RPVCCA_SR_2010_03_02_11_Five_Yr_Capital_Imp_Plan_Mid_Yr_ReviewCITY OF MEMORANDUM RANCHO PALOS VERDES TO: FROM: DATE: SUBJECT: HONORABLE MAYOR AND CITY COUNCIL MEMBERS CAROLYNN PETRU,DEPUTY CITY MANAGER@) MARCH 2,2010 FIVE-YEAR CAPITAL IMPROVEMENT PLAN MID-YEAR REVIEW REVIEWED BY:CAROLYN LEHR,CITY MANAGERoY-- Project Manager:Sara Singer,Senior Administrative Analyst ¢r RECOMMENDATION Adopt the updated FY09-10 Five-Year Capital Improvement Plan. BACKGROUND A Capital Improvement Plan (CIP)is a guide for the efficient and effective provision of resources for improving and maintaining public infrastructure and facilities.Programming capital facilities and improvements over time can promote better use of the City's limited financial resources,reduce costs and assist in the coordination of public and private development. The City Council approved this five year plan as part of the FY09-1 0 budget process.The projects were compiled in an inventory based on a comprehensive review of existing reports,infrastructure plans,community input and City Council direction.Some of these plans include the following:the Pavement Management System,Coast Vision Plan, Sanitary Sewer Master Plan,Public Use Master Plan,Trails Network Plan,Storm Drain Master Plan and the General Plan.This plan was also developed through an extensive public outreach effort which collected input from various groups in the community.Staff has received input from the City Council,the Storm Drain Oversight Committee,community members at the Community Leaders'Breakfast,RPV Council of Homeowners Associations (CHOA),the Peninsula Seniors and other various community stakeholders and homeowner associations. 11-1 FIVE-YEAR CAPITAL IMPROVEMENT PLAN MID-YEAR REVIEW March 2,2010 Page 2 Staff has updated the plan according to project managers'revised project costs,new projects that have been identified or existing projects which have revised scopes of work. While this update is being provided during the first year the CIP process has been in place, Staff proposes to provide the City Council with future updates of projects and expenditures through the annual budget review process. DISCUSSION Updates to the FY09-10 Plan As indicated in the FY09-10 Project Status schedule (see Attachment A),there are many projects listed for this fiscal year.This schedule provides updates on the status of all current projects.Out of the 21 projects listed for FY09-1 0,12 of these projects have been added as continuing appropriations from FY08-09,or have partial project funding that are continuing appropriations from FY08-09.One of the carryover projects requires a budget adjustment due to a revised project scope and estimate.The project is the Hesse Park and PVIC Emergency Generators,which was originally budgeted for $51,000 for FY08-09 and the revised estimate shows that it will be approximately $215,000.It will require a budget adjustment of $164,000,and Staff proposes that this be funded using EET funds. This project will need to be presented to the City Council at a separate meeting for a budget adjustment and details regarding the revised cost estimate. The Fred J.Hesse Park Field Upgrade Phase I was included in the FY09-1 0 Budgetforthe amount of $146,300 to rehabilitate the existing ball field.The City's grant consultant has identified a promising funding opportunity (Baseball Tomorrow Grant)to upgrade the existing field as well as construct the second field planned for this location.Therefore,one of the changes being proposed is to shift this funding to improve and upgrade the field at Robert E.Ryan Park in FY09-10.Staff is working with one of the City's on-call engineering firms to develop cost estimates to include the Fred J.Hesse Park Field Upgrade Phase I and Phase II to be constructed in FY10-11.Preliminary estimates show that the design and construction of these fields will cost approximately $500,000.Staff is proposing to use TOT revenue (Transient Occupancy Tax revenue received during the current fiscal year,as well as previous fiscal years which is included in General fund reserves)and grant funding (Baseball Tomorrow Grant)to complete this project.Completing both Phase I and Phase II simultaneously should help to achieve additional cost savings through construction material discounts and efficient use of consultants.In addition,Staff has begun preliminary meetings with the Palos Verdes Peninsula Unified School District to explore the possibility of developing a comprehensive Peninsula-wide