,740 1,081,800
Information Technology - Voice 100,933 93,138 96,277 112,000 110,000
TOTAL CITY ADMINISTRATION 3,027,620 3,398,207 2,925,625 3,564,052 3,398,200
FINANCE
Finance 1,265,590 1,349,974 1,502,164 1,616,603 1,565,100
TOTAL FINANCE 1,265,590 1,349,974 1,502,164 1,616,603 1,565,100
NON-DEPARTMENT
Non-departmental 2,400,364 1,166,153 1,133,907 1,207,209 1,874,700
TOTAL NON-DEPARTMENT 2,400,364 1,166,153 1,133,907 1,207,209 1,874,700
COMMUNITY DEVELOPMENT
Administration 547,072 670,903 525,754 604,200
Planning 1,322,813 688,279 835,015 775,043 840,000
Building & Safety 773,627 791,009 826,228 664,723 787,200
Code Enforcement 116,264 183,129 184,457 227,087 295,600
View Restoration 302,403 394,012 321,836 372,028 359,300
NCCP - 16,870 11,445 15,000 50,000
Geology 148,448 115,578 107,253 100,000 100,000
Animal Control - - 89,842 120,000 109,000
TOTAL COMMUNITY DEVELOPMENT 2,663,555 2,735,949 3,046,979 2,799,635 3,145,300
PUBLIC WORKS
Public Works Administration 2,175,728 2,157,495 2,155,312 2,070,095 2,095,500
Traffic Management 391,742 485,705 418,941 270,500 304,800
Storm Water Quality 230,695 310,929 535,921 529,700 506,000
Building Maintenance 448,843 597,137 453,631 548,100 529,000
Parks Maintenance 585,191 670,000 702,000
Street Landscape Maintenance 425,073 573,849 181,000 181,000
Trails & Open Space Maintenance 838,107 935,465 404,279 546,550 334,800
Fuel Modification 1,010,000 554,500
Vehicles Maintenance 418 40,694 41,641 49,500 47,000
Sewer Maintenance 951 1,554 22,550 45,000 35,000
TOTAL PUBLIC WORKS 4,086,484 4,954,052 5,191,315 5,920,445 5,289,600
CITY OF RANCHO PALOS VERDES
STATEMENT OF EXPENDITURES - ALL FUNDS
FISCAL YEAR 2020-2021
D-31
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF EXPENDITURES - ALL FUNDS
FISCAL YEAR 2020-2021
RECREATION AND PARKS
Recreation Administration 873,450 1,042,367 1,026,224 942,604 1,088,000
Other Recreational Facilities 166,130 34,650 64,466 5,697 1,000
Fred Hesse Jr. Park 158,196 215,126 187,970 182,085 181,800
Robert E. Ryan Park 99,820 83,568 92,393 84,967 86,700
Ladera Linda Community Center 75,109 76,440 86,410 73,353 67,600
Abalone Cove Shoreline Park 91,173 139,626 135,175 136,179 155,300
Special Events and Programs 146,374 188,264 194,344 156,173 209,700
Point Vicente Interpretive Center 447,107 471,653 513,920 462,256 550,400
REACH 39,683 64,370 69,327 23,179 71,700
Support Services 74,468 40,978 29,084 20,026 21,000
City Run Sports - 5,659 3,066 4,518 4,900
Contract Classes - 21,649 41,695 55,000 50,000
Volunteer Program - - - 6,000 7,000
Park Rangers - - - 142,661 308,300
Eastview - 4,952 7,354 62,609 67,900
Open Space Management 3,592 104,013 235,721 206,859 232,100
TOTAL RECREATION & PARKS 2,175,102 2,493,315 2,687,149 2,564,166 3,103,400
TOTAL GENERAL FUND 27,591,795 29,429,059 29,201,459 29,028,812 28,800,900
ALL OTHER FUNDS
STATE GAS TAX
Street Pavement Maintenance 365,074 205,666 256,454 150,000 150,000
Street Landscape Maintenance 1,121,909 676,964 508,460 656,460 942,000
Traffic Signal Maintenance 10,175 10,000 16,770 - -
Portuguese Bend Rd. Maintenance - - 48,867 50,000 70,000
Street Maintenance (CIP)442,622 471,592 - 1,395,380 -
TOTAL STATE GAS TAX 1,939,780 1,364,222 830,551 2,251,840 1,162,000
1972 ACT
Street Lights Maintenance 264,903 - - - -
Transfers Out - - - - -
TOTAL 1972 ACT 264,903 - - - -
EL PRADO 237 493 593 800 800
1911 ACT
Street Lights Maintenance 459,441 566,480 536,861 399,902 347,100
Capital Improvements - 48,105 856,683 516,902 342,000
Transfers Out - - - - -
TOTAL 1911 ACT 459,441 614,585 1,393,544 916,804 689,100
BEAUTIFICATION
Operating Expenses - - - - -
Street Maintenance - - - - -
Capital Improvements - 106,283 383,737 - -
Transfers Out - - - - -
TOTAL BEAUTIFICATION - 106,283 383,737 - -
WASTE REDUCTION
Operating Expenses 231,578 244,656 212,991 239,578 287,500
Transfers Out - - - - -
TOTAL WASTE REDUCTION 231,578 244,656 212,991 239,578 287,500
D-32
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF EXPENDITURES - ALL FUNDS
FISCAL YEAR 2020-2021
AIR QUALITY
Operating Expenses 78,284 49,995 50,000 50,000 57,000
Transfers Out - - - - -
TOTAL AIR QUALITY 78,284 49,995 50,000 50,000 57,000
PROP "C" TRANSPORTATION
Street Maintenance - - - - -
Traffic Maintenance 66,699 9,081
Street Maintenance (CIP)539,740 599,924 572,312 640,000 945,000
Transfers Out - - - - -
TOTAL PROPOSITION "C"539,740 599,924 639,011 649,081 945,000
PROP "A" TRANSPORTATION
Dial-a-Ride 613,003 630,334 705,644 774,100 776,600
Capital Projects 10,581 496,443 44,108 454,852 -
Transfers out - - - - -
TOTAL PROPOSITION "A"623,584 1,126,777 749,752 1,228,952 776,600
PUBLIC SAFETY
Transfers out 100,000 140,000 130,000 175,000 130,000
TOTAL PUBLIC SAFETY 100,000 140,000 130,000 175,000 130,000
MEASURE R
Street Landscape Maintenance 169,952 - 28,032 250,000
