Loading...
RPVCCA_CC_SR_2012_01_03_01_City_Council_Goal_Setting_WorkshopMEMORANDUM TO:HONORABLE MAYOR AND CITY COUNCIL FROM:CAROLYNN PETRU,DEPUTY CITY MANAGER@) DATE:JANUARY 3,2012 SUBJECT:CITY COUNCIL GOAL SETTING WORKSHOP REVIEWED:CAROLYN LEHR,CITY MANAGER In conjunction with the City Council's workshop this evening,the following documents are attached to help facilitate the discussion: 1.Workshop Overview and Objectives prepared by Dr.AI Edwards in consultation with Mayor Misetich;and, 2.Rancho Palos Verdes Major Projects List prepared by staff,which provides an overview of major work efforts that are currently in progress.The attached list, identified by program or department,has not been prioritized in any fashion and does not include on-going routine,administrative or mandated programs and services provided by the City. Enclosures 1-1 RANCHO PALOS VERDES CITY COUNCIL WORKSHOP FACILITATION JANUARY 3,2012 WORKSHOP OVERVIEW AND OBJECTIVES This facilitation will focus on understanding and developing the Rancho Palos Verdes City Council vision and expectations subsequent to the election of new Council members in November 2011.The following objectives were designed to support specific workshop agenda items,and engage Council around organizational dynamics,communication with staff,and opportunity to share its goals and projects for the future: 1.Understand the vision and long-term goals and projects of RPV Council Members; 2.Provide direction and a communication process around which the projects/goals will be achieved; 3.Enable each Council Member to create a "Legacy Statement;" 4.Determine how projects (in the pipeline)will be handled from a forward-thinking perspective. There are four distinct activities scheduled to be included in the workshop agenda,which include: 1.Brainstorming of future projects,proposed policy changes,or anticipated goals by each Council member.This approach allows each member to generate a list of these items over a 20-30 minute period of time.The outcome is a list of what they believe will enhance the lives of RPV residents,provide opportunities to improve the City's infrastructure,and advance beliefs around public safety and other key policy considerations for the City. 2.The identification of Long-Term (LT)and Short-Term (ST) goals,based on the items generated,comprises the second activity for the evening.Council members will be asked to designate the time period of the project,for instance,ST=Less than 90 days or LT=Longer than 90 days.This process begins to clarify what might be perceived as strategic imperatives around which more data might be collected from the community through surveys,town hall meetings,and focus groups.This process also begins to inform the Council about potential competing issues as they relate to existing projects. 3.Moreover,the workshop will afford the City Council an overall view of projects currently in the "pipeline"and,subsequently,move toward an understanding of how these projects will be supported in conjunction with any newly proposed projects by Council.The intent here is to begin this dialogue in order to create awareness of the existing projects,along with an estimate of time and cost invested in the projects to date. 4.In addition,each Council Member will create what has been termed a "Legacy Statement"that will enable him/her to engage in forward thinking about his/her tenure and the significant contributions and accomplishments to be achieved during that time period.This final agenda activity will give the Council an opportunity to reflect on the original list generated and ask questions regarding priorities of projects and goals. This workshop should be seen as the beginning of what may become periodic sessions for Council to foster increasingly higher levels of collaboration. 1-2 December 2011 RANCHO PALOS VERDES MAJOR PROJECTS LIST·WORKING DRAFT No.Project Name Project Manager Group Scope of Work Stabilize Tarapaca landslide within canyon;stabilize Palos Verdes Drive East 1 San Ramon Canyon Stabilization Water Quality/Flood Protection Switchbacks;install mid-canyon storm drain system with an outlet to the beach; minimize water/debris delivery to 25th Street from RPV 25th Street Improvements and City of LA has an interim improvement project designed to improve storm runoff at 2 Cleanup Water Quality/Flood Protection 25th Street.Meanwhile,RPVand LA are developing a Memorandum Of Aoreement to formalize roadway c1eanino arranoements. 