CC SR 20160517 02 - FY16-17 CIP & 5-Year CIPRANCHO PALOS VERDES CITY COUNCIL
MEETING DATE: 05/31/2016
AGENDA REPORT AGENDA HEADING: Regular Business
AGENDA DESCRIPTION:
Consideration and possible action regarding the proposed FY16-17 Capital
Improvement Budget and 5 -year Capital Improvement Program.
RECOMMENDED COUNCIL ACTION:
(1) Review and discuss capital improvement needs and provide direction.
FISCAL IMPACT: Work to prepare the capital improvement budget is included in the
FY15-16 municipal budget.
Amount Budgeted: Not applicable
Additional Appropriation: None requested
Account Number(s): Not applicable
ORIGINATED BY: Michael Throne, PE, Director of Public Works
REVIEWED BY: Same as above
f.
APPROVED BY: Doug Willmore, City Manager.! "'II
ATTACHED SUPPORTING DOCUMENTS:
A. Proposed new projects (page A-1)
B. Current status of FY15-16 capital improvement projects (page B-1)
C. Proposed FY16-17 Capital Improvement Budget and 5 -year Capital
Improvement Program table (Version 2) (page C-1)
BACKGROUND AND DISCUSSION:
The Public Works Department will be presenting a proposed draft FY16-17 Capital
Improvement Budget and 5 -year Capital Improvement Program (CIP) for discussion and
consideration of the City Council. Direction received from the City Council will be
incorporated into the draft FY16-17 municipal budget.
The proposed 5 -year CIP prioritizes, among others, the objectives of:
(1) Continuing to have streets with a Pavement Condition Index (PCI) grade of "very
good" with no deferred maintenance;
(2) A safe and reliable sewer system in the Abalone Cove Landslide Abatement
District;
1
(3) Rehabilitating or replacing old, worn-out, failure -prone local stormwater drainage
systems;
(4) Constructing and completing Council -approved local park developments; and,
(5) Master planning of the Civic Center/public safety site.
The proposed first year of the 5 -year plan proposes to focus on completing the final first
cycle of the 7 -year pavement rehabilitation program; continuing installation of
dewatering wells in Portuguese Bend; resurfacing Miraleste Drive; installing lining,
performing point repairs, and replacing storm drain culverts; placing sidewalks and trees
along Hawthorne Boulevard; initiating master planning and design for the Ladera Linda
Community Center and for the City Hall Civic Center; and all landscaping improvements
at Lower Hesse Park.
A presentation (Attachment A) will be made that outlines the objectives of the proposed
5 -year plan; a summary of the work proposed for each infrastructure category; funding
sources for all projects; and, a summary of fund balances. Public Works will also
provide updates on all current, on-going, and planned capital projects (Attachment B).
The attached table (Attachment C) summarizes the budgeted CIP work for FY15-16 and
the proposed FY16-17 capital improvement budget (including revenue funding sources
for each project and fund balances) and the 5 -year CIP. The City Council received a
concise tutorial on the components of the table on April 19, 2016.
On April 14 and May 12, 2016, the Infrastructure Management Advisory Committee
(IMAC) met to review the proposed 2016 Capital Improvement Budget and 5 -year CIP
as part of their overall mission to provide advice to the City Council and to Public Works.
Overall, they are supportive of the expansion of the current CIP table into one that
shows at a glance all the projects/programs and their funding sources, and provided
suggestions as to how to make the next version of the table more user friendly. They
were enthused that the table will ultimately refer back to the project profile data sheets
that Public Works has developed with input from the Committee, which again will make
the table more useful to the community and the Council in the future. They did not
weigh-in at this time on the merits of the proposed new projects/programs and
suggested that a discussion of the overall objectives of CIP would be beneficial. A
member of the Committee is expected to be in tonight's audience to answer any
questions the Council might have of the Committee.
ALTERNATIVES:
In addition to the recommended action, the following alternative actions are available for
the City Council's consideration:
Discuss and take other action related to this matter.
2
Proposed NEW Capital Projects and
Programs
May 31, 2016
A-1
Page Intentionally Blank
li�
A-2
Coastal Bluff Fence Replacement Program
• Replace All Deteriorating Cliff -
and Bluff -Edge
• Program Commences Along
Oceanfront Estates
• $200,000 Requested
• Source: CIP Reserves
A-3
RPV CIPPS
Project: Coastal Bluff Fence Replacement Program
Page 2 of 14
General Project Profile Information
Project Name Coastal Bluff Fence Replacement Program
Location Entire length of cliff- and bluff -edges
Project Description Programmatically and systematically remove and replace all deteriorating fencing with new
fencing of more durable materials and that match existing fence design and aesthetics
Describe the community benefit or outcome Reduce risk of injury due to old fencing and associated maintenance costs
from implementing this project
Describe the outcome if the project is not Existing fencing will continue to deteriorate due to effects of weather, ocean spray corrosion,
implemented and pests with increasing maintenance and replacement costs
Date of original proposal 05-31-2016
Name of department proposing this project Public Works
Name of departmental project manager Larvenz
Name and contact information for resident N/A
or community group proposing this project
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community Adjacent subdivision plans
plans to be referenced/utilized for design
List the standards to be referenced/utilized Location specific
for design
Identify infrastructure category O Public buildings O Park sites *i Trails O Stormwater system
Q Citywide sanitary sewer system Q Ab Cove sewer system
Q R/W, traffic control devices Q PB landslide
Name of department or community group Public Works
that will take responsibility for the project
after completion
Does that group have the resources to O Yes O No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
* Yes O No
https://tpvpay.com/project/Print_project.php?id=267
A-4
5/24/2016
RPV CIPPS
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
Page 3 of 14
Local HOAs
There may be an interest in changing or enhancing the existing fence design and/or
configuration that could be achieved through a partnership agreement
A-5
https://rpvpay.com/project/print_project.php?id=267 5/24/2016
RPV CIPPS
Will the project enhance or improve the
overall safety of the city and the delivery of
services?
PUBLIC HEALTH AND SAFETY
* Yes O No
If yes, describe how Maintain physical assets
If yes, quantify if feasible
Will the project protect the health and Yes Q No
welfare of residents and/or the environment?
Page 4 of 14
If yes, describe sector and how Delineate the limits of a safe zone for individuals and environmental areas to
protect from human use
Is the project required to mitigate or 0 Yes Q No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be Weak fencing
addressed
Will the project eliminate an identified Yes Q No
safety condition?
If yes, describe how the condition is Replacing weak fencing with new
eliminated
If no, will the project mitigate it? O Yes O No
If yes, describe the mitigation
Will the project eliminate an identified O Yes Qi No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? * Yes O No
If yes, describe the mitigation Continue to define the limits of the safe area along cliffs and bluff -
edges
https://tpvpay.com/project/Print_project.php?id=267
A-6
5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the project improve efficiency? * Yes 0 No
If yes, describe how Urgent repairs would be avoided
If ff ' bff d9 0 Yes OQ No
yes, can e iciency e quan i ie .
If yes, describe quantity
Will the project improve economy? 0 Yes OQ No
If yes, quantify amount
Will the project increase or improve
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
*Yes 0 No
Urgent and uneconomical repairs would be avoided
0 Yes *No
0 Yes *No
funding source
Go to Funding Worksheet and enter amounts
*Yes 0 No
state
*Yes 0 No
If yes, go to Funding Worksheet and enter amounts.
*Yes 0 No
If yes, go to Funding Worksheet and enter amounts.
0 Yes *No
percent completion
Page 8 of 14
If yes, go to Funding Worksheet and enter amounts. A-7
https://rpvpay.com/project/print_project.php?id=267 5/24/2016
RPV CIPPS Page 9 of 14
Will the project require additional part-time 0 Yes No
personnel?
If yes, estimate number
If yes, go to Funding Worksheet and enter amounts.
Will the project generate revenue? 0 Yes Q No
If yes, estimate annual amount
If yes, go to Funding Worksheet and enter amounts.
Can the City partner with other agencies, O Yes Q No
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction Potentially participation from adjacent HOAs
If yes, is it anticipated that other agency, 0 Yes QQ No
group, jurisdiction would be able to assist
financially?
If yes, describe how N/A
If yes, identify potential funding amount or N/A
percentage of total expenditure
If no, would the other agency, group, Yes 0 No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution Minor maintenance
If the project is work to an existing facility, 07-01-2000
identify or estimate original construction
date
Estimate remaining life of existing facility to 5
be replaced in years
Estimate residual value of existing facility 0
Provide anticipated life of new facility in 20
years
Can the life cycle cost be calculated? 0 Yes Q No
If yes, show the annual maintenance cost To be determined
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + N/A
Operating Costs) _
A-8
https://rpvpay.com/project/print_project.php?id=267 5/24/2016
RPV CIPPS
Page 10 of 14
Describe the degree of uncertainty (high, medium, low) for:
Capital cost
OH
OM
*L
Why?
Construction duration
O H
O M
L
Why?
Operating and maintenance costs
O H
O M
QQ L
Why?
Negative environmental impact
O H
O M
L
Why?
Positive environmental impact
O H
O M
Qi L
Why?
Over/under estimation of benefits (e.g.,
O H
O M
Q L
Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes
Qi No
cost been prepared?
If yes, is it a range?
O Yes
No
If yes, show range in Funding Worksheet
If no, show
estimated amount in Funding
Worksheet
Can the cost of not implementing the project
O Yes
O No
be estimated?
If yes, identify cost
If yes, does it increase deferred maintenance
0 Yes
O No
for its infrastructure category?
If yes, estimate deferred cost and duration
A-9
https://rpvpay.com/project/print_project.php?id=267 5/24/2016
RPV CIPPS Page 11 of 14
OUTSIDE FUNDING
Is the project currently spending grant or O Yes No
other outside funds?
If yes, identify funding source amount expenditure
deadline
agreement title, date Go to Funding Worksheet and enter amounts.
Is the project eligible for outside funding? O Yes QQ No
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Go to Funding Worksheet and enter amounts.
Are there funding constraints? O Yes Q No
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Are there consequences of missing O Yes No
milestones, deadlines, etc.?
If yes, describe situation and consequence
Is funding tied to expenditure phases? O Yes QQ No
If yes, describe the expenditure phase
A-10
https://rpvpay.com/project/print_project.php?id=267 5/24/2016
RPV CIPPS Page 13 of 14
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document Potential categorical exemption
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Qi No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document N/A
required
Does the project require NEPA review? O Yes Q No
If yes, describe NEPA document
Has a NEPA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes QQ No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-11
https://rpvpay.com/project/print_project.php?id=267 5/24/2016
RPV CIPPS Page 14 of 14
PROJECT PROFILE FUNDING WORKSHEET
Annual impact on operating budget
Are operating impacts anticipated? * Yes O No
If yes, identify impact on worksheet:
Name of impacted fund General Fund
Revenue generated 0
Savings created 0
Additional FTEs needed 0
Salaries/benefits for additional FTEs 0
Additional (decreased) operating expenses +0
Debt service (P+I) 0
Fiscal year impacts anticipated to begin FY 16/17
Construction management and inspection $10000 $ $
Contingency (list amount % and basis) $10% $ $
Totals $200000 $0 $0
A-12
https://rpvpay.com/project/print_project.php?id=267 5/24/2016
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate
Aproved Budget
Current Estimate
Preliminary engineering
$5000
$
$
Environmental
$1000
$
$
Right -of -Way (legal plus acquisition)
$0
$
$
Capital equipment
$0
$
$
Construction (identify relevant infrastructure
$184000
$
$
categories)
Construction management and inspection $10000 $ $
Contingency (list amount % and basis) $10% $ $
Totals $200000 $0 $0
A-12
https://rpvpay.com/project/print_project.php?id=267 5/24/2016
Ladera Linda Community Center Parking Lot
• Paved Parking Lot ._
• Address Stormwater Issues
• $50,000 Requested for Design
• Source: Quimby
dLmw=iw...
A-13
RPV CIPPS Page 2 of 13
Project: Ladera Linda Community Center Parking Lot
General Project Profile Information
Project Name Ladera Linda Community Center Parking
Lot
Location Ladera Linda Community Center
Project Description Replace existing gravel parking area near the paddleball courts with an all-weather paved
surface that complies with ADA requirements and NPDES regulations
Describe the community benefit or outcome Improve appearance and comfort of patrons using the parking lot
from implementing this project
Describe the outcome if the project is not
implemented
Date of original proposal
Name of department proposing this project
Name of departmental project manager
Name and contact information for resident
or community group proposing this project
Patrons would continue to use the gravel lot for vehicle parking
05-31-2016
Recreation and Parks
Linder
N/A
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community General Plan, Parks Master Plan, Ladera Linda master plan (in development)
plans to be referenced/utilized for design
List the standards to be referenced/utilized ADA, NPDES
for design
Identify infrastructure category 0 Public buildings Q Park sites 0 Trails 0 Stormwater system
0 Citywide sanitary sewer system 0 Ab Cove sewer system
0 R/W, traffic control devices 0 PB landslide
Name of department or community group Public Works
that will take responsibility for the project
after completion
Does that group have the resources to O Yes 0 No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
0 Yes *No A-14
https://rpvpay.com/project/print_project.php?id=268 5/24/2016
RPV CIPPS Page 3 of 13
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
A-15
https://rpvpay.com/project/print_project.php?id=268 5/24/2016
RPV CIPPS
PUBLIC HEALTH AND SAFETY
Page 4 of 13
Will the project enhance or improve the Yes No
overall safety of the city and the delivery of
services?
If yes, describe how Improve access for disabled individuals and improve stormwater quality runoff
If yes, quantify if feasible
Will the project protect the health and O Yes Q No
welfare of residents and/or the environment?
If yes, describe sector and how Improve access for disabled individuals and improve stormwater quality runoff
Is the project required to mitigate or 0 Yes No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be
addressed
Will the project eliminate an identified 0 Yes QQ No
safety condition?
If yes, describe how the condition is
eliminated
If no, will the project mitigate it? * Yes 0 No
If yes, describe the mitigation Paved walking surfaces are generally more desirable than gravel for
some individuals
Will the project eliminate an identified 0 Yes Qi No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? 0 Yes No
If yes, describe the mitigation
https://tpvpay.com/project/Print_project.php?id=268
A-16
5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
Does the project support maintenance and
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation?
If yes, cite law or regulation
Page 5 of 13
ESSENTIAL CITY SERVICES
* Yes No
Ladera Linda Community Center
Reduce maintenance costs associated with gravel parking lots
*Yes Q No
Ladera Linda Community Center
The new parking lot would complement the in development site master plan
O Yes *No
If the project is not done, would not O Yes Qi No
performing the project violate a law or
regulation?
If yes, cite law or regulation
and identify
penalty
Is the project required by a court order, O Yes No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the
proj ect?
If yes, describe alternative or option
If no, describe why
Describe how that department will operate
or maintain the project after completion
Will public engagement be employed to
develop or implement the project?
If yes, describe sector(s) of the public,
engagement level and influence
If yes, estimate cost and/or revenue benefit
of public engagement
* Yes Q No
The city would continue to maintain the gravel parking lot
Routing pavement maintenance (spot repairs and scheduled resurfacing/restriping) and drainage
0 Yes O No
Through the LL master planning process
N/A
Enter this amount in the Funding Worksheet.
https://tpvpay.com/project/Print_project.php?id=268
A-17
5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the miect im rove efficienc ? O Yes Q No
P J p y
If yes, describe how
If yes, can efficiency be quantified? O Yes O No
If yes, describe quantity
Will the project improve economy? O Yes Q No
If yes, quantify amount
Will the project increase or improve
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
*Yes Q No
Would reduce the regular maintenance needs of a gravel surface
O Yes *No
Q Yes Q No
funding source
Go to Funding Worksheet and enter amounts
*Yes Q No
state
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
percent completion
Page 7 of 13
If yes, go to Funding Worksheet and enter amounts. A_1 g
https://rpvpay.com/project/print_project.php?id=268 5/24/2016
RPV CIPPS
Will the project require additional part-time O Yes Qi No
personnel?
If yes, estimate number
Will the project generate revenue?
If yes, estimate annual amount
Can the City partner with other agencies,
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
If yes, is it anticipated that other agency,
Q Yes Q No
group, jurisdiction would be able to assist
financially?
