Consideration and possible action to approve a change order to the professional
services agreement with CWE Corporation for storm drain design services.
RECOMMENDED COUNCIL ACTION:
(1) Award Change Order No. 1 in the amount of $54,770 to the professional services
agreement with CWE Corporation for storm drain engineering design services
dated December 15, 2015; and,
(2) Authorize the Contract Officer to execute the change order.
FISCAL IMPACT: None
Amount Budgeted: $760,360
Additional Appropriation: None
Account Number(s): 501-3052-431-73-00
ORIGINATED BY: Andy Winje, PE, Senior Engineer;; .
REVIEWED BY: Michael Throne, PE, Public Works Director�-,,�
APPROVED BY: Doug Willmore, City Manager'
ATTACHED SUPPORTING DOCUMENTS:
A. Change Order No. 1 (page A-1)
BACKGROUND AND DISCUSSION:
The Capital Improvements Program (CIP) includes two (2) storm drain system projects
that required a study of alternatives to determine the most cost-effective solution to
flooding and erosion problems in portions of the City's existing drainage system. One
project location is just north of Calle Entradero and just west of Palos Verdes Drive
West. The other location, is near the intersection of Palos Verdes Drive South and Sea
Cove Drive. On October 1, 2013 the City Council awarded a preliminary engineering
contract to KPFF Consulting Engineers (KPFF) to provide preliminary design services
for these locations. A final report was prepared and delivered to the City in June 2015.
The recommended alternative for each location includes improvements to certain
drainage structures and channels that require development of final engineering plans
and specifications for eventual bidding and award of a Public Works contract to
implement them.
On December 15, 2015, the City Council awarded an engineering design contract to
CWE Corporation (CWE) for another storm drain project, the Storm Drain Point Repair
1
Project, as recommended by Staff after a competitive proposal process. This design
contract will provide final engineering plans and specifications (construction documents)
for seven (7) locations needing repair in the City's storm drain system that were
discovered during the last lining project in 2013.
Staff would like to add scope to the Storm Drain Point Repair Project design contract
with CWE to include preparation of construction documents for the projects studied
earlier by KPFF. The work is quite similar to the work CWE is already doing. CWE has
done an excellent job to date in its contract, and using them to perform this additional
work will avoid delays that would result from a redundant selection process. It would
also allow these two additional projects to be built sooner.
Staff has negotiated Change Order No. 1 (Attachment A) to include the additional scope
elements, costs and time to the existing contract. Per Section 1.8 of the contract, a
change order of this magnitude must be brought to City Council for approval before it
can be executed by the City's contract officer. Funds for this change order have already
been appropriated in the budget as part of the Water Quality Flood Protection Fund.
CONCLUSION:
The City has a backlog of storm drain repair and improvement projects, and Staff would
like to accelerate the schedule to complete certain projects by adding scope to an
existing design contract begin performed by a competent consulting engineering firm
selected in a competitive process. Therefore, Staff recommends awarding Change
Order No. 1 to the CWE contract in the amount of $54,770.
ALTERNATIVES:
In addition to the Staff recommendation, the following alternative actions are available
for the City Council's consideration:
Discuss and take other action related to this item.
2
Project: Storm Drain Point Repair Design Project
Change Order # 1
Attention: William Young
C;rrY cF L 12Aricl io I-)ktf)s\/F.Fs CWE Corporation
30940 Hawthorne Blvd. 1561 E. Orangethorpe Ave., Suite 240
Rancho Palos Verdes, CA 90275 Fullerton, CA 92831
Explanantion for Change Order
Increase in contract value and extension of expiration date to provide design and construction
document preparation services for two additional locations per project scope in contract awarded on
December 15, 2015. The two new sites are known as Marguerite Storm Drain and Channel and Lower
Barkentine crossinE at PVDS.
Itemized Description
Quantity
Unit Price
Amount
Time and materials - Hydrology and hydraulics for two additional sites
1
3,900.00
3,900.00
Time and materials - Environmental Compliance & Permits for two additional sites
1
4,990.00
4,990.00
Time and materials - Geotehcnical Investigation for two additional sites
1
18,700.00
18,700.00
Time and materials - Plans, Specification and & Estimate for two additional sites
1
27,180.00
27,180.00
These estimates and costs may be moved between tasks such that the Total value is not to
excceded without further written aurthorization from the City
Total
54,770.00
Original Contract Value
149,560.00
Total Value of all Previous Change Orders
0.00
Total Revised Contract Sum Prior to this Change Order
Value of this Change Order
149,560.00
54,770.00
New Contract Sum 204,330.00
Change in Contract Days 60
Revised Contract Completion Date 6/28/2015
Accepted: CWE Car oration
r
By
Directo�orr Engin ing
Date:. � rte" �
Authorized: Rancho Palos Verdes
By
Contract Manager
A-1