Loading...
CC SR 20160517 I - Sunnyside Ridge Trail Project Budget Increase with KOARANCHO PALOS VERDES CITY COUNCIL AGENDA REPORT AGENDA DESCRIPTION: MEETING DATE: 05/17/2016 AGENDA HEADING: Consent Calendar Consideration and possible action to authorize a project budget increase to the Sunnyside Ridge Trail Segment Project that is cost neutral to the City budget. RECOMMENDED COUNCIL ACTION: (1) Authorize the Director of Public Works to execute a change order to the design contract with KOA in the amount of $20,000; and, (2) Authorize an increase to the project budget in the amount of $35,000 to accommodate additional costs associated with the revised design. FISCAL IMPACT: Amount Budgeted: $465,000 Encumbered to Date: $439,914 Additional Project Authorization $ 35,000 Additional Appropriation: $ 0 Account Number(s): 330-3033-461-73-00 ORIGINATED BY: Andy Winje, PE, Senior Engineer v, REVIEWED BY: Michael Throne, PE, Director of Public Works APPROVED BY: Doug Willmore, City Manager ATTACHED SUPPORTING DOCUMENTS: A. Alternate Design Concept (page A-1) B. Change Order to KOA contract (page B-1) BACKGROUND AND DISCUSSION: A project budget for the Sunnyside Ridge Trail Segment Project was authorized and funds appropriated for design and construction by City Council in the amount of $465,000. On November 18, 2014, City Council awarded a professional services contract for engineering design and construction management to KOA in the amount of $140,450. On November 4, 2015, the City Council awarded a construction contract in the amount of $290,864 to Concept Consultant, Inc. and authorized a construction contingency of $30,000. On December 15, 2015, the City Council directed Staff to re -design elements of the project to ensure that no part of the enduring project was outside the 10 -foot trail easement. In the exploration of design alternatives, the Director of Public Works also authorized additional geotechnical engineering work using a previously awarded on-call contract. Table 1 summarizes these authorizations. 1 Table 1 Project Budget $465,000 Encumbrances to Date Design and Construction Management KOA Nov. 2014 $140,450 Construction Concept Consultants Nov. 2015 $290,864 Additional Geotechnical Work (Hamilton — on call) $ 6,800 Construction Contingency' $ 30,000 Unencumbered Budget $ 3,114 1 The construction contingency is not actually encumbered, but is shown this way to demonstrate it is being held in reserve for unexpected construction needs, to avoid delays. Staff directed Concept Consultant, Inc. to develop a construction change order for negotiation to accommodate the change. KOA is the City's agent in these negotiations. Concept Consultant, Inc.'s most economical change order proposal was $96,560, due to significantly increased construction complexity of two retaining walls, which would significantly increase the awarded cost. There were also constructability concerns regarding the change proposed by the contractor. Therefore, Staff and the design engineer are pursuing a more straightforward design concept (Attachment A) including a concrete walkway that requires additional structural engineering, but is easier and cheaper to build. This concept keeps the project within the easement as Staff was previously directed to do by the Council. Staff expects this design change will result in a cost neutral or perhaps negative change order (i.e., savings) from the contractor, but the amount is uncertain without a complete design and the contractor's input. Staff recommends an increase to the project budget of $35,000 to accommodate these design changes (work by KOA, $20,000) and needed geotechnical engineering and inspection during design (Hamilton, $6,800) and construction (Hamilton, estimated at $8,200). Although the City Council previously authorized a contingency for the project that could be used for this effort, construction contingency is typically reserved for unexpected construction needs during construction, which must be addressed quickly to avoid delay claims by the contractor. There is available funding in the budget program for improvements to parks, trails and open space (Account 330-3033-461-73-00) to pay for this increase, due to savings from other budgeted projects. So, while the project budget may increase, the overall impact to the City budget is nil. It is likely that the total expenditure for the project will approximate the original budget if savings on the change order are as expected and the construction contingency is not needed. ALTERNATIVES: In addition to the Staff recommendation, the following alternative actions may be taken by the City Council: 2 1. Authorize the Director of Public Works to execute a $20,000 change order to KOA without increasing the project budget, in which case funds for the additional design work would be charged against the contingency. 2. Take other action as deemed appropriate by the City Council. 9 SUNNYSIDE RIDGE TRAIL SEGMENT - REVISED SCOPE ELEVATED WALKWAY - CONCEPT ORIGINAL BID: ENGINEER'S OPINION OF COST SAVINGS $290,864 BID ITEMS TO BE REMOVED OR ADJUSTED: WOOD EROSION CONTROL STRUCTURE $2,500.00 REMOVED RETAINING WALL, (TYPE 1) $36,520.00 REMOVED RETAINING WALL (TYPE 2) $43,200.00 REMOVED TOTAL $82,220.00 ESTIMATED COST OF ELEVATED WALKWAY OPTION: EXCAVATION FOR CAISSONS AND GRADE BEAMS $1,800.00 CAISSONS, DECK SOFFIT AND SIDES $14,400.00 REINFORCED CONCRETE DECK $8,000.00 ADDITIONAL WORK CONTINGENCY $5,750.00 TOTAL $29,950.00 ESTIMATED PROJECTED COST SAVINGS: $52,270.00 A-1 Project: i_;I I Y of ii�I:ariCl l0 RAI p5 VERDE 30940 Hawthorne Blvd. Sunnyside Ridge Trail Segment Design Project Change Order # Attention: Alan Braatvedt KCIA Corporation 1411 W 190th Street Rancho Palos Verdes, CA 90275 Gardena, CA 90248 Explanantion for Change Order Increase in contract value to provide additional scope of work including construction management, design and construction document preparation services for design changes to the Sunnyside Ridge Trail Segment Project. Itemized Description Time and materials - Construction Management and Design Services Increase in Scope Quantity Unit Price Amount 1 120,000.00 20,000.00 Total 20, 000.00 Original Contract Value 140,450.00 Total Value of all Previous Change Orders Total Revised Contract Sum Prior to this Change Order Value of this Change Order New Contract Sum Change in Contract Days 0.00 140,450.00 20,000.00 160,450.00 Revised Contract Completion Date 11/17/2016 Accepted: KOA Corporation By Vice President Date: Authorized: Rancho Palos Verdes By Director of Public Works As