Loading...
CC SR 20150721 01 - St. John Fisher Master Plan CUP RevisionCITY OF RANCHO PALOS VERDES PUBLIC HEARING Date: July 21, 2015 Subject: Revision "E" to the St. John Fisher Master Plan to Extend the Planning Entitlements for Phase Two of the Master Plan for an Additional 8 Years (Case Nos. ZON2007-00492) Subject Property: 5448 Crest Road — Corner of Crest Rd. and Crenshaw Blvd. 1. Report of Notice Given: City Clerk Morreale 2. Declare the Hearing Open: Mayor Knight 3. Staff Report & Recommendation: Senior Planner Leza Mikhail 4. Public Testimony: Appellants: N/A Applicants: St. John Fisher 5. Council Questions: 6. Rebuttal: 7. Declare Hearing Closed: Mayor Knight 8. Council Deliberation: 9. Council Action: Public Hearing Cover Page CITY OF k RANCHO PALOS VERDES MEMORANDUM TO: HONORABLE MAYOR AND CITY COUNCIL MEMBERS FROM: JOEL ROJAS, COMMUNID V LOPMENT DIRECTOR DATE: JULY 21, 2015 SUBJECT: REVISION "E" TO THE ST. JOHN FISHER MASTER PLAN TO EXTEND THE PLANNING ENTITLEMENTS FOR PHASE TWO OF THE MASTER PLAN FOR AN ADDITIONAL 8 YEARS (Location: 5448 Crest Road — Corner of Crest Rd. and Crenshaw Blvd. - Case No. ZON2007-00492) REVIEWED: DOUG WILLMORE, CITY MA R W" Project Manager: Leza Mikhail, Senior Plann '( RECOMMENDATION Adopt Resolution No. 2015-_, thereby approving Addendum No. 1 to the Mitigated Negative Declaration (MND) and Mitigation Monitoring Program (MMP), and conditionally approving CUP 96 — Revision "E" to amend the St. John Fisher Master Plan Condition No. 45(b), to allow the planning entitlements for Phase Two to be extended an additional eight (8) years, to August 24, 2022 (Case No. ZON2007-00492). Quasi -Judicial Decision This item is a quasi-judicial decision in which the City Council is being asked to affirm whether specific findings of fact can be made in order to support approval of a development application. The specific findings of fact are listed and discussed in the "Discussion" portion of the Staff Report. BACKGROUND On October 14, 2008, the Planning Commission adopted a Mitigated Negative Declaration (MND) and a Mitigation Monitoring Program (MMP), and conditionally approved the St. John Fisher Master Plan. On October 29, 2008, the Planning Commission's decision was appealed to the City Council by some adjacent neighbors raising issues related to Neighborhood Compatibility, impacts due to the size of the sanctuary, inadequate parking, noise impacts due to the use of a gymnasium, ringing of the proposed electronic bells, the Revision "E" to the St. John Fisher Maser Plan — Phase Two Extension lighting of the sanctuary tower and steeple, concerns with removal of certain mature trees and the desire for additional setbacks around the sanctuary. On February 17, 2009, after conducting five (5) public hearings, including a special on-site public hearing, the City Council adopted Resolution No. 2009-09 (attached), adopting the MND/MMP, and adopting Resolution No. 2009-10, thereby conditionally approving Conditional Use Permit No. 96 — Revision "D", Grading Permit, Minor Exception Permit and Sign Permit to establish a Master Plan for the St. John Fisher Church and School property. Aside from the operational conditions of the Master Plan, the approval included planning entitlements for the construction of 32,426 square feet of new building area, the demolition of 10,329 square feet of existing building area, a total of 30,688 cubic yards of associated grading and a new monument sign for the property. At the time of approval, the construction -related Master Plan improvements were divided into two separate phases as outlined in Condition No. 45(a) and (b), Phase One and Phase Two respectively. While the Applicant completed all portions of the project outlined in Phase One on May 14, 2014, the Applicant was unable to submit their plans into Building and Safety Plan Check for the portions of Phase Two prior to the expiration of their construction -related planning entitlements, which expired on August 24, 2014. On July 23, 2014, prior to the August 24, 2014 expiration of the construction -related Planning Entitlements for Phase Two, the Applicant submitted a request (attached) to modify the St. John Fisher Master Plan, in order for the planning entitlements for Phase Two be extended to eight (8) years to allow additional time to obtain funding for the construction of Phase Two. On July 29, 2014, the application requesting an extension of their Phase Two planning entitlements was deemed incomplete for processing, pending the review and approval of an updated Traffic Analysis by the City's Public Works Department. On April 27, 2015, the City's Public Works Staff (Melissa Countryman) presented the Applicant's updated Traffic Analysis to the City's Traffic Safety Committee, along with Public Works Staff's positon that the Traffic Analysis be approved. At that meeting, the City's Traffic Safety Committee affirmed Public Works Staff's recommendation to approve the updated Traffic Analysis. Subsequently, on June 1, 2015, Planning Staff received confirmation from the City's Public Works Staff that the review of the updated Traffic Analysis was completed and satisfactory. On June 29, 2015, the application was deemed complete for processing, and at the same time, a public notice was sent to all property owners within a 500 -foot radius of the subject property and was published in the Peninsula News. At this time, Staff has not received any public comments as a result of the public notice. 64 111 111 =1 ki The St. John Fisher property is located at 5448 Crest Road, on the southeast corner of the intersection at Crest Road and Crenshaw Boulevard. The property is 399,804 square feet (9.2 acres) in area and zoned Institutional. The property is currently developed with a new E Revision "E" to the St. John Fisher Maser Plan — Phase Two Extension sanctuary, an elementary school (K-8), administrative/parish offices, a recreational hall (Barrett Hall), rectory (priest's residence), and parish activity center/gymnasium (converted from the previous sanctuary). The campus is sited 15 — 20 feet above the adjacent streets (Crest Road and Crenshaw Boulevard). The main parking lot is located along the south property line and provides 331 parking spaces for everyday use. Additional seasonal/peak parking is located within the classroom courtyard and provides an additional 23 parking spaces for larger events when school is not in session. PROJECT DESCRIPTION The applicant requests that the City Council extend the planning entitlements of Phase Two of the St. John Fisher Master Plan for an additional eight (8) years, with a proposed expiration date of August 24, 2022. Phase Two includes the construction of a new administration building, remodel of the existing administration building into meeting rooms, construction of a new preschool, library, art room, and remaining site work associated with Phase Two construction. DISCUSSION In considering the Applicant's request to extend the construction -related activity of Phase Two by eight (8) years, to August 24, 2022, the City Council must be able to continue to make all of the required findings of a Conditional Use Permit (CUP). The specific CUP findings required to be made by the City Council are listed below, followed by Staff's assessment of the applicant's request. 1. The site is adequate in size and shape to accommodate said use and for all of the yards, setbacks, walls or fences, landscaping and other features required by this title [Title 17 "Zoning] or by conditions imposed under this section [Section 17.60.050] to adjust said use to those on abutting land and within the neighborhood. 2. The site for the proposed use relates to streets and highways sufficient to carry the type and quality of traffic generated by the subject use. 3. In approving the subject use at the specific location, there will be no significant adverse effect on adjacent property or the permitted use thereof. 4. The proposed use is not contrary to the General Plan. 5. If the site of the proposed use is within any of the overlay control districts established by Chapter 17.40 (Overlay Control Districts) of this title [Title 17 "Zoning"], the proposed use complies with all applicable requirements of that chapter. 3 Revision "E" to the St. John Fisher Maser Plan - Phase Two Extension 6. Conditions regarding any of the requirements listed in this paragraph, which the Planning Commission finds to be necessary to protect the health, safety and general welfare, have been imposed [including but not limited to]: setbacks and buffers; fences or walls; lighting; vehicular ingress and egress; noise, vibration, odors and similar emissions; landscaping; maintenance of structures, grounds or signs; service roads or alleys; and such other conditions as will make possible development of the City in an orderly and efficient manner and in conformity with the intent and purposes set for in this title [Title 17 "Zoning"]. Staff's Assessment of the Applicant's Time Extension Request With respect to the CUP Findings listed above, Staff is of the opinion that the Applicant's request to extend the planning entitlements by eight (8) years continues to be consistent with the required Finding Nos. 1, 3, 4, 5 and 6. As the Applicant is not proposing to alter any of the proposed construction or development plans of Phase Two, which was previously approved by the City Council on February 1, 2009, the previous analysis of the project in the City's record remains the same. A review of the entire project analysis of Finding Nos. 1, 3, 4, 5 and 6, which were considered as part of the February 1, 2009 City Council approval, can be found on the City's website, or in the attached Resolution 2009- 10. With respect to Finding No. 2, given that the Applicant's original Traffic Study was prepared over seven years ago, and one element of the Phase Two project includes the addition of a new preschool and new trips to and from the project site, which might not be initiated until 2022, the City requested that the Applicant provide an updated Traffic Study (attached) to ensure that there would be no new significant impacts resulting from buildout of Phase Two, given today's traffic conditions. The methodology of the updated Traffic Study was kept consistent to that used in the original Traffic Study so that the findings of the updated Traffic Study could reasonably be compared to the original Traffic Study. More specifically, the updated Traffic Study compared the existing traffic conditions (now that Phase One is completed) to those estimated traffic impacts related to the planned Phase Two improvements, most notably the new preschool. The analysis included collecting updated traffic count data during peak travel times on a weekday and a Sunday at the same intersection and roadway segments as the original study, and forecasting ambient growth of traffic for the year 2022. According to the updated Traffic Study, the study intersection (Crest Road and Crenshaw Boulevard) and nearby roadway segments (Crenshaw Boulevard, north of Crest Road and Crest Road, and west of Crenshaw Boulevard) are operating at acceptable levels of service during peak hours for both weekday and Sunday conditions. Additionally, the traffic study states that under "existing with 2022 ambient growth and project" conditions, the proposed improvements for Phase Two are not expected to significantly impact the study locations beyond the threshold limits required by the City for review. The City's Public Works Staff M Revision "E" to the St. John Fisher Maser Plan — Phase Two Extension has noted that the increase in trip generation is negligible and would not require traffic mitigation. Given the conclusions of the updated Traffic Study, which found that no new significant traffic -related impacts would result from the completion of Phase Two, and the extension of Phase Two of the St. John Fisher Master Plan to August 24, 2022, Staff recommends that the City Council amend Condition No. 45(b) as follows (new language is indicated in bold/underline and old language is indicated in ): 47. The proposed St. John Fisher Master Plan may be broken up into two main phases as described below. If within one year of the final effective date of the Notice of Decision, the applicant has not submitted an application for a building permit for the approved project or has not commenced the approved project as described in Phase One below, approval of the project shall expire and be of no further effect unless, prior to expiration, a written request for extension is filed with the Department of Planning, Building and Code Enforcement and approved by the Director. All elements of the approved Master Plan that are not submitted as described in Phase One and Phase Two below, shall require additional future review and approval through the CUP process and additional CEQA review. Phase One and Phase Two are described as follows: a. Phase One: Phase One includes the construction of the new sanctuary, remodel of the existing sanctuary into a gymnasium/parish activity center, construction of a new parking lot, demolition of the existing rectory and youth building on the north and east sides of the property, remodel/conversion of existing convent into rectory and site work that will not be impacted by future phase construction. The Planning Entitlements for all construction described under "Phase One" shall remain in full force and effect for a maximum of one (1) year from the final effective date of the Notice of Decision for the St. John Fisher Master Plan unless construction plans have been submitted to Building and Safety for plan check. b. Phase Two: Phase Two includes the construction of the new administration building, remodel the existing administration building into meeting rooms, construction of a new preschool, library, and art room and remaining site work associated with phase two construction. The Planning Entitlements for all construction described under "Phase Two" shall remain in full force and effect for a Fnaximunl-4af five (5) an additional eight (8) (until August 24, 2022) years from the final effective date of the Notise of Desisiee of the Tolling Agreement between the City and St. John Fisher (August 24, 2009) for the St. John Fisher Master Plan unless construction plans for the final phase of construction have been submitted to Building and Safety for Plan Check, by August 24, 2022, or an additional extension application has been submitted to the Cityy that date. 6i Revision "E" to the St. John Fisher Maser Plan — Phase Two Extension ADDITIONAL INFORMATION Related St. John Fisher Master Plan Applications As noted in the Background section of this report, in addition to establishing the St. John Fisher Master Plan through Conditional Use Permit — Revision "D," the City Council also approved a Grading Permit, Minor Exception Permit and Sign Permit to accommodate the various aspects of the project development through the requirements of the Development Code. The proposed revision request to extend the planning entitlements for Phase Two of the St. John Fisher Master Plan an additional eight (8) years will not change the findings made for the approved Master Plan, adopted under Resolution No. 2009-10, with respect to the Grading Permit, Minor Exception Permit or Sign Permit. Environmental Assessment On February 17, 2009, the City Council adopted a Mitigated Negative Declaration (MND) and Mitigation Monitoring Program (MMP) in conjunction with establishing the St. John Fisher Master Plan (Planning Case No. ZON2007-00493). The MND/MMP and Master Plan stipulate the mitigation measures and conditions of approval, which the City Council found to reduce all impacts of the Master Plan to a less than significant level. As noted in the analysis of the CUP Findings, Staff believes that the proposed Revision to Condition No. 45(b) of the St. John Fisher Master Plan, along with the updated Traffic Analysis, are within the scope of the project originally analyzed in the MND for the entire Master Plan. Therefore, Staff has prepared Addendum No. 1 to the St. John Fisher Master Plan MND/MMP to address the compliance of the proposed Revision to extend the entitlements of Phase Two for eight (8) years with the provisions of the California Environmental Quality Act (CEQA). Addendum No. 1 is attached to the Resolution presented for the City Council's approval. Future Reviews As a result of the high quantity of input from the public throughout the public hearing process in 2008/2009, the City Council required a number of "future reviews" of the property as various phases are completed to ensure that all impacts are adequately mitigated through conditions of approval. These future reviews are noted in Condition Nos. 74 - 77 of Exhibit "B" to Resolution No. 2009-10 (attached), and continue to be included in the attached conditions of approval. The first review (Condition No. 74) occurred on February 4, 2014. The second and third review (Condition Nos. 75 and 76) occurred on November 18, 2014. One (1) final review (Condition No. 75 —Year 2 review) is expected to occur in the Fall of 2015. At that time, Staff will report to the City Council any concerns raised that relate to landscape screening of the sanctuary pursuant to Condition No. 47, exterior sanctuary lighting, parking and the carillon bells. This final review will require a public notice and public hearing. FT Revision "E" to the St. John Fisher Maser Plan — Phase Two Extension CONCLUSION Based on the discussions above, Staff believes that Revision "E" of the St. John Fisher Master Plan can be approved to allow the planning entitlements of Phase Two to be extended and additional eight (8) years, with an expiration date of August 24, 2022. As such, Staff recommends that the City Council adopt Resolution No. 2015-_, thereby adopting Addendum No. 1 to the MND/MMP, and adopting Resolution No. 2015-_, thereby conditionally approving Revision "E" to the St. John Fisher Master Plan to revise Condition No. 45(b), which stipulates the expiration of a multi -phased project, and allows the planning entitlements to be extended to August 24, 2022. FISCAL IMPACT The Applicant submitted the applicable fees to request a Revision of their planning entitlements. Regardless of the City Council's action on this item, the fees paid by the Applicant for this request cover the fully burdened rate of City Staff for the preparation of this report. No refunds of the fees are being requested by the Applicant. ALTERNATIVES In addition to Staff's recommendation, the following alternative is available for consideration by the Planning Commission: Deny the Project (Revision "E" of the St. John Fisher Master Plan), and direct Staff to return to the next City Council meeting with the appropriate Resolution memorializing a denial. 2. Identify any issues of concern related to the extension of Phase Two of the St. John Fisher Master Plan, provide Staff and/or the property owner with direction in modifying the project or conditions of approval related Phase Two of the Master Plan, and continue the public hearing to a date certain for discussion of these issues. ATTACHMENTS O Draft Resolution No. 2015-_ (Revision "E" of the St. John Fisher Master Plan) - (Page 8) • Applicants Letter Requesting Revision "E" - (Page 26) • Updated Traffic Study (dated February 2, 2015) & Public Works Staff Report and Recommendation - (Page 29) • Resolution No. 2009-09 (Original MND/MMP) - (Page 74) • Resolution No. 2009-10 (Original Planning Entitlements) - (Page 97) 7 Draft Resolution No. 2015 - (Revision "E" of St. John Fisher Master Plan) RESOLUTION NO. 2015- A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, APPROVING CUP REVISION "E" TO THE ST. JOHN FISHER MASTER PLAN TO EXTEND THE PLANNING ENTITLEMENTS FOR PHASE TWO OF THE MASTER PLAN AN ADDITIONAL EIGHT (8) YEARS, BY ESTABLISHING A NEW EXPIRATION DATE FOR CONSTRUCTION OF PHASE TWO TO AUGUST 24, 2022, LOCATED AT 5448 CREST ROAD (CASE NO. ZON2007-00492). WHEREAS, on February 17, 2009, after conducting five (5) public hearings, including a special on-site public hearing, the City Council adopted Resolution No. 2009-09, adopting the Mitigated Negative Declaration and Mitigation Monitoring Program, and Resolution No. 2009-10, conditionally approving Conditional Use Permit No. 96 — Revision "D", Grading Permit, Minor Exception Permit and Sign Permit to establish a Master Plan for the St. John Fisher Church and School property. Aside from the operational conditions of the Master Plan, the approval included planning entitlements for the construction of 32,426 square feet of new building area, the demolition of 10,329 square feet of existing building area, a total of 30,688 cubic yards of associated grading and a new monument sign for the property. At the time of approval, the construction -related improvements were divided into two separate phases as outlined in Condition No. 45(a) and (b), Phase One and Phase Two respectively. The Applicant completed all portions of the project outlined in Phase One on May 14, 2014, however the Applicant was unable to submit their plans into Building and Safety Plan Check for the portions of Phase Two prior to the expiration of their construction -related planning entitlements, which expired on August 24, 2014; and, WHEREAS, on July 23, 2014, prior to the August 24, 2014 expiration of the construction - related Planning Entitlements for Phase Two, the Applicant submitted a request to modify the St. John Fisher Master Plan conditions of approval to allow the planning entitlements for Phase Two to be extended an additional eight (8) years to allow additional time to obtain funding for the construction of Phase Two; and, WHEREAS, on July 29, 2014, the application requesting an extension of their Phase Two planning entitlements was deemed incomplete for processing, pending the review and approval of an updated Traffic Analysis by the City's Traffic Engineer; and, WHEREAS, on April 27, 2015, an updated Traffic Analysis was presented to the City's Traffic Safety Committee. At that meeting, the City's Traffic Safety Committee approved Staff's recommendation to approve the updated Traffic Analysis for City Council consideration. Subsequently, on June 1, 2015, the Planning Division received confirmation from the City's Traffic Engineer that the review of the updated Traffic Analysis was completed and satisfactory; and, WHEREAS, on June 29, 2015, the application was deemed complete for processing. At the same time, a public notice was sent to all property owners within a 500 -foot radius of the subject property and was published in the Peninsula News. No public comments were received as a result of the public notice. NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES DOES HEREBY FIND, DETERMINE, AND RESOLVE AS FOLLOWS: Section 1: The proposed revision to extend the planning entitlements of Phase Two of the St. John Fisher Master Plan will not substantially change the approved project, which allows the construction of all previously approved development, including a new sanctuary, administration Resolution No. 2015 - Page 1 of 17 9 building, art room, library, a new preschool, ancillary offices and storage area. Furthermore, all elements of the Master Plan continue to comply with the general development standards of the RPVMC. Section 2: The City Council has independently reviewed and analyzed the applicant's request in accordance with the California Environmental Quality Act ("CEQA") and determined that the proposed revision to the project conditions of approval to extend the planning entitlements of Phase Two will require an Addendum to the Mitigated Negative Declaration (MND) and Mitigation Monitoring Program (MMP), which was previously approved by the City Council on February 17, 2009, under Resolution No. 2009-09. Said Resolution determined that the project's impacts are not significant or that the potential impacts could be mitigated to a less than significant impact. The City Council finds that the proposed amendments to the conditions of approval (Revision "E" to the St. John Fisher Master Plan) will not alter or diminish the spirit and intent of the original project approved by the City Council in 2009 because the project design and improvements will not be changed but will, instead be permitted to complete construction of Phase Two eight years later than the original deadline. Furthermore, the proposed amendments will not result in a deviation from the findings made by the City Council when the project was approved, and does not modify the scope of the project or the related uses. As such, the City Council finds that the amendments to the conditions of approval will not introduce new significant environmental impacts that previously were identified and analyzed in the Mitigated Negative Declaration. Furthermore, the City Council also finds that there are no changed circumstances or new information, which was not known at the time when the MND was adopted that would require the preparation of a subsequent MND or initiation of an Environmental Impact Report (EIR), pursuant to CEQA Guidelines Section 15162. In accordance with Section 15164 of the State CEQA Guidelines, the City Council hereby certifies that Addendum No. 1 to the MND, which is attached hereto as Exhibit "A" and incorporated herein by this reference, was completed in compliance with the requirements of the California Environmental Quality Act and State and local guidelines with respect thereto and approved Addendum No. 1. Section 3: Pursuant to Section 17.60.050 of the Rancho Palos Verdes Municipal Code (the "Municipal Code"), and based upon the evidence presented in the record, including the Staff Report, oral and written testimony, the MND/MMP and attached Addendum, the City Council hereby finds that the proposed revision to the project conditions of approval to extend to the planning entitlements for Phase Two an additional eight (8) years, to August 24, 2022, will not change the findings made for the approved Master Plan, adopted under Resolution No. 2009-10, with respect to the Conditional Use Permit (CUP) establishing the St. John Fisher Master Plan, which are incorporated herein by this reference. Furthermore, as a result of the Applicant's request to extend the planning entitlements of Phase Two, an updated Traffic Study was prepared that compared the existing traffic conditions to those estimated traffic impacts related to other planned Phase Two improvements. The analysis included collecting traffic count data during peak travel times on a weekday and a Sunday at the same intersection and roadway segments as the original study prepared for the Mitigated Negative Declaration. Three scenarios were evaluated within the updated Traffic Study: 1) existing 2014 traffic conditions, 2) the existing conditions plus ambient growth and project conditions (new preschool), and 3) the existing conditions plus ambient growth plus the project conditions and cumulative projects. The updated Traffic Study was forecasted for the year 2022, and states that under "existing with ambient growth and project" conditions, the proposed new preschool, and other associated development in Phase Two, is not expected to significantly impact the study locations beyond the threshold limits required by the City for review, utilizing the Institute of Transportation Engineers' Trip Generation rate and the Los Angeles County accepted methodologies. The updated Traffic Study notes that the increase in trip generation is negligible and would not require mitigation as a result of the new preschool. Therefore, the proposed revisions to extend the planning entitlements for Phase Two to August 24, 2022 will not result in new significant Resolution No. 2015 - Page 2 of 17 10 environmental impacts or a substantial increase in the severity of any existing impacts, and the findings for CUP can be made. Section 4: Pursuant to Section 17.76.040, and based upon the evidence presented in the record, including the Staff Report, oral and written testimony, and the MND/MMP and the attached Addendum, the City Council hereby finds that the proposed revision to the project conditions of approval to extend to the planning entitlements for Phase Two an additional eight (8) years, to August 24, 2022, will not change the findings made for the approved Master Plan, adopted under Resolution No. 2009-10, with respect to the Grading Permit associated with the St. John Fisher Master Plan, which are incorporated herein by this reference. Section 5: Pursuant to Section 17.66.050, and based upon the evidence presented in the record, including the Staff Report, oral and written testimony, and the MND/MMP and the attached Addendum, the City Council hereby finds that the proposed revision to the project conditions of approval to extend to the planning entitlements for Phase Two an additional eight (8) years, to August 24, 2022, will not change the findings made for the approved Master Plan, adopted under Resolution No. 2009-10, with respect to the Minor Exception Permit associated with the St. John Fisher Master Plan, which are incorporated herein by this reference. Section 6: Pursuant to Section 17.76.050, and based upon the evidence presented in the record, including the Staff Report, oral and written testimony, and the MND/MMP and the attached Addendum, the City Council hereby finds that the proposed revision to the project conditions of approval to extend to the planning entitlements for Phase Two an additional eight (8) years, to August 24, 2022, will not change the findings made for the approved Master Plan, adopted under Resolution No. 2009-10, with respect to the Sign Permit associated with the St. John Fisher