Appendix-FAppendix F
Detailed
Alternative
Design
Discussion
Cil)'or R:l.ncho Palos Verde-s Sml Ramon Dl':l.inage SJ'Slcm _Proicrl Study Report
Appendix T'-Storm D~in /\!ternalh·cs Data
APPENDIX F -STORM DRAIN DESIGN ALIGNMENT ALTERNATIVES
The aerial topographic survey specifically obtained for this study was used to layout out and
analyze several alternate storm drain design alignments.The alternative alignments were
narrowed down to two (2)primary storm drain alignments,each with a "sub-option"extension to
the Upper San Ramon Canyon,as well as a low-cost possible alternative,and a "no cost-or do
nothing alternative.This resulted in a total of six (6)alternatives (1A,1B,2A,2B,3 &4)
being considered for the San Ramon Canyon Drainage Study (see Appendix F).Following is a
discussion of each alternative alignment along with a summary of all the associated issues
affecting the alternative,including pros and cons that will help determine the preferred solution
for the San Ramon Canyon Drainage System.
A.Alternative 1A -Mid-canyon inlet with "tunnel alignment"that outlets to the bluffs
Alternative 1A consists of a mid-canyon inlet with 54-inch HDPE pipe in a "tunnel
alignment"that outlets to the bluffs.The entire length of this storm drain alignment falls
within the City of Rancho Palos Verdes (RPV)allowing RPV sole jurisdiction.The
upstream terminus is a proposed inlet structure in the -middle-of San Ramon Canyon at
a location that was strategically chosen to intercept flood waters above the Tarapaca
Landslide.At this location bedrock -daylights"in the existing canyon bottom and side
walls (see Photos F1 &F2:Bedrock at "mid-canyon"invert and downstream
adjacent wall).
Photo F1 Photo F2
Pll*iF3-_Harris &AssociatesPagelof35
The storm drain then conveys flows to the southwest in a ~tunnel alignment-
approximately 1,900-feet in length with no horizontal or vertical grade breaks (to facilitate
construction) to a launching pit location just south of 2S ltl Street I PVDS.(The tunnel
construction will actually proceed uphill from the
launching pit until it daylights in the canyon invert
just downstream of the proposed inlet structure
location.)The method of installation going
downstream from the launching pit then changes to
open cut trenching.At this location,there is a
horizontal angle point and vertical grade break in
order to bring the alignment parallel with the
RPV/CLA boundary line.The alignment will remain
within an existing 100-foot wide utility easement
dedicated within the RPV-owned Palos Verdes
Shoreline Park I Open Space that was specifically
set aside for just such an installation.The 100-foot
(ill'or Rlmcoo Palos Vcnl~San Ramon Dnil1ll&(S)'$t(m -ProiC'(:t Stud)'Rqx)R
,\ppmdi:l"r -Storm Dr.lin Altcrnali\·~D:l.1:l.
wide easement has lesser environmental impact requirements and also serves as a
firebreak for the adjacent mobile home park and a hiking trail path passes through it to
the ocean (see Photo F3).
The open trench reach proceeds downstream approximately 1,700-feet to a point just a
couple of hundred feet from the ocean bluff top where a launching pit is proposed (see
Photo F4).From the launching pit,which will proceed downstream due to intent to
minimize access impacts on the beach,a 38%sloped slant drain would be tunneled
approximately 300-feet to Kdaylight"at the bottom of the bluff face (see Photo F5,which
would be similar to the recent McCarrell Canyon Storm Drain slant drain tunnel outlet &
structure,see Photo F6)with an outlet structure being constructed at the bottom of the
bluff,with the pipeline above the high tide mark.
PliiIo F4
Alternative 1A Facts:
•Tributary area =123.7 acres
•050 =144 cfs (FYI only)
•Q100 =170 cfs (Actual system>Q100)
• Mid-canyon inlet structure
•48-inch HDPE mainline (req'd for Q100)
•54-inch HDPE mainline (recommended
to minimize the PCC annular backfill in
the tunnel &allow a future liner)
•Bluff bottom outlet structure
•Total Cost:$19.2 million
PliiIo F5
PIlrIo F6
To end the viscous cycle of the canyon's historical erosion problems generated I fed by
the Tarapaca Landslide,a ·gravity buttress·fill of approximately 20 to 3D-feet in depth
would be placed from the new mid-canyon inlet structure downstream along the entire
canyon limits of the existing Tarapaca Landslide (see Section E-E on Alternative 1A,
Sheets 5 of 6 and 6 of 6 in Appendix G)which would raise the existing canyon's invert
and flatten the side slopes of the canyon.
Page 2 of 35 IIHarris &Associates
Cit)'of Rancho 1':1105 Verdes 52n Ramon Drainagr S)'Stml -Project Sllld)'Rcpon
/\ppnxlix I'_Storm Dmn /\lttrrt:lth''''S Data
The -gravity buttress·fill within the canyon would also support Palos Verdes Drive East
switchbacks and combined with the proposed storm flow diversion would end the threat
of a potential failure of the switchbacks that is deemed possible if the present rate of
erosion tqward the switchbacks continued unchecked.The interception of the canyon
flows at mid-canyon and the raising of the invert by filling the canyon would further
prevent erosion of the canyon invert and as a bi-product,would eventually stabilize the
Tarapaca Landslide (see previous Photo 2 of PSR).Ungrouted rip rap rock energy
dissipators are proposed at regular intervals to flatten the invert grade and control I
concentrate the energy dissipation in these rock-lined areas.No grout is proposed
because the rip rap is then less likely to be undermined and the rock can naturally self-
level and compact in the unlikely event they experience significant flows (but should not
occur since only local tributary flows from the adjacent canyon slopes and perhaps a
"low flow"bypass flow would be all that this raised canyon invert should ever
experience).
The interception of the flows at mid-canyon would also significantly decrease the amount
of flows that are currently flowing to the existing CLA storm drain system at 25 th Street
resulting in elimination of the flooding and debris deposition at 2S It1 Street (see Photos 6
& 7 ofPSR).
MTD Transfer of Alternative 1A:The option of transferring the maintenance of the
Alternative 1A storm drain via the Miscellaneous Transfer Drain (MTD)process to the
County of Los Angeles Land Development Department (LAC)is unfortunately not
possible due to the following:
•Paved vehicular access to inlet,outlet &entire storm drain length:LAC
requires that a paved vehicular access road be provided to inlet structure (which
we will be providing),outlet structure (which we will not be providing due to
sensitive environmental constraints and self-cleaning nature of the proposed
steep outlet apron)&along the entire storm drain length (which is not physically
possible or environmentally desirable along the 33%slopes below the PVDE
switchback,nor would it accomplish anything even if it was constructible because
there is no proposed mid-line access to the very deep tunnel alignment.
•Manhole access spacing requirements:LAC's manhole access spacing
requirements along the length of the storm drain (per Chapter 36,Private Drain
Plans and Supporting Data)set the manhole spacing at SOO-feet.Alternative 1A
proposes a 1,900-foot tunnel alignment without manholes due to its depth,which
approaches 100-feet below existing ground surface.As such mid-line manholes
in this reach are not presently being contemplated for the proposed tunnel
portion of the Alternative 1A storm drain.
•Velocity control rings restrictions:LAC does not allow velocity control rings to
be used in pipelines that may potentially cany debris-laden flows.Since it is
anticipated that high velocities will be generated (proposed velocities would
range from 19 fps to 48 fps if no velocity rings are introduced),and since
velocities above 40 ftIs are to be avoided,velocity rings will be recommended I
required.HOPE velocity rings are available and regularly utilized I factory
welded inside HOPE pipe at regular intervals to slow down flows.
Page 3 uf 3S IIHarris &Associates
Cil)'or Rllncho PaIo$V~rdcs San R;IIT1on Dl':linage Sj'Slem -ProjCC1 Stud}'Rcpon
t\ppcndix r -Slonn Dn]n AII~ITIllIi\"C5 [hIll
•Reinforced Concrete Pipe:LAC does not typically allow the use of HOPE pipe.
Instead they strongly prefer RCP and LAC staff noted that only for fare
exceptions have they allowed HOPE,specifically it was allowed for an above
ground installation down a steep slope.Although it is not altogether
inconceivable that we could get LAC to approve the use of HOPE pipe,it would
at a minimum lengthen the LAC approval processing time for the project.
Fifteen Point Analysis of Alternative 1A
The following addresses Fifteen (15)majof issues associated with the Alternative 1A and will
similarly be addressed for all of the other alternatives and are rated in a summary chart on
page 28 of the PSR.
1.Project costs:
• Construction:$12.4 million
•PS&E =$1.0 million (8%assumed)
•Design Admin I CM I Inspection =$1.0 million (8%assumed)
•RJW and Easement =$175,000 (place holder cost if necessary)
•Environmental Mitigation =$200.000
Grand Total =$19.0 million (includes 30%contingency)
2.Project Schedule:
Funding Procurement Period:
PS&E Design Phase:
MND Prep &Approval:
CLA Review &Approval:
Obtain RJW &Easements
Bidding I Award Phase:
Construction Phase:
Approximate Total Time Required:
:..Months (Can overlap with PS&E Design Phase)
12 Months (Includes additional geotechnical study)
18 Months (Can overlap with Design I Bid Phase)°Months (Not applicable to Alternative 1A)
12 Months (Can overlap with PS&E Design Phase)
6 Months (Includes advertise/bid/award/contracts)
17 Months (See below for additional breakdown)
35 Months or 2 Years &11 months·
*NOTE:If funding can be obtained during the same overlapping period that the PS&E Design
Phase is completed and the Mitigated Negative Declaration (MNO)environmental clearance
documents can overlap with both the design and bidding phases then construction of Alternative
1A could be completed as soon as Winter 2014,assuming that the PS&E Design Phase could
begin as soon as Summer 2011 and funding is secured within the next 2-years.
Construction Schedule Breakdown
Mobilization I Clearing &Grubbing I Rough Grading =
Canst launch pit access shaft for short tunnel =
Canst short steep tunnel (60 day shifts)
Canst downstream outlet structure =
Canst open trench reach between tunnels (1,700')=
Canst launch pit access shaft for long tunnel =
Canst long tunnel (170 day shifts)
Canst canyon buttress filiI new creek invert =
Canst access road to upstream inlet structure =
Page"or 35
4 weeks
3 weeks
12 weeks
4 weeks
4 weeks
3 weeks
34 weeks
6 weeks
6 weeks
IIHarris &Associates
Cit)'of R~ncho Palos Vndn San R:lmlXl Dr.tinagc Sptcm -I>roiea Stool'Rcpon
/\ppnxlix F -Slonn Drain /\hcrn::ul\'cs [hl:l
Canst upstream inlet structure =
Demobilization I punch Jist I Clean up I hydro-seed =
Sub-Total Construction Period =
20%reduction due to overlapping operations =
Grand Total Construction Period =
6 weeks
4 weeks
86 weeks (21.5 months)
17 weeks (4.5 months)
69 weeks (17 months)
3.Constructability issues:
•Stability of canyon walls at mid-eanyon inlet structure:The stability of the
canyon walls during the construction of the mid-canyon inlet structure is of
primary concern,however,it is an issue that is common for all alternatives and
as such is not a distinguishing feature between the alternatives.Specifically,it is
anticipated that the grading for the permanent access road,which will be utilized
to maintain the inlet structure in the future,be performed to allow construction
equipment access to the mid-canyon inlet structure location.(Also see the
Tarapaca Landslide backfill discussion that follows,which suggested the
stabilized I backfilled canyon may also provide a suitable temporary access road
to the inlet structure location.)It is envisioned that cast-in-drilled-hole (CIDH)
soldier piles will then be installed at an even intervals such as 8-feet (exact
spacing pending future PS&E phase design refinements)all around the outside
perimeter of the inlet structure headwall and wing walls similar to the two soldier
pile used to construct the headwall at the outlet structure on McCarrell Canyon
storm drain (see Photo F6).Once the CIDH piles are in place (extending all the
way up to the proposed inlet structure top of wall elevation)then the grading of
the existing canyon slopes can begin with thick steel plate shoring being placed
behind the piles as excavation proceeds downward (similar to photo F6).Once
the proper sub-grade depths are achieved the invert of the inlet structure can be
formed and constructed.Eventually the headwalls and wing walls will be formed
and constructed high into the air well above the canyon floor and then backfilled
to create a large level area to each side of the inlet structure.The inlet structure
will have an emergency overflow notch that ideally will never be breached
because the wall will have many feet of excess freeboard and the wall will serve
as the upstream beginning point for the 20 to 3D-feet of canyon fill that will be
placed downstream well past the Tarapaca Landslide location to create a "gravity
buttress"that will eventually stabilize the canyon walls.
