RPVCCA_SR_2010_04_20_09_Civic_Center_Preliminary_ScheduleMEMORANDUM TO:HONORABLE MAYOR AND CITY COUNCIL FROM:CAROLYNN PETRU,DEPUTY CITY MANAGER~ DATE:APRIL 20,2010 SUBJECT:CIVIC CENTER PRELIMINARY SCHEDULE REVIEWED:CAROLYN LEHR,CITY MANAGER 09-- RECOMMENDATION Receive and file. BACKGROUND Since January 2004,the City Council has identified the development of a new Civic Center as one of its Tactical Goals.This project has been carried forward and further refined over the last six years,initially through the work of the Open Space Planning Recreation and Parks Task Force in 2004 and later through the adoption of the Coast Vision Plan in 2008. On November 17,2009,the City Council authorized the Civic Center Master Plan to proceed to the next level by authorizing staff to take a series of actions,including retaining an architect to prepare a space and parking needs analysis for City Hall,a landscape architect to advise the City on site planning issues and a financial advisor to assist the City in the development of funding alternatives for the Civic Center. As part of the 2010 Tactical Plan adopted on February 16th ,the City Council established several milestones related to the Civic Center.Milestone No.1 calls for the development of a realistic schedule,including incremental steps such as needs assessment,space planning,site planning,financing options,etc.,to create a new Civic Center.This staff report,with the attached Preliminary Schedule,is intended to satisfy this milestone. DISCUSSION Although work has progressed on the Civic Center for many years,including much of the site baseline work performed in 2008 and 2009,the attached Preliminary Schedule commences in May 2010 and includes three main phases and the associated major components listed below: MEMORANDUM TO:HONORABLE MAYOR AND CITY COUNCIL FROM:CAROLYNN PETRU,DEPUTY CITY MANAGER~ DATE:APRIL 20,2010 SUBJECT:CIVIC CENTER PRELIMINARY SCHEDULE REVIEWED:CAROLYN LEHR,CITY MANAGER 09-- RECOMMENDATION Receive and file. BACKGROUND Since January 2004,the City Council has identified the development of a new Civic Center as one of its Tactical Goals.This project has been carried forward and further refined over the last six years,initially through the work of the Open Space Planning Recreation and Parks Task Force in 2004 and later through the adoption of the Coast Vision Plan in 2008. On November 17,2009,the City Council authorized the Civic Center Master Plan to proceed to the next level by authorizing staff to take a series of actions,including retaining an architect to prepare a space and parking needs analysis for City Hall,a landscape architect to advise the City on site planning issues and a financial advisor to assist the City in the development of funding alternatives for the Civic Center. As part of the 2010 Tactical Plan adopted on February 16th ,the City Council established several milestones related to the Civic Center.Milestone No.1 calls for the development of a realistic schedule,including incremental steps such as needs assessment,space planning,site planning,financing options,etc.,to create a new Civic Center.This staff report,with the attached Preliminary Schedule,is intended to satisfy this milestone. DISCUSSION Although work has