3 Storm Drain Lining Fiscal Year 11-12 Water Quality/Flood Protection This multi-year project installs liners into storm drains (typically Corrugated Metal Pipe)that are determined to be in need of repair. Create a Geographic Information System-based storm drain management 4 Storm Drain Master Plan Update Water Quality/Flood Protection program to include attribute information,hydrology and hydraulics model, deficiency analysis,prioritization tools. 5 Subregion One Bluff Top Drainage Water Quality/Flood Protection Project is to minimize bluff top erosion and will install at least one gabion basked Control along the bluff top. 6 Septic System List Water Quality/Flood Protection Develop list of parcels using septic system for future requirements of LA Regional Board 7 San Pedro Canyon Area Storm Drain Water Quality/Flood Protection Correct structural deficiencies in several pipes and culverts in Miraleste /San Improvements Pedro Canyon Area 8 Storm Drain Easements Water Quality/Flood Protection Obtain easements for existing storm drains located on Sea View and Via Corsini. 9 Trump Storm Drains Water Quality/Flood Protection Finalize a plan with Trump and LA County so LA County will accept maintenance of drains on Trump property. 10 Via Canada Storm Drain Water Quality/Flood Protection Design and construction of improvements to Via Canada catch basin and pipe Improvements system to alleviate recurring flooding in the cul-de-sac at the end of Via Canada. 11 Citywide Traffic Safety Battery TrafficlTransportation/Safety This project will install battery backup systems at all signalized intersections in the Backup Project City. Crest RdlWhitley Collins Pedestrian This project will construct pedestrian-activated flashing beacon crossing at the 12 Flashing Crossing TrafficlTransportation/Safety intersection of Crest Road and Whitley Collins Drive.Construction is anticipated to begin January 2012. Crestridge Crenshaw Traffic Signal Upgrade traffic signal to include protected left-turns on all phases including 13 Upgrades TrafficlTransportation/Safety access ramp improvements,median modifications,equipment upgrades,and crosswalk restriping This project will create a 'Walk To School"program that will be a joint venture 14 Safe Routes To School TrafficlTransportation/Safety between the City and Palos Verdes Peninsula Unified School District.The program includes informational handouts and incentives for students to walk to school. 15 Hawthorne Blvd Traffic Signal TrafficlTransportation/Safety Synchronize 11 traffic signals along Hawthorne Blvd from Highridge/Grayslake Dr SYnchronization to Palos Verdes Drive West. Determine how to eliminate the subsidy of the Abalone Cove Sewer System and 16 Citywide Sewer Analysis Sewer System develop funding alternatives for capacity related projects that are needed within the citywide sewer system. Grant through the State Land and Water Conservation Fund Program has been applied for.The scope of work includes:trail heads,picnic area,shade 17 Abalone Cove Shoreline Park Parks,Open Space,and Trails structures/outdoor classrooms,viewing areas,interpretive signage/kiosk, Improvements exploration Play Area,bike racks,bluff top fencing,landscaping,irrigation improvements.State Grant is $31 OK with $31 OK City's matching fund for a total Ioroiect estimated cost of $620K. Improvements to the City's segment of California Coastal Trails along Palos 18 California Coastal Trail Parks,Open Space,and Trails Verdes Drive West,Palos Verdes Drive South &trail easements along the coast. Improvements State Grant is $540K with $60K City's matching fund for a total project estimated cost of $600K 19 Landslide Global Positioning System Parks,Open Space,and Trails Monitor Ground Movement at the Abalone Cove,Portuguese Bend &Klondike Monitoring 2011 Canyon Landslides In coordination with the City Manager's office and the Community Development 20 Public Space Uniform Sign Project Parks,Open Space,and Trails Department,create a uniform sign program for the City's public spaces,including roadway turnouts,parks,trails,vistas,and preserve areas. Arterial Roads Rehabilitation -Palos This project will rehabilitate Palos Verdes Drive East.Improvements related to this 21 Verdes Drive East Right of Way project will be coordinated with Cal Water major water main project.Design is anticipated to begin in March 2012. P:\Project List\CC Project List Dec_2011_TO_JR.xls 1-3 December 2011 RANCHO PALOS VERDES MAJOR PROJECTS LIST -WORKING DRAFT Arterial Roads Rehabilitation -Palos Roadway resurfacing of portions of Palos Verdes South and Palos Verdes Drive 22 Verdes Drive South Right of Way West.Project components include road resurfacing,access ramp and sidewalk imorovements bus stoo imorovements,sianaae,and strioina. 