Capital Projects - 2,036,294 113,705 450,000
Transfers out - - - - -
TOTAL MEASURE R 169,952 - 2,064,326 363,705 450,000
MEASURE M
Repairs & Maintenance - 448,464 565,972 536,000 536,000
Capital Projects - - - -
Transfers out - - - - -
TOTAL MEASURE M - 448,464 565,972 536,000 536,000
HABITAT RESTORATION 140,825 150,633 149,499 179,500 184,900
SUBREGION 1 35,107 36,228 43,831 41,400 41,600
MEASURE A
Transfers out 90,000 90,000 90,000 100,000 100,000
TOTAL MEASURE A 90,000 90,000 90,000 100,000 100,000
ABALONE COVE SEWER MAINTENANCE 163,615 118,188 49,925 221,570 146,000
GINSBURG CULTURAL ARTS BUILDING - 86,344 1,045 -
DONOR RESTRICTED DONATIONS
Operating Expenses 9,760 46,724 31,259 28,000 25,000
Capital Improvements - - 137,683 4,331 -
Transfers out - - - - -
TOTAL DONOR RESTRICTED DONATIONS 9,760 46,724 168,942 32,331 25,000
COMMUNITY DEVELOPMENT BLOCK GRANT 142,317 194,556 193,586 281,861 150,600
D-33
PROJECTED DRAFT
ACTUALS ACTUALS ACTUALS YEAR-END BUDGET
FY 2016-17 FY 2017-18 FY 2018-19 FY 2019-20 FY 2020-21
CITY OF RANCHO PALOS VERDES
STATEMENT OF EXPENDITURES - ALL FUNDS
FISCAL YEAR 2020-2021
CAPITAL IMPROVEMENT PROGRAM FUND
Administration 15,341 - - 35,313
Street Improvements 6,385,358 6,911,774 1,862,690 4,193,214 200,000
Parks, Trails & Open Space Improvements 231,565 425,485 215,942 373,324 450,000
Sewer Improvements 198,900 - - 41,291 -
Building Improvements 31,423 9,000 135,649 266,450 301,000
Storm Water Quality Improvements - - 157,319 598,270 370,000
Landslide Improvements 242,935 157,349 37,132 388,138 1,200,000
Transfers Out - - - - -
TOTAL CAPITAL IMPROVEMENT 7,105,522 7,503,608 2,408,733 5,896,000 2,521,000
FEDERAL GRANTS
Capital Improvements - 197,621 - -
Transfers Out - - 1,087,318 98,315 -
TOTAL FEDERAL GRANTS - 197,621 1,087,318 98,315 -
STATE GRANTS
Capital Improvements - - 163,796 200,428 -
Transfers Out - - 300,000 - -
TOTAL STATE GRANTS - - 463,796 200,428 -
QUIMBY
Capital Improvements 80,550 562,680 142,004 475,259 -
Transfers Out - - - - -
TOTAL QUIMBY 80,550 562,680 142,004 475,259 -
ENVIRONMENTAL EXCISE TAX (EET)
Street Landscape Maintenance 75 - - 300,000 210,000
Transfers Out - - - - -
TOTAL ENVIRONMENTAL EXCISE TAX (EET)75 - - 300,000 210,000
TDA ARTICLE 3 - SB 821 BIKEWAY FUND
Capital Improvements - 82,500 - - -
Transfers Out - - - - -
TOTAL TDA ARTICLE 3 - SB 821 BIKEWAY - 82,500 - - -
WATER QUALITY/FLOOD PROTECTION
Operating Expenses - - - - -
Capital Improvements 1,399,913 1,070,747 811,110 - -
Transfers Out - - - - -
TOTAL WATER QUALITY/FLOOD PROTECTION 1,399,913 1,070,747 811,110 - -
EQUIPMENT REPLACEMENT 734,172 203,283 452,376 529,170 650,000
EMPLOYEE BENEFITS - - - - -
TOTAL ALL OTHER FUNDS 14,309,355 14,952,167 13,167,941 14,768,639 9,063,100
TOTAL ALL FUNDS 41,901,150 44,381,226 42,369,400 43,797,451 37,864,000
D-34
FY 2020-21 Draft 5-year Capital Improvement Program
Project
Code Project Fund FY 20-21 FY 21-22 FY 22-23 FY 23-24 FY 24-25 TBD
Abalone Cove Sanitary Sewer
Maintenance System
8202 Abalone Cove Sanitary Sewer System
Rehabilitation Program - Construction 225 - Ab Cove Sewer - 450,000 650,000 - -
Total Abalone Cove Sanitary Sewer
Maintenance System - 450,000 650,000 - - -
Palos Verdes Drive South (PVDS)
Landslide
8301 PVDS Realignment - East End
Construction 330 - CIP Fund 1,200,000
8302 Annual Portuguese Bend Landslide
Area Resurfacing Program 215 - Prop C 650,000 650,000 700,000 700,000 750,000
Total PVDS Landslide 1,850,000 650,000 700,000 700,000 750,000 -
Park Sites
8404 Coastal Bluff Fence Replacement
Program 330 - CIP Fund 200,000 200,000
8418 Hesse Park Parking Lot & Lighting
Improvements Project - Construction 330 - CIP Fund - 750,000
8419 Hesse Park Athletic Field Improvement
Project 330 - CIP Fund - 392,420
8421 PVIC Park Improvements - Master Plan 330 - CIP Fund 50,000
8421 PVIC Park Improvements 330 - CIP Fund - 700,000
Parking Lot Lighting Improvements at
Point Vicente Interpretive Center (PVIC)211 - 1911 Act 50,000
Lower Hesse Park Improvements 330 - CIP Fund 1,500,000
Restoration of "Bubbles" Statue 330 - CIP Fund 200,000
Total Park Sites 250,000 50,000 - - - 3,742,420
Trails
Nature Preserve Gate for Burma Road
Trail 330 - CIP Fund 100,000
Nature Preserve Gate for Rattlesnake
Trail 330 - CIP Fund 100,000
Total Trails 200,000 - - - - -
Public Buildings
8507 PVIC Lift Station Upgrade 330 - CIP Fund - 30,000 200,000
8503 Civic Center Master Plan 330 - CIP Fund 151,000
8504 Citywide ADA Transition Plan 330 - CIP Fund 150,000
Restroom Improvements (indoor &
outdoor) at PVIC 330 - CIP Fund 150,000
Civic Center (the Storm Room)
Improvements 330 - CIP Fund 100,000
Total Public Buildings 301,000 150,000 - 30,000 200,000 100,000
Storm Water System - Stormwater
Quality
8701 Storm Drain Lining Program 330 - CIP Fund - 450,000
8711 Bayend Drive Catch Basin Inlets and
Storm Sewer Lateral - Construction 330 - CIP Fund - 170,000