Master Plan, which are incorporated herein by this reference. Section 7: The City Council hereby amends Condition of Approval No. 45(b) to extend the planning entitlements of Phase Two of the St. John Fisher Master Plan as shown below (deleted language is indicated in strikethro gh and new language is indicated with bold/underline): 45(b) Phase Two: Phase Two includes the construction of the new administration building, remodel the existing administration building into meeting rooms, construction of a new preschool, library, and art room and remaining site work associated with phase two construction. The Planning Entitlements for all construction described under "Phase Two" shall remain in full force and effect for a-maximurn--of five (5) an additional eight (8) (until August 242022) years from the final effective date of the Notice -of -Decision, of the Tolling Agreement between the City and St. John Fisher (August 24, 2009) for the St. John Fisher Master Plan unless construction plans for the final phase of construction have been submitted to Building and Safety for Plan Check, by August 24, 2022, or an additional extension application has been submitted to the City by that date. Section 8: Based upon the evidence presented in the record, the findings adopted under Resolution No. 2009-10, which are incorporated herein by reference, the MND/MMP and attached Addendum, the City Council hereby approves Revision "E" to the St. John Fisher Master Plan, including a CUP, Grading Permit, Minor Exception Permit and Sign Permit, subject to the conditions set forth in Exhibit "B," which is attached hereto and incorporated herein by this reference. Resolution No. 2015 - Page 3 of 17 11 Section 9: The time within which judicial review of the decision reflected in this Resolution must be sought is governed by Section 1094.6 of the California Code of Civil Procedure and other applicable short periods of limitation. PASSED, APPROVED, AND ADOPTED this 21St day of July 2015, Mayor Attest: City Clerk State of California } County of Los Angeles ) ss City or Rancho Palos Verdes ) I, Carla Morreale, the City Clerk of the City of Rancho Palos Verdes, do hereby certify that the above Resolution No. 2015-_ was duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on July 21, 2015. City Clerk Resolution No. 2015- 12 Page 4 of 17 Exhibit "A" Addendum No. 1 to the Approved MND/MMP Case No. ZON2007-00492 (St. John Fisher Master Plan — Revision "E", et. all.) On February 17, 2009, the City Council adopted Resolution No. 2009-09, thereby adopting the Mitigated Negative Declaration (MND) and Mitigation Monitoring Program (MMP) to allowforthe St. John Fisher Master Plan, which included the construction of 32,426 square feet of new building area, demolition of 10,329 square feet of existing building area, a total of 30,688 cubic yards of associated grading and a new monument sign. In adopting the Mitigated Negative Declaration and Mitigation Monitoring Program, the City Council found that the Mitigated Negative Declaration was prepared in the manner required by law. Based upon its independent judgement and analysis of the proposed Mitigated Negative Declaration and the record of this matter, the City Council finds that with the imposition of the mitigation measures that were proposed and which will remain in full force and effect, which address the potential significant impacts of the project upon Aesthetics, Air Quality, Geology and Soils, Hydrology and Water and Noise, and reduce them to an insignificant level, the Project will not have a significant adverse effect on the environment. The City Council has reviewed and analyzed the proposed amendments to the conditions of approval to extend the planning entitlements for Phase Two of the St. John Fisher Master Plan an additional eight (8) years. Said request would alter Condition of Approval No. 45(b) of the approved Master Plan, thereby establishing a new expiration date of August 24, 2022. Having reviewed the applicant's request, the City Council finds that the revisions to the respective condition that establishes the effective expiration of the planning entitlements will not alter or diminish the spirit and intent of the original project approved by the City Council in 2008. The proposed revisions will not result in any significant change that would affect the findings made by the Council when the project was approved, and does not modify the scope of the project or the related uses. The proposed revisions will not introduce new significant environmental effects or substantially increase the severity of the environmental impacts that previously were identified and analyzed in the MND/MMP. Therefore, the City Council finds that there are no changed circumstances or new information, which were not known at the time the MND/MMP was adopted, that would require the preparation of a subsequent MND/MMP or the initiation of an EIR pursuant to CEQA Guidelines Section 15162. In accordance with Section 15164 of the State CEQA Guidelines, the City Council has independently reviewed and considered and hereby adopts this Addendum No. 1 to the MND/MMP. Resolution No. 2015- Page 5 of 17 13 Exhibit "B" Conditions of Approval Case No. ZON2007-00492 (St. John Fisher Master Plan — Revision "E", et. all.) General All mitigation measures contained in the approved Mitigation Monitoring Program contained in C.C. Resolution No. 2009-10 for the Mitigated Negative Declaration, shall be incorporated into the proposed Project and adhered to, and are incorporated herein by reference. 2. The proposed Project, including site layout, the building and appearances, and signage throughout the site, shall be constructed and maintained in substantial compliance with the plans reviewed and approved by the City Council, and stamped APPROVED by the City with the effective date of the Notice of Decision. 3. The Director of Planning, Building and Code Enforcement is authorized to approve minor modifications to the approved plans or any of the conditions if such modifications achieve substantially the same results as would strict compliance with said plans and conditions. Otherwise, all other modifications shall be subject to review and approval by the City Council. 4. Prior to the submittal of plans into Building and Safety plan check, the applicant and the property owner shall submit to the City a statement, in writing, that they have read, understand and agree to all conditions of approval listed below. Failure to provide said written statement within ninety (90) days following the date of this approval shall render this approval null and void. 5. Prior to the submittal of plans into Building and Safety plan -check, the applicant shall obtain an encroachment permit from the Director of Public Works for any curb cuts or any other temporary or permanent improvements within the public rights-of-way. 6. Approval of this permit shall not be construed as a waiver of applicable and appropriate zoning regulations, or any Federal, State, County and/or City laws and regulations. Unless otherwise expressly specified, all other requirements of the City of Rancho Palos Verdes Municipal Code shall apply. 7. The project development on the site shall conform to the specific standards contained in these conditions of approval or, if not addressed herein, shall conform to the appropriate development and operational standards of the City's Municipal Code. 8, Failure to comply with and adhere to all of these conditions of approval may be cause to revoke the approval of the project pursuant to the revocation procedures contained in Section 17.86.060 of the City's Municipal Code. 9. In the event that any of these conditions conflict with the requirements of another permitting agency or City department, the stricter standard shall apply. 10. The construction site and adjacent public and private properties and streets shall be kept free of all loose materials resembling trash and debris in excess of that material used for immediate construction purposes. Such excess material may include, but is not limited to: the accumulation of debris, garbage, lumber, scrap metal, concrete asphalt, piles of earth, Resolution No. 2015 - Page 6 of 17 14 salvage materials, abandoned or discarded furniture, appliances or fixtures. 11. All applicable permits required by the Building and Safety Division shall be obtained by the applicant prior to the commencement of construction. 12. All mechanical equipment, whether roof -mounted or ground -mounted, shall be adequately screened to the extent practicable from other properties and/or public rights-of-way. 13. The project applicant shall maintain, in good condition, two access driveways. One access driveway shall be provided from Crest Road and a second access driveway shall be provided from Crenshaw Boulevard. Project Description 14. This approval establishes a Master Plan (St. John Fisher Master Plan) for the St. John Fisher property located at 5448 Crest Road. The approved Master Plan identifies a combined total of 32,426 square feet of new building area for a new sanctuary, preschool, administration building, library, art room, storage area, storage garage and offices; 10,329 square feet of existing facilities to be demolished, including offices, a youth building and the existing rectory along the north property line, and 26,544 square feet of the existing facilities to be remodeled, including converting the existing convent into a new rectory, converting the existing sanctuary into a new gymnasium and remodeling existing classrooms and offices. 15. The approved St. John Fisher Master Plan allows for the following additions to the property: => A new 17,000 square foot sanctuary (to replace the existing 15,402 square foot sanctuary) to be located at the northwest corner of the subject property. The sanctuary also includes a 900 square foot basement for the housing of mechanical equipment. The new sanctuary will be circular in shape, whereby the main structure will range in height from 15'-0" at the northeast end of the structure to 43'-0" at the southwest. In addition, the new sanctuary will include a steeple, at the west end of the structure, with a maximum height of 60'-0" to the top of the steeple and 74'-0" to the top of the cross which will be affixed to the top of the steeple. ► e • -�'�,� 7 S guar c minist€ation b ildi g SB u € fse €+rst leer nd=- a90 squaft-asement) A 10,204 square foot Administrative Building with a building footprint of 51784 square feet (including a 2,548 square foot basement and second floor within the approved 26'-0" building height) [Minor Modification, approved by Director on January 11, 20101 = ^^ ° 74 -square footer€idition=fo",ie=creation of=t.w"ew=e#assraams=fes E- -�ehoal A new, two -classroom preschool (including 2,081 square feet of remodeled area and 256 square feet of new floor area). [Minor Modification, approved by Director on January 11, 2010] => A new 1,289 square foot art room at the northwest corner of the existing classrooms; and A new 1,217 square foot school library at the northeast corner of the existing classrooms; and Resolution No. 2015 - Page 7 of 17 15 => A 304 square foot expansion to Barrett Hall for storage area; and => A new 454 square foot garage at the southeast corner of the property, adjacent to the priest's new rectory (previously a convent); and => A 400 square foot addition north of the existing music room to accommodate two (2) new offices. 16. The style and exterior materials of the proposed buildings shall be consistent with the architectural plans presented to and approved by the City Council. Lighting 17. Exterior lighting shall be in compliance with the standards of Section 17.56.040 of the Rancho Palos Verdes Development Code and as identified and conditioned in the Certified Mitigated Negative Declaration. 18. All exterior lighting shall be arranged and shielded so as to prevent direct illumination of surrounding property and to prevent distraction of drivers of vehicles on public rights-of-way. Luminaries shall be of a low-level, indirect and diffused type. 19. No one light fixture shall exceed 1,200 watts, and the light source shall not be directed toward or result in direct illumination of an adjacent parcel of property or properties other than that upon which such light source is physically located. All exterior lighting shall be arranged and shielded so as to prevent direct illumination of abutting properties and to prevent distraction of drivers of vehicles on public rights-of-way. 20. No building -mounted outdoor lighting shall be permitted where the light source or fixture is mounted more than sixteen (16) feet above grade, as measured from grade, adjacent to the building. 21. All outdoor lighting, including all outdoor illuminated signs, shall be turned off by 9:00 P.M. Monday through Sunday, except for lighting used for security, lighting of the sanctuary on Christmas Eve and Easter Vigil, which shall be turned off by 2 A.M, and additional security lighting the first Friday of every month. Prior to issuance of a Building Permit or Grading Permit, the applicant shall provide the Planning Department with a lighting plan for review and approval by the Planning Director that indicates the lights that will remain lit throughout the evening for security. 22. Exterior sanctuary lighting shall be installed prior to issuance of the Certificate of Occupancy for the sanctuary. After installation of all lighting, but prior to Issuance of Certificate of Use and Occupancy of the proposed sanctuary and parking lot, the developer shall request that the City conduct an inspection of the site to ensure that there is no spill-over of light onto adjacent properties. Grading and Drainage 23. This approval allows a total of 30,688 cubic yards of grading with the following quantity breakdown: a. 19,694 cubic yards of excavation Resolution No. 2015 - Page 8 of 17 16 b. 10,994 cubic yards of fill 24. Stockpiling of earthwork shall be limited to a maximum of 200 cubic yards in any given area, shall not be stockpiled on the property for more than a period of six (6) months, and the applicant shall adequately screen the visibility of all stockpiles to the extent practicable from the public right-of-way, as determined by the City's Building Official. 25. A maximum of 8,700 cubic yards of excavation is permitted for export. 26. The applicant is allowed to construct a total of five (5) retaining walls as described below: a. A combination wall along the east property line, adjacent to the existing driveway, shall not exceed a maximum height of 11'-6", b. A combination wall along the west side of the existing driveway, accessed from Crest Road (maximum height of 11'-6"), G, A combination wall to accommodate new parking along the south property line (maximum height of 1 V-6"), and d. A new retaining wall, just north of the proposed parking lot (maximum height of 7'-6", e. An 8'-0" tall retaining wall between the proposed Parish Activity Center/gymnasium and new sanctuary for a columbarium. 27. The applicant shall install wrought -iron or aluminum decorative fencing on top of all proposed combination walls, with the exception of the combination wall listed in Condition No. 26 (c) of this document, which shall be comprised of one solid wall. The wrought -iron or aluminum fencing shall be constructed in a manner by which not less than eighty (80%) of the vertical surface is open to permit the transmission of light, air or vision through said surface in a horizontal plane, as described in the development code definition for a "fence" pursuant to the RPVMC. [Minor Modification, approved by Director on January 11, 2010] 28. Construction of buildings is prohibited on extreme slopes (35% or greater slope). Parking 29. Only the uses which are listed in the parking analysis that was approved by the City Council, shall be allowed to be constructed on the St. John Fisher property. These uses will generally take place in the following structures: • Sanctuary (assembly space) • Elementary School (classrooms) • Preschool (classrooms) • Administrative Building (office space) • School Library • Barrett Hall Complex (including the assembly space) • Parish Activity Center/Gymnasium (assembly space) • Fireside Room (assembly space) • Multi-purpose room (assembly space) • Rectory (single-family residential) Resolution No. 2015- 17 Page 9 of 17 K-8 Religious education (in existing structures) Art Room (classroom) 30. All facilities, activities and/or uses on the St. John Fisher property shall be operated in such a manner so as not to create simultaneous demand for maximum on-site parking requirements that would exceed 331 spaces when the St. John Fisher School is in session and 354 parking spaces (331 regular spaces and 23 seasonal/peak parking spaces on-site) when school is not in session, without approval from the Director of Planning, Building and Code Enforcement of a Special Use Permit. If the church is fully occupied and concurrent Religious Education classes are fully occupied, no other assembly activity can occur on the property unless that activity requires 23 or fewer parking spaces. 31. If an event or activity is proposed that would occupy the parking spaces, thereby reducing available parking by more than 25% of the 331 required parking spaces, a Special Use Permit shall be required. 32. Of the 331 required parking spaces, 265 standard parking spaces shall be provided, which meet the minimum dimensions set forth in Section 17.50 of the RPVMC (9' width by 20' depth). 33. Of the 331 required parking spaces, a maximum 66 compact parking spaces are permitted, provided the spaces meet the minimum dimensions set forth in Section 17.50 of the RPVMC (8' width by 15' depth). 34. In addition to the required 331 parking spaces, the applicant shall provide a minimum of 3 loading spaces, which shall meet the minimum dimensions set forth in Section 17.50 of the RPVMC (10' width by 20' depth with 14' clearance). 35. In addition to the required 331 parking spaces, the property owner shall maintain 23 additional seasonal/peak parking spaces for overflow parking. The seasonal/peak parking spaces shall not be used when St. John Fisher Elementary School or Preschool is in session. 36. The seasonal/peak parking areas shall be planted and maintained with turf that is wear - resistant. 37. The seasonal/peak parking spaces shall meet the minimum dimensions and requirements for standard parking spaces (9' width by 20' depth) and compact parking standards (8' width by 15' depth). A maximum of 20% of the seasonal/peak parking spaces may be dedicated for compact parking. 38. The seasonal/peak parking areas shall be located in the areas depicted on the City Council - approved site plan. Specifically, a minimum of 23 seasonal/peak parking spaces shall be located in the turf area just south of Barrett Hall. 39. The property owner shall execute an agreement with the property owner of Daughters of Mary and Joseph, to be recorded with the County of Los Angeles, against both the subject property and the Daughters of Mary and Joseph property, prior to issuance of a building permit and/or grading permit, allowing St. John Fisher to use a minimum of 50% of the Daughters of Mary and Joseph paved parking spaces (45 spaces) for overflow parking on Christmas Eve, Easter Sunday and during the construction period. 40. Throughout all phases of demolition, construction and grading, the applicant shall make reasonable efforts to maintain the 331 required parking spaces. The property owner shall Resolution No. 2015 - Page 10 of 17 18 maintain a minimum of 217 non-seasonal/peak parking spaces for the sanctuary at all times during construction and prior to issuance of the Certificate of Occupancy of the new sanctuary. 41. No overnight parking or storage of vehicles associated with construction shall be permitted in the public right-of-way during construction. Building Heights and Square Footage 42. The new sanctuary shall not exceed a maximum footprint of 17,000 square feet with a 900 square foot basement beneath the main floor. The new sanctuary shall not exceed a maximum height of 15'-0" at the northeast end of the structure and 60'-0" at the top of the steeple and 74'-0" at the top of the cross that is placed upon the steeple, which is located at the west end of the structure. The sanctuary shall be setback a minimum of 5~ € 77'-0" from the west street -side property line along Crenshaw Boulevard and 62'-0" from the north street -side property line along Crest Road. BUILDING AREA CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO BUILDING PERMIT FINAL. SETBACK CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO POURING OF FOOTINGS. BUILDING HEIGHT CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO ROOF FRAMING/SHEETING INSPECTION. [Minor Modification, approved by Director on January 11, 2010] 43. The new administrative building, along the west side of the existing school, shall not exceed a maximum footprint of 7=,488 5,784 square feet. Additionally, a 27_300 2,548 square foot basement beneath the main floor shall be permitted. The new administrative building shall not exceed a maximum height of 26'-0", as measured from lowest adjacent grade. BUILDING AREA CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO BUILDING PERMIT FINAL. BUILDING AREA CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO BULDING PERMIT FINAL. [Minor Modification, approved by Director on January 11, 2010 Resolution No. 2015- 19 Page 11 of 17 Phi 44. Installation of any temporary modular buildings, other than those used by the contractor during construction, shall require a Special Use Permit during all phases of the St. John Fisher Master Plan. 45. The proposed St. John Fisher Master Plan may be broken up into two main phases as described below. If within one year of the final effective date of the Notice of Decision, the applicant has not submitted an application for a building permit for the approved project or has not commenced the approved project as described in Phase One below, approval of the project shall expire and be of no further effect unless, prior to expiration, a written request for extension is filed with the Department of Planning, Building and Code Enforcement and approved by the Director. All elements of the approved Master Plan that are not submitted as described in Phase One and Phase Two below, shall require additional future review and approval through the CUP process and additional CEQA review. Phase One and Phase Two are described as follows: a. Phase One: Phase One includes the construction of the new sanctuary, remodel of the existing sanctuary into a gymnasium/parish activity center, construction of a new parking lot, demolition of the existing rectory and youth building on the north and east sides of the property, remodel/conversion of existing convent into rectory and site work that will not be impacted by future phase construction. The Planning Entitlements for all construction described under "Phase One" shall remain in full force and effect for a maximum of one (1) year from the final effective date of the Notice of Decision for the St. John Fisher Master Plan unless construction plans have been submitted to Building and Safety for plan check. [The Planning Entitlements for all construction described under "Phase One" have been completed within the timeframes established by the City Council.] b. Phase Two: Phase Two includes the construction of the new administration building, remodel the existing administration building into meeting rooms, construction of a new preschool, library, and art room and remaining site work associated with phase two construction. The Planning Entitlements for all construction described under "Phase Two" shall remain in full force and effect for an additional eight (8) (until August 24, 2022 years from the final effective date efes+ai of the Tolling A gree me_n_t between the City and St. John Fisher (August 24, 2009) for the St. John Fisher Master Plan unless construction plans for the final phase of construction have been submitted to Building and Safety for Plan Check, by August 24, 2022, or an additional extension application has been submitted to the City by that date. [Revision "E" approved by City Council on July 21, 2015] Affordable Housing Requirement 46. The property owner and/or applicant shall provide affordable housing as required by Section Resolution No. 2015- 20 Page 12 of 17 17.11.140(A) (Affordable Housing) of the RPVMC prior to issuance of the first Certificate of Occupancy associated with the St. John Fisher Master Plan, unless the applicant demonstrates to the satisfaction of the Director of Planning, Building and Code Enforcement that they are exempted from such requirement pursuant to the exemptions described in Section 17.11.140(B) of the RPVMC. Landscaping 47. A Landscape Plan shall be submitted to the City and approved by the City's Landscape Consultant prior to issuance of a Building Permit or Grading Permit. The proposed landscaping shall be in substantial compliance with the City Council approved Landscape Plan and shall screen the new sanctuary from neighboring properties and the surrounding rights-of-way, consistent with the Applicant's photo simulations presented to the City Council on December 16, 2008, and shall be in substantial compliance with the site plan reviewed and approved by the City Council. The landscaping plan shall also indicate the species, growth rate and maximum heights of all proposed trees. 48. The applicant shall retain a majority of the existing mature trees located along the west street side property line, along Crenshaw Boulevard. Included in the Landscape Plan identified in Condition No. 51, the applicant shall submit a Tree Retention Plan indicating which existing trees will be removed and which trees will be maintained in a thriving manner along Crenshaw Boulevard. Said plan shall be reviewed and approved by the Director of Planning, Building and Code Enforcement prior to issuance of grading permits or building permits. If any of the retained mature trees become diseased or die, the trees shall be replaced by the Applicant within thirty days with a species of tree approved by the Director of Planning, Building and Code Enforcement. 49. All landscaping at the corner of Crest and Crenshaw Boulevard shall be planted and installed prior to issuance of Certificate of Occupancy of the new sanctuary to the satisfaction of the Director of Planning, Building and Code Enforcement. 50. New trees provided for screening of the new sanctuary at the corner of Crest Road and Crenshaw Boulevard shall be non -deciduous trees. 51. All existing trees that are not affected by the proposed construction, shall be maintained in a thriving manner. Any trees that become diseased or die shall be replaced within thirty days by the Applicant with a species of tree approved by the Director of Planning, Building and Code Enforcement. 52. Landscaping shall be provided and maintained along south property line, adjacent to the parking lot. In the event the required landscaping is destroyed and/or removed, the property owner shall either install a 5'-0" tall masonry wall along the south property line or restore the landscaping to adequately screen the parking lot from the residential neighborhood to the south, as determined by the Director of Planning, Building and Code Enforcement. 53. Prior to issuance of a grading and/or building permit, the Applicant, St. John Fisher, shall fund a Trust Deposit in an amount of $18,500 to cover the cost of the installation of 24 -inch box New Zealand Christmas trees along the west side of Crenshaw Boulevard within the City's public right-of-way, south of Crest Road and north of the Island View entrance to help screen the new sanctuary building from the four properties that abut Crenshaw Blvd at this location. The location of the trees and number of trees shall be determined by the Director of Planning, Building and Code Enforcement but in no case shall the number exceed 20 Resolution No. 2015- 21 Page 13 of 17 trees. Said trees shall be installed prior to the issuance of a Building Permit for the sanctuary. All costs for installation and future maintenance of said trees shall be fully paid for by the Applicant. The Applicant shall maintain said trees as directed by the City. Maintenance shall consist of trimming, watering, replacement, or spraying or other care of diseased or damaged trees. Prior to conducting maintenance on any of said trees, the Applicant shall provide proof to the City that any contractors used by the Applicant to maintain said trees are licensed, insured and bonded. If any of the trees die as a result of the negligent or willful action of a third party, the Applicant may attempt to recoverthe cost of replacing the tree from the third party, and the City shall reasonably cooperate with the Church in that effort. The trees shall not be installed adjacent to any property where the owner has notified the City in writing by June 1, 2009 that they do not want trees installed adjacent to their respective property. If all four property owners object to the planting of trees, the Applicant will not be required to pay for the installation or maintenance of said trees. Sell Schedule 54. The carillon bells are permitted to ring on the following days and times only: a. Monday through Saturday at 8:00 AM, 12:00 PM, and 6:00 PM; and b. Either shortly before or at the commencement of Sunday Masses, for a maximum of six (6) times, not before 8:50 AM or after 6:00 PM; and c. Christmas Eve Masses, but at no time before 8:00 AM or after 6:OOPM; and d. After Weddings, but at no time before 8:00 AM or after 6:OOPM; and e. After Funerals, but at no time before 8:00 AM or after 6:OOPM; and f. the following Holy Days: 1) The Assumption of the Blessed Mother (August 15), 2) All Saints Day (November 1), and 3) The Immaculate Conception (December 8), but at no time before 7:00 AM or after 6:OOPM. 55. The carillon bells shall not chime for more than a period of 90 seconds at each allotted time. 56. The speakers for the carillon bells shall be directed towards fare the interior of the lot and shall not directly face any adjacent residential properties. 