Loading...
CC SR 20160802 E - Corporation Yard StudyRANCHO PALOS VERDES CITY COUNCIL MEETING DATE: 08/02/2016 AGENDA REPORT AGENDA HEADING: Regular Business AGENDA DESCRIPTION: Consideration and possible action regarding a space needs study of the City's corporation yard RECOMMENDED COUNCIL ACTION: (1) Receive and file the Corporation Yard Needs Assessment Study prepared by Griffin Structures, Inc. FISCAL IMPACT: None Amount Budgeted: $30,000 Additional Appropriation: None Account Number(s): 330-3030-461-32-00 ORIGINATED BY: Andy Winje, PE, Senior Engineer; REVIEWED BY: Michael Throne, PE, Director of Public Works ?,,;�)O APPROVED BY: Doug Willmore, City Manager ATTACHED SUPPORTING DOCUMENTS: A. Corporation Yard Needs Assessment Study (page A-1) BACKGROUND AND DISCUSSION: The Public Works Department has been using a portion (about three and a half acres) of the Civic Center campus for equipment and material storage, contractor staging, refuse bin operations, rolling stock parking, and shop operations for many years (Page A-10 of Attachment A). Over time, the City's needs have evolved and these areas, known collectively as the Corporation Yard (Yard) have been used without the benefit of any space planning. In addition, very little has been done in the way of maintenance of the facility, especially regarding site security. The idea to re -secure the Yard boundaries with new fencing and gates last year led to a discussion of the appropriate size, layout and space needs of the facility. Griffin Structures, Inc. (Griffin) was commissioned to prepare a needs assessment study for $25,000 under the City Manager's contracting authority. The contract called for three primary deliverables: a Space Needs Assessment, a Conceptual Site Plan and a Probable Cost Estimate, which are included in the study (Attachment A). The process began with an analysis of the City's current operations and future needs. Space needs were then computed using established standards. Needs were examined in light of site 1 constraints and opportunities, and a site layout was developed for review by Staff. After review and acceptance of this site concept, a detailed (albeit very preliminary) cost estimate was prepared. With Staff's direction, Griffin assumed that future operations would revolve around Yard - based operations personnel. This is a change and improvement to current operations. There are no office facilities in the Yard at this time, but Staff believes that maintenance, operations and contractor management would be better served by a closer proximity of City maintenance personnel to the facilities, equipment and materials needed for delivery of services. The programming for the Yard also includes space to make small repairs and warehousing (indoor and outdoor) that support building, park, street and trail maintenance. In addition, an Emergency Operations Center (EOC) was included in the needs programming, based upon the assumption that a new facility could more easily be built to the "essential facility" standard necessary for an EOC than could retrofitting the current City Hall building. The total building facility was also assumed to meet the highest Leadership in Energy and Environmental Design (LEED) standard. The programming was computed in a modular fashion, allowing for removal of the EOC from Yard programming (for example) if it is preferred elsewhere on the campus. When parking and circulation areas are accounted for, the study determined a required site footprint that, when applied to the current site, is just under two acres (Pages A-12 & A-13), including a ±12,000 -square -foot building footprint. The concept also assumes using one of the former missile bunkers for storage. The needs of the Yard could be further compressed into an "ideal" site (e.g., rectangular, street corner, etc.) of about an acre -and -a -half, if such a location could be found elsewhere in the City (Page A-14). Finally, the study provides a "Conceptual Estimate of Probable Cost" for both on-site and "ideal" locations of between $12.89M and $12.78M, respectively, in 2016 dollars. These costs include estimated fees for planning and program management, design, permitting, construction management and inspection, construction, temporary facilities, FF&E (fixtures furnishings and equipment), electronic systems (including EOC technologies), builders risk insurance, utility connections and plan check. Contingencies were applied to design and construction era activities, but no overall contingency was added. The "ideal" location estimate does not include land acquisition. Staff recommends City Council receive and file this study in anticipation of future discussions regarding the Civic Center Master Plan and improvements to the City Hall campus. ALTERNATIVES: In addition to the Staff recommendation, the following alternative action is available for the City Council's consideration: Discuss and take other action related to this item. 2 t�4 o TS ITWM6 r, —4. 71%w- kl Rancho Palos Verdes Corporate Yard Needs Assessment Submitted: June 6, 2016 M GRIFFIN STRUCTURES, INC. Program and Construction V.anigers wx o TS ITWM6 r, —4. 71%w- kl Rancho Palos Verdes Corporate Yard Needs Assessment Submitted: June 6, 2016 M GRIFFIN STRUCTURES, INC. Program and Construction V.anigers Report Presented to The City of Rancho Palos Verdes, California Rancho Palos Verdes Corporate Yard Needs Assessment Including Space Needs Assessment Conceptual Site Design Conceptual Estimate of Probable Cost Report Submitted June 6, 2016 GRIFFIN STRUCTURES, INC. 2 Technology Drive, Suite 150, Irvine, CA 92618 949-497-9000 - www.griffinholdings.net A-2 TABLE OF CONTENTS TABLE OF CONTENTS..............................................................................................................................I INTRODUCTION....................................................................................................................................... THISPROJECT.................................................................................................................................................................................... I THISREPORT......................................................................................................................................................................................2 SPACE NEEDS ASSESSMENT.................................................................................................................. 3 YARD -BASED STAFF.......................................................................................................................................................................... 3 COMPUTATION OF SPACE REQUIREMENTS....................................................................................................................................4 QUALITATIVE CONSIDERATIONS....................................................................................................................................................6 CONCEPTUAL SITE PLAN....................................................................................................................... 7 EXISTINGSITE.................................................................................................................................................................................... 7 PROPOSED CONCEPTUAL SITE PLAN............................................................................................................................................. 8 OPTIONAL CONCEPTUAL SITE PLAN — MINIMAL FOOTPRINT & UNSPECIFIED LOCATION .................................................. I I CONCEPTUAL ESTIMATE OF PROBABLE COST............................................................................. 12 CONSTRUCTION ASSUMPTIONS, CLARIFICATIONS, AND EXCLUSIONS................................................................................... 