plan for additional active recreational fields Updates to the Five-Year Plan The updated Five-Year Plan (see Attachment B)shows the addition of projects in future years,including the construction of Lower Hesse Park and Grandview Park.At the November 1i h ,2009 City Council meeting the Council directed Staff to retain a consultant 11-2 FIVE-YEAR CAPITAL IMPROVEMENT PLAN MID-YEAR REVIEW March 2,2010 Page 3 to develop conceptual designs for these City parks.The development of the conceptual designs is funded in the FY09-10 Budget,and the construction of these parks is being proposed for FY10-11.Staff proposes using TOT revenue,(Transient Occupancy Tax revenue received during the current fiscal year,as well as previous fiscal years which is included in General fund reserves)and grant funding to fund the construction of these two parks.A preliminary estimate for the construction of Grandview Park and Lower Hesse Park is approximately $2 million. Other needs have also been identified by staff,the City Council or the public and have been added to the Unfunded Projects list.These items include the following projects:1) Operational Improvements at the Intersection of Crenshaw &Crest,2)Hesse Park/Hawthorne Blvd.Traffic Circulation and Safety Study,3)Improvements at the Intersection of Palos Verdes Drive East (PVDE)&Bronco Drive,and 4)Traffic Safety Improvements on the Switchbacks.The Operational Improvements at the Crenshaw & Crest project was identified through parking issues resulting from activity at St.John Fisher Church.The Hesse Park/Hawthorne Blvd.Traffic Circulation and Safety Study was identified through the public outreach process for the Lower Hesse Park C~:>nceptual Design process.The Bronco Drive and Switchback traffic safety projects on PVDE were introduced to the City Council at the January 23,2010 Tactical Planning Workshop.These projects were two of nine traffic safety projects resulting from the Palos Verdes Drive East Preliminary Study Report and have been included on the unfunded project list.Some of the projects resulting from the PVDE Preliminary Study Report do not meet the $100,000 threshold required to be included in the CIP;therefore,these smaller projects will be considered for inclusion in the Public Works program budget.Staff is reviewing and evaluating the other projects identified in the study report to determine cost estimates.See Attachment C for additional information about the projects that have been added to the unfunded project list. FISCAL IMPACT The chart below provides a summary of the changes in the CIP for FY09-1 O.The fiscal impact of future year changes will be shown in more detail during the presentation of the 2011 Five-Year Model.Such changes will include the following projects:Construction of Lower Hesse and Grandview Parks and the Fred J.Hesse Park Field Upgrade Phase I and II.Staff is proposing to fund these projects using grant funds and TOT revenue (Transient Occupancy Tax revenue received during the current fiscal year,as well as previous fiscal years which is included in General fund reserves). *For Hesse Park and pVle Emergency Generators. 11-3 FIVE-YEAR CAPITAL IMPROVEMENT PLAN MID-YEAR REVIEW March 2,2010 Page 4 ATTACHMENTS: Attachment A-FY09-10 Project Status Attachment B-FY09-10 Five Year CIP Attachment C-Unfunded Projects 11-4 ATTACHMENT A City Hall Feasibility Study C.Petru $391,000 I $350,000 I $41,000 PSA's with financial,architectural and site planning consultants in progress.Work on Alta Survey continuing. Overall project scheduled to be presented to Council in March 2010.EETfunds City Hall Emergency Generator S.Motahari I $246,400 $220,000 I $26,400 Construction began January 2010.Estimated completion date is mid-April 2010.BA was approved 11/17/2009.Building Improvement Fund On schedule;will award design February 2010.Estimated Residential Overlay and Slurry Seal Zone 8 and 9 IN.Jules 1$1,710,000 I $1,710,000 1 I Iconstruction start date is summer 2010.I General fund RFP's due February 2010.Design contract will be awarded Arterial Overlay and Slurry Seal PVDE (Miraleste to IN.Jules 1$ in March.Estimated construction start date is fall 2010.I Prop C,Measure R, North City Limits)2,543,560 $2,543,560 Prop 1B IHawthorne Blvd.Median Improvements IN.Jules 1$ Design is complete;construction began January 2010.I Beautification295,500 $295,500 IPVDW Phase I Median Improvements IN.Jules 1$250,500 $250,500 Design will begin March 2010.1 Beautification Letter of Authorization (LOA)signed.Project design to begin 2011.Construction is authorized to begin in 2013.IGrant/City 20%Match Pedestrian Improvement Project on Hawthome IN.Jules 1$285,400 I $285,400 I I I from GF Archaeological review is in progress;estimated completion date is March 2010,The City must address any archaeological issues before the LOA is signed.Design IGrant/City 20%Match Bike Compatible Roadway Safety and Linkage on PVDS 1N.Jules 1$788,000 I $723,0001$65,000 I Iprocess will start after LOA is received.from GF,CIP SUbstantially complete.NOC to be filed in March 2010. Residential Overlay and Slurry Seal -FY 08-09 IN.Jules 1$1,700,000 I I $1,700,000 I I I GF,Bikeways Construction in progress.Change order issued to include median work on PVDW and Hawthorne (funded by median project budgets)will extend scheduled date of completion Arterial Overlay and Slurry -FY 08-09 IN.Jules 1$2,894,603 I I $2,894,603 I from February to March 2010. I ARRA,Prop C.,Prop.A Design is complete.Construction began January 2010. I BeautificationPVDW/Hawthorne Blvd.Median Improvements IN.Jules 1$292,000 1 1$292,000 I IN.Jules 1$263,000 I 1$263,000 I Design is complete.Construction to begin March 2010. Crestridge/Crenshaw Traffic Signal Improvement I HSIP Grant,GF match Waiting for E-76 approval.Design is expected to begin PVDE Traffic Safety Improvements IN.Jules 1$280,000 1 1$280,000 I IAugust 2010.I HSIP Grant,GF match Page 1 11-5 ATTACHMENT A Storm Drain Lining PVDS &PVDE Roadway Stabilization Via Colinita Vickery Canyon PVIC Exhibits Phase II Fred J.Hesse Park Lower Picnic Playground Fred J.Hesse Park Field Upgrade Phase I (See staff Report) H.Starr 1$ S.Motahari I $ T.Odom 1$ 600,000 I $ 251,300 I $ 146,300 I $ 600,000 186,300 I $ 146,300 65,000 Exhibits are currently being designed and fabrication of the exhibits is expected to begin in FY 10-11 and will take approximately one year to complete. Construction began January 2010 and is expected to be completed March 2010. Staff is proposing changing this project to Ryan Park Field Upgrade. Donations/Grant EET funds (Transferred to CIP) EET funds (Transferred toCIP) Hesse Park and PVIC Emergency Gene~s.Motahari I $215,000 $51,000 I $164,000 Bid opening January 2010.Tentative contract award date is February 2010,with an estimated completion date of June 2010.Total project cost estimate is $215,000,requiring a bUdget adjustment of $164,000. EETfunds *CA -Continuing Appropriation *GF -General Funds BA -Budget Adjustment Page 2 11-6 ATTACHMENT B Rancho Palos Verdes Five Year Capital Improvement Plan Project Residential Overlay and Slurry Seal Zone 8 and 9 Residential Overlay and Slurry Seal Zone 3 (Partial)and 4 Residential Overlay and Slurry Seal Zone 5 Residential Overlay and Slurry Seal Zone 1 and 3 (Partial) Residential Overlay and Slurry Seal Zone 2 $1,710,0001 I I I IGeneral fund $1,520,000 I I IGeneral fund $1,800,000 I IGeneral fund $1,600,000 1 IGeneral fund $1,500,000 IGeneral fund Arterial Overlay and Slurry Seal PVDE (Miraleste to North City Limits) Arterial Overlay and Slurry Seal PVDS (Hawthorne Blvd.to Barkentine Rd.) Hawthorne Blvd.Median Improvements PVDW Phase I Median Improvements PVDW Phase II Median Improvements Pedestrian Improvement Project on Hawthorne Bike Compatible Roadway Safety and Linkage on PVDS $2,543,560 I I $2,700,000 $295,500 $250,500 $250,000 $285,400 $1,141,600 $723,000 Prop C,Measure R,Prop 1B* Prop C,STPL,Measure R,General fund Beautification fund Beautification fund Beautification fund Grant/City 20%Match from General fund Grant/City 20%Match from General fund Storm Drain Lining $309,822 $314,617 $319,555 $324,642 $919,676 WQFP PVDS &PVDE Roadway Stabilization Project $360,000 $350,000 WQFP Via Colinita Vickery Canyon $251,500 $292,500 WQFP for $250,000 and $275,000 Hawthorne Blvd.$370,000 $200,000 WQFP Donations,Grant EETfunds EETfunds TOT,Grant TOT,Grant 425,000 $425,000 Grant/City 20%Match 200,000 $275,000 Grant/City 20%Match 100,000 $150,000 Grant/City 20%Match *Stimulus/ARRA funds are being received for an arterial project for FY08-09,thereby allowing the Prop.1B funds to be reallocated to this arterial project.11-7 ATTACHMENT C RPV Capital Improvement Plan -Unfunded Projects Cost Range Project 1 Fred Hesse Jr.Park Renovation Minimum $500,000 Maximum $900,000 Funding Sources 2 Community and Aquatic Center 3 City Hall 4 Maintenance Yard Relocation 5 Fiber Optic Cabling:Hesse Park 6 Fiber Optic Cabling:Ladera Linda 7 Arterial Improvements -Miraleste Drive 8 Arterial