•Stability of canyon walls at Tarapaca Landslide:The stability of the canyon
walls within the Tarapaca Landslide area during construction is of primary
concern,however,it is an issue that is common for all alternatives and is actually
less of an issue for this Alternative 1A since the added step of installing a large
mainline storm drain pipe within the canyon backfill does not apply to Alternative
1A.Thus the canyon backfill operation will actually be more simplified for
Alternative 1A than for any other alternative.As previously mentioned the -gravity
butlress"filt of approximately 20 to 3D-feet in depth would be placed from the
new mid-canyon inlet structure downstream along the entire canyon limits past
the existing Tarapaca Landslide area then eventually tapered down to join the
existing canyon invert downstream (see Section E-E on Alternative 1A,Sheet
6 of 6 in Appendix G)which would raise the existing canyon's invert and flatten
the side slopes of the canyon.Additional temporary shoring methodologies and
other related constructability issues need to be detailed during the future PS&E
Page 5 of 35 IIHarriS &Assodates
Cily of Rgncho P:l.los Verdes S,m Rgmon D....in:l&C'S)'Slrol -Pmjt"O SlUdl'Rcpon
J\ppmdilt r -Slonn Dr:ain i\hanat.i,·es D:ng
Design Phase.Special full time emergency monitoring will be also be required
until enough of the buttress fill has been placed.The grading will likely be a trial
and error process of reacting to localize movement and even causing controlled
movement that can be graded into place and compacted in lifts.
The actual process to place the fill,starting from the bottom.will include minor
grading (if any)and placement of a thin layer of base rock (to avoid undercutting
the slide toe and to create a relatively level pad)and then placement of filter
fabric to hold back ·fine particles·.The excess filter fabric material on each side
of the canyon floor,which will wrap the sides and top of a rock galley sub-drain,
will be pinned up onto the sides of the canyon wall while another layer of base
rock is placed,then a 12-inch perforated PVC sub-drain will be installed,
additional galley rock placed and then the fabric will be folded over into place on
top of the rock galley.After the sub-drain rock galley is complete the placement
of the canyon backfill can begin in rapid fashion and "keyed"into the existing
canyon slopes via multiple stepped "notches".It is anticipated that imported
backfill will be required in conjunction with the existing canyon excavation that
will undoubtedly be spilling into the backfill operation as the grade is raised
higher and higher.Eventually the width of the backfilled canyon will be
comfortably wide and the adjacent canyon slopes will stop spilling into the
operation as that grades approach the designed raised canyon flow line
elevation.It is even conceivable that this stable canyon access path could be
used as an alternative temporary access road to the inlet structure site during
construction.Eventually rip rap energy dissipaters will be placed and the canyon
invert and flattened slopes will be hydro-seeded with an approved native plant
mix in combination with jute mesh,fiber roles and other recommended erosion
control measures that will allow the plants time to get established.
•Access road to mid·canyon inlet structure:As previously mentioned there are
two opportunities to provide temporary access down to the inlet structure location
and it is likely that both will be utilized to provide redundancy,safety and
improved access logistics (such as a round trip path without having to turn
around or get out of the way of other vehicles and haulers).Eventually the
canyon path will not be drivable,once the rip rap energy dissipaters that include
vertical drops are installed,and then the only permanent access road to the inlet
structure will be the proposed long~term maintenance access road (see Access
Road Plan in Appendix G).The conceptual plans presently show the access
road being cut into the easterly canyon slope from the Tarapaca Road cul-de-sac
and would also double as a terrace drain that would intercept sheet flow from the
canyon slopes above the Tarapaca Landslide ·head-scarp~thus preventing water
from infiltrating into the slide area from above (see Section A-A on Access
Road Plan in Appendix G).However,upon further geotechnical investigation,it
has been determined that the stability of the easterly canyon slopes is not the
best should not be challenged by such potentially impactful grading.Thus an
alternative temporary I permanent access road to the inlet structure should be
considered from the westerly canyon slopes taking access to the PVDE
switchbacks.A small ·brow ditch~V-gutter can still be installed on the easterly
canyon slope above the Tarapaca Landslide ·head-scarp·to prevent water from
infiltrating.With the access road on the westerly slope it also provides an
improved opportunity to interconnect and coordinate with the switchback
drainage pipe systems that are causing some erosion on the westerly canyon
slopes and the access road could collect these flows,serve as a terrace drain
Page 6 of 35 IIHarris &Associates
City or RmKho Palos Veroo S:m Ramon Dfliinage Sl'stem -Project Smell'Report
Appeneli"r _Stonn Dr:un Altern:atkes D:lIa
and convey the flows toward the new inlet structure.Any grading of an access
road along the westeny canyon slopes will also likely require the construction of
retaining walls in order to get a relatively level driveway along the relatively steep
slopes.It is presently envisioned that a CIDH soldier pile retaining system or a
soil nail tie back system (methods pending the future PS&E design phase)will be
utilized to construct the access road.The permanent retaining system will likely
have to be placed to even allow a temporary access road to be graded.
Ultimately an all weather paved surface will be constructed along the access
road wearing surface that is capable of withstanding heavy truck loads and
conveying storm flows like a terrace drain.
•Tunneling operations (1,900'upper reach):The constructability of the
proposed 2,000-foot long tunnel along the upper project reach from the inlet
structure to just downstream of 25 th Street I PVDS has been confirmed with
tunneling experts.After closely studying the proposed design alignment and
PhoIo F7 PIiiIo F8
geotechnical conditions it is strongly recommend that the tunneling operation
consist of traditional ~rib and lagging~supports (see photo F7)that are placed
behind a fully shielded excavator (see photo F6)and can be retrofitted mid-
construction with a rock crushing roadheader rock breaker (see photo F9)if high
strength bedrock is encountered that the excavator bucket is not capable of
removing.One important feature that will help to make sure the tunneling
operation is a success is the fact that the tunnel face will be Mmanned~which puts
PI1JIo F9 PIltFl0
a set of human eyes constantly monitoring the progress and conditions (similar to
Page 7 of35 Harris &Assodates
Cil)'of R:mcho P:lJos Vndes S,m R,,1I\OIl D....in:lge S)'SICl1I-Pro~5100)'Report
I\ppmdi);r -SlOnn O ....in Aharuui\'e:5 Dal"
the McCarrell Canyon Storm Drain)rather than a -blind-drill head that can
become stuck or damaged before a change of conditions is noticed.The tunnel
length proposed is regular1y constructed by this method and the lack of
groundwater combined with the anticipated rock and soil types all consistently
point to this method.Before this conclusion was arrived upon other alternative
tunneling methods were considered like microtunneling with a slurry retrieval
system but the length,soil conditions,design alignment and size would result in
microtunneling being a much riskier and more costly operation.The tunnel will
likely have an inside diameter of BO-inches and the round steel "ribs·will be
constructed from W-section (J~shaped beam)material bent into three
prefabricated ring sections (see Photo F10:complete "rib &lagging set"
ready for delivery to tunnel)that form a full circle when connected.The lagging
will create 5~foot long wood ~barrels·constructed from 3~inch x 8~inch x 5~foot
long Douglas fir boards placed like wood slats in a barrel around the rib rings and
held in pace by the steel flanges of the regular interval steel ribs.This also allows
the flexibility to stray from a straight alignment,if need be,but we are specifically
planning on a straight alignment so that a simple laser can control the alignment
instead of complicated surveying methods.The rib and lagging is expanded into
place by hydraulic jacks at the back of the shielded excavator unit, which allows
the tunnel to compress into the surrounding soil.The shielded excavator unit
then pushes itself forward on the rail car rails using the last set rib and lagging.
Rail cars on a small gage railroad track alternate between hauling out the
excavated -muck-and hauling in a new rib &lagging set.A small receiving pit will
be graded and shored at the upstream end at or near Station 50+00 (see
Alternative 1A,Plan Sheet 4 of 6)and would daylight in the existing canyon invert
at the proposed inlet structure location.
POOIoFl1
•Outlet Structure at the Bluff
Bottom ,Beach:The
constructability of the proposed
outlet structure at the bluff
bottom'beach is anticipated to
closely resemble the successful
recently constructed McCarrell
Canyon Storm Drain outlet
•Tunneling operations (300'lower "slant drain"reach):The constructability of
the proposed 300-foot long lower "slant drain·tunnel is anticipated to closely
resemble the successful recently constructed McCarrell Canyon Storm Drain
"slant drain"tunnel (see photos F6 &F11)and as such is expected to be very
constructible.The tunnel would end at the 140-foot high bluff bottom with soldier
piles to shore of the bluff toe similar to the McCarrell Canyon tunnel.It is also
anticipated that the tunnel will be hand mined through the solid bedrock bluff
which is similar to McCarrell Canyon bedrock and a jack~&~bore steel sleeve
would be pushed forward as the rock is jackhammers at the tunnel face at a rate
of 2 to 5-feet per day.The tunnel operations would take place from a launch pit
on top of the bluff in the flat
landing area approximately 200-
feet back from the edge of the
bluff at an approximate slope of
38%.
Page 8 of 35 Harris &Assodates
OIY or R:mcho P:llos Vcrdes S:m Ramon Dr.lin:tge SYStCfll -Proica SlUdy Repon
Appcnd.i.:f _Stonn Dmn Altcm:l.ti\'t'S D:lt"
structure (see previous photo 17 &photo 22 in PSR)and as such is expected
to be very constructible.The tunnel would end at the 140-foot high bluff bottom
with soldier piles to shore of the bluff toe similar to the McCarrell Canyon tunnel.
The pipe outlet would be located well above the high tide line to avoid potential
wave damage and the wing wall walls will hold back the adjacent bluff slopes and
transition into a wider beach ·apron-that allows the flow to spread out and slow
down.The Beach apron will include large ·sound-beach boulders to help further
dissipate the flow velocities and protect the beach from erosion.
•Potential for collateral damage in adjacent structures:Prior to
commencement of construction,vertical (extensometer)and horizontal
(inclinometer)ground movement monitoring systems will be placed during the
construction phase as well as a long~term array of multiple survey monitors
placed during this study phase to monitor the movement of the ground within San
Ramon Canyon before,during and after construction.Further,a detailed photo
and video documentation survey will be required of all adjacent structures
(especially along the Tarapaca Road cul-de-sac dwellings)to define all pre-
existing conditions.The combination of all of these methods will protect all
interested parties against any frivolous claims,especially if it can be proved that
no ground movement occurred in the hillside plain between the construction site
and private properties.
