2014 FIVE-YEAR INFORMATION TECHNOLOGY PLAN
CAROLYNN PETRU, ACTING CITY MANAGE~
RECOMMENDATION
Receive and file.
INTRODUCTION
The 2014 5-Year IT Plan (2014 IT Plan) is a management tool used to organize and
prioritize IT projects in a way that best accomplishes goals and priorities of the City. A
clear plan allows for the phased implementation of components, building one on top of
the other in order to realize the most gains as quickly as possible, while insuring installed
technologies are flexible enough to integrate with future technologies.
The 2014 IT Plan was developed conjunction with the FY14-15 Equipment Replacement
Fund-IT budget and the citywide 2014 Five-Year Financial Model that includes the
Equipment Replacement Fund-Computers and about 35 other operating funds of the City.
The 2014 IT Plan will form the basis for IT purchases consistent with the vision of the
forthcoming 2015 IT Strategic Plan (Strategic Plan).
The 2014 IT Plan is a financial modeling tool based upon current goals and existing
technologies, but both goals and technologies change frequently. It is prudent to update
plans regularly as new opportunities become available. The forthcoming 2015 IT
Strategic Plan will be prepared in conjunction with the FY15-16 draft budget and the draft
2015 IT Plan that will then be incorporated into the draft 2015 Five-Year Financial Model
for the City as a part of the City Council's annual budget process. As individual
components of the IT Plan are designed and scheduled for implementation, equipment
and software licensing purchases will be also approved by City Council as required by
the Municipal Code.
K-1
RECEIVE AND FILE 2014 CITY FIVE-YEAR INFORMATION TECHNOLOGY PLAN
Page 2of4
DISCUSSION
1. Budgeting and Funding -the Equipment Replacement Fund -Computers
The City plans and funds the support, maintenance and replacement of technology using
the Equipment Replacement Fund (ERF). The ERF receives a transfer from the General
Fund equal to the total annual depreciation of technology equipment and software, as
well as estimated annual licensing and support costs. The annual transfer from the
General Fund to the ERF is allocated ("charged to") each operating department (e.g.
Recreation, Finance) based upon industry standard allocation factors (e.g. handsets
used, desktop computers used, number of department employees). This funding
mechanism smooths the impact on the General Fund that would otherwise result from
large IT purchases (e.g. the replacement of the virtual network server may cost
$200,000). Another benefit of this model is that ongoing support costs are known and
planned for in advance and included in the budgeting process.
All technology related systems, from computers and servers to business systems,
networking components, audio/visual, web technologies, voice and GIS mapping are
considered and included in the annual budget and the citywide Five-Year Financial Model
presented to the City Council for review, consideration and annual adoption.
2. IT Plan
The IT Plan consists of budgeted and modeled spending estimates for the upcoming 5
years. The IT Plan insures IT expenditures remain within confines of the Equipment
Replacement Fund (ERF), the annual budget and the citywide Five Year Financial Model.
The 2014 5 Year IT Plan also includes the on-going technology projects and tasks that
were included in the FY13-14 budget and are expected to be carried forward to FY14-15
as a part of the Continuing Appropriations staff report to be presented to the City Council
on September 2, 2014, the vast majority being the Enterprise Resource Planning (ERP)
systems for Finance, Community Development and Public Works. The plan that identifies
estimated annualized costs (the "IT Spending Plan") is attached as Exhibit A for review,
and the projected carry forward summary is outlined below.
Summary of Equipment Replacement Fund-Computers -FY13-14 Carryforward to
FY14-15 (subject to Council approval on September 2, 2014)
681-2082-499.43 -Maintenance (licensing, support & maintenance) including
implementation of Recreation and Parks online registration system and PVIC point of
sale system not paid in FY13-14) $ 83,000
681-2082-499.61 -Operating Supplies/Minor Equipment, including desktop printers &
scanners, UPS devices, monitors and utility copier/scanners $ 177,050
681-2082-499. 75 -Capital Equipment, Tyler financial and permitting system, Cityworks
for Public Works work order and infrastructure management and LARIAC GIS licensing. $ 671,400
TOTAL $ 931,450
3. IT Strategic Plan
Each year, the City Council creates a guiding document for the City in the form of annual
goals. The 2014 City Council Goals will be used to form the high level 2015 IT Strategic
Plans which are then used to create the more detailed 2015 IT Plans as described herein.
K-2
RECEIVE AND FILE 2014 CITY FIVE-YEAR INFORMATION TECHNOLOGY PLAN
Page 3 of 4
The forthcoming 2015 IT Strategic Plan will also incorporate the changes in City Council
goals in early 2015 which will be the primary guiding document for City technology into
the future.