progressed on the Civic Center for many years,including much of the site baseline work performed in 2008 and 2009,the attached Preliminary Schedule commences in May 2010 and includes three main phases and the associated major components listed below: 9-1 MEMORANDUM TO:HONORABLE MAYOR AND CITY COUNCIL FROM:CAROLYNN PETRU,DEPUTY CITY MANAGER~ DATE:APRIL 20,2010 SUBJECT:CIVIC CENTER PRELIMINARY SCHEDULE REVIEWED:CAROLYN LEHR,CITY MANAGER 09-- RECOMMENDATION Receive and file. BACKGROUND Since January 2004,the City Council has identified the development of a new Civic Center as one of its Tactical Goals.This project has been carried forward and further refined over the last six years,initially through the work of the Open Space Planning Recreation and Parks Task Force in 2004 and later through the adoption of the Coast Vision Plan in 2008. On November 17,2009,the City Council authorized the Civic Center Master Plan to proceed to the next level by authorizing staff to take a series of actions,including retaining an architect to prepare a space and parking needs analysis for City Hall,a landscape architect to advise the City on site planning issues and a financial advisor to assist the City in the development of funding alternatives for the Civic Center. As part of the 2010 Tactical Plan adopted on February 16th ,the City Council established several milestones related to the Civic Center.Milestone No.1 calls for the development of a realistic schedule,including incremental steps such as needs assessment,space planning,site planning,financing options,etc.,to create a new Civic Center.This staff report,with the attached Preliminary Schedule,is intended to satisfy this milestone. DISCUSSION Although work has progressed on the Civic Center for many years,including much of the site baseline work performed in 2008 and 2009,the attached Preliminary Schedule commences in May 2010 and includes three main phases and the associated major components listed below: Topic:Civic Center Preliminary Schedule Date:April 20,2010 Page 2 PHASE 1 -PROJECT DESIGN •Baseline Study •Program of Utilization (POU) •Preliminary Project Design •Community Outreach •Financing (Identification of Alternatives) PHASE 2 -APPLICATION PROCESS •Project Applications/Environmental Review •Community Outreach •Financing (Selection of Funding Mechanism) PHASE 3 -CONSTRUCTION •Financing (Securing Project Funding) •Community Outreach •Pre-Construction •Construction The entire project is expected to take approximately four and a half years to complete, with occupancy of the new Civic Center occurring in August 2014.In general terms, staff estimates that Phase 1 (Project Design)will take will take a little over a year to complete.Phase 2 (Application Process)will take a year and several months to complete and Phase 3 (Construction)will take two years to complete.The Community Outreach and Financing components of the project would be ongoing throughout the process. ADDITIONAL INFORMATION Staff is currently planning a Council Workshop on June 29,2010 (fifth Tuesday)to present and discuss the pros and cons of various potential funding mechanisms for the Civic Center Project,including Public/Private Partnerships (P3). FISCAL IMPACT The current budget to complete