57. The speakers for the carillon bells shall not exceed a maximum height of 16'-0", as measured from grade, adjacent to the location of the bells on the sanctuary. 58. The speakers for the carillon bells shall be setback a minimum of 110'-5" from any property line, as noted on the approved project plans. 59. The speakers for the carillon bells shall only be used for the sounding of bells at the approved times. 60. The signage on the subject property shall be subject to the following conditions: a) One major wall sign at the corner of Crest Road and Crenshaw Boulevard, attached and parallel to the proposed building fagade of the new sanctuary. b) The maximum sign area shall not exceed a maximum of 75 square feet (63 square feet proposed). Resolution No. 2015- Page 14 of 17 22 C) The signage shall not be internally illuminated. Indemnification 61. The owner of the property upon which the project is located shall hold harmless and indemnify the City, members of its City Council, boards, committees, commissions, officers, employees, servants, attorneys, volunteers, and agents serving as independent contractors in the role of city or agency officials, (collectively, "Indemnitees"), from any claim, demand, damage, liability, loss, cost or expense, including but not limited to death or injury to any person and injury to any property, resulting from willful misconduct, negligent acts, error or omissions of the owner, the applicant, the project operator, or any of their respective officers, employees, or agents, arising or claimed to arise, directly or indirectly, in whole or in part, out of, in conjunction with, resulting from, the maintenance of the trees adopted by the Applicant pursuant to Condition No. 53 or related to the construction approved by this resolution. Source Reduction and Recycling 62. Prior to issuance of any Certificate of Occupancy, the applicant shall prepare and submit to the Director of Public Works for review and approval a comprehensive Integrated Waste Management Plan (Plan) that addresses source reduction, reuse and recycling. 63. Prior to issuance of any building and/or grading permits, an approved Construction and Demolition Materials Management Plan (CDMMP) shall be prepared and submitted to the Director of Public Works for approval. 64. Prior to issuance of any Certificate of Occupancy, a Construction and Demolition Materials Disposition Summary (Summary) shall be submitted to the Director of Public Works upon completion of deconstruction and construction. The Summary shall indicate actual recycling activities and compliance with the diversion requirement, based on weight tags or other sufficient documentation. 65. Where possible, the site design shall incorporate the use of recycled building materials and the re -use of on-site demolition debris. 66. The project site design shall incorporate areas for collection of solid waste with adequate space for separate collection of recyclables. Miscellaneous 67. The access stairs and ramp at the corner of Crest and Crenshaw shall only be installed if required by the California Building Code or Fire Department, and if required, shall not vary materially from the minimum specifications of size required by law. The applicant shall obtain an encroachment permit for any portion of the stairs or ramp which is located within the public right of way. 68. Prior to issuance of building permits and/or grading permits, the property owner shall submit final geotechnical and soils reports to the City for review and approval by the Building Official and the City's Geotechnical Consultant. All conditions specified in the approved geotechnical and soils reports shall be incorporated into the project. 69. Prior to the issuance of a building and/or grading permit from the City's Building and Safety Resolution No. 2015 - Page 15 of 17 23 Division, the applicant shall obtain NPDES approval from the City's NPDES consultant. 70. Prior to issuance of demolition, building, and/or grading permits, a construction haul route plan shall be submitted and approved by the City's Public Works Department. 71. The speakers attached to the existing sanctuary that is proposed to be remodeled into a new Parish Activity Center/Gymnasium shall be removed prior to issuance of certificate of occupancy for the new sanctuary. 72. Sports Activities in the Parish Activity Center/Gymnasium shall not be permitted after 10:00 P.M. without the review and approval from the Director of Planning, Building and Code Enforcement of a Special Use Permit. Bleachers shall not be used in the Parish Activity Center/Gymnasium. 73. The Parish Activity Center/Gymnasium shall not be used by unaffiliated sports leagues of which St. John Fisher is not a member without the review and approval by the Director of Planning, Building and Code Enforcement of a Special Use Permit. Future City Council Reviews 74. The carillon bells and the exterior lighting of the sanctuary shall be installed prior to issuance of a Certificate of Occupancy for the new sanctuary and shall be installed as shown on the approved plans. No later than two (2) months after issuance of a Certificate of Occupancy for the new sanctuary, the City Council shall review the impacts of the carillon bells and exterior sanctuary lighting to assess the effectiveness of the Conditions of Approval in minimizing the impacts of the bells and exterior sanctuary lighting to neighboring properties. At that time, the City Council may add, relieve, delete and/or modify any of the respective conditions of approval or may prohibit the use of the carillon bells and/or outdoor sanctuary lighting if the City Council determines that the imposed conditions are not effective in minimizing the sound and/or lighting effects to neighbors. Said modifications shall not result in substantial changes to the design of the sanctuary or other ancillary structures. Notice of said review hearing shall be published and provided to owners of property within a 500 -foot radius of the subject site, to persons requesting a notice, to all affected homeowner associations and to the property owner in accordance with the RPVMC. The City Council may require such subsequent additional reviews, as the City Council deems appropriate. 75. The effectiveness of the landscaping for screening the sanctuary pursuant to Condition No. 47, exterior sanctuary lighting, parking and the carillon bells shall be subject to review and modification, as deemed necessary and appropriate by the City Council, no later than one (1) year, and subsequently two (2) years, after the Certificate of Occupancy for the new sanctuary is issued. Notice of said review hearing shall be published and provided to owners of property within a 500' radius, to persons requesting notice, to all affected homeowners associations, and to the property owner in accordance with Rancho Palos Verdes Development Code Section 17.80.090. At that time, the City Council may add, delete, or modify the related conditions of approval as deemed necessary and appropriate by the City Council. The City Council may impose more restrictive standards and conditions to mitigate any impacts resulting from the installation of landscaping, lighting, parking and the carillon bells. 76. The Conditions of Approval contained herein shall be subject to review and modification, as deemed necessary and appropriate by the City Council, six (6) months after issuance of a final Certificate of Occupancy for all structures within Phase One, as defined in Condition Resolution No. 2015 - Page 16 of 17 24 No. 45. The City Council shall review the applicant's compliance with the conditions of approval, and to determine if the conditions are accomplishing their intended purposes. Notice of said review hearing shall be published and provided to owners of property within a 500' radius, to persons requesting notice, to all affected homeowners associations, and to the property owner in accordance with Rancho Palos Verdes Development Code Section 17.80.090. At that time, the City Council may add, delete, or modify the conditions of approval as deemed necessary and appropriate by the City Council. As part of the six month review, the City Council shall consider the on-site lighting, parking conditions, circulation patterns and the hours of operation for the uses permitted on-site, in addition to other concerns raised by the City Council and/or interested parties. The City Council may impose more restrictive standards and conditions to mitigate any impacts resulting from the operation of the Project. 77, At anytime in the future, the effectiveness of the parking conditions shall be reviewed by the City Council if the number of Sunday masses is reduced to four (4) orfewer Sunday masses for a period of time exceeding three (3) months. Notice of said review hearing shall be published and provided to owners of property within a 500' radius, to persons requesting notice, to all affected homeowners' associations, and to the property owner in accordance with Rancho Palos Verdes Development Code Section 17.80.090. Storage Shed 78. The installation and use of one (1) 10' wide by 20' long prefabricated, metal shed is permitted along the north side of the new Rectory for the sole purpose of storing emergency materials. [Minor Modification approved by Director on August 24, 2011] 79. The approved storage shed shall not exceed a maximum height of 12'-0" T-11 1/2" proposed height), as measured from existing adjacent grade. [Minor Modification approved by Director on August 24, 2011] 80. The approved storage shed shall maintain a minimum 20'-0" interior setback from the east side property line21'-5'/2" proposed interior setback [Minor Modification approved by Director on August 24, 2011] 81. Landscaping shall be provided around the storage shed for screening purposes and the storage: shed shall be a dark green color to blend with the landscaping° [Minor Modification approved by Director on August 24, 2011] 82. The approved storage shed structure cannot be replaced with a cargo container that is designed and fabricated to transport items from one location to another. [Minor Modification approved by Director on August 24, 2011] Resolution No. 2015 - Page 17 of 17 25 Applicant's Letter Requesting Revision "E" of St. John Fisher Master Plan 26 SAINT JOHN FISHER PARISH "CELEBRATING LIFE: IN'i"HE LIGHT OF CHRIST" July 22, 2014 Ms. Leza Mikhail, Assistant Planner City of Rancho Palos Verdes Planning Department 30940 Hawthorne Blvd. Rancho Palos Verdes, CA 90275 RE; Conditional Use Permit #2009-09 Dear Leza, Phase Two of our approved master plan (Conditional Use Permit 42009-09), issued to the Archdiocese of Los Angeles for the St. John Fisher Catholic Church property in Rancho Palos Verdes, is set to expire on August 24, 2014. The parish has completed and constructed Phase One, of the approved master plan but has yet to submit plans into plan check for Phase Two, which would automatically extend our planning entitlement. The approved master plan indicating the location of the Phase Two components is ' attached with the incomplete construction highlighted in green. The location of the subject buildings is generally internal to the project site and has little to no impact on the public view of the campus. St. John Fisher Church is requesting an extension of time equivalent to an additional 10 years to complete the construction of these remaining; project components. The reason for the request is to provide time for fund raising needed to support the construction costs of the remaining project scope. The parish has shown due diligence in constructing and completing Phase One through its efforts to complete the project to date and is committed to continuing to build quality structures that are an asset to the community. To this end, we respectfully request your consideration in providing us ample time to fund the remaining project. Please let us know what additional information may be required in order to process this request. Yours sincerer, �ev ,kslgr. Dav d , Sork Pastor 5448 CrassT ROAD — RANCHO PA LOS VERIDes, CALIFORNIA 90275-5027 V- PARIS,= OFFICE (3 t 0) 377-5571 F,,Ax (3 10) 377-6303 E-MAIL; INFO@SJF.ORG -V 27 BUILDING AND SITE CHANGES ��•� A 0«4 rr f4,Mn R�alci.i/JatD R C Ds EostiaF G m PVII iA W. it Crl6 �A° 6 DLscaa.ncrD w �Rs seD eutn�w. i..- - am[B tv v D&rouswn s< RLu4DaED sr aaq v raaratpl r9c na 1DDn+tnn :nnrr:a TP1'tl�'r':�.. w."iv'�"` «'« ww a",oe"' '-+t'«�✓xrwn rlr ov,e'r ; w t'0. +t'Yw "";,.' °"•nia"'w�..'°0i.: Iwt c Poo[ rint. +1],000 9a9nt0l a Irl ce E,°svr;ro °` xowaw,« a�, .:.i'.,w w••.:• �i 1�ew r w,.�et : r ., e�.l � 17.000Ll- . o.,>a« aa.°aw � .. ,�, a.cr w ra w•. fr. Meia.il.i +t�.ru � m •.Law ,awnn'.a xtireER i�rrsc V1 p 2,081 �R1 -1,048 1,048 1.048 - ~ +1,289 1,269 1,289 r r~ / 1 u 0 V v + +r b..re� ,% •e, +1,217 _ - 1,217 1,217 'y? f - +304 -114 10,986 «„waa a«a ow vrr,vu w rw ,wu 4 j +454 454 454 ` e +400 2,222 2,5602560 arum manav / 11 ry / 4,783 ooi ,�'' / Y , DraDarlY •w°ea ie.,,.mme. r 9®,I;,,at.aulaay mW.vA_ awa: y<a 4,646 4,64fi ,o >.oae. mwra,Qs,« r« o.. °r Dx,+✓ ..aaneamo.«,aa„ay� °u.:ao.i..aano,.c.n.a.wma weEne,n:aus ROplrttl:altD orom,an,.,n roorv.mm: am awa:z, 1nuL: uacz a.awmncwutrenlaurnn 9,77] CbN,N9,773 2 1 EC QN QAG.RAfr{ 1 aMwD D i ro0�+rn+uuA30,730 6,641 6,641 6,641 rns � 074 x. D«a•cm .,.tin aza u Ra°a al ntumt am,.. b Baron nd ,o -1,024 1,Oz4 1,024-338 !f+ .-er uaL..• e�8,114 6,114 6,069 8,114 0,1146,069 3,779 3,77926,542 55,758 67,810 74,946 1 64,700 DEURvnox��aRS DosmDosED mE 111111 � � � tic r«rw DPab,Ra w.w ... , „� AREAS SUMMARY 1 4`a q 1 t,�trt ,Mr 1. 0 ."� :.'am d p,an � y�. A« • oro danxc Dm �Rtrr: muL 1,.]se C0.1r0 E r. RaDRNt D _ __... _ u t _ tai'nD +?PM roru r y{-t� I � Vie•.. ri ��D.e1, rwfan r+riN Mr ,a�1`rt re .re• 1 �'/Wi cDLDBn nl RUCSED ] lPR%: TOrAL .Aa6 � � ' '� andlMt •«dq+�� M CarLOOfWx x 11.,100 �. � _ � :« wm r C�1 : _ �_ 1 , o,n w Kt -rrs � +Sc"s t►!a+'ct d>.y`°°`�'.'w "• ••••6`y rm rucmanru. roru 'r,me rCLWx :-E � �i }q3. 1 i i, i Z °Na+'{ Lt Fw/ �`GV.w pow N Mw oM ' r �Z • 1 w1 O w , r^i"t � Rtr> Y"°'wr nw.wa• iw ..th '� rarMat Ir �a� xl LL�� I 1 1 I t� 11 1 V. •r �� 1. 1T t}'f iY TM �1 1 1 1 U � 0. CRMaRwr .P wr+MrNy -tfm •,.} h.•� a-®aw a.rrR.'... yr. .� � _ ��• � r w°°•1Y►MDN'{1°� � � +I I 1 s � 5 I • O 7U VI atn : „•°•a!•Y. •wa dcb'.a w° IA/l m 1 /Q 10001 aSY 0. tnnlaac ��_ - -- I z. 0 A0.1 Updated Traffic Study (dated February 2, 2015) & Public Works Staff Report and Approval of Updated Traffic Study WE Iq MEMORANDUM IL RANCHO PALOS VERDES TO: Leza Mikhail, Associate Planner FROM: Melissa Countryman, Senior Engineer DATE: June 1, 2015 SUBJECT: Review of Traffic Study Update for St. John Fisher Church Phase II Project I have reviewed the Traffic Study Update prepared by KOA Corporation, originally dated October 29, 2014, for the subject project. Based on the applicant's response and subsequent revisions, I am satisfied with the results of the study. On April 27th, 2015, the Traffic Safety Committee approved Staff's recommendation to approve the traffic study as well. Please forward my recommendation to the City Council for consideration. Cc: File WE Traffic Study Update for St. John Fisher Church Rancho Palos Verdes, California February 2, 2015 Prepared For: St. John Fisher Church 5448 Crest Road Rancho Palos Verdes, CA 90275 Prepared by: KOA CORPORATION PLANNING & ENGINEERING 1100 Corporate Center Drive, Suite 201 Monterey Park, California 91754 (323) 260-4703 JB41143 31 KOA CORPORATION PLANNING & ENGINEERING Table of Contents 1. INTRODUCTION.................................................................................................................................................1 PROJECTSTUDY AREA.................................................................................................................................................2 PROJECTACCESS......................................................................................................................................................... 5 ANALYSISMETHODOLOGY..........................................................................................................................................5 2. EXISTING 2014 CONDITIONS...............................................................................................................,........8 EXISTING ROADWAY SYSTEM EXISTING TRAFFIC VOLUMES. EXISTING LEVELS OF SERVICE ....................................................... 8 ....................................................... 8 ....................................................... 9 3. EXISTING CONDITIONS PLUS AMBIENT GROWTH PLUS PROJECT..........................................13 AMBIENT TRAFFIC GROWTH.....................................................................................................................................13 PROJECT TRIP GENERATION......................................................................................................................................16 PROJECT TRIP DISTRIBUTION.....................................................................................................................................16 PROJECT TRIP ASSIGNMENT.......................................................................................................................................16 EXISTING PLUS AMBIENT GROWTH PLUS PROJECT TRIPS.............................................................................................16 4. EXISTING PLUS AMBIENT GROWTH PLUS CUMULATIVE PROJECTS PLUS PROJECT ........ 22 EXISTING PLUS AMBIENT GROWTH PLUS CUMULATIVE PROJECTS PLUS PROJECT TRIPS.................................................24 5. CONGESTION MANAGEMENT PLAN CONFORMANCE....................................................................27 6. SUMMARY AND PROJECT RECOMMENDATIONS................................................................................28 Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page i JB41143 32 KOA CORPORATION PLANNING & ENGINEERING List of Figures FIGURE I: STUDY AREA 3 FIGURE 2: SITE PLAN 4 FIGURE 3: EXISTING LANE CONFIGURATION 11 FIGURE 4: EXISTING 2014 PEAK HOUR TRAFFIC VOLUMES 12 FIGURE 5: EXISTING WITH AMBIENT TRAFFIC GROWTH 15 FIGURE 6: PROJECT TRIP DISTRIBUTION 17 FIGURE 7: PROJECT ONLY TRAFFIC VOLUMES 18 FIGURE 8: EXISTING PLUS AMBIENT GROWTH PLUS PROJECT TRAFFIC VOLUMES 19 FIGURE 9: LOCATION OF CUMULATIVE PROJECTS 23 FIGURE 10: EXISTING 2014 PLUS AMBIENT PLUS CUMULATIVE PROJECTS PLUS PROJECT 16 PEAK HOUR TRAFFIC VOLUMES 26 List of Tables TABLE I — LEVEL OF SERVICE DEFINITIONS 6 TABLE 2 — EXISTING LEVEL OF SERVICE — STUDY INTERSECTION 9 TABLE 3 — EXISTING LEVEL OF SERVICE — WEEKDAY — STUDY ROADWAY SEGMENTS 9 TABLE 4 — EXISTING LEVEL OF SERVICE — SUNDAY — STUDY ROADWAY SEGMENTS 10 TABLE 5 — EXISTING WITH AMBIENT GROWTH LEVEL OF SERVICE - STUDY INTERSECTION 13 TABLE 6 — EXISTING WITH AMBIENT GROWTH LEVEL OF SERVICE —WEEKDAY — STUDY ROADWAY SEGMENTS 13 TABLE 7 — EXISTING WITH AMBIENT GROWTH LEVEL OF SERVICE — SUNDAY — STUDY ROADWAYS SEGMENTS 14 TABLE 8 — PROJECT TRIP GENERATION 16 TABLE 9 — EXISTING PLUS AMBIENT GROWTH PLUS PROJECT LEVEL OF SERVICE — WEEKDAY — STUDY INTERSECTION 21 TABLE 10 — EXISTING PLUS AMBIENT GROWTH PLUS PROJECT LEVEL OF SERVICE — WEEKDAY — STUDY ROADWAY SEGMENTS 21 TABLE I I — CUMULATIVE PROJECTS — TRIP RATES APPLIED 22 TABLE 12 — CUMULATIVE PROJECTS — TRIP GENERATION 22 TABLE 13 — EXISTING PLUS AMBIENT GROWTH PLUS CUMULATIVE PROJECTS PLUS PROJECT LEVEL OF SERVICE — WEEKDAY — STUDY INTERSECTION 25 TABLE 14 — EXISTING PLUS AMBIENT GROWTH PLUS CUMULATIVE PROJECTS PLUS PROJECT LEVEL OF SERVICE — WEEKDAY — STUDY ROADWAY SEGMENTS 25 Traffic Study Update for St. John Fisher Church Page ii Prepared for St. John Fisher Church JB41143 February 2, 2015 33 KOA CORPORATION PLANNING & ENGINEERING Appendices APPENDIX A — STUDY SCOPING DOCUMENT APPENDIX B I — TRAFFIC COUNT DATA — STUDY INTERSECTIONS APPENDIX B2 — TRAFFIC COUNT DATA — STUDY ROADWAY SEGMENTS APPENDIX C — STUDY INTERSECTION ANALYSIS WORKSHEETS — EXISTING CONDITIONS APPENDIX D — STUDY INTERSECTION ANALYSIS WORKSHEETS — EXISTING PLUS AMBIENT GROWTH APPENDIX E — STUDY INTERSECTION ANALYSIS WORKSHEETS — EXISTING PLUS AMBIENT GROWTH PLUS PROJECT APPENDIX F — STUDY INTERSECTION ANALYSIS WORKSHEETS — EXISTING PLUS AMBIENT GROWTH PLUS CUMULATIVE PROJECTS PLUS PROJECT Traffic Study Update for St. john Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page iii JB41143 34 KOA CORPORATION PLANNING & ENGINEERING I. Introduction This report provides an update to the original project traffic impact analysis report associated with the previously -approved St. John Fisher Church/School expansion (Project). The existing church site is located at 5448 Crest Road within the City of Rancho Palos Verdes, California. St. John Fisher Church has completed the first phase of improvements to its facilities, which had been analyzed in a traffic study effort by KOA that culminated in a final deliverable in December of 2007. The proposed Project, for purposes of this report, is the previously -approved phase two improvements to the church property yet to be completed. The only trip -generating use under phase two would be a preschool facility with weekday operations. As part of the review process for the Conditional Use Permit (CUP) extension of the previously approved phase two Project scope, the City has requested an updated traffic study that accomplishes two objectives: Determine area traffic conditions with Project phase one operations, and compare to estimated conditions of 2007 study. Update the Project phase two improvements analysis and summarize the overall project traffic impacts relative to current cumulative impacts. The previously -approved phase two of the church master plan would provide for replacement of educational and site ancillary facilities including the following: Art room • School library Preschool facility Music offices • Remodeling of existing offices into meeting rooms Administrative offices All of these facilities would serve current on-site operations, other than the preschool. The preschool is a previously -approved use and would serve up to 40 children (20 children in a morning program, and 20 children under a separate afternoon program), on weekdays only. The project will be analyzed with a 40 -student program for both peak and daily conditions, as is consistent with the 2007 study. The previously -approved meeting rooms would only serve existing church operations, would be used by existing church members and ministries, and would also not be available to outside groups. The church also does not plan to create new programs due to the pending completion of the meeting rooms. The Project traffic study area, as defined through consultation with the City of Rancho Palos Verdes, included one nearby intersection and two roadway segments, matching the study area of the 2007 study. Traffic impacts were based on weekday and Sunday traffic data; with weekday AM and PM peak -hour traffic and Sunday AM peak -hour traffic analyzed at the study intersection, and weekday and Sunday daily traffic analyzed at the two study roadway segments. Traffic Study Update for St. John Fisher Church Page I Prepared for St. John Fisher Church JB41 143 February 2, 20 15 35 KOA CORPORATION •.' PLANNING & ENGINEERING The traffic analysis included the following traffic scenarios: Existing 2014 Conditions Existing plus Ambient Growth plus Project Conditions Existing plus Ambient Growth plus Cumulative Projects (including St. John Fisher Project) plus Project Conditions Based on discussions with City staff, the analysis focuses on weekday AM and PM peak hour conditions and Sunday peak hour conditions. Project Study Area The Project study area is defined by the study intersection of Crenshaw Boulevard and Crest Road (an all -way stop -controlled intersection) and the following two roadway segments: I. Crenshaw Boulevard north of Crest Road 2. Crest Road west of Crenshaw Boulevard Figure I illustrates the location of the Project site and the three study locations. Figure 2 provides the Project site plan. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 2 JB41143 36 LEGEND ® Project Location Study Intersection Study Roadway Segment N No Scala PMKOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 1 PLANNING R ENGINEERING Study Area 37 _ * LEGEND: LASS NEW 1 NFWAPT ti R Cc)'34. 4RD 1 M75 n% rr ti "EW �y{� 1 a r 2 t h csr y+ Y�1 1 3 y � esI I r ACSlVfFY CiN[ER � ..;. ��� -�r_-- :..- t � --•- --- :-- .. _- - .ter LU PAM ;ON 41 et KOA CORPORATION ISt. John Fisher Church - Phase II - Traffic Impact Study Figure 2 Projegt,jto Plan KOA CORPORATION PLANNING & ENGINEERING Project Access Access to and from the project site are via driveways located on Crenshaw Boulevard (south of Crest Road) and Crest Road (east of Crenshaw Boulevard). Figure 2 also shows the location of the current driveways. Analysis Methodology The proposed Project site is located within the City of Rancho Palos Verdes. KOA coordinated with city staff to achieve consensus on assumptions such as trip generation, trip distribution, study locations, ambient growth and cumulative projects. The following describes the methodology for this report: Project Trip Generation and Distribution Forecast Project trip generation was based on the Institute of Transportation Engineers' (ITE) publication Trip Generation, 9th Edition rates. The assumptions utilized for Project trip distribution are discussed in the Project Trip Generation section of this report. Level of Service Methodol The study intersection of Crenshaw Boulevard and Crest Road is a four-way stop controlled intersection. Typically for stop -controlled intersections, the Highway Capacity Manual (HCM) methodology is utilized. At this location however, due to the unusual lane configurations (i.e. southbound approach has a shared through/right-turn lane and an exclusive right -turn lane), the HCM methodology restrictions/limitations prevents the analysis to accurately estimate average delay and corresponding level of service. As the City has adopted the same methodology as Los Angeles County, the traffic impact analysis for this location utilizes the Intersection Capacity Utilization (ICU) methodology which is typically used to determine level of service for signalized intersection. To account for the lower capacity/flow-rate at a stop -controlled intersection, the overall capacity of 1,600 vehicles per hour per lane (vphpl) has been adjusted to 1,200 vphpl. This adjustment methodology has been recently adopted by the City of Los Angeles Department of Transportation (LADOT). Consistent with County guidelines, the resultant volume -to -capacity ratio (V/C) also allows for measurement of traffic impacts associated with the proposed Project. The ICU methodology requires the inputs of approach lanes and number by type (left, thru, right), control (free movement or limited by traffic controls), and considers conflicting movements at the intersection and adds the cumulative total of volume -to -capacity ratios for the conflicting movements (opposing left and thru movements, for example) across all of the intersection approaches. The ICU value then is translated to a level of service (LOS) value, which range from LOS A to LOS F. LOS A indicates excellent operating conditions with little delay to motorists, whereas LOS F represents congested conditions with excessive vehicle delay. LOS E is typically defined as the operating capacity of a roadway. Table I defines the level of service criteria. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 5 JB41143 W KOA CORPORATION PLANNING 8. ENGINEERING Table I — Level of Service Definitions Significant Traffic Impacts As defined by City of Rancho Palos Verdes traffic study review policies, significant impacts of a proposed project at an intersection must be mitigated to a level of insignificance. In cases where capacity increases are possible, KOA analyzed mitigation measures that would restore operations commensurate with the future pre -Project period or better. The City has adopted County of Los Angeles Department of Public Works significance standards for study intersections, which are based on project -related increases in the volume -to -capacity ratio (V/C). The following increases in peak -hour V/C ratios are considered significant impacts: Level of Service Final V/C [a] Signalized LOS Interpretation Intersection D 0.81 —0.90 Volume to E and F 0.901 or more Capacity Ratio (ICUICMA) Excellent operation. All approaches to the intersection appear A quite open, turning movements are easily made, and nearly all 0.000 - 0.600 drivers find freedom of operation. Very good operation. Many drivers begin to feel somewhat B restricted within platoons of vehicles. This represents stable 0.601 - 0.700 flow. An approach to an intersection may occasionally be fully utilized and traffic queues start to form. C Good operation. Occasionally backups may develop behind 0.701 - 0.800 turning vehicles. Most drivers feel somewhat restricted. D Fair operation. There are no long-standing traffic queues. This 0.801 - 0.900 level is typically associated with design practice for peak periods. E Poor operation. Some long standing vehicular queues develop 0.901 - 1.000 on critical approaches. Forced flow. Represents jammed conditions. Backups from locations downstream or on the cross street may restrict or F prevent movements of vehicles out of the intersection approach Over 1,000 lanes; therefore, volumes carried are not predictable. Potential for stop and go type traffic flow. Source: Highway Capacity Manual, Special Report 209, Transportation Research Board, Washington D.C., 2000 and Interim Materials on Highway Capacity, NCHRP Circular 212, 1982 Significant Traffic Impacts As defined by City of Rancho Palos Verdes traffic study review policies, significant impacts of a proposed project at an intersection must be mitigated to a level of insignificance. In cases where capacity increases are possible, KOA analyzed mitigation measures that would restore operations commensurate with the future pre -Project period or better. The City has adopted County of Los Angeles Department of Public Works significance standards for study intersections, which are based on project -related increases in the volume -to -capacity ratio (V/C). The following increases in peak -hour V/C ratios are considered significant impacts: Level of Service Final V/C [a] Project Related vic increase C 0.71 —0.80 Equal to or greater than 0.040 D 0.81 —0.90 Equal to or greater than 0.020 E and F 0.901 or more Equal to or greater than 0.010 [a] Final WC is the VIC ratio at an intersection, considering impacts from the project, ambient and related project growth, and without proposed traffic impact mitigations. The County of Los Angeles does not have significant impact criteria for unsignalized intersections. For the purpose of identifying incremental and significant Project related traffic impacts at stop -controlled intersections, the ICU methodology was utilized. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 6 JB41143 ME KOA CORPORATION PLANNING & ENGINEERING Based on City traffic study review policies, the following significance thresholds apply for project -related increases in the volume -to -capacity ratio (V/C) of roadway segments: Final Level of Service Percent Increase In Passenger Car by Project C 4% D 2% EorF 1% Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2,2015 Page 7 JB41143 41 KOA CORPORATION PLANNING & ENGINEERING 2. Existing 2014 Conditions This section describes the existing conditions within the study area, in terms of roadway facilities and operating conditions within the study area. Existing Roadway System Fieldwork within the Project study area was undertaken to identify traffic control and approach lane configuration at each study intersection. Figure 3 illustrates the existing study intersection approach lane and control configuration. Crenshaw Boulevard, to the north of Crest Road, is a four -lane divided facility. South of Crest Road, Crenshaw Boulevard terminates as a two-lane roadway serving the Project, Del Cerro Park and residential use. Crest Road west of Crenshaw Boulevard is a four -lane east -west roadway which provides connection to Hawthorne Boulevard. East of Crenshaw Boulevard, Crest Road is a two-lane facility. Existing Traffic Volumes KOA compiled new manual intersection turn movement counts that were conducted at the study intersection. KOA also compiled new roadway segment counts for this study. Peak period turning movement counts were collected between the hours of 7:00 AM to 9:00 AM and 4:00 PM to 6:00 PM on a weekday and between 8:00 AM to 12:00 PM on a Sunday. The results of counts were utilized to determine existing weekday AM and PM peak -hour conditions and Sunday AM and midday peak hour conditions. The study roadway segment counts were conducted on the following dates. Due to problems with equipment, data at one of the locations was collected on subsequent days: • Crest Road, west of Crenshaw Blvd. — Thursday, October 9th and Sunday, October 12th of 2014. • Crenshaw Blvd, north of Crest Rd. — Thursday, October 2nd and Sunday, October 5th of 2014. The study intersection counts were conducted on the following days: U Thursday, October 2^d and Sunday, October 5th of 2014. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 8 JB41143 Ir KOA CORPORATION PLANNING & ENGINEERING Existing Levels of Service Based on the weekday and weekend traffic volumes, a volume -to -capacity ratio and corresponding level of service were determined for three study locations. As shown in Table 2, the study intersection is currently operating at a good level of service (LOS D or better) during peak hours under both weekday and Sunday conditions. The December 2007 traffic study identified LOS values at the study intersection as D for weekday a.m. peak, C for weekday p.m. peak, and A for Sunday morning peak. Traffic volumes in the area have diminished since the 2007 study was completed. Table 2 — Existing Level of Service — Study Intersection Weekday Sunday Study Intersections AM Peak PM Peak AM Peak V/C LOS V/C LOS V/C LOS I ICrenshaw Blvd & Crest Rd (a) 0.663 B 0.497 A 0.469 A [a] Stop -controlled intersection. LOS was calculated based on the 1,200 capacity utilizing the Intersection Capacity Utilization (ICU) Method, Table 3 summarizes the existing weekday level of service results at the study roadway segments. As the table shows, both roadway segments are operating at LOS A on weekdays. These LOS values match those identified for these locations in the 2007 traffic study. Table 3 — Existing Level of Service — Weekday — Study Roadway Segments Segment Capacity-- Daily [a] Existing 2014 Weekday V/C LOS Daily I Crenshaw Blvd north of Crest Rd 127,200 14,667 0.115 A 2 Crest Rd west of Crenshaw Blvd 127,200 11,709 1 0.092 A [a] Daily Capacity obtained from "Los Angeles County Traffic Impact Analysis Report Guidelines". Daily Capacity obtained using 60/40 directional split and by multiplying Peak hour roadway capacity (passenger car per hour) times 24 hours. Table 4 summarizes the existing Sunday level of service results at the study roadway segments. As the table shows, both roadway segments are operating at LOS A. These LOS values match those identified for these locations in the 2007 traffic study. Traffic Study Update for St. John Fisher Church Page 9 Prepared for St. John Fisher Church JB41 143 February 2, 2015 43 KOA CORPORATION PLANNING & ENGINEERING Table 4 — Existing Level of Service — Sunday — Study Roadway Segments Capacity Segment Daily [a] Existing 2014 Sunday V/C LOS Daily I Crenshaw Blvd north of Crest Rd 127,200 11,686 0.092 A 2 Crest Rd west of Crenshaw Blvd 127,200 9,212 1 0.072 A [a] Daily Capacity obtained from "Los Angeles County Trak Impact Analysis Report Guidelines". Daily Capacity obtained using 60140 directional split and by multiplying Peak hour roadway capacity (passenger car per hour) times 24 hours. Traffic count summaries are provided in Appendix B I for the study intersections and Appendix B2 for the study roadway segments. Figure 4 illustrates the existing weekday and weekend traffic volumes at the study locations. Existing conditions level of service worksheets are provided in Appendix C of this report. Traffic Study Update for St. John Fisher Church Prepared for St. john Fisher Church February 2, 2015 Page 10 JB41143 E, Beech ate O, Ur Ind. Q yr Crestrrd Middlecrest �o �a �a asaa r tiej h/ � s Ln• z __..-- hii► M - r' tes tca a 5a LEGEND ® Project Location 18 Study Intersection CEM Stop Sign Controlled Intersection N Stop Sign Z► Intersection Lane Geometry No Scale KOA CORPORATION St. John Fisher Church - Phase If - Traffic Impact Study Figure 3 ,'�ING , NG Existing Intersection Lane Configuration -45 KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study ;•;:.ir.! [ I INC, EXlstl No scale Figure 4 2014 Traffic Volumes 46 LEGEND ® Project Location IS Study Intersection Xx Intersection Turn Volume XXXX Weekday [Sunday] Roadway [XXXX] Segment ADT Volumes KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study ;•;:.ir.! [ I INC, EXlstl No scale Figure 4 2014 Traffic Volumes 46 KOA CORPORATION PLANNING $ ENGINEERING 3. Existing Conditions plus Ambient Growth plus Project In order to measure Project related traffic impacts, it is necessary to forecast future traffic conditions within the study area, both with and without Project -generated traffic. The forecast for this scenario provides a basis against which Project traffic impacts can be measured. Ambient Traffic Growth Forecast of future traffic also includes an ambient growth increase which is attributed to both regional population and employment growth outside of the study area. Based on data contained in the Los Angeles County Congestion Management Program (CMP), an ambient growth rate of 0.5% was applied to existing 2014 traffic counts to estimate 2022 traffic. Table 5 summarizes the level of service results. The study intersection would continue to operate at the same LOS values identified for the existing conditions analysis. The December 2007 traffic study identified LOS values for this scenario at the study intersection as D for weekday a.m. peak, C for weekday p.m. peak, and A for Sunday morning peak. Table 5 — Existing with Ambient Growth Level of Service - Study Intersection Study Intersections Weekday Sunday AM Peak PM Peak AM Peak V/C LOS VIC LOS VIC LOS Crenshaw Blvd & Crest Rd [a] 0.686 B 0.514 A 0.484 A [a] Stop -controlled intersection. LOS was calculated based on the 1,200 capacity utilizing the Intersection Capacity Utilization (ICU) Method. Table 6 summarizes the weekday level of service results at the study roadway segments. As the table shows, both roadway segments would continue to operate at LOS A on weekdays, matching the LOS identified in the 2007 traffic study. Table 6 — Existing with Ambient Growth Level of Service — Weekday — Study Roadway Segments [a] Daily Capacity obtained from "Los Angeles County Traffic Impact Analysis Report Guidelines". Daily Capacity obtained using 60/40 directional split and by multiplying Peak hour roadway capacity (passenger car per hour) times 24 hours. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 13 JB41143 47 Existing 2014 + Ambient Segment Capacity Daily [a] Growth Weekday V/C LOS Daily I JCrenshaw Blvd north of Crest Rd 127,200 15,264 0.120 A 2 JCrest Rd west of Crenshaw Blvd 1 127,200 12,186 1 0.096 A [a] Daily Capacity obtained from "Los Angeles County Traffic Impact Analysis Report Guidelines". Daily Capacity obtained using 60/40 directional split and by multiplying Peak hour roadway capacity (passenger car per hour) times 24 hours. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 13 JB41143 47 FMKOA CORPORATION PLANNING & ENGINEERING Table 7 summarizes the existing level of service results at the study roadway segments on a Sunday. As the table shows, both roadway segments would continue operating at LOS A, matching the LOS identified in the 2007 traffic study. Table 7 — Existing with Ambient Growth Level of Service — Sunday — Study Roadways Segments [a] Daily Capacity obtained from "Los Angeles County Trak Impact Analysis Report Guidelines". Daily Capacity obtained using 60/40 directional split and by multiplying Peak hour roadway capacity (passenger car per hour) times 24 hours. Figure 5 illustrates the analyzed volumes for this scenario. Level of service worksheets for the level of service calculations at the study intersection are provided in Appendix D. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 14 JB41143 .; Existing 2014 + Ambient Capacity Segment Daily [a] Growth Sunday V/C LOS Daily I Crenshaw Blvd north of Crest Rd 127,200 12,162 0.096 A 2 Crest Rd west of Crenshaw Blvd 127,200 9,587 0.075 A [a] Daily Capacity obtained from "Los Angeles County Trak Impact Analysis Report Guidelines". Daily Capacity obtained using 60/40 directional split and by multiplying Peak hour roadway capacity (passenger car per hour) times 24 hours. Figure 5 illustrates the analyzed volumes for this scenario. Level of service worksheets for the level of service calculations at the study intersection are provided in Appendix D. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 14 JB41143 .; N No Scale KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 5 ' PLANNING a ENGINEERING Existing 2014 Plus Ambient Growth Traffic Volumes M LEGEND Project Location • Study Intersection xx Intersection Turn Volume XXXX Weekday [Sunday] Roadway [XXXX] Segment ADT Volumes N No Scale KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 5 ' PLANNING a ENGINEERING Existing 2014 Plus Ambient Growth Traffic Volumes M KOA CORPORATION PLANNING S ENGINEERING Project Trip Generation Table 8 summarizes the trip generation rates and calculated vehicle trip totals for the proposed Project. Trip generation rates defined by Trip Generation (91h Edition), published by the Institute of Transportation Engineers (ITE), were used to estimate the number of Project -generated trips. Table 8 — Project Trip Generation Land Use ITE Code Intensity Average Weekday AM Peak Hour PM Peak Hour In Out Total In Out Total Trip Generation Rates Day Care Center 565 I 1 student 4.38 53% 47% 0.80 47% 53% 1 0.81 Proposed Project Pre -School 15 % Reduction 565 40 students 175 -27 17 -3 15 -2 32 -5 15 -2 17 -3 32 -5 Proposed Project Subtotal 148 14 13 27 13 15 27 Source: Trip Generation Manual, 9th Edition, Institute of Transportation Engineers, 2012 * Estimated parent drivers with students in existing grade school program. The Project is projected to generate approximately 148 weekday daily trips, including 27 during the a.m. peak hour and 27 during the p.m. peak hour. The Project (day care center) would be operating on weekdays only, and it would not be generating new trips on Sundays. Therefore generated trips were not analyzed for the Sunday peak -hour analysis. Project Trip Distribution Trip Distribution is the process of assigning the directions from which traffic will access a project site. Trip distribution is dependent upon the land use characteristics of the project and the general locations of other land uses to which project trips would originate or terminate. Figure 6 illustrates the intersection trip distribution percentages that were utilized for Project traffic volumes. Project Trip Assignment Based on the estimated trip generation and distribution assumptions described above, Project traffic was assigned based on project access and the area roadway network. The Project -only trips are illustrated on Figure 7. Existing -plus Ambient Growth -plus Project Trips The Project trips were added to the volumes calculated for the Existing plus Ambient Growth scenario to estimate traffic conditions with Project traffic. The resulting peak -hour traffic volumes are shown on Figure 8. Traffic Study Update for St. John Fisher Church Page 16 Prepared for St. John Fisher Church JB41 143 February 2, 2015 WE LEGEND ■ Project Location +♦ Study Intersection 5% H Project Trip Distribution P" Ii►OA CORPORATION St. John Fisher Church - Phase II - Traffic Im s ANNNG . , ,... NG N No Scale Study Figure 6 Project Trip Distribution 51 N No scale KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 7 PLANNING & ENGINEERING Project Only Traffic Volumes 52 LEGEND Project Location Study Intersection Xx Intersection Turn Volume N No scale KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 7 PLANNING & ENGINEERING Project Only Traffic Volumes 52 N No Scale KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 8 ' PLANNING a ENGINEERING Existing 2014 Plus Ambient Growth Plus Project Traffic Volumes 53 LEGEND Project Location Study Intersection xx Intersection Turn Volume N No Scale KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 8 ' PLANNING a ENGINEERING Existing 2014 Plus Ambient Growth Plus Project Traffic Volumes 53 �KOA CORPORATION V' PLANNING B ENGINEERING As Table 9 shows, the intersection level of service will remain the same as under the existing plus ambient growth scenario. The Project will not create any significant impacts at the study intersection on weekdays. As Table 10 shows, the study roadway segments will continue operating at LOS A during the weekday peak periods. The Project will not trigger any significant impacts at the roadway segments. The Project analyzed in the 2007 study did not cause any LOS values changes at these roadway segments. Traffic impacts are identified if the proposed development will result in a significant change in traffic conditions at a study intersection. A significant impact is typically identified if project -related traffic will cause service levels to deteriorate beyond a threshold limit specified by the overseeing agency. Impacts can also be significant if an intersection is already operating below the poorest acceptable level and project traffic will cause a further decline below a certain threshold. Based on the forecast and level of service results, it is concluded that with a baseline including ambient annual growth, the proposed Project is not expected to significantly impact any of the study locations. Level of service worksheets for this scenario are provided in Appendix E. Traffic Study Update for St. John Fisher Church Page 20 Prepared for St. John Fisher Church JB41 143 February 2,2015 54 KOA CORPORATION PLA, 'N; N,G :� t G :vE -� 1 N r, Table 9 — Existing plus Ambient Growth plus Project Level of Service — Weekday — Study Intersection Study Intersections Existing + Ambient Growth Existing + Ambient Growth + Project Change in VIC AM Peak PM Peak AM Peak PM Peak Signif? V/C LOS V/C LOS V/C LOS V/C I LOS AM Peak PM Peak Daily Crenshaw Blvd & Crest Rd (a] 0.686 B 0.514 A 0.695 B 0.520 A 0.009 0.006 NO [a] Stop -controlled intersection. LOS was calculated based on the 1,200 capacity utilizing the Intersection Capacity Utilization (ICU) Method. Table 10 — Existing plus Ambient Growth plus Project Level of Service — Weekday — Study Roadway Segments Capacity Segment Daily [a] Existing 2014 + Ambient Growth Project Only (Weekday) Existing 2014 + Ambient Growth + Project % Significant Increase Impact ? Weekday VIC LOS Weekday Weekday LOS Daily Daily Crenshaw Blvd north of Crest Rd 127,200 1 15,264 0.120 A 1 84 15,348 0.121 A 0.5% NO 2 Crest Rd west of Crenshaw Blvd 127,200 1 12,186 0.096 A 1 54 12,240 0.096 A 0.4% NO (a] Daily Capacity obtained from "Los Angeles County Traffic Impact Analysis Report Guidelines'. Daily Capacity obtained using 60/40 directional split and by multiplying Peak hour roadway capacity (passenger car per hour) times 24 hours. Traffic Study Update for St. John Fisher Church Page 21 Prepared for St John Fisher Church ]B41 143 February 2, 2015 55 KOA CORPORATION i NANNING & ENGINIMNG 4. Existing plus Ambient Growth plus Cumulative Projects plus Project This section summarizes traffic impacts due to cumulative projects within the vicinity of the study area. Potential cumulative projects traffic impacts and mitigation measures are discussed. KOA Corporation conducted research and obtained a list of cumulative developments anticipated to be constructed within the timeframe of the proposed Project. The year 2022 was selected to be analyzed based on the anticipated buildout date and occupancy of the proposed Project. Figure 9 illustrates the location of the ten cumulative projects. Table I I provides the applied rates to the analysis. Table 12 summarizes the trip generation of the ten cumulative projects included in the forecast. Trip generation estimates are based on rates defined by the Institute of Transportation Engineers (ITE) "Trip Generation Manual — 9th Edition." Table I I — Cumulative Projects — Trip Rates Applied Land Use Daily Total WEEKEND (SUNDAY) AM Peak PM Peak Daily Sunday Mid -Day Total In Out Total In Out Total Total In Out Shopping Center Private School K-12 Residential CondominiunvTownhouse 42.7 2.48 5.81 1 3.44 0.96 62% 38% 3.71 48% 52% 25.24 3.12 49% 51% 0.81 61% 39% 0.17 43% 57% n/a n/a n/a n/a 0.44 17% 83% 0.52 67% 33% 4.84 0.45 49% 51% seniorhousing- attached 1 0.2 34% 66% 0.25 54% 46% 2.84 0.41 50% 50% Table 12 — Cumulative Projects — Trip Generation DU = Dwelling Units, KSF = 1,000 square feet of floor area Trip Generation Rates Source: Institute of Tronsportation Engineers (ITE) 'Trip Generation - 9th Edition". Weekday Daily and Peak Hour trips were used from the arch beach consulting traffic study; Sunday Peak Hour trips were based on Trip Generation - 9th Edition Based on the estimated trip generation summarized in Table 12, cumulative project trips along with the proposed Project trips were assigned onto the roadway network. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 22 JB41143 56 WEEKDAY WEEKEND (SUNDAY) Map ITE Daily AM Peak Hour PM Peak Hour Dally Sunday Peak Hour Project Name Location Land Use lnteaslty Units Total In Out Total In Out Total In Ou[ ID Code Total Total City of Rancho Palos Verdes Lower Hesse Park - Park 18 Acres 29 B 4 4 8 4 4 301 90 45 45 1 Master Plan 29301 Hawthorne Boulevard Tennis Court 3,000 Courts 100 5 8 4 e 113 15 8 7 Subtotal - 129 13 7 6 16 B 8 414 105 53 52 Crestridge Senior 2 5600 Crestridge Road 252 Senior -Housing 60 DU 206 12 4 8 15 8 7 170 25 13 12 Condominium Project Highridge 3 28220 Highridge Road 230 Condominiums 28 DU 163 12 2 10 IS 10 5 136 13 6 7 C ondannjum Project City of Rolling Hills Estates 230 Condominiums 58 DU 337 26 4 22 30 20 10 281 26 13 13 4 627 Deep Valley 627 Deep Valley Drive 820 Commercial 2204 KSF 94 2 1 1 8 4 4 56 7 3 4 Subtotal 431 28 5 23 38 24 14 337 33 16 17 5 5883 Crest 5883 Crest Road 230 Townhomes 4 DU 23 2 0 2 2 1 1 19 2 1 1 6 827 Deep Valley 827 Deep Valley Drive 252 Senior -Housing 16 DU 55. 3 1 2 4 2 2 45 7 4 3 230 Condominiums 75 DU 436 33 6 27 39 26 13 363 34 17 17 7 927 Deep Valley 927 Deep Valley Drive 820 Commercial 2.000 KSF 85 2 1 1 7 3 4 50 6 3 3 Subtotal - - 1 521 1 35 T 28 46 29 17 1 413 40 20 20 230 Condominiums 148 DU 860 65 11 54 77 52 25 716 67 33 34 8 655 Deep Valley 655-683 Deep Valley Drive 820 Commercial 14.200 KSF 606 14 9 5 53 25 28 358 44 22 22 Subtotal - - 1,466 79 20 59 130 77 53 1,074 111 55 56 926438 Crenshaw 26438 Crenshaw Boulevard 536 Classroom Addition 200 Students 496 162 99 63 34 15 19 0 0 0 0 Corner of Hawthorne Peaninsula Shopping 10 Boulevard and Silver Spur 820 Shopping Center 16.583 KSF 708 16 10 6. 62 30 32 419 52 17 35 Center Expansion Road Total 1 4,198 362 ISS 1 207 1 362 1 204 158 1 3,027 1 388 185 203 DU = Dwelling Units, KSF = 1,000 square feet of floor area Trip Generation Rates Source: Institute of Tronsportation Engineers (ITE) 'Trip Generation - 9th Edition". Weekday Daily and Peak Hour trips were used from the arch beach consulting traffic study; Sunday Peak Hour trips were based on Trip Generation - 9th Edition Based on the estimated trip generation summarized in Table 12, cumulative project trips along with the proposed Project trips were assigned onto the roadway network. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 22 JB41143 56 10 O Beech ate Q` ��� L`�ffeyOr S'iI �rS Lr 1?d. a Adak 8 xc� O ar Crest6d 2 e e fWddtecrest vim. Ra, m3 c� 0 \ave. �a a� ea 4?'�fr10' S,� ear as`�e ye: hfs O„ Ln. 31r��e P; h i Bey tea a LEGEND ■ Project Location O N Related Project and Reference Number No Scale KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 9 ' PLANNING & ENGINEERING Location of Cumulative Projects 57 KOA CORPORATION PLANNING & ENGINEERING Existing plus Ambient Growth -plus Cumulative Projects -plus Project Trips Based on the traffic forecast, and adding ambient growth and Project traffic, intersection level of service analysis was conducted at the study locations. As Table 13 shows, the intersection will continue operating at a good level of service (D or better). The Project will not trigger any weekday significant impacts at the study intersection. The Project analyzed in the 2007 study did not cause any LOS values changes at this intersection. As Table 14 shows, the study roadway segments will continue operating at LOS A on the weekday peak periods. The Project will not trigger any significant impacts at the roadway segments. The Project analyzed in the 2007 study did not cause any LOS values changes at these roadway segments. Figure 10 illustrates the resultant existing plus ambient plus cumulative projects plus Project traffic volumes. Based on the forecast and level of service results, it is concluded that with a baseline including existing volumes, ambient annual growth, and cumulative projects the proposed Project is not expected to significantly impact any of the study locations. Level of service worksheets for Existing plus Ambient Growth plus Cumulative Projects plus Project are presented in Appendix F. Traffic Study Update for St. John Fisher Church Page 24 Prepared for St. John Fisher Church JB41 143 February 2, 2015 WP FFKOA CORPORATION t A:v i iU vC: Table 13 — Existing plus Ambient Growth plus Cumulative Projects plus Project Level of Service — Weekday — Study Intersection Study Intersections Existing + Ambient Growth Existing + Ambient Growth + Cumulative Projects + Project Change in VIC AM Peak PM Peak AM Peak PM Peak Signif ? Existing + Ambient Growth + Cumulative Projects + Project % Significant Increase Impact ? VIC LOS VIC LOS V/C LOS VIC LOS AM Peak PM Peak 1 I Crenshaw Blvd & Crest Rd [a] 0.686 B 0.514 A 0.711 C 0.548 A 0.025 0.034 NO [a] Stop -controlled intersection. LOS was calculated based on the 1,200 capacity utilizing the Intersection Capacity Utilization (ICU) Method Table 14 — Existing plus Ambient Growth plus Cumulative Projects plus Project Level of Service — Weekday — Study Roadway Segments Capacity Segment Daily [a] Existing 2014 + Ambient Growth Cumulative Projects + Projct Existing + Ambient Growth + Cumulative Projects + Project % Significant Increase Impact ? Weekday VIC LOS Daily Weekday VIC LOS Daily I Crenshaw Blvd north of Crest Rd 127,200 15,264 0.120 A 834 16,098 0.127 A 5.2% NO 2 1 Crest Rd west of Crenshaw Blvd 127,200 12, 186 0.096 A 1 656 12,842 0.101 A 5.1% NO [a] Daily Capacity obtained from 'Los Angeles County Traffic Impact Analysis Report Guidelines". Daily Capacity obtained using 60/40 directional split and by multiplying Peak hour roadway capacity (passenger car per hour) times 24 hours. Traffic Study Update for St. John Fisher Church Page 25 Prepared for St. John Fisher Church JB41 143 February 2, 2015 59 $gECh L'°Iley©f ul f2d. X44 Crestrid� Weekday AM Peak Hour 97 M+ddlecre t �p 3¢ 358 I I 1178 o 622 115 ¢ 60- 1 -58 107 6�7ir crm 197 ry° e4 eekday PM_Peak_Hc�t�r NS� 130 478 1116 rf CYr 328 t_89 30- -35 3 rn 391 t 95 t Gtr a LEGEND Project Location N In Study Intersection xx Intersection Turn Volume No Scale KOA CORPORATION St. John Fisher Church - Phase II - Traffic Impact Study Figure 10 PLANNING, a ENGINEERING Existing 2014 +Ambient Growth + Cum. Projects + Project Peak Hour Traffic Volumes KOA CORPORATION PLANNING & ENGINEERING S. Congestion Management Plan Conformance This section demonstrates the ways in which this traffic study was prepared to be in conformance with the procedures mandated by the County of Los Angeles Congestion Management Program. The Congestion Management Program (CMP) was created statewide because of Proposition I I I and was implemented locally by the Los Angeles County Metropolitan Transportation Authority (LACMTA). The CMP for Los Angeles County requires that the traffic impact of individual development projects of potentially regional significance be analyzed. A specific system of arterial roadways plus all freeways comprises the CMP system. Per CMP Transportation Impact Analysis (TIA) Guidelines, a traffic impact analysis is conducted where: At CMP arterial monitoring intersections, including freeway on -ramps or off -ramps, where the proposed project will add 50 or more vehicle trips during either AM or PM weekday peak hours. • At CMP mainline freeway -monitoring locations, where the project will add 150 or more trips, in either direction, during the either the AM or PM weekday peak hours. The nearest CMP arterial monitoring intersection to the project site is Pacific Coast Highway at Crenshaw Boulevard. Based on the Project trip generation and the distance of these CMP routes from the study intersections, it is not expected that 50 or more new trips per hour would be added to these locations. Therefore, no further analysis of potential CMP impacts is required. The nearest CMP mainline freeway -monitoring location to the project site is on I -I 10 at Wilmington south of C Street. Based on the trip distribution and traffic assignment presented, the proposed project is primarily local traffic rather than regional traffic. The proposed project is expected to add less than 150 new trips per hour to any freeway segments near the project site since the project generates local/neighborhood trips than regional trips. Therefore, no further analysis of CMP freeway monitoring stations is required. Traffic Study Update for St.John Fisher Church Page 27 Prepared for St. John Fisher Church JB41143 February 2, 2015 61 KOA CORPORATION PLANNING & ENGINEERING 6. Summary and Project Recommendations The following summarizes the traffic study results, findings and conclusions: • Under existing 2014 conditions, all of the three study locations are operating at LOS D or better during both peak hours under weekday and Sunday conditions. LOS values have improved, versus those calculated for the 2007 traffic study, due to diminished traffic volumes in the area. • An ambient growth rate of 0.5% per year was applied to reflect regional traffic growth in the study area. • Under existing plus ambient growth conditions, all of the three study locations will continue operating at LOS D or better during both peak hours under weekday and Sunday conditions. • The proposed Project is estimated to generate: 0 148 weekday trips 0 27 weekday AM peak hour trips 0 27 weekday PM peak hour trips • Under existing plus ambient plus Project conditions, traffic from the proposed Project is not expected to significantly impact any of the study locations. • Under existing plus ambient plus cumulative projects conditions, ten cumulative projects have been identified within the vicinity of the Project site. • Under existing plus ambient plus cumulative projects plus Project conditions (which includes the St. John Fisher Project), traffic from the proposed cumulative projects is not expected to significantly impact any of the study locations. Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Page 28 JB41143 HOA CORPORATION t' PLANNING & ENGINEERING APPENDIX A Study Scoping Document Traffic Study Update for St.John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Appendices JB41143 63 TRAFFIC STUDY SCOPING DOCUMENT St. John Fisher Church, 5448 Crest Road, Rancho Palos Verdes October 2, 2014 — v3 This scoping document acknowledges the City of Rancho Palos Verdes requirements of traffic impact analysis for the following project: Project Address: 5448 Crest Road Project Description St. John Fisher Church has completed the first phase of improvements to its facilities, which had been analyzed in a traffic study effort by KOA that culminated in a final deliverable in December of 2007. As part of the review process for the CUP extension of the previous approved phase two project scope, the City has requested an updated traffic study that accomplishes two objectives: Determine area traffic conditions with project phase one operations, and compare to estimated conditions of 2007 study. Document the project phase two improvements, the trip generation potential of those improvements, and summarize the overall project traffic impacts. The previously -approved phase two of the church master plan would provide for replacement of educational and site ancillary facilities including the following: - Art room School library • Preschool facility Music offices • Remodeling of existing offices into meeting rooms Administrative offices All of these facilities would serve current on-site operations, other than the preschool. The preschool is a proposed use and would serve up to 40 children (20 children in a morning program, and 20 children under a separate afternoon program), on weekdays only. The project will be analyzed with a 40 -student program for both peak and daily conditions, in order to be consistent with the 2007 study. The proposed meeting rooms would only serve existing church operations, would be used by existing church members and ministries, and would also not be available to outside groups. The church also does not plan to create new programs due to the pending completion of the meeting rooms. The site plan is included in Attachment A. Geogr-apl rjc Distribution: The same project trip distribution used in the 2007 KOA traffic impact study will be applied to this analysis, as applicable to new generated trips. The project study area is illustrated on the figure in Attachment B. T! -la Generation Calculations The trip generation table is provided below, for the preschool serving 40 children. It is assumed that some percent of vehicle trips to and from the overall school facilities on the site would be parents with children in both the preschool program and the grade school program. A 15 percent reduction in trips was taken for this purpose, as an estimate of the proportion of vehicle trips that would apply to this situation. TRAFFIC STUDY SCOPING DOCUMENT Page 1 J841143 TRAFFIC STUDY SCOPING DOCUMENT St. John Fisher Church, 5448 Crest Road, Rancho Palos Verdes October 2, 2014 — v3 TRIP GENERATION FOR APPLICABLE PHASE 2 USES (PROPOSED PRESCHOOL USE) The distribution of the new trips generated by the proposed preschool use will use the methodology applied in the 2007 KOA traffic impact study. Project Build -out Year: 2022 Ambient Growth Rate: 0.5 percent per year, consistent with 2007 study Area/Cumulative Projects: The list of 10 pending area development projects provided by the City of Rancho Palos Verdes in the letter of September 16, 2014 will define the cumulative project list. Any associated trip generation will be included in the future pre -project and post -project analyses. Study Area The study area locations are illustrated in Attachment B. This figure is from the 2007 KOA traffic impact study report and the study area will remain unchanged. The following is a list of the study intersections and their traffic count sources: • Crenshaw Boulevard & Crest Road Study Roadway Segment Locations • Crenshaw Boulevard, north of Crest Road • Crest Road, west of Crenshaw Boulevard Traffic Count Details Traffic counts are complete and are currently being compiled, as the City letter of September 16, 2014 that responded to the initial scoping document did not indicate any need to modify the study area. The new intersections counts at the study intersection have been conducted from 7:00 a.m. to 9:00 a.m. and from 4:00 p.m. to 6:00 p.m. on a weekday (Thursday) and from 8:00 a.m. to 12:00 p.m. on a Sunday. The roadway segment counts have been conducted on one weekday (Thursday) for a 24-hour period and on one Sunday for a 24-hour period. Analysis will be based on the County of Los Angeles traffic study guidelines thresholds for study intersection volume -to -capacity (v/c) impacts and post -project level of service (LOS) values, and percentage increases in traffic at the study roadway segments. TRAFFIC STUDY SCOPING DOCUMENT Page 2 J841143 65 WEEKDAY ITE Daily AM Peak PM Peak # I Land Use Type Method I Intensity IType Total Total In Out Total In Out 565 JDay Care Center (Adj Streets, 7-9A, 4-6P)l Linear Rate 1 40.000 IStudents 179 32 17 15 33 15 17 Reduction of 15% - Estimated parent drivers with students in existing grade school program -27 -5 -3 -2 -5 -2 -3 TOTAL 1 152 27 14 13 1 28 13 15 The distribution of the new trips generated by the proposed preschool use will use the methodology applied in the 2007 KOA traffic impact study. Project Build -out Year: 2022 Ambient Growth Rate: 0.5 percent per year, consistent with 2007 study Area/Cumulative Projects: The list of 10 pending area development projects provided by the City of Rancho Palos Verdes in the letter of September 16, 2014 will define the cumulative project list. Any associated trip generation will be included in the future pre -project and post -project analyses. Study Area The study area locations are illustrated in Attachment B. This figure is from the 2007 KOA traffic impact study report and the study area will remain unchanged. The following is a list of the study intersections and their traffic count sources: • Crenshaw Boulevard & Crest Road Study Roadway Segment Locations • Crenshaw Boulevard, north of Crest Road • Crest Road, west of Crenshaw Boulevard Traffic Count Details Traffic counts are complete and are currently being compiled, as the City letter of September 16, 2014 that responded to the initial scoping document did not indicate any need to modify the study area. The new intersections counts at the study intersection have been conducted from 7:00 a.m. to 9:00 a.m. and from 4:00 p.m. to 6:00 p.m. on a weekday (Thursday) and from 8:00 a.m. to 12:00 p.m. on a Sunday. The roadway segment counts have been conducted on one weekday (Thursday) for a 24-hour period and on one Sunday for a 24-hour period. Analysis will be based on the County of Los Angeles traffic study guidelines thresholds for study intersection volume -to -capacity (v/c) impacts and post -project level of service (LOS) values, and percentage increases in traffic at the study roadway segments. TRAFFIC STUDY SCOPING DOCUMENT Page 2 J841143 65 TRAFFIC STUDY SCOPING DOCUMENT St. John Fisher Church, 5448 Crest Road, Rancho Palos Verdes October 2, 2014 — v3 Site Monitoring We have generally monitored peak church activity on one weekend, over the course of a two-hour Sunday morning period, to understand traffic circulation issues at the existing site. Site parking demand counts will not be conducted. Contact Information Consultant: Name KOA Corporation Address 1 100 Corporate Center Dr., Suite 201 Monterey Park, CA 91754-7642 Brian A. Marchetti, AICP Telephone: (323) 260-4703 TRAFFIC STUDY SCOPING DOCUMENT Client: St. John Fisher Church 5448 Crest Road Rancho Palos Verdes, CA 90275 Gayle Plecha, Parish Administrator (562) 597-8760 Page 3 JB41143 •i TRAFFIC STUDY SCOPING DOCUMENT St. John Fisher Church, 5448 Crest Road, Rancho Palos Verdes October 2, 2014 — A ATTACHMENT A PROJECT SITE PLAN 71 Ot. At,- GNnJ iss<n ren- FiS' • 3 ',1 y yak r Rb045 i.3% HALL - `1 _ - � // Y �:.��•t�atl ,..�.C� �T ;rte i � --,Tr—`. -�.. _. - !� %it kl ACIIVIIY;CENHR In." In ON i 14 TRAFFIC STUDY SCOPING DOCUMENT Attachments J841143 67 TRAFFIC STUDY SCOPING DOCUMENT St. John Fisher Church, 5448 Crest Road, Rancho Palos Verdes October 2, 2014 — v3 ATTACHMENT13 PROJECT STUDY AREA LEGEND ■ Project Location Study Intemectlon N Study Roadway Segment No 6cele KOA CORPORATIONS t. John Fisher Church - Traffic Impact Study Figure 1 a;,ninic a ewGlntlrv+v Study Area TRAFFIC STUDY SCOPING DOCUMENT Attachments JB41143 m• KOA CORPORATION PLANNING & ENGINEERING APPENDIX BI Traffic Count Data — Study Intersections Traffic Study Update for St. John Fisher Church Prepared for St. John Fisher Church February 2, 2015 Appendices JB41143 •! Intersection Turning Movement Prepared by: National Data & Surveying Services Project ID: 14-5614-001 Day: Thursday City: Rancho Palos Verdes Date: 10/2/2014 AM NS/EW Streets:Cans?lowIM0 Crcnshaw tt d CmtAtd Crest Rd TOTAL VOLUMES :I 95 308 4 I 228 149 556 I 1022 90 128 I 4 86 180 1 2850 APPROACH Ws : 23.34% 75.68% 0.98% 24.44% 15.97% 59.59% 82.42% 7.26% 10.32% 1.48% 31.85% 66.67°/0 PEAK HR START TIME ; 730 AN I TOTAL PEAK HR VOL : 62 185- 2 1 161 49 313 1 577 55 101 1 3 53 105 1706 PEAK HR FACTOR : 0.582 0.722 0.841 0.759 0.830 CONTROL : 4 -Way Stop fff NL NT NR SL ST SR EL ET ER WL WT WR TOTAL LANES: 1 1 0 1 1.5 1.5 1.5 0.5 1 0 1 1 7:00 AM 4 15 0 10 15 52 82 7 5 1 5 9 205 7:15 AM 6 29 0 22 8 77 120 13 6 0 9 17 307 7:30 AM 16 43 0 48 29 118 160 10 48 0 13 29 514 7:45 AM 20 87 0 50 23 78 156 8 35 0 15 38 510 8:00 AM 17 31 0 39 22 58 124 13 10 0 10 21 345 8:15 AM 9 24 2 24 15 59 137 24 8 3 15 17 337 8:30 AM 15 42 0 18 20 64 117 8 13 0 10 24 331 8:45 AM 8 37 2 17 17 50 126 7 3 0 9 25 301 All NT ND I CI CT CO I M FT FD I \All 5Arr WD I TnTa1 TOTAL VOLUMES :I 95 308 4 I 228 149 556 I 1022 90 128 I 4 86 180 1 2850 APPROACH Ws : 23.34% 75.68% 0.98% 24.44% 15.97% 59.59% 82.42% 7.26% 10.32% 1.48% 31.85% 66.67°/0 PEAK HR START TIME ; 730 AN I TOTAL PEAK HR VOL : 62 185- 2 1 161 49 313 1 577 55 101 1 3 53 105 1706 PEAK HR FACTOR : 0.582 0.722 0.841 0.759 0.830 CONTROL : 4 -Way Stop fff Intersection Turning Movement Prepared by: National Data & Surveying Services Project ID: 14-5614-001 10 21 Day: Thursday City: Rancho Palos Verdes 25 102 Date: 10/2/2014 9 PM 1 6 NS/EW Streets: Crenshaw Blvd F Crenshaw Blvd 6 Crest Rd Cre<,, Rd 28 NORTHBOUND SOUTHBOUND EASTBOUND WESTBOUND NL NT NR SL ST SR EL ET ER WL WT WR TOTAL LANES: 1 1 0 1 1.5 1.5 1.5 0.5 1 0 1 1 4:00 PM 10 21 0 27 25 102 80 9 6 1 6 27 314 4:15 PM 6 27 0 28 16 102 60 5 9 0 6 18 277 4:30 PM 10 27 0 22 33 106 75 7 9 0 5 19 313 4:45 PM 8 14 0 29 23 102 79 6 9 1 11 23 305 5:00 PM 5 21 1 31 35 122 72 4 13 0 9 17 330 5:15 PM 4 25 0 21 30 109 61 9 5 1 6 15 286 5:30 PM 5 17 0 20 32 120 69 11 6 1 3 16 300 5:45 PM 9 35 0 29 25 101 66 12 4 0 8 16 305 NL NT NR SL ST SR EL ET ER WL WT WR TOTAL TOTAL VOLUMES : 57 187 1 207 219 864 562 63 61 4 54 151 2430 APPROACH WS : 23.27% 76.33% 0.41% 16.05% 16.98% 66.98% 81.92% 9.18% 8.89% 1.91% 25.84% 72.25% PEAK HR START TINE : 430 PMl'OTAL PEAR HR VOL : 27 87 1 1.03 121 439 1 217 26 -, 2 31 74 7c34 PEAK HR FACTOR : 0.777 0.882 0.928 1 0.761 6.935 CONTROL : 4 -Way Stop 71 MEMORANDUM I RANCHO PALOS VERDES TO: TRAFFIC SAFETY COMMITTEE FROM: MICHAEL THRONE, DIRECTOR OF PUBLIC WORKS BY: MELISSA COUNTRYMAN, P.E., T.E., SENIOR ENGINEER DATE: APRIL 27, 2015 SUBJECT: SAINT JOHN FISHER CHURCH TRAFFIC STUDY UPDATE FOR PHASE II REPORT RECOMMENDATION Approve the Traffic Study Update Report for the St. John Fisher Church Phase II project. BACKGROUND The St. John Fisher Church, located at the intersection of Crest Road and Crenshaw Boulevard, has completed its first phase of improvements to its facilities and would now like to begin the second phase of improvements, which had been previously approved by the City. Due to the time that had elapsed since the initial traffic study had been performed, the City requested that the applicant provide an updated traffic study that compares the existing traffic conditions (now that the phase one improvements have been completed) to those estimated in the original traffic study performed in 2007, as well as to revisit the estimated traffic impacts related to the planned phase two improvements. The phase two improvements include an art room, school library, preschool facility, music offices, remodeling of existing offices into meeting rooms, and administrative offices. All of these phase two improvements would serve current on-site operations, with the exception of the pre-school facility. Therefore, the potential traffic impacts of the pre- school facility were evaluated in this study. DISCUSSION The traffic study approach was kept consistent to that used in 2007 so that an "apples -to - apples" comparison could be made. The traffic study methods also utilize the Institute of Transportation Engineers' Trip Generation rates and Los Angeles County accepted methodologies. The analysis included collecting traffic count data during peak travel times on a weekday and a Sunday at the same intersection and roadway segments as had been done in the prior study. Furthermore, three scenarios were evaluated: the existing 2014 traffic conditions, the existing conditions plus ambient growth and project conditions, and the existing conditions plus ambient growth plus the project conditions and cumulative projects. Ambient growth of traffic was forecasted for the year 2022, since that is when it is anticipated that the phase two improvements would be complete. The list of cumulative 72 Saint John Fisher Church Traffic Study Update for Phase II Report April 27, 2015 Page 2 projects considered consists of ten nearby planned projects within the City of Rancho Palos Verdes, as well as the City of Rolling Hills Estates, that are anticipated to generate additional trips in the area. Taking all of these factors into account, the study found that there will not be any significant traffic impacts to the study locations caused by the phase two improvements at the St. John Fisher Church. CONCLUSION Staff recommends that this traffic study report be approved. Upon approval by the Traffic Safety Committee, the application for the phase two of the project will then proceed to the rest of the process with the City Council. Attachment: Traffic Study Update for St. John Fisher Church prepared by KOA Corporation End of report 73 Resolution No. 2009-09 (Original MND/MMP) 74 RESOLUTION NO. 2009-09 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES ADOPTING A MITIGATED NEGATIVE DECLARATION AND A MITIGATION MONITORING PROGRAM PURSUANT TO THE CALIFORNIA ENVIRONMENTAL QUALITY ACT FOR CASE NO. ZON2007-00492 (CONDITIONAL USE PERMIT #96 — REVISION "D", GRADING PERMIT, MINOR EXCEPTION PERMIT, SIGN PERMIT, AND ENVIRONMENTAL ASSESSMENT), FOR PROPERTY AT 5448 CREST ROAD LOCATED AT THE SOUTHEAST CORNER OF CREST ROAD AND HAWTHORNE BOULEVARD. WHEREAS, on October 5, 2007, Hyndman and Hyndman, representing St. John Fisher Church and School, submitted Case No. ZON2007-00492, applications for a Conditional Use Permit #96 — Revision "D", Grading Permit, Minor Exception Permit, Sign Permit and Environmental Assessment, for the subject property at 5448 Crest Road (referred to collectively as "the Project"); and, WHEREAS, on October 29, 2007, the Project was deemed incomplete by Staff pending the submittal of additional information on the project plans and review and approval from the Fire Department, City Traffic Consultant, City Geologist and City's National Pollution Discharge Elimination System (NPDES) Consultant; and, WHEREAS, on April 29, 2008, upon submittal of all required information, the Project was deemed complete by Staff; and, WHEREAS, pursuant to the provisions of the California Environmental Quality Act, Public Resources Code Sections 21000 et. seq. ("CEQA"), the State's CEQA Guidelines, California Code of Regulations, Title 14, Section 15000 et. seq., the City's Local CEQA Guidelines, and Government Code Section 65962.5(f) (Hazardous Waste and Substances Statement), the City of Rancho Palos Verdes prepared an Initial Study and determined that, with appropriate mitigation, there is no substantial evidence that the Project would result in a significant adverse effect upon the environment and, therefore, a Mitigated Negative Declaration has been prepared and notice of same was given in the manner required by law; and, WHEREAS, after notice was issued pursuant to the requirements of the Rancho Palos Verdes Development Code, the Planning Commission held a duly noticed public hearing on June 24, 2008, at which time all interested parties were given an opportunity to be heard and present evidence; and, WHEREAS, on June 24, 2008, the Planning Commission continued the public hearing to the July 22, 2008 Planning Commission meeting to allow time for the applicant to address concerns about the height of the proposed sanctuary steeple and provide clarification on the methodology used to determine the number of parking spaces that will be provided on site; and, 75 WHEREAS, on July 2, 2008, the applicant submitted modified plans and updated information to Staff which included the following modifications: 1) a reduction in height of the proposed steeple by 14'-0", 2) an overall reduction in height of the main sanctuary building by up to 6'-0", 3) elimination of the stepped roof lines along the south side of the sanctuary, 4) a reduction in the footprint of the sanctuary by 1,400 square feet, 5) the addition of a 900 square foot basement beneath the sanctuary to accommodate mechanical equipment, 6) an increase in the sanctuary street side yard setbacks by 14'-0" along Crest Road, 7) an increase in the sanctuary street side yard setback by 17'-0" along Crenshaw Boulevard and 8) a reduction in the footprint of the administrative building by 1,480 square feet; and, WHEREAS, the Planning Commission held a duly noticed public hearing on July 22, 2008, at which time all interested parties were given an opportunity to be heard and present evidence; and, WHEREAS, on July 22, 2008, the Planning Commission continued the public hearing to the September 23, 2008 Planning Commission meeting to allow time for the applicant to consider providing a sound study to determine if any significant impacts would result from the proposed bells, a shadow study to determine if the height and/or scale of the sanctuary and steeple would create any significant impacts to surrounding properties, a copy of St. John Fisher's recent parking counts, further clarification of the applicant's parking analysis and whether the applicant is willing to provide additional parking on days when the demand for parking is the greatest due to activities at the site; and, WHEREAS, on September 23, 2008, the Planning Commission held a duly noticed public hearing, at which time all interested parties were given an opportunity to be heard and present evidence; and, WHEREAS, on September 23, 2008, the Planning Commission conceptually approved the Project and directed Staff to bring back the appropriate resolutions with Conditions of Approval; and, WHEREAS, on October 14, 2008, the Planning Commission adopted PC Resolution No. 2008-34, adopting a Mitigated Negative Declaration and adopting a Mitigation Monitoring Program and PC Resolution No. 2008-35, approving the St. John Fisher Master Plan, as conditioned; and, WHEREAS, on October 29, 2008, Case No. ZON2007-00492 was appealed to the City Council, including issues with the Environmental Assessment and CUP findings, a request to analyze Neighborhood Compatibility, impacts due to the size of the sanctuary, inadequate parking, noise impacts due to the use of a gymnasium and the ringing of the proposed electronic bells, the lighting of the sanctuary tower and steeple, concerns with removal of certain mature trees and to require additional setbacks around the sanctuary (collectively referred to as the "Appeal"); and, 1111089.2 Resolution No, 2009-09 Page 2 of 9 76 WHEREAS, On November 1, 2008, a Notice of the public hearing on the Appeal was published in the Peninsula News; the City also sent notice of the Appeal hearing to the property owners who reside within 500 feet of the subject property, to all persons listed on the City's Interested Parties List, and to all St. John Fisher list -serve subscribers; and, WHEREAS, on November 16, 2008, the City Council opened the public hearing on the Appeal, and after hearing the public testimony and considering the information presented in the Staff Report, the City Council adjourned the public hearing to a site visit at the St. John Fisher property to beheld on November 22, 2008, to allow the City Council to walk throughout the subject property and surrounding neighborhood to assess the project and its potential impacts; and, WHEREAS, on November 22, 2008, the City Council conducted the continued public hearing, which was a site visit at the St. John Fisher property, and at the conclusion of the site visit, the City Council continued the public hearing to December 16, 2008; and, WHEREAS, on December 16, 2008, the City Council conducted the continued public hearing on the Appeal and heard and considered all of the additional materials that have been submitted after the first public hearing and all of the additional testimony that was presented; NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES DOES HEREBY FIND, DETERMINE, AND RESOLVE AS FOLLOWS: Section 1: The City Council has independently reviewed and considered the proposed Mitigated Negative Declaration ("MND"), all of the public comments, both written and oral, about the proposed MND, and all of the other evidence that was presented to the City Council, including the staff reports prepared for the City Council and the Planning Commission. For the reasons discussed below, the City Council finds that the MND was prepared in the manner required by law and that there is no substantial evidence in the record of proceedings that, with the imposition of the proposed mitigation measures, the approval of the Project would result in a significant adverse effect upon the environment that would require the preparation of an environmental impact report ("EIR"). A. The proposed Project primarily consists of the construction of new structures and the remodel of some existing structures that are present on the site, to accommodate a church, school, pre-school and related administrative activities. The site was developed with a church, school, parking lot, and other related uses prior to the incorporation of the City. The only proposed new use on the site is a two -room pre-school. A new 17,000 square foot sanctuary is proposed, and the existing sanctuary will be converted into a gymnasium and multi-purpose room to accommodate school and church -related activities. The new sanctuary will be located on the portion of the site that abuts Crest Road to the north and Crenshaw Boulevard to the west, which is approximately seventy feet wide 1111089.2 Resolution No. 2009-09 Page 3 of 9 77 including public sidewalks on both sides of the street. The closest residences to the proposed new sanctuary are located in the Island View subdivision, which is on the opposite side of Crenshaw Boulevard. B. Staff prepared an Initial Study for the proposed project pursuant to CEQA. The results of the Initial Study determined that the proposed Project on this developed site will not result in or create any significant adverse environmental impacts, and will have a less than significant impact to Agricultural Resources, Biological Resources, Cultural Resources, Hazards and Hazardous Materials, Land Use and Planning, Mineral Resources, Population and Housing, Public Services, Recreation, Transportation and/or Traffic, and Utilities and Service Systems. However, the Initial Study for the Project identified potentially significant impacts to Aesthetics, Air Quality, Geology and Soils, Hydrology and Water Quality, and Noise. After preparing the Initial Study, Staff determined that all of the potentially significant impacts could be mitigated to a less than significant level with the imposition of the mitigation measures identified in the MND. As such, Staff determined that a mitigated negative declaration was the appropriate CEQA document for analyzing and disclosing the proposed Project's potential significant environmental impacts. The City Council has independently reviewed and considered Staffs determination and the Planning Commission's decision, which confirmed Staff's findings, and has reached the same conclusion. C. Public Resources Code § 21080(c) states that an EIR is not required if the initial study demonstrates that no significant impacts will occur as a result of a proposed project, which cannot be mitigated to an insignificant level by the imposition of mitigation measures. As stated in Public Resources Code § 21064.5, a Mitigated Negative Declaration: "means a negative declaration prepared for a project when the initial study has identified potentially significant effects on the environment, but (1) revisions in the project plans or proposals made by, or agreed to by, the applicant before the proposed negative declaration and initial study are released for public review would avoid the effects or mitigate the effects to a point where clearly no significant effect on the environment would occur, and (2) there is no substantial evidence in light of the whole record before the public agency that the project, as revised, may have a significant effect on the environment." D. An EIR must be prepared if a lead agency is presented with a fair argument, based on substantial evidence, that the project may have a significant environmental impact (CEQA Guidelines § 15064.f.1). Substantial evidence is defined as: "(a) ... enough relevant information and reasonable inferences from this information that a fair argument can be made to support a conclusion, even though other conclusions might also be reached. Whether a fair argument can be made that the project may have a significant effect on the environment is to be determined by examining the whole record before the lead agency. Argument, speculation, unsubstantiated opinion or narrative, evidence which is clearly erroneous or inaccurate, or evidence of social or economic impacts which do not contribute to or are not caused by physical impacts on the environment does not constitute substantial evidence, [and] (b) Substantial evidence shall include facts, reasonable 1111089.2 Resolution No. 2009-09 Page 4 of 9 WR assumptions predicated upon facts, and expert opinion supported by facts" (CEQA Guidelines § 15384). Additionally, according to Public Resources Code § 21082.2(b): "the existence of public controversy over the environmental effects of a project shall not require preparation of an environmental impact report if there is no substantial evidence in light of the whole record before the lead agency that the project may have a significant effect on the environment." E. Several residents have testified that it is their opinion that the proposed sanctuary, which was reduced in height, size, scale and setback farther from the property line by the Planning Commission, will cause a significant impact due to its bulk and mass. In response to those concerns, a professional consultant conducted a study to ascertain if the proposed sanctuary and steeple will cast shadows upon adjacent residential properties. The shadow study concluded that no portion of the proposed sanctuary building would create shadows that affect any residential properties. The City Council finds that the distance between the proposed sanctuary and the nearest residences in the Island View tract, with Crenshaw Boulevard located in between, along with the study that was conducted, negates the opinions of the residents, which are not supported by substantial evidence, that a significant environmental impact will be caused by the new structure. Although opinions have been expressed by some residents that the proposed sanctuary will be visible from surrounding areas thus causing an aesthetic impact, the City Council finds that mere visibility from off-site locations does not constitute a significant environmental impact related to aesthetics. Further, there is not substantial evidence in the record to support the opinion and argument of the residents regarding alleged aesthetic impacts. Accordingly, the City Council finds that the Initial Study and Mitigated Negative Declaration have correctly concluded that the bulk and mass of the proposed sanctuary and steeple will not cause a significant environmental impact that requires the preparation of an EIR, because any environmental impacts from the proposed sanctuary have been mitigated to an insignificant level by the imposition of mitigation measures limiting the height of the proposed structure and requiring it to be located 14'-0" feet from the Crest Road, north street side property line and 17'-0" from the Crenshaw Boulevard, west street side property line. F. The MND is based upon a Traffic Study and a Parking Analysis, which were prepared by professional consultants, and both of which conclude that there would be no significant adverse traffic or parking impacts as a result of the proposed Project. 