RPVCCA_RDA_SR_2010_06_01_C_PVDS_Landslide_And_Road_Stability_GradingMEMORANDUM
TO:
FROM:
DATE:
SUBJECT:
CHAIRMAN WOLOWICZ AND BOARD MEMBERS OF THE
RANCHO PALOS VERDES REDEVELOPMENT AGENCY
DIRECTOR OF PUBLIC WORKS(j&.{}.f.~
JUNE 1,2010
PALOS VERDES DRIVE SOUTH LANDSLIDE (EAST END)
LANDSLIDE AND ROAD STABILITY GRADING
REVIEWED:CAROLYN LEHR,EXECUTIVE DIRECTOR oSL-
STAFF L1ASON:RON DRAGOO,SENIOR ENGINE~
RECOMMENDATIONS:1)Based on the facts set forth in this report,find that an
emergency exists which will not permit a delay arising from a competitive solicitation for bids
and that the actions taken below are necessary to respond to the emergency;2)Approve
and authorize the Chairman of the Board of Directors to execute a Contract with Mike Drews
Construction Company,Inc.,to remove approximately 1000 feet of vegetation located to the
south of the Palos Verdes Drive South roadway and to re-grade a portion of the roadway
shoulder and adjacent slope to eliminate cracks and fissures adjacent to Palos Verdes Drive
South,and 3)Adopt Resolution 2010-_,A RESOLUTION OF THE BOARD OF THE
RANCHO PALOS VERDES REDEVELOPMENT AGENCY,AMENDING RESOLUTION
2009-07,THE BUDGET APPROPRIATION FOR FISCAL YEAR 2009-10,TO INCREASE
THE BUDGET IN THE PORTUGUESE BEND CAPITAL PROJECTS FUND.
BACKGROUND
The Portuguese Bend Landslide is moving at the rate of approximately 7 to 8 feet per year in
the area that is south of Palos Verdes Drive South ("the Road").This is the most active area
of the Landslide.The City Geologist has explained that the loss of the beach,which
previously provided a buttress to the Landslide due to wave erosion,along with recent
increased rainfall,has accelerated the land movement so that large cracks and fissures
have developed seaward of the Road.The cracks and fissures,in turn,allow more water to
enter the Landslide,which exacerbates the land movement.This situation has adversely
affected the integrity and viability of the Road and has increased the amount and cost of the
annual work that the City performs to keep the Road in a useable condition.
The movement of the Portuguese Bend Landslide also has caused earth to be moved from
the property that is owned by the Redevelopment Agency ("RDA"),which is located to the
south of the road,onto adjacent property to the east,which is owned by the Portuguese
Bend Club ("the Club").For many years,the Club has been performing remedial grading
R6876-00011232443.2
RDA C-1
pursuant to a permit that was issued by the Planning Commission in 1996,pursuant to the
recommendations of former City Geologist Perry Ehlig.The grading permit allows the Club
to perform remedial grading on an as needed basis in order to maintain specific gradients
identified on an approved grading plan.This action consists of taking dirt that is deposited
on the Club's property by the Landslide and to relocate it onto the RDA Property at a
location determined acceptable by former City Geologist Perry Ehlig.Club representatives
have undertaken these actions to preserve the Club's private road (Yacht Harbor Drive)as
well as to protect the homes that are located on the western side of their residential
subdivision.The Club recently entered into a contract with Mike Drews Construction to
relocate 60,000 cubic yards of dirt,pursuant to its grading permit,and has requested that the
City or RDA take over this effort.
DISCUSSION
The City Geologist recommends that grading be performed on the RDA's property that is
located to the south of the Road.The purpose of the grading is to fill the cracks and fissures
close to the Road so water will not enter the Landslide so easily and to create a 2:1 slope on
the seaward side of the Road to provide support and increased stability for the Road.The
stability of the Road is vitally important to the public and to the City's ability to provide law
enforcement and fire suppression services to residents who reside on the south side of the
City,since it is one of the City's main arterials.
The intent of the proposed project is to enhance the stability of the area that is being graded,
which will have the corresponding benefit of increasing the stability of this portion of the
Landslide area and of the Road itself.Thus,the proposed project will help maintain the
viability of the major roadway that is located on the south side of the City,which extends
from the eastern boundary to the western boundary of the City.Albeit it is difficult to
estimate the amount of movement (and associated cost of repairs)the Road will be subject
to during anyone year,this project should have the additional benefit of reducing,to some
extent,the City's annual cost to maintain the Road,which has been approximately $350,000
per year,during recent years.
