RPVCCA_CC_SR_2014_06_17_I_Five_Year_CIPCITY OF MEMORANDUM TO: HONORABLE MAYOR & CITY COUNCIL MEMB FROM: DENNIS McLEAN, DIRECTOR OF FINANCE & INFORMATION TECHNOLOGY DATE: JUNE 17, 2014 SUBJECT: 2014 FIVE-YEAR CAPITAL IMPROVEMENT PLAN REVIEWED: CAROLYNN PETRU, ACTING CITY MANAGE~ Project Manager: Kathryn Downs, Deputy Director of Finance & Information Technology RECOMMENDATION Approve the 2014 Five-Year Capital Improvement Plan. EXECUTIVE SUMMARY The CIP is a guide for the efficient and effective provision of resources for improving and maintaining public infrastructure and facilities. The CIP is segregated into both Funded and Unfunded projects and includes detailed "project sheets" that provide a project description, project type (e.g. Roadway Infrastructure), location, department responsible, estimates of cost, and the justification (e.g. safety, City Council goal, outside funding available). The CIP document does not include any projects with estimated costs below the infrastructure capitalization threshold of $100,000. Although the CIP document presents project funding for five years, the City Council approves CIP projects for the upcoming fiscal year only. This gives the City Council the ability to shift priorities when needed, while at the same time identify future projects and potential funding mechanisms. Projects are generally added to the "Funded" list as available funding sources are identified. Projects are usually funded first from restricted funds, to be conservative in allocating General Fund monies only when necessary. Staff recommends planning for use of the CIP Reserve (funded with General Fund money equivalent to transient I-1 2014 FIVE-YEAR CAPITAL IMPROVEMENT PLAN June 17, 2014 Page 2 of 3 occupancy tax revenue and prior year favorable General Fund expenditure variance in accordance with City Council Policy No. 41 -Reserve Policies). On May 13, 2014, the Planning Commission reviewed the CIP Document and adopted P.C. Resolution 2014-15, finding it to be consistent with the General Plan. Per City Council direction on June 3, 2014, the following cha·nges have been made to the 2014 CIP: • The Landslide Early Warning System (estimated cost of $300,000) was moved to the Unfunded List; • The estimated cost for improvements to the lower portion of Hesse Park was decreased to $500,000 on the Funded List (year 1) and included in the FY14-15 budget; • Two additional dewatering wells were added to the Funded List (year 1) and the proposed FY14-15 budget, resulting in a total budget appropriation of $360,00 in FY14-15; and • Civic Center Air Conditioning (placeholder estimate of $120,000) was added to the Funded List (year 1) and the proposed FY14-15 budget. The CIP list of "funded" projects (totaling $49.1 million) has been integrated into the 2014 Five-Year Financial Model. Projects listed in Year 1 of the CIP (totaling $10.5 million) have been included in the proposed FY14-15 budget, which is also on the June 17, 2014 agenda for City Council consideration. BACKGROUND AND DISCUSSION Programming capital facilities and improvements over time can promote better use of the City's limited financial resources, reduce costs and assist in the coordination of public and private development. Based on guidelines of the framework and those set forth by the City Council, Staff developed an inventory of capital projects. This inventory was compiled through a comprehensive review of existing reports, infrastructure plans, community input and the City Council's direction, goals and priorities. Some of these plans include the following: the Pavement Management System, Vision Plan, Sanitary Sewer Master Plan, Public Use Master Plan, Trails Network Plan, Storm Drain Master Plan and the General Plan. Staff evaluated every project quantified during the establishment and update of the CIP and established Criteria justifications that are reflected on each project sheet. These justification categories include: safety, support of essential City services, support of Council plan goals, economy and efficiency, outside funding, and community quality/sustainability. The Criteria justifications and the availability of restricted (non- General Fund) monies, are utilized to establish the priority level of CIP projects. Staff has included columns on the Funded and Unfunded lists (pages 11 & 68 of the I-2 2014 FIVE-YEAR CAPITAL IMPROVEMENT PLAN June 17, 2014 Page 3 of 3 document) to indicate whether the project supports public safety or another City Council priority. Expected Additions to Future CIP Documents Staff expects that there are at least two factors that will drive the addition of projects to the CIP. 1. Additional storm drain projects will likely be identified when the Storm Drain Master Plan is completed towards the end of 2014. 2. Additional water quality projects will likely be identified when the Regional Water Quality Board adopts a plan document towards the end of 2015. Attachment: 2014 Five-Year Capital Improvement Plan I-3 2014 Five-Year Capital Improvement Plan I-4 TABLE OF CONTENTS INTRODUCTION 3 FUNDED PROJECTS 10 FIVE YEAR CIP FUNDED LIST 11 BUILDINGS AND OTHER FACILITY IMPROVEMENTS 12 INTANGIBLE CAPITAL OUTLAY 22 ROADWAY INFRASTRUCTURE 24 UTILITY UNDERGROUNDING 38 STORM DRAIN SYSTEM 40 LANDSLIDE MITIGATION PROJECTS 47 STORM WATER QUALITY 49 SEWER PROJECTS 52 RECREATION, PARKS & OPEN SPACE 57 UNFUNDED PROJECTS 67 UNFUNDED LIST 68 BUILDINGS AND OTHER FACILITY IMPROVEMENTS 69 INTANGIBLE CAPITAL OUTLAY 73 ROADWAY INFRASTRUCTURE 75 UTILITY UNDERGROUNDING 83 STORM DRAIN SYSTEM 87 LANDSLIDE MITIGATION 92 RECREATION, PARKS & OPEN SPACE 94 I-5 INTRODUCTION A Capital Improvement Plan (CIP) is a guide toward the efficient and effective provision of public infrastructure and facilities. Programming capital facilities and improvements over time can promote better use of the City’s limited financial resources, reduce costs and assist in the coordination of public and private development. In addition, the planning process is valuable as a means of coordinating and taking advantage of joint planning and development of facilities and infrastructure where possible. Careful management of these assets keeps the City poised for flexible and responsive strategic planning that allows the City to proactively prepare the groundwork for capital projects so when funding opportunities arise, a plan is ready to be implemented. By looking beyond year-to-year budgeting and projecting what, where, when and how capital investments should be made, capital planning enables public organizations to maintain an effective level of service for the present and future population. THE CAPITAL IMPROVEMENT PLAN (CIP) The result of this continuing planning process is the CIP, which is the City’s five-year plan for infrastructure projects. The CIP addresses the City’s needs relating to the acquisition, expansion, and rehabilitation of long-lived facilities and infrastructure. The CIP serves as a planning instrument in conjunction with the City’s General Plan and the City Council’s Goals to identify needed capital projects and coordinate the financing and timing of improvements in a way that maximizes the return to the public. It provides a planned systematic approach to utilizing the City’s limited financial resources in the most responsive and efficient manner to meet its service and infrastructure needs. It serves as the “blueprint” for the future of the community and is a management and planning tool, rather than a binding document. The underlying strategy of the CIP is to plan for necessary land acquisition, construction and maintenance of public facilities necessary for the safe and efficient provision of public services in accordance with City policies and objectives adopted in the City’s General Plan. A critical element of a balanced CIP is the provision of funds to both preserve or enhance existing facilities and provide new assets to respond to changing needs and community growth. While the program serves as a long range plan, it is reviewed and revised annually in conjunction with the budget. Priorities may be changed due to funding opportunities or circumstances that propel a project to a higher importance. Along the way, projects may be revised for significant costing variances. The CIP is primarily a document that assists in addressing the City’s long-term needs. As such, the projects and their scopes are subject to change from year to year as the needs of the community become more defined and projects move closer to final implementation. The adoption of the CIP is neither a commitment to a particular project nor a limitation to a particular cost. As a basic tool for scheduling anticipated capital projects, it is also a key element in controlling future capital financing. For this reason, the CIP includes some “unfunded” projects in which needs have been qualified, but specific solutions and funding sources have not been determined. When adopted, the CIP provides the framework for the City’s management team and the City Council with respect to investment planning, project planning and the managing of any debt. This document is independent of the City Council’s goals and is intended to serve as a mid-term planning document. THE CIP PROCESS The capital improvement plan and budget is the result of an ongoing infrastructure planning process. Infrastructure planning decisions must be made with regard to both existing and new facilities and equipment. For existing facilities, the planning process addresses appropriate capital renewal strategies and repair-versus-replacement of facilities. New service demands are also considered since they often affect capital facility requirements. Planning for the five-year CIP period and subsequent years, includes linking the General Plan to the capital plan requirements, conducting needs assessments and allowing for flexibility to take advantage of opportunities for I-6 capital investment. The FY14-15 through FY18-19 CIP is developed through input from professional staff, citizens of Rancho Palos Verdes, and elected or appointed City officials. CIP REVIEW TEAM A CIP Review team is responsible for annually reviewing capital project requests and providing recommendations to the City Manager. This team is comprised of staff from the Office of the City Manager, Finance, Public Works, Community Development, and Recreation and Parks departments, and the City Attorney. This team conducts an in-depth analysis of the impact of the CIP on present and future cash flows and financial obligations, as well as the City’s ability to finance, process, design, and ultimately maintain projects. The team will also analyze the fiscal impact for each individual project; including future maintenance and replacement costs, associated monetary benefits (e.g. future maintenance savings), as well as any applicable future revenue opportunities. The team meets periodically throughout the year to evaluate the progress of projects, and examine future needs of the City. The overall goal of the CIP Review Team is to develop CIP recommendations that:  Preserve the past by investing in the continued upgrade of City assets and infrastructure;  Protect the present with improvements to City facilities and infrastructure;  Plan for the future. Projects are identified by staff, professional consultants, residents and/or elected officials. There are typically more proposals than can be funded in the five-year CIP period, so the team conducts an internal project ranking process. The criteria used in this internal ranking includes, but is not limited to, safety, support of essential City services, support of City Council’s goals, economy and efficiency, outside funding committed (or eligible for), and community quality/sustainability. Projects are prioritized based on the criteria outlined in this plan in the following section. If a project receives a lower ranking, it just means that other projects in that period of time are more critical for the City to address. While ratings are important in determining recommended projects, the realities of the City’s financial situation are critical to all decisions. CIP CRITERIA Safety: Enhance or improve the overall safety of the City and delivery of services. Protect the health and welfare of residents. Supports Essential City Services: Maintenance and development of existing or new facilities and infrastructure which allows the City to deliver essential services to residents of Rancho Palos Verdes. Supports City Council Goals: Supports the goals annually established by the City Council in the CITY COUNCIL. Meets citywide long-term goals and is in compliance with the City’s General Plan. Economy and Efficiency: Maintain and enhance the economy and efficiency of providing services in Rancho Palos Verdes. This criterion would include projects which improve business processes and overall efficiency while also evaluating environmental impacts. Outside Funding Committed or Eligible: Support a project which outside funding has been committed to or may be obtained through restricted revenue sources. Community Quality/Sustainability: Maintain and enhance the infrastructure and services which supports our residential and business community. This criterion would include projects which preserve and enhance the overall quality of life in Rancho Palos Verdes and projects which ensure economic viability to support a the community. I-7 THE CIP CALENDAR August-October Departments prepare CIP requests November- January CIP Team reviews requests February-May Recommendations developed to be included in the Five-Year Model and Draft Budget May-June Planning Commission Review May-June Recommendations presented to the City Council for approval Additional forms and methods of public outreach will be conducted as directed by the City Council. PROJECT LISTS The CIP includes a comprehensive listing of all projects contained in the Five-Year Plan and also projects beyond the five-year period. Detailed project sheets are contained in the plan for all projects included in the CIP. Another list of unfunded projects is also contained in the plan to highlight quantified projects beyond the five-year period. Projects which are included in the CIP were evaluated based on the criteria approved by the City Council and are in compliance with the goals set forth in the City’s General Plan. Application of these criteria ensures that each project recommended for Council consideration does indeed support the policy objectives of the City’s long-term planning documents and identifies a basis for scheduling and allocation of resources. Cost estimates have been developed for each project based on preliminary project