4.Availability of Material and Methods:
•HOPE pipe:High strength 54-inch inside diameter HOPE pipe (butt fused)is the
size and type of pipe material recommended for this alternative.HOPE is
somewhat flexible,chemical and corrosion resistant,lightweight, strong and
ductile.It is ideal for this project due to the steep grades since its fused welded
joints create seamless pipe.It will stand up well to the anticipated high velocities
and can be fitted with HOPE velocity reducer rings.The anticipated sediment-
laden flows will cause some scouring but HOPE holds up well and since the 54-
inch inside diameter is oversized to reduce the amount of PCC to placed in the
tunnel annular space it can be lined in the future,if needed.
•Fill:In order to stabilize the canyon walls,it is recommended that a substantial
amount of fill be placed to elevate the canyon invert and to decrease the vertical
slopes of the existing canyon walls.It estimated that 44,770 cubic yards of fill
would be required to achieve the new canyon flow line and cross section (see
Section E-E on plan sheet 6 of 6 for Alternative 1A in Appendix G).Per the
geotechnical report,the excavated material for the tunnel and trench section is
suitable as backfill.It is estimated that the excavated tunnel materials would
produce approximately 3,000 cubic yards of usable backfill material.The City has
indicated the Portuguese Bend is also a possible source of fill materials that
would not require hauling and traffic impacts outside the RPV peninsula area.
The logistic of when the tunnel excavation is available relative to when the
canyon fill will be placed has yet to be defined,but will be further evaluated
during the PS&E phase of the project.
•Tunneling Equipment:The two proposed tunneling construction methods and
related vertical and horizontal ground movement monitoring systems during
tunneling will require equipment that is readily available and can easily be
mobilized to the site.
P:lge 9 of 35 IIHarris &Associates
Page 10 of 35
Cit)'of R:mcno P:tlos Vada San Ramon D ....inage System -I'ro;ea Stud)·Report
i\ppmdi,;r -Stonn D....m Ahemam'cs DaI1l
5.Contractor's Expertise Required:
Several competent tunneling contractors are known to practice in the local area and
given the percentage of tunnel length to open trench length proposed the tunneling
contractor will likely prime the project bid.The challenge will not be finding
contractors to bid,instead it will be to make sure only competent experienced
contractors qualify to bid.To make sure this happens the contractor performing the
tunnel construction work (whether subcontractor or prime contractor)shall have
performed a pre-established number (say two or three minimum)of steel rib and
wood lagging shored tunnel projects for a continuous length in excess of 1,000 lineal
feet,with a diameter of six feet (6')or larger,within the last five years.The tunnel
contractors will also be required to have completed at least one tunnel with minimum
grade I slope of 25%for at least 250 lineal feet in length with in the last five years.
6.RJW and Easement Requirements:
The proposed Alternative 1A storm drain alignment and westerly canyon slope
access road would all be completely within the City of Rancho Palos Verdes with
only limited work being required on private property (namely 0.10 acre within LAC's
Friendship Park,0.09 acres within APN 7561-039-006 and 0.16 acres within APN
7561-039-002 for a total of 0.35 acres).Although it is anticipated that the City will be
granted no-cost construction easement for Alternative 1A because the drainage
system will be beneficial to the adjacent property owners,for worse case estimation
purposes,a $500,000/acre placeholder cost has been included in the project
estimate.Additional reasons why a no fee easement may be assumed include the
fact that the adjacent residences along Tarapaca Road are supportive of the project
(confirmed at the community meetings)and the adjacent Friendship County Park is
owned by LAC who is also supportive of the project.A temporary construction
easement may need to be obtained from the property owner adjacent to 25th Street
if access to the canyon is required from the south.If a permanent access road is
pursued from the easterly canyon slope (per geotechnical recommends this is now
not likely)then an easement would be required from the CLA and two other private
owners.
7,Environmental Impacts:
The Mid-Canyon Inlet Alternative 1A will have least significant environmental
impacts of any alternative because it affect the least amount of natural canyon
slopes and inverts (pristine or otherwise)and utilizes tunneling installation methods
which are the least impactful to the protected open space areas and natural bluffs.
The following details feature by feature why the Mid-Canyon Inlet Alternative 1A will
have least significant environmental impacts of any alternative:
•Canyon Walls and Inverts:The Mid-Canyon Inlet Alternative 1A impacts the
least amount of natural canyon slopes and inverts (pristine or otherwise)of any
alternative.Further,both the Mid-Canyon Inlet Alternatives 1A and 2A will have
less significant impacts than the two Upper San Ramon Canyon Connection
Alternatives 1Band 28 due to the latter's more extensive invert filling operations
that are required in the more pristine upper canyon,including extensive grading
and filling operations.Further,it has been noted that the upper canyon is more
stable,suffers less from erosion,has more bedrock outcroppings and has a
IIHarris &Associates
Cil)'or R~ncho 1'2105 Vtrde!S~n Ramon Drainage S)'Slem -ProjKl Sloor Repon
Appcndil<r _SIOffli Drain Ahem:l.li\'e!D:u~
rockier invert in general.This is largely what is driving the Mid~Canyon Inlet
Alternatives 1A and 2A to stop where they do because upstream from that point
the canyon is more natural and stable thus being a much lesser priority to disturb
it.Many hilltop homes look down to this natural upper canyon thus their pristine
canyon views would also be more impacted by Alternatives 18 and 28 than 1A
and 2A.
•Tarapaca Landslide:All of the alternatives will remedy the Tarapaca Landslide
conditions utilizing similar methods so this item is not a distinguishing factor
between the alternatives.Regardless it is worth noting that the solution to place a
20 to 30~foot high buttress fill will return the canyon back closer to its original
natural creek state.The 30~foot high near vertical canyon walls are an unnatural
condition that send too much sediment down the creek.The proposed solution
will be more beneficial to native flora and fauna and will be more sustainable in
the long run.
•Two Tunneling Locations:The two tunneling alternatives 1A and 18 will utilize
tunneling installation methods which are the least impactful to the protected open
space areas and natural bluffs.
•Open Trench Excavation Location:The open trench portion of Alternative 1A
impacts the least pristine area (compared to the open trench installations in San
Ramon Canyon)and is proposed in a 100-foot wide easement corridor
specifically set aside for such purposes.The adjacent natural open space
remaining untouched,
•Inlet Structure and Access Road:All of the alternatives will require either a
large or small mid-eanyon inlet structure and accompanying access road (so that
the Tarapaca Landslide buttress fill downstream will be protected)thus this item
is not a distinguishing factor between the alternatives.Regardless it is worth
noting that the natural canyon has been identified as being fairly barren of native
plants and animals but will likely improve once the canyon is stabilized and re~
hydro~seeded.
•Outlet Structure:Although the proposed Alternative 1A (and 18)outlet structure
will impact a small portion of the natural bluff bottom and beach,these impacts
have already been mitigated by RPV's proactive actions to set aside open space
to mitigate even larger impacts than are proposed by the project.Also the
proposed outlet structure will be camouflaged to some extent,similar to (and
hopefully even more so on the side slopes outside the wing walls)the recent
McCarrell Canyon outlet structure (see previous Photo F11)through the use of
bluff color concrete,irregular texture patterns stamped into the surface and the
use of natural beach rock embedded into the beach apron (which also collects
beach rock from the wave action as the McCarrell Canyon beach outlet shows).
8.Geotechnical Issues:
•Tarapaca Landslide:To evaluate how much fill is required in the canyon bottom
to act as a ~gravity buttress~,cross sections of the canyon were analyzed with
various heights.The results of these analyses indicated that approximately 20 to
Page 11 of35 Harris &Assodates
Cit),of R~n(ho 1>:'105 Verdes S~n R~mon Dr,lin:tgc Srslcm -ProjCCl Stud)'Rcpon
Appendi,;f'-Storm Dr,lin Altcm~li\'es Dat~
30 feet of fill placed in the canyon at the toe of the landslide would be required to
obtain a safety factor of approximately 1.5.Note this is true for all alternatives.
Additional temporary shoring method need to be detailed during the future PS&E
Design Phase.
•Canyon Walls:The result of the stability analyses for the canyon slopes below
the PVDE switchbacks indicated that where continuously adversely oriented
bedding plains that are not exposed in the bluff face.The existing in-place factor
of safety (FS)of the canyon walls is likely in the range of 1.3 to 1.4.Where
adversely oriented bedrock exists relative to the canyon wall -such as in the
area of the Tarapaca landslide -failure has either already occurred and/or the
current slope stability factor of safety is in the range of just above 1.0 to 1.2 (FS =
1.0 indicates movement is eminent).In addition,local occurrences of adversely
oriented planar bedrock surfaces may also result in local small failures.
•Pipe /Structure Design:Pipe design and appurtenant structures should take
into consideration potential movement of adjacent slopes and the landslide mass.
Minor movements in localized areas may occur during construction and during
the life of the storm drain system.
•Tunneling:
i.Hard siliceous zones or blocks of materials should be expected to be
encountered during tunneling.
ii.Some of the Altamira Shale member bedrock cores swelled after being
exposed to the air for several days.The swelling is attributed to air drying
and potentially secondary mineral crystal growth.The swelling will create
pressure on the ground supports installed for the tunnel construction.
m.Tunneling may encounter local zones of adversely oriented geologic
discontinuities that may be lined with Bentonite.These zones may produce
local stability problems during tunneling.NOTE:If excess void pockets are
generated during the tunnel construction they can be subsequently injected
with pressurized grout backfill while the tunnel operation progresses forward.
iv.The proposed tunnel will be excavated through fair to poor rock and stand-up
time during tunneling is expected to range from 10 hours to 1 week for an 8-
foot to lS-foot span.
•Trench Excavation:Based on the preliminary evaluation and the results of the
geotechnical engineer's field exploration,variable stability conditions will be
encountered in the open trench walls during construction of the storm drain south
of 2S tIl StreeVPVDS.Some local areas may be temporarily unstable,particularly
within the deeper areas of the trench;therefore,shoring or trench wall lay-back
slopes will be required.Further exploration and analyses will be required in order
to provide detailed shoring and temporary stability recommendations during the
PS&E phase.However,for the purposes preliminary design alternative
evaluations,trench waifs excavated at a slope of 1:1 (horizontal to vertical)
should be anticipated to be temporarily stable.
Pagc12uf35 IIHarriS &Assodates
Cil)'or Rancho PaJos Verdes San Ramon Dminage S)'stem _Proiect SIIKI)'Report
I\p~ndi>:F ~SlOnn Dl':I.in l\hcrnati\'C$D:lta
•Backfill of Pipe Bedding:It is anticipated the onsite soils will be suitable for
backfill of the trench above the pipe bedding zone.Some oversize materials will
likely be encountered,and will not be suitable for placement within the backfill.
•Inlet Structure:While the canyon slopes at the propose inlet structure location
may be grossly stable during construction,surficial slumping or localized ~pop
outs~are likely to occur.The design of the structure should take into
consideration highly expansive soils.It can be assumed that shoring or other
stability methods (i.e.CIOH piles,caissons,sheet piles,etc.)will likely be
required for temporary stability.
•Outlet Structure:While the bluff in the area of the proposed outlet structure
location may be grossly stable.minor surficial slumping or localized "pop outs"
may potentially occur.It is anticipated that the outlet structure will be founded on
bedrock or ancient landslide debris and keyed into the bluff toe with the
previously detailed soldier piles.The design of the structure should take into
consideration highly expansive soils.