23 Oceanview Home Owners Right of Way Neighborhood trees on Berryhill,Via Cambron,and Via Callado will be removed Association Tree Replacement and replaced due to view and infrastructure impacts. 24 Palos Verdes Drive South Landslide Right of Way Periodically Repair Asphalt damaged due to earth movement in the landslide.Road Maintenance Pavement Management Program -Every three years,the Pavement Management System report is updated to reflect25PavementManagementSystemRightofWaycurrentpavementconditionandrecommendedrepairmethodsReport 26 Palos Verdes Drive South Bikeway Right of Way The project will construct bike-compatible lanes along Palos Verdes Drive South Safetv Proiect throuah the landslide.Desian is exoected to beain Januarv 2012. 27 Palos Verdes Drive South Landslide Right of Way Regular review with City Geologist to address land movement issues.Area Drainage Corrections Americans with Disabilities Act-Design and construct Americans with Disabilities Act-compliant curb ramps where 28 Compliant Curb Ramps -Miraleste Right of Way either curb ramps are out of compliance or do not exist at all in the Miraleste Plaza Plaza.Will coordinate relocating of catch basins as needed.This is a CDBG funded project. Americans with Disabilities Act-Design and construct Americans with Disabilities Act-compliant curb ramps where 29 Compliant Curb Ramps -Vista Right of Way either curb ramps are out of compliance or do not exist at all in the vicinity of Vista Grande School Area Grande Elementary School.This is a CDBG funded project. Design and construct Americans with Disabilities Act-compliant curb ramps where Americans with Disabilities Act-either curb ramps are out of compliance or do not exist at all in the vicinity of 30 Compliant Curb Ramps -Blackhorse Right of Way Blackhorse Road near Hawthorne Blvd.Project improvements include new Road ramps,crosswalks,bus-stop relocation and new sidewalk.This is a CDBG funded project. Replace existing guardrail along Palos Verdes Drive East that is in need of repair 31 Palos Verdes Drive East Guardrails Right of Way or that is not in compliance with current standards with new guardrail.Specific Traffic Safety Improvements locations that are eligible for this guardrail replacement are called out in the Highway Safety Improvements Program grant. 32 Palos Verdes Drive West Center Right of Way Design phase underway.Project kick-off meeting schedule for December 15, Median Project Phase I 2011.Construction anticipate to start April 2012 33 Palos Verdes Drive West Center Right of Way Design phase underway.Project kick-off meeting schedule for December 15, Median Project Phase II 2011.Construction anticipate to start April 2012 Residential Rehabilitation Project Residential Rehab Project in Areas 4 & 8 for Fiscal Year 09-10.This project 34 Right of Way includes curb,gutter,sidewalk and access ramp improvements as well asFiscalYear09-10 resurfaced residential streets with caoe seal and rubberized slurrv seal. Preliminary Engineering Study Palos Evaluate the feasibility of continuing repairs on the landslide road in its current 35 Verdes Drive South Landslide Road Right of Way location vs.relocating the road to its original location;Evaluate need to extend drainage facilities that have been destroyed by land movement. 36 Annual Sidewalk Repair Program Right of Way Annual Sidewalk Repair Program Fiscal Year 10-11 and 11-12.Fiscal Year 11-12 Hawthorne Blvd Pedestrian Linkage Construct sidewalk in missing segments along both sides of Hawthorne Blvd,from 37 Right of Way Palos Verdes Drive South to Crest Rd.Project includes installation of AmericansSidewalkProjectwithDisabilitiesAct-compliant curb ramps and landscaping improvements. Residential Rehabilitation for two Fiscal Years 10-11 and 11-12.This includes 38 Residential Rehabilitation Fiscal Right of Way roadway resurfacing,curb and gutter repair,and sidewalk repair in Areas 5 and 3, Years 10-12:Areas 5 and 3 which include neighborhoods off of Hawthorne Blvd,Crest Rd,and Palos Verdes Drive West. Citywide Accessibility Self-Evaluation Preparation of a 'Self Evaluation Report'and a 'Transition Plan'for City facilities, 39 &Transition Plan Facilities programs and services to comply with Americans with Disabilities Act requirements. 