14 ATTACHMENT I — DETAILED SPACE REQUIREMENTS DATA SHEETS ATTACHMENT 2 — CONCEPTUAL SITE PLAN ATTACHMENT 3 — CONCEPTUAL ESTIMATE Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Table of Contents — Page i A-3 INTRODUCTION THIS PROJECT This project has the objective of providing a complete and thorough space needs for the City's corporate yard area, to assess current and future use, address site security, identify an operational foot print, and ex- amine the spatial needs to increase productivity and efficiency. This study also includes recommenda- tions regarding cost effective modifications to accomplish City goals. The Space Needs Study has assessed the space requirements for all operational areas of the existing yard, and includes a review of the City's emergency protocols, inasmuch as the corporate yard will often serve as a first responder in the event of a major disaster. This study addresses operational practices, alterna- tives for space usage, and the analytics of space needs computation. The study scope includes office are- as, shop areas, covered areas, open areas, and parking needs for city, employee and visitor vehicles. We have reviewed best practices and related space allocations to assist the City in better supporting its con- tracted services. In execution of this work, Griffin has employed suitable space standards, based in part on information collected in the City and in part of the best -practices in place in other communities or promoted by vari- ous agencies. These have been applied to the projected operations so as to arrive at space requirements for each part of the operation. In the final step of the space analysis, we have added and allowance for circulation, building access, mechanical and systems, and special areas to obtain a total space requirement for the proposed facility. Our computation of space needs was also applied to the present operations, to compare the computed existing need with what is actually occupied now. Space was also then computed for projected future operations under City -approved scenarios. After the space needs were computed, a review was made of the existing site capacity and site usage op- portunities. A future Conceptual Site Plan was then developed that incorporates the findings of the space needs study into a visual tool for planning the future use of, and feasible modifications to, the site. On approval of this result, Griffin developed a Conceptual Statement of Probable Cost for the delivery of the identified improvements, in a format acceptable to the City. Project Deliverables By agreement, Griffin is to prepare the following items as deliverable products in the course of work in this project: • Space Assessment Report • Conceptual Site Plan • Conceptual Statement of Probable Cost Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page I &M11 THIS REPORT This document contains the elements of the items listed above: Space Needs Assessment, Conceptual Site Plan, and Conceptual Statement of Probable Cost. Our methodology is iterative: first the operations are examined and quantified, then the space needs are computed based on established standards and accumulation of overall requirements out of the analysis of the various component pieces, then the site is examined as to its constraints and opportunities, then the computed requirements are fitted to the site conditions and design review, and then a conceptual budget is prepared based on the implications of the design. SurveylbfO SpaceNeedsO Situ Site®esign0 StatementIMM Operations0 Assessment0 Opportunities0 andltayout(s)0 ProbableMostM 01 0 &Xonstraints0 0 —0 Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 2 A-5 SPACE NEEDSASSESSMENT 7_x;1 •I&I rel 9: Public Services yard space requirements depend on the services delivered from the yard, and the methods by which these services are provided. These requirements are therefore reflected in the types and sizes of shops, amount of equipment and materials stored, volume of rolling stock, numbers of employees, amount of employee parking, and the like. The yard operations at Rancho Palos Verdes are largely performed by contracted services, and so the yard area requirements are driven largely by the service levels, the technologies used to perform those services, and the implicit staff and equipment requirements of them. There are, however, some City staff and City - managed services (such as contract management and verification) which must be accounted for within the subject facilities. Accordingly, City staffing levels and staff deployment has a small but direct impact up- on the computation of space requirements, and it is necessary to identify projected staffing assignments to identify yard space needs. Griffin has discussed future contract as well as City -based operations with City management staff, and based future space needs on assumptions and guidelines given to us. This project does not contain any analysis of operations alternatives or alternatives in service delivery. We have, however, have taken a "modular" approach to the determination of space and the computation of requirements to include future assumptions of operational levels, staffing plans, and service requirements on a unit -by -unit basis, so space needs remain up to date with City objectives as they may evolve. The following exhibit presents the summary of City -based staffing levels and assumptions. Exhibit Staff Levels for Space Computation Shops Building Maintenance Now Future Comment / Note ADMINISTRATION AREAS Contracted services Marina Maintenance Contracted services Maintenance Superintendent 1 1 Contracted services Lead Worker 1 1 Future Offices 0 note Two positions allowed for future contingency Office Support Specialist 1 1 Located at entry reception point Administrative Crew 2 4 future space projected Maintenance Staff Workstations 2 2 EOC Areas No dedicated staff Shops Building Maintenance Contracted services Park Maintenance Contracted services Street Maintenance Contracted services Marina Maintenance Contracted services Refuse Contracted services Warehousing & Storage Contracted services Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 3 1 o COMPUTATION OF SPACE REQUIREMENTS The amount of space needed in a yard facility depends on several factors, including the number and de- ployment of staff to be accommodated, assumptions of operational needs (levels of service, types of equipment, etc.), allowances made for operational support areas (such as locker rooms, meeting areas, training areas, etc.), the needs for special operational areas, and assumptions of circulation and access within the site. The computation of these elements has been based on a sequence of activities beginning with data collection and including analysis of each functional area in turn. Data Collection. Our first step was to survey the current space use, observing the types and amount of space in use as well as tabulating the equipment in use, the nature of space, and areas of visible space deficiency or surplus. Following the survey process, we interviewed key City Staff regarding their services under contract, operations, staffing, space usage, earlier space planning, and long term re- quirements. Projection of Operations and Areas Required. We projected future space needs based on information obtained from each of the staff interviewed. In those interviews, we discuss the specific space needs of each respective unit, with an understanding of the workflow required to increase efficiencies where possible. We identified the types of spaces needed for operations, support spaces for contracted ser- vices, the capacity and use of those spaces, and the relation of the spaces to other areas of the yard. We also discussed distributed versus central lockers, lunchroom, support and reference areas, material storage, and others. Space Standards. We developed space standards for use in this project by (a) review of existing op- erational requirements and working conditions, (b) consideration of existing and projected activities, (c) analysis of established standards in use in other cities, and (d) consideration of future trends and the needs for flexibility and adaptability. For appropriate areas, space standards are used in compu- ting space requirements by applying the "unit" standards to the quantities applicable here. Computation of Space Requirements. The calculation of space requirements for each of the functions and operations in the yard was accomplished in large part by applying space standards to the required operational levels. For equipment areas, we use the existing allowance for items now in use as a baseline, and adjusted this square footage for future needs based on City -identified growth factors, space use efficiency, alternate racking and storage systems, etc. Tabulation and Summary. The requirements details are then tabulated on data sheets for each func- tion area. These detail sheets show the items, the space standards used, and the projected quantity and well as square footage requirement at each of the projection levels. This allows the City to ana- lyze the needs on an individual basis, and also to examine how requirements change from now to the future. The calculation of space requirements tabulated for each of the functions and operations in the yard was entered onto tabulation data sheets, which are presented in this report. We use the existing allowance for items now in use as a baseline in our space calculation, but have adjusted this square footage in the future projection period based on growth factors, space use efficiency, and other operations information ob- tained in our data collection. The requirements details are formatted and presented in terms of