the baseline studies for the Civic Center is $371,000, which was funded with Environmental Excise Tax (EET)received from the Terranea Resort.Once the baseline studies are complete later this year,staff can engage in more in depth study with the City's financial advisor and the selected project architect to identify additional project costs.Staff will present these cost estimates to Council in a separate staff report in satisfaction of Civic Center Tactical Goals Milestone No.2. Attachment: Civic Center Preliminary Schedule Spreadsheet V:\CAROLYNN\REPORTS\201 0\201 00420_Civic Center Schedule_staff report.doc Topic:Civic Center Preliminary Schedule Date:April 20,2010 Page 2 PHASE 1 -PROJECT DESIGN •Baseline Study •Program of Utilization (POU) •Preliminary Project Design •Community Outreach •Financing (Identification of Alternatives) PHASE 2 -APPLICATION PROCESS •Project Applications/Environmental Review •Community Outreach •Financing (Selection of Funding Mechanism) PHASE 3 -CONSTRUCTION •Financing (Securing Project Funding) •Community Outreach •Pre-Construction •Construction The entire project is expected to take approximately four and a half years to complete, with occupancy of the new Civic Center occurring in August 2014.In general terms, staff estimates that Phase 1 (Project Design)will take will take a little over a year to complete.Phase 2 (Application Process)will take a year and several months to complete and Phase 3 (Construction)will take two years to complete.The Community Outreach and Financing components of the project would be ongoing throughout the process. ADDITIONAL INFORMATION Staff is currently planning a Council Workshop on June 29,2010 (fifth Tuesday)to present and discuss the pros and cons of various potential funding mechanisms for the Civic Center Project,including Public/Private Partnerships (P3). FISCAL IMPACT The current budget to complete the baseline studies for the Civic Center is $371,000, which was funded with Environmental Excise Tax (EET)received from the Terranea Resort.Once the baseline studies are complete later this year,staff can engage in more in depth study with the City's financial advisor and the selected project architect to identify additional project costs.Staff will present these cost estimates to Council in a separate staff report in satisfaction of Civic Center Tactical Goals Milestone No.2. Attachment: Civic Center Preliminary Schedule Spreadsheet V:\CAROLYNN\REPORTS\201 0\201 00420_Civic Center Schedule_staff report.doc 9-2 Topic:Civic Center Preliminary Schedule Date:April 20,2010 Page 2 PHASE 1 -PROJECT DESIGN •Baseline Study •Program of Utilization (POU) •Preliminary Project Design •Community Outreach •Financing (Identification of Alternatives) PHASE 2 -APPLICATION PROCESS •Project Applications/Environmental Review •Community Outreach •Financing (Selection of Funding Mechanism) PHASE 3 -CONSTRUCTION •Financing (Securing Project Funding) •Community Outreach •Pre-Construction •Construction The entire project is expected to take approximately four and a half years to complete, with occupancy of the new Civic Center occurring in August 2014.In general terms, staff estimates that Phase 1 (Project Design)will take will take a little over a year to