40 Eastview Park Playground Facilities These improvements will make the playground and restrooms at Eastview Park in Improvements compliance with the safety and accessibility requirements of the code. 41 Hesse Park Drop Ceiling Facilities Replacement of the aging tongue &groove drop ceiling with a T-bar ceiling Replacement designed to withstand seismic forces and improve accessibility for maintenance. P;\Project List\CC Project List Dec_2011_TO_JR.xls 2 1-4 December 2011 RANCHO PALOS VERDES MAJOR PROJECTS LIST·WORKING DRAFT Create a report to include all RPV infrastructure and their condition in order to 42 Infrastructure Report Card Facilities assess the need for their improvements,alterations or maintenance/repairs and the associated cost estimates.The list covers Buildings,Parks,Right-Of-Way, Water Quality/Flood Control and Sanitary Sewer infrastructure. Irrigation Water Savings Compliance Installation of the Smart Controllers for the irrigation system at Point Vicente 43 Program Point Vicente Interpretive Facilities Interpretive Center &Eastview Park to comply with the State-mandated irrigation Center &Eastview Park water conservation. 21 Martingale house is by a trail head entrance and the easement for the trail.A 44 21 Martingale Trail and Slope Repair Facilities slope failure in 2009 covered part of the trail.Site conditions under review by Geotechnical Engineers. 45 RPV Beach Life Guard Station Facilities Project includes installation of telephone and power lines for the County's life Telephone and Power Lines guard station. 46 Ryan Park Restrooms Americans Facilities Improving Ryan Park restrooms for Americans with Disabilities Act compliance with Disabilities Act Compliance along with the painting of the bUilding. Ryan Park South Entrance Design to modify the south entrance of Ryan Park to make it possible for trucks 47 Realignment Design Facilities and large vehicles to enter without impacting traffic on southbound Hawthorne Blvd. Scope of work has been modified to include only replacement of the stove/oven 48 Hesse Park Kitchen Improvements Facilities and its ventilation line,improving air conditioning inside the kitchen and other minor work 49 City Hall Building Signs Replacement Facilities Preparing new signs with updated contents to replace the current deteriorating and outdated signs. 50 City Hall Community Room Drop Facilities Retrofit the Community Room drop ceiling against seismic forcesCeilingRetrofit 51 Cooling Options at City Hall Facilities Exploring cooling options for the City Hall &Community Development Department buildings 52 General Plan Update Community Development A complete update of the City's 36-year old General Plan 53 Trails Plan Update Community Development An update of the City's Conceptual Trails Plan and Bikeways Plan which will be consolidated into one Trails Network Plan Completion of Final Public Use Final plan will include Trails Plan for Upper Filiroum,updated trail designations for54MasterPlan(PUMP)for the Community Development Preserve the Preserve's existing Trails Plan and list of approved public uses. 55 Western Ave Compass Project Grant Community Development Coordination with a selected consultant to prepare a plan for Western Avenue that will improve the aesthetic appearance and promote economic development 56 FAR Code Amendment Community Development A proposal to study how a Floor Area Ratio (FAR)limit could be incorporated into the current residential review process. Open Space Hazard (OH)line A proposal to study how the City's existing interpretation procedure can be 57 interpretation Code Amendment Community Development amended to make it easier for property owners to adjust the OH boundary line on their orooertv. 58 Hedges in the front setback Code Community Development A proposal to study whether hedges over 42 inches in height may be allowed in Amendment the front yard setback in residential zones. 59 LivelWork Code Amendment Community Development A proposal to allow dwelling units in certain commercial developments. 60 Trump National Golf Course Community Development The review and/or processing of permits related to ongoing activities or proposed improvements. 61 Marymount College Community Development The review and/or processing of permits related to ongoing activities or proposed imorovements. 62 Proposed Event Garden at Point Community Development The processing of the entitlement permit and CEQA document related to a View proposed minor golf courlie and outdoor banquet facility. 