the existing organization. This allows for easier review and comment by the operating divisions involved. The detail sheets show the items, the space standards used, and the projected quantity and well as square footage requirement at each of the Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 4 A-7 projection levels. This also allows the City to analyze and examine how requirements change from pre- sent to the future. Administrative Areas Space is computed by application of appropriate office and support space standards to the projected City staff to arrive at space requirements for the workstations and offices in the Administrative Areas. We then add allowances for other rooms and functions, including filing and office support, storage, confer- ence rooms, public counters, and the like. Finally, we add an allowance for circulation within the net functional area of the department. This circulation allows for pathways inside a department's "suite" or working area, including both corridors and paths through the various open work areas or "bullpens" if they are programmed. The total of all this results in what we have termed "total net square feet" of the building requirements. EOC A City EOC is added to this program for several reasons, including the need to provide emergency re- sponse resources serving the department, and the fact that it is easier to incorporate the necessary struc- tural resistance levels in new construction than within the existing City Hall facilities. The proposed complex is planned around a large central room for primary operations, in which tables around the room can be used for response -team seating, and counters at the side can be used for charging stations and other support functions. A side conference room, in direct communication with the main operations room, is for executive policy decision-making during the time of activation. Other support areas include a small food and beverage station as well as integral storage facilities. Contract Services Contracted services are utilized as the primary approach for providing necessary resources to the city of Rancho Palos Verdes. As such, the yard has been programmed to support those functions, predominately covered areas and laydown space for materials, equipment storage and related items to ensure contractors have the necessary infrastructure for efficient operations and competitive pricing for their service con- tracts. Administrative spaces were programmed for City staff to specifically manage all service contracts including the City's anticipated future expectations for operations. Additional areas such as the lunch room, restrooms, and related operational support spaces have been provided as amenities to contract staff as well as the administrative City staff Space Requirements Detail and Summary The space requirements are divided into several types of space: • Administration areas: include executive office facilities, clerical areas, file space, and office support areas. • Offices and Shops: include contractor work areas, assembly space, workshop areas, and shop mate- rial / equipment storage. • Covered Areas: Typically, areas with canopy cover for shade or light protection from the elements. If functionally needed, may be secured with a lockable door, or may be in some cases designed with an open front, but may be enclosed on four sides. • Open Areas: includes areas that are fully open. • Parking: includes all City rolling stock, employee parking, and visitor parking. Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 5 1 • • Space is tabulated for (a) actual operations (to show a baseline of what is occupied now), (b) required op- erations (what is needed today), and (c) future operations (what is needed for the future). This allows for blocking or stacking the space needs, examining the implications of alternatives, and examination of changes presented by each scenario. The detailed requirements, computed according to the approach, methodology and assumptions discussed above, are presented in Attachment 1 to this document. The following exhibit provides a summary of these space requirements, including allowances for circula- tion which provides not only for the individual items which require space, but also for the access to and around those items, site driveways, set -backs, minimal required landscaping, and other elements which are part of the total site space requirement. Exhibit Summary of Space Requirements by Type of Space Actual Footprint Admin Building / EOC/ Shop Areas 5,341 Covered Areas 523 Open Areas 17,071 Equipment Rolling Stock 4,400 Employee Parking 1,000 Visitor Parking 600 Subtotal (sq. ft.) 28,935 Site Circulation / Roadway 82,606 Site Setbacks and Contingency 38,727 Total Site Requirement 150,268 Total (acres) 3.45 QUALITATIVE CONSIDERATIONS Footprint GSF/Access REQ'D Footprint GSF/Access FUTURE Req'd Allowance SITE SF Future Allowance SITE SF 9,324 50% 13,989 9,931 50% 14,897 5,880 25% 7,350 5,880 25% 7,350 3,800 25% 4,750 3,800 25% 4,750 4,400 100% 8,800 4,400 100% 8,800 3,000 100% 6,000 4,800 100% 9,600 600 100% 1,200 600 100% 1,200 27,004 42,086 29,411 46,597 50.0% 21,043 50.0% 23,299 15.0% 9,469 15.0% 10,484 72,599 80,380 1.67 1.85 Quantitative needs, discussed above, are a major part of the needs assessment process, but another, and very critical consideration, is the set of qualitative requirements which apply. These non -quantitative considerations include proximity and adjacency requirements, security control, special HVAC (and other environmental) needs, and various design requirements for surfaces materials, durability, maintainability, and so on. Specific notes have been provided as part of the detailed needs assessment located in Attach- ment 1. Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment - Report Submitted by Griffin Structures, Inc. Page 6 1 • CONCEPTUAL SITE PLAN Conceptual site plans for this project are included as Attachment 2 to this document. These plans are based on the existing site conditions, the projected quantitative requirements (above), and an assessment of the functional requirements for these operations. EXISTING SITE Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 7 A-10 The above site plan shows the city hall buildings, which are situated generally to the north of the area shown, and the primary yard facilities which are located generally to the south. The yard area also in- cludes old Nike silo structures which are inactive. The south site area is the intended location of yard im- provements, and the architectural analysis, site constraint assessment, and opportunities review show that this can be accomplished. As such, one of the Nike silo structures is located within the parameters of the suggested concept site plan. After reviewing the options of preserving or reusing this facility for yard functions, it was deemed cost prohibitive and we have suggested to cap the lid of the silo to make the cir- culation on this part of the site much more efficient. PROPOSED CONCEPTUAL SITE PLAN The following three exhibits shows the proposed plan. The first is a larger site plan showing total context, and the second exhibit is an enlargement (with background) showing the yard areas. The third exhibit is the enlargement shown without background. Due to the irregularity of the site's shape, the circulation factors increase the overall square footage from what was suggested in the space assessment. Exhibit Overall Proposed Conceptual Site Plan Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 8 A-11 Exhibit Enlarged Proposed Conceptual Site Plan — With Background .V r _ .