RPVCCA_CC_SR_2013_04_02_01_Crestridge_Senior_Condominium_Housing_ProjectCITY OF
MEMORANDUM
4o RANCHO PALOS VERDES
TO:
FROM:
DATE:
SUBJECT:
REVIEWED:
HONORABLE MAYOR &CITY COUNCIL MEMBERS
JOEL ROJAS,COMMU~LOPMENT DIRECTOR
APRIL 2,2013
CRESTRIDGE SENIOR CONDOMINIUM HOUSING
PROJECT (ZON2012-00067 &SUB2012-00001)I 5601
Crestridge Road
CAROLYN LEHR,CITY MANAGE~.f(b\"c'-
Project Manager:Eduardo Schonborn,AICP,Senior Planner
RECOMMENDATION
At the request of the applicant,continue the public hearing to the May 21,2013 City
Council meeting.
DISCUSSION
This item was originally scheduled for consideration at the March 5,2013 City Council
meeting.However,at the request of the applicant,the City Council continued the item to
April 2,2013.The applicant continues to work on several internal matters with the project,
and has requested that the City Council continue the public hearing to the earliest meeting
in May.Due to the items already scheduled on the May i h meeting,Staff recommends
that the City Council continue the public hearing to the May 21 ,2013 City Council meeting.
ATTACHMENTS
•Request for continuance
1-1
Eduardo Schon born
From:
Sent:
To:
Cc:
Subject:
Eduardo,
James O'Malley <jomalley@trumarkco.com>
Wednesday,March 20,20137:25 PM
Eduardo Schonborn
Jason Kliewer;jkrout@rgpcorp.com
Crestridge
Great speaking with you as always,and thank you for your "patience".Very much appreciated.As we discussed we wish
to be heard at the earliest hearing this May 2013 by the City Council of RPV.
In the mean time please process and proceed on any needed steps to extend the CEQA statutes timing etc needed to
conform to this extension of time requested by Trumark (the applicant).
Take care,
James
1
1-2