CC SR 20160419 01 - Proposed 5-Year Capital Improvement ProgramRANCHO PALOS VERDES CITY COUNCIL MEETING DATE: 04/19/2016 AGENDA REPORT AGENDA HEADING: Regular Business AGENDA DESCRIPTION: Consideration and possible action regarding a proposed FY 2016-17 capital improvement budget and 5 -year Capital Improvement Program. RECOMMENDED COUNCIL ACTION: (1) Review and discuss capital improvement needs and provide guidance. FISCAL IMPACT: This work is included in the FY 2015/16 municipal budget. Amount Budgeted: None Additional Appropriation: None requested Account Number(s): Not Applicable ORIGINATED BY: Michael Throne, PE, Director of Public Works REVIEWED BY: Same as above APPROVED BY: Doug Willmore, City Manager') ATTACHED SUPPORTING DOCUMENTS: A. Input from IMAC (to be provided as Late Correspondence) BACKGROUND AND DISCUSSION: The Public Works Department will be presenting a proposed draft FY 2016-17 capital improvement budget and 5 -year Capital Improvement Program for discussion and consideration of the City Council. The Infrastructure Management Advisory Committee will be presented with preliminary information on Thursday, April 14, 2016, and their input will be also considered. Guidance and direction received from the City Council at tonight's meeting will be incorporated into the draft FY 2016-17 municipal budget. 1 MEMORANDUM L 11 RANCHO PALOS VERDES DATE: APRIL 14, 2016 TO: HONORABLE MAYOR DYDA AND MEMBERS OF THE CITY COUNCIL FROM: MICHAEL THRONE, PE, DIRECTOR OF PUBLIC WORKS SUBJECT: AGENDA ITEM NO. 1 — SUPPORTING DOCUMENTS (ATTACHMENT B) This memorandum is Attachment B to the April 19, 2016 staff report. Public Works has prepared a proposed 5 -year Capital Improvement Program (CIP) that prioritizes, among others, the objectives of: (1) Continuing to have very good -graded streets with no deferred maintenance; (2) A safe and reliable sewer system in the Abalone Cove Landslide Abatement District; (3) Rehabilitating or replacing old, worn-out, failure -prone local stormwater drainage systems. (4) Constructing and completing Council -approved local park developments; and (5) Master planning the Civic Center/public safety site. The proposed first year of the 5 -year plan proposes to focus on completing the final first cycle of the 7 -year pavement rehabilitation program; continuing installation of dewatering wells in Portuguese Bend; resurfacing Miraleste Drive; installing lining, performing point repairs, and replacing storm drain culverts; placing sidewalks and trees along Hawthorne; initiating master planning and design for the Ladera Linda Community Center and for the City Hall Civic Center; and all landscaping improvements at Lower Hesse Park. A presentation will be made that outlines the objectives of the proposed 5 -year plan; a summary of the work proposed for each infrastructure category; funding sources for all projects; and, a summary of fund balances. Public Works will also provide updates on all current, on-going, and planned capital projects. The attached table summarizes the budgeted CIP work for FY 2015-16 and the proposed FY 2016-17 capital improvement budget (including revenue funding sources for each project and fund balances) and the 5 -year CIP. Proposed FY 2016-17 Capital Budget and 5 -yr Capital Improvement