- nc.. - f!F. Area: 85,670 SF — 1.47 Acre Bin 2 Bin 3 + * S., r4 . MR,5 Bin Refuss o), ENLARW S1j N -6jjDUT _ -2f8 Scale • .).i w _ __. ���'��� �•�h �+,� � Ai ♦.ten-_•_ r.a Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 9 A-12 Generate� Exhibit Enlarged Proposed Conceptual Site Plan — Without Background B 40 y Staff, Coniractor/Vendor & Visitor Parking Visitor Gate 20 Shop & Storage Bldg. EOC & Policy Room Administration Bldg. 5,200 SF 2,340 SF 3,210 SF I Yard Area: 85,570 SF = 1,97 Acre Bin 1 Bin 2 Bin 3 Bin G Laydown Areas ♦ 1 910 Sf ' Bin 4 1 Bin 5 Bin R u Bin ransf y L[ 4 -waydown NOW !uses - - - 2,425 SF Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 10 A-13 OPTIONAL CONCEPTUAL SITE PLAN — MINIMAL FOOTPRINT & UNSPECIFIED LOCATION An alternate site plan was also developed, based on a minimal site footprint on a hypothetical and unspec- ified site. This option is shown in the following exhibit (enlarged, without background). Exhibit Enlarged Alternative/Optional Conceptual Site Plan — Without Background Unspecified Site Location Area: 68,400 SF = 1.57 Acre SECONDARY STREET + * 18 10 Shop & Storage Bldg. EDC & Policy Room 4,465 SF 2,340 SF Administration Bldg. 1 3,210 SF 6 12 r Bin 1 Bin 2 Bin 3 Bin 4 Bin 5 I Laydown Areas j 1,300 SF Bin 6 Bin'' R Bi [rci - -- ---------1 Emerger------------ - - - - -- Laydown Areas - - - - - Generator 2,500 SF ------------------------------- 1— W LU fY ri N Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment - Report Submitted by Griffin Structures, Inc. Page I I A-14 CONCEPTUAL ESTIMATE OF PROBABLE COST A programmatic budget has been prepared based on the Corporate Yard program requirements and con- ceptual site plan. This is a total project conceptual budget, which is thorough and detailed appropriate to the scope of conceptual -level design and project description. As shown in the below diagram, a series of calculated steps have been performed to arrive at the pro- grammatic budget. Public Input Design Principles Unit Costs& Confirmed Market Analysis Amenities Analysis Needs Assessment Net Bldg SF Site Plan Gross Bldg SF & Programmatic Non -Bldg Areas Budget Parking Stalls It is intended that these budgets will be refined as the design process continues, however, the estimate may be relied on for planning and "order of magnitude" budgeting purposes. Thus, if the design assump- tions and criteria remain the same, the figures represented here may be refined downwards during future design phases. The costs presented here represent reasonable conceptual total project budgets with an ap- propriate contingency, and we expect these will not likely escalate as the project progresses, assuming no material changes in project scope, upgrades in identified materials assumptions, adverse revelations re- garding unknown sub -soil conditions or hazardous materials, or other such changes in the project defini- tions. The following pages present the results of applying our cost models on the assumptions and details asso- ciated with the programmed facility requirements, based on a tradition design -bid -build methodology. Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 12 A-15 Exhibit Conceptual Estimate of Probable Cost Based on the Proposed Site Plan and as Qualified by the Attached Notations Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment - Report Submitted by Griffin Structures, Inc. Page 13 A-16 COMPONENT Concept 1 Concept 2 COMMENTS 1 PRE -CONSTRUCTION SERVICES ._....�„_..w,w._- eµ 120,000 120,000 Allowance Pro ram Mana eme...._._...... Incl Incl �I Scheduling Incl Incl Estimatin Incl Incl Design Team Management Incl Incl .................................................................................................................................................................................................................................................................................................................................................................................................................. Develo ment of Guaranteed Maximum Price Incl Incl .................................................................................................................................................................................................................................................................................................................................................................................................................. Reimburs ables Incl Incl 2 A/E SERVICES 840,000834,000 Allowance ...__.._....- ...._................_....._.._.._......._____.______.._.._. ._____________.m____ Conce tual Desi n _ Incl ._....... ._....._.._...._..._c .__.......__.___......_.._....._._._.._......_._.......__...__._._.__..._________._._._......_... Inl - Schematic Desi n Incl Incl Design Development Incl Incl Construction Documents Incl Incl ...__.....__ _....Bidd.........___................________......_.......................�_._.... ..... Bidding _____........._._. Incl _......................_.. �........... Incl Construction Administration Incl Incl ........................a-b-l...s.................._...___................................_...................................................................................................................Inc[ Reimbursables Incl __-.__..........................................................__._._..._.._.....___..._.._._....___. Incl FF&E Design & Procurement Services Incl Incl Design Fee Contingency 42,000 42,000 Allowance 3 IGEOTECHNICAL Soils Resorts Buildin s, Parkin Areas 35,000 35,000 Allowance 4 ENVIRONMENTAL Phase 1 ESA 10,000 10,000 Allowance Phase 2 Report 0 0 Assumes that Phase 1 will not require a Phase 2 report .................................................................................................................................................................................................................................................................................................................................................................................................................. CEQA 0 0 Assumes that Cit will determine the ro'ect is exem t from CEQA ...................................................................................................................................................................................................................................... 5 DEPUTY TESTING AND INSPECTION -..............--.......--................ .................................... ..................................... .............................. ..................... Soils Testing 75,000 75,000 Allowance ........................................................., ................................................................................................................................................................................................................................................................................................... Matenals Testin 100,000 100,000 Allowance Roofing Inspections 15,000 15,000 Allowance 6 DIRECT COSTS 9,337,000 9,268,000 New Administration Buildin Incl Inc( New Shop and Stora a Buildin Incl Incl New EOC Building Incl Incl New Material Bins w/ Canopy Incl Incl Sitework (Fencing, Utilities, Demolition, Paving, Landscaping, etc) Incl Incl Includes concrete cap over abandoned missle silo Course of Construction Contin enc 934,000 927,000 10.00 7 TEMPORARY FACILITIES DURING CONSTRUCTION Temporary Trailers 25,000 0 8 1 FIXTURES, FURNISHINGS, & EQUIPMENT FF&E Office Furniture Administration Buildina and ECC 160,000 160,000 Allowance based on 6,400 SF at 25/SF EOC Audio / Visual Equipment 450,000 450,000 Allowance Sho Shelvin 501000 50,000 Excludes all related sho a ui ment such as tools, machine , etc. Misc. Furnishings and Fixtures 25,000 25,000 Allowance ................................................id............................................................................................................................................................................................................................................................................................................................................................. 9 ELECTRONIC SYSTEMS AND SPECIAL EQUIPMENT .................................................................................................................................................................................................................................................................................................................................................................................................................. Computers, Phones, Servers, Scanners, Fax Machines, Copiers Not included Not included City TBD PROGRAM 4;ONSTRUCTION MANAGEMENT ,10 ..............................................................................................................................................................................................................................................................................................d'u"......................... Overhead, Fee &Administration costs 450,000 Gi:i..r......................................................... 450,000 Assumes 4 da s/week Burin construction Reimbursables25,000 25,000 Includes online document management software .................... ............................................................................................ ............................................................................ Le al ............................... 1,500 ............................... ...................................................... :............... ............................................................. ..................... 1,500 Insurance__._,-_.._�.._.._........._....._..___ 5,000 5,000 ...__.......... _.......___....-..............._.._.. Contin enc .........._....._.._ 50,000 ...._._......_.-..........