8713 Upper Point Vicente Stormwater Runoff
Control Project (Helipad)330 - CIP Fund - 200,000
8714 Crest Road to Crestridge Canyon Storm
Drain Project - Engineering 330 - CIP Fund -
8714 Crest Road to Crestridge Canyon Storm
Drain Project - Construction 330 - CIP Fund - 1,285,000
8715
Storm Drain Deficiency Improvement
(PVDS at Peppertree Dr. and
Hawthorne Blvd. near Hawkhurst) -
Construction
330 - CIP Fund - 2,750,000
8716
Hawthorne: Via de la Vis Shadow
Wood; Amber Sky; Middlecrest;
Oceanaire; Rue La Fleur; PVDS;
Sasilina at Hawksmoor; Via Colinita;
Vista Mesad; Via Colinita; Kingsridge -
Engineering
330 - CIP Fund - 250,000 -
8716
Hawthorne: Via de la Vis Shadow
Wood; Amber Sky; Middlecrest;
Oceanaire; Rue La Fleur; PVDS;
Sasilina at Hawksmoor; Via Colinita;
Vista Mesad; Via Colinita; Kingsridge -
Construction
330 - CIP Fund - 2,100,000 -
DRAFT 5-YR CAPITAL IMPROVEMENT PROGRAM
W:\Finance Mgmt\Budget\Budget 2021\2020-06-02 Budget Hearing\Final SR\Attachment B_2020-21 Draft 5 Year CIP.xlsx Printed: 5/20/2020 12:06 PMD-35
FY 2020-21 Draft 5-year Capital Improvement Program
Project
Code Project Fund FY 20-21 FY 21-22 FY 22-23 FY 23-24 FY 24-25 TBD
DRAFT 5-YR CAPITAL IMPROVEMENT PROGRAM
8717
Crestridge; Lightfoot; Via Colinita; Knoll
View; Deluna; Schooner; Via Cambron;
PVDW; Northern S. Western Ave;
PVDS - Engineering
330 - CIP Fund - 350,000 -
8717
Crestridge; Lightfoot; Via Colinita; Knoll
View; Deluna; Schooner; Via Cambron;
PVDW; Northern S. Western Ave;
PVDS - Construction
330 - CIP Fund - 3,330,300
Storm Drain Improvement at 6415
Corsini 330 - CIP Fund 20,000 250,000
Altamira Canyon Drainage and Erosion
Control Project 330 - CIP Fund 350,000
Total Storm Water Quality 370,000 3,000,000 - 250,000 2,450,000 5,435,300
Right of Way and Traffic Control
Devices
8001 Pavement Management Program
Triennial Update 330 - CIP Fund - 120,000 - - 120,000
8004 Public Signs Replacement Program 330 - CIP Fund 50,000 250,000 -
8801 Sidewalk Repair and Replacement
Program 220 - Measure R 250,000 250,000 250,000 250,000
8808 Crenshaw Blvd - Arterial Roads Rehab
Project - Construction 330 - CIP Fund - 2,000,000
8809 Western Ave Traffic Congestion
Improvements - Construction 330 - CIP Fund - 3,200,000
8811 Arterial Fences and Walls Standards -
Citywide Master Plan 330 - CIP Fund - 25,000
8811 Arterial Fences and Walls Standards -
Citywide Engineering (Phase 2)330 - CIP Fund - 75,000
8811 Arterial Fences and Walls Standards -
Citywide Construction (Phase 3)330 - CIP Fund - 1,000,000
8828 PVDS Intersections Improvement 330 - CIP Fund - 750,000
8837 Traffic Signal Light @ PVDS & PVDE 215 - Prop C 295,000
8838 Traffic Signal Light @ Hawthorne & Via
Rivera 211 - 1911 Act 342,000
8816 Residential Street Rehabilitation
Program Areas 1 - Engineering 220 - Measure R - 200,000
8816 Residential Street Rehabilitation
Program Areas 1 - Construction 330 - CIP Fund - 2,361,600 -
8826 Residential Street Rehabilitation
Program Areas 2 - Engineering 220 - Measure R - 305,700
8826 Residential Street Rehabilitation
Program Areas 2 Construction 330 - CIP Fund - 2,200,800 -
8834 Residential Street Rehabilitation
Program Areas 3&4 - Engineering 330 - CIP Fund - .318,700
8834 Residential Street Rehabilitation
Program Areas 3&4 - Construction 330 - CIP Fund - 3,605,000
8815 Residential Street Rehabilitation
Program Area 5 - Engineering 220 - Measure R - 200,000
8815 Residential Street Rehabilitation
Program Area 5 - Survey 220 - Measure R - 150,000
8815 Residential Street Rehabilitation
Program Area 5 - Construction 330 - CIP Fund - 2,198,800
8836 Residential Street Rehabilitation
Program Areas 6 - Engineering 220 - Measure R - 305,700
Western Ave Beautification
(Engineering)330 - CIP Fund 150,000
PVDE Widening and Path
Improvements at Bronco 220 - Measure R 200,000 1,300,000 -
PVDS Rehabilitation 330 - CIP Fund - 500,000
Indian Peak Road Rehabilitation 330 - CIP Fund - 500,000
PVDW Pedestrian Crossing 330 - CIP Fund - 1,000,000
PVDE Rehabilitation 330 - CIP Fund - 2,000,000
Silver Spur Road Rehabilitation 330 - CIP Fund - 2,000,000
Ganado Drive Beautification 330 - CIP Fund - 100,000
Total R/W and TCD 1,287,000 5,845,000 4,523,800 3,817,300 3,076,500 10,273,700
4,258,000 10,145,000 5,873,800 4,797,300 6,476,500 19,551,420 Total Approved Projects
W:\Finance Mgmt\Budget\Budget 2021\2020-06-02 Budget Hearing\Final SR\Attachment B_2020-21 Draft 5 Year CIP.xlsx Printed: 5/20/2020 12:06 PMD-36
FY 2020-21 Draft 5-year Capital Improvement Program
DRAFT 5-YR CAPITAL IMPROVEMENT PROGRAM
FY 20-21 FY 21-22 FY 22-23 FY 23-24 FY 24-25 TBD
202 - Gas Tax - - - - - -
211 - 1911 Act 342,000 50,000 - - - -
215 - Prop C 945,000 650,000 700,000 700,000 750,000 -
216 - Prop A - - - - - -
220 - Measure R 450,000 1,500,000 250,000 455,700 755,700 250,000