complete.Phase 2 (Application Process)will take a year and several months to complete and Phase 3 (Construction)will take two years to complete.The Community Outreach and Financing components of the project would be ongoing throughout the process. ADDITIONAL INFORMATION Staff is currently planning a Council Workshop on June 29,2010 (fifth Tuesday)to present and discuss the pros and cons of various potential funding mechanisms for the Civic Center Project,including Public/Private Partnerships (P3). FISCAL IMPACT The current budget to complete the baseline studies for the Civic Center is $371,000, which was funded with Environmental Excise Tax (EET)received from the Terranea Resort.Once the baseline studies are complete later this year,staff can engage in more in depth study with the City's financial advisor and the selected project architect to identify additional project costs.Staff will present these cost estimates to Council in a separate staff report in satisfaction of Civic Center Tactical Goals Milestone No.2. Attachment: Civic Center Preliminary Schedule Spreadsheet V:\CAROLYNN\REPORTS\201 0\201 00420_Civic Center Schedule_staff report.doc ID Ta s k N a m e Du r a t i o n St a r t Fi n i s h 1 PH A S E 1 - P R O J E C T D E S I G N 14 4 w k s Mo n 5 / 3 / 1 0 Fr i 2 / 1 / 1 3 2 Ba s e l i n e S t u d y 17 . 6 w k s Mo n 5 / 3 / 1 0 We d 9 / 1 / 1 0 3 Co m p l e t e S p a c e N e e d s A n a l y s i s 44 d a y s Mo n 5 / 3 / 1 0 Th u 7 / 1 / 1 0 4 Co m p l e t e S i t e M a s t e r P l a n 60 d a y s Tu e 5 / 1 1 / 1 0 Mo n 8 / 2 / 1 0 5 Co m p l e t e A L T A S u r v e y 88 d a y s Mo n 5 / 3 / 1 0 We d 9 / 1 / 1 0 6 Pr o g r a m o f U t i l i z a t i o n 14 4 w k s Mo n 5 / 3 / 1 0 Fr i 2 / 1 / 1 3 7 De f i n e R e q u e s t e d P O U M o d i f i c a t i o n 66 d a y s Mo n 5 / 3 / 1 0 Mo n 8 / 2 / 1 0 8 Su b m i t A p p l i c a t i o n f o r P O U M o d i f i c a t i o n 11 d a y s Mo n 8 / 2 / 1 0 Mo n 8 / 1 6 / 1 0 9 Co m p l e t e E n v i r o n m e n t a l R e v i e w f o r P O U 32 9 d a y s We d 6 / 1 / 1 1 Mo n 9 / 3 / 1 2 10 Re c e i v e N P S A p p r o v a l o f R e v i s e d P O U 13 3 d a y s We d 8 / 1 / 1 2 Fr i 2 / 1 / 1 3 11 Pr e l i m i n a r y P r o j e c t D e s i g n 43 . 6 w k s Mo n 8 / 2 / 1 0 We d 6 / 1 / 1 1 12 CC A p p r o v a l o f C i v i c C e n t e r M a s t e r P l a n 33 d a y s Mo n 8 / 2 / 1 0 We d 9 / 1 5 / 1 0 13 Ci r c u l a t e R e q u e s t f o r Q u a l i f i c a t i o n s ( R F Q ) 33 d a y s Mo n 8 / 2 / 1 0 We d 9 / 1 5 / 1 0 14 Se l e c t P r o j e c t A r c h i t e c t 34 d a y s We d 9 / 1 5 / 1 0 Mo n 1 1 / 1 / 1 0 15 Co m p l e t e P r e l i m i n a r y P r o j e c t D e s i g n 13 1 d a y s Mo n 1 1 / 1 / 1 0 Mo n 5 / 2 / 1 1 16 CC A p p r o v a l o f P r e l i m i n a r y D e s i g n 23 d a y s Mo n 5 / 2 / 1 1 We d 6 / 1 / 1 1 17 PH A S E 2 - A P P L I C A T I O N P R O C E S S 65 . 8 w k s We d 6 / 1 / 1 1 Mo n 9 / 3 / 1 2 18 Pr o j e c t A p p l i c a t i o n s / E n v i r o n m e n t a l R e v i e w 65 . 