-.... _______......_-.._....._. .___...... 50,000 _______. 11 __.....-..................-...___.............._......_.._.................._........_______....-....._._........_ OWNERS BUILDERS RISK INSURANCE _......-..-..-........._....._.-..............-.........._ See Note .._........................ See Note Included in Direct Costs 12 .................................._.........................................................._._._._.._....-_....._.._.._..._._._......_ UTILITY COMPANY CONNECTION SERVICES AND FEES ._............................._.._.................................._.___________._.._..._................. Southern California Edison SCE / Gas CompanX 10,000 10,000 Allowance: Ci of Rancho Palos Verdes Phone/Data Service for new buildings 10,000 10,000 Allowance: City of Rancho Palos Verdes Cable TV for new Admin / EOC Building 7,500 7,500 Allowance: City of Rancho Palos Verdes Water/Sewer for new buildings 10,000 10,000 Allowance: City of Rancho Palos Verdes 13 CITY OF RANCHO PALOS VERDES FEES AND ADMINISTRATION Plan Check, Permit Fees, and Buildin Ins ections 100,000 100,000 Allowance: Cit of Rancho Palos Verdes 14 CONTINGENCY: CITY OF RANCHO PALOS VERDES See Note See Note City TBD CONCEPTUAL STATEMENT OF PROBABLE COST $12,887,000 $12,780,000 Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment - Report Submitted by Griffin Structures, Inc. Page 13 A-16 CONSTRUCTION ASSUMPTIONS, CLARIFICATIONS, AND EXCLUSIONS General Items • Griffin Structures, Inc. is offering this Statement of Probable Cost based on current level of documen- tation available which is based upon conceptual drawings. Griffin has used its reasonable best efforts to assess identified project specific program requirements, geographic considerations, assumed build- ing type, construction methods, current labor rates and material costs, and local market conditions to generate an opinion of possible project specific costs. Griffin cannot be held responsible for adjust- ments to this estimate which could produce amendments to subsequent and future project budget up- dates based upon changes in project specific requirements or unforeseen adjustments in local market conditions affecting both direct and indirect costs. • Programmatic Budget is based on May 2016 values, and includes future estimated escalation based on a midpoint of construction of December 2017. • Programmatic Budget is based on the needs assessment and programmatic space requirements devel- oped by Griffin Structures, and conceptual site analysis and plans developed by GPa Architects. • Construction budgets are based on the City of Rancho Palos Verdes contracting for the completion of the complete facility and site work improvements in a continuous phase to a single General Contrac- tor. Neither multiple prime contractors nor phased construction is included. • Construction budgets are based on State of California Prevailing Wages only and do not include Fed- eral funding wages and requirements. • Budget excludes all environmental consultant fees required for the Environmental Impact Report (EIR) and/or California Environmental Quality Act (CEQA) process. • Budget excludes any costs associated with hazardous material remediation and it is assumed that the Phase 1 will not require a Phase 2 report. • Budget includes fees associated with obtaining a LEED Platinum certification from the USGBC. • Budget includes temporary facilities during construction such as storage space. • Owners course of construction builders risk insurance is included within the direct costs. • The budget excludes all design and construction efforts in upgrading the existing generator. Instead, a new generator is budgeted to serve the site and related operation. Site Work • Budget assumes Southern California Edison (SCE) will increase service using installation allowances. • Budget assumes Gas Company will provide new or relocated services using installation allowances. • Budget assumes existing water pressures are adequate for domestic, fire, and irrigation water for the site and buildings without the need for pressure booster pumps. Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Page 14 A-17 ATTACHMENT I - DETAILED SPACE REQUIREMENTS DATA SHEETS Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Attachment I 1 • • Computation of Space Requirements Data Sheets Line Department/Division/Title Space Standard Actual Sq.Ft. Required Need Future - On Site Comment Name Code Sq.Ft. SL Staff Qty Sq.Ft. Staff Qty Sq.Ft. 1 ADMINISTRATION AREAS 2 Administration 3 Private Offices 4 Maintenance Supertintendent PO -4 180 150 1 1 180 120 1 1 1 1 0 2 180 Sean Larvenz 5 Lead Worker PO -2 120 1 80 1 1 120 1 Gonzalo Garnica 6 Future Offices PO -2 120 0 0 0 240 Future Growth Future 7 8 Open Work Areas & Cubicles 9 Office Support Specialist recept-1 120 100 1 120 1 120 Located at entry reception point 10 Includes communication system, typewriter, printer, and counter for public check-in I I Guest Seating seat -2 30 60 2 60 2 60 12 Small Lobby allow 60 80 1 60 1 60 13 14 Printer print -2 20 40 1 20 1 20 15 Mail Boxes with Assembly Counter allow 20 incl above 1 20 1 20 16 17 Other Rooms and Areas 18 Administrative Crew Room 90 2 2 4 19 Maintenance Staff Workstations en -b 48 incl above 96 4 192 future space projected Banuelos, Valadez 20 Locker Area locker -2 10 incl above 40 8 80 21 File Storage Iat-5 15 incl above 2 30 4 60 22 Reference Material, Supplies, Etc. allow 60 incl above 1 60 1 60 23 24 Conference Room C-7 420 400 1 420 1 420 Sits 16-20 people; doubles as DOC 25 Emergency Closet closet -2 90 145 1 90 1 90 Contains emergency supplies, cots, etc. 26 27 Lunch Room 240 400 500 28 Warming Kitchen kitchen -w 180 incl above I I 29 Pantry allow 90 incl above 1 1 30 Vending Area allow 20 incl above 1 1 31 Seating - dining chair -dine 25 incl above 4 8 32 Trash / Recycling Bin bin 10 incl above 1 1 33 34 Staff Lavatories allow 100 180 2 200 2 200 35 Shower / Changing Room shower -2 100 1 100 1 100 DOC Support 36 janitorial Closet allow 30 30 1 30 1 30 37 Server / MDF Room allow 120 90 1 120 1 120 2 server racks 38 39 Administration Area Subtotal 40 41 Subtotal Usable SF 1,685 2,166 2,672 42 Unit Circulation unit circ -4 20% 337 433 534 43 Total Net Sq. Ft. 2,022 2,599 3,206 44 45 46 47 48 49 50 51 52 53 54 Griffin Structures, Inc. Program and Construction Managers Rancho Palos Verdes Corporate Yard Needs Assessment Page 1 Computation of Space Requirements Data Sheets Griffin Structures, Inc. Program and Construction Managers Rancho Palos Verdes Corporate Yard Needs Assessment Page 2 Space... I Emerizency Operations Center (E• no Administration m■■■ Rooms .. Areas NZIMIMIMEmergency Operations Center Room Room to be set up in 6, 5 -person pods 1111MMIMInclude counters on side room for charging stations, also include plenty of wall space for whiteboards, TV screens, and projector sc7eeM. NEW KIM 1111MMIM MESIMINE MIM m■■■■■ EOC Supply�� .. ��� NIMMIMI 0 MEN EOC Subtotal m■■■■■ MEN GINNIE 131MIMEM Subtotal Usable SF NEW INEW I M! 1111MMIM Unit Circulation 1311MMIM Total Net Sq. Ft. NZIMEMIM NZIMEMIM NZIMINEM NZIMINEM I --1-I _EME INIME 011011 1111MMIM MIMMEEMEMEME _EME 11MEMEMINE MIM NZIMIMIM I --1-I _EMEI 11M INIME 011011 1111MMIM I--ME111111 _-1 11MEMEMINE MIM MENNEN MEEMEMEME SEI IIMMEEIMMEMI MIM 111■■■■M MEEMEMEI 11MEME 11MEMEMINE 0 1 M■■■■■ MEEMEMEME SEI MIMMEMEMMIN I MENNEN MEEMEMEME 11MEME 111MEME I MENNEN MEEMEMEME 11MEME 11MEME MENNEN MEEMEMEME 11MEME 11MEME MENNEN MEEMEME1 11MEME I M■■■■■ MEEMEMEME MIMME�I M■■■■■ 1��1�1 �� �I Griffin Structures, Inc. Program and Construction Managers Rancho Palos Verdes Corporate Yard Needs Assessment Page 2 Computation of Space Requirements Data Sheets Griffin Structures, Inc. Program and Construction Managers Rancho Palos Verdes Corporate Yard Needs Assessment Page 3 A-21 Department/Division/Title Space Standard Actual Sq.Ft. Required Need Future - On Site Comment Name Code Sq.Ft. Staff Qty Sq.Ft. Staff Qty Sq.Ft. log SHOPS AREAS 110 Maintenance III Shop / Work Area 112 Workcounter allow 150 300 1 150 1 150 includes table saw, drill press, sanding machine 113 Workstation sws 25 incl abve 1 25 1 25 114 File Cabinet file 10 incl abve 2 20 2 20 2 30 Includes tools, safety equipment, etc. 115 Tool Storage stg cab 15 incl abve 2 30 116 Air Compressor air -2 10 incl abve 1 10 1 10 117 Paint, Adhesives, etc. stg cab 15 3 45 3 45 Flammables 118 Misc Equipment Storage allow 100 incl abve 1 100 1 100 119 Misc Material Storage allow 100 incl abve 1 100 1 100 Non Flammables 120 121 Subtotal Usable SF 300 0 480 0 480 192 122 Unit Circulation unit circ -8 40% 100 192 123 Total Net Sq. Ft. 400 Q 672 672 124 125 126 Storage Areas 127 Building Maintenance Materials allow 300 250 1 300 1 300 128 129 Park Maintenance Materials 180 300 300 130 Shovels, rakes, weed