If yes, describe how
If yes, identify potential funding amount or
percentage of total expenditure
If no, would the other agency, group, O Yes Qi No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1960
identify or estimate original construction
date
Estimate remaining life of existing facility to 0
be replaced in years
Estimate residual value of existing facility 0
Provide anticipated life of new facility in 20
years
Can the life cycle cost be calculated? * Yes Q No
If yes, show the annual maintenance cost To be calculated
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + N/A
Operating Costs) _
https://tpvpay.com/project/Print_project.php?id=268
Page 8 of 13
A-19
5/24/2016
RPV CIPPS Page 9 of 13
Describe the degree of uncertainty (high, medium, low) for:
Capital cost H Q M Q L Why? Presently unknown as to the complete
scope of project
Construction duration O H QQ M Q L Why?
Operating and maintenance costs O H O M Qi L Why?
Negative environmental impact O H Q M Di L Why?
OH OM OL
Positive environmental impact
Why?
Over/under estimation of benefits (e.g.,
O H
Q M Qi L Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes
Qi No
cost been prepared?
If yes, is it a range?
O Yes
Q No
If yes, show range in Funding Worksheet
If no, show
estimated amount in Funding Worksheet
Can the cost of not implementing the project
O Yes
Q No
be estimated?
If yes, identify cost
20000 per year
If yes, does it increase deferred maintenance
Yes
Q No
for its infrastructure category?
If yes, estimate deferred cost and duration
20000
https://tpvpay.com/project/Print_project.php?id=268
A-20
5/24/2016
RPV CIPPS Page 10 of 13
OUTSIDE FUNDING
Is the project currently spending grant or O Yes No
other outside funds?
If yes, identify funding source amount expenditure
deadline
agreement title, date Go to Funding Worksheet and enter amounts.
Is the project eligible for outside funding? O Yes QQ No
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Go to Funding Worksheet and enter amounts.
Are there funding constraints? O Yes Q No
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Are there consequences of missing O Yes No
milestones, deadlines, etc.?
If yes, describe situation and consequence
Is funding tied to expenditure phases? O Yes QQ No
If yes, describe the expenditure phase
A-21
https://rpvpay.com/project/print_project.php?id=268 5/24/2016
RPV CIPPS Page 12 of 13
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document Potentially initial study/mitigated negative declaration
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document see above
required
Does the project require NEPA review? O Yes Q No
If yes, describe NEPA document
Has a NEPA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-22
https://rpvpay.com/project/print_project.php?id=268 5/24/2016
RPV CIPPS Page 13 of 13
PROJECT PROFILE FUNDING WORKSHEET
Park Sites
Construction management and inspection $0 $ $
Contingency (list amount % and basis) $0 $ $
Totals $50000 $0 $0
https://tpvpay.com/project/Print_project.php?id=268
A-23
5/24/2016
Annual impact on operating budget
Are operating impacts anticipated?
* Yes O No
If yes, identify impact on worksheet:
Name of impacted fund
General Fund
Revenue generated
0
Savings created
0
Additional FTEs needed
0
Salaries/benefits for additional FTEs
0
Additional (decreased) operating expenses
0
Debt service (P+I)
0
Fiscal year impacts anticipated to begin
2017/18
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate Aproved Budget
Current Estimate
Preliminary engineering
$45000 $
$
Environmental
$5000 $
$
Right -of -Way (legal plus acquisition)
$0 $
$
Capital equipment
$0 $
$
Construction (identify relevant infrastructure
$0 $
$
categories)
Park Sites
Construction management and inspection $0 $ $
Contingency (list amount % and basis) $0 $ $
Totals $50000 $0 $0
https://tpvpay.com/project/Print_project.php?id=268
A-23
5/24/2016
Page Intentionally Blank
A-24
Upper Pt Vicente/Hesse Pk Marquee Signage
• Monument Signs with Electronic
Message Boards PAPER SHREDDING DAY
• $110,000 Requested for Design RFV Residents only
Saturday, April 23
and Construction FREE 8 am to ll am FREE
at R.P.V. Ci
Center
• Source: CIP Reserves
ME PAPER SIMEDI)NO DAY
FOR RPV RESIDENTS
SATURDAY, APRIL 2 3
SAM ,,", AM AT APV CIVIC CTR.
A-25
RPV CIPPS
Project: Upper Pt Vicente/Hesse Park Marquee Signage
Page 2 of 13
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community
plans to be referenced/utilized for design
List the standards to be referenced/utilized
for design
Identify infrastructure category Public buildings Q Park sites Q Trails Q Stormwater system
Q Citywide sanitary sewer system Q Ab Cove sewer system
O R/W, traffic control devices Q PB landslide
Name of department or community group Public Works (maintenance); Recreation and Parks (advertising management)
that will take responsibility for the project
after completion
Does that group have the resources to O Yes O No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
Q Yes Q No A-26
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
General Project Profile Information
Project Name
Upper Pt Vicente/Hesse Park Marquee
Signage
Location
Upper Pt Vicente and Hesse Park
Project Description
Install monument signs with electronic message boards intended to advertise city and
community events and activities
Describe the community benefit or outcome
There would be added flexibility and frequency in advertising events and activities
from implementing this project
Describe the outcome if the project is not
The City would continue to use the existing plywood sign structures for advertising
implemented
Date of original proposal
05-31-2016
Name of department proposing this project
Public Works
Name of departmental project manager
Landon
Name and contact information for resident
N/A
or community group proposing this project
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community
plans to be referenced/utilized for design
List the standards to be referenced/utilized
for design
Identify infrastructure category Public buildings Q Park sites Q Trails Q Stormwater system
Q Citywide sanitary sewer system Q Ab Cove sewer system
O R/W, traffic control devices Q PB landslide
Name of department or community group Public Works (maintenance); Recreation and Parks (advertising management)
that will take responsibility for the project
after completion
Does that group have the resources to O Yes O No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
Q Yes Q No A-26
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
RPV CIPPS
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
Local community groups
Potential monetary sponsorship and/or In-kind donations
Page 3 of 13
A-27
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
RPV CIPPS Page 4 of 13
PUBLIC HEALTH AND SAFETY
Will the project enhance or improve the O Yes Q No
overall safety of the city and the delivery of
services?
If yes, describe how
If yes, quantify if feasible
Will the project protect the health and O Yes QQ No
welfare of residents and/or the environment?
If yes, describe sector and how
Is the project required to mitigate or O Yes Qi No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be
addressed
Will the project eliminate an identified O Yes No
safety condition?
If yes, describe how the condition is
eliminated
If no, will the project mitigate it? O Yes Q No
If yes, describe the mitigation
Will the project eliminate an identified O Yes No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? O Yes QQ No
If yes, describe the mitigation
A-28
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
ESSENTIAL CITY SERVICES
* Yes No
Hesse and City Hall
Improve communication with community
Does the project support maintenance and O Yes QQ No
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation? O Yes No
If yes, cite law or regulation
If the project is not done, would not O Yes QQ No
performing the project violate a law or
regulation?
If yes, cite law or regulation
Is the project required by a court order, O Yes Qi No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the O Yes Q No
proj ect?
and identify
penalty
Page 5 of 13
If yes, describe alternative or option Continue with status quo
If no, describe why
Describe how that department will operate Public Works will maintain the monument sign; Recreation and Parks will administer the
or maintain the project after completion advertising messages; Information Technology will support the electronics
Will public engagement be employed to O Yes Q No
develop or implement the project?
If yes, describe sector(s) of the public, The City Council and interested members of the public would be invited to share thoughts and
engagement level and influence comments on operations and design features
If yes, estimate cost and/or revenue benefit Minimal
of public engagement
Enter this amount in the Funding Worksheet. A-29
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the project improve efficiency? * Yes O No
If yes, describe how Staff would no long be required to clamp and maintain banners
If yes, can efficiency be quantified? * Yes Q No
If yes, describe quantity 80 hours per year (estimated)
W'ill t+1't ' 7 O Yes QQ No
e pmprove economy.
If yes, quantify amount
Will the project increase or improve
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
Q Yes Q No
Reduce staff time
Increase staff capacity for other work by up to 60 hours annually
Q Yes *No
O Yes Qi No
funding source
Go to Funding Worksheet and enter amounts
*Yes O No
state
* Yes Q No
If yes, go to Funding Worksheet and enter amounts.
*Yes O No
If yes, go to Funding Worksheet and enter amounts.
O Yes *No
If yes, go to Funding Worksheet and enter amounts.
https://tpvpay.com/project/Print_project.php?id=269
percent completion
Page 7 of 13
A-30
5/24/2016
RPV CIPPS Page 8 of 13
Will the project require additional part-time O Yes No
personnel?
If yes, estimate number
If yes, go to Funding Worksheet and enter amounts.
Will the project generate revenue?
@) Yes Q No
If yes, estimate annual amount
Contingent on adopting advertising policies
If yes, go to Funding Worksheet and enter amounts.
Can the City partner with other agencies,
Yes Q No
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
Local community groups
If yes, is it anticipated that other agency,
Yes O No
group, jurisdiction would be able to assist
financially?
If yes, describe how
Sponsorship of construction
If yes, identify potential funding amount or
Unknown
percentage of total expenditure
If no, would the other agency, group,
O Yes O No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1996
identify or estimate original construction
date
Estimate remaining life of existing facility to 0
be replaced in years
Estimate residual value of existing facility 0
Provide anticipated life of new facility in 20
years
Can the life cycle cost be calculated? * Yes O No
If yes, show the annual maintenance cost 1200
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + To be calculated if the signage generates revenue
Operating Costs) _
Describe the degree of uncertainty (high, medium, low) for: A-31
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
RPV CIPPS
Page 9 of 13
Capital cost
O H
Oi M
Q L
Why?
Construction duration
O H
0 M
L
Why?
Operating and maintenance costs
O H
O M
L
Why?
Negative environmental impact
O H
O M
Q L
Why?
Positive environmental impact
O H
O M
L
Why?
Over/under estimation of benefits (e.g.,
O H
O M
L
Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes
Q No
cost been prepared?
If yes, is it a range?
O Yes
QQ No
If yes, show range in Funding Worksheet
If no, show
estimated amount in Funding
Worksheet
Can the cost of not implementing the project
O Yes
Q No
be estimated?
If yes, identify cost
3000/yr
If yes, does it increase deferred maintenance
O Yes
Qi No
for its infrastructure category?
If yes, estimate deferred cost and duration
A-32
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
RPV CIPPS Page 10 of 13
OUTSIDE FUNDING
Is the project currently spending grant or O Yes No
other outside funds?
If yes, identify funding source amount expenditure
deadline
agreement title, date Go to Funding Worksheet and enter amounts.
Is the project eligible for outside funding? O Yes QQ No
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Go to Funding Worksheet and enter amounts.
Are there funding constraints? O Yes Q No
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Are there consequences of missing O Yes No
milestones, deadlines, etc.?
If yes, describe situation and consequence
Is funding tied to expenditure phases? O Yes QQ No
If yes, describe the expenditure phase
A-33
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
RPV CIPPS Page 12 of 13
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? Yes Q No
If yes, describe CEQA document
Has a CEQA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document None anticipated
required
Does the project require NEPA review? O Yes Qi No
If yes, describe NEPA document
Has a NEPA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes O No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-34
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
RPV CIPPS Page 13 of 13
PROJECT PROFILE FUNDING WORKSHEET
Annual impact on operating budget
Are operating impacts anticipated? * Yes O No
If yes, identify impact on worksheet:
Name of impacted fund General Fund
Revenue generated To be determined
Savings created 0
Additional FTEs needed 0
Salaries/benefits for additional FTEs 0
Additional (decreased) operating expenses 1200
Debt service (P+I) 0
Fiscal year impacts anticipated to begin 2016/2017
Construction management and inspection $4000 $ $
Contingency (list amount % and basis) $ $ $
Totals $150000 $0 $0
A-35
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate
Aproved Budget
Current Estimate
Preliminary engineering
$20000
$
$
Environmental
$0
$
$
Right -of -Way (legal plus acquisition)
$0
$
$
Capital equipment
$1000
$
$
Construction (identify relevant infrastructure
$125000
$
$
categories)
Construction management and inspection $4000 $ $
Contingency (list amount % and basis) $ $ $
Totals $150000 $0 $0
A-35
https://rpvpay.com/project/print_project.php?id=269 5/24/2016
Page Intentionally Blank
A-36
Eastview Park Site and Recreation
Improvements
Trail Widening, Facilities
Improvements and Exercise
Stations
• $250,000 Requested for Design
and Construction
• Source: Quimby
A-37
RPV CIPPS
Page 2 of 13
Project: Eastview Park Site and Recreation Improvements
General Project Profile Information
Project Name Eastview Park Site and Recreation
Improvements
Location Eastview Park
Project Description
Describe the community benefit or outcome
from implementing this project
Describe the outcome if the project is not
implemented
Date of original proposal
Name of department proposing this project
Name of departmental project manager
Name and contact information for resident
or community group proposing this project
Improve and widen existing trails, replace and improve existing playground/recreational
facilities and exercise stations, establish dog park
Improved accessibility for disabled park patrons, improved park experience for all patrons and
those with dogs
Park would remain partially inaccessible to patrons with disabilities, dogs would continue to
not be welcome
05-31-2016
Recreation and Parks
Linder
N/A
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community General Plan, Parks Master Plan
plans to be referenced/utilized for design
List the standards to be referenced/utilized ADA
for design
Identify infrastructure category O Public buildings QQ Park sites Q Trails Q Stormwater system
Q Citywide sanitary sewer system Q Ab Cove sewer system
O R/W, traffic control devices Q PB landslide
Name of department or community group Public Works (maintenance), Recreation and Parks (operations)
that will take responsibility for the project
after completion
Does that group have the resources to O Yes O No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
Q Yes Q No A_38
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
RPV CIPPS
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
local community groups
monetary and in-kind donations
Page 3 of 13
A-39
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
RPV CIPPS Page 4 of 13
PUBLIC HEALTH AND SAFETY
Will the project enhance or improve the Yes No
overall safety of the city and the delivery of
services?
If yes, describe how improved access, upgraded playground equipment, fenced dog run
If yes, quantify if feasible N/A
Will the project protect the health and Yes Q No
welfare of residents and/or the environment?
If yes, describe sector and how
Is the project required to mitigate or 0 Yes No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be
addressed
Will the project eliminate an identified 0 Yes QQ No
safety condition?
If yes, describe how the condition is
eliminated
If no, will the project mitigate it? 0 Yes OQ No
If yes, describe the mitigation
Will the project eliminate an identified 0 Yes QQ No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? 0 Yes Qi No
If yes, describe the mitigation
A-40
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
ESSENTIAL CITY SERVICES
* Yes No
park site
Response to citizen requests and current actual use of the park by patrons
Does the project support maintenance and 0 Yes QQ No
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation? 0 Yes No
If yes, cite law or regulation
If the project is not done, would not 0 Yes QQ No
performing the project violate a law or
regulation?
If yes, cite law or regulation
Is the project required by a court order, 0 Yes Qi No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the O Yes Q No
proj ect?
and identify
penalty
If yes, describe alternative or option Continue with operations and maintenance of facilities as -is
If no, describe why
Describe how that department will operate
or maintain the project after completion
Page 5 of 13
Will public engagement be employed to Yes Q No
develop or implement the project?
If yes, describe sector(s) of the public, City Council and interested members of the public would be invited to share thoughts and
engagement level and influence comments on the project plans
If yes, estimate cost and/or revenue benefit Community ownership in the features ultimately constructed
of public engagement
Enter this amount in the Funding Worksheet.
https://tpvpay.com/project/Print_project.php?id=270
A-41
5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the miect im rove efficienc ? O Yes Q No
P J p y
If yes, describe how
If yes, can efficiency be quantified? O Yes O No
If yes, describe quantity
Will the project improve economy? O Yes Q No
If yes, quantify amount
Will the project increase or improve O Yes QQ No
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
O Yes *No
O Yes *No
funding source
Go to Funding Worksheet and enter amounts
*Yes Q No
state
*Yes O No
If yes, go to Funding Worksheet and enter amounts.
Q Yes Q No
If yes, go to Funding Worksheet and enter amounts.
O Yes *No
percent completion
Page 7 of 13
If yes, go to Funding Worksheet and enter amounts. A-42
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
RPV CIPPS Page 8 of 13
Will the project require additional part-time O Yes Qi No
personnel?