•Access Road:Bedding orientations in the area of the presently detailed easterly
canyon slope access road will result in adversely oriented bedrock exposed
during grading of the road.This easterly road would be located upslope of the
currently moving Tarapaca landslide,and directly downslope of existing
residential development.The wall design will need to accommodate adverse
structure,and temporary instability will require corrective grading,and structural
support such as tiebacks.In addition,alternative paving that may accommodate
expansive soils and slope creep.BOTTOM LINE:Per the geotechnical report
conclusions the access road should be relocated and design from the PVOE
switchbacks along the westerly canyon slope to the inlet structure -Harris &
Associates concurs.
9.Flood Protection:
•Upstream of 25 th Street:The proposed storm drain will be design to convey a
1OO~year (plus)storm reoccurrence.
•Downstream of 25 th Street:The existing CLA storm drain south of 25 th Street
was designed to roughly convey a 50~year storm event (see previous discussion
about doubts that it will perform well under a full 050 storm).A
Hydrology/Hydraulic study was done by Harris &Associates and it was found
that the existing system can convey the flows of a 50~year storm but the resulting
velocities ranging from 19 fps to 46 fps,with the velocities ranging closer to 48
fps.Per the City of Los Angeles as-built plans,the pipe was not specified to
have extra thickness cover over the steel to handle the high velocities.BOTTOM
LINE:The deficiencies in the existing CLA Storm Drain system will experience
significant relief due to the proposed construction of Alternative 1A,which is not
the case for the down canyon Storm drain Alternative 2A that would connect
directly to the CLA system.
10.Impacts to the City of Los Angeles (CLA):
Since the proposed Alternative 1A storm drain alignment and westerly canyon slope
access road would all be completely within the City of Rancho Palos Verdes the
anticipated impacts to and involvement by CLA would be minimal,perhaps relegated
to funding participation and project advocacy /fund lobbying.Since the existing
Page 13 or 3S IIHarris &Associates
City of Rancho P:llos Verdes San Ramon Dr:linagc S}'stem -Project Stud}'Report
Appendix F -SlUm,D~in Alternatives Data
storm drain system,south of 25 th Street,would remain in place and would convey
less flows than originally designed there would be an increase in the overall area's
flood protection level with RPV taking the lead on the design and construction effort,
which should be very acceptable to CLA,
11.Impacts to the Los Angeles County (LAC):
As long as the alignment of the access road is not on the westerly canyon slope and
shifted away from the easterly canyon slope and thus not going through Friendship
Park (LAC's property)only a small easement,if any would be required from LAC.
Further,LAC mentioned their nonexistence jurisdictional authority for this project,
which would remain the case especially if a MTO process is not pursued between
RPVand LAC.
12.Impacts to Private Residents:
Residents within the Peninsula Community that use the 25th StreetIPVOS and PVOE
transportation corridors can expect to have the corridor open during the majority of
the construction schedule (only minor temporary closures anticipated)and will enjoy
full access during future rain events after construction.See previous easement
discussion for minor temporary construction easement impacts to private residences
and their considerable support for the project in general.
13.Impacts to Traffic:
Alternative 1A proposes to tunnel under 25th StreeVPVOS and PVOE switchbacks,
therefore making any traffic impacts minimal.Only minor temporary lane closures
would be allowed during construction.Traffic Control would be limited to
informational signs and some traffic control during ingress/egress of any construction
traffic int%ut of the project sites.
14.Resulting Service Life:
Alternative 1A is anticipated to have service life that is comparable to any similar
storm drain system,or even longer given a majority of the pipe alignment will be
protected by a surrounding tunnel support system and locked into place with PCC in
the annular space,The service life is estimated to be at least 75-years for the both
the HOPE pipe and reinforced concrete inlet /outlet structures.Further the service
life will be the same if not longer than the other alternatives being considered,thus
not raising the Yservice IifeM issue to be a distinguishing factor between the various
alternatives.
15.Future Maintenance Issues:
Alternative 1A is anticipated to have future maintenance requirements that are
comparable to any similar natural canyon feed storm drain system,such as the
recently constructed McCarrell Canyon SO,including regular preventative
maintenance before each winter season and more reactive maintenance after each
big storm event.This would primarily consist of make sure that the inlet structure and
debris rack are clear and free from rocks,branches and other debris and perhaps a
once a year two-man -Walk-through-inspection of the 54-inch HOPE pipe to check
for premature wear.
Page 140(35 IIHarris &Associates
Cit)'of R~llCho 1~105 Verdes S~n R~mon Dr:tinage S)'5tClll -Project Studr RqxlfI
Appendix F _StOml Dr::Un Ahcnuti\'es D:II:&
Further,as previously mentioned,since the 54-inch inside diameter HOPE pipe is
being recommended to save on the annular space concrete fill in the two tunnel
reaches there is an opportunity in 50-years or more to add a liner inside the HOPE
pipe without adversely affecting the hydraulics because only 48~inch HOPE pipe is
required.Finally,the service life of Alternative 1A will be the similar to the other
alternatives being consider,with the ·debris-Iaden flow concern-of Alternative 1A
being an offsetting concern to the Nburied pipe adjacent to a still settling landslide
concern N related to alternatives 2A and 28,since both would prompt an equal
urgency to perform in-pipe walk~through inspections,thus not raising ·future
maintenance Nissues to be a significantly distinguishing factor between the various
alternatives.
B.Alternative 1B -!:!.I!.Q!!-canyon inlet with "tunnel alignment"that outlets to the bluffs
Alternative 18 consists essentially of the exact
same design approach and alignment as
Alternative 1A,except that instead of
constructing a mid-canyon inlet within San
Ramon Canyon the proposed storm drain
alignment would be extended upstream,
consisting of a 48-inch HOPE pipe installed via
Nprepared canyon bottom backfill N installation in
an imported canyon fill along the natural canyon
invert (see Alternative 1B conceptual plans
and Typical Section 0-0 in Appendix G).The
proposed pipe installation would extend an
additional 1,3OO-feet upstream of the Mid-
Canyon inlet structure,(required for Alternative PIdoF12
1A but not for Alternative 18)and would connect with an existing upper San Ramon Canyon
storm drain outlet pipe (see Photo F12).This upstream outlet pipe structure that was
constructed as part of the slope repair and terrace drain construction performed in 2002.
The 48-inch HOPE pipe in this upper-canyon alignment would be placed above a perforated
12 M diameter pipe (see Typical Section D-D in Appendix G).No excavation below the
existing canyon floor would be done,The placement of the storm drain would be on top of
"bedding M which would be placed above the canyon floor.
The remaining alignment downstream would be exactly the same as Alternative 1A with the
only difference that perhaps a small mid-canyon inlet structure might be considered just
before the tunnel alignment veers off to the west under the PVDE switchbacks since this
would be the last chance to intercept any additional surface flows that are tributary to the
natural canyon slopes (and from the down drain for the Tarapaca Road cul-de-sac and
Tarapaca Slide ·brow ditch-above the head-scarp.
The thought process driving this ·sub-alternative-is that since the main line storm drain
flows have already been collected from the housing tract above and confined to a pipe it
may be advantageous to keep these flows in a pipe rather than allowing these concentrated
flows to again run free in the natural channel bottom.
Alternative 1B Facts:
•Tributary area =98 acres (top connection point)
P:lge 15 of35 nHarris &Associates
City of R::mcho ralos Verdes San R~mon D,..~inagt System -Project Stud),Rtport
Appendix F -Stonn Drnin Altt'rn.1.tivts D~t:r.
•Tributary area =123.7 acres (as alignment leaves Cyn into tunnel)
•050 of 122 cfs (FYI only,top connection point)
•050 =144 cfs (FYI only,as alignment leaves Cyn into tunnel)
•OHlOof 143 cfs (Actual system>0100,top connection point)
•0100 =170 cfs (Actual system>0100,as alignment leaves Cyn into tunnel)
•Upper-canyon connection junction structure
•48·inch HOPE mainline (req'd for 0100)use in upper canyon to tunnel diversion
•54·inch HOPE mainline (use from tunnel to beach,recommended to minimize
the PCC annular backfill in the tunnel &allow a future liner)
•Bluff bottom outlet structure
•Total Cost:$23.2 million
MTD Transfer of Alternative 1B:The option of transferring the maintenance of the Alternative
1B storm drain via the Miscellaneous Transfer Drain (MTD)process to the County of Los
Angeles Land Development Department (LAC)is unfortunately not possible for the same
reasons detailed in Alternative 1A (see previous write up).
Fifteen Point Analysis of Alternative 1B
The following addresses Fifteen (15)major issues associated with the Alternative 1B and will
similarly be addressed for all of the other alternatives and are rated in a summary chart on
page 28 of the PSR.
1.Project costs:
•Construction:$14.3 million
•PS&E =$1.2 million (8%assumed)
•Design Admin I CM I Inspection =$1.2 million (8%assumed)
•RfIN and Easement =$725,000 (place holder cost if necessary)
•Environmental Mitigation =$500,000
Grand Total =$23.0 million (includes 30%contingency)
2.Project Schedule:
Funding Procurement Period:
PS&E Design Phase:
MND Prep &Approval:
CLA Review &Approval:
Obtain RIW &Easements
Bidding I Award Phase:
Construction Phase:
Approximate Total Time Required:
:-Months (Can overlap with PS&E Design Phase)
12 Months (Includes additional geotechnical study)
18 Months (Can overlap with Design I Bid Phase)
a Months (Not applicable to Alternative 1B)
12 Months (Can overlap with PS&E Design Phase)
6 Months (Includes advertiselbid/award/contracts)
18 Months (See below for additional breakdown)
36 Months or 3 Years &a months·
•NOTE:If funding can be obtained during the same overlapping period that the PS&E
Design Phase is completed and the Mitigated Negative Declaration (MND)
environmental clearance documents can overlap with both the design and bidding
phases then construction of Alternative 1B could be completed as soon as Winter 2014,
Page 16 of 35 IIHarris &Assodates
Cil)'or Rnncho 1"n10$VrrdM San Ramon Dminagc S)'slcm _Pro;CC1 Slud)'Rcporl
APPCllt1ill r -Slonn Drnill Ahcmali\'cs Ihla
assuming that the PS&E Design Phase could begin as soon as Summer 2011 and
funding is secured within the next 2·years.
Construction Schedule Breakdown
Mobilization I Clearing &Grubbing I Rough Grading =
Canst launch pit access shaft for short tunnel =
Canst short steep tunnel (60 day shifts)
Canst downstream inlet structure =
Canst open trench reach between tunnels (1,700')=
Canst launch pit access shaft for long tunnel =
Canst long tunnel (170 day shifts)
Canst canyon buttress filii new creek invert =
Canst access road to mid-canyon for upper cyn const =
Canst ·prepared canyon bottom backfill·reach in
upper canyon (1,300')=
Canst upstream junction structure =
Demobilization I punch list I Clean up I hydro-seed =
Sub-Total Construction Period =
20%reduction due to overlapping operations =
Grand Total Construction Period =
4 weeks
3 weeks
12 weeks
4 weeks
4 weeks
3 weeks
34 weeks
6 weeks
6 weeks
8 weeks
2 weeks
4 weeks
90 weeks (22.5 months)
18 weeks (4.5 months)
72 weeks (18 months)
3.Constructability issues:
8ecause Alternative 18 consists essentially of the exact same design approach and
alignment as Alternative 1A all of the constructability issues raised in the Alternative
1A discussion also apply to Alternative 18,with two exceptions f clarifications:
•Small Mid-Canyon Inlet:The large mid-canyon inlet in Alternative 1A will be
replaced with a smaller mid-canyon inlet in Alternative 1B and,as such,any
issues raised in the previous Alternative discussion would also apply here,
including the need to grade an access road,but some canyon impacts would be
smaller in scale.