whackers, etc. racked sto 120 incl above I I 131 Lawn roller, blowers, inverter allow 60 incl above 1 1 132 Tool box stg cab 15 incl above 2 2 133 Janitorial supplies, cocking, lubricants, paint, tarps allow 90 incl above 1 1 134 135 Warehouse Storage allow 300 300 1 300 1 300 includes files, misc furniture, et al 136 Holiday Storage allow 120 125 1 120 1 120 Locate with warehouse storage 137 Public Works Engineering Records Storage Iat-5 15 375 20 300 20 300 Locate with warehouse storage 138 139 Street Maintenance Storage 600 625 625 140 Sign Rack sign -5 240 incl above I I organize into racking system 141 Paint Pallet Paint room 120 incl above 2 2 Nonflammable 142 Adhesives, Chemicals, etc. stg cab 15 incl above 3 3 Flammable; included w above paint room 143 Quikrete Pallet pallet -1 50 incl above 2 2 144 Unused Areas / Old Materials, etc. 200 Discard for future 145 146 Marina Maintenance Storage allow 300 366 1 300 1 300 147 Emergency Storage Supplies allow 400 [450] 1 400 1 400 Includes emergency delineators, etc. 148 149 150 Subtotal Usable SF 2,396 1 0 2,645 0 2,645 1,058 151 Unit Circulation unit circ -8 40% 523 1,058 152 Total Net Sq. Ft. 2,9190 3,703 0 3,703 1 153 154 Shop Area Subtotal il 155 156 Total Usable SF 2,696 0 0 3,125 0 3,125 0 1,250 157 Total Circulation Allowances 623 1,250 158 Total Net Sq. Ft. 3,319 0 4,375 0 4,375 159 160 161 162 Griffin Structures, Inc. Program and Construction Managers Rancho Palos Verdes Corporate Yard Needs Assessment Page 3 A-21 Computation of Space Requirements Data Sheets Line Department/Division/Title Space Standard Actual Sq.Ft. Required Need Future - On Site Comment Name Code Sq.Ft. Staff Qty Sq.Ft. Staff Qty Sq.Ft. 163 COVERED AREAS 164 Materials Bin(s) 165 Bin 1 166 Wood Stumps, large tree pieces, etc. allow 400 [816] 1 400 1 400 167 Bin 2 168 Wood Chips allow 400 [349] 1 400 1 400 169 Bin 3 170 Decomposed Granite allow 400 [352] 1 400 1 400 171 Bin 4 172 Sand allow 400 [356] 1 400 1 400 Locate next to Sand Bag Area 173 Bin 5 174 Sand Bag Storage allow 200 [537] 1 200 1 200 Store on organized pallets 175 Sand Bag Prep Area allow 200 [ 196] 1 200 1 200 176 Bin 6 177 Lumber Storage rack -5 200 [485] 1 200 1 200 Racked vertically 178 Sign Posts rack -5 200 xxx 1 200 1 200 Racked vertically 179 PVC Pipe Storage rack -5 200 [1 1 10] 1 200 1 200 Racked vertically 180 Bin 7 181 Material Wash Bay allow 200 1 200 1 200 182 Note: includes power washer and drain 183 184 Refuse Bins 185 Steel Waste Collection bin -3 200 [200] 1 200 1 200 8'x20' plus circulation 186 Electronic Waste Collection bin -3 200 [200] 1 200 1 200 8'x20' plus circulation 187 Bulk Item Collection bin -3 200 [200] 1 200 1 200 8'x20' plus circulation 188 Catch Basin Collection bin -3 200 [200] 1 200 1 200 8'x20' plus circulation 189 Green Waste bin -3 200 [200] 1 200 1 200 8'x20' plus circulation 190 Transfer Area allow 400 [650] 1 400 1 400 Utilized for sorting materials into bins 191 192 193 Covered Area Subtotal 194 195 Subtotal Usable SF 0 4,200 4,200 196 Unit Circulation unit circ -8 40% 523 1,680 1,680 197 Total Net Sq. Ft. 523 5,880 5,880 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 Griffin Structures, Inc. Program and Construction Managers Rancho Palos Verdes Corporate Yard Needs Assessment Page 4 A-22 Computation of Space Requirements Data Sheets Line Department/Division/Title Space Standard Actual Sq.Ft. Required Need Future - On Site Comment Name Code Sq.Ft. Staff I Qty Sq.Ft. Staff Qty Sq.Ft. 217 OPEN AREAS 218 Shared by All 219 Open Areas 220 General City Laydown Storage allow 2000 712 1 2,000 1 2,000 Misc equipment 221 Landscape Materials, Scoops, Etc. allow 600 1,350 1 600 1 600 222 Marina Materials allow 400 458 1 400 1 400 223 224 Refuse Contractor Storage Area allow 800 1,250 1 800 1 800 Includes trash bin staging and storage area 225 Emergency Storage Supplies [450] See Enclosed Areas above for required and future need 226 227 Refuse Bins 228 Steel Waste Collection 200 See Covered Areas above for required and future need 229 Electronic Waste Collection 200 See Covered Areas above for required and future need 230 Bulk Item Collection 200 See Covered Areas above for required and future need 231 Catch Basin Collection 200 See Covered Areas above for required and future need 232 Green Waste 200 See Covered Areas above for required and future need 233 Transfer Area 650 See Covered Areas above for required and future need 234 235 Materials Bin(s) 236 Wood Stumps, large tree pieces, etc. 816 See Covered Areas above for required and future need 237 Wood Chips 349 See Covered Areas above for required and future need 238 Decomposed Granite 352 See Covered Areas above for required and future need 239 Sand 356 See Covered Areas above for required and future need 240 Sand Bag Storage 537 See Covered Areas above for required and future need 241 Sand Bag Prep Area 196 See Covered Areas above for required and future need 242 Lumber Storage 485 See Covered Areas above for required and future need 243 PVC Pipe Storage 1,110 See Covered Areas above for required and future need 244 245 Asphalt Grindings 4,850 0 0 0 0 Not needed for future 246 Concrete Grindings 2,600 0 0 0 0 Not needed for future 247 248 Emergency Generator 249 250 251 Subtotal Usable SF 17,071 3,800 3,800 252 Unit Circulation incl above 0 0 253 Total Net Sq. Ft. 17,071 3,800 3,800 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 Griffin Structures, Inc. Program and Construction Managers Rancho Palos Verdes Corporate Yard Needs Assessment Page 5 A-23 Rancho Palos Verdes Corporate Yard Vehicle Projections Line Standards Dimensions Sq.Ft. Total I Bay-pkg-XLL 15 x 50 750 I Bay-pkg-XL 12 x 35 420 2 Bay-pkg-X 12 x 30 360 3 Bay-pkg-H 12 x 25 300 4 Bay-pkg-M 10 x 20 200 5 6 Equipment List Space Standard Required 7 Division Vehicle Description Code Sq.Ft. Qty Sq.Ft. 8 9 Vehicles Owned 10 PRIUS HYBRID 2006 - WHITE (PW) Bay-pkg-M 200 1.0 200 11 RECREATION VAN 2006 Bay-pkg-M 200 1.0 200 12 RECREATION BUS 2006 Bay-pkg-H 300 1.0 300 13 PRIUS HYBRID 2007 - BLUE (PBCE) Bay-pkg-M 200 0.0 0 14 PRIUS HYBRID 2007 - GREEN (PBCE) Bay-pkg-M 200 0.0 0 I5 TRUCK, 4X4 WITH LIGHT BAR (PW) Bay-pkg-M 200 1.0 200 16 FORD ESCAPE 2009 W/ LIGHT BAR (PW) Bay-pkg-M 200 1.0 200 17 FORD RANGER XLT 4X4 2011 Bay-pkg-M 200 1.0 200 18 FORD RANGER XLT 4X4 2011 Bay-pkg-M 200 1.0 200 19 GATOR UTILITY VEHICLE HPX 4X4 GAS Bay-pkg-M 200 1.0 200 20 RADAR TRAILER Bay-pkg-M 200 1.0 200 21 CHEV EQUINOX -AUTO SUV Bay-pkg-M 200 0.0 0 22 CHEV EQUINOX -COMMERCIAL SUV Bay-pkg-M 200 0.0 0 23 SIGN BOARD TRAILER I (PW) Bay-pkg-M 200 1.0 200 24 SIGN BOARD TRAILER 2 (PW) Bay-pkg-M 200 1.0 200 25 UTILITY TRAILER (WHITE) (PW) Bay-pkg-M 200 1.0 200 26 FORD F350 4X4 DRW 2015 (PW) Bay-pkg-H 300 1.0 300 27 DECKOVER TILT BED TRAILER 2015 (PW) Bay-pkg-M 200 1.0 200 28 UTILITY TRAILER (BLACK) Bay-pkg-M 200 1.0 200 29 30 Vehicles Rented 31 5YD DUMP TRUCK Bay-pkg-H 300 1.0 300 32 EQUIPMENT TRAILER Bay-pkg-H 300 1.0 300 33 BACKHOE Bay-pkg-H 300 1.0 300 34 HI -LIFT FORKLIFT Bay-pkg-H 300 1.0 300 35 36 Note: 2 of the above stalls are dedicated for electric vehicles. 37 38 TOTAL 19.0 4,400 39 40 41 42 43 44 Equipment List Space Standard Required 45 Division Vehicle Description Code Sq.Ft. Qty Sq.Ft. 46 47 Staff Sedans Bay-pkg-M 200 9.0 1,800 48 Contractor Sedans Bay-pkg-M 200 15.0 3,000 49 Visitors / ADA Sedans Bay-pkg-M 200 3.0 600 50 51 Note: 2 of the above stalls are dedicated for electric vehicles. 52 53 54 55 56 57 58 59 60 61 62 A-24 ATTACHMENT 2 - CONCEPTUAL SITE PLAN Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Attachment 2 A-25 o� FULL SITE PLAN -1 r3 Scale : 1/128" = 1'-0" I�oress�mre�aae�a ma �oi�n�iaal ololo GRIFFIN STRUCTURES. IN�k$-1r3 Lu D ry Lu cn O QO � L J = U Z 4-J W b ~ LL. 0 O Cl. ® 0 LL UU GRIFFIN STRUCTURES. IN�k$-1r3 4� _ �, I . � it .�--�•_ �► ♦ �, � r. i jAf `� r� r IbN s 1 f' I • f r ' ^ - • �R __ • li,, _ of of o r I" ' • • Y . . " • Ir h �i I .