If yes, estimate number
If yes, go to Funding Worksheet and enter amounts.
Will the project generate revenue?
O Yes Qi No
If yes, estimate annual amount
If yes, go to Funding Worksheet and enter amounts.
Can the City partner with other agencies,
Yes Q No
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
local community groups
If yes, is it anticipated that other agency,
Q Yes Q No
group, jurisdiction would be able to assist
financially?
If yes, describe how
donations and/or service projects
If yes, identify potential funding amount or
unknown at this time
percentage of total expenditure
If no, would the other agency, group,
O Yes Q No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1996
identify or estimate original construction
date
Estimate remaining life of existing facility to 10
be replaced in years
Estimate residual value of existing facility 0
Provide anticipated life of new facility in 20
years
Can the life cycle cost be calculated? * Yes Q No
If yes, show the annual maintenance cost to be calculated
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + N/A
Operating Costs) _
A-43
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
RPV CIPPS
Page 9 of 13
Describe the degree of uncertainty (high, medium, low) for:
Capital cost
OH
OM
*L
Why?
Construction duration
O H
O M
L
Why?
Operating and maintenance costs
O H
O M
OQ L
Why?
Negative environmental impact
O H
O M
L
Why?
Positive environmental impact
O H
0 M
Oi L
Why?
Over/under estimation of benefits (e.g.,
O H
0 M
Q L
Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes
O No
cost been prepared?
If yes, is it a range?
O Yes
No
If yes, show range in Funding Worksheet
If no, show
estimated amount in Funding
Worksheet
Can the cost of not implementing the project
O Yes
Oi No
be estimated?
If yes, identify cost
If yes, does it increase deferred maintenance
O Yes
O No
for its infrastructure category?
If yes, estimate deferred cost and duration
A-44
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
RPV CIPPS Page 10 of 13
OUTSIDE FUNDING
Is the project currently spending grant or O Yes No
other outside funds?
If yes, identify funding source amount expenditure
deadline
agreement title, date Go to Funding Worksheet and enter amounts.
Is the project eligible for outside funding? O Yes QQ No
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Go to Funding Worksheet and enter amounts.
Are there funding constraints? O Yes Q No
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Are there consequences of missing O Yes No
milestones, deadlines, etc.?
If yes, describe situation and consequence
Is funding tied to expenditure phases? O Yes QQ No
If yes, describe the expenditure phase
A-45
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
RPV CIPPS Page 12 of 13
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document potentially categorical exemption
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document see above
required
Does the project require NEPA review? O Yes Q No
If yes, describe NEPA document
Has a NEPA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-46
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
RPV CIPPS Page 13 of 13
PROJECT PROFILE FUNDING WORKSHEET
Annual impact on operating budget
Are operating impacts anticipated? * Yes O No
If yes, identify impact on worksheet:
Name of impacted fund General Fund (operations); Quimby (capital improvement)
Revenue generated 0
Savings created 0
Additional FTEs needed 0
Salaries/benefits for additional FTEs 0
Additional (decreased) operating expenses
+25000 annually
Debt service (P+I) 0
Fiscal year impacts anticipated to begin 2016/17
Construction management and inspection $10000 $ $
Contingency (list amount % and basis) $ $ $
Totals $250000 $0 $0
A-47
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate
Aproved Budget
Current Estimate
Preliminary engineering
$20000
$
$
Environmental
$
$
$
Right -of -Way (legal plus acquisition)
$
$
$
Capital equipment
$20000
$
$
Construction (identify relevant infrastructure
$200000
$
$
categories)
Construction management and inspection $10000 $ $
Contingency (list amount % and basis) $ $ $
Totals $250000 $0 $0
A-47
https://rpvpay.com/project/print_project.php?id=270 5/24/2016
Page Intentionally Blank
li�
Civic Center Master Plan
• Master Site Planning for Civic
Center Including City Hall, Public
Safety Facilities and Corporation
Ya rd
• Requested $250,000 for Design
• Source: CIP Reserves
RPV CIPPS
Project: Civic Center Master Plan
Project Name
Location
Project Description
Describe the community benefit or outcome
from implementing this project
Describe the outcome if the project is not
implemented
Date of original proposal
Name of department proposing this project
Name of departmental project manager
Name and contact information for resident
or community group proposing this project
Page 2 of 14
General Project Profile Information
Civic Center Master Plan
City Hall/Upper Point Vicente Park
Develop a master plan for the Civic Center property including a city hall, public safety facilities
and corporation yard
A master plan that articulates the community vision for the site and the proposed facilities that
can be funded and constructed
The site would remain as -is and ultimately require major renovations to accommodate civic
operations including significant energy efficiency and accessibility upgrades
05-31-2016
Administration
Yap
N/A
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community General Plan, Parks Master Plan, Corporation Yard Utilization Study
plans to be referenced/utilized for design
List the standards to be referenced/utilized California Building Code, LEED
for design
Identify infrastructure category Public buildings O Park sites O Trails O Stormwater system
Q Citywide sanitary sewer system Q Ab Cove sewer system
Q R/W, traffic control devices Q PB landslide
Name of department or community group Public Works
that will take responsibility for the project
after completion
Does that group have the resources to O Yes O No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
* Yes O No
https://tpvpay.com/project/Print_project.php?id=271
A-50
5/24/2016
RPV CIPPS
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
local community groups
monetary and in-kind donations and grants
Page 3 of 14
A-51
https://rpvpay.com/project/print_project.php?id=271 5/24/2016
RPV CIPPS
PUBLIC HEALTH AND SAFETY
Will the project enhance or improve the Yes No
overall safety of the city and the delivery of
services?
If yes, describe how eliminate safety issues in the corporation yard
If yes, quantify if feasible
Will the project protect the health and O Yes Q No
welfare of residents and/or the environment?
If yes, describe sector and how
Is the project required to mitigate or O Yes 0 No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be less than contemporary working conditions in the corporation yard
addressed
Will the project eliminate an identified Yes Q No
safety condition?
Page 4 of 14
If yes, describe how the condition is new construction would be fully compliant with contemporary safe operational
eliminated standards for corporation yards
If no, will the project mitigate it? 0 Yes No
If yes, describe the mitigation
Will the project eliminate an identified 0 Yes QQ No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? 0 Yes No
If yes, describe the mitigation
A-52
https://rpvpay.com/project/print_project.php?id=271 5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
Does the project support maintenance and
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation?
If yes, cite law or regulation
Page 5 of 14
ESSENTIAL CITY SERVICES
* Yes No
city hall and corporation yard
new construction would be fully compliant with contemporary safe operational standards for
corporation yards
*Yes Q No
new construction would be fully compliant with contemporary safe operational standards for
corporation yards
O Yes *No
If the project is not done, would not O Yes No
performing the project violate a law or
regulation?
If yes, cite law or regulation
Is the project required by a court order, O Yes QQ No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
and identify
penalty
Are there alternatives or options to the O Yes O No
proj ect?
If yes, describe alternative or option maintenance of the status quo, as -is condition, which would require significant expenditure to
bring up to current standards
If no, describe why
Describe how that department will operate
or maintain the project after completion
Will public engagement be employed to Yes Q No
develop or implement the project?
If yes, describe sector(s) of the public, City Council and interested parties would be invited to participate in the design process
engagement level and influence
If — e timatos t nd/ r r n b n fit Community ownership in the final design
Y s e ca o eve ue e e
of public engagement A-53
https://rpvpay.com/project/print_project.php?id=271 5/24/2016
RPV CIPPS
Page 8 of 14
ECONOMY AND EFFICIENCY
Will the project improve efficiency? * Yes O No
If yes, describe how less effort would be involved in maintaining the mid-century facilities
If yes, can efficiency be quantified? 0 Yes 0 No
If yes, describe quantity to be calculated
Will the project improve economy? * Yes 0 No
If yes, quantify amount to be calculated
Will the project increase or improve
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
*Yes O No
there will be less wasted operational space on site that would become available for parkland
and passive recreational activities
to be calculated
0 Yes *No
0 Yes *No
funding source
Go to Funding Worksheet and enter amounts
Q Yes 0 No
state
* Yes O No
If yes, go to Funding Worksheet and enter amounts.
*Yes 0 No
If yes, go to Funding Worksheet and enter amounts.
0 Yes *No
percent completion
If yes, go to Funding Worksheet and enter amounts. A-54
https://rpvpay.com/project/print_project.php?id=271 5/24/2016
RPV CIPPS
Will the project require additional part-time O Yes Qi No
Page 9 of 14
personnel?
If yes, estimate number
If yes, go to Funding Worksheet and enter amounts.
Will the project generate revenue?
O Yes Qi No
If yes, estimate annual amount
If yes, go to Funding Worksheet and enter amounts.
Can the City partner with other agencies,
Yes Q No
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
fire and police agencies, telecommunication companies, local community groups
If yes, is it anticipated that other agency,
Q Yes Q No
group, jurisdiction would be able to assist
financially?
If yes, describe how
Public safety would co -locate facilities on-site, ground lease possibilities for local community
groups
If yes, identify potential funding amount or
to be calculated
percentage of total expenditure
If no, would the other agency, group,
O Yes Q No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1950
identify or estimate original construction
date
Estimate remaining life of existing facility to 0
be replaced in years
Estimate residual value of existing facility 0
Provide anticipated life of new facility in 50
years
Can the life cycle cost be calculated? * Yes Q No
If yes, show the annual maintenance cost to be calculated
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + N/A
Operating Costs) = A-55
https://rpvpay.com/project/print_project.php?id=271 5/24/2016
RPV CIPPS Page 10 of 14
Describe the degree of uncertainty (high, medium, low) for:
Capital cost H 0 M L Why?
Construction duration 0 H 0 M Ce? L Why?
Operating and maintenance costs 0 H 0 M OQ L Why?
Negative environmental impact 0 H 0 M Oi L Why?
Positive environmental impact
0 H 0 M Oi L Why?
Over/under estimation of benefits (e.g.,
0 H 0 M Oi L Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
0 Yes OQ No
cost been prepared?
If yes, is it a range?
0 Yes 0 No
If yes, show range in Funding Worksheet
If no, show estimated amount in Funding Worksheet
Can the cost of not implementing the project
0 Yes 0 No
be estimated?
If yes, identify cost
500,000 to 1,000,000 for upgrades to existing facilities
If yes, does it increase deferred maintenance
O Yes 0 No
for its infrastructure category?
If yes, estimate deferred cost and duration 500,000 to 1,000,000 for upgrades to existing facilities
A-56
https://rpvpay.com/project/print_project.php?id=271 5/24/2016
RPV CIPPS
Is the project currently spending grant or
other outside funds?
If yes, identify funding source
agreement title, date
Is the project eligible for outside funding?
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Are there funding constraints?
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
OUTSIDE FUNDING
0 Yes Q No
amount expenditure
deadline
Go to Funding Worksheet and enter amounts.
*Yes 0 No
To be determined
To be determined
To be determined
To be determined
Go to Funding Worksheet and enter amounts.
0 Yes *No
Are there consequences of missing 0 Yes 0 No
milestones, deadlines, etc.?
If yes, describe situation and consequence
Is funding tied to expenditure phases? 0 Yes 0 No
If yes, describe the expenditure phase
https://tpvpay.com/project/Print_project.php?id=271
Page 11 of 14
A-57
5/24/2016
RPV CIPPS Page 13 of 14
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document Potentially initial study/mitigated negative declaration
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document see above
required
Does the project require NEPA review? 0 Yes Q No
If yes, describe NEPA document potentially yes if federal funding is acquired
Has a NEPA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-58
https://rpvpay.com/project/print_project.php?id=271 5/24/2016
RPV CIPPS Page 14 of 14
PROJECT PROFILE FUNDING WORKSHEET
https://tpvpay.com/project/Print_project.php?id=271
A-59
5/24/2016
Annual impact on operating budget
Are operating impacts anticipated?
* Yes O No
If yes, identify impact on worksheet:
Name of impacted fund
General Fund
Revenue generated
unknown
Savings created
to be calculated
Additional FTEs needed
0
Salaries/benefits for additional FTEs
0
Additional (decreased) operating expenses
0
Debt service (P+I)
depends on funding strategy
Fiscal year impacts anticipated to begin
2016/2017
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate Aproved Budget
Current Estimate
Preliminary engineering
$250000 $
$
Environmental
$to be determined $
$
Right -of -Way (legal plus acquisition)
$to be determined $
$
Capital equipment
$to be determined $
$
Construction (identify relevant infrastructure
$to be determined $
$
categories)
Public Buildings
Construction management and inspection
$to be determined $
$
Contingency (list amount % and basis)
$to be determined $
$
Totals
$250000 $0
$0
https://tpvpay.com/project/Print_project.php?id=271
A-59
5/24/2016
Page Intentionally Blank
ADA Improvements at City Hall Bus Stop
• Accessible Connection to
Metro Bus Stop from City
Hall Parking Lot
• $192,400 Requested for
Design and Construction
• Source: CDBG
A-61
RPV CIPPS
Project: ADA Improvements at City Hall Bus Stop
Project Name
Location
Project Description
Describe the community benefit or outcome
from implementing this project
Describe the outcome if the project is not
implemented
Date of original proposal
Name of department proposing this project
Name of departmental project manager
Name and contact information for resident
or community group proposing this project
Page 2 of 13
General Project Profile Information
ADA Improvements at City Hall Bus Stop
City Hall Driveway on Hawthorne Blvd
Create an accessible connection between the existing METRO bus stop on Hawthorne Blvd and
the Community Room at City Hall
Visitors to City Hall that use the bus would have an all weather, accessible route to the
Community Room and City Hall proper
Visitors would continue to traverse a turf pathway or use the driveway to get to the Community
Room
05-31-2016
Public Works
Gibson
N/A
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community General Plan
plans to be referenced/utilized for design
List the standards to be referenced/utilized ADA Guidelines, California Building Code
for design
Identify infrastructure category Public buildings O Park sites O Trails O Stormwater system
0 Citywide sanitary sewer system 0 Ab Cove sewer system
0 R/W, traffic control devices 0 PB landslide
Name of department or community group Public Works
that will take responsibility for the project
after completion
Does that group have the resources to O Yes O No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
0 Yes *No
https://tpvpay.com/project/Print_project.php?id=272
A-62
5/24/2016
RPV CIPPS Page 3 of 13
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
A-63
https://rpvpay.com/project/print_project.php?id=272 5/24/2016
RPV CIPPS
Will the project enhance or improve the
overall safety of the city and the delivery of
services?
PUBLIC HEALTH AND SAFETY
* Yes No
Page 4 of 13
If yes, describe how by removing accessibility impediments to city hall patrons who travel by bus
If yes, quantify if feasible N/A
Will the project protect the health and Yes Q No
welfare of residents and/or the environment?
If yes, describe sector and how eliminate the use of the turf pathway and vehicular driveway as walkways
Is the project required to mitigate or Yes Q No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be use of turf pathway or driveway as pedestrian access to Community Room
addressed
Will the project eliminate an identified Yes Q No
safety condition?
If yes, describe how the condition is construction of an all weather, accessible and separate from vehicular traffic
eliminated Walkway
If no, will the project mitigate it? O Yes O No
If yes, describe the mitigation
Will the project eliminate an identified O Yes Qi No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? O Yes No
If yes, describe the mitigation
https://tpvpay.com/project/Print_project.php?id=272
A-64
5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
ESSENTIAL CITY SERVICES
* Yes No
city hall
improve access
Does the project support maintenance and 0 Yes QQ No
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation? 0 Yes No
If yes, cite law or regulation
If the project is not done, would not 0 Yes QQ No
performing the project violate a law or
regulation?
If yes, cite law or regulation
Is the project required by a court order, 0 Yes Qi No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the O Yes Q No
proj ect?
and identify
penalty
Page 5 of 13
If yes, describe alternative or option existing pedestrian routes from the bus stop to city hall proper would continue to be used
If no, describe why
Describe how that department will operate
or maintain the project after completion
Will public engagement be employed to
develop or implement the project?