1. Parking. The St. John Fisher Master Plan will have two main operating functions: 1) an elementary school that operates Monday through Friday and, 2) a sanctuary with multiple masses conducted primarily on Saturdays and Sundays and intermittent small masses throughout the week. In addition to the two primary operating functions of the St. John Fisher property, groups utilize the St. John Fisher facilities after primary school hours to conduct meetings or religious education classes. Due to the fact St. John Fisher is a multi - 1111089.2 Resolution No. 2009-09 Page 5 of 9 WE use property, Section 17.50.030(8) of the City's Development Code is applicable to the proposed project. This required the applicant to provide a detailed parking analysis that examined the parking demands for each component of the entire St. John Fisher Master Plan so that adequate parking is provided on-site and that there will be no significant impacts upon surrounding residential areas. The primary daytime uses of the St. John Fisher property that were analyzed in the parking study are the operation of an elementary school, new preschool, administration building and the new gymnasium between Monday and Friday and the operation of a church and religious education classes on Saturdays and Sundays. In addition to these primary uses, Staff identified additional ancillary uses within the St. John Fisher property that were also included in the parking analysis. These ancillary uses include the rectory (single-family residence), new library and the assembly spaces within the Barrett Hall, Fireside Room and Multi-purpose room. Staff required that the Applicant include these uses in a parking analysis to ensure that adequate on-site parking will be provided at all times. The Applicant proposed to provide 331 parking spaces along the southern portion of the subject property to meet the "worst-case" parking demand scenario that was identified by the detailed analysis that was prepared by the Applicant, which was reviewed and approved by the City's Traffic Consultant. The parking analysis determined that, in the worst-case scenario (regular Sundays between 10 AM and Noon) and based on the proposed operation of the St. John Fisher facilities, there was a demand for 331 parking spaces every Sunday between 10 AM and Noon. This worst-case scenario assumed the new sanctuary is filled to capacity (870 persons) and used in conjunction with religious education classes and the rectory. The primary weekday use(s) of the St. John Fisher facilities that are occupied by children enrolled in the school or persons working for the school during regular school hours, Monday through Friday, will be the elementary school, the preschool and the administrative offices. Because the St. John Fisher School is a member of the Catholic Youth Organization and participates in various sport leagues available to the children who are enrolled in the school and the youth organization, Staff also determined that the gymnasium was a primary daytime use Monday through Friday, during school hours. The Development Code requires the following parking for these primary daytime uses: Elementary School = 18 spaces Preschool = 8 spaces Administrative Offices = 37 spaces Gymnasium = 121 spaces TOTAL = 184 spaces The Applicant is proposing 331 parking spaces on site, leaving a surplus of 147 additional parking spaces along the southern portion of the subject property for use during 1111089.2 Resolution No. 2009-09 Page 6 of 9 .0 regular school hours. Based upon the parking analysis that was prepared by the Applicant and reviewed by the City's Traffic Consultant, in conjunction with the specifically designated classroom uses for religious education, the Applicant meets the requirements of Section 17.50.030 of the Development Code for joint -use and common parking facilities for both weekday and weekend uses. Thus, the Applicant's parking analysis demonstrated that the parking needs for all of the uses that would be conducted concurrently were being satisfied by the Applicant's parking plan. In addition, the City Council incorporated the requirement imposed by the Planning Commission that the applicant enter into an agreement with the owner of the adjacent Daughter's of Mary and Joseph property to allow St. John Fisher to use 50% of the parking (45 spaces) at Daughter's of Mary and Joseph site for overflow parking on Christmas, Easter Sunday and during the construction period. In addition, the 23 surplus seasonal/peak parking spaces located south of Barrett Hall will be provided for overflow parking. Accordingly, with ample parking being provided on-site, pursuant to the mitigation measures and conditions of approval, there will be no significant adverse impact on the environment arising from parking related to activities conducted on the site that cannot be mitigated to a level of insignificance. Accordingly, the preparation of an EIR is not required to address this issue. 2. Traffic. The Applicant had a licensed traffic engineer prepare an analysis of the impacts on traffic that would be generated by the proposed project. The traffic study, which was reviewed and approved by the City's Traffic Engineer, concluded that the addition of structures on the property, which would accommodate existing uses, plus the addition of the new two -room pre-school, would not cause any significant impacts upon traffic. In addition, the consultant also reviewed the proposed Project along with other projects in the vicinity to determine if there would be any cumulative impacts upon traffic in the area, when other projects are considered, and again determined that the Project would not contribute to cumulative significant environmental impacts upon traffic in the area. The City's traffic consultant reviewed a supplemental cumulative traffic study and agreed with these conclusions. Accordingly, there is no substantial evidence in the record that the Project will cause a significant adverse impact on the environment due to individual or cumulative impacts on traffic. G. The initial study contained a Staff analysis, which concluded that any potential impacts to aesthetics, air quality, geology, hydrology, noise, and water quality could be mitigated to a less than significant level with the incorporation of appropriate mitigation measures into the project. During the MND's formal comment period, as well as throughout the entire public hearing process before the Planning Commission and City Council, there was no substantial evidence submitted to suggest that the proposed Project, as mitigated, would have a significant adverse effect on the environment. On the contrary, additional evidence was submitted to affirm the MND's conclusions that, as conditioned, the proposed Project would not have a significant effect on the environment. Specifically, a sound study, which was prepared by a professional consultant, concluded that noise 1111089.2 Resolution No. 2009-09 Page 7 of 9 51 impacts from the proposed carillon bell would not be significant because the bells would not exceed 50 db, when measured at the property lines, which is well below the ambient noise level that occurs from constant daily traffic at the north and west property lines, adjacent to Crest Road and Crenshaw Boulevard. In addition, mitigation measures have been imposed that will regulate the times, duration and loudness of the proposed bells. Thus, the addition of the carillon bells will not create noise that will have a significant environmental impact. Accordingly, the City Council finds that an EIR also is not required to address this issue. H. Lighting Under the "aesthetics" section of the Initial Study, the Project was identified to potentially result in an aesthetic impact with regard to the creation of a new source of substantial light or glare, which could adversely affect day or nighttime views in the area. The Initial Study identified components of the photometric site lighting plan to include new light standards within the new parking lot and exterior light fixtures around the new sanctuary. Based on the initial study, mitigation measures were incorporated into the Project to reduce the lighting impacts by requiring shields on lighting fixtures, requiring an inspection to insure no spillover onto adjacent properties and providing a trial period of six months to assess all lighting impacts. The six-month review period allows the City to require additional screening, reduction in intensity of any light or the incorporation of time -restrictions for exterior lighting that is determined to be excessively bright after installation. In addition, conditions of approval also have been imposed to regulate the brightness of, and limit the hours when, the lights that will illuminate the steeple and cross can be turned on. The City Council has reviewed this issue and determined that incorporation of these mitigation measures will result in less than significant impacts from the proposed lights. Section 2: There are no sensitive natural habitat areas on the subject site, which is currently developed and being used as a church and school. Therefore, the Project will have no individual or cumulative adverse impacts upon resources, as defined in Section 711.2 of the State Fish and Game Code. Section 3: Based on the foregoing, the City Council finds, based upon its independent judgment and analysis of the proposed Mitigated Negative Declaration and the record of this matter, that with the imposition of the mitigation measures that have been proposed, which address the potential significant impacts of the project upon Aesthetics, Air Quality, Geology and Soils, Hydrology and Water and Noise, and reduce them to an insignificant level, the Project will not have a significant adverse effect on the environment. The City Council further finds that after examining the whole record before the Planning Commission and City Council, including the testimony and studies that have been prepared and presented, the opponents to the Project have not presented a fair argument supported by substantial evidence in the record, that the Project will have a significant adverse effect on the environment that would require that an EIR be prepared. 1111089.2 Resolution No. 2009-09 Page 8 of 9 VA Section 4: For the foregoing reasons and based on the information and findings included in the record before the City Council, including the Staff Report, the Initial Study, the studies that have been conducted to evaluate whether the Project would cause significant environmental impacts, the proposed Mitigated Negative Declaration, and the Mitigation Monitoring Program, all of which are incorporated herein by this reference, the City Council of the City of Rancho Palos Verdes hereby certifies that the Mitigated Negative Declaration has been prepared in compliance with CEQA, adopts the Mitigated Negative Declaration and adopts the attached Mitigation Monitoring Program (Exhibit "A"), which is attached hereto and incorporated herein by this reference. Section 5: The documents, staff reports, technical studies, appendices, plans, specifications, and other materials that constitute the record of proceedings upon which this resolution is based are on file for public examination during normal business hours at the Department of Planning, Building and Code Enforcement, City of Rancho Palos Verdes City Hall, 30940 Hawthorne Boulevard, Rancho Palos Verdes, California 90275. Section 6: The time within which to seek review of this determination, if any, is governed by the California Environmental Quality Act or other similar shortened period of limitations. PASSED, APPROVED, and ADOPTED this 17th day of February 2009. -' �6� (�� Mayor ATTEST: Ciiy Clerk State of California ) County of Los Angeles ) ss City or Rancho Palos Verdes ) I, Carla Morreale, the City Clerk of the City of Rancho Palos Verdes, do hereby certify that the above Resolution No. 2009-09 was duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on February 17, 2009. 1111089.2 City Clark Resolution No. 2009-09 Page 9 of 9 51 Exhibit A Resolution No. 2009-09 Mitigation Monitoring Program Project: Case No. ZON2007-00492 (Environmental Assessment, Conditional Use Permit #96 — Revision "D", Grading Permit, Minor Exception Permit and Sign Permit) Location: 5448 Crest Road Rancho Palos Verdes, CA 90275 Applicant: Hyndman & Hyndman (Shelly Hyndman), representing St. John Fisher Landowner: The Roman Catholic Archbishop of Los Angeles TABLE OF CONTENTS Introduction.................................................................................................2 Purpose................................................................................................... 2 Environmental Procedures.............................................................................2 Mitigation Monitoring Program Requirements.....................................................2 II. Management of the Mitigation Monitoring Program..............................................3 Roles and Responsibilities..............................................................................3 Mitigation and Monitoring Program Procedures...................................................3 Mitigation Monitoring Operations......................................................................4 III. Mitigation Monitoring Program Checklist............................................................5 IV. Mitigation Monitoring Summary Table................................................................6 Resolution No. 2009-09 Exhibit A Page 1 of 13 :E I. INTRODUCTION PURPOSE This Mitigation Monitoring Program (MMP) is to allow the following project at 5448 Crenshaw Road, located at the southeast corner of Crenshaw Boulevard and Crest Road, in the City of Rancho Palos Verdes: A request for Conditional Use Permit #96 — Revision "D", Grading Permit, Minor Exception Permit and Sign Permit to establish a Master Plan for the St. John Fisher Church and School property including: 32,426 square feet of new building area for a new sanctuary, preschool, administration building, library, art room, storage area, storage garage and offices; demolition of 10,329 square feet, including the existing rectory, youth building and offices; remodel 26,544 square feet of existing building area, including existing offices, classrooms, converting the existing convent into a new rectory and converting the existing sanctuary into a new gymnasium; a total of 30,688 cubic yards of grading, including 19,694 cubic yards of raw cut and 10,994 cubic yards of raw fill, resulting in 8,700 cubic yards of exportation; and a new monument sign, attached to the sanctuary, at the corner of Crest and Crenshaw. The MMP responds to Section 21081.6 of the Public Resources Code, which requires a lead or responsible agency that approves or carries out a project where a Mitigated Negative Declaration has identified significant environmental effects, to adopt a "reporting or monitoring program for adopted or required changes to mitigate or avoid significant environmental effects." The City of Rancho Palos Verdes is acting as lead agency for the project. An Initial Study/Mitigated Negative Declaration was prepared to address the potential environmental impacts of the project. Where appropriate, this environmental document recommended mitigation measures to mitigate or avoid impacts identified. Consistent with Section 21080 (2)(c) of the Public Resources Code, a mitigation reporting or monitoring program is required to ensure that the adopted mitigation measures under the jurisdiction of the City are implemented. The City will adopt this MMP when adopting the Mitigated Negative Declaration. ENVIRONMENTAL PROCEDURES This MMP has been prepared in accordance with the California Environmental Quality Act of 1970 (CEQA), as amended (Public Resources Code Section 21000 et seq.) and the State Guidelines for Implementation of CEQA (CEQA Guidelines), as amended (California Administrative Code Section 15000 et seq.). This MMP complies with the rules, regulations, and procedures adopted by the City of Rancho Palos Verdes for implementation of CEQA. MITIGATION MONITORING PROGRAM REQUIREMENTS Section 21081.6 of the Public Resources Code states: "When making the findings required by subdivision (a) of Section 21081 or when adopting a negative declaration pursuant to paragraph (2) of subdivision (c) of Section 21081, the public agency shall adopt a reporting or monitoring program for the changes to the project which it has adopted or made a condition of project Resolution No. 2009-09 Exhibit A Page 2 of 13 NR approval in order to mitigate or avoid significant effects on the environment. The reporting or monitoring program shall be designed to ensure compliance during project implementation. For those changes which have been required or incorporated into the project at the request of an agency having jurisdiction by law over natural resources affected by the project, that agency shall, if so requested by the lead or responsible agency, prepare and submit a proposed reporting or monitoring program." II. MANAGEMENT OF THE MITIGATION MONITORING PROGRAM ROLES AND RESPONSIBILITIES The MMP for the project will be in place through all phases of the project including final design, pre -grading, construction, and operation. The City will have the primary enforcement role for the mitigation measures. MITIGATION MONITORING PROGRAM PROCEDURES The mitigation monitoring procedures for this MMP consists of, filing requirements, and compliance verification. The Mitigation Monitoring Checklist and procedures for its use are outlined below. Mitigation Monitorina Proaram Checklist The MMP Checklist provides a comprehensive list of the required mitigation measures. In addition, the Mitigation Monitoring Checklist includes: the implementing action when the mitigation measure will occur; the method of verification of compliance; the timing of verification; the department or agency responsible for implementing the mitigation measures; and compliance verification. Section III provides the MMP Checklist. Mitiaation Monitorina Proaram Files Files shall be established to document and retain the records of this MMP. The files shall be established, organized, and retained by the City of Rancho Palos Verdes department of Planning, Building, and Code Enforcement. Compliance Verification The MMP Checklist shall be signed when compliance of the mitigation measure is met according to the City of Rancho Palos Verdes Director of Planning, Building, and Code Enforcement. The compliance verification section of the MMP Checklist shall be signed, for mitigation measures requiring ongoing monitoring, and when the monitoring of a mitigation measure is completed. Resolution No. 2009-09 Exhibit A Page 3 of 13 RU MITIGATION MONITORING OPERATIONS The following steps shall be followed for implementation, monitoring, and verification of each mitigation measure: The City of Rancho Palos Verdes, Director of Planning, Building, and Code Enforcement shall designate a party responsible for monitoring of the mitigation measures. 2. The City of Rancho Palos Verdes, Director of Planning, Building, and Code Enforcement shall provide to the party responsible for the monitoring of a given mitigation measure, a copy of the MMP Checklist indicating the mitigation measures for which the person is responsible and other pertinent information. 3. The party responsible for monitoring shall then verify compliance and sign the Compliance Verification column of the MMP Checklist for the appropriate mitigation measures. Mitigation measures shall be implemented as specified by the MMP Checklist. During any project phase, unanticipated circumstances may arise requiring the refinement or addition of mitigation measures. The City of Rancho Palos Verdes, Director of Planning, Building, and Code Enforcement with advice from Staff or another City department, is responsible for recommending changes to the mitigation measures, if needed. If mitigation measures are refined, the Director of Planning, Building, and Code Enforcement would document the change and shall notify the appropriate design, construction, or operations personnel about refined requirements. Resolution No. 2009-09 Exhibit A Page 4 of 13 III. MITIGATION MONITORING PROGRAM CHECKLIST INTRODUCTION This section provides the MMP Checklist for the project as approved by the Planning Commission of the City of Rancho Palos Verdes on August 26, 2008. Mitigation measures are listed in the order in which they appear in the Initial Study. Types of measures are project design, construction, operational, or cumulative. Time of Implementation indicates when the measure is to be implemented. Responsible Entity indicates who is responsible for implementation. * Compliance Verification provides space for future reference and notation that compliance has been monitored, verified, and is consistent with these mitigation measures. Resolution No. 2009-09 Exhibit A Page 5 of 13 MITIGATION MEASURES TYPE TIME OF IMPLEMENTATION RESPONSIBLE ENTITY COMPLIANCE VERIFICATION 1. AESTHETICS AA1: If the new sanctuary results in significant view impairment from the viewing areas of surrounding properties, as defined by the City or Department of Prior to approval of Property Owner / Rancho Palos Verdes' Development Code, then Project Design entitlements applicant. Planning, Building and elements of the proposed project which Code Enforcement significantly impair views shall be reduced to a less than significant impairment. AA=2: If the new sanctuary is determined to create Department of Project Design bulk and mass impacts, then elements of the roject DiPrior to approval of Property Owner / Planning, Building and proposed project shall be reduced in height or entitlements applicant. architecturally modified to minimize said impacts. Code Enforcement AA3: Subject to the satisfaction of the Director of Planning, Building and Code Enforcement, and prior to issuance of Certificate of Use and Occupancy for Department of the sanctuary and parking lot, each fixture head shall Cumulative Prior to issuance of Certificate Property Owner / Planning, Building and incorporate appropriate shields on the fixtures to of Use and Occupancy applicant, adequately shield the light source from adjacent Code Enforcement property. The fixtures shall be hooded so that the light is directed downward. A=4: After installation of all lighting, but prior to Issuance of Certificate of Use and Occupancy of any and all of the proposed buildings, the applicant shall request that the City conduct an inspection of the Construction & Prior to issuance of Certificate Property Owner / site to ensure that there is no spill-over of on-site Operational of Use and Occupancy applicant. lighting onto adjacent properties. Department of Planning, Building and Code Enforcement AA5: A trial period of six months from issuance of Certificate of Use and Occupancy for assessment of exterior lighting impacts shall be instituted. At the Construction / Prior to issuance of Certificate Property Owner / end of the six-month period, the City may require Operational of Use and Occupancy applicant. Planning Commission additional screening, reduction in intensity of any light or the incorporation of time -restricting for exterior liahtina that has been determined to be excessivelv Resolution No. 2009-09 Exhibit A Page 6 of 13 MITIGATION MEASURES TYPE TIME OF RESPONSIBLE COMPLIANCE IMPLEMENTATION ENTITY VERIFICATION bright. III. AIR QUALITY AQ -1: Prior to issuance of any Building Permit and/or Grading Permit, the Director of Public Works and the Building Official shall confirm that the Grading Plan, Building Plans and specifications stipulate that, in compliance with South Coast Air Quality Management District Rule 403, excessive fugitive dust emissions shall be controlled by regular watering or other dust preventative measures, as specified in the South Coast Air Quality Management District's Rules and Regulations In addition, South Coast Air Quality Management District Rule 402 requires implementation of dust suppression techniques to prevent fugitive dust from creating a nuisance off-site. Implementation of the following measures would reduce short-term fugitive dust impacts on nearby sensitive receptors: • All materials transported off-site shall be either sufficiently watered or securely covered to prevent excessive amounts of dust prior to departing the job site; • All delivery truck tires shall be watered down and/or scraped down prior to departing the job site; • All active portions of the construction site shall be watered to prevent excessive amounts of dust; • All materials excavated or graded shall be sufficiently watered to prevent excessive amounts of dust; watering with complete coverage, shall occur at least twice daily, preferably in the late morning and after school hours; Project Design & Construction Prior to issuance Grading Property Owner/ Permit and/or Building Permit I applicant Exhibit A Page 7 of 13 Department of Planning, Building and Code Enforcement & Department of Public Works Resolution No. 2009-09 a MITIGATION MEASURES TYPE TIME OF RESPONSIBLE COMPLIANCE IMPLEMENTATION ENTITY VERIFICATION • If dust is visibly generated that travels beyond the site boundaries, clearing, grading, earth moving, or excavation activities that are generating dust shall cease during periods of high winds (i.e. greater than 25 mph average over one hour; AQ -2: Prior to issuance of any Building Permit and/or Grading Permit, the Directory of Public Works and the Building Official shall confirm that the Grading Plan, Building Plans and specifications stipulate that, in compliance with South Coast Air Quality Management District Rule 403, ozone precursor emissions from construction equipment vehicles shall be controlled by maintaining equipment engines in good condition and properly tuned per manufacturer's specifications, to the satisfaction of the City Engineer. Maintenance records shall be provided to the City. The City Inspector shall be responsible for ensuring that contractors comply with this measure during construction. AQ -3: Prior to issuance of any Grading Permit and/or Building Permit, the City shall verify that the construction contract standard specifications include a written list of instructions to be carried out by the construction manager specifying measures to minimize emissions by heavy equipment for approval by the Director of Public Works. Measures shall include provisions for property maintenance of equipment engines, measures to avoid equipment idling more than two minutes, and avoidance of unnecessary delay of traffic along off-site access roads by heavy equipment blocking traffic. Department of Project Design & Prior to issuance of Building Property Owner/ Planning, Building and Construction Permits and/or Grading applicant Code Enforcement & Permits Department of Public Works Department of Project Design & Prior to issuance of Building Property Owner/ Planning, Building and Construction Permits and/or Grading applicant Code Enforcement & Permits Department of Public Works Exhibit A Page 8 of 13 Resolution No. 2009-09 91 MITIGATION MEASURES TYPE TIME OF RESPONSIBLE COMPLIANCE IMPLEMENTATION ENTITY VERIFICATION AQ -4: During construction and in compliance with South Coast Air Quality Management District Rule 1113, ROG emissions from architectural coatings shall be reduced by using pre-coated/natural-colored building materials, water-based or low-ROG coatings Department and using coating transfer or spray equipment with Construction Throughout construction Property Owner/ Planning, Building and high transfer efficiency. applicant Code Enforcement AQ -5: Prior to issuance of any Grading Permit, the contractor shall include the following measures with the Grading Plan, to the satisfaction of the Director of Public Works and Building Official: • The Applicant shall submit, for review and approval by the City, a Construction Traffic Management Plan that specifies that construction activities shall be organized so as not to interfere significantly with peak -hour traffic and minimize Department of obstruction of through traffic lanes adjacent to the g 1 Project Design & Prior to issuance of Grading Property Planning, Building and site, includingconstruction related parkingand Construction Permits and/or Building Owner/applicant Code Enforcement & deliveries; if ecessary, a flag persons all be Permits Department of Public p retained to maintain safety adjacent to the existing Works roadways,- oadways;• -The General Contractor shall utilize electric- or diesel -powered stationary equipment in lieu of gasoline powered engines where feasible; and • The General Contractor shall state in the Grading Plans that work crews turn off equipment when not in use. VI. GEOLOGY AND SOILS Exhibit A Page 9 of 13 Resolution No. 2009-09 92 MITIGATION MEASURES TYPE TIME OF RESPONSIBLE COMPLIANCE IMPLEMENTATION ENTITY VERIFICATION GS -1:. The applicant shall submit a geotechnical report for review and approval by the City Geologist Prior to issuance of Grading Department of prior to the issuance of a building and/or grading project Design Permits and/or Building Property Owner / Planning, Building and permit for the property, unless the City Geologist Permits applicant. Code Enforcement. deems that a geotechnical report is not warranted, based on a field assessment of the site. GS -2: The