• • WW �� Bin 3,,111Lay Area: 85,670 SF = 1.97 Acres + * �►: f n .. rvi 4 ' 5 "Ref __.' t- o� UT ENLARM S11, ,E'a N �. •O' , x; �►;�'•��`1,� — _ -2r3 scale A: • ' «' A, zv o z z o 8 u Yi cn LU LU � o W J ¢ L O ro LU z4 -J 0L. ® w LL. 0 �- Q ca U ES, IN_ 0-2r3 Ge rato Staff, ContractorNendor & Visitor Parking Shop & Storage Bldg. 5,200 SF Area: 85,670 SF = 1.97 Acre ENLARGED SITE PLAN - LAYOUT 1 Scale: 1/32" = P-0" 20 EOC & Policy Room 2,340 SF 1E1 Bin 1 Bin 4 Bin 5 Bi 7 13 Visitor Gate Administration Bldg. 3,210 SF 6 5 Laydown Areas 910 SF - --------------------------------- Laydown Areas 2,425 SF Yard Ga 0 ') U-) ce I-- 77 O a Bin 2 Bin 3 Bin 6 nj Q Lu I R us Bin ITransf.1 Laydown Areas 910 SF - --------------------------------- Laydown Areas 2,425 SF Yard Ga 0 ') U-) ce I-- 77 O a V / W � Q Lu o� O z a� O ro w U a) cr9 Z4 -J � b U.J (D LL. 0 O ® Ll. 0 z uU GRIFFIN STRUCTURES, IN�k_ g-3r3 Area: 68,400 SF = 1.57 Acre ENLARGED SITE PLAN - LAYOUT 2 Scale: 1/32" = P-0° 7 SECONDARY STREET m m5 U �0 5 C amd'7 a u U za `o N O 1 Q �n � QU' L OUN C ya CL 6�6 + me N V Nu /allRpnKlcnop�annech,l 10 �aeMo nl0ma ores I�� V V) W Shop & Storage Bldg. EOC & Policy Room _ z 4,465 SF 2,340 SF Administration Bldg. O 3,210 SF 7771 6 12 a a a Lu 0 0 0 ♦ � �m4 W es O U N z i Lu Bin 1Bin 2 Bin 3 Bin 4 Bin 5 Q N o Laydown I O Areas 0 5 1,300 SF Bin 6 Bin R Bin O USE Transfer — — — O} U M �L- * (D oa Emergency Laydown Areas Generator 2,500 SF -�0 0 GRIFFIN STRUCTURES, IN�qo-4r3 ATTACHMENT 3 - CONCEPTUAL ESTIMATE Report to the City of Rancho Palos Verdes, CA Corporate Yard Space Assessment — Report Submitted by Griffin Structures, Inc. Attachment 3 A-30 Rancho Palos Verdes Corporate Yard Conceptual Statement of Probable Cost NOTES: 1. Construction Costs are based on May 2016 values and include future escalation (midpoint of construction December 20 17) reflecting the anticipated start and completion of construction. 2. Griffin Structures, Inc. is offering this Statement of Probable Cost based on current level of documentation available which is based upon conceptual drawings. Griffin has used its reason -able best efforts to assess identified project specific program requirements, geographic consid-erations, assumed building type, construction methods, current labor rates and material costs, and local market conditions to generate an opinion of possible project specific costs. Griffin cannot be held responsible for adjustments to this estimate which could produce amendments to subsequent and future project budget updates based upon changes in project specific require-ments or unforeseen adjustments in local market conditions affecting both direct and indirect costs. Griffin Structures, Inc. Program and Construction Managers A-31 COMPONENT Concept 1 Concept 2 COMMENTS 1 PRE -CONSTRUCTION SERVICES 120,000 120,000 Allowance Program Management Incl Incl Scheduling Incl Incl Estimating Incl Incl Design Team Management Incl Incl Development of Guaranteed Maximum Price Incl Incl Reimbursables Incl Incl 2 A/E SERVICES Conceptual Design 840,000 Incl 834,000 Allowance Incl Schematic Design Design Development Incl Incl Incl Incl Construction Documents Incl Incl Bidding Incl Incl Construction Administration Incl Incl Reimbursables Incl Incl FF&E Design & Procurement Services Incl Incl Design Fee Contingency 42,000 42,000 Allowance 3 GEOTECHNICAL Soils Reports (Buildings, Parking Areas) 35,000 35,000 Allowance 4 ENVIRONMENTAL Phase 1 ESA 10,000 10,000 Allowance Phase 2 Report 0 0 Assumes that Phase 1 will not require a Phase 2 report CEQA 0 0 Assumes that City will determine the project is exempt from CEQA 5 DEPUTY TESTING AND INSPECTION Soils Testing 75,000 75,000 Allowance Materials Testing 100,000 100,000 Allowance Roofing Inspections 15,000 15,000 Allowance 6 DIRECT COSTS 9,337,000 9,268,000 New Administration Building Incl Incl New Shop and Storage Building Incl Incl New EOC Building Incl Incl New Material Bins w/ Canopy Incl Incl Sitework (Fencing, Utilities, Demolition, Paving, Landscaping, etc) Incl Incl Includes concrete cap over abandoned missle silo Course of Construction Contingency 934,000 927,000 10.00% 7 TEMPORARY FACILITIES DURING CONSTRUCTION Temporary Trailers 25,000 0 8 FIXTURES, FURNISHINGS, & EQUIPMENT (FF&E) Office Furniture (Administration Building and EOC) 160,000 160,000 Allowance based on 6,400 SF at $25/SF EOC Audio / Visual Equipment 450,000 450,000 Allowance Shop Shelving 50,000 50,000 Excludes all related shop equipment such as tools, machinery, etc. Misc. Furnishings and Fixtures 25,000 25,000 Allowance 9 ELECTRONIC SYSTEMS AND SPECIAL EQUIPMENT Computers, Phones, Servers, Scanners, Fax Machines, Copiers Not included Not included City TBD 10 PROGRAM & CONSTRUCTION MANAGEMENT Overhead, Fee & Administration costs 450,000 450,000 Assumes 4 days/week during construction Reimbursables 25,000 25,000 Includes online document management software Legal 1,500 1,500 Insurance 5,000 5,000 Contingency 50,000 50,000 11 OWNERS BUILDERS RISK INSURANCE See Note See Note Included in Direct Costs 12 UTILITY COMPANY CONNECTION SERVICES AND FEES Southern California Edison (SCE) / Gas Company 10,000 10,000 Allowance: City of Rancho Palos Verdes Phone/Data Service for new buildings 10,000 10,000 Allowance: City of Rancho Palos Verdes Cable TV for new Admin / EOC Building 7,500 7,500 Allowance: City of Rancho Palos Verdes Water/Sewer for new buildings 10,000 10,000 Allowance: City of Rancho Palos Verdes 13 CITY OF RANCHO PALOS VERDES FEES AND ADMINISTRATION Plan Check, Permit Fees, and Building Inspections 100,000 100,000 Allowance: City of Rancho Palos Verdes 14 CONTINGENCY: CITY OF RANCHO PALOS VERDES See Note See Note City TBD CONCEPTUAL STATEMENT OF PROBABLE COST $12,887,0001 $12,780,000 NOTES: 1. Construction Costs are based on May 2016 values and include future escalation (midpoint of construction December 20 17) reflecting the anticipated start and completion of construction. 2. Griffin Structures, Inc. is offering this Statement of Probable Cost based on current level of documentation available which is based upon conceptual drawings. Griffin has used its reason -able best efforts to assess identified project specific program requirements, geographic consid-erations, assumed building type, construction methods, current labor rates and material costs, and local market conditions to generate an opinion of possible project specific costs. Griffin cannot be held responsible for adjustments to this estimate which could produce amendments to subsequent and future project budget updates based upon changes in project specific require-ments or unforeseen adjustments in local market conditions affecting both direct and indirect costs. Griffin Structures, Inc. Program and Construction Managers A-31 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate INTRODUCTION 1. Basis Of Estimate May 9, 2016 This cost estimate is based upon Conceptual Documents by Gillis Panichapan Architects along with verbal and written guidance from the design team. Summary of Documentation 1) Architectural Drawings Site Plans For Options 1 and 2 2. Excluded Costs The following items are excluded from this estimate. 1) Professional fees, inspections and testing. 2) Escalation beyond midpoint of construction, December 2017. We are assuming a start date of June 2017, and a 12 month construction schedule. 3) FF and E, unless specifically referenced in this estimate. 4) Plan check fees and building permit fees. 5) Construction contingency costs. 6) Construction management fees. 7) Soft costs. 8) Upgrades to the site not specifically referenced in the estimate. 3. Clarifications 1) This estimate is based on the assumption of a competitive bid environment at both the general contractor and subcontractor level. We are assuming that this project will be procured through a design -bid -build methodology. 2) This estimate assumes the use of prevailing wage labor rates. Sheet 2 of 11 A-32 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 1 Summary Cost Excluding Cost Including Element Markups Markups Buildings New Shop and Storage Building New Administrative Building New EOC Building Sitework Site Clearance Site Security Earthwork Hardscape Specialties, Amenities, and Furnishings Walls and Fences Concrete Cap Over Abandoned Missile Silo Site Utilities Site Electrical Subtotal General Conditions Subtotal OH&P Subtotal Bonds & Insurance Subtotal Design Contingency Subtotal Escalation to MOC, December 2017 $1,585,000 $2,195,531 $1,125,905 $1,559,596 $1,140,563 $1,579,899 TOTAL ESTIMATED CONSTRUCTION COST $9,337,385 $9,337,385 Alternate #1 - Use AC paving In Lieu of Concrete Paving DEDUCT ($425,466) Sheet 3 of 11 A-33 $65,600 $90,869 $28,000 $38,785 $198,684 $275,216 $665,320 $921,597 $397,228 $550,237 $325,250 $450,534 $234,000 $324,135 $290,305 $402,128 $685,000 $948,857 $6,740,854 $9,337,385 7.34% $495,000 Incl above $7,235,854 $9,337,385 4.00% $289,434 Incl Above $7,525,288 $9,337,385 2.20% $165,556 Incl Above $7,690,845 $9,337,385 15.00% $1,153,627 Incl Above $8,844,471 $9,337,385 5.57% $492,913 Incl Above TOTAL ESTIMATED CONSTRUCTION COST $9,337,385 $9,337,385 Alternate #1 - Use AC paving In Lieu of Concrete Paving DEDUCT ($425,466) Sheet 3 of 11 A-33 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 1 Detail Elements Quantity Unit Unit Cost Total Element New Shop and Storage Building Provide new Shop / Central Employee Building 5,400 sf $250.00 $1,350,000 Premium for LEED platinum 1 Is $135,000.00 $135,000 Monorail system 1 Is $100,000.00 $100,000 Total - New Shop and Storage Building 1.585.000 New Administrative Building Provide new Administrative Building 3,722 sf $275.00 $1,023,550 Premium for LEED platinum 1 Is $102,355.00 $102,355 Total - New