Program (CIP) Project Infrastructure Improvements Admin Engineering Review/Labor Compliance Status as of Thursday April 14, 2016 Ongoing activity Original FY 15- 16 Budget _ 60,000 FY 15-16 Continuing Total FY 15-16 Appropriation Budget from Prior CIP 60,000 FY 16-17 Capital Budget FY 16-17 Capital Budget Revenue Sources 5 -yr Capital Improvement Program (CIP) Encumbered by June 30, 2016 60,000 72,500 25,000 157,500 25,000 Continuing Appro. (Funds to be Carried -over into FY 16- 17) - Rebudgeted New FY 16- from FY 15- 17 Funding 16 175,000 70,000 25,000 270,000 CIP Reserves (330-3030) 175,000 70,000 25,000 270,000 Community HUTA (Gas Beautificat- Restricted Dev Block Proposition Proposition Measure R Tax) (202- ion Fund (212 ACLAD (225) Donations Grant 3003) 3012) (330-3033) (CD(310- C (215-3015) A (216-3016) (220-3020) 309 3099) Quimby Fees (334- 3034) Environ Transp Dev Storm Drain Excise Tax Act (TDA) User Fee (EET) (338- Article 3 (340- (SDUF) (501- 3038) 3040) 3052) FY 16-17 175,000 70,000 25,000 270,000 - FY 17-18 60,000 70,000 130,000 FY 18-19 60,000 70,000 50,000 180,000 FY 19-20 60,000 70,000 130,000 FY 20-21 60,000 70,000 130,000 Grant Administration Infrastructure Management Plan Total Infrastructure Improvements Administration Abalone Cove Landslide Abatement District (ACLAD) Sewer System ACLAD Sewer System Capital Needs Study Ongoing activity 72,500 72,500 In process with IMAC 25,000 25,000 157,500 157,500 Study underway due June 25,000 25,000 ACLAD Sewer System Rehabilitation Program Design pending outcome of needs study 50,000 43,000 93,000 93,000 200,000 200,000 200,000 450,000 450,000 450,000 450,000 Total ACLAD Palos Verdes Drive South (PVDS) Landslide Landslide Dewatering Well Program 75,000 43,000 118,000 118,000 200,000 200,000 200,000 450,000 450,000 450,000 450,000 In construction 520,000 445,000 965,000 965,000 - 450,000 450,000 450,000 180,000 180,000 180,000 180,000 PVDS Realignment - East End In environmental review - 458,672 458,672 40,000 418,672 418,672 Portuguese Bend Landslide Area Strategic Plan In process with IMAC 75,000 75,000 - - 75,000 75,000 75,000 Portuguese Bend Landslide Area Resurfacing Program Ongoing activity; resurfacing this June 2016 550,000 550,000 550,000 - 550,000 550,000 550,000 550,000 600,000 600,000 650,000 Total PVDS Landslide 1,145,000 903,672 2,048,672 1,555,000 418,672 75,000 1,000,000 525,000 550,000 - 1,493,672 730,000 780,000 780,000 830,000 Park Sites Recognition Wall In design 40,000 40,000 40,000 - - 100,000 Lower Hesse Park Improvements RFP for design being circulated 487,575 487,575 60,000 427,575 200,000 200,000 627,575 Eastview Park Dog Park RFP for design being prepared 50,000 50,000 50,000 - - 100,000 Abalone Cove Beach Access Rd and Parking Rehabilitation (NEW) NEW - 50,000 50,000 50,000 150,000 Coastal Bluff Fence Replacement Program (NEW) NEW 200,000 200,000 200,000 200,000 200,000 200,000 200,000 Ladera Linda Community Center Parking Lot (NEW) NEW Preliminary design to establish scope 25,000 25,000 25,000 Upper Point Vicente/Hesse Park Marquee Signage (NEW) NEW 110,000 110,000 110,000 Eastview Park Site and Recreation Improvements (NEW) NEW - - 250,000 250,000 250,000 Total Park Sites 577,575 577,575 150,000 427,575 835,000 310,000 525,000 - 1,262,575 550,000 