CC SR 20180619 H - Miraleste Drive Arterial Rehabilitation NOCRANCHO PALOS VERDES CITY COUNCIL MEETING DATE: 06/19/2018
AGENDA REPORT AGENDA HEADING: Consent Calendar
AGENDA DESCRIPTION:
Consideration and possible action to approve the Notice of Completion for the Miraleste
Drive Arterial Rehabilitation Project
RECOMMENDED COUNCIL ACTION:
(1) Accept the project as complete;
(2) Authorize the City Clerk to file a Notice of Completion for the project with the Los
Angeles County Recorder; and if no claims are filed within 35 days after
recordation, send a notice to the surety company to exonerate the Payment and
Performance Bond; and,
(3) Authorize the Director of Public Works to release the 5% construction retention
payment to Excel Paving Company, 35 days after recordation of the Notice of
Completion by the Los Angeles County Recorder, contingent upon no claims being
filed on the project, and the contractor posting an acceptable warranty bond with
the City.
FISCAL IMPACT: The final cost of Construction and Construction Management was
$1,823,069.93. The original budgeted amount was $2,434,500.
Amount Budgeted: $2,434,500
Additional Appropriation: N/A
Account Number(s): 330-400-8031-8802
ORIGINATED BY: Charles Eder, PE, Senior Engineer
REVIEWED BY: Elias Sassoon, PE, Director of Public Works
APPROVED BY: Doug Willmore, City Manager
ATTACHED SUPPORTING DOCUMENTS:
A. Notice of Completion (page A-1)
BACKGROUND AND DISCUSSION:
The Miraleste Drive Arterial Rehabilitation Project was awarded in June 6, 2017, to
Excel Paving Company. The scope of work included roadway rehabilitation consisting
of removal of failing asphalt concrete and base material and replacing it with full-depth
asphalt concrete (AC), asphalt concrete grinding, asphalt rubberized hot mix overlay,
microsurfacing, installation of ADA-compliant curb access ramps, visibility
improvements, removal and replacement of damaged asphalt concrete sidewalk, tree
1
root pruning, replacement of damaged traffic signs, and replacement of existing striping
and pavement markers.
During the course of the project, quicker-setting cement was used for the bus pads and
cross gutters to help alleviate construction impacts upon school traffic on Miraleste
Drive. Additional AC walkways were also added to provide a clean, clear pathway for
pedestrians at the south end of the project. The contractor’s work is now finished and
has been successfully reviewed for conformance to the project plans and specifications.
The total cost of the project is summarized in the following table:
CONSTRUCTION COST SUMMARY
ITEM AMOUNT
Council Authorization
(construction + 10% contingency) $ 1,875,329.98
Construction Costs Construction Contract $ 1,624,411.98
Change Orders $ 115,504.20
Construction Management $ 83,153.75
Total Construction Costs $ 1,823,069.93
Project Savings $ 52,260.05