Administrative Building 1.125.905 New EOC Building Provide new EOC Building 2,765 sf $375.00 $1,036,875 Premium for LEED platinum 1 Is $103,687.50 $103,688 Total - New EOC Building 1.140.563 Site Clearance Site Preparation Clear site 92,000 sf $0.55 $50,600 Locate and protect in place existing underground utilities to remain 1 Is $15,000.00 $15,000 Total - Site Clearance Site Security Provide site cameras 6 ea $3,000.00 $18,000 Head end equipment for security system 1 Is $10,000.00 $10,000 Total - Site Security2$,QQQ Sheet 4 of 11 A-34 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 1 Detail Elements Quantity Unit Unit Cost Total Element Earthwork Earthwork Field staking Fine grading Rough grading Import / Export, Allowance Dust control Erosion control SWPPP Total - Earthwork Hardscape Hardscape Concrete paving Concrete paving at parking lot Concrete curbs and gutters Total - Hardscape Specialties, Amenities, and Furnishings Site Specialties Parking stall striping Handicap parking stall striping and signage Street markings and miscellaneous signage Concrete wheel stops Site signage Vehicle charging stations Site Amenities Covered canopies Trash enclosure Site Furnishings / Equipment Miscellaneous site furnishings including trash receptacles, bike racks, tables, benches, etc. Total - Specialties, Amenities, and Furnishings 92,000 sf $0.10 $9,200 92,000 sf $0.15 $13,800 12,181 cy $6.50 $79,180 1,218 cy $30.00 $36,544 92,000 sf $0.08 $7,360 92,000 sf $0.30 $27,600 1 Is $25,000.00 $25,000 7 ytf. (itf4 68,990 sf $8.00 $551,920 9,800 sf $8.00 $78,400 1 Is $35,000.00 $35,000 665 320 26 ea $18.00 $468 2 ea $250.00 $500 1 Is $2,000.00 $2,000 28 ea $45.00 $1,260 1 Is $2,500.00 $2,500 2 ea $25,000.00 $50,000 5,200 sf $60.00 $312,000 1 ea $23,500.00 $23,500 1 Is $5,000.00 $5,000 Sheet 5 of 11 A-35 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 1 Detail Elements Quantity Unit Unit Cost Total Element Walls and Fences Storage Bin Walls CMU walls Continuous footings Fences and Gates Perimeter Security Fence Electronic rolling entrance gate Pedestrian gate Total - Walls and Fences Concrete Cap Over Abandoned Missile Silo Provide concrete lid to missle silo Freight elevator Stairs Total - Concrete Cap Over Abandoned Missile Silo Site Utilities Sanitary Sewer 4" PVC pipe, including trench and backfill POC to main line Domestic Water 6" PVC pipe, including trench and backfill Water meter Reduced pressure backflow preventer POC to main line Fire Water 6" PVC pipe, including trench and backfill Double detector check valve Fire hydrant Fire department connection Storm Drain Storm drain upgrades to hardscaped areas (reuse as much as possible) Total - Site Utilities 4,760 sf $25.00 $119,000 680 If $70.00 $47,600 870 If $135.00 $117,450 1 ea $40,000.00 $40,000 1 ea $1,200.00 $1,200 325 250 1,200 sf $70.00 $84,000 1 Is $125,000.00 $125,000 1 fit $25,000.00 $25,000 400 If $135.00 $54,000 1 ea $5,000.00 $5,000 400 If $125.00 $50,000 1 ea $4,750.00 $4,750 1 ea $6,200.00 $6,200 1 ea $4,475.00 $4,475 400 If $160.00 $64,000 1 ea $4,850.00 $4,850 1 ea $6,800.00 $6,800 1 ea $7,500.00 $7,500 78,790 sf $1.05 $82,730 29� 0.305 Sheet 6 of 11 A-36 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 1 Detail Elements Quantity Unit Unit Cost Total Element Site Electrical Site Lighting 1 Is $125,000.00 200 KwGenerator, and infrastructure for power distrubution 1 Is $300,000.00 Solar panels over canopies 5,200 sf $50.00 $125,000 $300,000 $260,000 Total - Site Electrical 685 000 Sheet 7 of 11 A-37 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 2 Summary Cost Excluding Cost Including Element Markups Markups Buildings New Shop and Storage Building New Administrative Building New EOC Building Sitework Site Clearance Site Security Earthwork Hardscape Specialties, Amenities, and Furnishings Walls and Fences Site Utilities Site Electrical Subtotal General Conditions Subtotal OH&P Subtotal Bonds & Insurance Subtotal Design Contingency Subtotal Escalation to MOC, December 2017 $1,585,000 $2,196,730 $1,125,905 $1,560,447 $1,140,563 $1,580,762 TOTAL ESTIMATED CONSTRUCTION COST $9,268,525 $9,268,525 Alternate #1 - Use AC paving In Lieu of Concrete Paving DEDUCT ($292,545) Sheet 8 of 11 A-38 $51,300 $71,099 $28,000 $38,807 $143,213 $198,486 $463,400 $642,249 $703,228 $974,638 $309,625 $429,125 $197,259 $273,391 $940,000 $1,302,792 $6,687,493 $9,268,525 7.40% $495,000 Incl above $7,182,493 $9,268,525 4.00% $287,300 Incl Above $7,469,792 $9,268,525 2.20% $164,335 Incl Above $7,634,128 $9,268,525 15.00% $1,145,119 Incl Above $8,779,247 $9,268,525 5.57% $489,278 Incl Above TOTAL ESTIMATED CONSTRUCTION COST $9,268,525 $9,268,525 Alternate #1 - Use AC paving In Lieu of Concrete Paving DEDUCT ($292,545) Sheet 8 of 11 A-38 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 2 Detail Elements Quantity Unit Unit Cost Total Element New Shop and Storage Building Provide new Shop / Central Employee Building 5,400 sf $250.00 $1,350,000 Premium for LEED platinum 1 Is $135,000.00 $135,000 Monorail system 1 Is $100,000.00 $100,000 Total - New Shop and Storage Building 1.585.000 New Administrative Building Provide new Administrative Building 3,722 sf $275.00 $1,023,550 Premium for LEED platinum 1 Is $102,355.00 $102,355 Total - New Administrative Building 1.125.905 New EOC Building Provide new EOC Building 2,765 sf $375.00 $1,036,875 Premium for LEED platinum 1 Is $103,687.50 $103,688 Total - New EOC Building 1.140.563 Site Clearance Site Preparation Clear site 66,000 sf $0.55 $36,300 Locate and protect in place existing underground utilities to remain 1 Is $15,000.00 $15,000 Total - Site Clearance Site Security Provide site cameras 6 ea $3,000.00 $18,000 Head end equipment for security system 1 Is $10,000.00 $10,000 Total - Site Security Sheet 9 of 11 A-39 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 2 Detail Elements Quantity Unit Unit Cost Total Element Earthwork Earthwork Field staking Fine grading Rough grading Import / Export, Allowance Dust control Erosion control SWPPP Total - Earthwork Hardscape Hardscape Concrete paving Concrete paving at parking lot Concrete curbs and gutters Total - Hardscape Specialties, Amenities, and Furnishings Site Specialties Parking stall striping Handicap parking stall striping and signage Street markings and miscellaneous signage Concrete wheel stops Site signage Vehicle charging stations Site Amenities Covered canopies Trash enclosure Site Furnishings / Equipment Miscellaneous site furnishings including trash receptacles, bike racks, tables, benches, etc. Total - Specialties, Amenities, and Furnishings 66,000 sf $0.10 $6,600 66,000 sf $0.15 $9,900 8,067 cy $6.50 $52,433 807 cy $30.00 $24,200 66,000 sf $0.08 $5,280 66,000 sf $0.30 $19,800 1 Is $25,000.00 $25,000 a�gs.c►s 36,175 sf $8.00 $289,400 18,000 sf $8.00 $144,000 1 Is $30,000.00 $30,000 26 ea $18.00 $468 2 ea $250.00 $500 1 Is $2,000.00 $2,000 28 ea $45.00 $1,260 1 Is $2,500.00 $2,500 2 ea $25,000.00 $50,000 10,300 sf $60.00 $618,000 1 ea $23,500.00 $23,500 1 Is $5,000.00 $5,000 /U:f.11tf Sheet 10 of 11 A-40 Rancho Palos Verdes Corporate Yard Rancho Palos Verdes, CA Master Plan Cost Estimate 05/09/16 Option 2 Detail Elements Quantity Unit Unit Cost Total Element Walls and Fences Storage Bin Walls CMU walls Continuous footings Fences and Gates Perimeter Security Fence Electronic rolling entrance gate Pedestrian gate Total - Walls and Fences Site Utilities Sanitary Sewer 4" PVC pipe, including trench and backfill POC to main line Domestic Water 6" PVC pipe, including trench and backfill Water meter Reduced pressure backflow preventer POC to main line Fire Water 6" PVC pipe, including trench and backfill Double detector check valve Fire hydrant Fire department connection Storm Drain Storm drain upgrades to hardscaped areas (reuse as much as possible) Total - Site Utilities Site Electrical Site Lighting 200 KwGenerator, and infrastructure for power distrubution Solar panels over canopies Total - Site Electrical 5,355 sf $25.00 $133,875 765 If $70.00 $53,550 600 If $135.00 $81,000 1 ea $40,000.00 $40,000 1 ea $1,200.00 $1,200 309 625 240 If $135.00 $32,400 1 ea $5,000.00 $5,000 240 If $125.00 $30,000 1 ea $4,750.00 $4,750 1 ea $6,200.00 $6,200 1 ea $4,475.00 $4,475 240 If $160.00 $38,400 1 ea $4,850.00 $4,850 1 ea $6,800.00 $6,800 1 ea $7,500.00 $7,500 54,175 sf $1.05 $56,884 1 Is $125,000.00 $125,000 1 Is $300,000.00 $300,000 10,300 sf $50.00 $515,000 94� 0.000 Sheet 11 of 11 A-41 .;u v y .♦ - .i., p� r a � \ i✓�ifl. AN Xt r"" i� a \ �•_ � - fit•. � , � I. �4 A� '_ •��`` _�—fir 111 _� � ':z L- +•tw°i�� ZMGRIFFIN STRUCTURES, INC. Program and Construction Morogers 1 Y .;u v y .♦ - .i., p� r a � \ i✓�ifl. AN Xt r"" i� a \ �•_ � - fit•. � , � I. �4 A� '_ •��`` _�—fir 111 _� � ':z L- +•tw°i�� ZMGRIFFIN STRUCTURES, INC. Program and Construction Morogers