applicant shall ensure that all applicable Prior to issuance of Grading Department of conditions, as specified within the geotechnical report, and all measures required b the Ci p G y City Construction Permits and/or Building Property Owner / applicant. Planning, Building and Geologist are incorporated into the project. Permits Code Enforcement. VIII. HYDROLOGY AND WATER QUALITY HWO-1): The Applicant shall submit and obtain approval of a drainage report from the Building Project Design & Prior to issuance of Grading Property Owner / Department of Official, prior to issuance of any Grading Permit Construction Permit and/or Building Permit applicant. Planning, Building and and/or a Building Permit for new construction. & Throughout Construction Code Enforcement HWQ-2): The Applicant shall submit and obtain approval of a Standard Urban Stormwater Mitigation Prior to issuance of Grading Department of Plan (SUSMP) to the Department of Planning, Project Design & Permit and/or Building Permit Property Owner / Planning, Building and Building and Code Enforcement, prior to issuance of Construction &Throughout Construction applicant. Code Enforcement any Grading Permit and/or a Building Permit for all construction activity. HWQ-3): The Applicant shall submit and obtain Project Design & Prior to issuance of building Property Owner / Department of Planning, Building and approval of a Local Stormwater Pollution Prevention Construction and/or grading permit. applicant. Code Enforcement Plan SWPPP to the Department of Planning, Exhibit A Page 10 of 13 Resolution No. 2009-09 93 MITIGATION MEASURESTIME OF COMPLIANCE Building and Code Enforcement, prior to issuance of any Grading Permit and/or a Building Permit for all construction activity. XI. NOISE NN=1: Prior to issuance of any Grading Permit and/or Building Permit, the Applicant shall provide, to the satisfaction of the Director of Planning, Building and Code Enforcement, a Construction Noise Mitigation and Monitoring Program. Such plan would ensure that the proposed project shall provide the following: • Construction contracts specifying that all construction equipment, fixed or mobile, shall be equipped with properly operating and maintained mufflers and other state required noise attenuations devices. • Property owners and occupants located within 0.25 -mile of the Project construction site shall be sent a notice, at least 15 days prior to commencement of construction of each phase, regarding the construction schedule of the proposed project. A sign, legible at a distance of 50 feet shall also be posed at the project construction site. All notices and signs shall be reviewed and approved by the Director of Planning, Building and Code Enforcement, prior to mailing or posting and shall indicate the dates and duration of construction activities, a well as provide a contact name and telephone number where residents can inquire about the construction process and register complaints. • The Applicant shall provide, to the satisfaction of the Director of Planning, Building and Code Enforcement, a qualified "Noise Disturbance Coordinator." The Disturbance Coordinator shall be TYPE I IMPLEMENTATION I RE ENTNTY LE I VERIFICATION Prior to issuance of Grading Department of Project Design & Permit and/or Building Permit Property Owner / Planning, Building and Construction & Throughout Construction applicant. Code Enforcement. Exhibit A Page 11 of 13 Resolution No. 2009-09 0 MITIGATION MEASURES TYPE TIME OF IMPLEMENTATION RESPONSIBLE ENTITY COMPLIANCE VERIFICATION responsible for responding to any local complaints about construction noise. When a complaint is received, the Disturbance Coordinator shall notify the City within 24 -hours of the complaint and determine the cause of the noise complaint and shall implement reasonable measures to resolve the complaint, as deemed acceptable by the Director of Planning, Building and Code Enforcement. All notices that are sent to residential units within a 0.25 -mile radius of the construction site and all signs posted at the construction site shall include the contact name and the telephone number for the Disturbance Coordinator. • Prior to issuance of a Building Permit and/or Grading Permit, the Applicant shall demonstrate to the satisfaction of the Building Official how construction noise reduction methods such as shutting off idling equipment, installing temporary acoustic barriers around stationary construction noise sources, maximizing the distance between construction equipment staging areas and occupied residential areas and electric air compressors and similar power tools, rather than diesel equipment, shall be used where feasible. • During construction, stationary construction equipment shall be placed such that emitted noise is directed away from sensitive noise receivers. NN=2: Construction activity associated with the proposed project and grading operations shall be Property Department of limited to the hours of 7:00 am and 7:00 pm, Construction On-going Owner/applicant Planning, Building and Monday through Saturday, per Section 17.56 of the code Enforcement RPVMC. There shall be no construction on Sundays or federally observed holidays without the approval Exhibit A Page 12 of 13 Resolution No. 2009-09 95 MITIGATION MEASURES TYPE TIME OF RESPONSIBLE COMPLIANCE IMPLEMENTATION ENTITY VERIFICATION of a Special Construction Permit by the City's Department of Planning, Building and Code Enforcement. N-3: During demolition, construction and/or grading operations, trucks shall not park, queue and/or idle at the project site or in the adjoining public rights -of- Property Department of way before 7:00 am, Monday through Saturday, in Construction On-going Owner/applicant Planning, Building and accordance with the permitted hours of construction code Enforcement stated in mitigation N-2. NN4: Prior to issuance of any Demolition, Grading or Building Permit, the Director of Planning, Building and Code Enforcement shall review and approve a pp Project Design & Prior issuance of Property Department Construction Management Plan, which shall specify Construction Demolition Permit, Grading li Owner/applicant iof t Planning, Building and that demolition debris hauling shall be limited Permit and/or Building Permit code Enforcement between 9:00 AM and 4:00 PM. NN5: There shall be no staging of equipment or accumulation of vehicles on Rancho Palos Verdes Property Owner / Department of City streets. Staging of trucks for the hauling of all Construction On-going applicant Planning, Building and demolition debris would occur on the St. John Fisher code Enforcement site. Exhibit A Page 13 of 13 Resolution No. 2009-09 99 Resolution No. 2009-10 (Original Planning Entitlements for Master Plan) 97 RESOLUTION NO. 2009-10 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES, DENYING AN APPEAL, UPHOLDING THE PLANNING COMMISSION'S DECISION WITH MODIFICATIONS AND APPROVING CASE NO. ZON2007-00492 (CONDITIONAL USE PERMIT #96 — REVISION "D", GRADING PERMIT, MINOR EXCEPTION PERMIT AND SIGN PERMIT), TO ESTABLISH A MASTER PLAN FOR THE ST. JOHN FISHER CHURCH AND SCHOOL PROPERTY INCLUDING THE CONSTRUCTION OF 32,426 SQUARE FEET OF NEW BUILDING AREA, THE DEMOLITION OF 10,329 SQUARE FEET OF EXISTING FACILITIES, A REMODEL OF 26,544 SQUARE FEET, A TOTAL OF 30,688 CUBIC YARDS OF ASSOCIATED GRADING AND A NEW MONUMENT SIGN ATTACHED TO THE NEW SANCUTARY FOR THE PROPERTY AT 5448 CREST ROAD, LOCATED AT THE SOUTHEAST CORNER OF CREST ROAD AND CRENSHAW BOULEVARD. WHEREAS, on April 23, 1985, the Planning Commission approved Conditional Use Permit #96, thereby allowing the construction of a new social/meeting hall (Barrett Hall); and, WHEREAS, on July 22, 1986, the Planning Commission approved Conditional Use Permit #96 — Minor Revision, thereby allowing the construction of a 121 square foot trellis over an existing sun deck, located above the garage of the church rectory; and, WHEREAS, on January 11, 1994, the Planning Commission approved, with conditions, Variance #116 and Conditional Use Permit #96 — Revision "B", thereby allowing the construction of a 36'-6" tall elevator for access to the lower level meeting room, a 1,004 square foot expansion of the existing sanctuary and a 50'-0" tall bell tower and bells with a 15-0" tall cross affixed to the top of the tower, for a maximum overall height of 65'-0"; and, WHEREAS, on February 7, 1994, the applicant submitted a letter to the Planning, Building and Code Enforcement Department stating that the proposed tower and bells were eliminated from Conditional Use Permit #96 -- Revision "B" due to funding restrictions and, as a result, would not be constructed; and, WHEREAS, on February 11, 1997, the Planning Commission approved, with conditions, Conditional Use Permit, #96 — Revision "C", thereby allowing the construction of 3,189 square feet, in two phases, to provide 10 elementary school classrooms; and, WHEREAS, on October 5, 2007, Hyndman and Hyndman, representing St. John Fisher Church and School, submitted Case No. ZON2007-00492 including applications for a Conditional Use Permit #96 — Revision "D", Grading Permit, Minor Exception Permit, Sign Permit and Environmental Assessment, for the subject property at 5448 Crest Road; and, WHEREAS, on October 29, 2007 the project was deemed incomplete by Staff pending the submittal of additional information on the project plans and review and Resolution No. 2009-10 Page 1 of 7 WQ approval from the Fire Department, City Traffic Consultant, City Geologist and City's National Pollution Discharge Elimination System (NPDES) Consultant; and, WHEREAS, on April 29, 2008, upon submittal of all required information, the project was deemed complete by Staff; and, WHEREAS, pursuant to the provisions of the California Environmental Quality Act, Public Resources Code Sections 21000 et. seq. ("CEQA"), the State's CEQA Guidelines, California Code of Regulations, Title 14, Section 15000 et. seq., the City's Local CEQA Guidelines, and Government Code Section 65962.5(f) (Hazardous Waste and Substances Statement), the City of Rancho Palos Verdes prepared an Initial Study and determined that, with appropriate mitigation, there is no substantial evidence that the approval of ZON2007-00492 would result in a significant adverse effect upon the environment and, therefore, a Mitigated Negative Declaration has been prepared and notice of same was given in the manner required by law; and, WHEREAS, on May 31, 2008, a public notice was mailed to 102 property owners who reside within a 500 -foot radius of 5448 Crest Road (St. John Fisher) and concurrently published a public notice in the Peninsula News; and, WHEREAS, on June 4, 2008, a Mitigated Negative Declaration was circulated to the County Recorder for a posting and comment period of at least twenty (20) days and circulated to all appropriate public agencies for comments; and, WHEREAS, after notice issued pursuant to the requirements of the Rancho Palos Verdes Development Code and CEQA, the Planning Commission held a duly noticed public hearing on June 24, 2008, at which time all interested parties were given an opportunity to be heard and present evidence; and, WHEREAS, on June 24, 2008, the Planning Commission continued the item to the July 22, 2008 Planning Commission meeting to allow time for the applicant to address concerns with the height of the proposed sanctuary and steeple and to provide clarification on the methodology used to determine the number of provided parking spaces; and, WHEREAS, on July 2, 2008, the applicant submitted modified plans and updated information to Staff which included the following modifications: 1) a reduction in height of the proposed steeple by 14'-0", 2) an overall reduction in height of the main sanctuary building by up to 6'-0", 3) elimination of the stepped roof lines along the south side of the sanctuary, 4) a reduction in the footprint of the sanctuary by 1,400 square feet, 5) the addition of a 900 square foot basement beneath the sanctuary to accommodate mechanical equipment, 6) an increase in the sanctuary street side yard setbacks by 14'-0" along Crest Road, 7) an increase in the sanctuary street side yard setback by 17'-0" along Crenshaw Boulevard and 8) a reduction in the footprint of the administrative building by 1,480 square feet; and, Resolution No. 2009-10 Page 2 of 7 WHEREAS, the Planning Commission held a duly noticed public hearing on July 22, 2008, at which time all interested parties were given an opportunity to be heard and present evidence; and, WHEREAS, on July 22, 2008, the Planning Commission continued the item to the September 23, 2008 Planning Commission meeting to allow time for the applicant to consider providing a sound study to determine if any significant impacts would result from the proposed bells, a shadow study to determine if the height and/or scale of the sanctuary would create any significant impacts to surrounding properties, a copy of St. John Fisher's recent parking counts, further clarification on the applicant's parking analysis and consideration from the applicant to provide additional parking on high peak days; and, WHEREAS, on September 23, 2008, the Planning Commission held a duly noticed public hearing, at which time all interested parties were given an opportunity to be heard and present evidence; and, WHEREAS, on September 23, 2008, the Planning Commission conceptually approved Case No. ZON2007-00492 and directed Staff to bring back the appropriate resolutions with Conditions of Approval; and, WHEREAS, on October 14, 2008, the Planning Commission adopted PC Resolution No. 2008-34, certifying a Mitigated Negative Declaration and adopting a Mitigation Monitoring Program and PC Resolution No. 2008-35, adopting the St. John Fisher Master Plan, as conditioned; and WHEREAS, on October 29, 2008, Case No. ZON2007-00492 was appealed to the City Council, including issues with the Environmental Assessment and CUP findings, a request to analyze Neighborhood Compatibility, impacts due to the size of the sanctuary, inadequate parking, noise impacts due to the use of a gymnasium and the ringing of the proposed electronic bells, the lighting of the sanctuary tower and steeple, concerns with removal of certain mature trees and to require additional setbacks around the sanctuary; and, WHEREAS, On November 1, 2008, a Notice of the public hearing on the Appeal was published in the Peninsula News; the City also sent notice of the Appeal hearing to the property owners who reside within 500 feet of the subject property, to all persons listed on the City's Interested Parties List, and to all St. John Fisher list -serve subscribers; and, WHEREAS, on November 16, 2008, the City Council opened the public hearing on the appeal, and after hearing the public testimony and considering the information presented in the Staff Report, the City Council adjourned the public hearing to a site visit at the St. John Fisher property to beheld on November 22, 2008, to allow the City Council to walk throughout the subject property and surrounding neighborhood to assess the project and its potential impacts; and, Resolution No. 2009-10 Page 3 of 7 We WHEREAS, on November 22, 2008, the City Council conducted the continued public hearing, which was a site visit at the St. John Fisher property, and at the conclusion of the site visit, the City Council continued the public hearing to December 16, 2008; and, WHEREAS, on December 16, 2008, the City Council conducted the continued public hearing on the appeal and heard and considered all of the additional materials that have been submitted after the first public hearing and all of the additional testimony that was presented: NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO PALOS VERDES DOES HEREBY FIND, DETERMINE, AND RESOLVE AS FOLLOWS: Section 1: The site is adequate in size and shape to accommodate the intended use and implementation of the Project, as the site measures 399,804 square feet (9.2 acres), the majority of the site is relatively flat (less than 5% slope) and is large enough to accommodate the construction of a new sanctuary, administration building, art room, library, a new preschool, ancillary offices and storage area, and the elements of the Master Plan comply with the general development standards of the RPVMC. Additionally, the proposed parking and parking analysis were reviewed and determined to be adequate by the City's consulting Traffic Engineer. Section 2: The site for the proposed uses relates to streets and highways that are properly designed to carry the type and quantity of traffic generated by the subject use as a traffic impact study and supplemental cumulative traffic analysis, which was reviewed and approved by the City's Traffic Engineer, indicate that the increase in trip generation that would be caused by the Project is negligible and would not require mitigation. Further, a parking analysis was reviewed and approved by the City's Traffic Consultant whereby the highest number of parking spaces necessary to accommodate potential vehicles during the highest peak hours of operation for the entire property would be 331 parking spaces. Therefore, the City Council hereby concludes that, as conditioned, the off-street parking that is proposed for the Project will be adequate to accommodate the uses that are conducted on site, even during the days and hours of peak use. Section 3: There will be no significant adverse effect on adjacent property or the permitted use thereof because mitigation measures have been incorporated that reduce the potential impacts of the Project on Aesthetics, Air Quality, Geology and Soils, Hydrology and Water Quality, and Noise to an insignificant level. Further, additional conditions have been incorporated into the design of the Project that reduce to an insignificant level the potential impacts of the institutional use and related buildings on adjacent properties and the residents thereof. In that regard, a study was conducted to determine if the height of the proposed building and steeple will cast a shadow over adjacent residential properties. The conclusion of that study was that because of the size and configuration of the subject property, the height of the proposed structures will not cast shadows on adjacent properties. Residents in the community also raised concerns about potential impacts that could be caused by the installation of bells near the steeple that will ring periodically. After having heard the sound of the proposed bells, and imposing conditions that will regulate the time of day when the bells can be rung, and limiting the Resolution No. 2009-10 Page 4 of 7 101 number of times, volume, and the duration of the ringing, the City Council hereby finds that, as conditioned, the bells will not cause a significant adverse impact upon adjacent properties. Section 4: The proposed Project is consistent with the General Plan's Institutional land use designation of the site, and with the types of land uses permitted within the Development Code's Institutional zoning district, which includes religious institutions, as the General Plan states that "the City shall encourage the development of institutional facilities to serve the political, social and cultural needs of its citizens." Section 5: Conditions have been imposed to protect the public health, safety and general welfare, which include setback and buffers, lighting restrictions, vehicular ingress and/or egress, landscaping, maintenance of structures, and other conditions, as identified in Exhibit "B," which is attached hereto and incorporated herein by this reference. Section 6: The proposed grading is necessary for the implementation of the Project and the associated construction for the permitted primary use of the lot due to the size of the lot (9.2 acres) and the fact that a majority of the proposed grading will occur within the developed portions of the property. Section 7: The proposed grading and/or related construction would not significantly adversely affect the visual relationships with or views from the viewing area of neighboring properties, as a majority of the existing grade elevations will be maintained between grade elevation 1219' and 1222', which are heights that do not interfere with the visual relationships with, or views from, the viewing area of neighboring properties. Section 6: The proposed grading minimizes disturbances to the natural contours, and the finished contours are reasonably natural, as all grading will include blending man- made or manufactured slopes into the natural topography. Section 9: The grading would not cause excessive and unnecessary disturbance of the natural landscape or wildlife habitat through the removal of vegetation, as there is no evidence of natural landscape or wildlife on the property or within the surrounding neighborhood. Section 10: The grading application is consistent with the purpose and intent of the Section 17.76.040 of the Municipal Code, since it provides for the reasonable additional development of the parcel with an institutional use. Section 11: Approval of the grading permit will not constitute a special privilege with limitations upon other properties in the vicinity, as the surrounding neighborhood is comprised of many hillside properties that utilize retaining walls and grading techniques. Further, the subject property has an existing pad area that will be maximized to accommodate the new construction in the connection with the Project. Section 12; The proposed grading will not be detrimental to the public safety, or to other properties as the City's geotechnical consultant will be required to approve a soils Resolution No. 2009-10 Page 5 of 7 102 engineering report for the grading and retaining walls. Further, all structures and retaining walls will be required to be engineered to meet the requirements of the building code. Section 13: The proposed grading is acceptable, as the maximum height of cut and/or fill of remedial grading was determined by a geology and soils report submitted by the applicant and approved "in -concept for planning purposes" by the City's Geologist. Section 14: The minor exception to allow three combination walls to exceed the 6'- 0" "by -right" height limit for walls as measured from the highest grade elevation is necessary to avoid inconsistencies with the general intent of Title 17 of the RPVMC, as the Building Code requires a guardrail on top of all walls that exceed 30" in height adjacent to the neighboring properties and/or walkways throughout the subject property. The applicant will be required to construct a guardrail or fence on top of the proposed retaining walls to protect the safety of people on the subject property and adjacent properties. Section 15: The minor exception for the combination walls is warranted as the height of the combination walls will not be detrimental to the public safety and welfare as the fence on top of the proposed retaining walls will provide a safety barrier for people between the subject lot and the neighboring properties to the south and east as well as safety for the play area for the students and pedestrians in the parking lot. Section 16: The minor exception for the combination walls is warranted as the line of sight over or through the fences is adequate for safety and the walls do not significantly impair a view from the viewing area of an adjacent parcels, as there are no views over the site that are enjoyed from the viewing areas of adjacent parcels. Section 17: The minor exception permit is warranted, as the proposed combination walls will be located outside of the intersection visibility triangle. Section 18: The minor exception permit is warranted ,as the retaining portion of the combination walls does not exceed the grading limits set forth in Section 17.76.040 of the RPVMC. Section 19: The proposed signs are consistent with the sign standards of the City's Development Code and, accordingly, are approved for that reason. Section 20: For the foregoing reasons and based on the information and findings included in the Staff Report, Minutes and other records of proceedings, the City Council of the City of Rancho Palos Verdes hereby conditionally approves Conditional Use Permit #96 — Revision "D", Grading Permit, Minor Exception Permit and Sign Permit (Planning Case No. ZON2007-00492) for the establishment of a Master Plan for the development of the St. John Fisher Church and School property, including: 32,426 square feet of new building area for a new sanctuary, preschool, administration building, library, art room, storage area, storage garage and offices; demolition of 10,329 square feet, including the existing rectory, youth building and offices; remodel 26,544 square feet of existing building area, including existing offices, classrooms, converting the existing convent into a new rectory and converting the existing sanctuary into a new gymnasium; a total of 30,688 cubic Resolution No. 2009-10 Page 6 of 7 103 yards of grading, including 19,694 cubic yards of raw cut and 10,994 cubic yards of raw fill, resulting in 8,700 cubic yards of exportation; and a new monument sign, attached to the sanctuary, at the corner of Crest and Crenshaw, located at 5448 Crest Road, subject to the conditions of approval in the attached Exhibit 'B', which are incorporated herein and into the project by this reference. Section 21: The time within which judicial review of the decision reflected in this Resolution must be sought is governed by Section 1094.6 of the California Code of Civil Procedure and other applicable short periods of limitation. PASSED, APPROVED, AND ADOPTED this 17th day of February 2009, Mayor Attest: 0a _ City Clerk State of California ) County of Los Angeles ) ss City or Rancho Palos Verdes ) I, Carla Morreale, the City Clerk of the City of Rancho Palos Verdes, do hereby certify that the above Resolution No. 2009-10 was duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on February 17, 2009, City Clerk Resolution No. 2009-10 Page 7 of 7 104 Exhibit "B" Conditions of Approval Case No. ZON2007-00492 (Conditional Use Permit #96 — Revision "D", et. all.) C',aninral 1. All mitigation measures contained in the approved Mitigation Monitoring Program contained in C.C. Resolution No. 2009----- for the Mitigated Negative Declaration, shall be incorporated into the proposed Project and adhered to, and are incorporated herein by reference. 2. The proposed Project, including site layout, the building and appearances, and signage throughout the site, shall be constructed and maintained in substantial compliance with the plans reviewed and approved by the City Council, and stamped APPROVED by the City with the effective date of the Notice of Decision. I The Director of Planning, Building and Code Enforcement is authorized to approve minor modifications to the approved plans or any of the conditions if such modifications achieve substantially the same results as would strict compliance with said plans and conditions. Otherwise, all other modifications shall be subject to review and approval by the City Council. 4. Prior to the submittal of plans into Building and Safety plan check, the applicant and the property owner shall submit to the City a statement, in writing, that they have read, understand and agree to all conditions of approval listed below. Failure to provide said written statement within ninety (90) days following the date of this approval shall render this approval null and void. 5. Prior to the submittal of plans into Building and Safety plan -check, the applicant shall obtain an encroachment permit from the Director of Public Works for any curb cuts or any other temporary or permanent improvements within the public rights-of-way. 6. Approval of this permit shall not be construed as a waiver of applicable and appropriate zoning regulations, or any Federal, State, County and/or City laws and regulations. Unless otherwise expressly specified, all other requirements of the City of Rancho Palos Verdes Municipal Code shall apply. 7. The project development on the site shall conform to the specific standards contained in these conditions of approval or, if not addressed herein, shall conform to the appropriate development and operational standards of the City's Municipal Code. 8. Failure to comply with and adhere to all of these conditions of approval may be cause to revoke the approval of the project pursuant to the revocation Resolution No. 2009-10 Exhibit B Page 1 of 14 105 procedures contained in Section 17.86.060 of the City's Municipal Code. 9. In the event that any of these conditions conflict with the requirements of another permitting agency or City department, the stricter standard shall apply. 10. The construction site and adjacent public and private properties and streets shall be kept free of all loose materials resembling trash and debris in excess of that material used for immediate construction purposes. Such excess material may include, but is not limited to: the accumulation of debris, garbage, lumber, scrap metal, concrete asphalt, piles of earth, salvage materials, abandoned or discarded furniture, appliances or fixtures. 11. All applicable permits required by the Building and Safety Division shall be obtained by the applicant prior to the commencement of construction. 