•Upper Canyon Pipe Line:The additional 1,300-feet of 48-inch HOPE pipe will
be installed via "prepared canyon bottom backfill-in an imported canyon fill onto
of a filter fabric wrapped rock galley with a 12-inch perforated pipe,directly on top
of the natural canyon invert.This length would connect the smaller mid-canyon
inlet structure to an existing upper San Ramon Canyon storm drain outlet pipe
(see previous photo J12).The constructability issues applicable to this reach
would be most similar to Alternative 2A,which also has proposed mainline storm
drain pipe being installed within the narrow existing canyon,except with less risk
of land movement since there is no active landslide in this area (see Alternative
2A constructability discussion that follows).
4.Availability of Material and Methods:
Alternative 18 is essentially the same as Alternative 1A (see previous Item 4 write
up).One clarification is that more imported fill will be required,but is not anticipated
to be an issue due to the excess fill available in the Portuguese Bend area.
Specifically it estimated that 67,680 cubic yards of fill would be required for
Alternative 1B versus 44,770 cubic yards for Alternative 1A to achieve the new-Page 17 of 35 _Harris &Associates
City of Rancho "alo~Verdc~San Ramon Dl1linagc S)'SlCm -Proicet Srudj'Repon
I\ppendix r -Storm Drain i\liern~til'"D:na
canyon flow line and cross section (see Section E·E on plan sheet 6 of 6 for
Alternative 1A in Appendix G).
5.Contractor's Expertise Required:
Alternative 18 is essentially the as Alternative 1A (see previous Item 5 write up).
6.RIW and Easement Requirements:
Alternative 18 is essentially the same as Alternative 1A (see previous Item 6 write
up).There are a total of 14 properties within the City of Ranch Palos Verdes for
which the City would have to acquire a storm drain easement as follows:
a.7561-038-007 -0.01 acres
b.7561-038-008 -0.02 acres
c.7561-038-017 -0.06 acres
d.7561-038-010 -0.06 acres
e.7561-038-011 -0.Q7 acres
f.7561-038-012 -0.07 acres
9.7561-033-009 -0.09 acres
h.7561-033-010 -0.10 acres
i.7561-033-011 -0.09 acres
j.7561-033-012 -0.06 acres
k.7561-033-013 -0.04 acres
1.7561-033-014 -0.01 acres
m.7561-041-012 -0.05 acres
n.7561-041-002 -0.37 acres
Total easement required for the construction of Alternative 18 is 1.45 acres.
Although it is anticipated that the City will be granted a no-cost construction
easement for Alternative 18 because the drainage system will be beneficial to the
adjacent property owners,for worse case estimation purposes,a $500,OOO/acre
placeholder cost has been included in the project estimate.
7.Environmental Impacts:
Alternative 18 is essentially the same as Alternative 1A,with the exceptions that
more pristine canyon will be affected and that the view of additional private residents
would be affected by Alternative 18 because more of the canyon floor will be
disturbed by the extended pipe length (see previous Item 7 write up).
8.Geotechnical Issues:
Alternative 18 is essentially the same as Alternative 1A (see previous Item 8 write
up).
9.Flood Protection:
Alternative 18 is essentially the same as Alternative 1A,with the exception that
additional protection could be argued to apply to Alternative 18 because more of the
canyon floor is protected from erosion by the extended pipe length (see previous
Item 9 write up).
10.Impacts to the City of Los Angeles (CLA):
Alternative 18 is essentially the as Alternative 1A (see previous Item 10 write up).
11.Impacts to the Los Angeles County (LAC):
Alternative 18 is essentially the same as Alternative 1A (see previous Item 11 write
up).
Page 18 of 3S ==Harris &Associates
Cil)'of Rancho Palos Vades S;lIl RanK)fl Dnirug~Sl'Sttm -Project Stud)'Rcpon
I\ppmdix f -Storm Drain Ahtrruu;"e5 Data
12.Impacts to Private Residents:
Alternative 18 is essentially the same as Alternative 1A,with the exception that the
view of additional private residents would be affected by Alternative 18 because
more of the canyon floor will be disturbed by the extended pipe length (see previous
Item 12 write up).
13.Impacts to Traffic:
Alternative 18 is essentially the same as Alternative 1A (see previous Item 13 write
up).
14.Resulting Service Life:
Alternative 18 is essentially the same as Alternative 1A (see previous Item 14 write
up).
15.Future Maintenance Issues:
Alternative 18 is essentially the same as Alternative 1A,with the exception that
slightly more maintenance will be required for Alternative 18 because of the
extended pipe length (see previous Item 15 write up).
C.Alternative 2A -Mid..canyon inlet with "canyon alignment"outletting to 25th St SO
Alternative 2A consists of a mid-canyon inlet with 48-inch HOPE pipe in a -canyon
alignment"down San Ramon Canyon past the Tarapaca Landslide.This alternative would
outlet to the existing CLA .storm Drain at 25 th Street (see previous Photos 4 - 9 in PSR
and Section A-A on page 9 showing the existing San Ramon Canyon intersection with
25 th Street).The majority of the length of this storm drain alignment falls within the City of
Rancho Palos Verdes (RPV),however the most downstream portion will need to pass
through private property within CLA and as such RPV will not have sale jurisdiction for this
alternative.Similar to all of the "mid-canyon inlet alternatives~,the upstream terminus is a
proposed inlet structure in the "middle~of San Ramon Canyon.This location was
strategically chosen to intercept flood waters above the Tarapaca Landslide where bedrock
~daylightsft in the existing canyon bottom and side walls (see previous Photos F1 &F2:
Bedrock at "mid-canyon"invert and downstream adjacent wall).
The storm drain then conveys flows southerly in a -canyon alignment"down San Ramon
Canyon past the Tarapaca Landslide (see Photo 2 in PSR)approximately 1,900-feet in
length where it will connect to the existing CLA storm Drain at 25th Street (see Appendix 0
for CLA SO as-built plans).A small portion of 42-inch CMP was left in place under 25 th
Street when CLA constructed the 48ft RCP storm drain downstream.Since the 42-inch CMP
was left in place,half the width of 25 1h Street will now need to be open cut to an approximate
3D-foot depth to remove this 42-inch bottleneck.8ecause -clear water"will have to be
delivered to the CLA storm drain system,a very large debris basin structure would have to
be designed and constructed at the mid-canyon inlet.This debris basin would deliver clear
water flows downstream.It is envisioned that the debris basin I inlet structure for Alternative
2A (and 28)will be significantly larger than the inlet structure required for Alternative 1A
(and 18).
Page 190f35 IIHarris &Assodates
Cit)'of R~ncho I)alos Verdes S~n R~1110n Omin~ge S)'slcm -Proiecl Smd)'Report
Appendix ['-SIOrm Omin Ahcm~ti\'es Oala
The proposed storm drain construction will follow along the canyon's horizontal alignment
above the existing canyon floor with a minimum cover of 5-feet to the proposed new I raised
canyon invert (see Section C~C on Alternative 2A and two plan &profile sheets 1 of 2
and 2 of 2 in Appendix G).The proposed pipe slope will range from 21.5%maximum to
6.0%minimum.The proposed canyon installation will require a fill along the canyon of up to
3D-feet at some locations.The elevated creek bed and side canyon slopes would be graded
to have less severe steep slopes similar to all of the other alternatives.The filling of the
canyon would again act as a buttress for both the Tarapaca Landslide and the PVDE
switchbacks to eliminate the potential for future slope failures.
Unfortunately the CLA storm drain,starting at 25th Street and downstream to the existing
mid-bluff outlet,has some known deficiencies that were identified in a CCTV inspection
provided by CLA (offset pipe joints).It was noted that in the CLA record plans,there is
insufficient concrete cover over the interior reinforcement steel to withstand the anticipated
high velocity flows and abrupt horizontal angle points and vertical grade breaks.In addition,
the substandard bluff outlet is eroding the bluff face (see PSR discussion in section VI.
EXISTING CITY OF LOS ANGELES ICLA)STORM DRAIN AT 25TH STREET for more
detailed information).
Alternative 2A Facts:
•Tributary area =184 acres
•050 =219 cfs (Actual downstream existing system <050)
•0100 =263 cfs (FYI only)
•Mid-canyon inlet structure
•48-inch HOPE mainline
•CLA 25th Street storm drain outlet
•Total Cost:$18.0 million
Similar to all of the other alternatives a "gravity buttress"fill of approximately 20 to 30-
feet in depth would be placed from the new mid-canyon inlet structure downstream along
the entire canyon limits of the existing Tarapaca Landslide.The fill would raise the
existing canyon's invert and flatten the side slopes of the canyon.Again the "gravity
buttress"fill within the canyon would also support Palos Verdes Drive East switchbacks.
As with the other alternatives ungrouted rip rap rock energy dissipators are proposed at
regular intervals to flatten the invert grade and control I concentrate the energy
dissipation in these rock-lined areas.
Unfortunately the interception of flows at mid-canyon would significantly increase the
amount of flows that currently make it down to the existing CLA storm drain system at
25 1h Street resulting in the need to fortify and improve that system to provide true 050
protection and conveyance.
MTD Transfer of Alternative 2A:The option of transferring the maintenance of the
Alternative 2A storm drain via the Miscellaneous Transfer Drain (MTD)process to the
County of Los Angeles Land Development Department (LAC)is technically possible but
would apply only to the newly constructed reach from the mid~canyon inlet to 25 th Street
and would require the following:
Page 20 of35 IIHarris &Assodates
Cit)·o(RalKho Palos Verdes ~n Ramon Drainage S)'51cm -Project Stud}'Rcpon
Appendi..r _Storm Drain Ahem:ui\'cs D:lla
•Paved vehicular access to inlet &entire storm drain length:LAC requires
that a paved vehicular access road be provided to the inlet structure (which we
will be providing).The access road should also provide access along the entire
storm drain length (which is physically possible but environmentally undesirable
along the raised canyon slope which will be at a 15%grade and will have hard to
traverse energy dissipators evenly spaced along the new creek bed).This
access road in the creek may prove to be environmentally unacceptable.
•Reinforced Concrete Pipe:LAC does not typically allow the use of HDPE pipe.
Instead they strongly prefer RCP and LAC staff noted that only for rare
exceptions have they allowed HOPE,specifically it was allowed for an above
ground installation down a steep slope.Although it is not altogether
inconceivable that we could get LAC to approve the use of HOPE pipe,it would
at a minimum lengthen the LAC approval processing time for the project.
Fifteen Point Analysis of Alternative 2A
The following addresses Fifteen (15)major issues associated with the Alternative 1A and will
similarly be addressed for all of the other alternatives and are rated in a summary chart on
page 28 of the PSR.
1.Project costs:
•Construction:$10.7 million
•PS&E =$1.1 million (10%assumed)
•Design Admin I CM I Inspection =$1.0 million (10%assumed)
•RIW and Easement =$715,000 (place holder cost if necessary)
•Environmental Mitigation =$200.000
Grand Total =$18.3 million (includes 30%contingency)
2.Project Schedule:
Funding Procurement Period:
PS&E Design Phase:
MNO Prep &Approval:
CLA Review &Approval:
Obtain RIW &Easements
Bidding I Award Phase:
Construction Phase:
Approximate Total Time Required:
:.-Months (Can overlap with PS&E Design Phase)
12 Months (Includes additional geotechnical study)
18 Months (Can overlap with Design I Bid Phase)
36 Months (Actual time pending CLAILAC input)
12 Months (Actual time pending CLAILAC input)
6 Months (Includes advertise/bidlaward/contracts)
9 Months (See below for additional breakdown)
80 Months or 6 Years & 8 months·
•NOTE:If funding can be obtained during the same overlapping period that the PS&E
Design Phase is completed and the Mitigated Negative Declaration (MND)
environmental clearance documents can overlap with both the design and CLA review
phases then construction of Alternative 2A could be completed as soon as Winter 2017,
assuming that the PS&E Design Phase could begin as soon as Summer 2011.
