RPVCCA_CC_SR_2012_10_02_D_NOC_Annual_Sidewalk_Repair_ProgramCITY OF MEMORANDUM RANCHO PALOS VERDES TO: FROM: DATE: SUBJECT: REVIEWED: Project Manager: HONORABLE MAYOR &CITY COUNCIL MEMBERS JIM HENDRICKSON,INTERIM DIRECTOR OF PUBLIC WORKS OCTOBER 2,2012 NOTICE OF COMPLETION FOR THE ANNUAL SIDEWALK REPAIR PROGRAM,FY2011-2012 (SUPPORTS 2012 CITY COUNCIL GOAL #4 PUBLIC INFRASTRUCTURE - CITYWIDE STREET MAINTENANCE) CAROLYN LEHR,CITY MANAGER ~ Melissa Murphy,Associate Engineer ~ RECOMMENDATION 1.Accept the work as complete. 2.Authorize the City Clerk to file a Notice of Completion with the L.A.County Registrar- Recorder Office and if no claims are filed within 35 days after recordation,and upon the contractor posting an acceptable warranty bond,notice the surety company to exonerate the Payment and Performance bonds. 3.Authorize the Director of Public Works to release the 5%retention payment in the amount of $4,719.90 to Mora's Equipment and Construction,Inc.35 days after recordation of the Notice of Completion by the L.A.County Recorder contingent upon no claims being filed on the project,and the contractor posting an acceptable warranty bond. BACKGROUND Every year the City implements the sidewalk repair program where damaged sidewalk is repaired at various locations throughout the City.The City is sub-divided into nine maintenance zones and as requests are received regarding uplifted and/or damaged sidewalk throughout the year,these locations are logged and a database of repair areas is maintained until the quantity of repairs is sufficient to initiate the project. D-1 DISCUSSION The project's scope included demolition of uplifted concrete sidewalk panels,root trimming, and pouring of new concrete panels.A few locations also included curb and gutter and driveway apron work. An unusually large amount of roots were encountered during the root trimming process, which were underneath portions of the sidewalk and therefore not visible when the project was originally estimated.Nonetheless,due to the low bid prices and expedient completion of the work by Mora's Equipment and Construction,Inc.that resulted in inspection cost savings, the project was still completed within the amount budgeted,yielding a net savings of $184.50. Table 1 -Project Cost Summary . Authorized Construction Contract Amount $77,475.00 Authorized Inspection Contract Amount $21,600.00 Authorized Contingency Amount $9,907.50 Total Project Budget $108,982.50 Actual Project Cost (including Construction and Inspection)$108,798.00 Project Saving$.V'ii i $1tJ4,~Q> CONCLUSION Mora's Equipment and Construction,Inc.has successfully completed all work in accordance with the plans and specifications.Therefore,the work should be accepted as complete and a Notice of Completion filed. FISCAL IMPACT The recommended action will have no fiscal impact. Attachments:Notice of Completion M:\Sidewalk ProjectlStaff Reports\Staff Report for FY11-12 Annual Sidewalk Repair Program NOC_2012_1 O_02.doc D-2 RECORDING REQUESTED BY: r City Clerk 1 Name Ci ty of Rancho Palos Verde Street 30940 Hawthorne Blvd. Address Rancho Palos Verdes City CA State 90275 Zip L J Space above this line for recorder's use NOTICE OF COMPLETION Notice pursuant to Civil Code Section 3093,must be filed within 10 days after completion.(See reverse side for complete requirements.) Notice is hereby given that 1.The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the property hereinafter described. 