descriptions, and include all estimated costs for land acquisition, permits and inspections, project management and project engineering, consultant design, construction, utilities, information technology infrastructure and other associated project fees. Estimates are in today’s dollars. CAPITAL IMPROVEMENT POLICIES Time Period The Finance Department, in cooperation with all other City Departments and the City Attorney, shall produce a working document designed to identify capital needs annually in conjunction with the budget process. This Five-Year Capital Improvement Plan (CIP) is submitted to the City Council to utilize in reviewing and prioritizing capital projects. After adoption by Council during the budget process, the CIP becomes the City’s plan for capital improvements for the next five years, adjusted annually. Type of Project Definitions Capital asset: An asset with a cost in excess of $5,000 and an expected useful life of more than one year, such as automobiles, equipment, and furniture. These items will continue to be included in the operating budget. Items such as automobiles, minor equipment, and furniture will continue to be accounted for and funded using the Equipment Replacement Fund and are not included in the capital improvement plan. Capital project: A project expected to have a useful life greater than ten years and an estimated cost of $100,000 or more. Capital projects include the construction, acquisition, or major renovation of buildings, roadways, utility systems, or other structures, purchase of land, and major landscaping projects. I-8 Projects meeting the above definition will be included in the CIP document in addition to the City’s budget document. The information will be tied to the capital budget and totals for each project in the CIP will be included in the capital budget. Selecting the Projects for the CIP The comprehensive capital project planning process has the following essential components:  The General Plan (Long-term Plan - 10 Years)  The Capital Improvement Plan (Mid-term Plan - 5 Years)  The Capital Budget (Short-term Plan - 1 Year)  City Council Goals (Long-term and Short-term evaluated each year) All projects selected for the CIP should be consistent with the goals identified by the City Council or as outlined in the City’s General Plan. The project selection process strives to achieve a balanced plan for the community to include all necessary and high priority projects, while also enhancing City services and facilities. Operating Budget Impact Identified in the CIP The operating impact of proposed capital projects, including personnel, operating expenditures, capital outlay, and debt service, as applicable, will be identified in the CIP document and considered in preparing the annual operating budget and Five-Year Financial Model. Moving Projects from the CIP to the Capital Budget All projects approved in the annual capital budget are appropriated at the estimated cost to complete the project. At the end of each fiscal year, the remaining appropriation for uncompleted portions of the project will be carried forward to subsequent fiscal years. Staff will identify the estimated costs, potential funding sources, operating impact, and project schedule for each capital project proposal before it is submitted to the City Council. Staff will coordinate development of the capital improvement budget with the development of the operating budget. All costs for internal professional services needed to implement the CIP will be included in the capital budget as part of the budget document for the years the CIP is to be implemented. Cost tracking for components of the capital improvement program will be updated semi-annually to ensure project completion against budget and established time lines. Funding of the CIP Reserve Fund City Council Policy No. 41 regarding the City’s Reserves provides for a minimum CIP Reserve level of $3,000,000 for emergency projects, the transfer of the total annual Transient Occupancy Tax (TOT) revenue into the CIP Reserve, and the transfer of any prior year General Fund favorable expenditure variance to the CIP Reserve. The TOT revenue for FY14-15 is estimated to be about $4 million. Definition of Capital Budget Year A capital budget year runs concurrent to the operating budget fiscal year beginning July 1st and ending June 30th. Types of Financing The nature and cost of the project generally determines the financing options as do projected revenue resources. The following financing instruments could be used in the following preferred order:  Outside funding that does not require repayment, including grants, federal, state and county restricted funding (i.e. transportation funding), and donations; I-9  Developer Fees;  City restricted revenue imposed by voters (i.e. environmental excise tax, storm drain user fee);  Accumulated Fund Balances in Restricted Funds;  General Fund;  Debt secured by a Restricted Revenue Source; and  General Obligation Debt. Remaining Balances It is the City’s policy to apply restricted funding sources after a project is completed and final cost is identified, or at the close of each fiscal year, whichever occurs first. Evaluation of Capital Projects Capital project and program reviews are to monitor existing project performance and to update the Five-Year CIP. Each project must be actively managed and semi-annual reports on the physical and fiscal status of each project should be made available to the City Council in conjunction with the budget adoption and Mid-Year Financial Review. Green Building Standards The City of Rancho Palos Verdes requires the incorporation of green building principles and practices into the design, construction, and operation of all City facilities, and to evaluate all land purchases for future development on the basis of reducing environmental impacts whenever feasible. Standards for Maintenance It is important to have standards in place for the various infrastructure systems throughout the City to maintain this investment and be positioned to provide adequate services for the residents of Rancho Palos Verdes. Staff will develop maintenance standards and schedules as appropriate. Contingency Policy The need for contingencies will be evaluated with each project and be included in the CIP on a case-by-case basis. Project Change Orders Project change orders will be made in accordance with the policy stated in Section 02.44 of the Municipal Code. GENERAL PLAN GOALS The goals stated below are included in the City’s General Plan which serves as the City’s long-term strategic planning tool. All CIP projects should contribute to fulfilling one or more of the goals listed below. Natural Environment Element  It is the goal of the City of Rancho Palos Verdes to conserve, protect, and enhance its natural resources, beauty, and open space for the benefit and enjoyment of its residents and the residents of the entire region. Future development shall recognize the sensitivity of the natural environmental and be accomplished in such a manner as to maximize the protection of it. Socio/Cultural Element  The City shall strive to protect and preserve all significant archaeological, paleontological and historical resources within the City. I-10 Cultural Resources  The City shall strive to protect and preserve all significant archaeological, paleontological and historical resources within the City. Current Social, Service, and Cultural Organizations  Work toward a coordinated program to aid in matching the facility needs of the many and diverse groups in the community with existing and future facility resources throughout the City. Social Services  Encourage programs for community involvement, participation, and action to minimize the sense of isolation and powerlessness felt by many individuals in the community.  Encourage programs for recreation, social services, and cultural and educational achievement.  Encourage a framework for interaction among the four cities of the peninsula and between the peninsula and its surrounding communities to solve common problems. Urban Environment Element  It is the goal of the City to carefully control and direct future growth towards making a positive contribution to all elements of the community. Growth in Rancho Palos Verdes should be a cautious, evolutionary process that follows a well-conceived set of general guidelines which respond to both holding capacity limitations for the region and environmental factors on the peninsula. Activity Areas  It is the goal of the City of Rancho Palos Verdes to preserve and enhance the community's quality living environment; to enhance the visual character and physical quality of existing neighborhoods; and to encourage the development of housing in a manner which adequately serves the needs of all present and future residents of the community.  The City shall discourage industrial and major commercial activities due to the terrain and environmental characteristics of the City. Commercial development shall be carefully and strictly controlled, and limited to consideration of convenience or neighborhood service facilities.  The City shall encourage the development of institutional facilities to serve the political, social, and cultural needs of its citizens.  The City shall endeavor to provide, develop, and maintain recreational facilities and programs of various types to provide a variety of activities for persons of all age groups and in all areas of the community.  Agricultural uses within the City shall be encouraged, since they are desirable for resource management and open space. Infrastructure  It shall be a goal of the City to ensure adequate public utilities and communications services to all residents, while maintaining the quality of the environment.  It shall be a goal of the City to provide residents with a safe and efficient system of roads, trails and paths.  It shall be a goal of the City to encourage the increased mobility of residents through the development of an adequate public transportation system. I-11 Safety  It shall be a goal of the City to provide for the protection of life and property from both natural and man-made hazards within the community.  It shall be a goal of the City to provide for the protection of the public through effective law enforcement and fire protection programs.  It shall be a goal of the City to develop and enforce health and sanitation, emergency communications, and disaster preparedness programs to ensure the overall health and safety of all residents.  It shall be a goal of the City to protect life and property and reduce adverse economic, environmental, and social impacts resulting from any geologic activity. Sensory Environment  It shall be the goal of the City of Rancho Palos Verdes through proper land use planning and regulations, to provide for a quiet and serene residential community with a minimum of restriction on citizen activity.  Palos Verdes peninsula is graced with views and vistas of the surrounding Los Angeles basin and coastal region. Because of its unique geographic form and coastal resources, these views and vistas are a significant resource to residents and many visitors, as they provide a rare means of experiencing the beauty of the peninsula and the Los Angeles region. It is the responsibility of the City to preserve these views and vistas for the public benefit and, where appropriate, the City should strive to enhance and restore these resources, the visual character of the City, and provide and maintain access for the benefit and enjoyment of the public. Land Use Plan  It is the goal of the City of Rancho Palos Verdes to provide for land uses which will be sensitive to and enhance the natural environment and character of the community, supply appropriate facilities to serve residents and visitors, promote a range of housing types, promote fiscal balance, and protect the general health, safety, and welfare of the community. Fiscal Element  It shall be a goal of the City to hold the property tax to a minimum and to continually explore and analyze the advantages and disadvantages of alternate or new sources of revenue.  It shall be a goal of the City to explore cooperative financing strategies that might be undertaken in association with other jurisdictions.  It shall be a goal of the City to take maximum advantage of regulatory legislation to obtain contributions, dedications and reservations (i.e., easements).  It shall be a goal of the City to ascertain that all revenues generated by growth are sufficient to cover costs related to growth.  