225 - Ab Cove Sewer - 450,000 650,000 - - -
228 - Donor Restricted - - - - - -
310 - CDBG - - - - - -
330 - CIP Fund 2,521,000 7,495,000 4,273,800 3,641,600 4,970,800 19,301,420
332 - State Grants - - - - - -
334 - Quimby - - - - - -
4,258,000 10,145,000 5,873,800 4,797,300 6,476,500 19,551,420
W:\Finance Mgmt\Budget\Budget 2021\2020-06-02 Budget Hearing\Final SR\Attachment B_2020-21 Draft 5 Year CIP.xlsx Printed: 5/20/2020 12:06 PMD-37
1
Trang Nguyen
From:Trang Nguyen
Sent:Tuesday, May 26, 2020 11:26 AM
To:SUNSHINE
Cc:CC; CityClerk
Subject:RE: What is and isn't in the draft budget?
Good morning Ms. Sunshine,
The FY 19-20 budget is available on the City’s website. You can click on this link
http://rpvca.gov/DocumentCenter/View/14760/FY19-20-Adopted-Budget-PDF?bidId= to view the
budget book. The details of the budget are in the justification pages for each department. For FY 20-
21, the City has completed two budget workshops that included a review of the General Fund and the
Capital Improvement Program, held a preliminary budget meeting, and there will be public hearings
on June 2 and June 16. You can also view all the staff reports (April 13, April 27, May 19) related to
budget at http://rpvca.gov/772/City-Meeting-Video-and-Agendas. The FY 20-21 budget book with
details will be available at the end of August. As for who will be notified if the work is not funded, the
City Council and the public will be notified if a program is not being funded during the budget process.
Any projects that come up after the budget process will be taken to the City Council for
consideration.
Please contact me if you have any additional questions.
Thank you for your continuous support and I hope you had a wonderful weekend.
Trang Nguyen
Director of Finance
___________________________________
30940 Hawthorne Blvd.
Rancho Palos Verdes, CA 90275
310-544-5278 (telephone)
310-544-5293 (fax)
tnguyen@rpvca.gov
www.rpvca.gov
City Hall is open to the public during regular business hours. To help prevent the spread of COVID-
19, visitors are required to wear face coverings and adhere to physical distancing guidelines. Some
employees are working on rotation and may be working remotely. If you need to visit City Hall, please
schedule an appointment in advance by calling the appropriate department and follow all posted
directions during your visit. Walk-ups are limited to one person at a time. Please note that our
D-38
2
response to your inquiry could be delayed. For a list of department phone numbers, visit the Staff
Directory on the City website.
From: SUNSHINE <sunshinerpv@aol.com>
Sent: Monday, May 25, 2020 12:37 PM
To: Trang Nguyen <Tnguyen@rpvca.gov>
Cc: CC <CC@rpvca.gov>; CityClerk <CityClerk@rpvca.gov>
Subject: What is and isn't in the draft budget?
Hello Trang,
I am writing directly to you because at this late stage in the FY 20-21 Budget process, I still can't find
whether or not certain "action Items" are adequately funded. It appears that each Item requires Staff
Time from multiple departments/divisions and there is no identified "holder of the purse strings" to
make sure that work is coordinated in a timely and cost-effective manner. Please advise how I can
look up what was in the FY 19-20 Budget and what is proposed for FY 20-21. Who should get a
"heads up" if this work is not funded? TNX. Sunshine 310-377-8761
1. Living Documents. Our General Plan, Coastal Specific Plan, Parks Master Plan, Trails Network
Plan and now our Natural Communities Conservation Plan, all contain "Goals and
Policies". Whenever progress toward a Goal is made, particularly when the recording of a document
with the LA County Recorder or a "Ribbon Cutting Ceremony takes place, the primary Document is to
be wordsmithed/updated and official maps, GIS'd.
2. Encroachment Permits. Public Works has a document called the ENCROACHMENT PERMITS
MAP. It is not "lot specific". It divides the City into nine "Project Areas". Recently, I have seen a
computer-generated map with similar City divisions for Residential Roadway Rehabilitation which
impacts a lot of encroachments. Also, Staff has been working on updating the Trails Network Plan
which includes a Conceptual Trails Plan (CTP) that divides the City into five Areas. Given that the
preponderance of the non-motorized circulation in RPV is under the management of the Public Works
Department, it has been suggested that the trails and the roadways preservation and enhancement
activities use the same "Project Areas Map". Council has requested a focused area study on our
encroachment history and policies. The northern portion of Palos Verdes Drive East is in the CTP's
area five and the Encroachment Permit's area 8. This portion of PVDE is not covered in the City's
STREET STANDARDS STUDY. All this info is to be integrated and available via our GIS data base
and web site.