If yes, describe sector(s) of the public,
engagement level and influence
If yes, estimate cost and/or revenue benefit
of public engagement
Would be placed in the maintenance schedule for sidewalks and park landscaping
0 Yes *No
Enter this amount in the Funding Worksheet.
https://tpvpay.com/project/Print_project.php?id=272
A-65
5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the miect im rove efficienc ? O Yes Q No
P J p y
If yes, describe how
If yes, can efficiency be quantified? O Yes O No
If yes, describe quantity
Will the project improve economy? O Yes Q No
If yes, quantify amount
Will the project increase or improve
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
*Yes Q No
incremental cost to maintain sidewalk
O Yes *No
Q Yes *No
funding source
Go to Funding Worksheet and enter amounts
*Yes Q No
state
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
percent completion
Page 7 of 13
If yes, go to Funding Worksheet and enter amounts. A-66
https://rpvpay.com/project/print_project.php?id=272 5/24/2016
RPV CIPPS
Will the project require additional part-time O Yes Qi No
personnel?
If yes, estimate number
Will the project generate revenue?
If yes, estimate annual amount
Can the City partner with other agencies,
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
If yes, is it anticipated that other agency,
Q Yes Q No
group, jurisdiction would be able to assist
financially?
If yes, describe how
If yes, identify potential funding amount or
percentage of total expenditure
If no, would the other agency, group, O Yes Qi No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1950
identify or estimate original construction
date
Estimate remaining life of existing facility to 0
be replaced in years
Estimate residual value of existing facility 0
Provide anticipated life of new facility in 50
years
Can the life cycle cost be calculated? * Yes Q No
If yes, show the annual maintenance cost to be calculated
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + N/A
Operating Costs) _
https://tpvpay.com/project/Print_project.php?id=272
Page 8 of 13
A-67
5/24/2016
RPV CIPPS
Page 9 of 13
Describe the degree of uncertainty (high, medium, low) for:
Capital cost
OH
OM
*L
Why?
Construction duration
0 H
0 M
L
Why?
Operating and maintenance costs
0 H
0 M
OQ L
Why?
Negative environmental impact
0 H
0 M
Q L
Why?
Positive environmental impact
0 H
0 M
Oi L
Why?
Over/under estimation of benefits (e.g.,
0 H
0 M
Q L
Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes
0 No
cost been prepared?
If yes, is it a range?
0 Yes
No
If yes, show range in Funding Worksheet
If no, show
estimated amount in Funding
Worksheet
Can the cost of not implementing the project
0 Yes
Oi No
be estimated?
If yes, identify cost
If yes, does it increase deferred maintenance
0 Yes
0 No
for its infrastructure category?
If yes, estimate deferred cost and duration
A-68
https://rpvpay.com/project/print_project.php?id=272 5/24/2016
RPV CIPPS
Is the project currently spending grant or
other outside funds?
If yes, identify funding source CDBG
agreement title, date
Is the project eligible for outside funding?
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Are there funding constraints?
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Page 10 of 13
OUTSIDE FUNDING
* Yes No
amount 192400 expenditure 06-30-2017
deadline
Go to Funding Worksheet and enter amounts.
*Yes Q No
CDBG
192400
0
Accessibility
Go to Funding Worksheet and enter amounts.
*Yes O No
must be expended on accessibility projects
see above
Are there consequences of missing Yes Q No
milestones, deadlines, etc.?
If yes, describe situation and consequence grant funding could be retracted
Is funding tied to expenditure phases? O Yes O No
If yes, describe the expenditure phase design and construction
https://tpvpay.com/project/Print_project.php?id=272
A-69
5/24/2016
RPV CIPPS Page 12 of 13
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document potential categorical exemption
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document see above
required
Does the project require NEPA review? O Yes Q No
If yes, describe NEPA document
Has a NEPA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-70
https://rpvpay.com/project/print_project.php?id=272 5/24/2016
RPV CIPPS Page 13 of 13
PROJECT PROFILE FUNDING WORKSHEET
Annual impact on operating budget
Are operating impacts anticipated? * Yes O No
If yes, identify impact on worksheet:
Name of impacted fund General Fund
Revenue generated 0
Savings created 0
Additional FTEs needed 0
Salaries/benefits for additional FTEs 0
Additional (decreased) operating expenses +5000
Debt service (P+I) 0
Fiscal year impacts anticipated to begin 2017/18
Construction management and inspection $5000 $ $
Contingency (list amount % and basis) $ $ $
Totals $192000 $0 $0
A-71
https://rpvpay.com/project/print_project.php?id=272 5/24/2016
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate
Aproved Budget
Current Estimate
Preliminary engineering
$10000
$
$
Environmental
$
$
$
Right -of -Way (legal plus acquisition)
$
$
$
Capital equipment
$
$
$
Construction (identify relevant infrastructure
$177000
$
$
categories)
Construction management and inspection $5000 $ $
Contingency (list amount % and basis) $ $ $
Totals $192000 $0 $0
A-71
https://rpvpay.com/project/print_project.php?id=272 5/24/2016
Page Intentionally Blank
A-72
Arterial Walls and Fences Replacement Program
• Replace Deteriorated and
Unattractive Masonry Walls and
Fences
• Program Commences with
Hawthorne Blvd.
• $500,000 Requested
• Source: CIP Reserves
A-73
RPV CIPPS
Page 2 of 14
Project: Arterial Walls and Fences Replacement Program
Project Name
Location
Project Description
Describe the community benefit or outcome
from implementing this project
Describe the outcome if the project is not
implemented
Date of original proposal
Name of department proposing this project
Name of departmental project manager
Name and contact information for resident
or community group proposing this project
General Project Profile Information
Arterial Walls and Fences Replacement
Program
All arterial roads
Replace deteriorated, failing and unattractive masonry walls and chain link fences generally
along and outside of the arterial road public right-of-way through a long-term collaborative
effort between the private property owners and the City. The first order of work would be the
City removing damaged chain link fencing along Hawthorne Blvd (contingent on private
property owner permission and indemnification). Future program years would involve
replacement partnership with the affected private property owners.
Improved aesthetics and placement of new walls that are structurally suitable to retain slope
material
Walls and fences would be replaced on a sporadic basis pursuant to private property owner
response to code enforcement activity
05-31-2016
Community Development
Mihranian
N/A
Project Phases
Initiation Phase Time (Working Days)
Planning Phase Time (Working Days)
Execution Phase Time (Working Days)
Monitoring Phase Time (Working Days)
Closing Phase Time (Working Days)
List the municipal policies or community
plans to be referenced/utilized for design
List the standards to be referenced/utilized
for design
Identify infrastructure category
Name of department or community group
that will take responsibility for the project
after completion
General Plan
California Building Code
Can run concurrent?
Can run concurrent?
Can run concurrent?
Can run concurrent?
Can run concurrent?
O Public buildings 0 Park sites
0 Citywide sanitary sewer system
Oi R/W, traffic control devices
Individual private property owners
0 Yes *No
0 Trails 0 Stormwater system
0 Ab Cove sewer system
0 PB landslide
A-74
https://rpvpay.com/project/print_project.php?id=273 5/24/2016
RPV CIPPS
Page 3 of 14
Does that group have the resources to
provide long-term maintenance and
replacement?
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, go to Funding Worksheet and enter amount(s)
*Yes O No
If yes, identify agency, community, non- Individual private property owners
profit
If yes, describe the benefit of the collaboration with the Individual private property owners is essential to
collaboration implementation of this program
A-75
https://rpvpay.com/project/print_project.php?id=273 5/24/2016
RPV CIPPS
Will the project enhance or improve the
overall safety of the city and the delivery of
services?
PUBLIC HEALTH AND SAFETY
0 Yes Q No
If yes, describe how
If yes, quantify if feasible
Will the project protect the health and 0 Yes OQ No
welfare of residents and/or the environment?
If yes, describe sector and how
Is the project required to mitigate or O Yes 0 No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be failing masonry walls
addressed
Will the project eliminate an identified Yes O No
safety condition?
Page 4 of 14
If yes, describe how the condition is replacement of structurally -inadequate masonry walls with ones design to support
eliminated slope surcharge
If no, will the project mitigate it? 0 Yes 0 No
If yes, describe the mitigation
Will the project eliminate an identified 0 Yes Oi No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? 0 Yes OQ No
If yes, describe the mitigation
https://tpvpay.com/project/Print_project.php?id=273
A-76
5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
Does the project support maintenance and
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation?
If yes, cite law or regulation
Page 5 of 14
ESSENTIAL CITY SERVICES
Yes Q No
Q Yes * No
Q Yes *No
If the project is not done, would not O Yes Q No
performing the project violate a law or
regulation?
If yes, cite law or regulation
and identify
penalty
Is the project required by a court order, O Yes QQ No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the
proj ect?
If yes, describe alternative or option
If no, describe why
Describe how that department will operate
or maintain the project after completion
Will public engagement be employed to
develop or implement the project?
If yes, describe sector(s) of the public,
engagement level and influence
If yes, estimate cost and/or revenue benefit
of public engagement
*Yes O No
continue to use the code enforcement process to replace walls and fences
walls and fences will be maintained by their respective private property owner
*Yes O No
City Council, interested individuals and impacted private property owners would be invited to
participate in the process to implement this program
improved aesthetics
Enter this amount in the Funding Worksheet. A-77
https://rpvpay.com/project/print_project.php?id=273 5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the miect im rove efficienc ? O Ycs Q No
P J p y
If yes, describe how
If yes, can efficiency be quantified? O Yes O No
If yes, describe quantity
Will the project improve economy? O Yes Q No
If yes, quantify amount
Will the project increase or improve O Yes QQ No
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
O Yes *No
O Yes *No
funding source
Go to Funding Worksheet and enter amounts
*Yes Q No
percent completion
Page 8 of 14
Prevailing wages are required If the City takes the initial steps to remove damaged chain link
fencing
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
O Yes Q No
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
https://tpvpay.com/project/Print_project.php?id=273
A-78
5/24/2016
RPV CIPPS
Will the project require additional part-time
personnel?
If yes, estimate number
Will the project generate revenue?
If yes, estimate annual amount
Can the City partner with other agencies,
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
If yes, is it anticipated that other agency,
group, jurisdiction would be able to assist
financially?
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
If yes, go to Funding Worksheet and enter amounts.
Q Yes *No
If yes, go to Funding Worksheet and enter amounts.
*Yes O No
Individual private property owners
*Yes Q No
If yes, describe how a pro -rate cost participation formula may be developed
If yes, identify potential funding amount or unknown at this time
percentage of total expenditure
If no, would the other agency, group, O Yes Q No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1950
identify or estimate original construction
date
Estimate remaining life of existing facility to
be replaced in years
Estimate residual value of existing facility
Provide anticipated life of new facility in
years
Can the life cycle cost be calculated?
If yes, show the annual maintenance cost
and %
0
0
50 (walls) / 20 (fencing)
* Yes Q No
to be calculated
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
NA
https://tpvpay.com/project/Print_project.php?id=273
Page 9 of 14
A-79
5/24/2016
RPV CIPPS Page 10 of 14
BCR = Benefits / (Construction Costs +
Operating Costs) _
Describe the degree of uncertainty (high, medium, low) for:
Capital cost H M • L Why?
Construction duration O H M • L Why?
Operating and maintenance costs 0 H Q M Q L Why?
Negative environmental impact 0 H 0 M Qi L Why?
Q H Q M Q• L
Positive environmental impact
Why?
Over/under estimation of benefits (e.g.,
O H
O M L Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
Yes
O No
cost been prepared?
If yes, is it a range?
O Yes
No
If yes, show range in Funding Worksheet
If no, show
estimated amount in Funding Worksheet
Can the cost of not implementing the project
O Yes
Qi No
be estimated?
If yes, identify cost
If yes, does it increase deferred maintenance
O Yes
O No
for its infrastructure category?
If yes, estimate deferred cost and duration
A-80
https://rpvpay.com/project/print_project.php?id=273 5/24/2016
RPV CIPPS
Maintaining infrastructure?
If yes, describe how
Maintaining services?
If yes, describe how
Enhancing infrastructure?
If yes, describe how
Enhancing services?
If yes, describe how
Preserving overall quality of life?
If yes, describe how
QUALITY OF LIFE AND SUSTAINABILITY
Will the project support the residential and/or business community by:
0 Yes Q No
0 Yes Q No
0 Yes Q No
0 Yes Q No
0 Yes Q No
Maintaining/preserving overall quality of 0 Yes Q No
life?
If yes, describe how
Enhancing overall quality of life? 0 Yes Q No
If yes, describe how
Ensure or increase economic vitality? 0 Yes Q No
If yes, describe how and amount
https://tpvpay.com/project/Print_project.php?id=273
Page 12 of 14
A-81
5/24/2016
RPV CIPPS Page 13 of 14
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? Yes Q No
If yes, describe CEQA document
Has a CEQA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document NA
required
Does the project require NEPA review? O Yes Qi No
If yes, describe NEPA document
Has a NEPA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes O No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-82
https://rpvpay.com/project/print_project.php?id=273 5/24/2016
RPV CIPPS Page 14 of 14
PROJECT PROFILE FUNDING WORKSHEET
Annual impact on operating budget
Are operating impacts anticipated? O Yes Q No
If yes, identify impact on worksheet:
Name of impacted fund
Revenue generated
Savings created
Additional FTEs needed
Salaries benefits for additional FTEs
Additional (decreased) operating expenses
Debt service (P+I)
Fiscal year impacts anticipated to begin
Construction management and inspection $50000 $ $
Contingency (list amount % and basis) $ $ $
Totals $500000 $0 $0
A-83
https://rpvpay.com/project/print_project.php?id=273 5/24/2016
Project Costs
Show original cost estimate
range, approved budget and current estimate for each budgeted
phase
Original Estimate
Aproved Budget
Current Estimate
Preliminary engineering
$50000
$
$
Environmental
$
$
$
Right -of -Way (legal plus acquisition)
$
$
$
Capital equipment
$
$
$
Construction (identify relevant infrastructure
$400000
$
$
categories)
Construction management and inspection $50000 $ $
Contingency (list amount % and basis) $ $ $
Totals $500000 $0 $0
A-83
https://rpvpay.com/project/print_project.php?id=273 5/24/2016
Page Intentionally Blank
Altamira Cyn Culvert Modifications at PVDS
• Raise Culvert Outlet
to Prevent
Trespassing
• $75,000 Requested
for Design
• Source: CIP Reserves + Y
may_
A-85
RPV CIPPS
Page 2 of 14
Project: Altamira Canyon Culvert Modifications at PVDS
General Project Profile Information
Project Name Altamira Canyon Culvert Modifications at
PVDS
Location PVDS at Altamira Canyon
Project Description Raise the outlet of the Altamira Canyon culvert under PVDS to prevent trespassing
Describe the community benefit or outcome Essentially eliminate trespassing from Abalone Cove beach areas into the private Portuguese
from implementing this project Bend community
Describe the outcome if the project is not Temporary grating installed in May 2016 would remain to dissuade trespassers however debris
implemented transported by storm flows would collect behind the grate potentially creating significant
upstream flooding over Narcissa Drive
Date of original proposal 04-19-2016
Name of department proposing this project Public Works
Name of departmental project manager Winje
Name and contact information for resident NA
or community group proposing this project
Project Phases
Initiation Phase
Time (Working Days)
Can run concurrent?
Planning Phase
Time (Working Days)
Can run concurrent?
Execution Phase
Time (Working Days)
Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community General Plan, Master Plan of Drainage
plans to be referenced/utilized for design
List the standards to be referenced/utilized Caltrans, PW Green Book
for design
Identify infrastructure category O Public buildings Q Park sites Q Trails *i Stormwater system
Q Citywide sanitary sewer system Q Ab Cove sewer system
O R/W, traffic control devices Q PB landslide
Name of department or community group Public Works
that will take responsibility for the project
after completion
Does that group have the resources to O Yes O No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
Q Yes *No
https://tpvpay.com/project/Print_project.php?id=274
A-86
5/24/2016
RPV CIPPS Page 3 of 14
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
A-87
https://rpvpay.com/project/print_project.php?id=274 5/24/2016
RPV CIPPS
Will the project enhance or improve the
overall safety of the city and the delivery of
services?
PUBLIC HEALTH AND SAFETY
*Yes O No
Page 4 of 14
If yes, describe how effectively reduce potential of damage and vandalism of private property by
individuals using culvert as access into gated neighborhood
If yes, quantify if feasible unknown
Will the project protect the health and Yes Q No
welfare of residents and/or the environment?