It shall be a goal of the City to thoroughly evaluate capital acquisition and operating expenditures and their impacts before implementation of programs. I-12 FUNDED PROJECTS The following projects are those which have been identified as capital needs through various planning processes along with a proposed funding source. Because the City Council approves CIP projects for the upcoming year, proposed future funding sources could change in subsequent years. I-13 Rancho Palos Verdes Five Year Capital Improvement Plan - Funded Projects Page Safety Goal Council Priority FY14-15 FY15-16 FY16-17 FY17-18 FY18-19 Identified Funding Source Buildings and Other Facility Improvements Citywide ADA Transition Plan Implementation 14 X 400,000$ 200,000$ 150,000$ 150,000$ 150,000$ EET/CIP Reserve RPV TV Building Improvements 15 X 110,000$ CIP Reserve Fiber Optic Cabling - Hesse Park/Ryan Park 16 260,000$ CIP Reserve Fiber Optic Cabling - Abalone Cove Sewer Lift Stations/Shoreline Park/Ladera Linda 17 X 1,600,000$ CIP Reserve Ladera Linda Community Center Improvements 18 X 4,000,000$ CIP Reserve Solar Power System Hesse Park 19 385,000$ Energy Savings Grant Solar Power System PVIC 20 410,000$ Energy Savings Grant Civic Center Air Conditioning 21 X 120,000$ CIP Reserve Intangible Capital Outlay Pavement Management Program Update 23 X X 120,000$ CIP Reserve Roadway Infrastructure Residential Street Rehabilitation Zone 2 & 6 25 X X 3,000,000$ General Fund Residential Street Rehabilitation Zone 7 26 X X 2,000,000$ General Fund, TDA Article 3 funds Residential Street Rehabilitation Zone 8 27 X X 2,000,000$ General Fund, TDA Article 3 funds Residential Street Rehabilitation Zone 3 & 4 28 X X 2,100,000$ General Fund, TDA Article 3 funds Residential Street Rehabilitation Zone 5 29 X X 2,100,000$ General Fund, TDA Article 3 funds Arterial Rehabilitation - Miraleste Drive 30 X X 2,500,000$ STPL, Measure R, Prop A/C, CIP Reserve Arterial Rehabilitation - Crenshaw Boulevard 31 X X 200,000$ 2,600,000$ Measure R, Prop C, CIP Reserve Arterial Rehabilitation - Indian Peak Road 32 X X 1,800,000$ Measure R, Prop C, CIP Reserve Arterial Rehabilitation - Silver Spur Road 33 X X 1,800,000$ Measure R, Prop C, CIP Reserve Traffic Safety Improvements - PVDE at Bronco 34 X X 500,300$ HSIP 90%, CIP Reserve 10% PVDS Road Way Realignment and Drainage Project 35 X X 3,060,000$ CIP Reserve Western Avenue Traffic Improvements 36 X X 3,200,000$ 50/50 Inter-Agency Cost-Share/CIP Reserve Hawthorne Blvd Corridor Beautification Study 37 X 150,000$ CIP Reserve Utility Undergrounding Crenshaw Boulevard Undergrounding 39 1,200,000$ Rule 20A funds Storm Drain System Storm Drain Lining 41 X X 335,278$ 340,836$ 347,653$ 350,000$ 350,000$ WQFP User Fees/CIP Reserve South Hawthorne/Via Frascati 42 X X 440,000$ WQFP User Fees Altamira Canyon Drainage Project Study Report 43 X X 500,000$ CIP Reserve Paintbrush Canyon Drainage Project Study Report 44 X X 120,000$ WQFP User Fees PVDS Roadway Drainage Project at Sacred Cove 45 X X 450,000$ WQFP User Fees/CIP Reserve Storm Drain Line Point Repair Projects 46 X X 150,000$ 900,000$ WQFP User Fees/CIP Reserve Landslide Mitigation Projects Landslide Dewatering Well Program 48 X X 360,000$ 450,000$ 450,000$ 180,000$ 180,000$ CIP Reserve Storm Water Quality Projects Drainage Area Monitoring System 50 300,000$ CIP Reserve Storm Water Quality Improvement Program 51 100,000$ 100,000$ 100,000$ 100,000$ 100,000$ CIP Reserve Sewer Projects Capacity Project - Ginger Root Lane 53 X X 203,000$ CIP Reserve Capacity Project - Malaga Canyon 54 X X 407,000$ CIP Reserve Capacity Projects - Other Locations 55 X X $ 465,000 CIP Reserve Abalone Cove Sewer District Rehabilitation 56 X X 500,000$ 500,000$ 500,000$ 500,000$ CIP Reserve Recreation, Parks, and Open Space Lower Hesse Park Improvements (Phase 1)58 X 500,000$ CIP Reserve Hesse Park Parking Lot Resurfacing 59 X 210,000$ CIP Reserve Point Vicente Interpretive Center (PVIC) Screening Wall 60 110,000$ CIP Reserve Sunnyside Trail Segment 61 X 465,000$ Grant/CIP Reserve PVIC Exhibits 62 400,000$ Donations PVIC Landscaping Improvements 63 400,000$ Donations Gateway Park Trailhead & Parking Access Improvements 64 X 200,000$ CIP Reserve Abalone Cove Beach Access Road 65 X 100,000$ CIP Reserve Grandview Park Improvements (Phase 1)66 X 635,000$ CIP Reserve Totals 10,510,278$ 7,106,136$ 7,242,653$ 10,130,000$ 14,075,000$ I-14 BUILDINGS AND OTHER FACILITY IMPROVEMENTS Buildings and other facility improvements may include any proposed new City facility or renovation or improvement of any existing City facilities. The City owns and maintains the following public buildings:  City Hall Administration Building at Point Vicente Park  City Hall Community Development Building at Point Vicente Park  City Hall trailer leased by Palos Verdes on the Net at Point Vicente Park  City Hall Emergency Communications Center trailer at Point Vicente Park  Fred Hesse Jr. Community Center Building  Pointe Vicente Interpretive Center (PVIC) at Lower Point Vicente Park  Robert Ryan Park Building  Ladera Linda Community Center Buildings (5)  RPV TV Studio Building  Buildings at Abalone Cove Shoreline Park, currently used for staffing, public restrooms, and a nursery school on the beach.  Pelican Cove Restroom Building Except for PVIC, these buildings are 25 years old or older and showing the signs of daily use. Many of the facilities were purchased from the school district or transferred to the City from the federal government, and little to no improvements have been made since their acquisition. It is important to perform adequate maintenance to extend the life of these facilities. It will be necessary to renovate these buildings as they age to meet the needs of the community and ensure that all building and safety guidelines are satisfied. PVIC, the most recently remodeled City facility, was built in 1984 and expanded in 2005. The City Hall buildings and Ladera Linda Community Center buildings are the best examples of buildings that are in great need of renovation to meet organizational needs, comply with safety and code requirements, and comply with all Americans with Disabilities Act (ADA) guidelines. The projects listed on the following pages have been developed based on individual staff assessments, input from the community and professional consultants’ assessments and studies. In November 2010, the City’s consultants completed a Civic Center Facilities Assessment, which offered alternatives and general cost estimates for building improvements to serve municipal functions, as well as optional public amenities with a view to the long-term needs of the City. The alternatives identified range widely from a “no-frills” structural, HVAC and ADA retrofit to the existing administration facility--to newly-constructed civic facilities which could incorporate community-serving amenities (public meeting rooms, community center, etc.). In light of competing CIP demands, the City Council has directed Staff to focus on cost-effective renovation of existing City Hall buildings. Therefore, the full- expansion, new construction alternative is not included in the Unfunded project list within this document. The City Council ad-hoc subcommittee for the Point Vicente/Civic Center Master Plan is working with Staff on a critical needs I-15 assessment, including the seismic retrofit of City Hall buildings, improvements to address ADA compliance throughout the campus, as well as heating, ventilation, and air conditioning. Once those projects are fully considered by the Council, the project description and associated costs will be incorporated in accordance with Council’s direction into the CIP schedule. I-16 PROJECT: CITYWIDE ADA TRANSITION PLAN IMPLEMENTATION TYPE: Buildings and Other Facility Improvements LOCATION: Various DEPARTMENT: Public works DESCRIPTION: The Citywide ADA Transition Plan, adopted by the City Council on June 4, 2013, identified total costs of $11.85 million for implementation. The cost estimate included improvements to ADA compliance at the Civic Center (buildings and grounds) totaling $1.36 million, and those at Ladera Linda Park totaling $1.72 million. Any future improvements at those sites are expected to bring the facilities into ADA compliance. Additionally, the total cost of $11.85 million includes right-of-way improvements totaling $2.64 million, including curb ramps and bus stops. Those improvements will be addressed as part of each roadway rehabilitation project. The remaining identified costs of $6.12 million will be addressed through this annual implementation allocation. Total project costs to remove barriers categorized as “potential hazard” and “severe” was estimated to be about $800,000. Phase 1 of ADA Transition Plan (TP) implementation for those categories was appropriated in FY13-14 for $400,000. The FY14-15 appropriation is for Phase 2 of TP implementation for the same categories. The allocations in Years 2 through 5 are for other improvements included in the $6.12 million cost estimate noted above. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $40,000 $17,500 $10,000 $10,000 $10,000 CONSTRUCTION $360,000 $182,500 $140,000 $140,000 $140,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $400,000 $200,000 $150,000 $150,000 $150,000 IMPACT ON OPERATING BUDGET Funding Source: EET and CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-17 PROJECT: RPV TV BUILDING IMPROVEMENTS TYPE: Buildings and Other Facility Improvements LOCATION: Civic Center at Upper Point Vicente DEPARTMENT: Public Works DESCRIPTION: The HVAC system at the RPV TV Building is deteriorating and is beyond repair. This system which is required for daily activities and the cable television systems, is affixed to the ceiling of the storage room. The new HVAC system will be relocated to the back of the building (utility area), allowing the storage room to be converted to a much needed waiting area for visitors. The new HVAC system will have sufficient capacity to keep the server system at the required temperature. The cable/server system which currently occupies an office, will also be relocated to the utility area in the back of the building allowing the office to be utilized for its original purpose. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $25,000 CONSTRUCTION $85,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $110,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve JUSTIFICATION FOR INCLUSION IN FY 14-15 BUDGET SAFETY X ECONOMY AND EFFICIENCY X SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY OTHER PROJECT INFORMATION: I-18 PROJECT: FIBER OPTIC CABLING: HESSE/RYAN PARK TYPE: Buildings and Other Facility Improvements LOCATION: Hesse Park/Ryan Park DEPARTMENT: Administration and Public Works DESCRIPTION: This project includes the installation of fiber optic cabling for the City’s phone and information network between City facilities within the public right-of-way which will run adjacent to Ryan Park and directly on to Hesse Park. To reduce costs, this project will be strategically aligned with the Hawthorne Traffic Signal Synchronization Project to take advantage of the asphalt removed for the other project. Vaults will be placed adjacent to the roadway within the public right-of-way. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $260,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $260,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY X SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY OTHER PROJECT INFORMATION: The project design of $60,000 was appropriated in FY13-14. I-19 PROJECT: FIBER OPTIC CABLING: ABALONE COVE SEWER LIFT STATIONS/ SHORELINE PARK/LADERA LINDA TYPE: Buildings and Other Facility Improvements LOCATION: Ladera Linda/Abalone Cove Shoreline Park DEPARTMENT: Administration and Public Works DESCRIPTION: This project includes the installation of fiber optic cabling for unified communications and data transmission between remote City park and infrastructure facilities and the Civic Center administration facility. It is essential to establish communications to Abalone Cove Shore Line Park, the Abalone Cove Sewer Lift Stations and Ladera Linda Park. Improved connectivity with Ladera Linda is essential to provide full communication services to the eastside community park in conjunction with its rehabilitation. The entire fiber optic run could occur by a combination of aerial and underground line placement. The project includes running a single line of fiber optic cabling on its own network from City Hall to Abalone Cove Shoreline Park, Abalone Cove Sewer lift stations and on to Ladera Linda Park, with the cost of approximately $1.6M. The work would entail installing 24-48 strand fiber in 3” conduit within the public right of way along Palos Verdes Drive South by either open cut or boring construction methods. Due to challenges with running fiber through the landslide area, the option of leasing fiber from an Internet Service Provider between the Civic Center and Ladera Linda will be included in the scope of the project. Cox Communications currently has fiber that connects to users along the road adjacent to Ladera Linda. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $1,600,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $1,600,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-20 PROJECT: LADERA LINDA PARK & COMMUNITY CENTER BUILDINGS REPLACEMENT TYPE: Buildings and Other Facility Improvements LOCATION: Ladera Linda Park DEPARTMENT: Public Works DESCRIPTION: The initial stage of this project, for which a budget has been appropriated, is to create a master plan which will lay the groundwork for the site’s long-term redevelopment and phased implementation. This stage involves a study of community needs through public outreach along with contemplating the City’s needs for public service facilities. This work will be followed by programming, quantifying the needs, planning and preparing a feasibility report to create a master plan which can be phased for design and construction. The cost calculation for Ladera Linda Buildings Replacement project is based on an estimated need for 12,000 square-feet of buildings to replace the existing 18,000 square-feet. The anticipated square footage could include park restrooms, a staff building, multipurpose room, activity rooms, discovery room and a Park Ranger/Deputy Sheriff drop-in office. Other improvements include park grounds landscaping & irrigation, picnic tables, benches and an emergency generator. The project can be divided in three phases. The first phase will include Hazmat abatement, removal of all buildings, installation of all utility infrastructures, the construction of 6,000 SF of new building, park grounds, landscaping & improvements. The second and third phase will include 3,000 SF of new buildings each. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $4,000,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $4,000,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. Phase I - $4 million in CIP Reserves Phase II - $1.6 million in CIP Reserves Phase III - $1.6 million in CIP Reserves Total Cost: $7.2 million JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-21 PROJECT: SOLAR POWER SYSTEM FOR HESSE PARK BUILDING TYPE: Buildings and Other Facility Improvements LOCATION: Hesse Park DEPARTMENT: Public works DESCRIPTION: Installation of lightweight and advanced solar energy generating systems over the roof of Hesse Park to reduce power consumption with occasional opportunities to sell power to the grid. This project will help the City with its energy savings goal and will reduce considerable amounts of emissions. Typically the energy savings can cover the cost of projects of this scale in an estimated period of 15 to 20 years. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $35,000 CONSTRUCTION $350,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $385,000 IMPACT ON OPERATING BUDGET Funding Information: Fully funded with an Energy Savings grant (federal/state) JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY X SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Potential electricity savings is about $18,000 annually. The life of the system is expected to be 20-25 years. Solar system components are generally under warranty for 10-12 years. I-22 PROJECT: SOLAR POWER SYSTEM FOR POINT VICENTE INTERPRETIVE CENTER (PVIC) TYPE: Buildings and Other Facility Improvements LOCATION: PVIC DEPARTMENT: Public works DESCRIPTION: Installation of lightweight and advanced solar energy generating systems over the roof of PVIC to reduce power consumption with occasional opportunities to sell power to the grid. This project will help the City with its energy savings goal and will reduce considerable amounts of emissions. Typically the energy savings can cover the cost of projects of this scale in an estimated period of 15 to 20 years. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $35,000 CONSTRUCTION $375,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $410,000 IMPACT ON OPERATING BUDGET Funding: Fully funded with an Energy Savings grant (federal/state) JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY X SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Potential electricity savings is about $20,000 annually. The life of the system is expected to be 20-25 years. Solar system components are generally under warranty for 10-12 years. I-23 PROJECT: CIVIC CENTER AIR CONDITIONING TYPE: Buildings and Other Facility Improvements LOCATION: Civic Center DEPARTMENT: Public works DESCRIPTION: The project would include an assessment of various alternatives to install air conditioning in Civic Center buildings. Building temperatures during warm summer days contribute to reduced staff productivity. Alternatives could include individual wall-mounted units for each office, a split-area cooling system, or a central system that would also address heating. Due to the aged electrical system and the anticipated high power demand, the project may also include electrical modifications to accommodate air conditioning. The estimated project cost of $120,000 serves as a placeholder appropriation, and does not include design costs. After alternatives are vetted, estimated project costs may increase. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $120,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $120,000 IMPACT ON OPERATING BUDGET Funding: CIP Reserve JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY OTHER PROJECT INFORMATION: I-24 INTANGIBLE CAPITAL OUTLAY Intangible Capital Outlay improvements may not have significant physical substance, but they have more than minimal value and help the City in improving operations or planning for the future. Projects that could be classified as intangible capital outlay include the update or development of major planning processes and documents, significant software purchases that may improve the efficiency of business processes or large technology purchases that may improve or enhance service delivery to citizens. I-25 PROJECT: PAVEMENT MANAGEMENT PROGRAM (PMP) UPDATE TYPE: Intangible Capital Outlay LOCATION: N/A DEPARTMENT: Public Works DESCRIPTION: The PMP is updated every three years to evaluate the condition of the City’s roadway system and to identify Citywide Arterial and Residential Street Rehabilitation projects. The Metropolitan Transit Authority (Metro) requires the PMP update in order for the City to continue receiving Proposition C monies. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $120,000 CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $120,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY X SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-26 ROADWAY INFRASTRUCTURE Roadway infrastructure is one of the most widely used major capital investments of a municipality. Without a well-maintained street system, the transportation needs of the public, business, industry and government cannot be met. The roads are also part of a critical public safety need, as they contribute to the general health and welfare of the community. Maintaining quality roadway infrastructure is also important for maintaining property values. It has been shown that property values tend to suffer from adjacent poorly maintained streets. Roadway infrastructure includes residential streets, arterial streets and traffic safety improvements. In the City of Rancho Palos Verdes, there are 44.3 miles of arterial streets and 104.2 miles of residential streets. The total for all streets and alleys mileage is 148.5 centerline miles. To manage the City’s residential and arterial streets, the City hires a consultant that completes a full-detailed assessment of all streets every three years. This report, known as the Pavement Management Program (PMP), helps to identify any serious issues and provides the City with a rating for each street. The report includes the overall Pavement Condition Index (PCI). The City of Rancho Palos Verdes maintains a minimum standard for PCI for a municipal street system at 80. The City’s current PCI is 81.8 based upon the PMP report prepared by Bucknam Infrastructure Group, Inc. in 2013. Since 1997 the City has maintained a pavement rating between 80 and 90. The report also helps in defining a schedule to complete the work. The City has been divided into nine zones for residential streets, but in the case of some areas, zones may be completed together in one year for added efficiency. I-27 PROJECT: RESIDENTIAL REHABILITATION TYPE: Roadway Infrastructure LOCATION: Zones 2 & 6 DEPARTMENT: Public Works DESCRIPTION: As part of the City’s PMP, Zones 2 & 6 of the residential rehabilitation program are scheduled for implementation during the FY14-15 budget cycle. This project will include slurry seal, overlay, curb repair, root removals and ADA compliance updates of the streets and sidewalks in Zones 2 & 6. This infrastructure enhancement will also include updating traffic signs, striping, curb painting, house numbering and monument surveying. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $3,000,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $3,000,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: General Fund JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: This project is part of the annual residential street overlay and slurry seal program and is scheduled for completion in FY14-15. This project is funded by the General Fund, and has a goal to achieve a pavement condition of 86 or higher, which is considered “Very Good Condition”. LOCATION PHOTO LOCATION DESCRIPTION Zone 2: Residential streets in the northwestern part of the City between Crest Road and Grayslake Road, east and west of Hawthorne Blvd. Zone 6: Residential streets in the southern part of the City encompassing all neighborhoods to the east of Point Vicente Park and west of Trump National including Crestmont, Tramonto, Seaview, Barkentine, and Seacove. I-28 PROJECT: RESIDENTIAL REHABILITATION TYPE: Roadway Infrastructure LOCATION: Zone 7 DEPARTMENT: Public Works DESCRIPTION: As part of the City’s PMP, Zone 7 of the residential rehabilitation program is scheduled for implementation during the FY15-16 budget cycle. This project will include micro-surfacing, slurry seal, overlay, curb repair, root removals and ADA compliance updates of the streets and sidewalks in Zone 7. This infrastructure enhancement will also include updating traffic signs, striping, curb painting, house numbering, and monument surveying. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $2,000,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $2,000,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: General Fund and TDA Article 3 of approximately $25,000 JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: This project is part of the annual residential street overlay and slurry seal program and is scheduled for completion in FY15-16. This project is funded by the General Fund, and has a goal to achieve a pavement condition of 86 or higher, which is considered “Very Good Condition”. LOCATION PHOTO LOCATION DESCRIPTION Zone 7: The Ladera Linda community, Ganado Area, streets near Mira Catalina School, San Ramon and Calle Aventura. I-29 PROJECT: RESIDENTIAL REHABILITATION TYPE: Roadway Infrastructure LOCATION: Zone 8 DEPARTMENT: Public Works DESCRIPTION: As part of the City’s PMP, Zone 8 of the residential rehabilitation program is scheduled for implementation during the FY16-17 budget cycle. This project will include micro-surfacing, slurry seal, overlay, curb repair, root removals and ADA compliance updates of the streets and sidewalks in Zone 8. This infrastructure enhancement will also include updating traffic signs, striping, curb painting, house numbering, and monument surveying. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $2,000,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $2,000,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: General Fund and TDA Article 3 of approximately $25,000 JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: This project is part of the annual residential street overlay and slurry seal program and is scheduled for completion in FY16-17. This project is funded by the General Fund, and has a goal to achieve a pavement condition of 86 or higher, which is considered “Very Good Condition”. LOCATION PHOTO LOCATION DESCRIPTION Zone 8: Residential neighborhoods off of Palos Verdes Drive East in the northern and eastern parts of the City. I-30 PROJECT: RESIDENTIAL REHABILITATION TYPE: Roadway Infrastructure LOCATION: Zones 3 & 4 DEPARTMENT: Public Works DESCRIPTION: As part of the City’s PMP, Zones 3 & 4 of the residential rehabilitation program is scheduled for implementation during the FY17-18 budget cycle. This project will include micro-surfacing, slurry seal, overlay, curb repair, root removals and ADA compliance updates of the streets and sidewalks in Zones 3 & 4. This infrastructure enhancement will also include updating traffic signs, striping, curb painting, house numbering, and monument surveying. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $2,100,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $2,100,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: General Fund and TDA Article 3 of approximately $25,000 JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: This project is part of the annual residential street overlay and slurry seal program and is scheduled for completion in FY17-18. This project is funded by the General Fund, and has a goal to achieve a pavement condition of 86 or higher, which is considered “Very Good Condition”. LOCATION PHOTO LOCATION DESCRIPTION Zone 3: Residential streets north of Silver Spur Rd and east of Hawthorne Blvd, including the Blackhorse community, Silver Arrow, Longhill and Beechgate Zone 4: Residential streets bordering Crenshaw Blvd and Crest Road, including the Sea Crest, Sea Breeze, Island View, and Ridgecrest communities I-31 PROJECT: RESIDENTIAL REHABILITATION TYPE: Roadway Infrastructure LOCATION: Zone 5 DEPARTMENT: Public Works DESCRIPTION: As part of the City’s PMP, Zones 5 of the residential rehabilitation program is scheduled for implementation during the FY18-19 budget cycle. This project will include micro-surfacing, slurry seal, overlay, curb repair, root removals and ADA compliance updates of the streets and sidewalks in Zones 5. This infrastructure enhancement will also include updating traffic signs, striping, curb painting, house numbering, and monument surveying. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $2,100,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $2,100,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: General Fund and TDA Article 3 of approximately $25,000 JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: This project is part of the annual residential street overlay and slurry seal program and is scheduled for completion in FY18-19. This project is funded by the General Fund, and has a goal to achieve a pavement condition of 86 or higher, which is considered “Very Good Condition”. LOCATION PHOTO LOCATION DESCRIPTION Zone 5: Residential streets in the most western part of the City, off Hawthorne and between Crest and PVDW. I-32 PROJECT: ARTERIAL REHABILITATION – MIRALESTE DRIVE TYPE: Roadway Infrastructure LOCATION: Miraleste Drive DEPARTMENT: Public Works DESCRIPTION: As part of the City’s PMP, Miraleste Drive arterial will be resurfaced. The project will include milling and overlay, roadway patching, crack filling, curb and gutter repair, sidewalk repair and ADA upgrades. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $2,500,000 CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $2,500,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: STPL funding, Proposition C, Proposition A, Measure R and CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: The project goal would result in a pavement condition of 86 or higher, which is considered “Very Good Condition”. The project design of $70,000 was appropriated in FY13-14. I-33 PROJECT: ARTERIAL REHABILITATION – CRENSHAW BLVD TYPE: Roadway Infrastructure LOCATION: Crenshaw Blvd. DEPARTMENT: Public Works DESCRIPTION: As part of the City’s PMP, Crenshaw Blvd. arterial will be resurfaced. The project will include milling and overlay, roadway patching, crack filling, curb and gutter repair, sidewalk repair and ADA upgrades. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $200,000 $2,600,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $200,000 $2,600,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: Proposition C, Measure R and CIP Reserves. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: The project goal would result in a pavement condition of 86 or higher, which is considered “Very Good Condition”. I-34 PROJECT: ARTERIAL REHABILITATION – INDIAN PEAK ROAD TYPE: Roadway Infrastructure LOCATION: Indian Peak Road DEPARTMENT: Public Works DESCRIPTION: As part of the City’s PMP, Indian Peak Road arterial will be resurfaced. The project will include milling and overlay, roadway patching, crack filling, curb and gutter repair, sidewalk repair and ADA upgrades. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $100,000 CONSTRUCTION $1,700,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $1,800,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: Proposition C, CIP Reserve and Measure R funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: The project goal would result in a pavement condition of 86 or higher, which is considered “Very Good Condition” I-35 PROJECT: ARTERIAL REHABILITATION – SILVER SPUR ROAD (HAWTHORNE BLVD TO DRYBANK RD) TYPE: Roadway Infrastructure LOCATION: Silver Spur Road (Hawthorne Blvd to Drybank Rd) DEPARTMENT: Public Works DESCRIPTION: Silver Spur Road will be resurfaced to mitigate roadway distress and degradation that has occurred over the years. The project will require milling and overlay, root removal, asphalt patching, curb and gutter repair, sidewalk repair, ADA ramps and re-striping. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $100,000 CONSTRUCTION $1,700,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $1,800,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: Federal STPL, Proposition C, Measure R, and CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: The project goal would result in a pavement condition of 86 or higher, which is considered “Very Good Condition” I-36 PROJECT: TRAFFIC SAFETY IMPROVEMENTS PALOS VERDES DRIVE EAST AT BRONCO DRIVE TYPE: Traffic Improvements LOCATION: PVDE at Bronco Drive DEPARTMENT: Public Works DESCRIPTION: Improve portions of PVDE to provide wider travel lanes in each direction, a shared use equestrian and pedestrian path located behind the existing guardrail, a high visibility equestrian crossing at Bronco Drive complete with flashing beacons, augmented crossing signage and advanced crossing signage with flashing beacons, installation of safety barriers and railing to reduce vehicle collisions and cross-over accidents PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $500,300 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $500,300 IMPACT ON OPERATING BUDGET Staff attained an HSIP grant that requires a 10% local match from CIP Reserve. The total project cost is $542,000, including $41,700 that was appropriated in FY13-14 for design. The total grant of $487,800 will be applied to the construction planned for FY15-16. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: LOCATION PHOTO MAP I-37 PROJECT: PVDS ROADWAY REALIGNMENT TYPE: Roadway Project LOCATION: PVDS DEPARTMENT: Public Works DESCRIPTION: The project would re-align approximately 1.6 miles of Palos Verdes Drive South which is located within and traverses the Abalone Cove, Portuguese Bend, and Klondike Canyon Landslides. The location of the roadway is constantly moving as the sub-soils within the landslide move. Extensive grading is needed to re-establish (relocate) the roadway within the right-of-way. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $3,060,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $3,060,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Project design of $245,000 was appropriated in FY13-14. I-38 PROJECT: WESTERN AVENUE TRAFFIC IMPROVEMENTS TYPE: Roadway Infrastructure LOCATION: Western Avenue DEPARTMENT: Public Works DESCRIPTION: The Western Avenue Task Force group was formed consisting of RPV, City LA, and Caltrans. Since its inception, the working group completed a Western Avenue Corridor Study in 2007, which is a strategic action plan that: • Identified the current and future deficiencies in the multi-modal transportation system within the corridor; and • Recommended consensus-based solutions (including required strategies) to address the deficiencies. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $3,200,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $3,200,000 IMPACT ON OPERATING BUDGET 50-50 sharing agreement with a $1.6 million City contribution coming from CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-39 PROJECT: HAWTHORNE BLVD RIGHT OF WAY BEAUTIFICATION TYPE: Roadway Infrastructure LOCATION: Hawthorne Blvd (City Hall to Northerly City Limits) DEPARTMENT: Public Works DESCRIPTION: Beautification improvements to the City’s right-of-way along Hawthorne Blvd would include landscaping and masking blight conditions created by failed fences, walls and other private improvements. The medians in this area will be improved by landscape and/or hardscape enhancements. This allocation would fund a design and plan for those improvements that have a preliminary cost estimate of $2.2 to $2.6 million. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $150,000 CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $150,000 IMPACT ON OPERATING BUDGET Funding Information: CIP Reserve JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-40 UTILITY UNDERGROUNDING Pursuant to a formula set out in Tariff Rule 20A by the California Public Utilities Commission (CPUC), Southern California Edison is required to set aside an annual amount of work credits for the purpose of undergrounding electrical utilities within each city. Work credits are not funds available to the City to expend; they are utility company funds budgeted to perform engineering and construction work. To qualify, cities must determine that • Undergrounding will avoid or eliminate an unusually heavy concentration of overhead electric facilities • The street or road or right-of-way is extensively used by the general public and carries a high volume of pedestrian or vehicle traffic. • The street, road or right-of-way adjoins or passes through a civic area or public recreation area or an area of unusual scenic interest to the general public. • The street or road or right-of-way is considered an arterial street or major collector as defined in the Governor's Office of Planning and Research General Plan Guidelines. Under the tariff, work credits not committed to a qualifying project in one year are carried over to the next year. Annually, the City receives approximately $80,000 in Rule 20A funds. As of May 2012, the City’s Rule 20A fund balance was $839,749. In 2009, the CPUC amended the code to allow for governments to “mortgage” their current year’s work credits up to an additional five years in order to be able to undertake a qualifying Rule 20A project sooner than otherwise possible. The following project(s) has been identified that meet the criterion for the usage of Rule 20A work credits and would benefit the City as whole. I-41 PROJECT: CRENSHAW BLVD UTILITY UNDERGROUNDING PROJECT TYPE: Public Utilities LOCATION: Crenshaw Blvd at Crest Road DEPARTMENT: Public Works DESCRIPTION: The project will underground overhead utility lines along Crenshaw Blvd south of Crest Road. This project qualifies for Rule 20A funding. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $120,000 CONSTRUCTION $1,080,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $1,200,000 IMPACT ON OPERATING BUDGET There is no impact on the operating budget. This project is entirely funded by Rule 20A work credits. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-42 STORM DRAIN SYSTEM In June 2004, the City’s consulting engineers prepared an Update to the Storm Drain Master Plan. The updated plan identified serious storm drain deficiencies that required significant repair. The update identified 38 high-priority projects, which were the basis for establishing a “user fee.” Since then, some projects have been completed, and others have been reassessed to meet changing priorities and needs. A new Master Plan of Drainage is underway and expected to be completed in FY14-15. It is expected that new projects and priorities will be identified as the City seeks to eliminate deficiencies in the storm drain system infrastructure and add the structural improvements required for both water quality and flood protection. The 38 projects identified in the 2004 Master Plan have been grouped into 12 project areas, as listed below; however, these groupings may become obsolete with the new Master Plan. Area 1: Sunnyside Ridge Area 2: McCarrell Canyon Storm Drain System Area 3: Lower San Ramon Canyon/Tarapaca Canyon Area 4: Altamira Canyon Area 5: Palos Verdes Drive East/Miraleste Canyon Area 6: San Pedro and Averill Canyons Area 7: Via Colinita Vickery Canyon Area 8: Miraleste and Chandeleur Area 9: Palos Verdes Drive East Switchbacks Area 10: Hawthorne Boulevard Area 11: Palos Verdes Drive South Area 12: Citywide Storm Drain Programs I-43 PROJECT: STORM DRAIN LINING TYPE: Storm Drain System LOCATION: Project Area 12 DEPARTMENT: Public Works DESCRIPTION: All CMP storm drain lines within the City have reached their design life expectancy and need to be lined to extend their life another 30+ years. CMP dating back to the 1940s have been discovered and require rehabilitation along with those most recently installed in the 1970s. A large number of drainage problems citywide can be overcome by relining deteriorated pipes and improving inlets and outlet structures. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $335,278 $340,836 $347,653 $350,000 $350,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $335,278 $340,836 $347,653 $350,000 $350,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: WQFP user fees through Year 3 (FY16-17) and the CIP Reserve thereafter. Ongoing maintenance costs should decrease, as pipes which have been lined generally require less maintenance resulting in a cost savings. Because the Storm Drain User Fee sunsets in FY15-16, lining projects will compete with other infrastructure rehabilitation projects for funding the CIP Reserve in the future. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: LOCATION PHOTO MAP I-44 . PROJECT: SOUTH HAWTHORNE/VIA FRASCATI TYPE: Storm Drain System LOCATION: Project Area 10 DEPARTMENT: Public Works DESCRIPTION: This project will improve drainage across Hawthorne Boulevard by replacing two existing 18” pipes with one 24” and one 30” RCP pipes. Additionally, a second location on South Hawthorne will be evaluated after episodes of flooding in recent years. A curb and gutter project on Via Frascati will serve to direct drainage into the street and existing catch basins, which drain into the San Pedro Canyon. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $440,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $440,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: WQFP user fees JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: As this project makes improvements to two different locations, the project may be split into two discreet projects once the scoping is completed. I-45 PROJECT: ALTAMIRA CANYON DRAINAGE PROJECT STUDY REPORT TYPE: Storm Drain System LOCATION: Project Area 4 DEPARTMENT: Public Works DESCRIPTION: The Project Study Report is expected to include: 1) a study of the drainage area; 2) a study of the drainage needs; 3) multiple design alternatives; 4) identification of environmental requirements; 5) identification of right-of-way needs; and 6) a recommended scope for development of an engineering design leading to construction of drainage improvements. Any improvements to drainage in Altamira Canyon will be complex due to right-of-way and landslide issues. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $500,000 CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $500,000 IMPACT ON OPERATING BUDGET Funding Information: CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Preventing runoff water from entering the landslide has been shown to directly affect land movement in landslide areas. This project is expected to help slow movement within the Abalone Cove landslide, eventually affecting the land movement at Palos Verdes Drive South. I-46 PROJECT: PAINTBRUSH CANYON DRAINAGE PROJECT STUDY REPORT TYPE: Storm Drain System LOCATION: Project Area 11 DEPARTMENT: Public Works DESCRIPTION: The Project Study Report is expected to include: 1) a study of the drainage area; 2) a study of the drainage needs; 3) multiple design alternatives; 4) identification of environmental requirements; 5) identification of right-of-way needs; and 6) a recommended scope for development of an engineering design leading to construction of drainage improvements. Any improvements to drainage in Altamira Canyon will be complex due to right-of-way and landslide issues. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $120,000 CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $120,000 IMPACT ON OPERATING BUDGET Funding Information: CIP Reserve JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Preventing runoff water from entering the landslide has been shown to directly affect land movement in landslide areas. This project is expected to help slow movement within the Portuguese Bend landslide, eventually affecting the land movement at Palos Verdes Drive South. I-47 PROJECT: PVDS ROADWAY DRAINAGE PROJECT AT SACRED COVE TYPE: Drainage Project LOCATION: PVDS DEPARTMENT: Public Works DESCRIPTION: This project would construct improvements along a section of PVDS located in the Sacred Cove area. The project would aid in the passive drainage of runoff that is now trapped due to ground movement. The location of the roadway is constantly moving as the sub-soils within the landslide move. Grading is needed to re- establish (relocate) the drainage system inlet within the right-of- way. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $450,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $450,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-48 PROJECT: STORM DRAIN POINT-REPAIR PROJECTS TYPE: Drainage Project LOCATION: Project Area 12 DEPARTMENT: Public Works DESCRIPTION: As the City lines the storm drains to extend useful life, sections of pipeline are found to be in need of repair. This project would address point-repairs at 4 to 6 locations with costs ranging from $50,000 to $250,000 for each location. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $150,000 $900,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $150,000 $900,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-49 LANDSLIDE MITIGATION PROJECTS The City’s Landslide Mitigation Projects refers to projects that lessen the effect of erosion on the Portuguese Bend Landslide, which is the only continuously active landslide in the United States. These projects are intended to address landslide movement and public safety risks by using proven methods such as runoff diversion, dewatering and geospatial monitoring. I-50 PROJECT: INSTALLATION OF LANDSLIDE DEWATERING WELLS TYPE: Landslide Project LOCATION: Portuguese Bend and Abalone Cove DEPARTMENT: Public Works DESCRIPTION: Dewatering Wells are a high priority and are considered to be the most effective method of minimizing runoff from entering the landslide, which helps slow land movement within the landslide. All runoff that percolates into the ground eventually becomes part of the groundwater and will cause an increase in the depth of the groundwater table. Removing groundwater through dewatering wells helps to lower the groundwater table, relieving soil pressures at depth and minimizing the negative effects groundwater has on the landslide. These new wells should improve the system’s effectiveness by increasing the system’s water removal capacity and by removing water more rapidly. The cost to install each well is estimated to be $90,000. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $360,000 $450,000 $450,000 $180,000 $180,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $360,000 $450,000 $450,000 $180,000 $180,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-51 STORM WATER QUALITY In order to comply with the new Municipal Separate Storm Sewer System (MS4) Permit requirements in California, the Peninsula cities are working together to address storm water quality issues by developing an Enhanced Watershed Management Plan (EWMP). The plan may require capital improvements as well as operational changes. Capital improvements will likely include treatment projects, as well as water quality monitoring stations in storm drain outfalls to be used in wet or dry weather. To meet requirements of the Regional Water Quality Board, it is anticipated that automated data collection systems will need to be designed and installed in several locations in the various watersheds of the City. I-52 PROJECT: DRAINAGE AREA MONITORING SYSTEM TYPE: Stormwater Quality Project LOCATION: City wide, at storm drain outfalls DEPARTMENT: Public Works DESCRIPTION: In response to a new MS4 permit requirement, the City will need to monitor water quality in storm drain outfalls in both dry and wet weather. To meet data standards, it is anticipated that automated data collection systems will need to be designed and installed in several locations in the various watersheds of the City. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $50,000 CONSTRUCTION $200,000 PROJECT MANAGEMENT/OVERSIGHT $50,000 LEGAL TOTAL $300,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: This project is required as part of the MS4 Permit I-53 PROJECT: STORM WATER QUALITY REGIONAL IMPROVEMENT PROJECT TYPE: Stormwater Quality Project LOCATION: TBD DEPARTMENT: Public Works DESCRIPTION: In order to comply with the new MS4 Permit requirements, the Peninsula cities will work together to address storm water quality issues by developing an Enhanced Watershed Management Plan (EWMP), including the development of structural treatment projects. This is an estimate of the City’s share of the cost to build these Storm Water Quality improvement projects. The first phase projects must be built within 30 months of when the MS4 Permit is received. Scope and timing of future phases will be determined upon approval of the EWMP by the Regional Storm Water Quality Board. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $100,000 $100,000 $100,000 $100,000 $100,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $100,000 $100,000 $100,000 $100,000 $100,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Required as part of MS4 Permit Enhanced Watershed Management Plan. Locations to be determined once pollutant monitoring studies are analyzed. The FY14-15 first phase project cost is $300,000; however, $200,000 was appropriated in FY13-14 and is expected to be carried forward to FY14-15. The City will have an ongoing commitment to additional projects in the future. In the absence of more defined information, a placeholder of $100,000 annually has been included as the City’s contribution to other storm water quality projects. I-54 SEWER PROJECTS The City’s sanitary sewer system is essential for City operations, yet it has not required significant expenditures in past years due to an inter-local agreement with Los Angeles County for maintenance activities. The City owns the system, but the County has the primary responsibility for ongoing maintenance. The County collects a sewer fee from the City’s property owners that may be inadequate to maintain the system. Although the County maintains the City’s sewer system, the City retains responsibility for its operation, public safety and welfare. The City, not the County, maintains legal and regulatory responsibility (i.e. any state or federal fines resulting from spillage). The City conducted a survey of the system, and in 2004 the Sanitary Sewer Master Plan was created to help in the management of this asset. The study examined sample areas throughout the City and assessed the overall system as “fair.” The inspection revealed root intrusion in the pipes and cracking in the pipes, in addition to accumulated fats and grease clogging certain areas. It appeared that the County had not been performing preventative maintenance in prior years. Without regular maintenance, overflows due to root and grease blockages will occur. To minimize the potential for overflow and to restore and maintain the system in “good” condition, a significant investment in pipeline inspection, repair and maintenance is required. The County is nearing completion of a full inspection and cleaning of all RPV sewer mains. The projects identified herein were included in the City’s Wastewater Master Plan Update which was completed in 2009 to address potential locations of under- capacity (the ability of the existing pipe to convey sewage flows without overflowing into the street). The County maintenance and repair program does not provide for replacement of pipeline due to capacity issues. The Abalone Cove Sewer District is a unique system serving 110 developed parcels in an active landslide area, and is maintained by the City. Sewer user fees are collected from property owners, but are not sufficient to provide for maintenance and rehabilitation of the system. The Abalone Cove Sewer District is heavily subsidized by the City. I-55 PROJECT: SEWER CAPACITY PROJECT- GINGER ROOT LANE TYPE: Sewer System LOCATION: N/A DEPARTMENT: Public Works DESCRIPTION: This section of the City’s sewer system was identified in the 2009 Sanitary Sewer Master Plan Update to be under capacity. This project will evaluate that determination using specific flow testing; and, if required, replace 952 feet of 8 inch sewer pipe. The pipe will be replaced with a 15 inch vitrified clay pipeline. The pipeline runs along Ginger Root Lane between Narcissa Drive and Cinnamon Lane. This section of pipeline is over capacity when analyzed considering the factor of safety flow run. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $29,000 CONSTRUCTION $166,000 PROJECT MANAGEMENT/OVERSIGHT $8,000 LEGAL TOTAL $203,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: As funding becomes available, projects should be performed in the order they are ranked in the Wastewater Master Plan Update. This project is ranked number 7 of the 8 identified Capital Improvement Projects in the plan. I-56 PROJECT: SEWER CAPACITY PROJECT- MALAGA CANYON TYPE: Sewer System LOCATION: N/A DEPARTMENT: Public Works DESCRIPTION: This section of the City’s sewer system was identified in the 2009 Sanitary Sewer Master Plan update to be under capacity. This project will evaluate that determination using specific flow testing; and, if required, replace 1,850 feet of 10 inch sewer pipe. The pipe will be replaced with a 15 inch vitrified clay pipeline. The pipeline runs behind properties in Malaga Canyon parallel to Basswood Avenue between Mossbank Drive and Mazur Drive. This section of pipeline is over capacity when analyzed considering the factor of safety flow run. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $59,000 CONSTRUCTION $335,000 PROJECT MANAGEMENT/OVERSIGHT $13,000 LEGAL TOTAL $407,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: As funding becomes available, projects should be performed in the order they are ranked in the Wastewater Master Plan Update. This project is ranked number 5 of the 8 identified Capital Improvement Projects in the plan. I-57 PROJECT: SEWER CAPACITY PROJECT- OTHER LOCATIONS TYPE: Sewer System LOCATION: Various DEPARTMENT: Public Works DESCRIPTION: Several smaller locations throughout the City may require repairs. The 2009 Sanitary Sewer Master Plan indicated that unidentified sections of the City’s sewer system may be under capacity. The Plan indicates that these projects could replace 1,951 feet of 8 inch sewer pipe with 12 inch vitrified clay pipelines. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $75,000 CONSTRUCTION $340,000 PROJECT MANAGEMENT/OVERSIGHT $50,000 LEGAL TOTAL $465,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: As funding becomes available, projects should be performed in the order they are ranked in the Wastewater Master Plan Update. This project is ranked number 8 of the 8 identified Capital Improvement Projects in the plan. I-58 PROJECT: ABALONE COVE SEWER DISTRICT REHABILITATION TYPE: Sewer System LOCATION: Abalone Cove Sewer District DEPARTMENT: Public Works DESCRIPTION: Construction of the Abalone Cove Sewer system was completed in 2001 to replace property owner’s septic tanks in the active landslide area of the City. Minimal maintenance has been performed since that time. Due to the active landslide, the system is now in need of more substantive rehabilitation and upgrades to comply with current engineering, operations and maintenance standards in Los Angeles County. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $500,000 $500,000 $500,000 $500,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $500,000 $500,000 $500,000 $500,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve funds. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-59 RECREATION, PARKS & OPEN SPACE The development and maintenance of community parks, recreational areas and open space has been established as a top priority for the City as stated in the General Plan and various other planning documents. The General Plan states, “It is the goal of the City of Rancho Palos Verdes to conserve, protect and enhance its natural resources, beauty and open space for the benefit and enjoyment of its residents and the residents of the entire region. Future development shall recognize the sensitivity of the natural environment and be accomplished in such a manner as to maximize the protection of it.” Many park sites and open space areas have been acquired throughout the City, and some have been developed for use by the general public. Some sites remain vacant or underutilized. The City Council approved the Vision Plan in September 2008 which outlines various trail and park projects which have been included in this plan. The Public Use Master Plan has also outlined a strategy for the development of trails. These recreational projects add to the vibrancy of the community and they are designed to contribute to all residents’ quality of life. Parks and other open spaces have been carefully planned to take advantage of the beautiful coastline and natural landscape of the peninsula. I-60 PROJECT: LOWER HESSE PARK IMPROVEMENTS (PHASE 1) TYPE: Recreation, Parks & Open Space LOCATION: Lower Hesse Park DEPARTMENT: Public works DESCRIPTION: The scope of work of the proposed ‘phase one’ of Lower Hesse Park includes construction of a natural parking lot, restrooms, tennis court, play area, picnic area and some landscaping. These basic items are chosen from the concept plan option “Pacific” which was selected by the City Council. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $50,000 CONSTRUCTION $450,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $500,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Landscape maintenance is estimated to be about $12,000 annually, with annual water irrigation cost of about $1,500. I-61 PROJECT: HESSE PARK PARKING LOT RESURFACING TYPE: Recreation, Parks and Open Space LOCATION: Hesse Park DEPARTMENT: Public works DESCRIPTION: Hesse Park parking lot is one of the frequently used City facilities. The pavement at this parking lot is deteriorating and needs resurfacing. Delaying this improvement will add to the cost of work due to extension of cracks into the depth of the existing pavement caused by motorists’ usage. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $10,000 CONSTRUCTION $200,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $210,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve. JUSTIFICATION FOR INCLUSION IN FY 14-15 BUDGET SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: The parking lot will have a 5 year useful life once the project is completed. At that time, a slurry-seal will be needed to extend the useful life. I-62 PROJECT: POINT VICENTE INTERPRETIVE CENTER (PVIC) SCREENING WALL TYPE: Buildings and Other Facility Improvements LOCATION: PVIC DEPARTMENT: Public works DESCRIPTION: In order to provide a building identification sign that will also screen the existing above ground power generator, gas tank, electrical panels/ transformers, a 100-foot long concrete serpentine shaped wall is proposed to be installed in the lawn area adjacent to the pedestrian walkway. This decorative screening wall will include building identification. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $15,000 CONSTRUCTION $95,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $110,000 IMPACT ON OPERATING BUDGET Funding and/or Grant Information: CIP Reserve. JUSTIFICATION FOR INCLUSION IN FY 13-14 BUDGET SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-63 PROJECT: SUNNYSIDE TRAIL SEGMENT PROJECT TYPE: Recreation, Parks, & Open Space LOCATION: Sunnyside Ridge Road (Intersection of Sunnyside Ridge Trail and the Sol Vista Segment Trail) DEPARTMENT: Community Development/Public Works DESCRIPTION: The Sunnyside Segment Trail is a point-to-point trail segment that begins on Sunnyside Ridge Road at the intersection of the Sunnyside Ridge Trail and the currently unused Sol Vista Segment Trail on the old Narbonne Right-of-Way, as indicated in the City’s Conceptual Trail Plan. The proposal is to provide a usable trail linkage for pedestrians and equestrians within a recorded trail segment that traverses a privately owned lot that is currently developed with a single-family residence that was formally part of an old City right-of-way. The trail connection would involve the provision of a 5-foot wide decomposed granite surface trail. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $70,000 CONSTRUCTION $395,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $465,000 IMPACT ON OPERATING BUDGET Funding Information: $300,000 Grant from Regional Park and Open Space District, $165,000 from CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-64 PROJECT: POINT VICENTE INTERPRETIVE CENTER EXHIBITS TYPE: Recreation, Parks, & Open Space LOCATION: Point Vicente Interpretive Center DEPARTMENT: Recreation & Parks/Public Works DESCRIPTION: Private restricted donations have been collected for enhancements to the PVIC museum exhibits. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $400,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $400,000 IMPACT ON OPERATING BUDGET Funding Information: Private Restricted Donations. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-65 PROJECT: POINT VICENTE INTERPRETIVE CENTER LANDSCAPING TYPE: Recreation, Parks, & Open Space LOCATION: Point Vicente Interpretive Center DEPARTMENT: Recreation & Parks/Public Works DESCRIPTION: Private restricted donations have been collected for improvements to outdoor landscaping at PVIC. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $400,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $400,000 IMPACT ON OPERATING BUDGET Funding Information: Private Restricted Donations. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-66 PROJECT: GATEWAY PARK DEVELOPMENT PROJECT TYPE: Recreation, Parks, & Open Space LOCATION: PVDS in the Portuguese Landslide Area DEPARTMENT: Public Works/Community Development DESCRIPTION: The Vision Plan includes a proposed Gateway Park, a 23-acre site within the City’s Landslide Moratorium area just north of PVDS between the Portuguese Bend residential community and Klondike Canyon. Under the Vision Plan, the site has been approved for a combination of uses such as a “gateway park” for users of the Nature Preserve’s trail system, an outdoor education/nature appreciation center for school and community groups and an equestrian center. The following components of the approved concept plan are being developed as part of the California Coastal Trail Project and PVDS Landslide East End Road Realignment Project: Trail head, signage, fencing, and public parking area. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $200,000 CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $200,000 IMPACT ON OPERATING BUDGET Funding Information: CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-67 PROJECT: ABALONE COVE BEACH ACCESS ROAD TYPE: Recreation, Parks, & Open Space LOCATION: Abalone Cove DEPARTMENT: Public Works DESCRIPTION: The Abalone Cove Beach access road from PVDS to the beachfront must be re-graded and re-paved to improve accessibility for emergency response and maintenance vehicles. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION $100,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $100,000 IMPACT ON OPERATING BUDGET Funding Information: CIP Reserve. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-68 PROJECT: GRANDVIEW PARK IMPROVEMENTS (PHASE 1) TYPE: Recreation, Parks & Open Space LOCATION: Grandview Park DEPARTMENT: Public works DESCRIPTION: The scope of work of the proposed ‘phase one’ of Grandview park includes construction of a natural parking lot, restrooms/office, play area, picnic area and some landscaping. These basic items are chosen from the concept plan option “Sycamore” which was selected by the City Council. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN $75,000 CONSTRUCTION $560,000 PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL $635,000 IMPACT ON OPERATING BUDGET Funding Information: CIP Reserve JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: I-69 UNFUNDED PROJECTS The following projects are those which have been identified as capital needs through various planning processes, but currently there are not resources to complete the projects. As funding becomes available and the City Council prioritizes and approves projects, they may be moved into the funded Five-Year CIP schedule. I-70 Potential Safety City Council Project Page Funding Goal Priority Minimum Maximum Buildings and Other Facility Improvements Citywide ADA Transition Plan Implementation 70 X X $ 4,670,000 4,670,000$ Point Vicente Park Community Center 71 X 3,000,000 8,000,000 Corporation Storage Yard Relocation 72 300,000 1,000,000 Intangible Capital Outlay Infrastructure Management Plan 74 X X 125,000 175,000 Roadway Infrastructure Hawthorne Blvd. Median Improvements (Via Rivera to City Hall)76 250,000 250,000 Lower Point Vicente Park Access Modification Project (PVDW at PVIC)77 X X X 250,000 300,000 Operational Improvements at Crenshaw & Crest 78 X X X 470,000 520,000 Crenshaw Blvd Extension Parking Improvements 79 X 125,000 150,000 Hawthorne Blvd. Right of Way Beautification 80 X 2,200,000 2,600,000 Hawthorne Blvd. Bike Lane Gap Closure 81 X X 1,200,000 1,500,000 Traffic Safety Improvements - PVDE at Miraleste Drive 82 X X X 200,000 300,000 Utility Undergrounding Utility Undergrounding at 25th Street 84 X X 1,000,000 1,100,000 Utility Undergrounding at Entrance to PVIC 85 X X 150,000 200,000 Utility Undergrounding at PVDS and Terranea Way 86 X X 150,000 200,000 Storm Drain System Altamira Canyon 88 X X 1,600,000 5,350,000 Paintbrush Canyon Drainage 89 X X 2,568,000 2,568,000 PVDE - Miraleste Canyon 90 X X 2,500,000 3,200,000 San Pedro & Averill Canyons 91 X X 2,700,000 3,300,000 Landslide Mitigation Projects Landslide Early Warning System 93 300,000 300,000 Recreation, Parks & Open Space Restroom at Del Cerro Park 95 250,000 300,000 Preserve Trail Plan - New Trail Implementation 96 X X 150,000 150,000 Lower Point Vicente Park Improvement Project 97 X 2,400,000 2,400,000 Civic Center Skate Plaza 98 X 650,000 750,000 California Coastal Trail Improvements 99 X 223,000 223,000 Coast Vision Plan - Trailhead/Overlook/Vista Point Development 100 X 800,000 1,040,000 Totals (Min. and Max.) $28,231,000 40,546,000$ Cost Range RPV Capital Improvement Plan - Unfunded Projects I-71 BUILDINGS AND OTHER FACILITY IMPROVEMENTS UNFUNDED PROJECTS I-72 PROJECT: CITYWIDE ADA TRANSITION PLAN IMPLEMENTATION TYPE: Buildings and Other Facility Improvements LOCATION: Various DEPARTMENT: Public W orks DESCRIPTION: The Citywide ADA Transition Plan, adopted by the City Council on June 4, 2013, identified total costs of $11.85 million for implementation. The cost estimate included improvements to ADA compliance at the Civic Center (buildings and grounds) totaling $1.36 million, and those at Ladera Linda Park totaling $1.72 million. Any future improvements at those sites are expected to bring the facilities into ADA compliance. Additionally, the total cost of $11.85 million includes right-of-way improvements totaling $2.64 million, including curb ramps and bus stops. Those improvements will be addressed as part of each roadway rehabilitation project. The remaining identified costs of $6.12 million will be addressed through an annual implementation allocation that began in FY13-14. Project costs “funded” through FY18-19 total $1.45 million. The remaining portion of the $6.12 million, which has not been moved to the “funded” list is included here. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $4.67 million EET funding may become available. I-73 PROJECT: POINT VICENTE PARK COMMUNITY CENTER TYPE: Buildings and Other Facility Improvements LOCATION: Point Vicente/Civic Center DEPARTMENT: City Manager/Public Works DESCRIPTION: Originally studied by the Open Space Planning, Recreation and Parks Task Force in 2004, the concept for this facility was later refined during the redevelopment of the Coast Vision Plan. Adopted by the City Council in 2008, the latest concept calls for a 20,000 square-foot community center that could accommodate meeting space for community groups, recreational facilities, classroom space and a full-sized recreational pool. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET Impact will need to be assessed, as projects are considered. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $3,000,000 - $8,000,000 A private donation of $120,000 has been made, and additional donations and/or other outside funding may become available based upon the scope of the project. I-74 PROJECT: CORPORATION STORAGE YARD RELOCATION TYPE: Buildings and Other Facility Improvements LOCATION: Various Locations throughout the City DEPARTMENT: City Manager/Public Works DESCRIPTION: It has been proposed that City maintenance services be spread citywide in strategic locations with a central office in City Hall. The existing corporations/storage yard is located on the Point Vicente Park site which had been identified for various other community uses due to its prime location. It may be feasible to create a central location for the storage yard with satellite locations throughout the City, serving the storage and other construction needs of the Public Works Department. The central location of the storage yard will be situated at or near City Hall for administrative purposes. This central location will control all satellite locations through the use of maintenance personnel and through the efficient use of the City’s network. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET To be assessed. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY X SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY OTHER PROJECT INFORMATION: The satellite locations will fulfill the following roles: there will be an office trailer at each location; a construction yard for contractors located throughout the City (possibly generating rental income for the City); possible satellite EOC centers for access throughout the City; and storage space for various equipment. Estimated Cost: $300,000 - $1,000,000 I-75 INTANGIBLE CAPITAL OUTLAY UNFUNDED PROJECTS I-76 PROJECT: INFRASTRUCTURE MANAGEMENT PLAN TYPE: Intangible Capital Outlay LOCATION: N/A DEPARTMENT: Public Works & Finance DESCRIPTION: The RPV Infrastructure Management Plan (IMP) will be the tool to chart an operations and financial course for the actions and funding required to maintain and preserve community public property, which will improve the condition of each infrastructure category. The IMP will provide a comprehensive basis to create a reality-based capital improvement program by allowing the City Council and the community to determine the impact of different funding strategies/scenarios and prioritize project delivery over the course of multiple planning decades. The IMP will also estimate technical and funding requirements and make recommendations of policies to assist the City Council with program implementation, goal-setting, and prioritization. The IMP will include: • Integration with the City’s geographic information system (GIS) and the future use of an asset/maintenance management system • A civic engagement process to invite, assess, evaluate, and include citizen-initiated capital improvement projects (CIP) • Identification of best management practices and key performance indicators for each infrastructure category to help guide policy formulation and decision-making • A web-based tool for “what-if” scenarios based on priorities and economic and community factors PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET Approximately $5,000 annually to maintain the web-based planning tool. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY X SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $125,000 to $175,000 I-77 ROADWAY INFRASTRUCTURE UNFUNDED PROJECTS I-78 PROJECT: HAWTHORNE BLVD. MEDIAN IMPROVEMENTS (VIA RIVERA TO CITY HALL) TYPE: Roadway Infrastructure LOCATION: Hawthorne Blvd. (Via Rivera to City Hall) DEPARTMENT: Public Works DESCRIPTION: The development of this median would include installing draught tolerant landscaping which will require minimal maintenance. Development will also include the installation of irrigation systems and controllers, hardscape, and decorative stone. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET To be assessed. However, a rough estimate of annual maintenance is about 10% of total project cost. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $250,000 I-79 PROJECT: LOWER POINT VICENTE PARK ACCESS MODIFICATION PROJECT TYPE: Traffic Improvements LOCATION: PVDW/PVDS at Lower Point Vicente Park entrance DEPARTMENT: Public Works DESCRIPTION: Improve access into and out of the Lower Point Vicente park area by restricting turn movements to right turn only out of the site at the southern entrance/exit to minimize vehicle conflicts while negotiating turn movements. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET To be assessed. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY OTHER PROJECT INFORMATION: Estimated Cost: $250,000 - $300,000 Highway Safety grant money may become available. I-80 PROJECT: OPERATIONAL IMPROVEMENTS- CRENSHAW BLVD. AND CREST DRIVE TYPE: Roadway Infrastructure LOCATION: Crenshaw Blvd. and Crest Drive DEPARTMENT: Public Works DESCRIPTION: Currently this intersection is a four-way stop controlled intersection. During the AM and PM peak hours, the westbound left-turn lanes back up for several hundreds of feet creating extensive delay and long vehicle queues. An operational improvement to the intersection is required to improve traffic flow. A study has been conducted to determine the best solution, and a roundabout is being considered. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $470,000 - $520,000 Highway Safety grant money may become available. I-81 PROJECT: CRENSHAW BOULEVARD EXTENSION PARKING IMPROVEMENTS TYPE: Roadway Infrastructure LOCATION: Crenshaw Blvd (Valley View Rd to Burma Rd) DEPARTMENT: Public Works DESCRIPTION: In an effort to improve safety, parking and access to the Nature Preserve entrance near Del Cerro Park, parking improvements and restrictions are needed to accommodate the growing user demand and need for emergency vehicle access. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET There is no impact on the operating budget. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $125,000 - $150,000 I-82 PROJECT: HAWTHORNE BLVD RIGHT OF WAY BEAUTIFICATION TYPE: Roadway Infrastructure LOCATION: Hawthorne Blvd (City Hall to Northerly City Limits) DEPARTMENT: Public Works DESCRIPTION: The City’s Right of Way along Hawthorne Blvd will be beautified by landscaping and masking blight conditions created by failed fences, walls and other private improvements. The medians in this area will be improved by landscape and/or hardscape enhancements. A study has been funded for FY14-15 to identify options and cost estimates. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET There is no impact on the operating budget. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $2,200,00 - $2,600,000 I-83 PROJECT: HAWTHORNE BLVD BIKE LANE GAP CLOSURE TYPE: Roadway Infrastructure LOCATION: Hawthorne Blvd (Vallon Drive to Dupre Road) DEPARTMENT: Public Works DESCRIPTION: This project will improve roadway safety and complete a bike lane gap closure that exists due to on-street parking demand, roadway configuration and existing median barriers. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET There is no impact on the operating budget. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $1,200,000-$1,500,000 Highway Safety grant money may become available. I-84 PROJECT: TRAFFIC SAFETY IMPROVEMENTS – PALOS VERDES DRIVE EAST AT MIRALESTE DRIVE TYPE: Traffic Improvements LOCATION: PVDE at Miraleste Drive DEPARTMENT: Public Works DESCRIPTION: Improve intersection operations to create improved traffic flow, vehicle and pedestrian safety. Operational improvements could include a roundabout. If a traffic signal were considered, the cost estimate would increase; and Marymount College would likely fund a small share of project cost. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET If a traffic signal is contemplated, annual maintenance cost could be about $7,000. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY OTHER PROJECT INFORMATION: Estimated Cost: $200,000 - $300,000 Highway Safety grant money could become available. I-85 UTILITY UNDERGROUNDING UNFUNDED PROJECTS I-86 PROJECT: UTILITY UNDERGROUNDING AT 25TH STREET TYPE: Public Utilities LOCATION: 25th Street DEPARTMENT: Public Works DESCRIPTION: This project includes the removal of overhead wires and coordination of undergrounding all utilities at this location. The City will coordinate with the associated utility companies (electrical, communications, etc.) to locate all wires underground. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET This project could be funded through Southern California Edison’s Rule 20A Funding, which accumulates at a rate of about $80,000 per year. The balance of this funding has been preliminarily committed to a project on Crenshaw Blvd in FY18-19. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $1,000,000 - $1,100,000 I-87 PROJECT: UTILITY UNDERGROUNDING AT ENTRANCE TO PVIC TYPE: Public Utilities LOCATION: Palos Verdes Drive South (at PVIC) DEPARTMENT: Public Works DESCRIPTION: This project includes the removal of overhead wires and coordination of undergrounding all utilities at this location. The City will coordinate with the associated utility companies (electrical, communications, etc.) to locate all wires underground. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET This project could be funded through Southern California Edison’s Rule 20A Funding, which accumulates at a rate of about $80,000 per year. The balance of this funding has been preliminarily committed to a project on Crenshaw Blvd in FY18-19. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $150,000 - $200,000 I-88 PROJECT: UTILITY UNDERGROUNDING AT PVDS AND TERRANEA WAY TYPE: Public Utilities LOCATION: PVDS and Terranea Way DEPARTMENT: Public Works DESCRIPTION: This project includes the removal of overhead wires and coordination of undergrounding all utilities at this location. The City will coordinate with the associated utility companies (electrical, communications, etc.) to locate all wires underground. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET This project could be funded through Southern California Edison’s Rule 20A Funding, which accumulates at a rate of about $80,000 per year. The balance of this funding has been preliminarily committed to a project on Crenshaw Blvd in FY18-19. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $150,000 - $200,000 I-89 STORM DRAIN SYSTEM UNFUNDED PROJECTS I-90 PROJECT: ALTAMIRA CANYON TYPE: Storm Drain System LOCATION: Project Area 4 DEPARTMENT: Public Works DESCRIPTION: A project within lower Altamira Canyon to aid in slowing the damage being caused by storm water runoff through the entire reach of the Canyon is needed. The installation of Gabion type erosion control structures within lower Altamira Canyon are needed to help control runoff velocities and minimize erosion within the canyon. This project includes the installation of protective measures to minimize further erosion in the Altamira Canyon. This project could range from stabilization at bends in stream beds, with limited velocity controls, to channeled stabilization. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET To be assessed. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Note: The Altamira Canyon project has been studied and analyzed over the past decades; however the need to minimize runoff from entering the ground in Altamira Canyon still remains. A project study report has been funded for FY14-15. This estimate does not include right of way costs. A previously designed and funded project was abandoned due to right of way issues and owners lack of support. Estimated Cost: $1,600,000 - $5,350,000 I-91 PROJECT: PAINTBRUSH CANYON DRAINAGE TYPE: Storm Drain System LOCATION: Portuguese Bend DEPARTMENT: Public Works DESCRIPTION: The Paintbrush Canyon Drainage System project will capture runoff at the head of the Portuguese Bend landslide in three locations, transfer that runoff via surface mounted High Density Polyethylene (HDPE) pipe under Palos Verdes Drive South, (through an existing steel tunnel) and continue along the existing storm drain pipe alignment to the ocean. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Preventing runoff water from entering the landslide has been shown to directly affect land movement in landslide areas. This project is expected to help slow movement within the Portuguese Bend landslide, eventually affecting the land movement at Palos Verdes Drive South. A project study report has been proposed for FY16-17. Estimated Cost: $2,568,000 I-92 PROJECT: PVDE- MIRALESTE CANYON TYPE: Storm Drain System LOCATION: Project Area 5 DEPARTMENT: Public Works DESCRIPTION: Work within this project area includes storm drainage systems along Palos Verdes Drive East at the Northern end of PVDE, South Coach, Rocking Horse, Clevis, North Colt, South Colt, Via Canada, and at South Via Canada. This project includes the installation of a number of pipelines and re-setting surface drainage systems to drain into Miraleste Canyon. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $2,500,000 - $3,200,000 I-93 PROJECT: SAN PEDRO & AVERILL CANYONS TYPE: Storm Drain Systems LOCATION: Project Area 6 DEPARTMENT: Public Works DESCRIPTION: Work within this project area would include storm drainage systems at Miraleste, South Miraleste, North Corsini, Via Colinita, La Vista, Vista Mesa, and a curb and gutter project on Via Frascati. This project would include the installation of a number of pipelines and regarding of roads and surface drainage systems to drain into the San Pedro and Averill Canyons. A project at Miraleste Plaza is currently under design. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $2,700,000 - $3,300,000 I-94 LANDSLIDE MITIGATION UNFUNDED PROJECTS I-95 PROJECT: LANDSLIDE EARLY WARNING SYSTEM (LEWS) TYPE: Landslide Project LOCATION: Palos Verdes Drive South in the Portuguese Bend Landslide Area DEPARTMENT: Public Works DESCRIPTION: The main sewer trunk line owned and operated by the Sanitation Districts of Los Angeles County, and which serves a significant portion of the residential properties in RPV, parallels the PVDS roadway aboveground in the landslide area. Both facilities require constant maintenance due to landslide movement, which poses a significant operational hazard should the landslide experience rapid land movement. Closure of these facilities would be highly disruptive to the city’s economic vitality, transportation, public health and safety and use of public open space and trails. Sewer overflows from the trunk line could potentially threaten the ecosystems of the nearby Pacific Ocean coastline. A landslide early warning system (LEWS) would provide critical advanced knowledge of changed landslide conditions by alerting public safety and public works first responders, who would be able to respond sooner and more proactively with public safety information and preventative measures. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET It is estimated that LEWS annual operations and maintenance cost may be approximately $30,000 per year, which would include scheduled on-site equipment inspection and fees for wireless or satellite communication JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY X ECONOMY AND EFFICIENCY X SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Sensors placed in the area would transmit data through a wireless or satellite-based system to a web-hosted application designed to send alerts to public safety and public works first responders when specified land movement criteria is reached. Many of the existing dewatering wells may be suitable for sensor deployment. The first responders would then be afforded more time to notify users of the public open space and trails in the area, mobilize equipm ent, establish roadway detours and alternative sewer conveyance, all of which is intended to protect the public and the environment. There are partnership possibilities with the Sanitation Districts of LA County and the LA County Sheriff’s and Fire Departm ents. I-96 RECREATION, PARKS AND OPEN SPACE UNFUNDED PROJECTS I-97 PROJECT: RESTROOM AT DEL CERRO PARK TYPE: Recreation, Parks, & Open Space LOCATION: Del Cerro Park DEPARTMENT: Recreation and Parks/Community Development DESCRIPTION: This project would include the construction of a restroom at Del Cerro park to serve the park visitors and the users of the trails in the Portuguese Bend Open Space. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET To be assessed. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $250,000 - $300,000 I-98 PROJECT: PRESERVE TRAILS PLAN - NEW TRAIL IMPLEMENTATION TYPE: Recreation, Parks, & Open Space LOCATION: Palos Verdes Nature Preserve DEPARTMENT: Community Development/Public Works DESCRIPTION: In October 2012, the City Council adopted an updated Preserve Trails Plan (PTP) for the NCCP’s Palos Verdes Nature Preserve which identifies trail routes and trail uses within the Preserve. Pursuant to the approved management agreement between the City and PVPLC, the PVPLC is responsible for maintenance and repair of existing unimproved trails in the Preserve while the City is responsible for the construction of new trails identified in the PTP. According to the PTP, there are 3 approved trail routes that currently do not exist and need to be constructed at some point by the City. Since projects are moving forward on two of the three new trails needed (the Smugglers Trail in the Abalone Cove Reserve and the Switchback Trail in the San Ramon Reserve, construction of the Crystal Trail (.12 mile) in the Forrestal Reserve remains as the only new trail that needs construction. In addition, the Rim Trail will need to be relocated since the current route passes over private property in Rolling Hills. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET To be assessed. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $150,000 If a trail improvement is considered to be a critical link, outside grant funding may become available. If the trail improvement is in the right-of-way, then potential funding may become available through the Active Transportation Program. I-99 PROJECT: LOWER POINT VICENTE PARK IMPROVEMENT PROJECT TYPE: Recreation Parks & Trails Improvements LOCATION: Lower Point Vicente DEPARTMENT: Public Works DESCRIPTION: The park improvement plan for Lower Point Vicente derives from an extensive public outreach process associated with the City Council adopted Vision Plan. The scope of work consists of constructing new decomposed granite trails, overlooks, reconfigured and new parking spaces (including new upper terrace parking lot), drainage facilities (including a bioswale), landscaping, fencing, way finding signs and minor site grading to accommodate the improvements (excavation cannot occur in areas capped for the lead remediation.) PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $2,400,000 I-100 PROJECT: CIVIC CENTER SKATE PLAZA TYPE: Recreation Parks & Trails Improvements LOCATION: Point Vicente Park DEPARTMENT: Public Works & Recreation DESCRIPTION: This project could include construction of: 1) a 15,000 square foot skate plaza; 2) a restroom; 3) appropriate parking and benches; and 4) landscaping. If a skate plaza is determined to be a feasible use through the Program of Utilization that controls the site, Staff will continue to work with the City Council and local skate advocate groups. The plaza/skate area would be constructed of concrete with complimenting walkways, stage, handrails, planters, landscaping, restroom building and parking. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET Annual facility maintenance is currently estimated to be $13,000. Additional Staffing and security may be necessary to operate the facility. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE X SUPPORTS CITY COUNCIL GOALS COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $650,000-$750,000. Private funding may become available for project construction and ongoing maintenance. I-101 PROJECT: CALIFORNIA COASTAL TRAIL IMPROVEMENTS TYPE: Recreation Parks & Trails Improvements LOCATION: PVDW – Marguerite Drive to Calle Entradero & PVIC Blufftop DEPARTMENT: Public Works & Recreation DESCRIPTION: Two sections of the California Coastal Trail near Point Vicente Interpretive Center (PVIC) and Oceanfront Estates are paved with asphalt that has deteriorated. This project would replace the asphalt with decomposed granite, enhancing the aesthetic value of the California Coastal Trail within the City. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET To be assessed. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES X OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $223,000 I-102 PROJECT: COAST VISION PLAN TRAILHEAD/OVERLOOK/VISTA POINT DEVELOPMENT TYPE: Recreation, Parks, & Open Space LOCATION: Various Locations DEPARTMENT: Public Works/Community Development DESCRIPTION: The Vision Plan identifies the construction of trailheads at key entrances to the existing City trail system along with overlooks and vista points within the Vision Plan project area. The trailheads would consist of a permeable surface pad, a bench, a plastic bag kiosk for dog owners, trash and recycling receptacles, signage, a freestanding kiosk for trail notices, small native trees for shade and pockets of native shrubs, where appropriate. The overlooks/vista points would be placed on decomposed granite or other permeable material with flush stone edging and could include a semicircle bench, a stone pilaster displaying pertinent information, a stone clad wall less than 3 feet in height and pockets of native shrubs. . Phase 1 would involve a trail head at Shoreline Park/25th and overlooks/vista points at Inspiration Point and Eagles Nest. Phase 2 would involve trail heads and overlooks/vistas at the cul-de-sac next to St. Paul’s Church, Del Cerro Park, and the end of Ocean Terrace. Phase 3 would involve a trail head at the Switchbacks/PVDE Turnout and overlooks/vista points at the Switchbacks/PVDE Turnout, Paintbrush Canyon/Burma Road, and Burma Road above Gateway Park. PROJECT COST ESTIMATES (IF KNOWN) CATEGORY YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5 ACQUISITION ENGINEERING/DESIGN CONSTRUCTION PROJECT MANAGEMENT/OVERSIGHT LEGAL TOTAL IMPACT ON OPERATING BUDGET To be assessed. JUSTIFICATION FOR INCLUSION ON 5 YEAR CIP SAFETY ECONOMY AND EFFICIENCY SUPPORTS ESSENTIAL CITY SERVICES OUTSIDE FUNDING COMMITTED/ELIGIBLE SUPPORTS CITY COUNCIL GOALS X COMMUNITY QUALITY/SUSTAINABILITY X OTHER PROJECT INFORMATION: Estimated Cost: $100,000 to $130,000 per site X 8 sites = Range of $800,000 to $1,040,000 I-103