200,000 200,000 200,000 Public Buildings John C McTaggart Memorial Hall Improvements COMPLETED 94,242 94,242 50,000 - - Public Facility Connectivity (Hesse/ Park/Ryan Park Fiber Optic Cabling) In construction 320,000 320,000 320,000 RPV TV Building Improvements Advertising for bids 94,795 94,795 94,795 - - Citywide ADA Transition Plan Implementation Program In design 200,000 610,137 810,137 40,000 770,137 770,137 150,000 150,000 150,000 150,000 Corporation Yard Utilization Study Study underway due June 30,000 30,000 30,000 - Ladera Linda Community Center Master Plan RFP for design being circulated to consultants 93,722 93,722 93,722 - - PVIC Exhibit Replacement/Renovation Seeking grant funding to increase project scope 455,000 455,000 - 455,000 455,000 455,000 Civic Center Master Plan (NEW) NEW - - 250,000 250,000 250,000 Total Public Buildings 685,000 1,212,896 1,897,896 628,517 770,137 455,000 250,000 250,000 455,000 1,475,137 150,000 150,000 150,000 150,000 Right of Way and Traffic Control Devices Residential Street Rehabilitation Program Cycle 1 Yr 5 (Prior Years) COMPLETED (Fund 310) 790,957 790,957 790,957 ADA Access Improv at PVDW at Hawthorne Blvd COMPLETED (Fund 310) 174,900 174,900 174,900 ADA Access Improv at Mira Catalina COMPLETED (Fund 310) 64,700 64,700 64,700 Citywide Traffic Signal Battery Back -Up In construction 90,000 90,000 90,000 Hawthorne Blvd Corridor Beautification (Median Trees) In construction 150,000 150,000 150,000 Hawthorne Blvd Traffic Signal Synchronization In construction (10% match requirement) 683,628 683,628 683,628 Residential Street Rehabilitation Program Cycle 1 Yr 6 (FY 14-15) Advertising for bids 2,229,400 2,229,400 2,229,400 Sidewalk Repair and Replacement Program Advertising for bids; Ongoing activity 250,000 250,000 250,000 250,000 250,000 250,000 250,000 250,000 250,000 250,000 PVDE Guardrail Replacement Ready to advertise (10% match requirement) 268,794 268,794 268,794 - PVDW Median Improvements at Palos Verdes Estates Ready to advertise 473,690 473,690 473,690 - - Hawthorne Blvd Pedestrian Linkage Improvements Ready to advertise (20% match requirement) 1,240,351 1,240,351 150,000 1,090,351 1,090,351 PVDS Bike Lane Improvements In design (20% match requirement) 779,975 779,975 25,000 754,975 754,975 PVDE at Bronco Intersection Improvements In design 500,300 26,795 527,095 25,000 502,095 502,095 Pavement Management Program Biennial Update Consultant selection underway 120,000 69,600 189,600 120,000 - - 120,000 120,000 Miraleste Arterial Street Rehabilitation RFP for design being circulated to consultants 2,534,500 2,534,500 100,000 2,434,500 2,434,500 Residential Street Rehabilitation Program Cycle 1 Yr 7 (Final Yr) FY 16-17 design & construction - - 4,100,000 4,017,500 82,500 4,100,000 Residential Street Rehabilitation Program Cycle 2 FY 16-17 design only 400,000 400,000 400,000 3,300,000 3,300,000 3,300,000 3,300,000 Arterial Rehabilitation - Crenshaw Blvd Planned - 200,000 800,000 2,000,000 Western Av Traffic Congestion Improvements SBCOG Highway Program 200,000 3,000,000 Arterial Rehabilitation - Indian Peak Rd Planned - 200,000 1,600,000 ADA Improvements at City Hall Bus Stop (NEW) NEW - 192,400 192,400 192,400 Arterial Walls and Fences Replacement Program (NEW) NEW Year 1 = Hawthorne CLF