63 Highridge Condos Community Development The coordination of the final items needed to issue the building permit for construction of the previously approved 28-unit condo building 64 Zone 2 EIR Community Development The preparation of an EIR to analyze the environmental impacts of alloWing 47 vacant lots to be developed in Zone 2 within the City's landslide moratorium area. P:\Project List\CC Project List Dec_2011_TO_JR.xls 3 1-5 December 2011 RANCHO PALOS VERDES MAJOR PROJECTS LIST -WORKING DRAFT The development of a master plan for Upper Point Vicente Park for a Civic Center, 65 Civic Center Master Plan City Manager's Office including City Hall facilities,Council Chambers,Emergency Operations Center, Community Building,Village Green and shared parking. City Hall Renovation Cost/Benefit A cost/benefits analysis of renovating the existing City Hall buildings for 66 Analysis City Manager's Office compliance with current building safety and access requirements versus new construction. Conduct a statistically valid telephone survey of residents'opinions regarding City 67 Community Survey City Manager's Office service levels to assist the City Council in developing its strategic objections and making policy decisions. Develop a Joint Use Agreement with the PVPUSD for City use of School District- 68 PVPUSD Joint Use Agreement City Manager's Office owned recreational facilities in conjunction with a $80,000 grant from the City towards the renovation of the pool at Peninsula High School. Water Wise Garden Demonstration A request from the West Basin Municipal Water District for donation of land to 69 Grant City Manager's Office plant an Ocean-Friendly Demonstration Garden.A grant of $15K to $30K is available to pay for all improvements. The lease for the monopole at City Hall expires in June 2014.A new lease need 70 City Hall Mono~ole Lease City Manager's Office to be negotiated with the owner,American Tower,for a more aesthetic facility. The monopole may also need to be relocated to accommodate the outcome of the Civic Center Master Plan. 71 Records Management Project City Clerk's Office Conversion of the City's hard copy documents and other historical records into a permanent,searchable electronic data base using Laserfische. .'An analysis to determine if the current regional cost sharing formula used to 72 Sheriff's Regional Contract Formula Public Safety allocate Sheriff's Department costs among the three regional cities should be modified to provide for less volatility. A study to identify a location on the south side of the City for an ambulance station 73 Ambulance Station Public Safety to be leased to the agency that contracts with the LA County Fire Department for these services. Execution of a lease with Verizon Wireless to co-locate a ham radio antenna on a 74 PVAN Antenna at CalWater Property Emergency Preparedness CalWater site at San Pedro Hill in order to provide emergency radio communications on the east side for the City's Peninsula Volunteer Alert Network (PVAN) Joint Natural Hazards Mitigation Plan An update to the adopted 2004 Joint NHMP in conjunction with the City of Rolling 75 Update Emergency Preparedness Hills Estates.Updating the plan is essential for eligibility for FEMA disaster reimbursement funds., 76 Park Ranger/Sheriff Drop In Office Recreation &Parks/Public Safety A study to identify a location on the south side of the City (in proximity to the Palos Verdes Nature Preserve)for a Park Ranger/Sheriff drop-in office. 77 Skate Park Site Location Study Recreation &Parks Identify potential locations for a Peninsula-wide skate park facility. 78 Dog Park Site Location Study Recreation &Parks Identify potential locations for a Peninsula-wide off-leash dog park. . 79 RPV Beach Off-Leash Dog Beach Recreation &Parks Determine if Rancho Palos Verdes Beach located below Founders Park and Study Trump National Golf Course should be an off-leash dog beach. The development of a Master Plan that will lay the groundwork for the site's long- 80 Ladera Linda Site Master Plan Recreation &Parks term redevelopment and potential phased implementation.The first step of this project involves a study of community needs through public outreach. Conceptual plans were approved for the park in November 2010.A Mitigated 81 Grandview Park Improvement Recreation &Parks Negative Declaration is currently being prepared for the project.The next steps Project will be to explore phasing of the project's concept plan,future design and construction of the proposed improvements. Conceptual plans were approved for the park in November 2010.The project is 82 Lower Hesse Park Improvement Recreation &Parks currently