Page2lof35 IIHarris &Associates
Cil)'<'lr Rancho P"los Verdes San Ramon Dninagc S)"Slcm -ProjC'Cl Stud)·Rcpon
I\ppendix r -Stoml Drain Alternatives Data
Construction Schedule Breakdown
Mobilization I Clearing &Grubbing I Rough Grading =
Open cut in 25 th Street to connect to 48-Rep =
Canst small downstream inlet structure =
Canst ·prepared canyon bottom backfill-reach (1,900')=
Canst canyon buttress filiI new creek invert =
Canst access road to upstream jnlet structure =
Canst large upstream inlet structure I debris basin =
Demobilization I punch list I Clean up I hydro-seed =
Sub-Total Construction Period =
10%reduction due to overlapping operations =
Grand Total Construction Period =
4 weeks
2 weeks
4 weeks
6 weeks
6 weeks
6 weeks
8 weeks
4 weeks
40 weeks (10 months)
4 weeks (1 month)
36 weeks (9 months)
3.Constructability issues:
•Stability of canyon walls at mid-canyon inlet structure:Alternative 2A is
essentially the same as Alternative 1A,with the exception that the required inlet
structure would need to be much larger to capture the required debris because
CLA requires clean water to their SO system (see previous Alternative 1A Item
3 write up).
•Stability of canyon walls at Tarapaca Landslide:Alternative 2A is essentially
the same as Alternative 1A,with the exception that a pipe line will also need to
be installed through the Tarapaca Landslide area (see Section C-e on
Alternative 2A and plan &profile sheets 1 of 2 and 2 of 2 in Appendix G).
Thus the canyon backfill operation will actually be more complicated for
Alternative 2A (and 2B)than for the other alternatives (see previous Alternative
1A Item 3 write up).
•Access road to mid-canyon inlet structure:Alternative 2A is essentially the
same as Alternative 1A (see previous write up).
•Existing Outlet Structure in Mid-Bluff Bottom:If more flows are added to the
existing CLA storm drain the existing mid-bluff 84~RCP outlet pipe is
recommended to be replaced with some sort of improved outlet structure (design
pending).A ·slant drain·tunnel would be very difficult if not physically impossible
given the existing houses along the entire existing storm drain alignment.Without
such an improvement the bluff would continue to erode at a faster pace and put
at least the two adjacent residential properties in jeopardy.
•Potential for collateral damage in adjacent structures:Alternative 2A is
essentially the same as Alternative 1A (see previous write up).
4.Availability of Material and Methods:
Alternative 2A is essentially the same as Alternative 1A,with the exception that
tunneling material and methods section does not apply (see previous Alternative
1A Item 4 write up).
5.Contractor's Expertise Required:
Alternative 2A does not require any special tunneling expertise thus a wider variety
of contractors would be eligible to perform this work.
Page 22 of 3S IIHarris &Associates
Cil)'of Rancho l'alos Verdes San Ramon Drainage S)'SICm -Project Stud)'Repon
J\PI>cndix r _SlOnn Drain I\hernalives Dala
6.RJW and Easement Requirements:
A portion of the proposed Alternative 2A storm drain alignment and westerly canyon
slope access road would be within the City of Los Angeles.The proposed work will
be in five (5)private properties with only limited if any work being required on the
upper three (3)private properties (0.10 acre within LAC's Friendship Park,0.09
acres within APN 7561-039-006 and 0.16 acres within APN 7561~039~002 for a total
of 0.35 acres).The more extensive pipe installation and grading work would be on
the lower two (2)private properties (0.82 acres within APN 7562-001-009 and 0.26
acres within APN 7561-025-900 for a total of 1.08 acres).Although it is anticipated
that the City will be granted no-cost construction easement for Alternative 1A
because the drainage system will be beneficial to the adjacent property owners,for
worse case estimation purposes,a $500,000/acre placeholder cost has been
included in the project estimate.Additional reasons why a no fee easement may be
assumed include the fact that the adjacent residences along Tarapaca Road are
supportive of the project (confirmed at the community meetings).Also,the adjacent
Friendship County Park is owned by LAC is also supportive of the project.A
temporary construction easement will also need to be obtained from the property
owner adjacent to 25th Street for access to the canyon from the south.A permanent
access road (per LAC requirements)from the 25 th Street may also trigger special
easement requirements.
7.Environmental Impacts:
The Mid-Canyon Inlet Alternative 2A will have the most significant environmental
impacts of any alternative (except Alternative 28).This alternative affects the most
amount of natural canyon slopes and inverts.The following details feature by feature
why the Mid-Canyon Inlet Alternative 2A will have most significant environmental
impacts of any alternative:
•Canyon Walls and Inverts:The Mid-Canyon Inlet I canyon alignment
Alternative 2A impacts the second most amount of natural canyon slopes and
inverts (after Alternative 28).The addition of a buried pipe makes both the short-
term construction and long-term canyon maintenance more complicated and
potentially environmentally impactful especially if a permanent access road is
required along the canyon invert.
•Tarapaca Landslide:All of the alternatives will remedy the Tarapaca Landslide
conditions utilizing similar methods so this item is not a distinguishing factor
between the alternatives.
•Inlet Structure and Access Road:All of the alternatives will require either a
large or small mid-canyon inlet structure and accompanying access road (so that
the Tarapaca Landslide buttress fill downstream wilt be protected)thus this item
is not a distinguishing factor between the alternatives.Regardless it is worth
noting that this Alternative 2A will require the largest debris basin of any
alternative.
•Existing CLA SO System &Outlet Structure:As previously mentioned more
flows will be added to the eXisting CLA storm drain which is known to be deficient
as previously detailed,including a deficient the existing mid-bluff 84~RCP outlet
pipe.The required improvements at the existing bluff outlet are still pending but
would be required to stop the bluff erosion and protect the two adjacent
residential properties.
P:lge 23 of 35 IIHarris &Assodates
Page 24 or 35
Cit},of Rancho Palos Venlcs S:ln Ramon Dl':linagc S)'Slffll -Pro;ca Stud)'Rq:><>n
I\ppmdix r -Storm Drain A!tem:ui\'cs Data
8.Geotechnical Issues:
The majority of the geotechnical issues for Alternative 2A are similar to Alternative
1A,with the exception that tunneling elements do not apply.Also,a QSO storm drain
pipe rnust be added through the Tarapaca Landslide area within the -buttress fill-.
The pipe though the -buttress fill-could be subject to some unwanted and potentially
pipe damaging land movement as the Tarapaca Landslide settles permanently
against the buttress fill (see previous Alternative 1A Item 8 write up).Also note
the connection to existing City system includes some additional geotechnical input /
requirements.The area of the storm drain where the proposed system connects to
the existing City system is underlain by recent alluvium over landslide debris of the
South Shores landslide.It is likely the alluvial soils underlying the pipe trench and
the connection area will require corrective grading to remove compressible alluvial
soils,
9.Flood Protection:
•Upstream of 25 th Street:The proposed storm drain will be design to convey a
50-year storm reoccurrence.
•Downstream of 25 th Street:The existing CLA storm drain south of 2511 Street
was designed to roughly convey a 50-year storm event (see previous discussion
about doubts that it will perform well under a full QSO storm).A
Hydrology/Hydraulic study was done by Harris &Associates.The study found
that the existing system can convey the flows of a 50-year storm but the resulting
velocities range from 19 fps to 48 fps,with the velocities ranging closer to 48 fps.
Per the City of Los Angeles as-built plans,the pipe was not specified to have
extra thickness cover over the steel to handle the high velocities.80nOM
LINE:The deficiencies in the existing CLA Storm Drain system will have to be
remedied in some agreeable manner to allow the proposed construction /
connection of Alternative 2A (and 28),which is not the case for the tunnel
diversion storm drain Alternatives 1A &18.
10.Impacts to the City of Los Angeles (CLA):
Since the proposed Alternative 2A storm drain alignment would encroach into CLA
and requires a connection to and upgrades to the CLA SO the anticipated impacts to
and involvement by CLA would be considerable.CLA will likely dictate every element
of the proposed design form the large debris basin to pipe (and other)materials and
construction methods.This could be complicated by the fact that CLA has said that
no funding is readily available to build the new SO improvements,much less upgrade
their existing storm drain system,south of 25 th Street.As this PSR is circulated to
CLA staff more input on their role and involvement,including funding,will be
available.
11.Impacts to the Los Angeles County (LAC):
As long as the alignment of the access road is not on the wester1y canyon slope and
shifted away from the easterly canyon slope and thus not going through Friendship
Park (LAC's property)only a small easement,if any would be required from LAC.
Further,LAC did mention they have no jurisdictional authority in the project,which
would remain the case especially if a MTD process is not pursued between RPV and
LAC.If a MTO transfer is pursued from LAC for the new SO pipe from 25th Street
BHarris &Associates
City of Rancho Palos Verda San Ramon Drairt:lge S)'Slcm -Project SIU<I}'Rcpon
J\ppmdix F -SlOnn Drain I\hemau\'cs Data
upstream then LAC would be involved to a similar extent as CLA staff,Once again,
this would likely dictate every element of the proposed design from the large debris
basin,to pipe (and other)materials and construction methods.
12.Impacts to Private Residents:
The majority of the private resident impacts for Alternative 2A are similar to
Alternative 1A,with the exception that the two (2)properties upstream of 25 th Street
will be much more significantly impacted because the 48·RCP storm drain pipe must
be added through the middle of their properties and significant grading will also be
required (see previous Alternative 1A Item 12 write up).
13.Impacts to Traffic:
Alternative 2A requires the temporary open trenching across one half of 25th Street
therefore making this alternative (and Alternative 28)the most impactful to traffic l.
Otherwise only minor temporary lane closures would be allowed during construction
and traffic control would be limited to informational signs and some traffic control
during ingress/egress of any construction traffic int%ut of the project sites.
14.Resulting Service Life:
Alternative 2A is anticipated to have service life that is comparable to any similar
storm drain system,which will be facilitated in the long-term by the clear water
requirement.As long as the Tarapaca Landslide does not ·settle-and cause
deformation to the proposed 48·pipe,then the long-term service life is estimated to
be at least 75-years for the both the pipe and reinforced concrete inlet /outlet
structures.Further the service life will be similar to the other alternatives being
considered,thus not raising the ·service life·issue to be a distinguishing factor
between the various alternatives.
15.Future Maintenance Issues:
Alternative 2A (and 28)is anticipated to have the most significant future
maintenance requirements because of CLA's requirement for clear water flows that
trigger the requirement for a large debris basin that must be maintained regularly.
O.Alternative 28 -~.-canyon inlet with "canyon alignment"outletting to 25 th 5t SO
Alternative 28 consists essentially of the exact same design approach and alignment as
Alternative 2A with some exceptions.Instead of constructing a large mid-canyon inlet within
San Ramon Canyon,the proposed storm drain alignment would be extended upstream.
The upper canyon alignment would consist of a 48-inch HOPE pipe installed via ·prepared
canyon bottom backfill·installation in an imported canyon fill along the natural canyon invert
(see Alternative 28 conceptual plans and Typical Section 0-0 in Appendix G).The
proposed pipe would extend an additional 1,3OO-feet upstream of the Mid-Canyon inlet
structure location and would connect with an existing upper San Ramon Canyon storm drain
outlet pipe with a junction structure (see previous Photo F12).This upstream outlet pipe
was constructed as part of the slope repair and terrace drain construction performed in
2002.The 48-inch HOPE pipe in this upper-canyon alignment would be placed above a
perforated 12·diameter pipe (see Typical Section 0-0 in Appendix G).No excavation
Page 25 of 35 IIHarriS &Associates
City of Rancho PaJos V..rdcs San Ramon Drainage'S)'stem _Project Smd)·Report
I\ppmdi:o;r -Sloml Drain I\lternatil'cs Data
below the existing canyon floor would be done.The placement of the storm drain would be
on top of Mbedding M which would be placed above the canyon floor.