3. Non-motorized circulation and emergency preparedness infrastructure maintenance. Some of this
is covered by the Infrastructure Management Advisory Committee's priority
recommendations. Smaller projects/needs/wants are to be included with the design/scope of work of
proposed projects which impact the same geographic area. For instance, Altamira Canyon erosion
control, Abalone Cove habitat planting, California Coastal Trail blufftop trail completion across
D-39
3
Altamira Canyon and landslide remediation are all being pursued on essentially the same five acres
of City owned land.
Subject: More on ROW encroachments, NOW
Date: 5/24/2020 8:34:35 PM Pacific Standard Time
From: sunshinerpv@aol.com
To: cc@rpvca.gov, cityclerk@rpvca.gov
Cc: trodrigue@rpvca.gov, jyoon@rpvca.gov
Sent from the Internet (Details)
Hello Council Members,
There is an urgent matter coming back to the Planning Commission. This is a residential
development application which has been in "the system" so long that Staff asked the Commission to
ask the Applicant for a time extension rather than deny the project.
28160 PVDE is either the result of a City Planner working in a vacuum or a City Planner being
directed to move the project forward without consideration for the community she works for. Either
way, driveways onto an arterial highway, permits for permanent encroachments in the public ROW,
no consideration for off-road circulation, no proposal for traffic calming, conflicting codes for grading
on extreme slopes, no early consultation with trail user advisors, no comment on Wildfire
Management and Fire Department input on only the access to the structure, not to mention all the
requests for variances for other "wants"… does not make for a "quality project".
Since this lot did not get declared "unbuildable" when the application first arrived at the Planning
counter, I sure hope that our City Attorney can come up with a way for the Planning Commission to
get us out of this jam. Then, I hope that there is funding in the proposed FY20-21 budget for the
Public Works Dept to get a grip on the day to day needs for our City's infrastructure to be "preserved
and enhanced" as a residential community as opposed to just a nature preserve here in paradise.
D-40
4
Tick tock, …S
D-41
This project consists of engineering, realigning and reconstructing
approximately 900 feet of the Palos Verdes Drive South roadway, at
the east end of the Portuguese Bend Landslide, to relocate the section
of roadway back into the public right-of-way and to eliminate an
unsafe “S” configuration that has developed as a result of the
landslide..
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $1,000,000 $150,000 $0 $0 $0 $0 $0 $1,150,000
Contingency $0 $50,000 $0 $0 $0 $0 $0 $50,000
Inspection $0 $0 $0 $0 $0 $0 $0 $0
$1,000,000 $200,000 $0 $0 $0 $0 $0 $1,200,000
Funding
330 (CIP) $1,000,000 $200,000 $1,200,000
$1,000,000 $200,000 $1,200,000
Estimated annual operating cost $650,000
Estimated Schedule:
Construction in Fiscal Year 2020-21.
Project Location Map Background:
Due to the land movement associated with the Portuguese Bend
Landslide, this portion of the road has encroached onto private
property and developed an unsafe “S” configuration that requires
elimination. The project will also accommodate required drainage
runoff of the area.
Justification:
Having the public right-of-way on private property may expose the
City to potential liability claims. Furthermore, properly aligning the
roadway may minimize the potential for traffic collisions.
E-1
As part of this annual program, this project consists of patching cracks
and surface repairs, on an as-needed basis, to the Palos Verdes Drive
South roadway throughout the fiscal year in response to damage
caused by the Portuguese Bend landslide.
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 N/A $0
Engineering $0 $0 $0 $0 $0 $0 N/A $0
Environmental $0 $0 $0 $0 $0 $0 N/A $0
Management $0 $0 $0 $0 $0 $0 N/A $0
Construction $0 $650,000 $650,000 $700,000 $700,000 $750,000 N/A $3,450,000
Contingency $0 $0 $0 $0 $0 $0 N/A $0
Inspection $0 $0 $0 $0 $0 $0 N/A $0
$0 $650,000 $650,000 $700,000 $700,000 $750,0000 N/A $3,450,000
Funding
215 (Prop. C) $0 $650,000 $650,000 $700,000 $700,000 $750,000 $3,450,000
$0 $650,000 $650,000 $700,000 $700,000 $750,000 $3,450,000
Estimated annual operating cost $650,000
Estimated Schedule:
Routine resurfacing occurs in response to damage caused by the Portuguese Bend Landslide,
and is an annual budget item (Fiscal Years 2020-21, 2021-22, 2022-23, 2023-24 and 2024-25 are shown
here).
Project Location Map Background:
The City annually budgets for necessary patching and repairs to the
Palos Verdes Drive South roadway within the landslide, and is
expected to continue to do so until landslide movement in this area
can be controlled.
Justification:
The City is required to properly maintain the roadway, and repairs,
such as resurfacing, are required to mitigate impacts to public safety
caused by the land movement in this area.
E-2
As part of the Coastal Bluff Replacement Program, this project
consists of replacing the section of deteriorating metal-pipe fencing
along the Seascape Trail and Golden Cove Trail in the Vicente Bluffs
Reserve with new 3-rail, colored, precast concrete ranch rail fencing
to match the adjacent new coastal bluff fence section.
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $303,981 $175,000 $0 $0 $0 $0 $175,000 $853,981
Contingency $0 $0 $0 $0 $0 $0 $0 $0
Inspection $22,926 $25,000 $0 $0 $0 $0 $25,000 $72,926
$326,907 $200,000 $0 $0 $0 $0 $200,000 $926,907
Funding
330 (CIP) $326,907 $200,000 $200,000 $926,907
$326,907 $200,000 $200,000 $926,907
Estimated annual operating cost $5,000
Estimated Schedule:
Phase 1 (at PVIC) installed approximately 1,579 feet of new fence in 2018.