12. All mechanical equipment, whether roof -mounted or ground -mounted, shall be adequately screened to the extent practicable from other properties and/or public rights-of-way. 13. The project applicant shall maintain, in good condition, two access driveways. One access driveway shall be provided from Crest Road and a second access driveway shall be provided from Crenshaw Boulevard. Proiect Description 14. This approval establishes a Master Plan (St. John Fisher Master Plan) for the St. John Fisher property located at 5448 Crest Road. The approved Master Plan identifies a combined total of 32,426 square feet of new building area for a new sanctuary, preschool, administration building, library, art room, storage area, storage garage and offices; 10,329 square feet of existing facilities to be demolished, including offices, a youth building and the existing rectory along the north property line, and 26,544 square feet of the existing facilities to be remodeled, including converting the existing convent into a new rectory, converting the existing sanctuary into a new gymnasium and remodeling existing classrooms and offices. 15. The approved St. John Fisher Master Plan allows for the following additions to the property: A new 17,000 square foot sanctuary (to replace the existing 15,402 square foot sanctuary) to be located at the northwest corner of the subject property. The sanctuary also includes a 900 square foot basement for the housing of mechanical equipment. The new sanctuary will be circular in shape, whereby the main structure will range in height from 15-0" at the northeast end of the structure to 43'-0" at the southwest. In addition, the new sanctuary will include a steeple, at the west end of the structure, with a maximum height of 60'-0" to Resolution No. 2009-10 Exhibit B Page 2 of 14 the top of the steeple and 74'-0" to the top of the cross which will be affixed to the top of the steeple. => A new 9,788 square foot administration building (7,488 square foot first floor and 2,300 square foot basement); and => A 1,074 square foot addition for the creation of two new classrooms for the preschool; and => A new 1,289 square foot art room at the northwest corner of the existing classrooms; and => A new 1,217 square foot school library at the northeast corner of the existing classrooms; and => A 304 square foot expansion to Barrett Hall for storage area; and => A new 454 square foot garage at the southeast corner of the property, adjacent to the priest's new rectory (previously a convent); and => A 400 square foot addition north of the existing music room to accommodate two (2) new offices. 16. The style and exterior materials of the proposed buildings shall be consistent with the architectural plans presented to and approved by the City Council. Lighting 17. Exterior lighting shall be in compliance with the standards of Section 17.56.040 of the Rancho Palos Verdes Development Code and as identified and conditioned in the Certified Mitigated Negative Declaration. 18. All exterior lighting shall be arranged and shielded so as to prevent direct illumination of surrounding property and to prevent distraction of drivers of vehicles on public rights-of-way. Luminaries shall be of a low-level, indirect and diffused type. 19. No one light fixture shall exceed 1,200 watts, and the light source shall not be directed toward or result in direct illumination of an adjacent parcel of property or properties other than that upon which such light source is physically located. All exterior lighting shall be arranged and shielded so as to prevent direct illumination of abutting properties and to prevent distraction of drivers of vehicles on public rights-of-way. 20. No building -mounted outdoor lighting shall be permitted where the light source or fixture is mounted more than sixteen (16) feet above grade, as measured from Resolution No. 2009-10 Exhibit B Page 3 of 14 107 grade, adjacent to the building. 21. All outdoor lighting, including all outdoor illuminated signs, shall be turned off by 9:00 P.M. Monday through Sunday, except for lighting used for security, lighting of the sanctuary on Christmas Eve and Easter Vigil, which shall be turned off by 2 A.M, and additional security lighting the first Friday of every month. Prior to issuance of a Building Permit or Grading Permit, the applicant shall provide the Planning Department with a lighting plan for review and approval by the Planning Director that indicates the lights that will remain lit throughout the evening for security. 22. Exterior sanctuary lighting shall be installed prior to issuance of the Certificate of Occupancy for the sanctuary._After installation of all lighting, but prior to Issuance of Certificate of Use and Occupancy of the proposed sanctuary and parking lot, the developer shall request that the City conduct an inspection of the site to ensure that there is no spill-over of light onto adjacent properties. Grading and Drainage 23. This approval allows a total of 30,688 cubic yards of grading with the following quantity breakdown: a. 19,694 cubic yards of excavation b. 10,994 cubic yards of fill 24. Stockpiling of earthwork shall be limited to a maximum of 200 cubic yards in any given area, shall not be stockpiled on the property for more than a period of six (6) months, and the applicant shall adequately screen the visibility of all stockpiles to the extent practicable from the public right-of-way, as determined by the City's Building Official. 25. A maximum of 8,700 cubic yards of excavation is permitted for export. 26. The applicant is allowed to construct a total of five (5) retaining walls as described below: a. A combination wall along the east property line, adjacent to the existing driveway, shall not exceed a maximum height of 11'-6", b. A combination wall along the west side of the existing driveway, accessed from Crest Road (maximum height of 11'-6"), c. A combination wall to accommodate new parking along the south property line (maximum height of 11'-6"), d. A new retaining wall, just north of the proposed parking lot (maximum height of 7'-6", Resolution No. 2009-10 Exhibit B Page 4 of 14 e. An 8'-0" tall retaining wall between the proposed Parish Activity Center/gymnasium and new sanctuary for a columbarium. 27. The applicant shall install wrought -iron or aluminum decorative fencing on top of all proposed combination walls. The wrought -iron or aluminum fencing shall be constructed in a manner by which not less than eighty (80%) of the vertical surface is open to permit the transmission of light, air or vision through said surface in a horizontal plane, as described in the development code definition for a "fence" pursuant to the RPVMC. 28. Construction of buildings is prohibited on extreme slopes (35% or greater slope). Parking 29. Only the uses which are listed in the parking analysis that was approved by the City Council, shall be allowed to be constructed on the St. John Fisher property. These uses will generally take place in the following structures: • Sanctuary (assembly space) • Elementary School (classrooms) • Preschool (classrooms) • Administrative Building (office space) • School Library • Barrett Hall Complex (including the assembly space) • Parish Activity Center/Gymnasium (assembly space) • Fireside Room (assembly space) • Multi-purpose room (assembly space) • Rectory (single-family residential) • K-8 Religious education (in existing structures) • Art Room (classroom) 30. All facilities, activities and/or uses on the St. John Fisher property shall be operated in such a manner so as not to create simultaneous demand for maximum on-site parking requirements that would exceed 331 spaces when the St. John Fisher School is in session and 354 parking spaces (331 regular spaces and 23 seasonal/peak parking spaces on-site) when school is not in session, without approval from the Director of Planning, Building and Code Enforcement of a Special Use Permit. If the church is fully occupied and concurrent Religious Education classes are fully occupied, no other assembly activity can occur on the property unless that activity requires 23 or fewer parking spaces. 31. If an event or activity is proposed that would occupy the parking spaces, thereby reducing available parking by more than 25% of the 331 required parking spaces, a Special Use Permit shall be required. 32. Of the 331 required parking spaces, 265 standard parking spaces shall be Resolution No. 2009-10 Exhibit B Page 5 of 14 WE provided, which meet the minimum dimensions set forth in Section 17.50 of the RPVMC (9' width by 20' depth). 33. Of the 331 required parking spaces, a maximum 66 compact parking spaces are permitted, provided the spaces meet the minimum dimensions set forth in Section 17.50 of the RPVMC (8' width by 15' depth). 34. In addition to the required 331 parking spaces, the applicant shall provide a minimum of 3 loading spaces, which shall meet the minimum dimensions set forth in Section 17.50 of the RPVMC (10' width by 20' depth with 14' clearance). 35. In addition to the required 331 parking spaces, the property owner shall maintain 23 additional seasonal/peak parking spaces for overflow parking. The seasonal/peak parking spaces shall not be used when St. John Fisher Elementary School or Preschool is in session. 36. The seasonal/peak parking areas shall be planted and maintained with turf that is wear -resistant. 37. The seasonal/peak parking spaces shall meet the minimum dimensions and requirements for standard parking spaces (9' width by 20' depth) and compact parking standards (8' width by 15' depth). A maximum of 20% of the seasonal/peak parking spaces may be dedicated for compact parking. 38. The seasonal/peak parking areas shall be located in the areas depicted on the City Council -approved site plan. Specifically, a minimum of 23 seasonal/peak parking spaces shall be located in the turf area just south of Barrett Hall. 39. The property owner shall execute an agreement with the property owner of Daughters of Mary and Joseph, to be recorded with the County of Los Angeles, against both the subject property and the Daughters of Mary and Joseph property, prior to issuance of a building permit and/or grading permit, allowing St. John Fisher to use a minimum of 50% of the Daughters of Mary and Joseph paved parking spaces (45 spaces) for overflow parking on Christmas Eve, Easter Sunday and during the construction period. 40. Throughout all phases of demolition, construction and grading, the applicant shall make reasonable efforts to maintain the 331 required parking spaces. The property owner shall maintain a minimum of 217 non-seasonal/peak parking spaces for the sanctuary at all times during construction and prior to issuance of the Certificate of Occupancy of the new sanctuary. 41. No overnight parking or storage of vehicles associated with construction shall be permitted in the public right-of-way during construction. Building Heights and Square Footage 42. The new sanctuary shall not exceed a maximum footprint of 17,000 square feet Resolution No. 2009-10 Exhibit B Page 6 of 14 110 with a 900 square foot basement beneath the main floor. The new sanctuary shall not exceed a maximum height of 15'-0" at the northeast end of the structure and 60'-0" at the top of the steeple and 74'-0" at the top of the cross that is placed upon the steeple, which is located at the west end of the structure. The sanctuary shall be setback a minimum of 57'-0" from the west street -side property line along Crenshaw Boulevard and 62'-0" from the north street -side property line along Crest Road. BUILDING AREA CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO BUILDING PERMIT FINAL. SETBACK CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO POURING OF FOOTINGS. BUILDING HEIGHT CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO ROOF FRAMING/SHEETING INSPECTION. 43. The new administrative building, along the west side of the existing school, shall not exceed a maximum footprint of 7,488 square feet. Additionally, a 2,300 square foot basement beneath the main floor shall be permitted. The new administrative building shall not exceed a maximum height of 26'-0", as measured from lowest adjacent grade. BUILDING AREA CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO BUILDING PERMIT FINAL. BUILDING AREA CERTIFICATION IS REQUIRED. A LICENSED CIVIL ENGINEER OR SURVEYOR SHALL PREPARE THE CERTIFICATION. CERTIFICATION SHALL BE SUBMITTED TO THE CITY'S BUILDING OFFICIAL FOR REVIEW AND APPROVAL PRIOR TO BULDING PERMIT FINAL. Phasing 44. Installation of any temporary modular buildings, other than those used by the contractor during construction, shall require a Special Use Permit during all phases of the St. John Fisher Master Plan. Resolution No. 2009-10 Exhibit B Page 7 of 14 111 45. The proposed St. John Fisher Master Plan may be broken up into two main phases as described below. If within one year of the final effective date of the Notice of Decision, the applicant has not submitted an application for a building permit for the approved project or has not commenced the approved project as described in Phase One below, approval of the project shall expire and be of no further effect unless, prior to expiration, a written request for extension is filed with the Department of Planning, Building and Code Enforcement and approved by the Director. All elements of the approved Master Pian that are not submitted as described in Phase One and Phase Two below, shall require additional future review and approval through the CUP process and additional CEQA review. Phase One and Phase Two are described as follows: a. Phase One: Phase One includes the construction of the new sanctuary, remodel of the existing sanctuary into a gymnasium/parish activity center, construction of a new parking lot, demolition of the existing rectory and youth building on the north and east sides of the property, remodel/conversion of existing convent into rectory and site work that will not be impacted by future phase construction. The Planning Entitlements for all construction described under "Phase One" shall remain in full force and effect for a maximum of one (1) year from the final effective date of the Notice of Decision for the St. John Fisher Master Plan unless construction plans have been submitted to Building and Safety for plan check. b. Phase Two: Phase Two includes the construction of the new administration building, remodel the existing administration building into meeting rooms, construction of a new preschool, library, and art room and remaining site work associated with phase two construction. The Planning Entitlements for all construction described under "Phase Two" shall remain in full force and effect for a maximum of five (5) years from the final effective date of the Notice of Decision for the St. John Fisher Master Plan unless construction plans for the final phase of construction have been submitted to Building and Safety for plan check. Affordable Housinq Requirement 46. The property owner and/or applicant shall provide affordable housing as required by Section 17.11.140(A) (Affordable Housing) of the RPVMC prior to issuance of the first Certificate of Occupancy associated with the St. John Fisher Master Plan, unless the applicant demonstrates to the satisfaction of the Director of Planning, Building and Code Enforcement that they are exempted from such requirement pursuant to the exemptions described in Section 17.11.140(B) of the RPVMC. Landscaping Resolution No. 2009-10 Exhibit B Page 8 of 14 112 47. A Landscape Plan shall be submitted to the City and approved by the City's Landscape Consultant prior to issuance of a Building Permit or Grading Permit. The proposed landscaping shall be in substantial compliance with the City Council approved Landscape Plan and shall screen the new sanctuary from neighboring properties and the surrounding rights-of-way, consistent with the Applicant's photo simulations presented to the City Council on December 16, 2008, and shall be in substantial compliance with the site plan reviewed and approved by the City Council. The landscaping plan shall also indicate the species, growth rate and maximum heights of all proposed trees. 48. The applicant shall retain a majority of the existing mature trees located along the west street side property line, along Crenshaw Boulevard. Included in the Landscape Plan identified in Condition No. 51, the applicant shall submit a Tree Retention Plan indicating which existing trees will be removed and which trees will be maintained in a thriving manner along Crenshaw Boulevard. Said plan shall be reviewed and approved by the Director of Planning, Building and Code Enforcement prior to issuance of grading permits or building permits. If any of the retained mature trees become diseased or die, the trees shall be replaced by the Applicant within thirty days with a species of tree approved by the Director of Planning, Building and Code Enforcement. 49. All landscaping at the corner of Crest and Crenshaw Boulevard shall be planted and installed prior to issuance of Certificate of Occupancy of the new sanctuary to the satisfaction of the Director of Planning, Building and Code Enforcement. 50. New trees provided for screening of the new sanctuary at the corner of Crest Road and Crenshaw Boulevard shall be non -deciduous trees. 51. All existing trees that are not affected by the proposed construction, shall be maintained in a thriving manner. Any trees that become diseased or die shall be replaced within thirty days by the Applicant with a species of tree approved by the Director of Planning, Building and Code Enforcement. 52. Landscaping shall be provided and maintained along south property line, adjacent to the parking lot. In the event the required landscaping is destroyed and/or removed, the property owner shall either install a 5-0" tall masonry wall along the south property line or restore the landscaping to adequately screen the parking lot from the residential neighborhood to the south, as determined by the Director of Planning, Building and Code Enforcement. 53. Prior to issuance of a grading and/or building permit, the Applicant, St. John Fisher, shall fund a Trust Deposit in an amount of $18,500 to cover the cost of the installation of 24 -inch box New Zealand Christmas trees along the west side of Crenshaw Boulevard within the City's public right-of-way, south of Crest Road and north of the Island View entrance to help screen the new sanctuary building Resolution No. 2009-10 Exhibit B Page 9 of 14 113 from the four properties that abut Crenshaw Blvd at this location. The location of the trees and number of trees shall be determined by the Director of Planning, Building and Code Enforcement but in no case shall the number exceed 20 trees. Said trees shall be installed prior to the issuance of a Building Permit for the sanctuary. All costs for installation and future maintenance of said trees shall be fully paid for by the Applicant. The Applicant shall maintain said trees as directed by the City. Maintenance shall consist of trimming, watering, replacement, or spraying or other care of diseased or damaged trees. Prior to conducting maintenance on any of said trees, the Applicant shall provide proof to the City that any contractors used by the Applicant to maintain said trees are licensed, insured and bonded. If any of the trees die as a result of the negligent or willful action of a third party, the Applicant may attempt to recover the cost of replacing the tree from the third party, and the City shall reasonably cooperate with the Church in that effort. The trees shall not be installed adjacent to any property where the owner has notified the City in writing by June 1, 2009 that they do not want trees installed adjacent to their respective property. If all four property owners object to the planting of trees, the Applicant will not be required to pay for the installation or maintenance of said trees. Bell Schedule 54. The carillon bells are permitted to ring on the following days and times only: a. Monday through Saturday at 8:00 AM, 12:00 PM, and 6:00 PM; and b. Either shortly before or at the commencement of Sunday Masses, for a maximum of six (6) times, not before 8:50 AM or after 6:00 PM; and c. Christmas Eve Masses, but at no time before 8:00 AM or after 6:OOPM; and d. After Weddings, but at no time before 8:00 AM or after 6:OOPM; and e. After Funerals, but at no time before 8:00 AM or after 6:OOPM; and f. the following Holy Days: 1) The Assumption of the Blessed Mother (August 15), 2) All Saints Day (November 1), and 3) The Immaculate Conception (December 8), but at no time before 7:00 AM or after 6:OOPM. 55. The carillon bells shall not chime for more than a period of 90 seconds at each allotted time. 56. The speakers for the carillon bells shall be directed towards face the interior of the lot and shall not directly face any adjacent residential properties. 57. The speakers for the carillon bells shall not exceed a maximum height of 16'-0", as measured from grade, adjacent to the location of the bells on the sanctuary. 58. The speakers for the carillon bells shall be setback a minimum of 110'-5" from any property line, as noted on the approved project plans. Resolution No. 2009-10 Exhibit B Page 10 of 14 114 Signs 59. The speakers for the carillon bells shall only be used for the sounding of bells at the approved times. 60. The signage on the subject property shall be subject to the following conditions: a) One major wall sign at the corner of Crest Road and Crenshaw Boulevard, attached and parallel to the proposed building fagade of the new sanctuary. b) The maximum sign area shall not exceed a maximum of 75 square feet (63 square feet proposed). c) The signage shall not be internally illuminated. Indemnification 61. The owner of the property upon which the project is located shall hold harmless and indemnify the City, members of its City Council, boards, committees, commissions, officers, employees, servants, attorneys, volunteers, and agents serving as independent contractors in the role of city or agency officials, (collectively, "Indemnitees"), from any claim, demand, damage, liability, loss, cost or expense, including but not limited to death or injury to any person and injury to any property, resulting from willful misconduct, negligent acts, error or omissions of the owner, the applicant, the project operator, or any of their respective officers, employees, or agents, arising or claimed to arise, directly or indirectly, in whole or in part, out of, in conjunction with, resulting from, the maintenance of the trees adopted by the Applicant pursuant to Condition No. -53 or related to the construction approved by this resolution. Source Reduction and Recycling 62. Prior to issuance of any Certificate of Occupancy, the applicant shall prepare and submit to the Director of Public Works for review and approval a comprehensive Integrated Waste Management Plan (Plan) that addresses source reduction, reuse and recycling. 63. Prior to issuance of any building and/or grading permits, an approved Construction and Demolition Materials Management Plan (CDMMP) shall be prepared and submitted to the Director of Public Works for approval. 64. Prior to issuance of any Certificate of Occupancy, a Construction and Demolition Materials Disposition Summary (Summary) shall be submitted to the Director of Public Works upon completion of deconstruction and construction. The Summary Resolution No. 2009-10 Exhibit B Page 11 of 14 115 shall indicate actual recycling activities and compliance with the diversion requirement, based on weight tags or other sufficient documentation. 65. Where possible, the site design shall incorporate the use of recycled building materials and the re -use of on-site demolition debris. 66. The project site design shall incorporate areas for collection of solid waste with adequate space for separate collection of recyclables. Miscellaneous 67. The access stairs and ramp at the corner of Crest and Crenshaw shall only be installed if required by the California Building Code or Fire Department, and if required, shall not vary materially from the minimum specifications of size required by law. The applicant shall obtain an encroachment permit for any portion of the stairs or ramp which is located within the public right of way. 68. Prior to issuance of building permits and/or grading permits, the property owner shall submit final geotechnical and soils reports to the City for review and approval by the Building Official and the City's Geotechnical Consultant. All conditions specified in the approved geotechnical and soils reports shall be incorporated into the project. 69. Prior to the issuance of a building and/or grading permit from the City's Building and Safety Division, the applicant shall obtain NPDES approval from the City's NPDES consultant. 70. Prior to issuance of demolition, building, and/or grading permits, a construction haul route plan shall be submitted and approved by the City's Public Works Department. 71. The speakers attached to the existing sanctuary that is proposed to be remodeled into a new Parish Activity Center/Gymnasium shall be removed prior to issuance of certificate of occupancy for the new sanctuary. 72. Sports Activities in the Parish Activity Center/Gymnasium shall not be permitted after 10:00 P.M. without the review and approval from the Director of Planning, Building and Code Enforcement of a Special Use Permit. Bleachers shall not be used in the Parish Activity Center/Gymnasium. 73. The Parish Activity Center/Gymnasium shall not be used by unaffiliated sports leagues of which St. John Fisher is not a member without the review and approval by the Director of Planning, Building and Code Enforcement of a Special Use Permit. Future City Council Reviews Resolution No. 2009-10 Exhibit B Page 12 of 14 116 74. The carillon bells and the exterior lighting of the sanctuary shall be installed prior to issuance of a Certificate of Occupancy for the new sanctuary and shall be installed as shown on the approved plans. No later than two (2) months after issuance of a Certificate of Occupancy for the new sanctuary, the City Council shall review the impacts of the carillon bells and exterior sanctuary lighting to assess the effectiveness of the Conditions of Approval in minimizing the impacts of the bells and exterior sanctuary lighting to neighboring properties. At that time, the City Council may add, relieve, delete and/or modify any of the respective conditions of approval or may prohibit the use of the carillon bells and/or outdoor sanctuary lighting if the City Council determines that the imposed conditions are not effective in minimizing the sound and/or lighting effects to neighbors. Said modifications shall not result in substantial changes to the design of the sanctuary or other ancillary structures. Notice of said review hearing shall be published and provided to owners of property within a 500 -foot radius of the subject site, to persons requesting a notice, to all affected homeowner associations and to the property owner in accordance with the RPVMC. The City Council may require such subsequent additional reviews, as the City Council deems appropriate. 75. The effectiveness of the landscaping for screening the sanctuary pursuant to Condition No. 47, exterior sanctuary lighting, parking and the carillon bells shall be subject to review and modification, as deemed necessary and appropriate by the City Council, no later than one (1) year, and subsequently two (2) years, after the Certificate of Occupancy for the new sanctuary is issued. Notice of said review hearing shall be published and provided to owners of property within a 500' radius, to persons requesting notice, to all affected homeowners associations, and to the property owner in accordance with Rancho Palos Verdes Development Code Section 17.80.090. At that time, the City Council may add, delete, or modify the related conditions of approval as deemed necessary and appropriate by the City Council. The City Council may impose more restrictive standards and conditions to mitigate any impacts resulting from the installation of landscaping, lighting, parking and the carillon bells. 76. The Conditions of Approval contained herein shall be subject to review and modification, as deemed necessary and appropriate by the City Council, six (6) months after issuance of a final Certificate of Occupancy for all structures within Phase One, as defined in Condition No. 45. The City Council shall review the applicant's compliance with the conditions of approval, and to determine if the conditions are accomplishing their intended purposes. Notice of said review hearing shall be published and provided to owners of property within a 500' radius, to persons requesting notice, to all affected homeowners associations, and to the property owner in accordance with Rancho Palos Verdes Development Code Section 17.80.090. At that time, the City Council may add, delete, or modify the conditions of approval as deemed necessary and appropriate by the City Council. As part of the six month review, the City Council Resolution No. 2009-10 Exhibit B Page 13 of 14 117 shall consider the on-site lighting, parking conditions, circulation patterns and the hours of operation for the uses permitted on-site, in addition to other concerns raised by the City Council and/or interested parties. The City Council may impose more restrictive standards and conditions to mitigate any impacts resulting from the operation of the Project. 77. At any time in the future, the effectiveness of the parking conditions shall be reviewed by the City Council if the number of Sunday masses is reduced to four (4) or fewer Sunday masses for a period of time exceeding three (3) months. Notice of said review hearing shall be published and provided to owners of property within a 500' radius, to persons requesting notice, to all affected homeowners' associations, and to the property owner in accordance with Rancho Palos Verdes Development Code Section 17.80.090. Resolution No. 2009-10 Exhibit B Page 14 of 14 118