8 w k s We d 6 / 1 / 1 1 Mo n 9 / 3 / 1 2 19 Ci r c u l a t e E I R R F P 33 d a y s We d 6 / 1 / 1 1 Fr i 7 / 1 5 / 1 1 20 Se l e c t E I R C o n s u l t a n t 22 d a y s Fr i 7 / 1 5 / 1 1 Mo n 8 / 1 5 / 1 1 21 Co m p l e t e I n i t i a l S t u d y 36 d a y s Mo n 8 / 1 5 / 1 1 Mo n 1 0 / 3 / 1 1 22 Ci r c u l a t e N o t i c e o f P r e p a r a t i o n 22 d a y s Mo n 1 0 / 3 / 1 1 Tu e 1 1 / 1 / 1 1 23 Pr e p a r e D r a f t E I R 88 d a y s Tu e 1 1 / 1 / 1 1 Th u 3 / 1 / 1 2 24 Ci r c u l a t e D r a f t E I R / P u b l i c C o m m e n t P e r i o d 33 d a y s Th u 3 / 1 / 1 2 Mo n 4 / 1 6 / 1 2 25 PC R e v i e w o f C U P , Z o n e C h a n g e a n d D E I R 35 d a y s Mo n 4 / 1 6 / 1 2 Fr i 6 / 1 / 1 2 26 Pr e p a r e F i n a l E I R 32 d a y s Fr i 6 / 1 / 1 2 Mo n 7 / 1 6 / 1 2 27 CC A c t i o n o n C U P , Z o n e C h a n g e & F E I R 36 d a y s Mo n 7 / 1 6 / 1 2 Mo n 9 / 3 / 1 2 28 PH A S E 3 - C O N S T R U C T I O N 10 2 w k s Mo n 9 / 3 / 1 2 Fr i 8 / 1 5 / 1 4 29 Pr e - C o n s t r u c t i o n 22 w k s Mo n 9 / 3 / 1 2 Fr i 2 / 1 / 1 3 30 Pr e p a r e C o n s t r u c t i o n D o c u m e n t s 66 d a y s Mo n 9 / 3 / 1 2 Mo n 1 2 / 3 / 1 2 31 Bu i l d i n g P l a n C h e c k 45 d a y s Mo n 1 2 / 3 / 1 2 Fr i 2 / 1 / 1 3 32 Si t e P r e p a r a t i o n 67 d a y s Th u 1 1 / 1 / 1 2 Fr i 2 / 1 / 1 3 33 Bi d a n d A w a r d C o n s t r u c t i o n C o n t r a c t 90 d a y s Mo n 1 0 / 1 / 1 2 Fr i 2 / 1 / 1 3 34 Co n s t r u c t i o n 80 . 2 w k s Fr i 2 / 1 / 1 3 Fr i 8 / 1 5 / 1 4 35 Ea r t h w o r k a n d S i t e W o r k 64 d a y s Fr i 2 / 1 / 1 3 We d 5 / 1 / 1 3 36 Fo u n d a t i o n a n d S t r u c t u r e 13 3 d a y s We d 5 / 1 / 1 3 Fr i 1 1 / 1 / 1 3 37 Ex t e r i o r 13 0 d a y s Fr i 1 1 / 1 / 1 3 Th u 5 / 1 / 1 4 38 In t e r i o r 10 9 d a y s Mo n 1 2 / 2 / 1 3 Th u 5 / 1 / 1 4 39 Si t e W o r k 64 d a y s Mo n 2 / 3 / 1 4 Th u 5 / 1 / 1 4 40 St a r t u p , T e s t , & I n s p e c t i o n 44 d a y s Th u 5 / 1 / 1 4 Tu e 7 / 1 / 1 4 41 Ce r t o f O c c , M o v e I n & R i b b o n C u t t i n g 34 d a y s Tu e 7 / 1 / 1 4 Fr i 8 / 1 5 / 1 4 42 ON G O I N G T A S K S 22 4 w k s Mo n 5 / 3 / 1 0 Fr i 8 / 1 5 / 1 4 43 Co m m u n i t y O u t r e a c h 22 4 w k s Mo n 5 / 3 / 1 0 Fr i 8 / 1 5 / 1 4 44 Co m m u n i t y C e n t e r N e e d s A s s e s s m e n t 44 d a y s Mo n 5 / 3 / 1 0 Th u 7 / 1 / 1 0 45 De v e l o p C i v i c C e n t e r D e s i g n G u i d e l i n e s 46 d a y s Mo n 1 1 / 1 / 1 0 Mo n 1 / 3 / 1 1 46 Co m m u n i t y O p e n H o u s e S e r i e s 26 2 d a y s Tu e 6 / 1 / 1 0 We d 6 / 1 / 1 1 47 Mu l t i - M e d i a O u t r e a c h 11 2 0 d a y s Mo n 5 / 3 / 1 0 Fr i 8 / 1 5 / 1 4 48 Fi n a n c i n g 13 1 w k s Mo n 8 / 2 / 1 0 Fr i 2 / 1 / 1 3 49 Fi n a n c i n g A l t e r n a t i v e s A n a l y s i s 66 d a y s Mo n 8 / 2 / 1 0 Mo n 1 1 / 1 / 1 0 50 CC S e l e c t i o n o f F i n a n c i n g M e c h a n i s m 23 d a y s Mo n 1 1 / 1 / 1 0 We d 1 2 / 1 / 1 0 51 Se c u r e P r o j e c t F i n a n c i n g 90 d a y s Mo n 1 0 / 1 / 1 2 Fr i 2 / 1 / 1 3 Ja n Ap r Ju l Oc t Ja n Ap r Ju l Oc t Ja n Ap r Ju l Oc t Ja n Apr Jul Oct Jan Apr Jul Oct 20 1 0 20 1 1 20 1 2 20 1 3 2014 Ta s k Sp l i t Pr o g r e s s Mi l e s t o n e Su m m a r y Pr o j e c t S u m m a r y Ex t e r n a l T a s k s Ex t e r n a l M i l e s t o n e Deadline CI V I C C E N T E R P R E L IM I N A R Y S C H E D U L E Pa g e 1 Pr o j e c t : C i v i c C e n t e r P r o j e c t T i m e l i n e Da t e : 4 / 1 8 / 2 0 1 0 9-3