Phase 2 (at three locations in Abalone Cove) installed approximately 4,325 feet of new fence in 2019.
Phase 3 (in the Vicente Bluffs Reserve) is to install approximately 4,500 feet of new fence in 2020.
Construction of Phase 4 is deferred to a Fiscal Year to be determined.
Project Location Map Background:
Prior to establishing this project, the City was receiving a growing
number of complaints about the safety of the rusting and
deteriorating nature of the existing metal pipe coastal bluff fencing.
Justification:
This project increases the safety and aesthetics of the public trails
along the City’s bluffs.
E-3
This project consists of:
Creating a Master Plan for the upper section of the PVIC lot
Installing a new, paved parking lot (in the general area where
the “overflow” parking lot exists)
Constructing new outdoor restrooms
Creating new trails, picnic areas and outlooks
Planting grassland areas and additional landscaping
Establishing locations for an Interactive Exhibit Program
(IEP) that will include four exhibits and be designed,
constructed and paid for by Los Serenos de Point Vicente
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $50,000 $0 $0 $0 $0 $0 $50,000
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0
Contingency $0 $0 $0 $0 $0 $0 $0 $0
Inspection $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0
Funding
330 (CI) $50,000 $50,000
$50,000 $50,000
Estimated annual operating cost Not Applicable
Estimated Schedule:
Master Plan work to be completed in Fiscal Year 2020-21.
Engineering and Construction is deferred to a Fiscal Year to be determined.
Project Location Map Background:
On November 20, 2012, the City Council adopted amendments to
the RPV Coast Vision Plan (adopted 9/2/2008) which replaced the
Annenberg Foundation project. An update to the Parks Master Plan
was adopted in October 2015, and Los Serenos de Point Vicente
presented a proposal for a Lower Point Vicente Concept Site Plan
in 2016.
Justification:
On August 2, 2016 the City Council directed staff to work with Los
Serenos de Point Vicente to seek public input.
In April 2017, the City Council modified the Parks and Recreation
Vision Plan for Lower Point Vicente and added the Interactive
Outdoor Educational Exhibits Concept Plan.
This project provides the proper infrastructure for those exhibits.
E-4
This project consists of improvements to secure the main entry point
to the Portuguese Bend Reserve of the Palos Verdes Nature Preserve,
at the entrance to the Burma Road Trail, including:
A five feet (5’) wide, black wrought iron, powered,
automatically timed, swing gate with a panic bar
A pair of seven feet (7’) wide, black wrought iron, swing
gates, with a multi-entity locking mechanism, to secure the
vehicle access
New black wrought iron fencing to secure the gate perimeters
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $100,000 $0 $0 $0 $0 $0 $100,000
Contingency $0 $0 $0 $0 $0 $0 $0 $0
Inspection $0 $0 $0 $0 $0 $0 $0 $0
$0 $100,000 $0 $0 $0 $0 $0 $100,000
Funding
330 (CIP) $100,000 $100,000
$100,000 $100,000
Estimated annual operating cost $500
Estimated Schedule:
Construction in Fiscal Year 2020-21.
Project Location Map Background:
It is important to prevent pedestrian traffic into the Portuguese Bend
Reserve at times, such as after sunset and after heavy rainfall, to
protect the Reserve and the quality of life of neighboring residents.
The existing gate, at the entrance of the Burma Road Trail, does not
adequately close the Preserve from pedestrian traffic when
warranted.
Justification:
A new gate will enhance the security of the Portuguese Bend Reserve
of the Palos Verdes Peninsula Nature Preserve and improve the
aesthetic nature of a heavily visited entrance to the Preserve. It will
enable staff to better manage the Preserve.
E-5
This project consists of improvements to secure the main entry point
to the Filiorum Reserve of the Palos Verdes Nature Preserve,
including:
Two hundred and fifty feet (250’) of new green, wrought iron
fence and decorative brick pilasters, matching the adjacent
fence of the Island View Homeowner Association (HOA),
along Crenshaw Boulevard and along the east side of the
downslope to the existing trail head
A five foot (5’) wide, powered, automatically timed, swing
gate with a panic bar
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $100,000 $0 $0 $0 $0 $0 $100,000
Contingency $0 $0 $0 $0 $0 $0 $0 $0
Inspection $0 $0 $0 $0 $0 $0 $0 $0
$0 $100,000 $0 $0 $0 $0 $0 $100,000
Funding
330 (CIP) $100,000 $100,000
$100,000 $100,000
Estimated annual operating cost $500
Estimated Schedule:
Construction in Fiscal Year 2020-21.
Project Location Map Background:
It is important to prevent pedestrian traffic into the Portuguese Bend
Reserve at times, such as after sunset and after heavy rainfall, to
protect the Reserve and the quality of life of neighboring residents.
Access to the trailhead of the Rattlesnake Trail is currently provided
only by an opening in the fence along Crenshaw Boulevard.
Justification:
Enhances security of the Portuguese Bend Reserve of the Palos
Verdes Peninsula Nature Preserve. It will enable staff to better
manage the Preserve.
E-6
This project consists of preparing supporting documents and
providing services towards the future development of a Master Plan
for the Upper Pointe Vicente property for the purpose of Civic Center
and open space improvements.
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $17,639 $151,000 $0 $0 $0 $0 $0 $168,639
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0
Contingency $0 $0 $0 $0 $0 $0 $0 $0
Inspection $0 $0 $0 $0 $0 $0 $0 $0
$17,639 $151,000 $0 $0 $0 $0 $0 $168,639
Funding
330 (CIP) $17,639 $151,000 $168,639
$17,639 $151,000 $168,639
Estimated annual operating cost Not Applicable
Estimated Schedule:
The Request For Proposal (RFP) for Engineering Services is under review by the Civic Center Advisory
Committee. The final RFP is estimated to be advertise in FY 2020-21.
