Loading...
RPVCCA_RDA_SR_2011_12_06_A_PVDS_Landslide_Drainage_GradingMEMORANDUM TO: FROM: DATE: SUBJECT: CHAIRMAN LONG AND BOARD MEMBERS OF THE RANCHO PALOS VERDES REDEVELOPMENT AGENCY DIRECTOR OF PUBLIC WORKttd0.---- DECEMBER 6,2011 PALOS VERDES DRIVE SOUTH LANDSLIDE DRAINAGE GRADING REVIEWED:CAROLYN LEHR,EXECUTIVE DIRECTOR~ STAFF L1ASON:RON DRAGOO,SENIOR ENGINEE~ RECOMMENDATIONS: Review and reconfirm by four/fifths (4/5)vote,the Redevelopment Agency's previous action taken on February 1,2011,authorizing staff to continue with the actions taken to perform emergency grading and the re-installation of a storm drainage system to address drainage within the Portuguese Bend Landslide. BACKGROUND On February 1,2011,the Redevelopment Agency Board found that an emergency exists, which will not permit a delay arising from a competitive solicitation for bids to enter into a contract with a grading contractor,to perform emergency grading to eliminate cracks and fissures on the seaward side of Palos Verdes Drive South and to reestablish the drainage path,and to re-install the storm drainage system adjacent and perpendicular to the Palos Verdes Drive South roadway.Accordingly,the Redevelopment Agency Board approved two contracts;one with Mike Drews Construction Company,Inc.to remove approximately 500 feet of vegetation located perpendicular and to the south of the Palos Verdes Drive South and to re-grade the drainage path from the roadway to the ocean.Another contract was approved with Hardy and Harper,Inc.,to re-install a storm drainage system between the roadway running south to the ocean. DISCUSSION Approval of the emergency for this work required a four-fifths (4/5)vote of the Redevelopment Agency Board under Public Contract Code Section 22050(a)(1). In addition,Public Contract Code Section 22050(c)(1)requires that when a governing body takes action under Section 22050(a)(1),it must review this action and reaffirm it by a four- RDA A-1 fifths (4/5)vote at each subsequent regularly scheduled meeting until the work is completed and accepted. Accordingly,staff has placed this item on tonight's agenda.This item will be placed on each subsequent agenda until all the work is completed and the Redevelopment Agency accepts the project as complete. Prior to the beginning of construction,the required environmental review of the project access routes were performed with the Palos Verdes Land Conversancy and a survey for nesting birds was performed.The bird survey included a field investigation which identified nesting birds that needed to be avoided during construction.The nesting season runs from February 1 through August 31.The consultant recommended postponing construction until August 31 as required by law and to accommodate the nesting season. Construction on the grading portion of this project began September 19,2011.The grading is complete,the pipe has been ordered and will be installed shortly.The pipe installation should be completed early in December. CONCLUSION Staff recommends that the Redevelopment Agency review and reconfirm by four/fifths (4/5) vote,their previous action taken on February 1,2011,authorizing staff to continue with the actions taken to perform emergency grading and the re-installation of a storm drainage system to address drainage within the Portuguese Bend Landslide and approve the attached budget resolution to carry forward the remaining budget required to complete this project. RDA A-2