The remaining alignment downstream would be exactly the same as Alternative 2A with the
only difference that perhaps a medium mid·canyon inlet structure would still be required.
This mid-canyon inlet would intercept any additional surface flows that are tributary to the
natural canyon slopes (and from the down drain for the Tarapaca Road cul·de-sac and
Tarapaca Slide -brow ditch M above the head-scarp).
The thought process driving this ·sub-alternativeM is that since the main line storm drain
flows have already been collected from the housing tract above and confined to a pipe it
may be advantageous to keep these flows in a pipe rather than allowing these concentrated
flows to again run free in the natural channel bottom.
Alternative 28 Facts:
•Tributary area =98 acres (top connection point)
•Tributary area =184 acres (northerly side of 25 th Street)
•050 of 122 cfs (top connection point)
•050 =219 cfs (northerly side of 25 th Street)
•OHIO =143 cfs (FYI only,top connection point)
•0100=263 cfs (FYI only,top connection point)
•Upper·canyon connection junction structure
•48·inch HOPE mainline in upper &lower canyons
• Mid-canyon inlet structure
•CLA 25th Street storm drain outlet
•Total Cost:$21.4 million
MTD Transfer of Alternative 28:The option of transferring the maintenance of the Alternative
28 storm drain via the Miscellaneous Transfer Drain (MTD)process to the County of Los
Angeles Land Development Department (LAC)is the same as for Alternative 2A (see previous
write up).
Fifteen Point Analysis of Alternative 28
The following addresses Fifteen (15)major issues associated with the Alternative 18 and will
similarly be addressed for all of the other alternatives and are rated in a summary chart on
page 28 of the PSR.
1.Project costs:
• Construction:$12.6 million
•PS&E =$1.1 million (8%assumed)
•Design Admin I CM J Inspection =$1.1 million (8%assumed)
•RNV and Easement =$1.3 million (place holder cost if necessary)
•Environmental Mitigation -$500,000
Grand Total =$21.1 million (includes 30%contingency)
Page 26 of35 BHarris &Associates
Cil)'of R~ncho P~los Verdes S~n Ramon DnUn~b~S)'stern _Projeel Smd)'Repon
t\ppendi~f'_Storm Dr.lin l\hem~li\'cs 1>.l1~
2.Project Schedule:
Funding Procurement Period:
PS&E Design Phase:
MND Prep &Approval:
CLA Review &Approval:
Obtain RJW &Easements
Bidding I Award Phase:
Construction Phase:
Approximate Total Time Required:
~Months (Can overlap with PS&E Design Phase)
12 Months (Includes additional geotechnical study)
18 Months (Can overlap with Design I Bid Phase)
36 Months (Actual time pending CLAILAC input)
12 Months (Actual time pending CLAILAC input)
6 Months (Includes advertiselbid/awardlcontracts)
11.5 Months (See below for additional breakdown)
82.5 Months or 7 Years &3 months*
•NOTE:If funding can be obtained during the same overlapping period that the PS&E
Design Phase is completed and the Mitigated Negative Declaration (MND)
environmental clearance documents can overlap with both the design and CLA review
phases then construction of Alternative 2A could be completed as soon as Winter 2018.
assuming that the PS&E Design Phase could begin as soon as Summer 2011.
Construction Schedule Breakdown
Mobilization I Clearing &Grubbing I Rough Grading =
Open cut in 25th Street to connect to 48 8 Rep =
Canst small downstream inlet structure =
Canst ~prepared canyon bottom backfill~reach
in canyon (1,900')=
Canst canyon buttress filiI new creek invert =
Canst access road to upstream inlet structure =
Const ~prepared canyon bottom backfill"reach
in upper canyon (1,300')=
Canst upstream junction structure =
Canst large upstream inlet structure I debris basin =
Demobilization I punch list I Clean up I hydro~seed =
Sub-Total Construction Period =
10%reduction due to overlapping operations =
Grand Total Construction Period =
4 weeks
2 weeks
4 weeks
6 weeks
6 weeks
6 weeks
8 weeks
2 weeks
8 weeks
4 weeks
50 weeks (12.5 months)
4 weeks (1 month)
46 weeks (11.5 months)
3.Constructability issues:
Because Alternative 2B consists essentially of the exact same design approach and
alignment as Alternative 2A all of the constructability issues raised in the Alternative
2A discussion also apply to Alternative 2B,with two exceptions I clarifications:
•Small Mid-Canyon Inlet:The large mid-canyon inlet in Alternative 1A will be
replaced with a smaller mid-eanyon inlet in Alternative 1B and,as such,any
issues raised in the previous Alternative discussion would also apply here.
including the need to grade an access road,but some canyon impacts would be
smaller in scale.
Page 27 of 35 BHarriS &Assodates
Cit)'of Rancho Palos Verdes San Ramon Drninagc System -ProjcC!Stud)·HCp<.>rt
/\ppendix r -Stuml Drnin t\hcmmi,'cs Data
•Upper Canyon Pipe Line:The additional 1,300-feet of 48-inch HOPE pipe will
be installed via ~prepared canyon bottom backfill"in an imported canyon fill onto
of a filter fabric wrapped rock galley with a 12-inch perforated pipe,directly on top
of the natural canyon invert.This length would connect the smaller mid-canyon
inlet structure to an existing upper San Ramon Canyon storm drain outlet pipe
(see previous photo F12).The constructability issues applicable to this reach
would be most similar to Alternative 2A,which also has proposed mainline storm
drain pipe being installed within the narrow existing canyon,except with less risk
of land movement since there is no active landslide in this area (see Alternative
2A constructability discussion that follows).
4.Availability of Material and Methods:
Alternative 2B is essentially the same as Alternative 2A (see previous Item 4 write
up).One clarification is that more imported fill will be required,but is not anticipated
to be an issue due to the excess fill available in the Portuguese Bend area.
Specifically it estimated that 67,680 cubic yards of fill would be required for
Alternative 18 versus 44,770 cubic yards for Alternative 1A to achieve the new
canyon flow line and cross section (see Section E-E on plan sheet 6 of 6 for
Alternative 1A in Appendix G).
5.Contractor's Expertise Required:
Alternative 28 is essentially the as Alternative 2A (see previous Item 5 write up).
6.RfW and Easement Requirements:
Alternative 28 is essentially the same as Alternative 2A (see previous Item 6 write
up).
In addition to the properties from Alternative 2A,there are a total of 14 properties
within the City of Ranch Palos Verdes for which the City would have to acquire a
storm drain easement as follows:
a.7561-038-007 -0.01 acres
b.7561-038-008 -0.02 acres
c.7561-038-017 -0.06 acres
d.7561-038-010 -0.06 acres
e.7561-038-011 -0.07 acres
f.7561-038-012 -0.07 acres
g.7561-033-009 -0.09 acres
h.7561-033-010 -0.10 acres
i.7561-033-011 -0.09 acres
j.7561-033-012 -0.06 acres
k.7561-033-013 -0.04 acres
I.7561-033-014 -0.01 acres
m.7561-041-012 -0.05 acres
n.7561-041-002 -0.37 acres
Total easement required for the construction of Alternative 28 is 2.53 acres.
Although it is anticipated that the City will be granted a no-cost construction
easement for Alternative 18 because the drainage system will be beneficial to the
adjacent property owners,for worse case estimation purposes,a $500,000Iacre
placeholder cost has been included in the project estimate.
7.Environmental Impacts:
Alternative 28 is essentially the same as Alternative 2A,with the exceptions that
more pristine canyon will be affected and that the view of additional private residents
Page 28 of35 IIHarriS &Assodates
City of R~ocho l~Verdcs S~n R~mon Dr:tin:lgC Srs1em -Project Stud)'Repon
I\ppmdix r:-Stann Dr:tin Ahem31i\'cs D:ll:lO
would be affected by Alternative 18 because more of the canyon floor will be
disturbed by the extended pipe length (see previous Item 7 write up).
8.Geotechnical Issues:
Alternative 28 is essentially the same as Alternative 2A (see previous Item 8 write
up).
9.Flood Protection:
Alternative 28 is essentially the same as Alternative 2A,with the exception that
additional protection could be argued to apply to Alternative 28 because more of the
canyon floor is protected from erosion by the extended pipe length (see previous
Item 9 write up).
10.Impacts to the City of Los Angeles (CLA):
Alternative 28 is essentially the as Alternative 2A (see previous Item 10 write up).
11.Impacts to the los Angeles County (LAC):
Alternative 28 is essentially the same as Alternative 2A (see previous Item 11 write
up).
12.Impacts to Private Residents:
Alternative 28 is essentially the same as Alternative 2A,with the exception that the
view of additional private residents would be affected by Alternative 28 because
more of the canyon floor will be disturbed by the extended pipe length (see previous
Item 12 write up).
13.Impacts to Traffic:
Alternative 28 is essentially the same as Alternative 2A (see previous Item 13 write
up).
14.Resulting Service life:
Alternative 28 is essentially the same as Alternative 2A (see previous Item 14 write
up).
15.Future Maintenance Issues:
Alternative 28 is essentially the same as Alternative 2A,with the exception that
slightly more maintenance will be required for Alternative 28 because of the
extended pipe length (see previous Item 15 write up).
E.Alternative 3 (low Cost):Upsize 25 th Street inlet and line existing canyon invert
Alternative 3 proposes to line the existing stream bed with materials that would eliminate
further erosion (Le.concrete channel which would exacerbate the environmental issues or
ungrouted rip rap)and would also include constructing a very large debris basin to generate
clear water flows and eliminate debris flow onto 25 th Street.The basin would be connected
to the storm drain pipe under 25 th Street.
Page 29 of 47 RHarris &Assodates
City or R,mcho Palos Vcrdes San Ramon Drainaj,'C'Sl'$ttm _l'roi\"CI SlUd)'Rtpon
AppendL'l:r:-Storm Drain Altcmam'CS Data
This alternative would not address the Tarapaca landslide,so there would continuously be
debris flowing to the existing City of Los Angeles system.
Alternative 3 Facts:
•Tributary area =187 acres
•Qso=144cfs
•Q1()()=217 cfs
•Upper 25 th Street inlet structure with large debris basin
•Bluff bottom outlet structure
•Total Cost:$3.7 million
Fifteen Point Analysis of Alternative 3 (Low Cost)
The following addresses Fifteen (15)major issues associated with the Alternative 3 and will
similarly be addressed for all of the other alternatives and are rated in a summary chart on
page 28 of the PSR.
1.Project costs:
• Construction:$2.0 million
•PS&E =$200,000 (10%assumed)
•Design Admin I CM I Inspection =$200,000 (10%assumed)
•RIW and Easement =$250,000 (place holder cost if necessary)
•Environmental Mitigation =$200,000
Grand Total =$3.7 million (Includes 30%contingency)
2.Project Schedule:
Funding Procurement Period:
PS&E Design Phase:
MND Prep &Approval:
CLA Review &Approval:
Obtain RJW &Easements
Bidding I Award Phase:
Construction Phase:
Approximate Total Time Required:
:..Months (Can overlap with PS&E Design Phase)
12 Months (Includes additional geotechnical study)
18 Months (Can overlap with Design I Bid Phase)
36 Months (Actual time pending CLAILAC input)
12 Months (Actual time pending CLAILAC input)
6 Months (Includes advertise/bid/award/contracts)
4.5 Months (See below for additional breakdown)
48 Months or 4 Years *
*NOTE:If funding can be obtained during the same over1apping period that the PS&E
Design Phase is completed and the Mitigated Negative Declaration (MND)
environmental clearance documents can over1ap with both the design and CLA review
phases then construction of Alternative 3 could be completed as soon as Winter 2015,
assuming that the PS&E Design Phase could begin as soon as Summer 2011.