Project Location Map Background:
As part of the City’s update to the Parks Master Plan, site specific
workshops are being held to receive community input regarding
desired uses at the park. A Master Plan will be created that
represents the interests of the residents. The Civic Center Advisory
Board was created to advise and to provide recommendations to the
City Council.
Justification:
A Master Plan serves as a framework to major components or
elements for the City Council’s consideration and could include a
variety of uses as recommended by the community through the
advisory committee.
E-7
This project consists of updating the current ADA (Americans with
Disabilities) Transition Plan, which identifies all of the ADA
deficiencies at City facilities and within the public right-of-way and
outlines a plan to make improvements to eliminate those deficiencies
through future projects. Work is being performed through the CJPIA
(California Joint Powers Insurance Authority), resulting in lower
costs.
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $66,450 $150,000 $0 $0 $0 $0 $0 $216,450
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0
Contingency $0 $0 $0 $0 $0 $0 $0 $0
Inspection $0 $0 $0 $0 $0 $0 $0 $0
$66,450 $150,000 $0 $0 $0 $0 $0 $216,450
Funding
330 (CIP) $66,450 $150,000 $216,450
$66,450 $150,000 $216,450
Estimated annual operating cost $
Estimated Schedule:
Work began in Fiscal Year 2019-20 and will be completed in Fiscal Year 2020-21.
Project Location Map Background:
Under Title II of the Americans with Disabilities Act, the City is
required to have a current Self-Evaluation and Transition Plan.
Justification:
The City may be at significant risk for claims and litigation, as well
as place the City at risk of losing or not being able to receive state
and federal pass-through funding, if it does not have a current plan.
E-8
This project consists of:
replacing the existing catch basin
replacing the existing broken pipe
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 $0 $0
Engineering $0 $20,000 $0 $0 $0 $0 $0 $20,000
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $240,000 $0 $0 $0 $0 $240,000
Contingency $0 $0 $0 $0 $0 $0 $0 $0
Inspection $0 $0 $10,000 $0 $0 $0 $0 $10,000
$0 $20,000 $250,000 $0 $0 $0 $0 $270,000
Funding
330 (CIP) $20,000 $250,000 $270,000
$20,000 $250,000 $270,000
Estimated annual operating cost $500
Estimated Schedule:
Engineering in Fiscal Year 2020-21.
Construction in Fiscal Year 2021-22.
Project Location Map Background:
The existing storm sewer pipe has breaks in it and the catch basin is
deteriorating
Justification:
Although no flooding currently occurs on private property, this
project will properly convey the storm water runoff that is collected
by the catch basin at this location.
E-9
This project consists of three phases, as follows:
Phase 1
Reviewing a previous study of a portion of the water shed
Performing an engineering analysis of the entire Altamira
Canyon and its tributaries
Establishing a priority for improvements
Phase 2
Preparing detailed plans for mitigation measures
Phase 3
Construction of the mitigation measures
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $350,00 $0 $0 $0 $0 $0 $350,000
Engineering $0 $0 $0 $0 $0 $0 TBD TBD
Environmental $0 $0 $0 $0 $0 $0 TBD TBD
Management $0 $0 $0 $0 $0 $0 TBD TBD
Construction $0 $0 $0 $0 $0 $0 TBD TBD
Contingency $0 $0 $0 $0 $0 $0 TBD TBD
Inspection $0 $0 $0 $0 $0 $0 TBD TBD
$0 $350,000 $0 $0 $0 $0 TBD TBD
Funding
330 (CIP) $350,000 TBD
$350,000 TBD
Estimated annual operating cost TBD
Estimated Schedule:
Project Study Report (Phase 1) in Fiscal Year 2020-21.
Project Location Map Background:
The canyon has been eroding for the last several years
Justification:
This study is needed to identify measures to mitigate the erosion of
the Altamira Canyon which poses a public safety concern to public
and private property.
E-10
This project consists of replacing traffic signs, including regulatory
signs, guide signs, warning signs, object marker signs and other signs
that were identified in 2017 as required, in three phases as follows:
Phase 1
Signs to be replaced in FY 2019-20
Phase 2
Signs to be replaced in FY 2020-21
Phase 3
Signs to be replaced in FY 2021-22
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 $0 $0
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 $0 $0
Construction $125,502 $45,000 $240,000 $0 $0 $0 $0 $410,502
Contingency $0 $0 $0 $0 $0 $0 $0 $0
Inspection $25,600 $5,000 $10,000 $0 $0 $0 $0 $40,600
$151,102 $50,000 $250,000 $0 $0 $0 $0 $451,502
Funding
330 (CIP) $151,102 $50,000 $250,000 $451,502
$151,102 $50,000 $250,000 $451,502
Estimated annual operating cost $3,000
Estimated Schedule:
Phase 1 in FY 2019-20
Phase 2 in FY 2020-21
Phase 3 in FY 2021-22
Project Location Map Background:
The City received an assessment report on its traffic sign inventory
in December 2017, which recommended a signage
replacement/update program over the next five years.
The 458 signs identified as needing replacement within 1-2 years
(from 2017) are addressed with this project, as the City has replaced
the signs that required immediate replacement in 2020,
Justification:
Roadway signs are required to comply with FHWA and California
Manual on Uniform Traffic Control Devices (MUTCD) standards,
including retro-reflectivity. This project is necessary for the City’s
roadway signs to be in compliance with applicable standards and
reduce City liability in the event of traffic accidents and improving
public safety.
E-11
T
This project consists of repairing and replacing identified sidewalk
segments in the public right-of-way on a biennial schedule.
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 N/A $0
Engineering $0 $0 $0 $0 $0 $0 N/A $0
Environmental $0 $0 $0 $0 $0 $0 N/A $0
Management $0 $0 $0 $0 $0 $0 N/A $0
Construction $ $240,000 $0 $240,000 $0 $240,000 N/A $
Contingency $0 $0 $0 $0 $0 $0 N/A $0
Inspection $0 $10,000 $0 $10,000 $0 $10,000 N/A $
$ $250,000 $0 $250,000 $0 $250,000 N/A $
Funding
220 (Measure R) $ $250,000 $250,000 $250,000 $
$ $250,000 $250,000 $250,000 $
Estimated annual operating cost TBD
Estimated Schedule:
Construction in Fiscal Year 2020-21
Construction in Fiscal Year 2022-23
Construction in Fiscal Year 2024-25
Project Location Map Background:
Under this biennial program, the City removes and replaces
identified broken sections of sidewalk city-wide.