2.The full name olthe ~wner is Ci ty of Rancho Palos Verdes 3.The full address of the owner is 30940 Hawthorne Blvd.,Rancho Palos Verdes,CA 90275 4.The nature of the interest or estate of the owner is:In fee. (If other than Fee.strike °In fee"and insert.for exarflJle."purd'laser under contract of purchase,"or "Lessee") 5.The full names and full addresses of all persons,if any,who hold title with the undersigned as joint tenants or as tenants in common are: NAMES ADDRESSES 6.The full names and full addresses of the predecessors in interest of the undersigned,if the property was transferred subsequent to the commencement of the work or improvements herein referred to: NAMES ADDRESSES 7.A..work of iropro...v~~nt on th(l prQPerty htlreinafter described was completed on Ju1 y 31,20 12 Annua~~1aewaiK ~epa1r Program,FY 2011-2012 .The work done was: 8. 9. Morals Equipment &ConstructionThenamesofthecontractor,if any,for such work of improvement was _ (If no contractor for work of irflJrovement as a whole,insert "None")(Dille 01 COQtrgct)_ _ _ _ The property on which said work of improvement was completed is in the City of __Rancho Palos Verdes County of Los Angeles ,State of CA,and is described as follows:_ Dated _ (Signature 01 Owner or corporate officer of Owner named in paragraph 2.or his agent) C't Cl ~ERIFICATION I,the undersigned,say:I am the 1 y er ,the Declarant of the foregoing Notice of Completion; (President of,Manager of,Partner of,Owner of.etc.) I have read said Notice of Completion and know the contents thereof;the same is true to my own knowledge.I declare under penalty of perjury that the foregoing is true and correct. Executedon ,20__at City of Rancho Palo.s Verdes ___.CA (Personal signature of the individual who Is swearing thaI the contents of the Notice of Conl:Jletion are true) Before you use this form fill in all blanks,and make whatever chan~es are appropriate and necessary to your particular transaclion.Consult a lawyer if you doubt the form s fitness for your purpose and use. Wolcotts makes no representation or warranty,express or iml>lied,with respect to the merchantability or fitness of this form for an intended use or purpose.e200S WOLCOTIS FORMS,INC.FORM 1114 Rev.H)·OS D-3 FY2011-2012 ANNUAL SIDEWALK REPAIR PROGRAM Location #Address 1 26221 Basswood Av (Opposite) 2 26307 Basswood Av (Opposite) 3 5809 Flambeau Rd 4 5909 Flambeau Rd 5 5915 Flambeau Rd 6 5542 Graylog St 7 26202 Grayslake Rd 8 6058 Groveoak PI 9 26939 Indian Peak Rd 10 26619 Shorewood Rd 11 26717 Shorewood Rd 12 26919 Springcreek Rd 13 26927 Springcreek Rd 14 26905 Springcreek Rd 15 5134 Wildbriar Dr 16 28822 Lomo Dr 17 6716 Abbottswood Dr 18 7024 Abbottswood Dr 19 28905 Golden Meadow Dr 20 28604 Golden Meadow Dr 21 28811 Geronimo Dr 22 28887 Blythewood Dr 23 6538 Certa Dr 24 28073 Acana Dr 25 28832 Cedarbluff Dr 26 28839 Trailriders Dr (Opposite) 27 28847 Trailriders Dr (Opposite) 28 6948 Brookford Dr 29 29216 Golden Meadow Dr 30 28130 Ambergate Dr 31 29211 Golden Meadow Dr 32 28205 Ambergate Dr 33 7025 Grovespring Dr (Opposite) 34 7035 Grovespring Dr (Opposite) 35 6970 Grovespring Dr 36 6955 Grovespring Dr 37 28310 Trailriders Dr 38 6902 Maycroft Dr 39 6902 Maycroft Dr (Opposite) 40 28105 Ambergate Dr 41 6944 Larkvale Rd 42 6616 Monero Dr 43 28017 Indian Rock Dr 44 28047 Lomo Dr 45 28504 Blythewood Dr 46 28315 Ella Rd 47 28050 Ella Rd 48 28040 Ella Rd 49 28027 Ella Rd 50 28304 Ella Rd 51 28304 Ella Rd 52 28043 Braidwood Dr 53 27936 Alvarez Dr 54 28133 Braidwood Dr 55 6584 Locklenna Ln 56 6710 Locklenna Ln 57 6710 Locklenna Ln (100'from) 58 Indian Peak Rd &Promenade Parking entrance 59 Crenshaw w/s 500'n/o Del Cerro Park 60 Crenshaw 300's/o Crestridge Rd 61 4222 Dauntless Dr 62 4244 Dauntless Dr 63 51 Albero Ct 64 3207 DelunaDr 65 2061 Via Colinita 66 28623 Mount Lassen Ln 67 1214 Bloomwood Rd 68 2003 Santa Rena Dr 69 1929 Santa Rena Dr 70 2003 Santa Rena Dr 71 2004 Santa Rena Dr 72 2004 Santa Rena Dr 73 1949 Avenida Aprenda 74 2152 Mendon Dr 75 30252 Via Victoria 76 26721 Hawkhurst Dr 77 26735 Hawkhurst Dr 78 5823 Flambeau Rd 79 28313 Lomo Dr 80 28040 Lomo Dr 81 28318 Trailriders Dr 82 28114 Braidwood Dr D-4