If yes, describe sector and how effectively reduce potential of damage and vandalism of private property by
individuals using culvert as access into gated neighborhood
Is the project required to mitigate or Yes Q No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be trespassing and vandalism
addressed
Will the project eliminate an identified 0 Yes 0 No
safety condition?
If yes, describe how the condition is creating a physical barrier to trespassing
eliminated
If no, will the project mitigate it? O Yes 0 No
If yes, describe the mitigation
Will the project eliminate an identified O Yes No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? 0 Yes Q No
If yes, describe the mitigation
https://tpvpay.com/project/Print_project.php?id=274
A-88
5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
Does the project support maintenance and
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation?
If yes, cite law or regulation
Page 5 of 14
ESSENTIAL CITY SERVICES
* Yes No
stormwater system
reduce the maintenance cost of removing debris collected against the outlet grate and graffiti
abatement costs
*Yes Q No
stormwater system
reduce the maintenance cost of removing debris collected against the outlet grate and graffiti
abatement costs
O Yes *No
If the project is not done, would not O Yes Qi No
performing the project violate a law or
regulation?
If yes, cite law or regulation
and identify
penalty
Is the project required by a court order, O Yes QQ No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the
proj ect?
If yes, describe alternative or option
If no, describe why
Describe how that department will operate
or maintain the project after completion
Will public engagement be employed to
develop or implement the project?
If yes, describe sector(s) of the public,
engagement level and influence
If yes, estimate cost and/or revenue benefit
of public engagement
Q Yes Q No
continue use of the outlet grate
Proposed solution will require scheduled maintenance
Q Yes *No
https://tpvpay.com/project/Print_project.php?id=274
A-89
5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the project improve efficiency? * Yes O No
If yes, describe how eliminate the cost and effort to maintain a grate on the culvert outlet
If yes, can efficiency be quantified? * Yes Q No
If yes, describe quantity 5000 per occurrence
W'll th t ' 7 O Yes QQ No
W;11
e pro�ec improve economy.
If yes, quantify amount
Will the project increase or improve O Yes Q No
productivity of municipal operations?
If yes, describe how eliminate the cost and effort to maintain a grate on the culvert outlet
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
Q Yes *No
O Yes Qi No
funding source
Go to Funding Worksheet and enter amounts
*Yes O No
state
* Yes Q No
If yes, go to Funding Worksheet and enter amounts.
*Yes O No
If yes, go to Funding Worksheet and enter amounts.
O Yes *No
If yes, go to Funding Worksheet and enter amounts.
https://tpvpay.com/project/Print_project.php?id=274
percent completion
Page 8 of 14
A-90
5/24/2016
RPV CIPPS Page 9 of 14
Will the project require additional part-time 0 Yes No
personnel?
If yes, estimate number
If yes, go to Funding Worksheet and enter amounts.
Will the project generate revenue? 0 Yes Q No
If yes, estimate annual amount
If yes, go to Funding Worksheet and enter amounts.
Can the City partner with other agencies, 0 Yes No
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
If yes, is it anticipated that other agency, 0 Yes Q No
group, jurisdiction would be able to assist
financially?
If yes, describe how
If yes, identify potential funding amount or
percentage of total expenditure
If no, would the other agency, group, 0 Yes QQ No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1985
identify or estimate original construction
date
Estimate remaining life of existing facility to 70
be replaced in years
Estimate residual value of existing facility 350000
Provide anticipated life of new facility in 100
years
Can the life cycle cost be calculated? * Yes Q No
If yes, show the annual maintenance cost will be calculated
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + NA
Operating Costs) _
A-91
https://rpvpay.com/project/print_project.php?id=274 5/24/2016
RPV CIPPS
Page 10 of 14
Describe the degree of uncertainty (high, medium, low) for:
Capital cost
O H
0 M
Q L
Why?
design is required to estimate
Has an engineer's estimate of construction
O Yes
No
construction cost
Construction duration
O H
Q M
QQ L
Why?
Operating and maintenance costs
O H
O M
Qi L
Why?
Q No
Negative environmental impact
O H
M
Q L
Why?
consultation with resource agencies is
If yes, does it increase deferred maintenance
O Yes
QQ No
for its infrastructure category?
required for work in canyon
If yes, estimate deferred cost and duration
OH
OM
OL
Positive environmental impact
Why?
Over/under estimation of benefits (e.g.,
O H
O M L Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes
No
cost been prepared?
If yes, is it a range?
O Yes
Q No
If yes, show range in Funding Worksheet
If no, show estimated amount in Funding Worksheet
Can the cost of not implementing the project
Yes
Q No
be estimated?
If yes, identify cost
+25000/yr
If yes, does it increase deferred maintenance
O Yes
QQ No
for its infrastructure category?
If yes, estimate deferred cost and duration
A-92
https://rpvpay.com/project/print_project.php?id=274 5/24/2016
RPV CIPPS Page 11 of 14
OUTSIDE FUNDING
Is the project currently spending grant or O Yes No
other outside funds?
If yes, identify funding source amount expenditure
deadline
agreement title, date Go to Funding Worksheet and enter amounts.
Is the project eligible for outside funding? O Yes QQ No
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Go to Funding Worksheet and enter amounts.
Are there funding constraints? O Yes Q No
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Are there consequences of missing O Yes No
milestones, deadlines, etc.?
If yes, describe situation and consequence
Is funding tied to expenditure phases? O Yes QQ No
If yes, describe the expenditure phase
A-93
https://rpvpay.com/project/print_project.php?id=274 5/24/2016
RPV CIPPS Page 13 of 14
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document most likely initial study/negative declaration
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document see above
required
Does the project require NEPA review? O Yes Q No
If yes, describe NEPA document
Has a NEPA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-94
https://rpvpay.com/project/print_project.php?id=274 5/24/2016
RPV CIPPS Page 14 of 14
PROJECT PROFILE FUNDING WORKSHEET
Annual impact on operating budget
Are operating impacts anticipated? * Yes O No
If yes, identify impact on worksheet:
Name of impacted fund General Fund
Revenue generated 0
Savings created 0
Additional FTEs needed 0
Salaries/benefits for additional FTEs 0
Additional (decreased) operating expenses unknown at this time
Debt service (P+I) 0
Fiscal year impacts anticipated to begin 2017/18
Construction management and inspection $ $ $
Contingency (list amount % and basis) $ $ $
Totals $75000 $0 $0
A-95
https://rpvpay.com/project/print_project.php?id=274 5/24/2016
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate
Aproved Budget
Current Estimate
Preliminary engineering
$75000
$
$
Environmental
$
$
$
Right -of -Way (legal plus acquisition)
$
$
$
Capital equipment
$
$
$
Construction (identify relevant infrastructure
$
$
$
categories)
Construction management and inspection $ $ $
Contingency (list amount % and basis) $ $ $
Totals $75000 $0 $0
A-95
https://rpvpay.com/project/print_project.php?id=274 5/24/2016
Page Intentionally Blank
Torrance Airport Storm Water Quality Project
• Improve SW Quality to Machado
La ke
• Multi -agency Project Led by City
of Torrance
• Grant Funding Pending
• $460,000 Requested (Matching
Funds)
• Source: CIP Reserves
Machado OrainawArea
A-97
RPV CIPPS
Project: Torrance Airport Stormwater Quality Project
General Project Profile Information
Proiect Name Torrance Airport Stormwater Quality Project
J
Location
Project Description
Describe the community benefit or outcome
from implementing this project
Describe the outcome if the project is not
implemented
Date of original proposal
Name of department proposing this project
Name of departmental project manager
Name and contact information for resident
or community group proposing this project
Page 2 of 14
Torrance Airport
Improve stormwater quality of flows from RPV into Machado Lake
The Machado Lake watershed will become compliant with our MS4 requirements
More expensive projects would be required
03-01-2016
Public Works
Winje
N/A
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community EWMP
plans to be referenced/utilized for design
List the standards to be referenced/utilized
for design
Identify infrastructure category 0 Public buildings 0 Park sites 0 Trails Oi Stormwater system
0 Citywide sanitary sewer system 0 Ab Cove sewer system
0 R/W, traffic control devices 0 PB landslide
Name of department or community group City of Torrance
that will take responsibility for the project
after completion
Does that group have the resources to O Yes 0 No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
* Yes 0 No
https://tpvpay.com/project/Print_project.php?id=195
A-98
5/24/2016
RPV CIPPS Page 3 of 14
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non- Cities of Torrance, Rolling Hills, Rolling Hills Estates, County of Los Angeles
profit
If yes, describe the benefit of the Mutually beneficial stormwater quality improvement for drainage entering into
collaboration Machado Lake
https://rpvpay.com/project/print_project.php?id=195 5/24/2016
RPV CIPPS
Will the project enhance or improve the
overall safety of the city and the delivery of
services?
PUBLIC HEALTH AND SAFETY
O Yes Q No
If yes, describe how
If yes, quantify if feasible
W'll th t t t +1' h 1 d O Yes QQ No
Page 4 of 14
W;11
e proJec pro ec a ea an
welfare of residents and/or the environment?
If yes, describe sector and how reducing pollutants in stormwater runoff into Machado Lake will improve its water
quality and the involved environment
Is the project required to mitigate or O Yes No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be
addressed
Will the project eliminate an identified O Yes QQ No
safety condition?
If yes, describe how the condition is
eliminated
If no, will the project mitigate it? O Yes QQ No
If yes, describe the mitigation
Will the project eliminate an identified O Yes QQ No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? O Yes No
If yes, describe the mitigation
A-100
https://rpvpay.com/project/print_project.php?id=195 5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
ESSENTIAL CITY SERVICES
* Yes No
stormwater system
improves stormwater quality
Does the project support maintenance and 0 Yes QQ No
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation? Yes 0 No
If yes, cite law or regulation NPDES
If the project is not done, would not Yes Q No
performing the project violate a law or
regulation?
If yes, cite law or regulation Cleanwater Act
Is the project required by a court order, 0 Yes No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the
proj ect?
If yes, describe alternative or option
If no, describe why
Describe how that department will operate
or maintain the project after completion
Will public engagement be employed to
develop or implement the project?
If yes, describe sector(s) of the public,
engagement level and influence
If yes, estimate cost and/or revenue benefit
of public engagement
*Yes Q No
Page 5 of 14
and identify financial, criminal and civil penalities if the
penalty City does not act on stormwater quality in
general
the city could construct within its own jurisdiction suitable stormwater treatment facilities that
could achieve the same outcome
the project will be operated and maintained by the city of Torrance
*Yes 0 No
interested local community groups
minimal cost
https://tpvpay.com/project/Print_project.php?id=195
A-101
5/24/2016
RPV CIPPS
Page 8 of 14
ECONOMY AND EFFICIENCY
Will the project improve efficiency? * Yes O No
If yes, describe how The City would not consequently be required to design, construct, operate, maintain its own
facility
If yes, can efficiency be quantified? * Yes Q No
If yes, describe quantity Reduction in capital expenses (approx $40,000,000)
Will the project improve economy? O Yes Qi No
If yes, quantify amount
Will the project increase or improve Yes O No
productivity of municipal operations?
If yes, describe how Another agency will operate and maintain the facility
If yes, quantify amount of increase or Not require additional personnel expenses
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
O Yes Qi No
O Yes *No
funding source
Go to Funding Worksheet and enter amounts
*Yes O No
state and federal if federal funding is used
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
O Yes *No
percent completion
If yes, go to Funding Worksheet and enter amounts. A-1 02
https://rpvpay.com/project/print_project.php?id=195 5/24/2016
RPV CIPPS Page 9 of 14
Will the project require additional part-time O Yes Qi No
personnel?
If yes, estimate number
If yes, go to Funding Worksheet and enter amounts.
Will the project generate revenue?
O Yes Qi No
If yes, estimate annual amount
If yes, go to Funding Worksheet and enter amounts.
Can the City partner with other agencies,
Yes Q No
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
As noted elsewhere
If yes, is it anticipated that other agency,
Q Yes Q No
group, jurisdiction would be able to assist
financially?
If yes, describe how
pro -rate cost sharing
If yes, identify potential funding amount or
Depends on number of participating agencies
percentage of total expenditure
If no, would the other agency, group,
O Yes QQ No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution NA
If the project is work to an existing facility,
identify or estimate original construction
date
Estimate remaining life of existing facility to N/A
be replaced in years
Estimate residual value of existing facility N/A
Provide anticipated life of new facility in 50 -yrs
years
Can the life cycle cost be calculated? * Yes Q No
If yes, show the annual maintenance cost To be determined
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + N/A
Operating Costs) _
A-103
https://rpvpay.com/project/print_project.php?id=195 5/24/2016
RPV CIPPS
Page 10 of 14
Describe the degree of uncertainty (high, medium, low) for:
Capital cost
O H Q M Q L
Why?
Construction duration
O H M 0 L
Why?
Operating and maintenance costs
O H Q M Q L
Why?
Negative environmental impact
O H O M * L
Why?
Positive environmental impact
O H O M O L
Why?
Over/under estimation of benefits (e.g.,
O H O M Q L
Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes O No
cost been prepared?
If yes, is it a range?
O Yes No
If yes, show range in Funding Worksheet
If no, show estimated amount in Funding
Worksheet
Can the cost of not implementing the project
O Yes O No
be estimated?
If yes, identify cost
47,500,000 (mid -point)
If yes, does it increase deferred maintenance
O Yes QQ No
for its infrastructure category?
If yes, estimate deferred cost and duration
A-104
https://rpvpay.com/project/print_project.php?id=195 5/24/2016
RPV CIPPS
Is the project currently spending grant or
other outside funds?
If yes, identify funding source
agreement title, date
Is the project eligible for outside funding?
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Are there funding constraints?
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Are there consequences of missing
milestones, deadlines, etc.?
If yes, describe situation and consequence
Page 11 of 14
OUTSIDE FUNDING
O Yes Q No
amount expenditure
deadline
Go to Funding Worksheet and enter amounts.
*Yes Q No
State of California Proposition 84
$500,000 (for design phase); potentially 50% of total estimated cost of $14,500,000
A pro -rata share based on number of participating agencies (maximum is 50%)
Our stormwater runoff drains directly to Machado Lake
Go to Funding Worksheet and enter amounts.
*Yes O No
Would be required to be spent only on this project
Same as above
*Yes Q No
Revocation of funding grant
Is funding tied to expenditure phases? * Yes O No
If yes, describe the expenditure phase Design and construction
A-105
https://rpvpay.com/project/print_project.php?id=195 5/24/2016
RPV CIPPS Page 13 of 14
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document Potentially initial study/mitigated negative declaration
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Qi No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document Potentially initial study/mitigated negative declaration
required
Does the project require NEPA review? O Yes Q No
If yes, describe NEPA document
Has a NEPA document previously been O Yes No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes QQ No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-106
https://rpvpay.com/project/print_project.php?id=195 5/24/2016
RPV CIPPS Page 14 of 14
PROJECT PROFILE FUNDING WORKSHEET
Stormwater
Construction management and inspection $1620000 $ $
Contingency (list amount % and basis) $ $ $
Totals $6710000 $0 $0
https://tpvpay.com/project/Print_project.php?id=195
A-107
5/24/2016
Annual impact on operating budget
Are operating impacts anticipated?
* Yes O No
If yes, identify impact on worksheet:
Name of impacted fund
General Fund
Revenue generated
None
Savings created
To be determined
Additional FTEs needed
None
Salaries/benefits for additional FTEs
N/A
Additional (decreased) operating expenses
To be determined
Debt service (P+I)
N/A
Fiscal year impacts anticipated to begin
2018/19
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate Aproved Budget
Current Estimate
Preliminary engineering
$460000 $
$
Environmental
$ $
$
Right -of -Way (legal plus acquisition)
$0 $
$
Capital equipment
$0 $
$
Construction (identify relevant infrastructure
$4630000 $
$
categories)
Stormwater
Construction management and inspection $1620000 $ $
Contingency (list amount % and basis) $ $ $
Totals $6710000 $0 $0
https://tpvpay.com/project/Print_project.php?id=195
A-107
5/24/2016
Page Intentionally Blank
li�
Conestoga Trail
• Connect to Sunnyside Ridge Trail
to Rolling Hills Estates
• $50,000 Requested for Design
• Source: CIP Reserves
A-109
RPV CIPPS
Project Name
Location
Project Description
Describe the community benefit or outcome
from implementing this project
Describe the outcome if the project is not
implemented
Date of original proposal
Name of department proposing this project
Name of departmental project manager
Name and contact information for resident
or community group proposing this project
Page 2 of 14
Project: Conestoga Trail
General Project Profile Information
Conestoga Trail
PVDE from Sunnyside Ridge Trail to city limits with Rolling Hills Estate
Create a roadside multi -use trail suitable for pedestrians and equestrians alongside PVDE. A
design is required to prepare a construction cost estimate.