The Director of Public Works estimates that the RDA will need approximately 40,000 cubic
yards of earth to fill in the cracks and fissures and provide the 2:1 slope on the seaward side
of the Road to enhance its stability.As discussed above,the Club seeks to have
approximately 60,000 cubic yards of earth removed from the western side of the Club's
property,which could adversely affect the homes and private road within the Club's
boundaries,and taken back to the RDA's property or placed somewhere else where it will
not adversely affect their properties.
Due to the immediate need to perform this grading work to fill the cracks and fissures and
stabilize the area and the Road,as well as the need to remove the dirt that the Landslide
pushed from the RDA's property onto the Club's property,Staff is recommending that the
RDA enter into a contract with Drews Construction to perform the work that is being
recommended by the City Geologist.Drews Construction has provided a proposal to the
RDA to remove the vegetation in the area where the cracks are located,fill the cracks and
R6876-000 1/1232443.2
RDA C-2
fissures and build the 2:1 slope adjacent to the Road with dirt that currently is located on the
Club's property for the cost of $213,750.Because of the benefits of addressing several
different problems by doing all of this work at once,and the immediate need to provide
additional stability to the Road,Staff recommends that the RDA find by a 4/5 vote that an
emergency exists,approve the agreement with Drews Construction,and authorize the
Chairman to execute the contract.
ADDITIONAL INFORMATION
Staff contacted two other grading contractors to obtain additional bids for this work.Cooper
&Cooper submitted a proposal in the amount of $225,390,which was higher than the
proposal of Drews Construction.The other company,Hardy and Harper,did not submit a
proposal to Staff.
CONCLUSION
The RDA needs approximately 40,000 cubic yards of earth to fill cracks and fissures,
enhance the stability of the Landslide area and improve the stability of the Road.The Club
has more than 40,000 cubic yards of dirt that the Landslide has moved onto its property from
the RDA's property that could adversely affect property within the Club,which the Club is
requesting the RDA to remove.Accomplishing both tasks at once is cost effective and
efficient and will eliminate hazardous conditions that are adversely affecting the Road and
residents of the City and the Redevelopment Project Area.Accordingly,Staff recommends
that the Agency Board take the actions recommended by Staff.
FISCAL IMPACT
The cost of this project is $213,750.
Attachment:Budget Resolution
R6876-0001/1232443.2
RDA C-3
RESOLUTION NO.RDA 2010-
A RESOLUTION OF THE BOARD OF THE RANCHO PALOS VERDES REDEVELOPMENT
AGENCY,AMENDING RESOLUTION 2009-07,THE BUDGET APPROPRIATION FOR FY09-10,TO
INCREASE THE BUDGET IN THE PORTUGUESE BEND CAPITAL PROJECTS FUND.
WHEREAS,Section 3.32 of the Rancho Palos Verdes Municipal Code provides that all expenditures
in excess of budgeted allocations must be by supplemental appropriation of the Agency Board:and
WHEREAS,on June 30,2009,the Board of the Rancho Palos Verdes Redevelopment Agency
adopted Resolution 2009-07,approving a spending plan and authorizing a budget appropriation for
FY09-10:and
WHEREAS,grading has become necessary for landslide mitigation in the Portuguese Bend portion of
the Redevelopment Project Area;and
WHEREAS,the Agency Board has determined that the specific grading expenditures should be
completed in FY09-10;and
BE IT,THEREFORE,RESOLVED BY THE BOARD OF THE RANCHO PALOS VERDES
REDEVELOPMENT AGENCY:
The following adjustment is made to the FY09-10 budget:
Increase the Redevelopment Agency's Portuguese Bend Capital Projects Fund budget as follows:
Portuguese Bend #375-3075-461-73-00 Improvements $213,750
PASSED,APPROVED,AND ADOPTED THE 1st DAY OF JUNE 2010.
AGENCY CHAIRPERSON
ATTEST:
AGENCY SECRETARY
State of California )
County of Los Angeles )ss
City of Rancho Palos Verdes )
I,CARLA MORREALE,Agency Secretary of the Rancho Palos Verdes Redevelopment Agency,
hereby certify that the above Resolution No.RDA 2010-was duly and regularly passed and
adopted by the said Board at regular meeting thereof held on June 1,2010.
AGENCY SECRETARY
CITY OF RANCHO PALOS VERDES
RDA C-4