Removal - 500,000 500,000 500,000 100,000 100,000 100,000 100,000 Total RIW and TCD 1,020,300 9,427,290 10,447,590 5,596,069 4,781,921 5,442,400 4,917,500 250,000 192,400 82,500 10,224,321 4,050,000 7,570,000 5,850,000 5,370,000 Sanitary Sewer System None No capacity - expansion projects identified Storm Water System - Stormwater Quality Torrance Airport SWQ Project (NEW) Trails Sunnyside Ridge Trail Accessibility Improvements at Del Cerro Park and Burma Rd Conestoga Trail Connection (NEW) Total Trails TOTAL GOVERNMENT FUNDS Storm Water System - Repairs & Rehabilition of Existing System Roan Drainage System Storm Drain Lining Program Storm Drain Point Repair Program Altamira Canyon Drainage Project Study Report Drainage and Roadway Improvements at Sacred Cove Marguerite/Lower Barkentine/Seacove Drainage Improvements Storm Drain Deficiency Improvement Program (Master Plan of Drainage)(NEW) TOTAL STORMWATER ENTERPRISE FUNDS NEW In construction In design NEW COMPLETED In construction In design Study underway; due December 2016 In design In design NEW TOTALS - ALL FUNDS 3,082,800 340,836 900,000 1 1,240,836 4,323,636 396,436 164,400 560,836 12,725,269 231,095 799,470 150,000 500,000 450,000 760,340 2,890,905 15,616,174 396,436 164,400 - 560,836 15,808,069 231,095 1,140,306 1,050,000 500,000 450,000 760,340 - 4,131,741 19,939,810 396,436 13,800 410,236 8,615,322 231,095 1,140,306 1,050,000 440,000 50,000 60,000 2,971,401 11,586,723 460,000 - 150,600 - 50,000 150,600 50,000 6,548,905 530,000 8,507,400 - 350,000 - 400,000 700,340 - 1,769,000 1 1,100,340 2,119,000 7,649,245 530,000 10,626,400 Beginning Balance July 1, 2015 FY 15-16 Encumbrances & Expenditures FY 15-16 YE Estimated Revenue 460,000 - 6,932,500 6,932,500 20,447,429 6,855,232 450,270 - - 250,000 550,000 455,000 192,400 250,000 - 550,000 - - - 455,000 192,400 1,321,716 571,865 192,990 236,073 1,153,223 54,552 870,750 (11,624) 860,000 473,690 93,000 253,400 642,600 772,394 484,620 20,968 164,400 50,000 50,000 575,000 575,000 1,337,510 50,000 1,131,383 - 82,500 350,000 1,769,000 2,119,000 82,500 2,119,000 336,998 97 6,725,725 2,071,401 23,172 460,000 - 150,600 50,000 200,600 15,586,305 01111111111111 - 350,000 - - 400,000 700,340 1,769,000 3,219,340 18,805,645 4,630,000 200,000 200,000 10,890,000 350,000 500,000 650,000 2,229,000 3,729,000 14,619,000 1,620,000 10,950,000 350,000 1,729,000 2,079,000 13,029,000 7,560,000 350,000 2,629,000 2,979,000 10,539,000 7,130,000 350,000 1,798,000 2,148,000 9,278,000 FY 15-16 Transfer -in Estimated Ending Balance June 30, 2016 FY15-16 Continuing Appropriation 8,327,603 22,370,070 6,398,305 1,035,791 1,497,507 98,175 835,590 1,008,467 1,637,843 80,700 42,252 891,718 (100,624) 150,600 2,418,893 360,170 97 4,654,324 1,100,340 FY15-16 Re -budget) 530,000 Proposed FY 16-17 Budget 6,932,500 250,000 - 550,000 - - - 455,000 192,400 575,000 - 82,500 2,119,000 Estimated FY 16-17 Revenue 300,000 - - 772,394 781,245 489,625 55,964 2,800 164,400 8,000 23,172 82,500 8,000 Estimated FY 16-17 Transfer -in Estimated Fund Balance Ending June 30, 2017 5,655,000 14,464,265 1,247,507 98,175 1,057,984 1,789,712 2,127,468 98,216 439,518 (279,224) 1,851,893 383,342 97 1,442,984 W:\MichaelT\CIP\Draft 2016\Proposed FY16-17 Budget 5 -yr CIP Rev D.xlsx B-2 4/14/2016 11:29 AM