Further completion of a trail gap segment between our communities
Users will continue to journey in an undeveloped and unsuitable roadside area
05-31-2016
Public Works
Dragoo
NA
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community General Plan, Trails Network Plan
plans to be referenced/utilized for design
List the standards to be referenced/utilized Trails Network Plan, Caltrans, National Park Service
for design
Identify infrastructure category O Public buildings O Park sites *i Trails O Stormwater system
Q Citywide sanitary sewer system Q Ab Cove sewer system
Q R/W, traffic control devices Q PB landslide
Name of department or community group Public Works
that will take responsibility for the project
after completion
Does that group have the resources to O Yes O No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
* Yes O No
https://tpvpay.com/project/Print_project.php?id=275
A-110
5/24/2016
RPV CIPPS
Is this project an opportunity to join with or
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
local equestrian groups
routine trail cleanup and maintenance
Page 3 of 14
A-111
https://rpvpay.com/project/print_project.php?id=275 5/24/2016
RPV CIPPS
Will the project enhance or improve the
overall safety of the city and the delivery of
services?
PUBLIC HEALTH AND SAFETY
* Yes No
Page 4 of 14
If yes, describe how provide a separate, suitable, all weather trail connection for pedestrians and
equestrians
If yes, quantify if feasible not feasible to directly quantify
Will the project protect the health and Yes Q No
welfare of residents and/or the environment?
If yes, describe sector and how a separate and properly designed and constructed facility will improve roadside
safety for trail users and motoring public
Is the project required to mitigate or Yes Q No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be Fail users journey in an undeveloped and unsuitable roadside area
addressed
Will the project eliminate an identified 0 Yes O No
safety condition?
If yes, describe how the condition is by the provision of a separate, suitable, all weather trail connection for pedestrians
eliminated and equestrians
If no, will the project mitigate it? O Yes O No
If yes, describe the mitigation
Will the project eliminate an identified O Yes No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it? O Yes QQ No
If yes, describe the mitigation
https://tpvpay.com/project/Print_project.php?id=275
A-112
5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
Does the project support maintenance and
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation?
If yes, cite law or regulation
Page 5 of 14
ESSENTIAL CITY SERVICES
Yes Q No
Q Yes * No
Q Yes *No
If the project is not done, would not O Yes Q No
performing the project violate a law or
regulation?
If yes, cite law or regulation
and identify
penalty
Is the project required by a court order, O Yes QQ No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the
proj ect?
If yes, describe alternative or option
If no, describe why
Describe how that department will operate
or maintain the project after completion
Will public engagement be employed to
develop or implement the project?
If yes, describe sector(s) of the public,
engagement level and influence
* Yes O No
users could continue to use the existing roadside for access
trail would be integrated into regular maintenance/preventative maintenance programs
*Yes O No
equestrian community
If yes, estimate cost and/or revenue benefit cost cannot be directly quantified; however implementing a project the users are involved in
of public engagement fashioning will create ownership
Enter this amount in the Funding Worksheet. A-1 13
https://rpvpay.com/project/print_project.php?id=275 5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the miect im rove efficienc ? O Yes Q No
P J p y
If yes, describe how
If yes, can efficiency be quantified? O Yes O No
If yes, describe quantity
Will the project improve economy? O Yes Q No
If yes, quantify amount
Will the project increase or improve O Yes QQ No
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
O Yes *No
O Yes *No
funding source
Go to Funding Worksheet and enter amounts
*Yes Q No
state
*Yes O No
If yes, go to Funding Worksheet and enter amounts.
Q Yes Q No
If yes, go to Funding Worksheet and enter amounts.
O Yes *No
percent completion
Page 8 of 14
If yes, go to Funding Worksheet and enter amounts. A-1 14
https://rpvpay.com/project/print_project.php?id=275 5/24/2016
RPV CIPPS
Will the project require additional part-time O Yes Qi No
personnel?
If yes, estimate number
Will the project generate revenue?
If yes, estimate annual amount
Can the City partner with other agencies,
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
If yes, is it anticipated that other agency,
group, jurisdiction would be able to assist
financially?
If yes, describe how
If yes, identify potential funding amount or
percentage of total expenditure
If no, would the other agency, group,
jurisdiction be able to support or contribute
in another fashion?
If yes, go to Funding Worksheet and enter amounts.
O Yes *No
If yes, go to Funding Worksheet and enter amounts.
*Yes Q No
local equestrian and hiking groups
Q Yes *No
O Yes Q No
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1926
identify or estimate original construction
date
Estimate remaining life of existing facility to
be replaced in years
Estimate residual value of existing facility
Provide anticipated life of new facility in
years
Can the life cycle cost be calculated?
If yes, show the annual maintenance cost
and %
0
0
20
O Yes *No
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + NA
Operating Costs) =
https://tpvpay.com/project/Print_project.php?id=275
Page 9 of 14
A-115
5/24/2016
RPV CIPPS Page 10 of 14
Describe the degree of uncertainty (high, medium, low) for:
Capital cost O H Q M Q L Why? design work is required to formulate a
construction estimate
Construction duration O H Q M QQ L Why?
Operating and maintenance costs O H O M Qi L Why?
Negative environmental impact O H Q M Di L Why?
OH OM OL
Positive environmental impact
Why?
Over/under estimation of benefits (e.g.,
O H
Q M Qi L Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes
Qi No
cost been prepared?
If yes, is it a range?
O Yes
Q No
If yes, show range in Funding Worksheet
If no, show
estimated amount in Funding Worksheet
Can the cost of not implementing the project
O Yes
QQ No
be estimated?
If yes, identify cost
If yes, does it increase deferred maintenance
O Yes
Q No
for its infrastructure category?
If yes, estimate deferred cost and duration
https://tpvpay.com/project/Print_project.php?id=275
A-116
5/24/2016
RPV CIPPS Page 11 of 14
OUTSIDE FUNDING
Is the project currently spending grant or O Yes No
other outside funds?
If yes, identify funding source amount expenditure
deadline
agreement title, date Go to Funding Worksheet and enter amounts.
Is the project eligible for outside funding? O Yes QQ No
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Go to Funding Worksheet and enter amounts.
Are there funding constraints? O Yes Q No
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Are there consequences of missing O Yes No
milestones, deadlines, etc.?
If yes, describe situation and consequence
Is funding tied to expenditure phases? O Yes QQ No
If yes, describe the expenditure phase
A-117
https://rpvpay.com/project/print_project.php?id=275 5/24/2016
RPV CIPPS Page 13 of 14
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document most likely a categorical exemption
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document most likely a categorical exemption
required
Does the project require NEPA review? O Yes Di No
If yes, describe NEPA document
Has a NEPA document previously been O Yes Q No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes Q No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-118
https://rpvpay.com/project/print_project.php?id=275 5/24/2016
RPV CIPPS Page 14 of 14
PROJECT PROFILE FUNDING WORKSHEET
Annual impact on operating budget
Are operating impacts anticipated? * Yes O No
If yes, identify impact on worksheet:
Name of impacted fund General Fund
Revenue generated 0
Savings created 0
Additional FTEs needed 0
Salaries/benefits for additional FTEs 0
Additional (decreased) operating expenses +6000
Debt service (P+I) 0
Fiscal year impacts anticipated to begin 2017/18
Trails
Construction management and inspection $to be determined $ $
Contingency (list amount % and basis) $to be determined $ $
Totals $50000 $0 $0
https://tpvpay.com/project/Print_project.php?id=275
A-119
5/24/2016
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate
Aproved Budget
Current Estimate
Preliminary engineering
$50000
$
$
Environmental
$to be determined
$
$
Right -of -Way (legal plus acquisition)
$to be determined
$
$
Capital equipment
$0
$
$
Construction (identify relevant infrastructure
$to be determined
$
$
categories)
Trails
Construction management and inspection $to be determined $ $
Contingency (list amount % and basis) $to be determined $ $
Totals $50000 $0 $0
https://tpvpay.com/project/Print_project.php?id=275
A-119
5/24/2016
Page Intentionally Blank
li�
A-120
Storm Drain Deficiency Improvement Program
• Replace Old Neighborhood -area
Pipes, Inlets Identified in Master
Plan of Drainage
• 10 -year Program
• $1,769,000 Requested for Year 1
• Source: SD User Fee
A-121
RPV CIPPS
Project: Storm Drain Deficiency Improvement Program
General Project Profile Information
Project Name Storm Drain Deficiency Improvement
Program
Location Citywide
Project Description
Describe the community benefit or outcome
from implementing this project
Describe the outcome if the project is not
implemented
Date of original proposal
Name of department proposing this project
Name of departmental project manager
Name and contact information for resident
or community group proposing this project
Page 2 of 14
Replace or rehabilitate existing old neighborhood -area culverts, pipes, drainage inlets, catch
basins, manholes identified in the 2015 Master Plan of Drainage as being structurally and/or
hydraulically deficient over a 10 -year period
Improved local drainage conditions
potential and risk of localized flooding due to inadequate drainage system
05-31-2016
Public Works
Winje
NA
Project Phases
Initiation Phase Time (Working Days) Can run concurrent?
Planning Phase Time (Working Days) Can run concurrent?
Execution Phase Time (Working Days) Can run concurrent?
Monitoring Phase Time (Working Days) Can run concurrent?
Closing Phase Time (Working Days) Can run concurrent?
List the municipal policies or community General Plan, 2015 Master Plan of Drainage
plans to be referenced/utilized for design
List the standards to be referenced/utilized LA County drainage standards, Caltrans, PW Green Book
for design
Identify infrastructure category O Public buildings Q Park sites Q Trails *i Stormwater system
Q Citywide sanitary sewer system Q Ab Cove sewer system
O R/W, traffic control devices 0 PB landslide
Name of department or community group Public Works
that will take responsibility for the project
after completion
Does that group have the resources to O Yes Q No
provide long-term maintenance and If yes, go to Funding Worksheet and enter amount(s)
replacement?
A-122
https://rpvpay.com/project/print_project.php?id=276 5/24/2016
RPV CIPPS Page 3 of 14
Is this project an opportunity to join with or O Yes Qi No
partner with another agency, community
organization or non-profit?
If yes, identify agency, community, non-
profit
If yes, describe the benefit of the
collaboration
A-123
https://rpvpay.com/project/print_project.php?id=276 5/24/2016
RPV CIPPS
PUBLIC HEALTH AND SAFETY
Page 4 of 14
Will the project enhance or improve the Yes
No
overall safety of the city and the delivery of
services?
If yes, describe how
reduce potential of localized flooding due to inadequate drainage systems
If yes, quantify if feasible
not directly calculable
Will the project protect the health and Yes
Q No
welfare of residents and/or the environment?
If yes, describe sector and how
flood prevention
Is the project required to mitigate or Yes
Q No
eliminate an existing safety condition or
hazard?
If yes, describe situation needed to be
potential of localized flooding due to inadequate drainage systems
addressed
Will the project eliminate an identified Yes
Q No
safety condition?
If yes, describe how the condition is
improved hydraulic performance will result in reduction of localized flooding
eliminated
If no, will the project mitigate it?
O Yes Q No
If yes, describe the
mitigation NA
Will the project eliminate an identified O Yes
Qi No
hazard?
If yes, describe how the hazard is eliminated
If no, will the project mitigate it?
O Yes O No
If yes, describe the
mitigation NA
https://tpvpay.com/project/Print_project.php?id=276
A-124
5/24/2016
RPV CIPPS
Does the project support maintenance and
development of existing facilities?
If yes, identify existing facilities
If yes, describe how
Page 5 of 14
ESSENTIAL CITY SERVICES
* Yes No
stormwater system
repaired and rehabilitated systems require less on-going maintenance or urgent repairs
Does the project support maintenance and 0 Yes QQ No
development of new facilities?
If yes, identify new facilities
If yes, describe how
Is the project required by law or regulation? 0 Yes No
If yes, cite law or regulation
If the project is not done, would not 0 Yes QQ No
performing the project violate a law or
regulation?
If yes, cite law or regulation
and identify
penalty
Is the project required by a court order, 0 Yes Qi No
settlement agreement or regulatory
directive?
If yes, cite date of order, agreement or
directive
If yes, cite terms and/or conditions
Are there alternatives or options to the
proj ect?
If yes, describe alternative or option
If no, describe why
Describe how that department will operate
or maintain the project after completion
Will public engagement be employed to
develop or implement the project?
If yes, describe sector(s) of the public,
engagement level and influence
If yes, estimate cost and/or revenue benefit
of public engagement
*Yes Q No
the status quo could be maintained wherein Public Works responds only to urgent needs to
repair systems
newly repaired/rehabilitated drainage systems would be integrated into regular
maintenance/preventative maintenance programs
*Yes Q No
local residents would be involved in identifying drainage problems
no significant cost
https://tpvpay.com/project/Print_project.php?id=276
A-125
5/24/2016
RPV CIPPS
ECONOMY AND EFFICIENCY
Will the project improve efficiency? * Yes 0 No
If yes, describe how reduction in expensive urgent responses
If yes, can efficiency be quantified? 0 Yes QQ No
If yes, describe quantity
Will the project improve economy?
If yes, quantify amount
Will the project increase or improve
productivity of municipal operations?
If yes, describe how
If yes, quantify amount of increase or
improvement
Will the project increase or improve
productivity of local businesses?
If yes, describe how
If yes, quantify amount of increase or
improvement
Is the project in construction?
If yes, identify budget
amount
Does the project require the payment of
prevailing wages?
If yes, cite state or federal or both
Will the project require on-going
maintenance after construction?
Will the project require an annual operating
expenditure?
Will the project require additional full-time
personnel?
If yes, estimate number
0 Yes *No
*Yes Q No
new systems require less maintenance than older systems
not directly calculable
0 Yes *No
0 Yes *No
funding source
Go to Funding Worksheet and enter amounts
*Yes Q No
state
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
*Yes Q No
If yes, go to Funding Worksheet and enter amounts.
0 Yes *No
If yes, go to Funding Worksheet and enter amounts.
https://tpvpay.com/project/Print_project.php?id=276
percent completion
Page 8 of 14
A-126
5/24/2016
RPV CIPPS Page 9 of 14
Will the project require additional part-time O Yes Oi No
personnel?
If yes, estimate number
If yes, go to Funding Worksheet and enter amounts.
Will the project generate revenue? O Yes Q No
If yes, estimate annual amount
If yes, go to Funding Worksheet and enter amounts.
Can the City partner with other agencies, O Yes OQ No
groups, jurisdictions to implement the
proj ect?
If yes, list agency, group, jurisdiction
If yes, is it anticipated that other agency, O Yes 0 No
group, jurisdiction would be able to assist
financially?
If yes, describe how
If yes, identify potential funding amount or
percentage of total expenditure
If no, would the other agency, group, O Yes 0 No
jurisdiction be able to support or contribute
in another fashion?
If yes, describe support or contribution
If the project is work to an existing facility, 07-01-1950
identify or estimate original construction
date
Estimate remaining life of existing facility to 0
be replaced in years
Estimate residual value of existing facility 0
Provide anticipated life of new facility in 50 minimum
years
Can the life cycle cost be calculated? O Yes 0 No
If yes, show the annual maintenance cost to be calculated
and %
If yes, go to Funding Worksheet and enter amounts.
For projects that create revenue, calculate the project benefit -cost ratio (BCR)
BCR = Benefits / (Construction Costs + NA
Operating Costs) _
A-127
https://rpvpay.com/project/print_project.php?id=276 5/24/2016
RPV CIPPS
Page 10 of 14
Describe the degree of uncertainty (high, medium, low) for:
Capital cost
OH
OM *L
Why?
Construction duration
D H
0 M L
Why?
Operating and maintenance costs
D H
0 M DQ L
Why?
Negative environmental impact
D H
0 M Q L
Why?