Justification:
Repair and replacement will reduce potential of injury to sidewalk
users and reduce overall city liability related to slip and fall claims.
E-12
This project consists of engineering and installing a new traffic signal
at the intersection of Palos Verdes Drive South and Palos Verdes
Drive East.
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 N/A $0
Engineering $25,000 $0 $0 $0 $0 $0 N/A $25,000
Environmental $0 $0 $0 $0 $0 $0 N/A $0
Management $0 $0 $0 $0 $0 $0 N/A $0
Construction $0 $275,000 $0 $0 $0 $0 N/A $275,000
Contingency $0 $0 $0 $0 $0 $0 N/A $0
Inspection $0 $20,000 $0 $0 $0 $0 N/A $20,000
$25,000 $295,000 $0 $0 $0 $0 N/A $320,000
Funding
215 (Prop. C) $25,000 $295,000 $0 $0 $0 $320,000
$25,000 $295,000 $0 $0 $0 $320,000
Estimated annual operating cost $5,000
Estimated Schedule:
Engineering in Fiscal Year 2019-20.
Construction in Fiscal Year 2020-21.
Project Location Map Background:
The design and construction of this project was initiated by the
Traffic Safety Committee and was approved subsequently by the
City Council.
Justification:
The installation of a new traffic signal will improve traffic flow and
increase vehicular safety at this intersection.
E-13
This project consists of engineering and installing a new traffic signal
at the intersection of Hawthorne Boulevard and Via Rivera.
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 N/A $0
Engineering $25,000 $0 $0 $0 $0 $0 N/A $25,000
Environmental $0 $0 $0 $0 $0 $0 N/A $0
Management $0 $0 $0 $0 $0 $0 N/A $0
Construction $0 $317,000 $0 $0 $0 $0 N/A $317,000
Contingency $0 $0 $0 $0 $0 $0 N/A $0
Inspection $0 $25,000 $0 $0 $0 $0 N/A $25,000
$25,000 $342,000 $0 $0 $0 $0 N/A $367,000
Funding
211 (1911 Act) $25,000 $342,000 $367,000
$25,000 $342,000 $367,000
Estimated annual operating cost $5,000
Estimated Schedule:
Engineering in Fiscal Year 2019-20.
Construction in Fiscal Year 2020-21.
Project Location Map Background:
The design and construction of this project was initiated by the
Traffic Safety Committee and was approved subsequently by the
City Council in February 2020.
Justification:
The installation of a new traffic signal will improve traffic flow and
enhance vehicular safety at this intersection.
E-14
The project consists of developing a plan for improvements to
enhance the aesthetics of the public right-of-way along the Western
Avenue corridor (from Peninsula Verde Drive to Summerland Street)
to possibly include:
New entrance features
Lighting improvements (including up-lighting of landscaping)
Hardscape improvements
new street furniture and trash receptacles
crosswalk improvements
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $150,000 $0 $0 $0 $0 $0 $150,000
Engineering $0 $0 $0 $0 $0 $0 $0 $0
Environmental $0 $0 $0 $0 $0 $0 $0 $0
Management $0 $0 $0 $0 $0 $0 TBD TBD
Construction $0 $0 $0 $0 $0 $0 TBD TBD
Contingency $0 $0 $0 $0 $0 $0 TBD TBD
Inspection $0 $0 $0 $0 $0 $0 TBD TBD
$0 $150,000 $0 $0 $0 $0 TBD TBD
Funding
330 (CIP) $150,000 TBD
$150,000 TBD
Estimated annual operating cost TBD
Estimated Schedule:
Developing a Plan for Improvements in Fiscal Year 2021-22
Project Location Map Background:
For many years, there has been a general desire by the City to
enhance the aesthetics and improvements along the Western
Avenue corridor.
Justification:
Aesthetic improvements to the public right-of-way and adjacent areas
would enhance the appeal of the surrounding area, bolster commerce
with local businesses, and reflect positively on the entire City.
E-15
This project consists of widening of the Palos Verdes Drive East
roadway, from Bronco Drive to lower Headland Drive, by adding a
12’ center turn lane and constructing a decomposed granite (“DG”)
pedestrian/equestrian path in the public right-of-way, from Bronco
Drive to Sunnyside Ridge Drive
Project Cost Estimates
Prior FYs FY20/21 FY21/22 FY22/23 FY23/24 FY24/25 FY TBD Totals
Planning $0 $0 $0 $0 $0 $0 N/A $0
Engineering $0 $200,000 $0 $0 $0 $0 N/A $200,00
Environmental $0 $0 $0 $0 $0 $0 N/A $0
Management $0 $0 $0 $0 $0 $0 N/A $0
Construction $0 $0 $1,250,000 $0 $0 $0 N/A $1,250,000
Contingency $0 $0 $0 $0 $0 $0 N/A $0
Inspection $0 $0 $50,000 $0 $0 $0 N/A $50,000
$0 $0 $1,300,000 $0 $0 $0 N/A $1,500,000
Funding
330 (CIP) $200,000 $1,300,000 $1,500,000
$200,000 $1,300,000 $1,500,000
Estimated annual operating cost $10,000
Estimated Schedule:
Engineering in Fiscal Year 2020-21.
Construction in Fiscal Year 2021-22.
Project Location Map Background:
The curb radius along Palos Verdes Drive East and Bronco is very
tight and motorists tend to drive fast through this segment of the
roadway.
Justification:
The widening of Palos Verdes Drive East and construction of a center
turn lane, and the construction of a path will address vehicular and
pedestrian safety concerns and will provide for safer travel in this
area.
E-16