on hold pending the outcome of the Skate Park Site Location Study. Project Following completion of that project,the next steps include an environmental assessment of the final concept plan and the exploration of phasing the project. P:\Project List\CC Project List Dec_2011_TO_JR.xls 4 1-6 December 2011 RANCHO PALOS VERDES MAJOR PROJECTS LIST·WORKING DRAFT Replacement current SunGard Finance Staff acquisition team has reviewed demonstrations by vendor candidates and accounting system and Acella permit has begun the selection process.The City's project advisor will assist the staff tracking system with a Enterprise team with selection and negotiating the ERP system and vendor that will be Resource Planning ("ERP")system recommended to the City Council for purchase in 2012. 83 Update of cost-based fee system Finance Staff has begun the process leading to a recommendation to the City Council to consider a revision of cost-based fee rates.Staff's review includes a revision of 84 the fee system for building permits in 2012. Update disaster recovery documents Finance Staff has begun the process of reviewing all disaster recovery documents and processes for improvement with the goal of moving to a electronic-based system. 85 Revision of Main Page of website Information Technology Working closely with PVNET,redesign the Main Page of the website to reduce clutter and establish an easier entry into the website that is consistent with other CA municipalities.This goal will be completed in early 2012,while attempting to minimize functional changes and programming of the website. 86 Revision of website Information Technology Subject to direction by City Council,establish the process to conduct a RFP to revise the website,including its current features like video on demand,emergency 87 notification,Iistserver system and non-emergency notification. Policy for email archival and retrieval Information Technology Staff expects to make a recommendation to the City Council in 2012 for establishing a policy for email archival and retrieval,as well as the acquisition of 88 hardware,software or a third party provider to manage email. IT Plan -Installation of Virtual Information Technology Install rack,servers,storage network routers &UPS,load MS server SW in 89 Machine ('VM")January 2012. IT Plan -Migration of Primary server,Information Technology Begin the migration of systems currently operating on dedicated servers to the VM Acella permit tracking system,in early 2012.. 90 Laserfiche document management IT -Plan -Migration of Email to Information Technology Once the VM is installed and tested,configure and test MS Exchange for email in Exchange •~'I Spring 2012. 91 IT Plan -Migration of Cisco to Lync Information Technology Once MS Exchange has been implemented and tested,configure Lync for unified communication that will enable the convergence of voice,email,voice messaging, video conferencing in Spring 2012. 92 Purchase and installation of Information Technology Once most all systems have been moved to the VM,upgrade about 30 desktop remaining desktop computers and computers and replace about 60 desktop computers mid-2012,installing both W7 migration of remaining desktop and and Office 2010. laptop computers to W7 93 Improve Internet access speed at Information Technology Complete the replacement of the 1MB Internet connection with at least 3MB in Hesse Park January 2012 to improve user access,staff access during meetings,as well as the 94 wireless experience available to the public. Improve Internet access speed at Information Technology Complete the replacement of the 3MB Internet connection with FIOS up to 60MB City Hall &PVIC (upload)in January 2012 to improve user access,video on demand quality,as 95 well as the wireless experience available to the public. Install microphone on/off switches for Information Technology Complete the installation in January 2012 of microphone switch boxes that will Hesse Park broadcasts enable staff and Council/Commission users to turn microphones off/on 96 Improve video quality during Hesse Information Technology Install new overhead lights in early 2012 over tables ~nd possibly install low Park broadcasts emission/non-glare lights at each table 97 Present a recommendation to City Information Technology Assess merits of joining LARIAC,analyze costlbenefits and prepare a staff report Council to upgrade GIS pictometry to present to the City Council as early as February 2012. 98 and join LARIAC P:\Project List\CC Project List Dec_2011_TO_JR.xls 5 1-7