Positive environmental impact
D H
0 M Di L
Why?
Over/under estimation of benefits (e.g.,
D H
0 M Q L
Why?
capacity, demand for service, etc.)
Has an engineer's estimate of construction
O Yes
O No
cost been prepared?
If yes, is it a range?
0 Yes
No
If yes, show range in Funding Worksheet
If no, show
estimated amount in Funding
Worksheet
Can the cost of not implementing the project
0 Yes
Di No
be estimated?
If yes, identify cost
If yes, does it increase deferred maintenance
0 Yes
0 No
for its infrastructure category?
If yes, estimate deferred cost and duration
unknown at this time
A-128
https://rpvpay.com/project/print_project.php?id=276 5/24/2016
RPV CIPPS Page 11 of 14
OUTSIDE FUNDING
Is the project currently spending grant or O Yes No
other outside funds?
If yes, identify funding source amount expenditure
deadline
agreement title, date Go to Funding Worksheet and enter amounts.
Is the project eligible for outside funding? O Yes QQ No
If yes, cite outside funding source
If yes, cite anticipated outside funding
amount
If yes, cite the amount of local match
If yes, describe how it is eligible
Go to Funding Worksheet and enter amounts.
Are there funding constraints? O Yes Q No
If yes, identify terms and conditions
affecting acceptance of funds
If yes, identify terms and conditions
affecting design, construction, operations
and/or maintenance
Are there consequences of missing O Yes No
milestones, deadlines, etc.?
If yes, describe situation and consequence
Is funding tied to expenditure phases? O Yes QQ No
If yes, describe the expenditure phase
A-129
https://rpvpay.com/project/print_project.php?id=276 5/24/2016
RPV CIPPS Page 13 of 14
ENVIRONMENTAL STEWARDSHIP
Does the project require CEQA review? * Yes O No
If yes, describe CEQA document most likely a categorical exemption
Has a CEQA document previously been O Yes QQ No
prepared?
If yes, identify document type
If a categorical exemption, cite exemption
If yes, note when it was approved
If yes, are there mitigation measures O Yes Qi No
required to be implemented?
If yes, describe the measures
If no, estimate type of CEQA document most likely a categorical exemption
required
Does the project require NEPA review? O Yes Di No
If yes, describe NEPA document
Has a NEPA document previously been O Yes Q No
prepared?
If yes, identify document type
If a categorical exclusion, cite type
If yes, note when it was approved
If yes, are there mitigation measures O Yes QQ No
required to be implemented?
If yes, describe the measures
If no, estimate type of NEPA document
required
A-130
https://rpvpay.com/project/print_project.php?id=276 5/24/2016
RPV CIPPS Page 14 of 14
PROJECT PROFILE FUNDING WORKSHEET
Annual impact on operating budget
Are operating impacts anticipated? * Yes O No
If yes, identify impact on worksheet:
Name of impacted fund Stormwater Enterprise
Revenue generated 0
Savings created 0
Additional FTEs needed 0
Salaries/benefits for additional FTEs 0
Additional (decreased) operating expenses unknown at this time
Debt service (P+I) 0
Fiscal year impacts anticipated to begin 2017/18
https://tpvpay.com/project/Print_project.php?id=276
A-131
5/24/2016
Project Costs
Show original cost estimate range, approved budget and current estimate for each budgeted
phase
Original Estimate
Aproved Budget
Current Estimate
Preliminary engineering
$150000
$
$
Environmental
$0
$
$
Right -of -Way (legal plus acquisition)
$0
$
$
Capital equipment
$0
$
$
Construction (identify relevant infrastructure
$1319000
$
$
categories)
Stormwater system
Construction management and inspection
$150000
$
$
Contingency (list amount % and basis)
$150000
$
$
Totals
$1769000
$0
$0
https://tpvpay.com/project/Print_project.php?id=276
A-131
5/24/2016
Page Intentionally Blank
A-132
FY 15-16 Capital Improvement
Program Project Update
May 31, 2016
ACLAD Sewer System
May 31, 2016
Public Works Department
A
Public Works Department
FY 15/16 CIP Project Update
B-1
May 31, 2016
ACLAD Sewer System Rehabilitation Program
• Sewer System Needs:
• Replace low pressure pumps
• Retrofit lift stations
• Clean & line manholes
• $93,000 Budget
• Design Begins Summer 2016
• Construction Begins Winter 2016
• New Budget $200,000 for
Construction
May 31, 2016
Palos Verdes Drive South
Landslide
Public Works Department
FY 15/16 CIP Project Update
B-2
Landslide Dewatering Well Program
• Nine New Dewatering Wells
Installed In The Portuguese Bend
Landslide Area
• $810,000 Encumbered FY15-16
• $450,000 Budgeted FY16-17
• Construction To Start May 2016
• Anticipated Construction
Completion October 2016
May 31, 2016
May 31, 2016
PVDS Realignment — East End
• Eliminate Sharp Curves
• $458,600 Budget
• Currently In Design, In
Environmental Review
• 90% Completed
• $40,000 Encumbered FY15-16
• Construction Begins Spring 2017
• Carryover of $418,600 for
Construction
May 31, 2016
FY 15/16 CIP Project Update
B-3
Portuguese Bend Landslide Area Resurfacing
Program
• Annual Maintenance Program To
Maintain The Landslide Area
• $520,000 Budgeted FY16-17
• New Maintenance Contract
Anticipated Summer 2016
May 31, 2016
Park Sites
P
7" k
W a , 1014
r
May 31, 2016
Public Works Department
FY 15/16 CIP Project Update
B-4
Lower Hesse Park Improvements
• Improve Underdeveloped Park
Land
• $487,500 Budget
• RFP for design Being Circulated
• $60,000 Encumbered this year
• Carryover of $427,500 for
Design and Construction
• $500,000 Budgeted FY16-17
May 31, 2016
Public Buildings
May 31, 2016
i
Public Works Department
FY 15/16 CIP Project Update
B-5
John C McTaggart Memorial Hall
Improvements
• Cosmetic And
IT Improvements
• $91,200 Budget
• $50,000 Encumbered FY15-16
• Construction Completed
May 31, 2016
May 31, 2016
Citywide ADA Transition Plan Implementation
Program
• Eliminate Potential Safety Hazard
and Severe Barriers to Access
• Hesse Park
• Ladera Linda Community Center
(Playgrounds Only)
• Point Vicente Interpretive Center
• Ryan Park
• $810,000 Budget
• $40,000 Encumbered FY15-16
• In Design
• Carryover of $770,137 for
Construction
May 31, 2016
FY 15/16 CIP Project Update
B-6
Right of Way and
Traffic Control Devices
May 31, 2016
Public Works Department
Hawthorne Blvd Corridor Beautification
(Median Trees)
• 71 Trees To Install In
Hawthorne Median
• $150,000 Budget
• $150,000 Encumbered FY15-16
• Construction Begins April 2016
• Anticipated Construction
Completion July 2016
May 31, 2016
ie-TypeA .-Type6 IS•TypeC
FY 15/16 CIP Project Update
B-7
May 31, 2016
Hawthorne Blvd Traffic Signal Synchronization
• Interconnect 7 Traffic Signals
Along Hawthorne Blvd Using
Fiber Optic Cabling & Install 8
Pedestrian Countdown Signals
• $683,600 Budget
• 10% Match Requirement
• $683,600 Encumbered FY15-16
• Currently In Construction
• Complete Construction Fall
2016
May 31, 2016
PVDE Guardrail Replacement
• Replace Existing Guardrail with
New Guardrail and Signs on PVDE
from PVDS to the north City limit
at Conestoga
• $268,700 Budget
• 10% Match Requirement
• $268,700 Encumbered FY15-16
• Ready to Advertise
• Construction Begins Winter 2016
May 31, 2016
FY 15/16 CIP Project Update
B-$
May 31, 2016
PVDW Median Improvements at Palos Verdes
Estates
• Improve Pedestrian Walking
Trail
• Install Drought -tolerant mi AL
Landscaping with Drip Irrigation
$473,600 Budget
• $473,600 Encumbered FY15-16
• Finalizing Advertisement
Package
A�
May 31, 2016
Hawthorne Blvd Pedestrian Linkage Improvements
• Install Sidewalk from Crest Rd
to PVDW with ADA -compliant
Access Ramps and Bus Shelter
Improvements
• $1,240,300 Budget
• 20% Match Requirement
• $150,000 Encumbered FY15-16
• Ready to Advertise
• Construction Begins Summer
2016
May 31, 2016
FY 15/16 CIP Project Update
B-9
PVDS Bike Lane Improvements
• Install 6 -ft Bike Lanes on Each Side
of PVDS by Modifying Medians
• $779,900 Budget
• 20% Match Requirement
• Currently In Design
• 65% completed
• $25,000 Encumbered FY15-16
• Carryover of $754,900 for
Construction
• Construction Begins Summer 2016
May 31, 2016
May 31, 2016
PVDE at Bronco Intersection Improvements
• Install Safety Improvements
• Median Barrier
• Advanced High -visibility Warning Devices
• New Guardrails, Equestrian Crossing, Trail
Improvements
• $500,300 Budget
• 10% Match Requirement
• Currently In Design
• $25,000 Encumbered FY15-16
• Carryover of $475,300 for
Construction
• Construction Begins Winter 2016
May 31,21,1'
FY 15/16 CIP Project Update
B-10
Miraleste Arterial Street Rehabilitation
• Roadway Resurfacing, Sidewalk
and Curb & Gutter Repairs,
Refreshed Striping, Updated New
Reflective Signs
• $2,534,500 Budget
• $100,000 Encumbered FY15-16
• RFP for design being Circulated
• Carryover of $2,434,500 for
Construction
• Construction start in January
2017
May 31, 2016
Storm Water System
May 31, 2016
Public Works Department
FY 15/16 CIP Project Update
B-11
Roan Drainage System
• Installation Of New Storm Drain
Structures
• $231,000 Budget
• $231,000 Encumbered FY15-16
• Construction Completed
December 2015
May 31, 2016
May 31, 2016
Storm Drain Lining Program
• Install Corrugated Metal Pipe
Liners Citywide
• $1,140,300 Budget
• $1,140,300 Encumbered FY15-16
• In construction
• $350,000 Budgeted FY16-17
May 31, 2016
FY 15/16 CIP Project Update
B-12
Storm Drain Point Repair Program
• Repair/Replace Severely Damaged
Identified Storm Drain Lines
• $1,050,000 Budget
• $1,020,000 Encumbered FY15-16
• In Design
• Carryover of $30,000 for
construction
May 31, 2016
May 31, 2016
is,
Altamira Canyon Drainage Project Study
ReportI1491tn¢ HOTS Yrr r
• Study To Acquire Runoff
Management Alternatives
• $500,000 Budget
• $440,000 Encumbered FY15-16
• Study Underway
May 31, 2016
Aho lrraeF
AM.- Cavo-
t andsunn
Atlivo
Pariuywse B�
l.u,rscNrtr
PGrlugL
Canyor
cxf—dfke Canyari
LarMslidr,
FY 15/16 CIP Project Update
B-13
Drainage and Roadway Improvements at
Sacred Cove
• Establish Positive Drainage
Condition
• $450,000 Budget
• $50,000 Encumbered FY15-16
• Carryover of $400,000 for
Construction
May 31, 2016
May 31, 2016
Marguerite/ Lower Barkentine/ Seacove
Drainage Improvement W.l
• Improve Drainage at the Three
Separate Locations
• $760,300 Budgets ,
• $60,000 Encumbered FY15-16
• In Design'
• Carryover of $700,300 for + ;
Construction
May 31, 2016
FY 15/16 CIP Project Update
B-14
Trails
Sunnyside Ridge Trail
• Construct a Neighborhood Trail
that connects Sunnyside Ridge
Road to the Conestoga Trail
• $396,400 Budget
• $396,400 Encumbered FY15-16
• In Construction
May 31, 2016
May 31, 2016
Public Works Department
FY 15/16 CIP Project Update
B-15
Accessibility Improvements at Del Cerro Park
and Burma Road
• ADA Improvements Including
New Sidewalk and Curb Ramps
• $164,400 Budget
• $13,800 Encumbered FY15-16
• Carryover of $150,600 for
Construction
• Project Design Anticipated
Completion May 2016
• Construction To Commence
Summer 2016
May 31, 2016
May 31, 2016
For More Project Information
• Visit Our Webpage
http://www.rpvca.gov/292/Public-Works
• Email Us LIR
publicworks@rpvca.gov Rnch.Pal. Verde.CAyHa11
Rw. ho Pal" Verdes, CA 90715
• Find Us
City of Rancho Palos Verdes, CA mp=
Report Graffiti
• Telephone Us With Our App!
310 544-5252
FY 15/16 CIP Project Update
B-16
Project ID#
Project
Status as of Monday May 23, 2016
Infrastructure Improvements Admin 40
-
Engineering Review/Labor Compliance
Ongoing activity
Ongoing activity
FY 16-17 Capital Budget
Grant Administration
Infrastructure Management Plan
Total Infrastructure Improvements Administration
Abalone Cove Landslide Abatement District (ACLAD) Sewer System
ACLAD Sewer System Capital Needs Study
ACLAD Sewer System Rehabilitation Program
Total ACLAD
Palos Verdes Drive South (PVDS) Landslide
Landslide Dewatering Well Program
IA2014-01
In process with IMAC
AC2015-01
40,000
Study underway due June
AC2016-01
Design pending outcome of needs study
LS2015-01
164,400
In construction
LS2014-02
PVDS Realignment - East End
In environmental review
LS2015-02
Portuguese Bend Landslide Area Strategic Plan
In process with IMAC
LS20XX-XX
Portuguese Bend Landslide Area Resurfacing Program
Ongoing activity; resurfacing this June 2016
50,000
Total PVDS Landslide
410,236
8,595,527
231,095
PS2015-01
Recognition Wall
In design
PS2014-01
Lower Hesse Park Improvements
RFP for design being circulated
PS2015-02
Eastview Park Dog Park
RFP for design being prepared
PS2016-01
Abalone Cove Beach Access Rd and Parking Rehabilitation
Planned
PS2016-02
Coastal Bluff Fence Replacement Program (NEW)
NEW
PS2016-03
Ladera Linda Community Center Parking Lot (NEW)
NEW Preliminary design to establish scope
PS2016-04
Upper Point Vicente/Hesse Park Marquee Signage (NEW)
NEW
PS2016-05
Eastview Park Site and Recreation Improvements (NEW)
NEW
Total Park Sites
Public Buildings
John C McTaggart Memorial Hall Improvements
(Funds to be
COMPLETED
PB2010-01
Public Facility Connectivity (Hesse/ Park/Ryan Park Fiber Optic Cabling)
In construction
PB2014-01
RPV TV Building Improvements
Rejected bids; Re -advertising
PB20XX-XX
Citywide ADA Transition Plan Implementation Program
In design
PB2015-01
Corporation Yard Utilization Study
Study underway due June
PB2014-02
Ladera Linda Community Center Master Plan
RFP for design being circulated to consultants
PB2014-03
PVIC Exhibit Replacement/Renovation
Seeking grant funding to increase project scope
PB2016-01
Civic Center Master Plan (NEW)
NEW
(220-3020)
(CDBG) (310- (330-3033)
Total Public Buildings
Right of Way and Traffic Control Devices
Residential Street Rehabilitation Program Cycle 1 Yr 5 (Prior Years)
Article 3 (340•
-
COMPLETED (Fund 310)
320,000
ADA Access Improv at PVDW at Hawthorne Blvd
COMPLETED (Fund 310)
ADA Access Improv at Mira Catalina
COMPLETED (Fund 310)
RW2010-01
Citywide Traffic Signal Battery Back -Up
In construction
RW2015-01
Hawthorne Blvd Corridor Beautification (Median Trees)
In construction
RW2010-01
Hawthorne Blvd Traffic Signal Synchronization
In construction (10% match requirement)
RW2014-01
Residential Street Rehabilitation Program Cycle 1 Yr 6 (FY 14-15)
Awarded PCC & digouts
RW20XX-XX
Sidewalk Repair and Replacement Program
Awarded; Ongoing activity
RW2014-02
PVDE Guardrail Replacement
Ready to advertise (10% match requirement)
RW2014-03
PVDW Median Improvements at Palos Verdes Estates
Ready to advertise
RW2014-04
Hawthorne Blvd Pedestrian Linkage Improvements
Ready to advertise (20% match requirement)
RW2014-05
PVDS Bike Lane Improvements
In design (20% match requirement)
RW2014-06
PVDE at Bronco Intersection Improvements
In design
RW20XX-XX
Pavement Management Program Biennial Update
Consultant selection underway
RW2010-02
Miraleste Arterial Street Rehabilitation
RFP for design being circulated to consultants
RW2016-01
Residential Street Rehabilitation Program Cycle 1 Yr 7 (Final Yr)
FY 16-17 design & construction
RW2016-02
Residential Street Rehabilitation Program Cycle 2
FY 16-17 design only
RW2017-01
Arterial Rehabilitation - Crenshaw Blvd
Planned
RW2017-02
Western Av Traffic Congestion Improvements
SBCOG Highway Program
RW2019-01
Arterial Rehabilitation - Indian Peak Rd
Planned
RW2016-03
ADA Improvements at City Hall Bus Stop (NEW)
NEW
RW20XX-XX
Arterial Walls and Fences Replacement Program (NEW)
NEW Year 1 = Hawthorne CLF Removal
Total RIW and TCD
Sanitary Sewer System
None
Storm Water System - Stormwater Quality
SW2016-01 Torrance Airport SWQ Project (NEW)
-
No capacity - expansion projects identified
NEW
T2014-01
Sunnyside Ridge Trail
In construction
T2016-01
Accessibility Improvements at Del Cerro Park and Burma Rd
In design
T2106-02
Conestoga Trail Connection (NEW)
Total Trails
TOTAL GOVERNMENT FUNDS
Storm Water System - Repairs & Rehabilition of Existing System
Roan Drainage System
Storm Drain Lining Program
NEW
COMPLETED
60,000
90,000
SW2014-01
In construction
SW2014-02
Storm Drain Point Repair Program
In design
SW2015-01
Altamira Canyon Drainage Project Study Report
Study underway; due December 2016
SW2015-02
Drainage and Roadway Improvements at Sacred Cove
In design
SW2015-03
Marguerite/Lower Barkentine/Seacove Drainage Improvements
In design
SW2016-01
Altamira Canyon Cyn Culvert Modifications at PVDS
NEW
SW20XX-XX Storm Drain Deficiency Improvement Program (Master Plan of Drainage)(NEW) NEW
TOTAL STORMWATER ENTERPRISE FUNDS
ALL FUNDS
Proposed FY 2016-17 Capital Budget and 5 -yr Capital Improvement Program (CIP)
250,000
192,400
- - 500,000 500,000
1,020,300 9,427,290 10,522,590 5,671,069 4,781,921 - 5,442,400 4,917,500 250,000
FY 15-16
-
FY 16-17 Capital Budget
460,0001 460,000
FY 16-17 Capital Budget Revenue Sources
396,436
40,000
40,000
5 -yr Capital Improvement Program (CIP)
-
20,014,810 11,566,928 7,649,245 624,795 10,756,400 6,987,500 250,000 550,000
164,400
164,400
487,575
Continuing
60,000
427,575
200,000
-
Community
50,000
50,000
50,000
-
410,236
8,595,527
231,095
150,600
6,548,905
-
50,000
624,795 8,562,400 6,987,500 250,000
340,836
-
Continuing
1,140,306
Encumbered
Appro.