One of the primary managerial/financial goals of the 2014 IT Plan (and annual revisions
to it) is to ensure that planned technology expenditures remain within budgeted norms of
3% and 5% of General Fund expenditures as well as used as a tool to prepare annual
budgets and forecasts.
4. Planned Major IT Objectives By Year
• Recently Completed
o Virtual cluster and conversion of over 30 servers from physical to virtual
o Microsoft Enterprise licensing agreement
o Dell City computers, conforming to standard system configurations
o Help Desk Ticketing solution
o PVNET Contract including the implementation of Service Level
Agreements
o Windows 7 upgrades
o Exchange 2013 and Lyne 2013 implementations
o Denali Cougar Mountain upgrade for PVIC Point of Sale (POS) system
o Activenet facility reservations portal
o IP Address reconfiguration almost complete
• FY2014-15
o Finance system implementation
o Website and list serve implementation to include self service capabilities
o City Council streaming and agenda automation system
o GIS, LARIAC4 and viewer upgrades and licensing
o Managed switch upgrades w/1 Ogig backbone speed
o Fiber optic connectivity to RPVtv cable studio to the City network
o City Council meeting room equipment upgrades resulting from Hesse Park
fiber project
o System Center computer management system configuration
o Converged Infrastructure upgrade resulting from system upgrades
o 5 year Strategic Plan
• FY 2015-16
o Land Management System implementation
o Work Order and Asset Management system
o Website Open Government initiative
o Business System integrations between finance and other systems
o Wireless Access Points at City locations
o Mobile devices management system
o Camera -website views and parking lot monitoring
o 311 System including mobile devices
o Citizen Relations Management System (integrated with 311)
K-3
RECEIVE AND FILE 2014 CITY FIVE-YEAR INFORMATION TECHNOLOGY PLAN
Page 4 of 4
• FY 2016-17
o Computer upgrades (50%)
o Emergency and Disaster Operations Software
o Integrated Devices -hard wired, wireless, mobile
o RPVTV server and network upgrades
o Park and offsite location connectivity
o Reverse 911 System
o Public Works System Integrations
• FY 2017-18
o Computer Upgrades (50%)
o Website refresh, new functionality and usability
o Unified Communications, messaging system upgrades
o Mobile systems refresh, field systems
o Infrastructure and security systems upgrades
o GIS upgrade, LARIAC5 imagery
• FY 2018-19
o Storage Area Network Infrastructure upgrade, storage expansion
o Disaster Recovery system upgrade
o Council agenda management system upgrade and refresh
o Finance system refresh
o Emergency Operations system refresh
o Camera systems refresh
FISCAL IMPACT
No fiscal impact. The 2014 IT Plan does not require any FY14-15 budget adjustments,·
nor revisions to the citywide Five-Year Financial Model.
Attachment:
Exhibit A-2014 IT Spending Plan Summary
K-4
5 Year IT Spending Plan Summary
Equipment Replacement Fund -Computers Expendatures
Maintenance Services $317aa5 ;"_,•,,••-... .J $347,070 $330iE)21
Ooeratina Suoolies/Min.or Equipment $117,500 $131,1ao $169,279
Capital Computer Equipmenf(Cost > $5,000) $4:15,000 $_39()"000 $387,00()
Total Planned Expendatures $850 .. 385 $86~;209 ... 86,900
% of Total General Fund Exoenditures (estimated) 4.15% 4.15%
ERP System Implementations $45,000 $100,000 $50,000
System Software Upgrades $30,000 $55,000 $62,000
Network and Security Infrastructure $205,000 $100,000 $105,000
Voice and Communications Infrastructure $20,000 $0 $30,000
Copiers, printers, AN and other equipment $0 $30,000 $40,000
GIS, Mapping and Land Data Systems $0 $0 $20,000
Internet and Web Based systems $60,000 $70,000 $55,000
RPVtv Infrastructure $35,000 $15,000 $5,000
Reserve for contingencies $20,000 $20,000 $20,000
I Total Capital Eguipment Plan __ _IL $415,oool $390,0001 $387,oool
$170,463 $91,168
$395,000 $489,000
$907,800 $929,700
$20,000 $80,000
$30,000 $34,000
$160,000 $195,000
$20,000 $30,000
$65,000 $15,000
$20,000 $80,000
$35,000 $20,000
$25,000 $15,000
$20,000 $20,000
$395,oool $489,oool