Page 30 of 47 IIHarris &Associates
ellJ or Rancho Palos Verdes San Ramon Dninage Sj'stem -Proiea.S".dy Repon
/\ppmdiJl r -Storm Drain /\hcrn;Il"'CS Data
Construction Schedule Breakdown
Mobilization I Clearing &Grubbing I Rough Grading =
Const canyon buttress filiI new creek invert =
Demobilization I punch list I Clean up I hydro·seed =
Grand Total Construction Period =
4 weeks
10 weeks
4 weeks
18 weeks (4.5 months)
3.Constructability issues:
•The stability of the canyon walls within the Tarapaca Landslide area during
construction is of primary concern,however,it is an issue that is common for all
alternatives and is actually less of an issue for this Alternative 1A since the
added step of installing a large mainline storm drain pipe within the canyon
backfill does not apply to Alternative 3,Thus the canyon backfill operation will
actually be more simplified for Alternative 3 than for any other alternative.As
previously mentioned the Ugravity buttressM fill of approximately 20 to 30-feet in
depth would be placed from upstream of Tarapaca Landslide downstream along
the entire canyon limits past the existing Tarapaca Landslide area then
eventually tapered down to join the existing canyon invert downstream (similar
to Section E·E on Alternative 1A,Sheet 6 of 6 in Appendix G)which would
raise the existing canyon's invert and flatten the side slopes of the canyon.
Additional temporary shoring methodologies and other related constructability
issues need to be detailed during the future PS&E Design Phase.Special full
time emergency monitoring will be also be required until enough of the buttress
fill has been placed.The grading will likely be a trial and error process of reacting
to localize movement and even causing controlled movement that can be graded
into place and compacted in lifts.
The actual process to place the fill,starting from the bottom,will include minor
grading (if any)and placement of a thin layer of base rock (to avoid undercutting
the slide toe and to create a relatively level pad)and then placement of filter
fabric to hold back ~fine particles~.The excess filter fabric material on each side
of the canyon floor,which will wrap the sides and top of a rock galley sub-drain,
will be pinned up onto the sides of the canyon wall while another layer of base
rock is placed,then a 12-inch perforated PVC sub-drain will be installed,
additional galley rock placed and then the fabric will be folded over into place on
top of the rock galley.After the sub-drain rock galley is complete the placement
of the canyon backfill can begin in rapid fashion and ~keyedU into the existing
canyon slopes via multiple stepped Unotches ft
•It is anticipated that imported
backfill will be required in conjunction with the existing canyon excavation that
will undoubtedly be spilling into the backfill operation as the grade is raised
higher and higher.Eventually the width of the backfilled canyon will be
comfortably wide and the adjacent canyon slopes will stop spilling into the
operation as that grades approach the designed raised canyon flow line
elevation.It is even conceivable that this stable canyon access path could be
used as an alternative temporary access road to the site during construction.
Eventually the canyon invert and flattened slopes will be hydro-seeded with an
approved native plant mix in combination with jute mesh,fiber roles and other
recommended erosion control measures that will allow the plants time to get
established.
Page 31 of 47 Harris &Associates
City or R:mcho P:ak>$Vtrdell San Ramon J)l1lin~SY1ttm -Projttt Study Rtpon
t\ppmdix F -Stoml Dl1lin Ahem:uh"C:1 Data
4.Availability of Material and Methods:
•Fill:In order to stabilize the canyon walls,it is recommended that a substantial
amount of fill be placed to elevate the canyon invert and to decrease the vertical
slopes of the existing canyon walls.It estimated that 21,000 cubic yards of fiU
would be required to achieve the new canyon flow line and cross section (similar
to Section E-E on plan sheet 6 of 6 for Alternative lA in Appendix G).The
City has indicated the Portuguese Bend is also a possible source of fill materials
that would not require hauling and traffic impacts outside the RPV peninsula
area.Other sources of fill will have to be studied during the PS&E phase.
5.Contractor's Expertise Required:
Alternative 2A does not require any special tunneling expertise thus a wider variety
of contractors would be eligible to perform this work.
6.RIW and Easement Requirements:
The more extensive grading work would be on the lower two (2)private properties
(APN 7562-001-009 upstream of 25-Street and APN 7561-025-900 County of Los
Angeles).A temporary construction easement will also need to be obtained from the
property owner adjacent to 25th Street for access to the canyon from the south.
7.Environmental Impacts:
•Canyon fill:All of the alternatives will fill the canyon utilizing similar methods so
this item is not a distinguishing factor between the alternatives.
•Existing CLA SO System &Outlet Structure:As previously mentioned more
flows will be added to the existing CLA storm drain due to the construction of inlet
structure at the upstream of 25 th Street.The deficient the existing mid~bluff 84-
RCP outlet pipe will require improvement,which are still pending but would be
required to stop the bluff erosion and protect the two adjacent residential
properties.
8.Geotechnical Issues:
•The area of the storm drain where the proposed system connects to the existing
City system is underlain by recent alluvium over landslide debris of the South
Shores landslide.It is likely the alluvial soils underlying the pipe trench and the
connection area will require corrective grading to remove compressible alluvial
soils.Also see previous Alternative lA Item 8 write ups.
9.Flood Protection:
See previous Alternative 2A Item 9 write up.This alternative is similar in that
once the upstream inlet of 25th Street is upsized,the flows for which the downstream
CLA system was designed,will be conveyed by the existing system.
10.Impacts to the City of Los Angeles (CLA):
Since the proposed Low Cost Alternative 3 would primarily be within CLA and
requires a connection to and upgrades to the CLA SO the anticipated impacts to and
involvement by CLA would be considerable.CLA will likely review every element of
the proposed design form the large debris basin to pipe (and other)materials and
construction methods.This could be complicated by the fact that CLA has said that
Page 32 of 47 IIHarris &Associates
GI)'of RallCho P:llos Vades San Ramon J)r:\in~System -Profcct Study Repon
i\ppendix r -SlOnn J)r:\in i\hnnau\'cs Data
no funding is readily available to build the new SD improvements,much less upgrade
their existing storm drain system,south of 25 th Street.As this PSR is circulated to
eLA staff more input on their role and involvement,including funding,will be
available.
11,Impacts to the Los Angeles County (LAC):
Only a small easement,if any would be required from LAC within Friendship Park
(LAC's property).Further,LAC mentioned their nonexistence jurisdictional authority
for this project,which would remain the case especially if a MTD process is not
pursued between RPV and LAC.
12.Impacts to Private Residents:
The majority of the private resident impacts for Alternative 3 are similar to Alternative
1A,with the exception that the two (2)properties upstream of 25 1h Street will be
much more significantly impacted because the proposed inlet and large debris basin
must be added through the middle of their properties and significant grading will also
be required (see previous Alternative 1A Item 12 write up).
13.Impacts to Traffic:
Alternative 3 requires the temporary open trenching across one half of 25th Street
therefore making this alternative one that impacts traffic significantly.OthelWise only
minor temporary lane closures would be allowed during construction and traffic
control would be limited to informational signs and some traffic control during
ingress/egress of any construction traffic int%ut of the project sites.
14.Resulting Service Life:
Alternative 3 is essentially the same as Alternative 2A (see Alternative 2A,Item 14
write up),with the difference of the Tarapaca Landslide stabilization.
15.Future Maintenance Issues:
Alternative 3 is anticipated to have significant future maintenance requirements
because of CLA's requirement for clear water flows that trigger the requirement for a
large debris basin that must be maintained regularly.Also,the fill within canyon will
not address the existing Tarapaca Landslide and it is expected that erosion will
continue to occur.Future storms will continue to carry sediment and debris down the
canyon and on to the proposed debris basin.
F.Alternative 4 -No Project Alternative:Leave existing conditions "as is"
Alternative 4 proposes to leave conditions as they presently exist.As a result of proceeding
with this alternative,the City should be expecting flooding during moderate rain events,and
possibly in the near future,the failure of the PVDE switchback along with the possible failure
of 25lh Street.This would allow the previously detailed existing dangerous conditions to
remain and carries considerable risk that essentially guarantees the ~no projecr alternative
is NOT a ~no cos'-alternative,likely costing more than the alternatives in the long-term if a
~claim6 ever arises that eventually trigger one of the other alternatives to be constructed on
top of settling the claim.
Page 33 of 35 IIHarris &Associates
Cit),of R3ncho P310s Verdes S3n Ramon Dminage System _Proje<::1 Study Report
Appendix r -Storm Dmin l\lternalil'es D~13
•Tributary area =187 acres
•Qso =144 cfs
•Q1oo=217cfs
•Existing two (2)twelve inch CMP stand pipes as inlet
•Existing failing Bluff bottom outlet structure
•Total Present Cost:$0
•Total Future Cost:Could be in the millions if loss of life or property would occur
Fifteen Point Analvsis of Alternative 4 (No Cost Alternative)
The following addresses Fifteen (15)major issues associated with the Alternative 4 and will
similarly be addressed for all of the other alternatives and are rated in a summary chart on
page 28 of the PSR.
1.Project costs:
• Construction:$0 million
•PS&E =$0
•Design Admin I CM I Inspection =$0
•RNJ and Easement =$0
•Environmental Mitigation =$0
Grand Total =$0 present costs but
UNLIMITED FUTURE MAINTENANCE AND LIABILITY COSTS
2.Project Schedule:
Not Applicable
3.Constructability issues:
Not Applicable
4.Availability of Material and Methods:
Not Applicable
5.Contractor's Expertise Required:
Not Applicable
6.RIW and Easement Requirements:
Although a permanent easement is not required due to "No Project"being constructed,
some type of agreement will need to be addressed with the property owner upstream of
25 1h Street (APN 7562-001-009)in order for City of Los Angeles to perform maintenance
at the existing inlet.
7.Environmental Impacts:
Not Applicable
Page 34 of35 -"Harris &Associates
Cil)'Qr Rancho l:>:Uos Vcrdes 5:m Ramoo Drainago=SyStCfTl -Proica Study Repon
Appendix F -Storm Dr:un Ahcmni\'cs D:lla
8.Geotechnical Issues:
Not Applicable
9.Flood Protection:
This alternative has less than a 1O-year storm reoccurrence.
10.Impacts to the City of Los Angeles (CLA):
This alternative will continue to have flooding on 25 th Street during consecutive storm
events.CLA will have to do
11.Impacts to the Los Angeles County (LAC):
None
12.Impacts to Private Residents:
Flooding of 25 th Street and potential collapse of the existing block wall on the southerly
side of 25 tll Street,could possibly result in flash flood events at the downstream mobile
home park community.This may result in loss of property and even possibly loss of life.
13.Impacts to Traffic:
Flooding of 25 th Street during consecutive rain events,as seen with the storms of
January 2010,will result in complete closures of 25 th Street and therefore impeding daily
traffic from reaching their destination.Additionally,if closure of 25 th Street would occur,
emergency response vehicles would not be able to reach their
14.Resulting Service Life:
Not Applicable -same as existing CLA SD system
15.Future Maintenance Issues:
Repeated major debris removal after several consecutive storms would have to be
performed.
Page 35 of 35 IIHarris &Assodates