Rebudgeted
FY 15-16 YE Estimated Revenue
CIP
HUTA (Gas Beautificat-
Dev Block Restricted
Environ
Quimby
Transp Dev
Storm Drain
-
100,000
FY 15-16 Transfer -in 10,542,545 1,035,791 - -
Estimated Ending Balance June 30, 2016 24,215,007 826,904 1,272 309,590 416,567 1,637,843
-
25,000
Original FY 15-
Appropriation
Total FY 15-16
by June 30,
(Funds to be
from FY 15-
New FY 16-
Reserves
Proposition Proposition
Tax) (202- ion Fund
Measure R
ACLAD (225) Grant Donations
Excise Tax
Fees (334-
Act (TDA)
User Fee
FY 16-17
FY 17-18
FY 18-19
FY 19-20
FY 20-21
16 Budget
from Prior CIP
Budget
2016
Carried -over
16
17 Funding
(330-3030)
C (215-3015) A (216-3016)
3003) (212-3012)
(220-3020)
(CDBG) (310- (330-3033)
(EET) (338-
3034)
Article 3 (340•
(SDUF) (501-
320,000
320,000
94,795
94,795
-
into FY 16-
94,795 55,000
55,000
200,000
610,137
3099)
3038)
3040)
3052)
30,000
250,000
30,000
30,000
-
250,000
17)
93,722
93,722
-
-
525,000
455,000
455,000
-
550,000
455,000
200,000
200,000
-
250,000
250,000
685,000
1,212,896
1,897,896
533,722
770,137
549,795 305,000
305,000
790,957
790,957
790,957
-
174,900
174,900
174,900
-
64,700
64,700
64,700
-
90,000
60,000
90,000
60,000
60,000
150,000
175,000
175,000
150,000
-
150,000
150,000
175,000
60,000
60,000
60,000
60,000
72,500
72,500
72,500
2,229,400
-
70,000
70,000
250,000
325,000
325,000
-
250,000
70,000
70,000
70,000
70,000
70,000
25,000
455,000
25,000
25,000
473,690
473,690
25,000
25,000
1,240,351
1,240,351
150,000
25,000
50,000
779,975
157,500
-
157,500
157,500
-
-
270,000
270,000
-
- - -
- - - -
- -
-
-
270,000
130,000
180,000
130,000
130,000
25,000
2,534,500
25,000
25,000
2,434,500
-
4,100,000
4,017,500
-
-
50,000
43,000
93,000
93,000
200,000
200,000
200,000
450,000
450,000
450,000
450,000
75,000
43,000
118,000
118,000
-
200,000
200,000
- - -
- - - -
- -
-
-
200,000
450,000
450,000
450,000
450,000
520,000
445,000
965,000
965,000
-
450,000
450,000
450,000
180,000
180,000
180,000
180,000
-
458,672
458,672
40,000
418,672
250,000
250,000
418,672
250,000
250,000
75,000
75,000
-
-
75,000
75,000
75,000
550,000
550,000
550,000
550,000
550,000
1,090,351
550,000
550,000
600,000
600,000
650,000
1,145,000
903,672
2,048,672
1,555,000
418,672
75,000
1,000,000
525,000
-
- 550,000 -
- - - -
- -
-
-
1,493,672
730,000
780,000
780,000
830,000
250,000
192,400
- - 500,000 500,000
1,020,300 9,427,290 10,522,590 5,671,069 4,781,921 - 5,442,400 4,917,500 250,000
Proposed FY 16-17 Capital Budget
-
75,000
460,0001 460,000
396,436
40,000
40,000
40,000
-
20,014,810 11,566,928 7,649,245 624,795 10,756,400 6,987,500 250,000 550,000
164,400
164,400
487,575
487,575
60,000
427,575
200,000
-
Adjusted encumbrances, expenditures, revenues, transfer -ins
50,000
50,000
50,000
-
410,236
8,595,527
231,095
150,600
6,548,905
-
50,000
624,795 8,562,400 6,987,500 250,000
340,836
-
1,140,306
1,140,306
50,000
516,100
350,000
FY 15-16 YE Estimated Revenue
900,000
150,000
1,050,000
200,000
200,000
484,620
-
100,000
FY 15-16 Transfer -in 10,542,545 1,035,791 - -
Estimated Ending Balance June 30, 2016 24,215,007 826,904 1,272 309,590 416,567 1,637,843
-
25,000
440,000
-
50,000
110,000
110,000
50,000
400,000
-
-
250,000
760,340
760,340
577,575
577,575
150,000
427,575
835,000
310,000
200,000
94,242
94,242
50,000
-
25,000
320,000
320,000
320,000
94,795
94,795
-
-
94,795 55,000
55,000
200,000
610,137
810,137
40,000
770,137
30,000
250,000
30,000
30,000
-
250,000
93,722
93,722
93,722
-
-
525,000
455,000
455,000
-
550,000
455,000
200,000
200,000
-
250,000
250,000
685,000
1,212,896
1,897,896
533,722
770,137
549,795 305,000
305,000
790,957
790,957
790,957
-
174,900
174,900
174,900
-
64,700
64,700
64,700
-
90,000
90,000
90,000
-
150,000
150,000
150,000
-
150,000
150,000
683,628
683,628
683,628
-
2,229,400
2,229,400
2,229,400
-
250,000
325,000
325,000
-
250,000
268,794
268,794
268,794
-
455,000
473,690
473,690
473,690
-
1,240,351
1,240,351
150,000
1,090,351
779,975
779,975
25,000
754,975
-
500,300
26,795
527,095
25,000
502,095
-
1,530,137
120,000
69,600
189,600
120,000
-
2,534,500
2,534,500
100,000
2,434,500
-
4,100,000
4,017,500
-
400,000
400,000
250,000
192,400
- - 500,000 500,000
1,020,300 9,427,290 10,522,590 5,671,069 4,781,921 - 5,442,400 4,917,500 250,000
Version Notes Date Estimated Fund Balance Ending June 30, 2017 16,560,507 34,004 1,292 513,984 559,512 2,127,468
W:\MichaelT\CIP\Draft 2016\Proposed FY16-17 Budget 5 -yr CIP Ver 2.xlsx
Proposed FY 16-17 Capital Budget
-
75,000
460,0001 460,000
396,436
396,436
396,436
-
4,323,636 15,616,174
20,014,810 11,566,928 7,649,245 624,795 10,756,400 6,987,500 250,000 550,000
164,400
164,400
13,800
150,600
Tuesday, May 24, 2016
(345,000)
(1,385,500)
-
Adjusted encumbrances, expenditures, revenues, transfer -ins
-
50,000
- 560,836
3,082,800 12,725,269
231,095
560,836
15,883,069
231,095
410,236
8,595,527
231,095
150,600
6,548,905
-
50,000
624,795 8,562,400 6,987,500 250,000
340,836
799,470
1,140,306
1,140,306
Estimated FY 16-17 Revenue
516,100
350,000
FY 15-16 YE Estimated Revenue
900,000
150,000
1,050,000
1,050,000
772,394
484,620
-
100,000
FY 15-16 Transfer -in 10,542,545 1,035,791 - -
Estimated Ending Balance June 30, 2016 24,215,007 826,904 1,272 309,590 416,567 1,637,843
500,000
500,000
440,000
-
50,000
450,000
450,000
50,000
400,000
760,340
760,340
60,000
700,340
200,000
200,000
Version Notes Date Estimated Fund Balance Ending June 30, 2017 16,560,507 34,004 1,292 513,984 559,512 2,127,468
W:\MichaelT\CIP\Draft 2016\Proposed FY16-17 Budget 5 -yr CIP Ver 2.xlsx
Proposed FY 16-17 Capital Budget
(6,912,500)
75,000
(550,000)
1,240,836 2,890,905
- - 1,769,000
4,131,741 2,971,401 1,100,340 2,194,000
4,323,636 15,616,174
20,014,810 11,566,928 7,649,245 624,795 10,756,400 6,987,500 250,000 550,000
2
SUMMARY OF REVENUE FUND BALANCES
Beginning Balance July 1, 2015 20,447,429 1,312,716 571,865 192,990 236,073 1,153,223
FY 15-16 Encumbrances & Expenditures (6,760,437) (965,000) (473,690) -
Tuesday, May 24, 2016
(345,000)
(1,385,500)
1
Adjusted encumbrances, expenditures, revenues, transfer -ins
Monday, April 18, 2016
Fy 15-16 Operating Expenses
(567,100)
(1,507,000)
(97,791)
(526,000)
(591,900)
-
Estimated FY 16-17 Revenue
516,100
842,600
FY 15-16 YE Estimated Revenue
552,570
950,397
888
642,600
772,394
484,620
-
100,000
FY 15-16 Transfer -in 10,542,545 1,035,791 - -
Estimated Ending Balance June 30, 2016 24,215,007 826,904 1,272 309,590 416,567 1,637,843
-
-
Version Notes Date Estimated Fund Balance Ending June 30, 2017 16,560,507 34,004 1,292 513,984 559,512 2,127,468
W:\MichaelT\CIP\Draft 2016\Proposed FY16-17 Budget 5 -yr CIP Ver 2.xlsx
Proposed FY 16-17 Capital Budget
(6,912,500)
(250,000)
(550,000)
FY15-16 Re -budget
(169,795)
2
Issued with May 31, 2016 Agenda. Added operating expenses
Tuesday, May 24, 2016
(345,000)
(1,385,500)
1
Adjusted encumbrances, expenditures, revenues, transfer -ins
Monday, April 18, 2016
0
Issued with April 19, 2016 Agenda Packet
Thursday, April 14, 2016
-
Version Notes Date Estimated Fund Balance Ending June 30, 2017 16,560,507 34,004 1,292 513,984 559,512 2,127,468
W:\MichaelT\CIP\Draft 2016\Proposed FY16-17 Budget 5 -yr CIP Ver 2.xlsx
Proposed FY 16-17 Capital Budget
(6,912,500)
(250,000)
(550,000)
FY15-16 Re -budget
(169,795)
Proposed FY 16-17 Operating Expenses
(345,000)
(1,385,500)
100,000
(18,000)
(638,300)
FY15-16 Continuing Appropriation
(6,398,305)
-
-
-
-
Estimated FY 16-17 Revenue
516,100
842,600
20
772,394
781,245
489,625
Estimated FY 16-17 Transfer -in
5,655,000
-
100,000
-
-
-
Version Notes Date Estimated Fund Balance Ending June 30, 2017 16,560,507 34,004 1,292 513,984 559,512 2,127,468
W:\MichaelT\CIP\Draft 2016\Proposed FY16-17 Budget 5 -yr CIP Ver 2.xlsx
1 Printed: 5/24/20163:30 PM
-
100,000
200,000
627,575
-
100,000
50,000
50,000
150,000
200,000
200,000
200,000
200,000
200,000
25,000
25,000
110,000
250,000
250,000
-
-
-
525,000
-
1,262,575
550,000
200,000
200,000
200,000
55,000
770,137
150,000
150,000
150,000
150,000
455,000
455,000
250,000
-
-
455,000
-
-
-
-
1,530,137
150,000
150,000
150,000
150,000
250,000
250,000
250,000
250,000
250,000
1,090,351
754,975
502,095
-
120,000
120,000
2,434,500
82,500
4,100,000
400,000
3,300,000
3,300,000
3,300,000
3,300,000
-200,000
800,000
2,000,000
-
200,000
3,000,000
-
200,000
1,600,000
192,400
192,400
500,000
100,000
100,000
100,000
100,000
-
192,400
-
-
-
82,500
-
10,224,321
4,050,000
7,570,000
5,850,000
5,370,000
460,0004,630,000
1,620,000
150,600
50,000
50,000
200,000
192,;400
455,000
50,000
575,000
82,500
200,600
200,000
-
-
-
15,641,305 10,890,000 10,950,000 7,560,000
7,130,000
350,000
350,000
350,000
350,000
350,000
350,000
-
500,000
400,000
700,340
650,000
75,000
500,000
1,769,000
2,194,000
1,769,000
3,219,340
2,229,000
4,229,000
1,729,000
2,079,000
2,629,000
2,979,000
1,798,000
2,148,000
192,400
455,000
575,000
82,500
2,194,000
1 18,860,645
15,119,000
13,029,000
10,539,000
9,278,000
54,552
(93,000)
(11,624)
(253,400)
870,740
-
1,337,510
(50,000)
336,998
-
97
5,333,829
(2,971,401)
(85,700)
-
(35,000)
-
(116,400)
269,938
15,058
876,740
200,600
1,238,600
136,684
12,536
-
11,624
16,538
(192,400)
850,798
-
-
2,164,250
(575,000)
537,598
-
97
(82,500)
3,484,628
(2,194,000)
-
(455,000)
249,400)
(5,000)
(149,800)
-
(150,600)
-
(1,100,340)
55,964
342,400
2,800
8,000
23,172
82,500
208,000
27,100
-
15,938
-
393,598
-
1,597,250
-
560,770
-
97
-
40,488
1 Printed: 5/24/20163:30 PM