PC RES 1991-064 PC RESOLUTION NO. 91-64
A RESOLUTION OF THE PLANNING COMMISSION OF THE
CITY OF RANCHO PALOS VERDES DETERMINING THAT
THE FISCAL YEAR '91-'92 CAPITAL IMPROVEMENTS
PLAN IS CONSISTENT WITH THE GENERAL PLAN
WHEREAS, the City of Rancho Palos Verdes has an adopted
General Plan with an Urban Environment Element which includes a
discussion of Infrastructure; and
WHEREAS, the California Planning and Zoning Law, Section 65401
requires that the City prepare a coordinated program for public
capital improvements for the ensuing fiscal year and that the
Planning Commission review and report to the City Council as to the
conformity of the Capital Improvements Plan with the adopted
General Plan; and
WHEREAS, on November 26, 1991, the Planning Commission
reviewed the City's Capital Improvements Plan for Fiscal Year '91-
'92 for consistency with the General Plan.
NOW, THEREFORE, THE PLANNING COMMISSION OF THE CITY OF RANCHO
PALOS VERDES DOES HEREBY FIND, DETERMINE AND RESOLVE AS FOLLOWS:
Section 1: That the proposed Capital Improvements Plan for
Fiscal Year '91-'92, as described in Exhibit "A", is consistent
with the goals and policies of the General Plan.
PASSED, APPROVED AND ADOPTED on November 26, 1991.
Peter Von Hagen j
Chairman
ifki/X11
R bert Bendrd, Direct() of
Environmental Service and
Secretary to the Commission
EXHIBIT "A"
1992 CIP PROGRAM
TOTAL
PROJECT CONSTR OTHER FUNDS RN) UTILITY TOTAL FUNDS
PROJECT DESCRIPTION COSTS COSTS DESIGN INSPECTION ADMIN ANTICIPATED SCUFCE TAX AMT AVAILABLE
HAWTHORNE BLVD.-(OVERLAY W/FABRIC) $600,000 $575,000 $20,000 $5,000 $5,000 DEVELOPER $420,000 $600,000
CREST RD TO INDIAN PEAK $63,000 BIKEWAYS
$112,000 S8300
GRAN.ALTAMIRA-(OVERLAY W/FABRIC) $169,000 $159,000 $7,000 $3,000 $39,000 DEVELOPER $36,000 $169,000
HAWTHORNE TO PVE C ITY LIMITS $38,000 BIKEWAYS
$21,000 SB300
$35,000 RECYCLING
ARMAGA SPRING-(OVERLAY W/FABRIC) $175,000 $157,000 $3,500 $9,500 $5,000 $145,000 DEVELOPER $30,000 $175,000
INDIAN VALLEY TO OUAILHILL
PVDS WESTBOUND-(RECONS.) $1,142,900 $1,112,900 $20,000 $10,000 $470,000 DEVELOPER $178,000 $1,142,900
WAYFARERS CHAPEL-HAWTHORNE $429,900 FAU
$40,000 BIKEWAYS
$25,000 PROP A
DELCERRO $5,000 $5,000 $5,000 $5,000
PRQJECT MANAGEMENT $25,000 $25,000 $25,000 $25,000
PROJECT CONTINGENCIES(92) $20,000 $20,000 $20,000 $20,000
TOTAL $2,136,900 $2,023,900 $3,500 $56,500 $53,000 $1,422,900 $714,000 $2,136.900
$429,900 FAU
$25,000 PROP A
$141,000 BIKEWAYS
$133,000 SB300
$35,000 RECYCUNG
$659,000 DEVELOPER
•
•
•
•
P.C. Resolution No. 91-64
Page 2