Improvements -Silver Spur Road 9 Arterial Improvements -PVDE (FY 13-14) 10 Traffic Signal Upgrades 11 Traffic Signal -PVDE and Miraleste Drive 12 Traffic Signal-Crenshaw Blvd.and Crest Drive 13 Bikeway Improvements:Phase I and II 14 PVDS Rehabilitation 15 Hawthorne Blvd.Runaway Truck System 16 Sidewalks Improvement Project:Phase I,II &III 17 Operational Improvements at Crenshaw &Crest Hesse Park/Hawthorne Blvd.Traffic Circulation & 18 Safety StUdy 19 Switchbacks 20 Intersection at Bronco Drive 21 Utility Undergrounding at 25th Street 22 Utility Undergrounding at PVDS and Terranea Way 23 Utility Undergrounding at Fisherman's Access 24 Utility Undergrounding at entrance to PVIC PVDS &PVDE Roadway Stabilization Project - 25 Phase II PVDS &PVDE Roadway Stabilization Project - 26 Phase III 27 Altamira Canyon 28 PVDE -Miraleste Canyon 29 San Pedro &Averill Canyons 30 PVDE Switchbacks 31 PVDS 30 Trailhead/Overlook/Vista Point Development 31 PUMP Trail Implementation 32 Portuguese Bend Reserve Trails 33 Sunnyside Trail Segment Project 34 Salvation Army Trail Segment 35 PVIC Exhibits Phase II 36 Bathroom at Del Cerro Park $3,000,000 $20,500,000 $300,000 $180,000 $300,000 $500,000 $1,300,000 $1,900,000 $1,400,000 $280,000 $270,000 $5,000,000 $3,000,000 $3,000,000 $2,600,000 $100,000 $100,000 $1,750,000 $100,000 $1,000,000 $150,000 $150,000 $150,000 $2,500,000 $14,000,000 $1,250,000 $2,500,000 $2,700,000 $750,000 $200,000 $100,000 $820,000 $600,000 $400,000 $120,000 $400,000 $250,000 $8,000,000 $200,000 Ginsburg Donation for "Performing Arts"bUilding. $35,000,000 $1 million in building replacement fund. $1,000,000 $270,000 $470,000 $600,000 $600,000 Prop C $1,500,000 $600,000 Prop C,$625,000 STPL $2,200,000 $600,000 Prop C $1,800,000 $340,000 $320,000 $8,000,000 $5,000,000 $5,000,000 $3,130,000 $250,000 $200,000 $2,000,000 $125,000 $1,100,000 $200,000 $200,000 $200,000 $3,000,000 $16,000,000 $5,000,000 $3,200,000 $3,300,000 $1,350,000 Storm Drain User Fee (supported at minimum cost) $350,000 $130,000 $1,100,000 $740,000 $450,000 $150,000 $700,000 $300,000 11-8 ATTACHMENT C PROJECT: TYPE: LOCATION: DEPARTMENT: DESCRIPTION: OPERATIONAL IMPROVEMENTS AT CRENSHAW &CREST Roadway Infrastructure Crenshaw &Crest Public Works Currently this intersection is a four-way stop controlled intersection.During the AM and PM peak hours,the westbound left-turn lanes back up for several hundreds of feet creating extensive delay and long vehicle queues.An operational improvement to the intersection is required to improve traffic flow. A study is being conducted to determine the best solution ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TBD COST ESTIMATE:$100,000 -$250,000 11-9 ATTACHMENT C PROJECT: TYPE: LOCATION: DEPARTMENT: DESCRIPTION: HESSE PARK/HAWTHORNE BLVD. TRAFFIC CIRCULATION &SAFETY STUDY Roadway Infrastructure Hesse Park Public Works With plans to improve Lower Hesse Park and current traffic concerns relating to access and vehicular circulation,actions are needed to improve left-turn access from Verde Ridge Road and Locklenna Lane onto Hawthorne Blvd.Additionally,pedestrian access across Hawthorne Blvd from Doverridge Drive to Hesse Park is a concern.Lastly,park parking and parking along Locklenna Lane is a concern to neighboring residents especially when the park improvements are realized.A study is currently being conducted to develop a preliminary traffic study to address the current issues.Once the park improvements are designed,a supplemental traffic study will be prepared to address specific demand enerated b the ark's ro osed uses. ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TBD COST ESTIMATE:$100,000 -$200,000 11-10 ATIACHMENTC PROJECT: TYPE: LOCATION: DEPARTMENT: DESCRIPTION: SWITCHBACKS Roadway Infrastructure Palos Verdes Drive East Public Works This project plans to narrow the travel lanes and widen the roadway to provide bike lanes.This project would be completed in conjunction with the catch basin and guardrail improvements if possible. ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TBD COST ESTIMATE:$1,750,000 -$2,000,000 11-11 ATTACHMENT C 2010 Mid-Year CIP Update Unfunded Projects 3/2/2010 PROJECT: TYPE: LOCATION: DEPARTMENT: DESCRIPTION: INTERSECTION AT BRONCO DRIVE Roadway Infrastructure PVDE &Bronco Drive Public Works This project plans to install a high visibility equestrian crossing when funding is received. ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TBD COST ESTIMATE:$100,00 -$125,000 11-12